CN107386031B - The processing method of Expressway Extension Project engaging portion - Google Patents

The processing method of Expressway Extension Project engaging portion Download PDF

Info

Publication number
CN107386031B
CN107386031B CN201710784087.XA CN201710784087A CN107386031B CN 107386031 B CN107386031 B CN 107386031B CN 201710784087 A CN201710784087 A CN 201710784087A CN 107386031 B CN107386031 B CN 107386031B
Authority
CN
China
Prior art keywords
roadbed
new
reinforcing rib
broken stone
former
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201710784087.XA
Other languages
Chinese (zh)
Other versions
CN107386031A (en
Inventor
崔宇鹏
严默非
常文洁
杨建芳
豆晓娟
谷静芬
董明月
陈晓亮
刘二丽
雷佳
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hebei Huijin Engineering Testing Co ltd
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201710784087.XA priority Critical patent/CN107386031B/en
Publication of CN107386031A publication Critical patent/CN107386031A/en
Application granted granted Critical
Publication of CN107386031B publication Critical patent/CN107386031B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01CCONSTRUCTION OF, OR SURFACES FOR, ROADS, SPORTS GROUNDS, OR THE LIKE; MACHINES OR AUXILIARY TOOLS FOR CONSTRUCTION OR REPAIR
    • E01C3/00Foundations for pavings
    • E01C3/04Foundations produced by soil stabilisation
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01CCONSTRUCTION OF, OR SURFACES FOR, ROADS, SPORTS GROUNDS, OR THE LIKE; MACHINES OR AUXILIARY TOOLS FOR CONSTRUCTION OR REPAIR
    • E01C2201/00Paving elements
    • E01C2201/16Elements joined together
    • E01C2201/167Elements joined together by reinforcement or mesh

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Road Paving Structures (AREA)

Abstract

The invention discloses a kind of processing methods of Expressway Extension Project engaging portion, by using the side slope angle of former roadbed, slope surface is built step by step, and the inclined-plane for being set as being tilted down to former roadbed center position from the former shoulder by slope surface, then it is laid with TGXG in every grade of slope surface, and reinforcing rib is set, and compaction in layers obtains new roadbed, realize the effect that new-old concrete bond is enable effectively to resist longitudinal force, the inhomogeneities of new-old concrete bond sedimentation is balanced, so as to avoid the generation of pavement crack.By setting broken stone pile in new-old concrete bond seam both sides, and broken stone pile and supporting beam, retainer plate are used cooperatively, effectively reduced between new-old concrete bond because of the possibility in horizontal force generation crack.Widening road bed and the settling amount on road surface, prevent the generation in crack between new-old pavement, improve the construction quality of reorganization and expansion highway, increase service life during so as to effectively reduce highway extension project.

