Shot blasting method for the frock moulding bed of steel member ball blast Download PDFInfo
- Publication number
- CN107378792A CN107378792A CN201710437728.4A CN201710437728A CN107378792A CN 107378792 A CN107378792 A CN 107378792A CN 201710437728 A CN201710437728 A CN 201710437728A CN 107378792 A CN107378792 A CN 107378792A
- Authority
- CN
- China
- Prior art keywords
- shot
- fixed
- tilted supporter
- tilted
- firm banking
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Withdrawn
Links
Classifications
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B24—GRINDING; POLISHING
- B24C—ABRASIVE OR RELATED BLASTING WITH PARTICULATE MATERIAL
- B24C1/00—Methods for use of abrasive blasting for producing particular effects; Use of auxiliary equipment in connection with such methods
- B24C1/08—Methods for use of abrasive blasting for producing particular effects; Use of auxiliary equipment in connection with such methods for polishing surfaces, e.g. smoothing a surface by making use of liquid-borne abrasives
- B24C1/086—Descaling; Removing coating films
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B23—MACHINE TOOLS; METAL-WORKING NOT OTHERWISE PROVIDED FOR
- B23K—SOLDERING OR UNSOLDERING; WELDING; CLADDING OR PLATING BY SOLDERING OR WELDING; CUTTING BY APPLYING HEAT LOCALLY, e.g. FLAME CUTTING; WORKING BY LASER BEAM
- B23K37/00—Auxiliary devices or processes, not specially adapted to a procedure covered by only one of the preceding main groups
- B23K37/08—Auxiliary devices or processes, not specially adapted to a procedure covered by only one of the preceding main groups for flash removal
Landscapes
- Engineering & Computer Science (AREA)
- Mechanical Engineering (AREA)
- Physics & Mathematics (AREA)
- Optics & Photonics (AREA)
- Load-Engaging Elements For Cranes (AREA)
Abstract
The invention discloses a kind of shot blasting method of the frock moulding bed for steel member ball blast, the shot blasting method comprises the following steps:1), frock moulding bed is lifted on the inlet roller way of shot-blasting machine, and multiple steel members are lifted on frock moulding bed successively by order from the bottom up;2) shot-blasting machine, is started, to enable the frock moulding bed for being placed with multiple steel members to enter the interior storehouse of shot-blasting machine;3), start the ramming head of shot-blasting machine, impeller blasting processing is carried out to multiple steel members;4), after the processing of multiple steel member impeller blastings, the frock moulding beds of multiple steel members will be placed with from outlet roller-way output, and unloaded from frock moulding bed multiple steel members with loop wheel machine.On the one hand the shot blasting method can improve the service efficiency of shot-blasting machine, on the other hand can also improve the operating efficiency of steel member impeller blasting.
Description
Technical field
The present invention relates to steel member ball blast manufacture field, in particular it relates to the throwing of the frock moulding bed for steel member ball blast
Ball method.
Background technology
In steel construction manufacturing procedure, impeller blasting is one of important process.After the completion of the weldering of ordinary steel component groups, typically
Impeller blasting is carried out using special shot-blast apparatus, removes the floating embroidery of component surface, and the extra coarse degree of component surface is met that paint applies
Dress and design requirement.Because shot-blasting machine belongs to modular system, component discrepancy hole and internal working volume are big compared with scantling, and one
As in the case of when carrying out impeller blasting work, no matter component physical dimension size, shot-blasting machine is sequentially entered using single component
Interior storehouse carry out impeller blasting work, for the less component of profile physical dimension, operating efficiency can be than relatively low for this.And
When carrying out ball blast work, mistake has ramming head to be required to open in ball blast cabin, and ramming head rotates at a high speed the shot dished out and hits profile chi
The very little effective shot of less component surface is less, on the one hand causes that equipment service efficiency is low, production efficiency is relatively low, on the other hand
The shot for not striking component surface strikes the interior bin-protecting plate on shot-blasting machine opposite, cause backplate spoilage higher, it is necessary to through
Furnace plate is often changed, improves the maintenance cost of equipment.
Therefore it provides on the one hand a kind of can improve shot-blast apparatus service efficiency, steel member throwing on the other hand can be improved
The problem of shot blasting method of the frock moulding bed for steel member ball blast of ball derusting operating efficiency is urgent need to resolve of the present invention.
