CN107368996A - The problem of live project processing/monitoring and managing method/system, storage medium, terminal - Google Patents

The problem of live project processing/monitoring and managing method/system, storage medium, terminal Download PDF

Info

Publication number
CN107368996A
CN107368996A CN201710432781.5A CN201710432781A CN107368996A CN 107368996 A CN107368996 A CN 107368996A CN 201710432781 A CN201710432781 A CN 201710432781A CN 107368996 A CN107368996 A CN 107368996A
Authority
CN
China
Prior art keywords
project
live
event
incident
buildings models
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201710432781.5A
Other languages
Chinese (zh)
Other versions
CN107368996B (en
Inventor
黄健
詹生锐
邢雷兵
王卓
潘强
苏威
王峰
徐雨祥
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Jiashi (group) Co Ltd
Original Assignee
Shanghai Jiashi (group) Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Jiashi (group) Co Ltd filed Critical Shanghai Jiashi (group) Co Ltd
Priority to CN201710432781.5A priority Critical patent/CN107368996B/en
Publication of CN107368996A publication Critical patent/CN107368996A/en
Application granted granted Critical
Publication of CN107368996B publication Critical patent/CN107368996B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/10Office automation; Time management
    • G06Q10/103Workflow collaboration or project management
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
    • G06Q50/08Construction

Landscapes

  • Business, Economics & Management (AREA)
  • Human Resources & Organizations (AREA)
  • Strategic Management (AREA)
  • Engineering & Computer Science (AREA)
  • General Business, Economics & Management (AREA)
  • Entrepreneurship & Innovation (AREA)
  • Economics (AREA)
  • Marketing (AREA)
  • Theoretical Computer Science (AREA)
  • General Physics & Mathematics (AREA)
  • Tourism & Hospitality (AREA)
  • Physics & Mathematics (AREA)
  • Data Mining & Analysis (AREA)
  • Quality & Reliability (AREA)
  • Operations Research (AREA)
  • Health & Medical Sciences (AREA)
  • General Health & Medical Sciences (AREA)
  • Primary Health Care (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The present invention provide a kind of the problem of live project handling method/system, monitoring and managing method/system of live project, storage medium, and terminal, processing system includes the problem of the live project:Problem creation module, for marking project problem on a BUILDINGS MODELS, the BUILDINGS MODELS picture starting problem event inputting interface of project problem has been marked by interception, the information data on project problem has been inputted using described problem event inputting interface, generates problem incident.The problem of live project of the present invention handling method/system, monitoring and managing method/system of live project, storage medium, and terminal can bring construction manager sensation on the spot in person, experience sense is more preferable, and improves the efficiency of management of workmen, realizes with no paper project management.