Description

The processing method of Expressway Extension Project engaging portion
Technical field
The present invention relates to road construction field more particularly to a kind of processing sides of Expressway Extension Project engaging portion Method.
Background technology
With the rapid development of Chinese society economy, automobile is had become as the essential vehicles of human society at present, And it is increasing with vehicle, existing major part highway cannot meet the growing transport need of society, For this purpose, it is imperative to carry out upgrading to original highway.Wherein widen either design also to express highway roadbed It is construction, is all the key that improvement project.And highway, after being open to traffic for many years, subgrade settlement has been basically completed, roadbed Widened section necessarily leads to the crack using longitudinal crack as representative, so as to highway due to the differential settlement of new-old concrete bond Generate destruction.For that purpose it is necessary to strengthen the Treatment Design optimization of engaging portion during to highway extension project and the improvement of method, make to sink Drop amount is kept at least, to ensure the quality of highway.While new and old embankment differential subsidence is reduced, new-old pavement difference is reduced Property sedimentation, new and old Embankment Settlements, new-old pavement disease etc. can be reduced, to Expressway Extension Project have great meaning Justice.
Invention content
The present invention provides a kind of Expressway Extension Project engaging portion for the above-mentioned problems in the prior art Processing method, widening road bed and the settling amount on road surface when can effectively reduce highway extension project are prevented between new-old pavement The generation in crack.
To achieve the above object with some other purposes, the present invention adopts the following technical scheme that:
A kind of processing method of Expressway Extension Project engaging portion, mainly includes the following steps that:
Step 1 need to widen former roadbed position and measure setting-out, and position need to be widened by marking, along the former shoulder Slope surface is opened up step by step, so that the original shoulder is in step-like, the surface of the step is set as by the former shoulder The angle of the inclined-plane tilted down to former roadbed center position, the inclined-plane and horizontal plane is 10-15 °, the slope surfaces at different levels Vertical height is 1-2 meters, and width is 1-2 meters;
Step 2 is laid with the first TGXG that width is 2-3 meters wide, and in the described first geotechnological lattice on floor plane Gravelly soil is laid on grid, is compacted after being often laid with the gravelly soil of 30-45 cm thicks, until neat with the peak of upper level slope surface It is flat;
Step 3 is laid with the second geotechnological lattice that width is 2-4 meters on the gravelly soil surface for reaching concordant with upper level slope surface Grid, and along highway extending direction a reinforcing rib is laid at interval of 3-5 meters in second TGXG;
Wherein, the reinforcing rib, which is set as one end, has the cylindricality of opening, the opening extension along the reinforcing rib side wall To the middle part of the reinforcing rib, the not opening one end of the reinforcing rib is stretched into the former roadbed, and with the side of the former roadbed Face is vertical, and the other end is separated from opening to both sides, so that the reinforcing rib forms Y-shaped structure;
Step 4, the casting concrete on the reinforcing rib, and concrete layer is made to cover the reinforcing rib;
Step 5 is laid with gravelly soil according to the method for step 2 on the concrete layer, and repeats step 3 and step 4, directly It is flushed to last layer concrete layer with the surface of the former roadbed, that is, forms the new roadbed of broadening;
Step 6 drills respectively in the seam both sides of the former roadbed and new roadbed, and a small amount of coagulation is poured into the drilling Soil, and the cement concrete broken stone pile coordinated with the boring aperture is inserted into the drilling before concrete setting, and make The broken stone pile protrudes 15-20 centimetres of the former roadbed and new road bed;
Step 7 is laid with supporting beam between two broken stone piles, and is arranged in the broken stone pile to fixed supporting beam Retainer plate;
Step 8 is laid with road surface, and the upper faying face in the junction of new-old pavement and lower faying face in the supporting beam Between be laid with Glass Fibre Earth Grid.
Preferably, in the processing method of the Expressway Extension Project engaging portion, first TGXG It is fixed in the slope surfaces at different levels by geotechnological glue with the second TGXG.