The content of the invention
The present invention provides a kind of shot blasting method of frock moulding bed for steel member ball blast, and the shot blasting method on the one hand can
The service efficiency of shot-blasting machine is improved, on the other hand can also improve the operating efficiency of steel member impeller blasting.
To achieve these goals, the invention provides a kind of shot blasting method of the frock moulding bed for steel member ball blast,
The shot blasting method comprises the following steps:
1), frock moulding bed is lifted on the inlet roller way of shot-blasting machine, and by multiple steel members by order from the bottom up
It is lifted into successively on frock moulding bed;
2) shot-blasting machine, is started, to enable the frock moulding bed for being placed with multiple steel members to enter the interior storehouse of shot-blasting machine;
3), start the ramming head of shot-blasting machine, impeller blasting processing is carried out to multiple steel members;
4), after the processing of multiple steel member impeller blastings, the frock moulding beds of multiple steel members will be placed with from outlet roller-way
Output, and unloaded from frock moulding bed multiple steel members with loop wheel machine;
The frock moulding bed includes firm banking, multiple fixed tilted supporters, multiple components and places bracket and multiple backstop machines
Structure;Multiple fixed tilted supporters are fixed on the firm banking, and shape between the fixed tilted supporter of arbitrary neighborhood two
Into there is gap;Multiple components are both provided with any one of fixed tilted supporter and place bracket, multiple components place support
Length direction of the frame along the fixed tilted supporter is evenly distributed;Any two component on two neighboring fixed tilted supporter places support
Frame is all staggered;The component is placed and is provided with stop mechanism on one end of the remote fixed tilted supporter of bracket.
Preferably, the entrance that multiple frock moulding beds are lifted into shot-blasting machine is also included after step 1), before step 1)
On roller-way, and place multiple steel members on multiple frock moulding beds respectively.
Preferably, multiple fixed tilted supporters include being fixed in multiple first fixation tilted supporters on firm banking and are fixed in
Multiple second on the firm banking fix tilted supporter;The first fixation tilted supporter and the second fixation tilted supporter are relative
Set, described first fixes tilted supporter and tilted supporter or the are fixed in the described second gap fixed between tilted supporter along described first
One end of the remote firm banking of two fixation tilted supporters becomes larger to one end close to the firm banking;And described
The upper end points that one fixation tilted supporter is fixed in the firm banking is equal to institute to the vertical range of one end of the firm banking
End points that the second fixation tilted supporter is fixed on the firm banking is stated to the vertical range of the other end of the firm banking.
Preferably, multiple reinforcement horizontal strokes are additionally provided between the first fixation tilted supporter and the second fixation tilted supporter
Beam;The both ends of the web beam are respectively and fixedly connected to described first and fixed on tilted supporter and the second fixation tilted supporter;It is multiple
The web beam straight line in the longitudinal direction be all parallel to each other.
Preferably, multiple described first fix between tilted supporters and strengthen longerons by multiple first and connect, multiple described the
Two fix between tilted supporter by the multiple second reinforcement longerons connections;And any number of described first strengthen longerons and/or any
Hanger is provided with multiple second reinforcement longerons.
Preferably, in step 1), any two steel member is all staggered, so as to obtain the exposed face of multiple steel members all
Shot Blasting can be carried out.
According to above-mentioned technical proposal, shot blasting method provided by the invention comprises the following steps:1), frock moulding bed is lifted into
On the inlet roller way of shot-blasting machine, and multiple steel members are lifted on frock moulding bed successively by order from the bottom up;2), start
Shot-blasting machine, to enable the frock moulding bed for being placed with multiple steel members to enter the interior storehouse of shot-blasting machine;3) shot-blasting machine, is started
Ramming head, impeller blasting processing is carried out to multiple steel members;4), after the processing of multiple steel member impeller blastings, will be placed with multiple
The frock moulding bed of steel member is unloaded from frock moulding bed multiple steel members with loop wheel machine from outlet roller-way output.The frock tire
Any two component of the two neighboring fixed tilted supporter of frame is placed bracket and is all staggered, so, multiple steel in step 1)
Component realizes that effective ball blast quantity is relatively more when carrying out impeller blasting work, and less strikes on shot-blasting machine, reduces pair
The damaged condition of shot-blasting machine;On the other hand, it is placed on the steel member that component is placed on bracket to be staggered, multiple steel members are simultaneously
Ball blast is carried out, improves the operating efficiency of impeller blasting.