Description

The problem of live project processing/monitoring and managing method/system, storage medium, terminal
Technical field
The invention belongs to architectural engineering application management field, is related to a kind of processing/monitoring and managing method and system, more particularly to A kind of the problem of live project processing/monitoring and managing method/system, storage medium, terminal.
Background technology
BIM (Building Information Modeling, i.e. BIM) is that (area of computer aided is set after CAD Meter) appear in the another important Computer Applied Technology of engineering construction industry after technology, triggering history of building trade without The thorough revolution of precedent.The technology utilizes digital modeling software, improves Project design, construction and the efficiency of management, and to use The building enterprise of the technology brings great newly-increased value.
Design is improved using BIM platforms at present, avoids doing over again, analogue simulation, Optimizing Construction Scheme etc. is carried out with BIM The relative maturity that technology has been applied.But for how using BIM to come the potential that accurate instruction construction carries out, not yet someone at the scene Excavate.
The situation of site operation is at present, site operation personnel according to the arrangement and method for construction worked out in advance, with reference to national standard Specification etc. carries out site operation, and then management carries out an acceptance inspection further according to national acceptance standard.The data such as substantial amounts of drawing, standard are all Need to take scene to, to consult at any time.The architectural drawing of traditional live project can not bring construction manager body and face it The sensation in border, experience sense are poor.
Therefore, a kind of the problem of how providing live project processing/monitoring and managing method/system, storage medium, terminal, with solution Certainly prior art can not bring construction manager sensation on the spot in person due to the architectural drawing of traditional live project, experience Feel the defects of poor, it is real with as those skilled in the art's technical problem urgently to be resolved hurrily.
The content of the invention
In view of the above the shortcomings that prior art, at a kind of the problem of live project Reason/monitoring and managing method/system, storage medium, terminal, for solving in the prior art due to the architectural drawing of traditional live project It can not bring construction manager sensation on the spot in person, the problem of experience sense difference.
In order to achieve the above objects and other related objects, processing system the problem of a kind of live project of one aspect of the present invention offer System, processing system includes the problem of the live project:Problem creation module, asked for marking project on a BUILDINGS MODELS Topic, the BUILDINGS MODELS picture starting problem event inputting interface of project problem is marked by interception, has utilized described problem event Inputting interface inputs the information data on project problem, creates problem incident.
In one embodiment of the invention, the information data of the live project includes project problem title, project problem Numbering, project problem types, project issue resolution status, project problem emergency level or/and project problem specialty;Described problem Type includes safety problem, quality problems or/and the 3rd type problem;The emergency level includes general data problem, important Project problem or/and emergent project problem;The project issue resolution status include state to be solved, solve in state or/and Solves state;The project problem specialty includes construction project problem, structure item problem, electrical project problem, plumbing Project problem, HVAC project problem, fire-fighting project problem, place project problem or/and the 9th items problem.
In one embodiment of the invention, after described problem event inputting interface starts, marked on the BUILDINGS MODELS Project problem is stored in the BUILDINGS MODELS picture, is not preserved on the BUILDINGS MODELS;The BUILDINGS MODELS picture is in institute State when problem incident inputting interface starts and be automatically added to described problem event inputting interface.
In one embodiment of the invention, described problem submits module to be used to submit asking for described problem creation module generation Topic event, and the live project information processing system enter communication link status after, with mail he submit described in ask Topic event;Or bind described problem event and Quick Response Code, submit the Quick Response Code.
Another aspect of the present invention provide a kind of the problem of live project processing method, processing side the problem of the live project Method includes:Project problem is marked on a BUILDINGS MODELS, the BUILDINGS MODELS picture startup that project problem has been marked by interception is asked Topic event inputting interface;The information data on project problem is inputted using described problem event inputting interface, creates problem thing Part.
Another aspect of the present invention also provides a kind of supervisory systems of live project, the supervisory systems bag of the live project Include:Memory module, for storing the BUILDINGS MODELS of live project;Screening module, for according to screening conditions, entering to problem incident Row screening, to obtain the selection result of problem incident;Described problem Event origin is in the live item described in power 1 to 4 any one of power Purpose problem processing system;Processing module, instruction is checked for Receiver Problem, instruction is checked according to described problem, searched therewith The content of corresponding problem incident, and show by display module the content of the problem incident;The content bag of described problem event Include project question number, promoter, project problem specialty, the type of project problem, problem title, and/or project problem details; The screening conditions include project problem types, emergency level, any combination for solving the problems, such as state or project specialty.
In one embodiment of the invention, the content also photo site including project problem, the positioning of described problem event Icon, Quick Response Code and/or message board;Include selection icon on the message board and transfer icon;The processing module includes:It is fixed Bit location, it is corresponding with described the target icon, for the BUILDINGS MODELS and described problem event link, to be sensed arrive to be triggered into institute After stating the target icon, modal position corresponding with the positioning instruction is searched on the BUILDINGS MODELS;Binding unit, for inciting somebody to action The content of described problem event is bound with Quick Response Code;It is waiting receive scan the Quick Response Code scan request when, push it is described The content of problem incident, and/or position of the problem incident where go the BUILDINGS MODELS;Photographing unit is selected, it is and described Select icon corresponding, for the selection demand according to user, selection is taken pictures the content of described problem event, and is input to institute State on message board;Unit is transferred, transfers that icon is corresponding with described, for transferring demand according to user, is showed from what collection obtained Picture is transferred in field picture, and is input on the message board.
Another aspect of the present invention provides a kind of monitoring and managing method of live project, the monitoring and managing method bag of the live project again Include:Store the BUILDINGS MODELS of live project;According to screening conditions, problem incident is screened, to obtain the sieve of problem incident Select result;Receiver Problem checks instruction, and instruction is checked according to described problem, searches the content of corresponding problem incident, and Show the content of the problem incident;The content of described problem event include project question number, promoter, project problem specialty, Type, problem title, and/or the project problem details of project problem.