Preferably, in the processing method of the Expressway Extension Project engaging portion, the length of the reinforcing rib It it is 1.5-2.5 meters, and the reinforcing rib stretches into half of the length of the former roadbed for the reinforcing rib length.
Preferably, in the processing method of the Expressway Extension Project engaging portion, the length of the supporting beam Distance between the broken stone pile matches, and the both ends of the supporting beam are set as the arc being recessed to the supporting beam central side Shape so that the both ends of the supporting beam and the side wall of the broken stone pile are mutually supported, is provided at the top of the arc of the supporting beam Through-hole;The retainer plate is set as the matched annular of outer diameter of internal diameter and the broken stone pile, the side setting of the retainer plate Have gap, be provided on the gap with the matched bolt of the lead to the hole site so that the retainer plate be inserted in it is described broken After stone mar, the supporting beam is embedded in the gap, and the bolt is inserted into the through-hole.
Preferably, in the processing method of the Expressway Extension Project engaging portion, the original roadbed or new road The bore position of base side is symmetrical, and the spacing between the drilling of homonymy is 7-10 meters.
Preferably, in the processing method of the Expressway Extension Project engaging portion, the diameter of the broken stone pile It it is 0.4-0.6 meters, the spacing on the original roadbed and new roadbed between corresponding two broken stone piles is 2-3 meters.
Preferably, in the processing method of the Expressway Extension Project engaging portion, often it is compacted one layer of gravelly soil Afterwards, the loosened soil and residue on the surface of the compacting are cleared up.
Preferably, in the processing method of the Expressway Extension Project engaging portion, the TGXG is steel Mould TGXG.
The present invention includes at least following advantageous effect:
In the processing method of the Expressway Extension Project engaging portion of the present invention, by using the slope angle of former roadbed Degree, builds slope surface step by step so that widened section roadbed and former roadbed are successively be overlapped, strengthen the contact surface between new-old concrete bond, have Effect prevents the generation in crack between new-old concrete bond;By being set as slope surface from the former shoulder to former roadbed center position The inclined-plane tilted down so that new roadbed fill part is more closer to old roadbed side filling gravelly soil, so that new and old Roadbed cross section bearing capacity significantly increases, and then effectively reduces the settling amount of widening road bed;By on every grade of slope surface upper berth If TGXG, and reinforcing rib is set, it is big using TGXG intensity, small advantage is deformed, increases the combination of new-old concrete bond, Increase engaging portion shear resistance, prevent destruction of the sedimentation of new roadbed to old road base, it is uneven so as to reach stable new-old concrete bond The effect of sedimentation so that the method for new roadbed is more firm, further reduces the settling amount of roadbed, and former roadbed is stretched into one end Reinforcing rib can also play certain supporting role to new roadbed, and the further inhomogeneities of balance new-old concrete bond sedimentation, from And avoid the generation of pavement crack;In addition, there is opening, and former roadbed is stretched into the other end by the way that reinforcing rib is set as one end Afterwards, just the other end of reinforcing rib is opened by opening so that reinforcing rib forms Y-shaped structure, in the second TGXG The reinforcing rib that opening separates can disperse the active force conducted downwards by road surface upper strata, and then reduce the settling amount of new roadbed, make It is further balanced to obtain subgrade settlement, reduces the generation of pavement crack;New roadbed is obtained by compaction in layers so that the pressure of roadbed Solidity is effectively improved, and in the case where compactness improves, the settling amount of roadbed also just further reduces, that is, reduces new Because longitudinal force generates the possibility in crack between old roadbed.By setting broken stone pile, and by rubble in new-old concrete bond seam both sides Stake is used cooperatively with supporting beam so that the distance that supporting beam can limit opposite broken stone pile will not reduce, and then reduce new The generation of the compression fissure of old roadbed seam crossing additionally by the use of cooperation retainer plate, and causes between opposite broken stone pile Distance will not increase, and then reduce the generation for separating crack between new-old concrete bond, that is, reduce between new-old concrete bond because of transversely acting Power generates the possibility in crack.