Other features and advantages of the present invention will be described in detail in subsequent specific embodiment part.
Brief description of the drawings
Accompanying drawing is for providing a further understanding of the present invention, and a part for constitution instruction, with following tool
Body embodiment is used to explain the present invention together, but is not construed as limiting the invention.In the accompanying drawings:
Fig. 1 is a kind of structural representation of the frock moulding bed for steel member ball blast of preferred embodiment provided by the invention
Figure.
Description of reference numerals
1st, firm banking 2, first fixes tilted supporter
3rd, second tilted supporter 4, web beam are fixed
5th, component places bracket 6, steel member
Embodiment
The embodiment of the present invention is described in detail below in conjunction with accompanying drawing.It should be appreciated that this place is retouched
The embodiment stated is merely to illustrate and explain the present invention, and is not intended to limit the invention.
In the present invention, in the case where not making opposite explanation, " upper and lower, left and right, inside and outside " etc. are included in term
The noun of locality only represents orientation of the term under normal service condition, or be skilled artisan understands that be commonly called as, without should
It is considered as the limitation to the term.
The invention provides a kind of shot blasting method of the frock moulding bed for steel member ball blast, the shot blasting method include with
Lower step:
1), frock moulding bed is lifted on the inlet roller way of shot-blasting machine, and by multiple steel members 6 by order from the bottom up
It is lifted into successively on frock moulding bed;
2) shot-blasting machine, is started, to enable the frock moulding bed for being placed with multiple steel members 6 to enter in shot-blasting machine
Storehouse;
3), start the ramming head of shot-blasting machine, impeller blasting processing is carried out to multiple steel members 6;
4), after the processing of multiple impeller blastings of steel member 6, the frock moulding beds of multiple steel members 6 will be placed with from outlet roller
Road exports, and is unloaded multiple steel members 6 from frock moulding bed with loop wheel machine;
The frock moulding bed includes firm banking 1, multiple fixed tilted supporters, multiple components and places bracket 5 and multiple backstops
Mechanism;Multiple fixed tilted supporters are fixed on the firm banking 1, and between the fixed tilted supporter of arbitrary neighborhood two
Formed with gap;Multiple components are both provided with any one of fixed tilted supporter and place bracket 5, multiple components are placed
Length direction of the bracket 5 along the fixed tilted supporter is evenly distributed;Any two component on two neighboring fixed tilted supporter is put
Bracket 5 is put all to be staggered;The component is placed and is provided with backstop machine on one end of the remote fixed tilted supporter of bracket 5
Structure.
Spirit of the invention, which is to provide one kind, can reduce shot-blasting machine damaged condition, and and can enough improves shot-blasting machine operating efficiency
Shot blasting method.The shot blasting method comprises the following steps:1), frock moulding bed is lifted on the inlet roller way of shot-blasting machine, and will
Multiple steel members 6 are lifted on frock moulding bed successively by order from the bottom up;2) shot-blasting machine, is started, it is more to be placed with
The frock moulding bed of individual steel member 6 can enter the interior storehouse of shot-blasting machine;3), start the ramming head of shot-blasting machine, multiple steel members 6 are entered
The processing of row impeller blasting;4), after the processing of multiple impeller blastings of steel member 6, will be placed with the frock moulding beds of multiple steel members 6 from
Roller-way output is exported, and is unloaded multiple steel members 6 from frock moulding bed with loop wheel machine.As shown in figure 1, the shot blasting method is used
To frock moulding bed two neighboring fixed tilted supporter any two component place bracket 5 be all staggered, so, step 1)
In multiple steel members 6 when carrying out impeller blasting work, realize that effective ball blast quantity is relatively more, less strikes shot-blasting machine
On, reduce the damaged condition to shot-blasting machine;On the other hand, the steel member 6 that component is placed on bracket 5 is placed on to be staggered,
Multiple steel members 6 carry out ball blast simultaneously, improve the operating efficiency of impeller blasting.
Further to improve operating efficiency, also include lifting multiple frock moulding beds after step 1), before step 1)
Onto the inlet roller way of shot-blasting machine, and multiple steel members 6 are placed on multiple frock moulding beds respectively.