Another aspect of the invention provides a kind of storage medium, is stored thereon with computer program, the program is held by processor The problem of live project is realized during row processing method, or realize the monitoring and managing method of the live project.
Last aspect of the present invention provides a kind of terminal, including:Processor and memory;The memory is based on storing Calculation machine program, the processor is used for the computer program for performing the memory storage, so that terminal execution is described existing The problem of project processing method, or realize the monitoring and managing method of the live project
As described above, the problem of live project of present invention processing/monitoring and managing method/system, storage medium, terminal, has Following beneficial effect:
Information processing/monitoring and managing method, system and the electronic equipment of live project of the present invention can bring construction pipe Reason personnel sensation on the spot in person, experience sense is more preferable, and improves the efficiency of management of workmen, realizes with no paper project pipe Reason.
Brief description of the drawings
Fig. 1 is shown as theory structure schematic diagram of the problem of live project of present invention processing system in an embodiment.
Fig. 2 is shown as schematic flow sheet of the problem of live project of present invention processing method in an embodiment.
Fig. 3 is shown as theory structure schematic diagram of the supervisory systems of the live project of the present invention in an embodiment.
Fig. 4 is shown as floor map of the second display interface of the present invention in an embodiment.
Fig. 5 is shown as schematic flow sheet of the monitoring and managing method of the live project of the present invention in an embodiment.
Component label instructions
The problem of 1 live project processing system
11 first memory modules
12 problem creation modules
13 problems submit module
The supervisory systems of 3 live projects
31 second memory modules
32 lightweight modules
33 screening modules
34 processing modules
35 display modules
341 positioning units
342 provide unit
343 selection photographing units
344 transfer unit
345 feedback units
S21~S23 steps
S51~S55 steps
Embodiment
Illustrate embodiments of the present invention below by way of specific instantiation, those skilled in the art can be by this specification Disclosed content understands other advantages and effect of the present invention easily.The present invention can also pass through specific realities different in addition The mode of applying is embodied or practiced, the various details in this specification can also be based on different viewpoints with application, without departing from Various modifications or alterations are carried out under the spirit of the present invention.It should be noted that in the case where not conflicting, following examples and implementation Feature in example can be mutually combined.
It should be noted that the diagram provided in following examples only illustrates the basic structure of the present invention in a schematic way Think, only show the component relevant with the present invention in schema then rather than according to component count, shape and the size during actual implement Draw, kenel, quantity and the ratio of each component can be a kind of random change during its actual implementation, and its assembly layout kenel It is likely more complexity.
Embodiment one
The present embodiment provide a kind of live project the problem of processing system, the information processing system bag of the live project Include:
Problem creation module, for marking project problem on a BUILDINGS MODELS, project problem is marked by interception BUILDINGS MODELS picture starting problem event inputting interface, the letter on project problem is inputted using described problem event inputting interface Data are ceased, create problem incident.
It is described in detail below with reference to processing system the problem of illustrating the live project provided the present embodiment.This The problem of live project described in embodiment, processing system was applied in the electronic equipment with touch display screen, wherein, it is described Touch display screen provides output interface and input interface simultaneously between electronic equipment and user.The electronic equipment includes one kind Can be automatic to carry out numerical computations and information processing according to the instruction for being previously set or storing, and there is multimedia video work( The electronic equipment of energy, it includes but unlimited smart mobile phone, tablet personal computer, notebook computer etc. have the electronic equipment for touching screen Deng.The electric signal of touch display screen is gone in touch display screen controller reception/transmission from/.The touch display screen is then to user The visual output of display.This visual output can include text, figure, video and its any combination.It is some or all visual defeated Going out can be corresponding with user-interface object, and hereinafter its more details will be described.
Touch display screen receives the input of user also based on tactile and/or tactile contact.The touch display screen forms one The individual touch sensitive surface for receiving user's input.The touch display screen and touch display screen controller are (together with any in memory Associated module and/or instruction set are together) detection touch display screen on contact (and the touch any movement or in It is disconnected), and by the contact transformation detected into including such as one or more soft-key buttons in touch display screen etc The interaction of user interface object.In one exemplary embodiment, the contact point between touch display screen and user, which corresponds to, uses One or more fingers at family.The touch display screen can use LCD (liquid crystal display) technologies or LPD, and (light emitting polymer shows Show device) technology, but other Display Techniques can be used in other embodiments.Touch display screen and touch display screen controller can be with Included but is not limited to using any one of a variety of Touch technologies to detect contact and its mobile or interruption, these Touch technologies Electric capacity, resistance, infrared and surface acoustic wave techniques, and other proximity sensor arrays, or for determining and touch display screen phase The other technologies of the one or more points of contact.User can use any appropriate object or accessory, such as instruction pen, finger etc. Deng to contact touch display screen.
Contact/motion module detects the contact with touch display screen together with touch display screen controller.Contact/the fortune Dynamic model block includes being used for the various component softwares for performing the associated various operations of the detection of the contact with touch display screen, described Operation for example, determines whether to be in contact, and determines whether the contact moves, and the movement in tracking touch display screen, and really Whether whether the fixed contact interrupted and (stop contacting).Determine that the operation of contact point movement can include determining that the speed of contact point (amplitude), speed (amplitude and direction) and/or acceleration (including amplitude and/or direction).In certain embodiments, contact/fortune Dynamic model block also detects the contact on touch pad with touch display screen controller.
In the present embodiment, the live project includes construction site, finishing scene etc..
Specifically, referring to Fig. 1, theory structure of the problem of the being shown as live project processing system in an embodiment shows It is intended to.As shown in figure 1, the problem of live project processing system 1 includes the first memory module 11, the and of problem creation module 12 Problem submits module 13.
First memory module 11 is used for the BUILDINGS MODELS for storing live project.The BUILDINGS MODELS is to be based on including Include various dependent vector architectural drawing, architecture information, component name, the geometry of component for being used to emulate the live construction project Size, material, weight, color, three-dimensional localization information under construction, progress msg, the place even cost information etc. transported to The 3D models obtained Deng model file emulation.