Part is illustrated to embody by further advantage, target and the feature of the present invention by following, and part will also be by this The research and practice of invention and be understood by the person skilled in the art.
Description of the drawings
Fig. 1 is the method schematic diagram of the processing method of Expressway Extension Project engaging portion provided by the invention;
Fig. 2 is structure diagram when reinforcing rib opening of the present invention is opened;
Fig. 3 is the structure diagram of supporting beam of the present invention and retainer plate.
Specific embodiment
It elaborates below in conjunction with the accompanying drawings to the present invention, to enable those of ordinary skill in the art refering to energy after this specification It is enough to implement according to this.
As depicted in figs. 1 and 2, a kind of processing method of Expressway Extension Project engaging portion, mainly including following step Suddenly:
Step 1 need to widen position to former roadbed 1 and measure setting-out, and position need to be widened by marking, along former 1 side of roadbed Edge opens up slope surface 2 step by step, so that 1 edge of the original roadbed is in step-like, the surface of the step is set as by the former roadbed 1 The angle of the inclined-plane that edge is tilted down to former 1 center position of roadbed, the inclined-plane and horizontal plane is 10-15 °, the slopes at different levels The vertical height in face 2 is 1-2 meters, and width is 1-2 meters.
Step 2 is laid with the first TGXG 3 that width is 2-3 meters wide, and in the described first geotechnological lattice on floor plane Gravelly soil is laid on grid 3, is compacted after being often laid with the gravelly soil of 30-45 cm thicks, until the peak with upper level slope surface 2 It flushes.
Step 3 is laid with the second geotechnique that width is 2-4 meters on the gravelly soil surface for reaching concordant with upper level slope surface 2 Grid 4, and along highway extending direction a reinforcing rib 5 is laid at interval of 3-5 meters in second TGXG 4.
Wherein, the reinforcing rib 5, which is set as one end, has the cylindricality of opening along 5 side wall of reinforcing rib, and the opening is prolonged Extend to the middle part of the reinforcing rib 5, the not opening one end of the reinforcing rib 5 is stretched into the former roadbed 1, and with the former roadbed 1 side is vertical, and the other end is separated from opening to both sides, so that the reinforcing rib 5 forms Y-shaped structure.
Step 4, the casting concrete on the reinforcing rib 5, and concrete layer 6 is made to cover the reinforcing rib 5.
Step 5 is laid with gravelly soil according to the method for step 2 on the concrete layer 6, and repeats step 3 and step 4, Until last layer concrete layer 6 is flushed with the surface of the former roadbed 1, that is, form the new roadbed of broadening.
Step 6 drills respectively in the seam both sides of the former roadbed 1 and new roadbed, is poured into the drilling a small amount of mixed Solidifying soil, and the cement concrete broken stone pile 7 coordinated with the boring aperture is inserted into the drilling before concrete setting, and The broken stone pile 7 is made to protrude 15-20 centimetres of the former roadbed 1 and new road bed.
Step 7 is laid with supporting beam 8 between two broken stone piles 7, and is arranged in the broken stone pile 8 to fixed branch Support the retainer plate 9 of beam 8.
Step 8 is laid with road surface, and the upper faying face in the junction of new-old pavement and lower combination in the supporting beam 8 Glass Fibre Earth Grid 10 is laid between face.
Be 10-15 ° in slope surface angle by testing repeatedly and analysis is found in said program, slope surfaces at different levels it is vertical It is highly 1-2 meters, it is best for roadbed subsidence control effect when slope surface width is 1-2 meters, and convenient for construction.By in each layer The surface of slope surface is laid with concrete layer, on the one hand can play the role of fixing and supporting to reinforcing rib, on the other hand using mixed The intensity of soil is coagulated, the sedimentation of new pavement is reduced, so as to control the generation of pavement crack.Cement concrete broken stone pile has certain Intensity, while the bearing capacity collective effect of inter-pile soil can be made full use of, and can transmit in load to deep foundation base, have compared with Good technical performance, can effectively control the generation in crack at pavement joint, while the broken stone pile is cheap, can drop Low construction cost.By being laid with Glass Fibre Earth Grid, glass soil between the upper faying face of new-old pavement junction and lower faying face Work grid intensity is big, modulus is high, has very high wearability and to cold, while without long-term creep, and thermal stability is good, thus The anti-shear performance of new-old pavement junction can be significantly improved, so as to further prevent the generation of pavement crack.