In a kind of preferred embodiment of the present invention, multiple fixed tilted supporters include being fixed on firm banking 1
Multiple first fixation tilted supporters 2 and the multiple second fixations tilted supporters 3 being fixed on the firm banking 1;Described first fixes
Tilted supporter 2 and the second fixation tilted supporter 3 are oppositely arranged, and described first, which fixes tilted supporter 2 and described second, fixes tilted supporter 3
Between gap fixed along the described first fixation tilted supporter 2 or second tilted supporter 3 the remote firm banking 1 one end to leaning on
One end of the nearly firm banking 1 becomes larger;And the first fixation tilted supporter 2 is fixed in the upper of the firm banking 1
End points is equal to the described second fixation tilted supporter 3 to the vertical range of one end of the firm banking 1 and is fixed in the firm banking 1
On end points to the other end of the firm banking 1 vertical range.So, affixed multiple first fixations on firm banking 1
Tilted supporter 2 and multiple second fixes tilted supporter 3, also, the first fixation tilted supporter 2 and second is fixed tilted supporter 3 and is oppositely arranged, and
And first fix tilted supporter 2 and second fix tilted supporter 3 between gap along first fix tilted supporter 2 away from firm banking 1
One end becomes larger to one end close to firm banking 1, is so advantageous to stability;And described first, which fixes tilted supporter 2, consolidates
The upper end points for being connected on the firm banking 1 is equal to the described second fixation tiltedly to the vertical range of one end of the firm banking 1
Support 3 is fixed in the end points on the firm banking 1 and fixed to the vertical range of the other end of the firm banking 1, i.e., first
Tilted supporter 2 and second fixes the middle position that tilted supporter 3 is arranged on firm banking 1, is so beneficial to improve resistance to overturning.
In the case of further preferably, also set up between the first fixation tilted supporter 2 and the second fixation tilted supporter 3
There are multiple web beams 4;The both ends of the web beam 4 are respectively and fixedly connected to the first fixation tilted supporter 2 and described second and consolidated
Determine on tilted supporter 3;Multiple web beams 4 straight line in the longitudinal direction be all parallel to each other.So, due to multiple steel structures
Part 6 is all placed on the frock moulding bed, and weight is larger, and the stability for improving frock moulding bed as far as possible is important, example
Multiple web beams 4, and the institute of multiple web beams 4 such as are set between the first fixation tilted supporter 2 and second fixes tilted supporter 3
Straight line in the longitudinal direction is all parallel to each other.
It is the stability for further improving the frock moulding bed in the case of still more preferably, multiple described first fix
Strengthen longeron by multiple first between tilted supporter 2 to connect, add between multiple second fixations tilted supporters 3 by multiple second
Strong longeron connection;And it is provided with and hangs on any number of first reinforcement longerons and/or any number of second reinforcement longerons
Ear 7.Here, it is that crane lifts by crane for convenience to set hanger 7, improves the security of driving allocation and transportation.
In a kind of preferred embodiment of the present invention, in step 1), any two steel member 6 is all staggered,
So that Shot Blasting can be carried out by obtaining the exposed face of multiple steel members 6.In such manner, it is possible to improve the operating efficiency of impeller blasting, meet
Close spirit of the invention.
The preferred embodiment of the present invention is described in detail above in association with accompanying drawing, still, the present invention is not limited to above-mentioned reality
The detail in mode is applied, in the range of the technology design of the present invention, a variety of letters can be carried out to technical scheme
Monotropic type, these simple variants belong to protection scope of the present invention.
It is further to note that each particular technique feature described in above-mentioned embodiment, in not lance
In the case of shield, can be combined by any suitable means, in order to avoid unnecessary repetition, the present invention to it is various can
The combination of energy no longer separately illustrates.
In addition, various embodiments of the present invention can be combined randomly, as long as it is without prejudice to originally
The thought of invention, it should equally be considered as content disclosed in this invention.