The described problem creation module 12 being connected with first memory module 11 is used to mark on the BUILDINGS MODELS Project problem, the BUILDINGS MODELS picture starting problem event inputting interface of project problem is marked by interception, has been asked using described Topic event inputting interface inputs the information data on project problem, creates problem incident..The information data of the project problem Including project problem title, project question number, project problem types, project problem emergency level and project problem specialty.
Specifically, described problem creation module 11 is used to be suspended on the predeterminable area of the BUILDINGS MODELS by touching Problem submits icon, and project problem is marked on the BUILDINGS MODELS.In the present embodiment, it is to be sensed to submit figure to described problem Put on when there is click action, combobox occur, the combobox includes various problems mark icon, and problem addition icon.Institute Stating problem mark icon includes label character icon, different colours underlining, and revocation previous action icon.Specifically, Described problem creation module 11 by the project problem according to problem types, emergency level, solve the problems, such as that state or/and project are special Industry is divided.Described problem type includes safety problem, quality problems or/and the 3rd type problem (other types problem); The emergency level includes general data problem, big event problem or/and emergent project problem;The solution state includes State to be solved, state or/and solves state in solving;The project problem specialty includes construction project problem, structure item Mesh problem, electrical project problem, plumbing project problem, HVAC project problem, fire-fighting project problem, place project problem or/ With the 9th items problem (other items problems).
For example, problem information is No. 6 building 2 construction area, the line that mops floor is oversize, and leaves unused always on ground, has a strong impact on small The safety of stroller operator.This problem may result in operator and trip, tumbles, injured possibility even be present, should be whole immediately Change.The picture for the BUILDINGS MODELS that No. 2 construction areas in No. 6 building are configured on interface is created in described problem for No. 6 construction area of building 2.Institute The photo site of project problem is stated in the photograph album of electronic equipment, or upper crossing is taken on site.
Specifically, described problem creation module 11 is according to label character icon, different colours underlining, and revocation upper one The marking Function that step handle icon is provided, to assist mark of operating personnel's addition for described problem event.The present embodiment Provided in a variety of marking Functions can be used for marked on BUILDINGS MODELS.
In the present embodiment, after described problem event inputting interface starts, the project problem that is marked on the BUILDINGS MODELS It is stored in the BUILDINGS MODELS picture, is not preserved on the BUILDINGS MODELS;The BUILDINGS MODELS picture is in described problem thing Part inputting interface is automatically added to described problem event inputting interface when starting.The problem of being connected with described problem creation module 12 The problem of submitting module 13 to be used to submit described problem creation module 12 to generate event, and in the information processing of the live project After system enters communication link status, described problem event is submitted with mail he;Or described problem event is tied up with Quick Response Code It is fixed, submit the Quick Response Code.In the present embodiment, described problem submits module 12 when submitting described problem event, can also incite somebody to action Described problem event is transmitted to the terminal bound with the electronic equipment, and is the Quick Response Code of described problem event binding one, to grasp Make personnel and download described problem event.In the present embodiment, the electronic equipment is in a printing device for printing Quick Response Code Connection.
In the present embodiment, described problem is created and also included to cancel the cancellation icon of establishment problem incident on interface, To print the print icon of the problem of created event.
Embodiment two
The present embodiment provide a kind of the problem of live project processing method, the information processing method of the live project is specific Including following steps:
Project problem is marked on a BUILDINGS MODELS, the BUILDINGS MODELS picture startup that project problem has been marked by interception is asked Topic event inputting interface;
The information data on project problem is inputted using described problem event inputting interface, creates problem incident.Below The information processing method of the live project described in the present embodiment will be described in detail with reference to diagram.Referring to Fig. 2, it is shown as The problem of live project schematic flow sheet of the processing method in an embodiment.As shown in Fig. 2 at the problem of live project Reason method specifically includes following steps:
S21, store the BUILDINGS MODELS of live project.
S22, project problem is marked on a BUILDINGS MODELS, the BUILDINGS MODELS picture that project problem has been marked by interception opens Dynamic problem incident inputting interface;The information data on project problem is inputted using described problem event inputting interface, establishment is asked Topic event.The problem incident is associated with the project problem in the live project occurs.The information data of the project problem Including project problem title, project question number, project problem types, project problem emergency level and project problem specialty. In the present embodiment, creating the process of problem incident includes:
By the project problem according to problem types, emergency level, solve the problems, such as that state or/and project specialty are drawn Point;
Project problem is marked on a BUILDINGS MODELS, the BUILDINGS MODELS picture startup that project problem has been marked by interception is asked Topic event inputting interface.In the present embodiment, according to label character icon, different colours underlining, and revocation previous step behaviour Make a variety of marking Functions that icon is provided, to assist operating personnel to mark project problem on the BUILDINGS MODELS.
The information data on project problem is inputted using described problem event inputting interface, generates problem incident.
S23, the problem of submitting the generation of described problem creation module event, and in the information processing system of the live project Into after communication link status, described problem event is submitted to the terminal with electronic equipment binding with mail he;Or by described in Problem incident is bound with Quick Response Code, submits the Quick Response Code, so that operating personnel download described problem event.
Embodiment three
The present embodiment provides a kind of supervisory systems of live project, it is characterised in that the supervisory systems of the live project Including:
Memory module, for storing the BUILDINGS MODELS of live project;
Screening module, for according to screening conditions, being screened to problem incident, to obtain the screening knot of problem incident Fruit;Described problem Event origin processing system in the live project described in embodiment one the problem of.
Processing module, instruction is checked for Receiver Problem, is checked instruction according to described problem, is searched corresponding problem The content of event, and show by display module the content of the problem incident;The content of described problem event includes project problem Numbering, promoter, project problem specialty, the type of project problem, problem title, and/or project problem details.
The supervisory systems of the live project provided below with reference to diagram the present embodiment is described in detail.It is described existing The supervisory systems of field project applies equally to have in the electronic equipment of touch display screen, wherein, the touch display screen is in electricity Output interface and input interface are provided between sub- equipment and user simultaneously.Referring to Fig. 3, it is shown as the supervisory systems of live project Theory structure schematic diagram in an embodiment.As shown in figure 3, the supervisory systems 3 of the live project includes the second storage mould Block 31, lightweight module 32, screening module 33, processing module 34 and display module 35.