In one preferred embodiment, 3 and second TGXG 4 of the first TGXG is fixed on institutes at different levels by geotechnological glue It states in slope surface 2.
In said program, the first TGXG and the second TGXG are fixed in slope surfaces at different levels by geotechnological glue, So that TGXG will not be displaced in the construction process, so as to ensure that construction quality.
In one preferred embodiment, the length of the reinforcing rib 5 is 1.5-2.5 meters, and the reinforcing rib 5 stretches into the former road The length of base 1 is the half of 5 length of reinforcing rib.
In said program, by being tested repeatedly with practice of construction it has been observed that the length of reinforcing rib is arranged on 1.5-2.5 Meter Jian, and the half of reinforcing rib is arranged on inside former roadbed so that the other half reinforcing rib is in above slope surface, between new-old concrete bond Equally distributed reinforcing rib can be good at balancing the differential settlement of new-old concrete bond, and then play good support to new roadbed Effect, the effective generation for reducing pavement crack.
As shown in figure 3, in a preferred embodiment, the distance between the length of the supporting beam 8 and the broken stone pile 7 matches It closes, and the both ends of the supporting beam 8 are set as the arc being recessed to 8 central side of supporting beam, so that the two of the supporting beam 8 The side wall with the broken stone pile 7 is held mutually to support, through-hole 11 is provided at the top of the arc of the supporting beam 8;The retainer plate 9 is set The matched annular of outer diameter of internal diameter and the broken stone pile 7 is set to, the side of the retainer plate 9 is provided with gap 12, described to slit Be provided on mouthfuls 12 with the matched bolt 13 in 11 position of through-hole so that the retainer plate 9 is being inserted in the broken stone pile 7 Afterwards, the supporting beam 8 is embedded in the gap 12, and the bolt 13 is inserted into the through-hole 11.
In said program, by setting supporting beam between broken stone pile, and specific retainer plate is configured so that supporting beam Distance the broken stone pile of new-old concrete bond both sides can be limited, so that the broken stone pile positioned at roadbed both sides can support The effect of lateral pull between anti-new-old concrete bond, so as to avoid the generation of the pavement crack caused by horizontal force.
In one preferred embodiment, the bore position of the original roadbed 1 or new roadbed side is symmetrical, and positioned at the drilling of homonymy Between spacing be 7-10 meters.
In said program, spacing is set as between 7-10 meters between drilling, you can resists the lateral pull between roadbed well.
It is a diameter of 0.4-0.6 meters of the broken stone pile 7, corresponding on the original roadbed 1 and new roadbed in one preferred embodiment Two broken stone piles 7 between spacing be 2-3 meters.
In said program, when the spacing between broken stone pile is 5 times or so of broken stone pile diameter, the collaboration between two broken stone piles Active force is most strong, thus the active force for the seam crossing being more highly resistant between new-old concrete bond.
In one preferred embodiment, after being often compacted one layer of gravelly soil, loosened soil and residue to the surface of the compacting carry out clear Reason.
In said program, to cleaning soil layer surface after one layer of gravelly soil of every compacting, the shadow because of loosened soil and residue is avoided It rings and the compaction quality of next layer of crushed stone soil layer is affected, that is, increase the adhesiveness between crushed stone soil layer, be correspondingly improved The stability of entire widening road bed, effectively reduces the sedimentation of widening road bed.
In one preferred embodiment, the TGXG is steel plastic geogrid.
In said program, steel plastic geogrid is made with high tensile steel wire, intensity is big, deformation is small, creep is small, it is corrosion-resistant, Long lifespan, therefore, steel plastic geogrid can meet the use demand of all kinds of permanent works 100 years or more, and performance is excellent, ruler Very little stability is good, and convenient and quick construction, period are short, at low cost, thus selects steel plastic geogrid can be to the roadbed widened Good fixed function is played, while construction at low cost is convenient.
Although the embodiments of the present invention have been disclosed as above, but its be not restricted in specification and embodiment it is listed With it can be fully applied to various fields suitable for the present invention, for those skilled in the art, can be easily Realize other modification, therefore without departing from the general concept defined in the claims and the equivalent scope, it is of the invention and unlimited In specific details and the legend herein shown with description.