Claims (6)
1. the shot blasting method of a kind of frock moulding bed for steel member ball blast, it is characterised in that the shot blasting method includes following
Step:
1), frock moulding bed is lifted on the inlet roller way of shot-blasting machine, and by multiple steel members (6) by from the bottom up order according to
It is secondary to be lifted on frock moulding bed;
2) shot-blasting machine, is started, to enable the frock moulding bed for being placed with multiple steel members (6) to enter the interior storehouse of shot-blasting machine;
3), start the ramming head of shot-blasting machine, impeller blasting processing is carried out to multiple steel members (6);
4), after the processing of multiple steel members (6) impeller blasting, the frock moulding beds of multiple steel members (6) will be placed with from outlet roller
Road exports, and is unloaded multiple steel members (6) from frock moulding bed with loop wheel machine;
The frock moulding bed includes firm banking (1), multiple fixed tilted supporters, multiple components and places bracket (5) and multiple backstops
Mechanism;Multiple fixed tilted supporters are fixed on the firm banking (1), and the fixed tilted supporter of arbitrary neighborhood two it
Between formed with gap;Multiple components are both provided with any one of fixed tilted supporter and place bracket (5), multiple components
It is evenly distributed to place length direction of the bracket (5) along the fixed tilted supporter;Any two on two neighboring fixed tilted supporter
Component is placed bracket (5) and is all staggered;The component is placed to be set on one end of the remote fixed tilted supporter of bracket (5)
There is stop mechanism.
2. shot blasting method according to claim 1, it is characterised in that after step 1), also including before step 1) will
Multiple frock moulding beds are lifted on the inlet roller way of shot-blasting machine, and place multiple steel members on multiple frock moulding beds respectively
(6)。
3. shot blasting method according to claim 1, it is characterised in that multiple fixed tilted supporters include being fixed in firm banking
(1) multiple first on fix tilted supporters (2) and the multiple second fixation tilted supporters (3) being fixed on the firm banking (1);
It is described first fixation tilted supporter (2) and it is described second fix tilted supporter (3) be oppositely arranged, it is described first fixation tilted supporter (2) and
The remote of tilted supporter (3) is fixed in described second gap fixed between tilted supporter (3) along the described first fixation tilted supporter (2) or second
One end from the firm banking (1) becomes larger to one end close to the firm banking (1);And described first fixes tiltedly branch
Frame (2) be fixed in the upper end points of the firm banking (1) be equal to the vertical range of one end of the firm banking (1) it is described
Second fixation tilted supporter (3) is fixed in end points on the firm banking (1) to the vertical of the other end of the firm banking (1)
Distance.
4. shot blasting method according to claim 3, it is characterised in that described first fixes tilted supporter (2) and described second
Multiple web beams (4) are additionally provided between fixed tilted supporter (3);The both ends of the web beam (4) are respectively and fixedly connected to described
First, which fixes tilted supporter (2) and described second, fixes on tilted supporter (3);The multiple web beam (4) institutes are in the longitudinal direction
Straight line be all parallel to each other.
5. shot blasting method according to claim 3, it is characterised in that lead between multiple first fixation tilted supporters (2)
Cross multiple first and strengthen longeron connection, multiple described second fix between tilted supporter (3) by the multiple second reinforcement longerons connections;
And it is provided with hanger (7) on any number of first reinforcement longerons and/or any number of second reinforcement longerons.
6. shot blasting method according to claim 3, it is characterised in that in step 1), any two steel member (6) is all handed over
Mistake is set, so that Shot Blasting can be carried out by obtaining the exposed face of multiple steel members (6).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710437728.4A CN107378792A (en) | 2017-06-12 | 2017-06-12 | Shot blasting method for the frock moulding bed of steel member ball blast |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710437728.4A CN107378792A (en) | 2017-06-12 | 2017-06-12 | Shot blasting method for the frock moulding bed of steel member ball blast |
Publications (1)
Publication Number | Publication Date |
---|---|
CN107378792A true CN107378792A (en) | 2017-11-24 |