Second memory module 31 is used for the BUILDINGS MODELS for storing live project.The BUILDINGS MODELS is to be based on including Include various dependent vector architectural drawing, architecture information, component name, the geometry of component for being used to emulate the live construction project Size, material, weight, color, three-dimensional localization information under construction, progress msg, the place even cost information etc. transported to The 3D models obtained Deng model file emulation.
The lightweight module 32 being connected with second memory module 31 is used for the building mould for the live project that will be stored Type carries out light-weight technologg, to extract the key point of the BUILDINGS MODELS, forms simplified BUILDINGS MODELS.It is light-weighted at present Technology has a variety of, and representative has two kinds of JT and 3DXML.3DXML is the lightweight skill of the propositions such as Dassault, Microsoft Art, JT are that JT opens the Lightweight Technology that tissue proposes.
The screening module 33 being connected with the lightweight module 32 is used for according to screening conditions, and problem incident is sieved Choosing, to obtain the selection result of problem incident.In the present embodiment, the screening conditions include problem types, emergency level, solution The certainly any combination of state or/and project problem specialty.Described problem type includes safety problem, quality problems or/and the 3rd Type problem;The emergency level includes general data problem, big event problem or/and emergent project problem;The solution State includes state in state to be solved, solution or/and has solved state;The project problem specialty is asked including construction project Topic, structure item problem, electrical project problem, plumbing project problem, HVAC project problem, fire-fighting project problem, place item Mesh problem or/and the 9th items problem.
For example, problem types is safety problem in the screening conditions, the emergency level is big event problem, described Solution state is unresolved state, and project problem specialty is place.Problem incident A, problem are filtered out according to above-mentioned screening conditions Event B, problem incident C, problem incident D.In the present embodiment by problem incident A, problem incident on first display interface B, problem incident C, problem incident D enter ranks with question icon A1, question icon B1, question icon C1, question icon D1 respectively Table is shown, and question icon A1, question icon B1, question icon C1, and question icon D1 provides the thing for entering and checking problem information Part enters incoming interface A2, and event enters incoming interface B2, and event enters incoming interface C2, and event enters incoming interface D2.Event enters incoming interface A2, event Enter incoming interface B2, the problem of event enters incoming interface C2, and event is entered incoming interface D2 and created event A, problem incident B, problem thing Part C, problem incident D are linked together.
For example, specialty described in the screening conditions is place, the proximity state is unresolved state, described problem class Type is that the special equipment management in safety problem is not in place.It is not in place that special equipment management is filtered out according to above-mentioned screening conditions Major issue event E1, special equipment manage burning issue event F1 not in place.Major issue event E1 and burning issue thing Part F1 is respectively with question icon E2 and question icon F2 list displays, and question icon E2 and question icon F2 is provided to enter and checked The event of problem information enters incoming interface E3 and F3, and event enters incoming interface E3 and F3 and the major issue event E1 that creates and promptly Problem incident F1 is linked together.
The processing module 34 being connected with the screening module 33 checks instruction for Receiver Problem, is checked according to described problem Instruction, the content of corresponding problem incident is searched, and the content of the problem incident is shown by display module;Described problem The content of event include project question number, promoter, project problem specialty, the type of project problem, problem title, and/or Project problem details.For example, Trigger Problems icon F2, enters incoming interface F3 by event and searches corresponding burning issue event Content F1.
The display module 35 being connected with the processing module 34 is used for the content for showing the problem of finding event.It is described The content of problem incident includes project question number, promoter, project problem specialty, the type of project problem, problem title, item The problem of mesh problem information, the photo site of project problem, the target icon, Quick Response Code and/or message board;Wrapped on the message board Include selection icon and transfer icon.In the present embodiment, the content of the problem of finding event is shown by display interface.
For example, the burning issue event F1 found is included on the display interface.Shown on the display interface It is place that it is 210011 that the problem of burning issue event F1, which numbers, initiates artificial so-and-so, the specialty, problem types is to ask safely Topic, the entitled Electrical Safety hidden danger of problem, information is No. 6 building 2 construction area the problem of project problem, and the line that mops floor is oversize, and one Directly leave unused on ground, have a strong impact on the safety of small handcart operator, this problem may result in operator and trip, tumbles, even In the presence of the possibility of injury, should rectify and improve immediately, the photo site of 4 width project problems, and navigate to the positioning of No. 2 construction areas in No. 6 building Icon, Quick Response Code and message board with burning issue event F1 bindings.The Quick Response Code is bound with described problem display interface, Or with the project problem in the binding positions where the BUILDINGS MODELS.Figure Fig. 4 is referred to, it is real in one to be shown as display interface Apply the floor map in example.
In the present embodiment, stay on the display interface sense click on described the target icon when, the processing module Positioning unit 341 in 34 is corresponding with described the target icon, for by the BUILDINGS MODELS and described problem event link, waiting to feel After measuring the described the target icon of triggering, modal position corresponding with the positioning instruction is searched on the BUILDINGS MODELS.
It is to be sensed to the scan instruction for scanning the Quick Response Code when, the binding unit 342 in the processing module 34 is used for The content Quick Response Code of problem incident is bound, it is waiting when receiving the scan request for scanning the Quick Response Code, push described problem event Content, and/or the problem incident go the BUILDINGS MODELS where position.
Stay on the display interface and sense when clicking on the selection icon, in the processing module 35 with the choosing Selection demand of the selection photographing unit 343 corresponding to icon according to user is selected, selects on the display interface selection to take pictures described The content of problem incident, and be input on the message board.
Stay on the display interface and sense described in click when transferring icon, in the processing module 34 with the tune Take icon correspondingly to transfer unit 344 and demand transferred according to user, picture is transferred in the photo site obtained from collection, and by its On input to the message board.
When staying on the message board on the display interface feedback opinion for receiving operating personnel, in the processing module 34 Feedback module 345 by the feedback opinion include on the message board.In the present embodiment, the profit of feedback module 345 With dummy keyboard on display interface opinion is inputted in feedback opinion input frame.
Example IV
The present embodiment provides a kind of monitoring and managing method of live project, and the monitoring and managing method of the live project includes:
Store the BUILDINGS MODELS of live project;
According to screening conditions, problem incident is screened, to obtain the selection result of problem incident;
Receiver Problem checks instruction, and instruction is checked according to described problem, searches the content of corresponding problem incident, and Show the content of the problem incident;The content of described problem event include project question number, promoter, project problem specialty, Type, problem title, and/or the project problem details of project problem.
The monitoring and managing method of the live project provided below with reference to diagram the present embodiment is described in detail.Refer to Fig. 5, it is shown as schematic flow sheet of the monitoring and managing method of live project in an embodiment.As shown in figure 5, the live project Monitoring and managing method specifically includes following steps:
S51, store the BUILDINGS MODELS of live project.The BUILDINGS MODELS is various described for emulating based on including The dependent vector architectural drawing of live construction project, the architecture information of component, component name, physical dimension, material, weight, face Color, three-dimensional localization information under construction, progress msg, place even cost information etc. model file emulation acquisition transported to 3D models.
S52, the BUILDINGS MODELS of the live project stored is subjected to light-weight technologg, to extract the BUILDINGS MODELS Key point, form simplified BUILDINGS MODELS.
S53, according to screening conditions, problem incident is screened, to obtain the selection result of problem incident.In this implementation In example, the screening conditions include problem types, emergency level, any combination for solving the problems, such as state or/and project specialty.Institute Stating problem types includes safety problem, quality problems or/and the 3rd type problem;The emergency level is asked including general data Topic, big event problem or/and emergent project problem;The solution state include state to be solved, solve in state or/and Solves state;The project problem specialty includes construction project problem, structure item problem, electrical project problem, plumbing Project problem, HVAC project problem, fire-fighting project problem, place project problem or/and the 9th items problem.
S54, Receiver Problem check instruction, check instruction according to described problem, search the interior of corresponding problem incident Hold.The content of described problem event includes project question number, promoter, project problem specialty, the type of project problem, problem Title, and/or project problem details.
The step S54 specifically include stay on the display interface sense click on described the target icon when, will described in BUILDINGS MODELS and described problem event link, it is to be sensed to after triggering described the target icon, searched on the BUILDINGS MODELS with Modal position corresponding to the positioning instruction.
It is to be sensed to the scan instruction for scanning the Quick Response Code when, the content Quick Response Code of problem incident is bound, it is to be received During to the scan request for scanning the Quick Response Code, the content of described problem event is pushed, and/or the problem incident is in the building mould Position where go type.
Stay on the display interface and sense when clicking on the selection icon, according to the selection demand of user, select institute State on display interface selection to take pictures the content of described problem event, and be input on the message board.
Stay on the display interface and sense described in click when transferring icon, demand is transferred according to user, from collection Picture is transferred in the photo site of acquisition, and is input on the message board.
When staying on the message board on the display interface feedback opinion for receiving operating personnel, the feedback opinion is shown Show on the message board.In the present embodiment, meaning is inputted in feedback opinion input frame using dummy keyboard on display interface See.
S55, show the content of the problem of finding event.The content of described problem event include project question number, The problem of promoter, project problem specialty, the type of project problem, problem title, project problem information, the scene of project problem Picture, the target icon, Quick Response Code and/or message board;Include selection icon on the message board and transfer icon.In the present embodiment In, the content of the problem of finding event is shown by display interface.
Embodiment five
The present embodiment provides a kind of storage medium (computer-readable recording medium), is stored thereon with computer program, its Be characterised by, the problem of program realizes the live project when being executed by processor processing method, or realize the live item Purpose monitoring and managing method.One of ordinary skill in the art will appreciate that:Realize all or part of step of above-mentioned each method embodiment It can be completed by the related hardware of computer program.Foregoing computer program can be stored in a computer-readable storage In medium.The program upon execution, execution the step of including above-mentioned each method embodiment;And foregoing storage medium includes: ROM, RAM, magnetic disc or CD etc. are various can be with the medium of store program codes.
Embodiment six
The present embodiment provides a kind of terminal, including:Processor, memory, transceiver, communication interface and system bus;Deposit Reservoir and communication interface are connected with processor and transceiver by system bus and complete mutual communication, and memory is used to deposit Computer program is stored up, communication interface is used for and other equipment is communicated, and processor and transceiver are used to run computer program, Terminal performs each step of the problem of live project as described above processing method, or performs the monitoring and managing method of live project as described above Each step.
System bus mentioned above can be Peripheral Component Interconnect standard (PeripheralPomponentInterconnect, abbreviation PCI) bus or EISA (ExtendedIndustryStandardArchitecture, abbreviation EISA) bus etc..The system bus can be divided into address Bus, data/address bus, controlling bus etc..For ease of representing, only represented in figure with a thick line, it is not intended that only one total Line or a type of bus.Communication interface is used for accessing data base device and other equipment (such as client, read-write storehouse And read-only storehouse) between communication.Memory may include random access memory (RandomAccessMemory, abbreviation RAM), Nonvolatile memory (non-volatilememory), for example, at least a magnetic disk storage may also also be included.
Above-mentioned processor can be general processor, including central processing unit (CentralProcessingUnit, letter Claim CPU), network processing unit (NetworkProcessor, abbreviation NP) etc.;It can also be digital signal processor (DigitalSignalProcessing, abbreviation DSP), application specific integrated circuit (ApplicationSpecificIntegratedCircuit, abbreviation ASIC), field programmable gate array (Field- ProgrammableGateArray, abbreviation FPGA) either other PLDs, discrete gate or transistor logic device Part, discrete hardware components.
In summary, processing/monitoring and managing method/system the problem of live project of the present invention, storage medium, terminal can To bring construction manager sensation on the spot in person, experience sense is more preferable, and improves the efficiency of management of workmen, realizes nothing Paper project management.So the present invention effectively overcomes various shortcoming of the prior art and has high industrial utilization.
The above-described embodiments merely illustrate the principles and effects of the present invention, not for the limitation present invention.It is any ripe Know the personage of this technology all can carry out modifications and changes under the spirit and scope without prejudice to the present invention to above-described embodiment.Cause This, those of ordinary skill in the art is complete without departing from disclosed spirit and institute under technological thought such as Into all equivalent modifications or change, should by the present invention claim be covered.