Claims (8)

1. a kind of processing method of Expressway Extension Project engaging portion, including:
Step 1 need to widen former roadbed position and measure setting-out, and position need to be widened by marking, along the former shoulder step by step Slope surface is opened up, so that the original shoulder is in step-like;
Step 2 is laid with the first TGXG on floor plane, and is laid with gravelly soil in first TGXG, often spreads If being compacted after one layer of gravelly soil, until being flushed with the peak of upper level slope surface;
Step 3 is laid with the second TGXG on the gravelly soil surface for reaching concordant with upper level slope surface;
Wherein, it is further comprising the steps of:
Step 4, the casting concrete on the reinforcing rib, and concrete layer is made to cover the reinforcing rib;
Step 5 is laid with gravelly soil according to the method for step 2 on the concrete layer, and repeats step 3 and step 4, until most Later layer concrete layer is flushed with the surface of the former roadbed, that is, forms the new roadbed of broadening;
Step 6 drills respectively in the seam both sides of the former roadbed and new roadbed, and a small amount of concrete is poured into the drilling, And the cement concrete broken stone pile coordinated with the boring aperture is inserted into the drilling before concrete setting, and make described 15-20 centimetres of the broken stone pile protrusion former roadbed and new road bed;
Step 7 is laid with supporting beam between two broken stone piles, and consolidating to fixed supporting beam is arranged in the broken stone pile Fixed circle;
Step 8 is laid with road surface in the supporting beam, and is spread between the upper faying face and lower faying face of the junction of new-old pavement If Glass Fibre Earth Grid;
In addition, in the step 1, the surface of the step be set as from the former shoulder to former roadbed center position to Under inclined inclined-plane, the angle of the inclined-plane and horizontal plane is 10-15 °, and the vertical height of the slope surfaces at different levels is 1-2 meters, wide Spend is 1-2 meters;
In the step 2, the width of first TGXG is 2-3 meters;The laying depth of every layer of gravelly soil is 30- 45 centimetres;
In the step 3, the width of second TGXG is 2-4 meters;And along highway extending direction in the described second soil At interval of a piece reinforcing rib of 3-5 meters of layings on work grid;
Wherein, the reinforcing rib, which is set as one end, has the cylindricality of opening along the reinforcing rib side wall, and the opening extends to institute The middle part of reinforcing rib is stated, the not opening one end of the reinforcing rib is stretched into the former roadbed, and is hung down with the side of the former roadbed Directly, the other end is separated from opening to both sides, so that the reinforcing rib forms Y-shaped structure.
2. the processing method of Expressway Extension Project engaging portion as described in claim 1, wherein, the described first geotechnological lattice Grid and the second TGXG are fixed on by geotechnological glue in the slope surfaces at different levels.
3. the processing method of Expressway Extension Project engaging portion as described in claim 1, wherein, the length of the reinforcing rib It is 1.5-2.5 meters to spend, and the reinforcing rib stretches into half of the length of the former roadbed for the reinforcing rib length.
4. the processing method of Expressway Extension Project engaging portion as described in claim 1, wherein, the length of the supporting beam Degree matches, and the both ends of the supporting beam are set as what is be recessed to the supporting beam central side with the distance between the broken stone pile Arc, so that the both ends of the supporting beam and the side wall of the broken stone pile are mutually supported, the top setting of the arc of the supporting beam There is through-hole;The retainer plate is set as the matched annular of outer diameter of internal diameter and the broken stone pile, and the side of the retainer plate is set Be equipped with gap, be provided on the gap with the matched bolt of the lead to the hole site so that the retainer plate be inserted in it is described After broken stone pile, the supporting beam is embedded in the gap, and the bolt is inserted into the through-hole.
5. the processing method of Expressway Extension Project engaging portion as described in claim 1, wherein, the original roadbed or new The bore position of roadbed side is symmetrical, and the spacing between the drilling of homonymy is 7-10 meters.
6. the processing method of Expressway Extension Project engaging portion as described in claim 1, wherein, the broken stone pile it is straight Diameter is 0.4-0.6 meters, and the spacing on the original roadbed and new roadbed between corresponding two broken stone piles is 2-3 meters.
7. the processing method of Expressway Extension Project engaging portion as described in claim 1, wherein, often it is compacted one layer of rubble After soil, the loosened soil and residue on the surface of the compacting are cleared up.
8. the processing method of Expressway Extension Project engaging portion as described in claim 1, wherein, the TGXG is Steel plastic geogrid.
CN201710784087.XA 2017-09-04 2017-09-04 The processing method of Expressway Extension Project engaging portion Active CN107386031B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710784087.XA CN107386031B (en) 2017-09-04 2017-09-04 The processing method of Expressway Extension Project engaging portion