Family
ID=60331766
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201710437728.4A Withdrawn CN107378792A (en) | 2017-06-12 | 2017-06-12 | Shot blasting method for the frock moulding bed of steel member ball blast |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN107378792A (en) |
Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2004066348A (en) * | 2002-08-01 | 2004-03-04 | Honda Motor Co Ltd | Shot blasting apparatus |
CN101157203A (en) * | 2007-09-24 | 2008-04-09 | 无锡国达机械设备有限公司 | Automobile gear ruggedization shot-blasting machine |
CN202071016U (en) * | 2011-05-12 | 2011-12-14 | 安徽伟宏钢结构有限公司 | Shot blasting device for large spare parts |
CN202895019U (en) * | 2012-11-12 | 2013-04-24 | 上海中远川崎重工钢结构有限公司 | Novel three-dimensional jig frame for efficient shot blasting of slender members |
CN104084733A (en) * | 2014-06-26 | 2014-10-08 | 宁夏共享装备有限公司 | Tooling jig frame |
CN105415200A (en) * | 2015-12-22 | 2016-03-23 | 杭州鑫格金属制品有限公司 | Full-automatic numerical control shotblast cleaning equipment |
CN106272089A (en) * | 2016-07-29 | 2017-01-04 | 中建钢构有限公司 | H-shaped steel shot blasting device and shot blasting processing method |
-
2017
- 2017-06-12 CN CN201710437728.4A patent/CN107378792A/en not_active Withdrawn
Patent Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2004066348A (en) * | 2002-08-01 | 2004-03-04 | Honda Motor Co Ltd | Shot blasting apparatus |
CN101157203A (en) * | 2007-09-24 | 2008-04-09 | 无锡国达机械设备有限公司 | Automobile gear ruggedization shot-blasting machine |
CN202071016U (en) * | 2011-05-12 | 2011-12-14 | 安徽伟宏钢结构有限公司 | Shot blasting device for large spare parts |
CN202895019U (en) * | 2012-11-12 | 2013-04-24 | 上海中远川崎重工钢结构有限公司 | Novel three-dimensional jig frame for efficient shot blasting of slender members |
CN104084733A (en) * | 2014-06-26 | 2014-10-08 | 宁夏共享装备有限公司 | Tooling jig frame |
CN105415200A (en) * | 2015-12-22 | 2016-03-23 | 杭州鑫格金属制品有限公司 | Full-automatic numerical control shotblast cleaning equipment |
CN106272089A (en) * | 2016-07-29 | 2017-01-04 | 中建钢构有限公司 | H-shaped steel shot blasting device and shot blasting processing method |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN106927353B (en) | LNG storage tank tank inner tube pipe fitting method | |
CN106141476B (en) | A kind of assemble method of super-large diameter without ribbed stiffener thin-wall semi top seal closure | |
CN104190834B (en) | A kind of arm hammer | |
CN106927361B (en) | A kind of electromechanics large scale equipment level and vertical multi-transportation hanging apparatus | |
CN107378792A (en) | Shot blasting method for the frock moulding bed of steel member ball blast | |
CN106272089A (en) | H-shaped steel shot blasting device and shot blasting processing method | |
CN110411865A (en) | A kind of bamboo composite material impact strength test equipment and its test method | |
CN105382779B (en) | Environmentally friendly liftable rotating type spraying room rotary lifting mechanism | |
CN106016233A (en) | Boiler roof with long span and fewer welding spots and hoisting method for boiler roof | |
KR20090123707A (en) | Automatic quenching machine for high pressure gas container | |
CN107139082A (en) | Frock moulding bed for steel member ball blast | |
CN207791912U (en) | A kind of upper winding apparatus | |
CN106121252B (en) | A kind of hydraulic stepping is from climbing material transfering device and method | |
CN106437126B (en) | A kind of console mode hydraulic lifting scaffold guiding bearing and method for dismounting | |
CN107132118A (en) | A kind of universal experimental provision of ship bay section crankling vibration | |
CN106518162A (en) | Blank storage heat-insulation device, ceramic brick drying and heat-insulation system and method | |
CN110358902B (en) | Shot peening strengthening device and method for remarkably prolonging fatigue life of transverse plate spring | |
CN114473881A (en) | Efficient surface treatment equipment and method for workpiece | |
CN108165711B (en) | A kind of quenching cooling system and quenching and cooling method | |
CN206843953U (en) | Sizing auxiliary construction platform in a kind of high-speed railway pier | |
CN106834598A (en) | A kind of converter oxygen gun gun body anti-deformation hanging method | |
CN205603035U (en) | Radiant tube hoist | |
CN206530874U (en) | Welded insulated gas cylinder frame structure | |
CN208545084U (en) | Fractionation combined console for the assembling of boiler furnace dry bottom hopper | |
CN205977715U (en) | Axial -flow pump that possesses high strength |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
WW01 | Invention patent application withdrawn after publication |
Application publication date: 20171124 |
|
WW01 | Invention patent application withdrawn after publication |