Claims (10)

1. the problem of a kind of live project processing system, it is characterised in that processing system includes the problem of the live project:
Problem creation module, for marking project problem on a BUILDINGS MODELS, the building of project problem is marked by interception Model picture starting problem event inputting interface, the Information Number on project problem is inputted using described problem event inputting interface According to establishment problem incident.
2. the problem of live project according to claim 1 processing system, it is characterised in that:Described information data include item Mesh problem title, project question number, project problem types, project issue resolution status, project problem emergency level or/and item Mesh problem specialty;Described problem type includes safety problem, quality problems or/and the 3rd type problem;The project problem is tight Anxious rank includes general data problem, big event problem or/and emergent project problem;The project issue resolution status bag Include state to be solved, solve in state or/and solved state;The project problem specialty includes construction project problem, structure Project problem, electrical project problem, plumbing project problem, HVAC project problem, fire-fighting project problem, place project problem Or/and the 9th items problem.
3. the problem of live project according to claim 1 processing system, it is characterised in that:Described problem event inputs boundary After face starts, the project problem marked on the BUILDINGS MODELS is stored in the BUILDINGS MODELS picture, is not preserved in described build Build on model;It is defeated that the BUILDINGS MODELS picture is automatically added to described problem event when described problem event inputting interface starts Enter interface.
4. the problem of live project according to claim 1 processing system, it is characterised in that:The problem of live project Processing system also includes problem and submits module;The problem of described problem submits module to be used to submit described problem creation module to generate Event, and after the information processing system of the live project enters communication link status, described problem is submitted with mail he Event, or described problem event and Quick Response Code are bound, submit the Quick Response Code.
5. the problem of a kind of live project processing method, it is characterised in that processing method includes the problem of the live project:
Project problem is marked on a BUILDINGS MODELS, the BUILDINGS MODELS picture starting problem thing of project problem has been marked by interception Part inputting interface;
The information data on project problem is inputted using described problem event inputting interface, creates problem incident.
6. a kind of supervisory systems of live project, it is characterised in that the supervisory systems of the live project includes:
Memory module, for storing the BUILDINGS MODELS of live project;
Screening module, for according to screening conditions, being screened to problem incident, to obtain the selection result of problem incident;Institute Problem incident is stated from power 1 to processing system the problem of weighing the live project described in 4 any one;
Processing module, instruction is checked for Receiver Problem, is checked instruction according to described problem, is searched corresponding problem incident Content, and show by display module the content of the problem incident;The content of described problem event include project question number, Promoter, project problem specialty, project problem types, project problem title, and/or project problem details;The screening conditions Include any combination of project problem types, project problem emergency level, project issue resolution status and project problem specialty.
7. the supervisory systems of live project according to claim 6, it is characterised in that:
The content of described problem event also includes photo site, the target icon, Quick Response Code and/or the message board of project problem;Institute Stating includes selection icon and transfers icon on message board;
The processing module includes:
Positioning unit, it is corresponding with described the target icon, it is to be sensed to arrive for by the BUILDINGS MODELS and described problem event link After triggering described the target icon, modal position corresponding with the positioning instruction is searched on the BUILDINGS MODELS;
Binding unit, for the content of described problem event and Quick Response Code to be bound;It is waiting to receive the scanning for scanning the Quick Response Code During request, the content of the described problem event, and/or position of the problem incident where go the BUILDINGS MODELS are pushed;
Photographing unit is selected, it is corresponding with the selection icon, for the selection demand according to user, select described problem thing of taking pictures The content of part, and be input on the message board;
Unit is transferred, transfers that icon is corresponding with described, for transferring demand according to user, in the photo site obtained from collection Picture is transferred, and is input on the message board.
8. a kind of monitoring and managing method of live project, it is characterised in that the monitoring and managing method of the live project includes:
Store the BUILDINGS MODELS of live project;
According to screening conditions, problem incident is screened, to obtain the selection result of problem incident;
Receiver Problem checks instruction, checks instruction according to described problem, searches the content of corresponding problem incident, and shows The content of the problem incident;The content of described problem event includes project question number, promoter, project problem specialty, project Problem types, project problem title, and/or project problem details.
9. a kind of storage medium, is stored thereon with computer program, it is characterised in that power is realized when the program is executed by processor Profit requires the problem of live project described in 5 processing method, or realizes the monitoring and managing method of the live project described in claim 8.
A kind of 10. terminal, it is characterised in that including:Processor and memory;
The memory is used to store computer program, and the processor is used for the computer journey for performing the memory storage Sequence, with
The problem of making the terminal perform live project as claimed in claim 5 processing method, or realize described in claim 8 Live project monitoring and managing method.
CN201710432781.5A 2017-06-09 2017-06-09 Method/system for problem handling/supervision of field project, storage medium, terminal Active CN107368996B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710432781.5A CN107368996B (en) 2017-06-09 2017-06-09 Method/system for problem handling/supervision of field project, storage medium, terminal