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710784087.XA CN107386031B (en) 2017-09-04 2017-09-04 The processing method of Expressway Extension Project engaging portion

Publications (2)

Publication Number Publication Date
CN107386031A CN107386031A (en) 2017-11-24
CN107386031B true CN107386031B (en) 2018-06-29

Family

ID=60349041

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710784087.XA Active CN107386031B (en) 2017-09-04 2017-09-04 The processing method of Expressway Extension Project engaging portion

Country Status (1)

Country Link
CN (1) CN107386031B (en)

Families Citing this family (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108661060B (en) * 2018-05-22 2020-05-08 宁夏路桥工程股份有限公司 Method for reinforcing road expansion construction excavation slope
CN109098058B (en) * 2018-08-21 2023-09-26 宁波交通工程建设集团有限公司 Traffic load vibration reduction structure and construction method
CN110528347B (en) * 2019-09-09 2021-08-24 中国建设基础设施有限公司 Permeable embankment structure applied to gully section and construction method thereof
CN110820455A (en) * 2019-11-27 2020-02-21 江西省公路桥梁工程有限公司 Construction process for lapping and expanding roadbed of asphalt concrete highway
CN111827033A (en) * 2020-07-21 2020-10-27 湖南长株高速公路开发有限责任公司 Construction method for widening and filling solidified soil of expressway intercommunicating ramp roadbed

Family Cites Families (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2008131480A1 (en) * 2007-04-26 2008-11-06 Paul Camilleri Method of constructing building slabs and pavements and storing water
CN102619150A (en) * 2012-04-26 2012-08-01 石家庄铁道大学 Anchored roadbed widening method
CN205501749U (en) * 2016-03-28 2016-08-24 重庆建工市政交通工程有限责任公司 Structure is widened to highway subgrade
CN106120501B (en) * 2016-08-10 2018-01-09 浙江大学城市学院 Existing barricade section roadbed spells width and increases structure and construction method
CN106522055B (en) * 2016-11-09 2017-11-17 郭昆朋 The construction method of highway broadening roadbed

Also Published As

Publication number Publication date
CN107386031A (en) 2017-11-24

Similar Documents

Publication Publication Date Title
CN107386031B (en) The processing method of Expressway Extension Project engaging portion
CN102619150A (en) Anchored roadbed widening method
CN204418003U (en) A kind of bridge platform post processing combined system
CN101144256B (en) Slag-free orbit reinforced concrete pile net structure roadbed and construction method thereof
CN103334357B (en) Viaduct road embankment structure with lower pile foundation bearing platform extending in roadbed, and construction method
CN201095716Y (en) Slag-free orbit reinforced concrete pile net structure roadbed
CN102359046A (en) High fill subgrade connection method
CN103046446B (en) Highway reconstruction and extension project joint portion treatment structure
CN109750571B (en) Road collapse emergency and permanent retaining integrated structure and construction method
CN110965416B (en) Bamboo reinforcement system for reinforcing mountain area high-fill roadbed and construction method
CN103074882A (en) Construction method for reinforcing island-type perennial frozen-soil foundation by adopting gravel piles
CN106522055A (en) Construction method of widening roadbed of road
CN113216147B (en) Soft rock roadbed longitudinal crack disease treatment method
CN214782984U (en) Road repairing structure of sponge city
CN202117072U (en) Assembled type base for power transmission line iron tower
CN212316575U (en) Be used for highway to expand ground processing structure
CN207552833U (en) A kind of elevated bridge basal perimeter ground road structure
CN214656089U (en) Be applied to assembled road surface structure in sinking area of underground coal mine
CN109082961A (en) Road construction method with abrupt slope
CN214737081U (en) Firm town road soft or hard is plugged into and is prevented novel structure that subsides
CN108316077A (en) One kind underlies shallow embedding cave dwelling roadbed treatment structures and method
CN211006716U (en) Combined retaining structure
CN209555946U (en) A kind of reparation structure that high embankment collapses
RU2691035C1 (en) Automobile road
CN214882672U (en) Highway subgrade reinforced structure

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
TR01 Transfer of patent right

Effective date of registration: 20240705

Address after: 050090 No. 52, Xinshi North Road, Qiaoxi District, Shijiazhuang City, Hebei Province

Patentee after: Hebei Huijin Engineering Testing Co.,Ltd.

Country or region after: China

Address before: 050000 No. 402, Unit 4, Building 1, No. 6, Police Academy Road, Qiaoxi District, Shijiazhuang City, Hebei Province

Patentee before: Cui Yupeng

Country or region before: China

Patentee before: Lei Jia

Patentee before: Yan Mofei

Patentee before: Chang Wenjie

Patentee before: Yang Jianfang

Patentee before: Dou Xiaojuan

Patentee before: Gu Jingfen

Patentee before: Dong Mingyue

Patentee before: Chen Xiaoliang

Patentee before: Liu Erli