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710432781.5A CN107368996B (en) 2017-06-09 2017-06-09 Method/system for problem handling/supervision of field project, storage medium, terminal

Publications (2)

Publication Number Publication Date
CN107368996A true CN107368996A (en) 2017-11-21
CN107368996B CN107368996B (en) 2021-03-26

Family

ID=60304797

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710432781.5A Active CN107368996B (en) 2017-06-09 2017-06-09 Method/system for problem handling/supervision of field project, storage medium, terminal

Country Status (1)

Country Link
CN (1) CN107368996B (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108595864A (en) * 2018-04-28 2018-09-28 四川隧唐科技股份有限公司 Disease preparation method and device
CN108595865A (en) * 2018-04-28 2018-09-28 四川隧唐科技股份有限公司 Disease preparation method and device
CN108629427A (en) * 2018-04-28 2018-10-09 四川隧唐科技股份有限公司 Disease preparation method and device
CN108647901A (en) * 2018-05-18 2018-10-12 四川隧唐科技股份有限公司 Disease preparation method and device
CN111832255A (en) * 2020-06-29 2020-10-27 万翼科技有限公司 Label processing method, electronic equipment and related product
CN112101904A (en) * 2020-09-15 2020-12-18 江南造船(集团)有限责任公司 Ship manufacturing site problem management method, system and device of three-dimensional model

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20130231981A1 (en) * 2011-01-25 2013-09-05 Tiffany Hosey Brown Construction trade building information management system, software and method
CN103886139A (en) * 2014-02-27 2014-06-25 上海蓝色星球科技有限公司 Event interaction method based on building information model (BIM)
CN104680588A (en) * 2015-02-13 2015-06-03 上海同筑信息科技有限公司 BIM-based event marking method and system
CN104766154A (en) * 2015-02-13 2015-07-08 上海同筑信息科技有限公司 System and method for applying snapshot image to intellectualized engineering management on basis of BIM
CN105580048A (en) * 2014-03-18 2016-05-11 深圳市希图数创科技有限公司 Process management system for digital media production and method therefor

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20130231981A1 (en) * 2011-01-25 2013-09-05 Tiffany Hosey Brown Construction trade building information management system, software and method
CN103886139A (en) * 2014-02-27 2014-06-25 上海蓝色星球科技有限公司 Event interaction method based on building information model (BIM)
CN105580048A (en) * 2014-03-18 2016-05-11 深圳市希图数创科技有限公司 Process management system for digital media production and method therefor
CN104680588A (en) * 2015-02-13 2015-06-03 上海同筑信息科技有限公司 BIM-based event marking method and system
CN104766154A (en) * 2015-02-13 2015-07-08 上海同筑信息科技有限公司 System and method for applying snapshot image to intellectualized engineering management on basis of BIM

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108595864A (en) * 2018-04-28 2018-09-28 四川隧唐科技股份有限公司 Disease preparation method and device
CN108595865A (en) * 2018-04-28 2018-09-28 四川隧唐科技股份有限公司 Disease preparation method and device
CN108629427A (en) * 2018-04-28 2018-10-09 四川隧唐科技股份有限公司 Disease preparation method and device
CN108647901A (en) * 2018-05-18 2018-10-12 四川隧唐科技股份有限公司 Disease preparation method and device
CN111832255A (en) * 2020-06-29 2020-10-27 万翼科技有限公司 Label processing method, electronic equipment and related product
CN111832255B (en) * 2020-06-29 2024-05-14 深圳市万翼数字技术有限公司 Labeling processing method, electronic equipment and related products
CN112101904A (en) * 2020-09-15 2020-12-18 江南造船(集团)有限责任公司 Ship manufacturing site problem management method, system and device of three-dimensional model

Also Published As

Publication number Publication date
CN107368996B (en) 2021-03-26

Similar Documents

Publication Publication Date Title
CN107368996A (en) The problem of live project processing/monitoring and managing method/system, storage medium, terminal
CN107358401A (en) Intelligent management system/method, readable storage medium storing program for executing and the terminal of construction project
CN101291251B (en) Synchronized control method and system for multicomputer
CN104680588B (en) Event marker method and system based on BIM
CN107438814A (en) Entity action suggestion on mobile device
CN106068521A (en) Communications status about the application closing rule policy update
CN103842961A (en) System for creating personalized and customized mobile devices
WO2011112572A2 (en) Systems and methods for construction field management and operations with building information modeling
CN107256208A (en) Interaction between WEB small tools and electrical form
CN104126295A (en) Mirrored interface navigation of multiple user interfaces
CN108345543A (en) A kind of data processing method, device, equipment and storage medium
CN107734142A (en) A kind of photographic method, mobile terminal and server
CN102769635A (en) Internet of things system and implementation method of internet of things system
JP2009265719A (en) Terminal device, production information system, and program
CN107357957A (en) Intelligent supervision method/system, readable storage medium storing program for executing and the terminal of live project
CN107944000A (en) Flight freight rate update method, device, electronic equipment, storage medium
JP2020030519A (en) Process management system, process management method and program
CN106062793B (en) The retrieval for the Enterprise content being presented
CN107390922A (en) virtual touch control method, device, storage medium and terminal
JP6263919B2 (en) Information display control device, information display control method, and information display control program
WO2017047888A1 (en) Support system capable of supporting problem solving and collaboration in bim environment
CN107729487A (en) Topic searching method, topic searching device and electronic terminal
JP2009134673A (en) Gui screen operation sequence verifying apparatus, method, and program
WO2020202992A1 (en) Maintenance method, maintenance server, and program
CN110163580B (en) Creation method of multitask VR training scene, VR training system and storage medium

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant