CN107358562A - For the electric network emergency repairing flattening command system and method under Rainfall Disaster - Google Patents

For the electric network emergency repairing flattening command system and method under Rainfall Disaster Download PDF

Info

Publication number
CN107358562A
CN107358562A CN201710587484.8A CN201710587484A CN107358562A CN 107358562 A CN107358562 A CN 107358562A CN 201710587484 A CN201710587484 A CN 201710587484A CN 107358562 A CN107358562 A CN 107358562A
Authority
CN
China
Prior art keywords
information
emergency
platform
repair
fault
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201710587484.8A
Other languages
Chinese (zh)
Inventor
郑桢
吴清
邢涛
刘春波
韩武奇
吴淑烽
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Haikou Keborui Information Science & Technology Co Ltd
HAINAN STATE GRID Co Ltd
Hainan Power Grid Co Ltd
Original Assignee
Haikou Keborui Information Science & Technology Co Ltd
HAINAN STATE GRID Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Haikou Keborui Information Science & Technology Co Ltd, HAINAN STATE GRID Co Ltd filed Critical Haikou Keborui Information Science & Technology Co Ltd
Priority to CN201710587484.8A priority Critical patent/CN107358562A/en
Publication of CN107358562A publication Critical patent/CN107358562A/en
Pending legal-status Critical Current

Links

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
    • G06Q50/10Services
    • G06Q50/26Government or public services
    • G06Q50/265Personal security, identity or safety
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
    • G06Q50/06Energy or water supply

Landscapes

  • Business, Economics & Management (AREA)
  • Engineering & Computer Science (AREA)
  • Tourism & Hospitality (AREA)
  • Health & Medical Sciences (AREA)
  • Economics (AREA)
  • Theoretical Computer Science (AREA)
  • Physics & Mathematics (AREA)
  • Human Resources & Organizations (AREA)
  • Marketing (AREA)
  • Primary Health Care (AREA)
  • Strategic Management (AREA)
  • General Physics & Mathematics (AREA)
  • General Health & Medical Sciences (AREA)
  • General Business, Economics & Management (AREA)
  • Water Supply & Treatment (AREA)
  • Public Health (AREA)
  • Computer Security & Cryptography (AREA)
  • Development Economics (AREA)
  • Educational Administration (AREA)
  • Alarm Systems (AREA)

Abstract

The invention belongs to electric power network technique field, discloses a kind of electric network emergency repairing flattening command system being used under Rainfall Disaster and method, builds perfect emergency first-aid repair Precaution Tactics automatically according to fault type etc.:The emergency first-aid repair instrument of the decisions such as rational meteorological condition time.By the emergency first-aid repair Precaution Tactics built automatically, intelligent adjustment assigns repairing task to repair personnel, ensures repairing the safe and stable, reliable of work, Effec-tive Function.The practical application scene rushed to repair with reference to electric network emergency under Rainfall Disaster, there is provided obtain the condition of a disaster information, line information and the instrument for rushing to repair place and environment information whenever and wherever possible;The very first time allows emergency first-aid repair instruction to be communicated to specific repair personnel on hand, judges to provide foundation to provide comprehensive commander.Direct interactive between enhancing repair personnel, the passivity of arrangement need to be commanded by reducing everything;Organically combine reality, it is ensured that the reasonability of command deployment, and the ability that repair personnel quickly reaches the spot.

Description

For the electric network emergency repairing flattening command system and method under Rainfall Disaster
Technical field
The invention belongs to electric power network technique field, more particularly to a kind of electric network emergency repairing flattening being used under Rainfall Disaster Command system and method.
Background technology
At present, " flattening " management method is a kind of Novel work management method under current " internet+" pattern, is passed through Using advanced development of Mobile Internet technology, the management for going " proceduring " is realized, reduces management level, shortens instruction flow, lifting Command and management efficiency.Intelligent mobile phone terminal function is growing, waterproof, dust-proof, can store present graphical, voice, word number It is longer according to, continuous working period.Wechat enterprise-level application on intelligent mobile phone terminal accesses mobile service management for enterprise and carried Supplied solid foundation, opened up mobile cooperation new tunnel, solve traditional cell phone can only one-way voice link up, no The more people of energy participate in the pattern that ditch passes through jointly, and passage base has been established for the emergency first-aid repair business development of " flattening " management mode Plinth.
In summary, the problem of prior art is present be:After Rainfall Disaster occurs, all power network repairing staff exist Outdoor field work, it is more that emergency first-aid repair instruction reception and registration process reports level, easily produces and omits and distortion.Electric network emergency always refers to After the repairing instruction waved is passed on, it can not quickly know whether truly to be communicated to specific all repair personnel of a line.In disaster relief and rescue The circuit corrupted information that process is found lacks visualization record, reports instrument, and traditional mode reporting by telephone describes unclear, and report is gone through History is difficult to thumb.Disaster relief and rescue engineering, first-line staff lack related disaster monitoring system Monitoring Data, and inquiry data level is more More, data acquisition is not in time.Disaster relief process, mutual aid unmanageable between numerous teams, difficult coordinate, easily shift responsibility onto others and refer to, it is necessary to wait Center United Dispatching is waved, reduces first-aid repair efficiency.Disaster relief carrying notebook computer is inconvenient to work out of doors, using based on intelligent hand Machine terminal device is more convenient, multipurpose.
The content of the invention
The problem of existing for prior art, the invention provides a kind of electric network emergency repairing being used under Rainfall Disaster is flat Graduation command system and method.
The present invention is achieved in that a kind of electric network emergency repairing flattening command system being used under Rainfall Disaster, institute State and be provided with for the electric network emergency repairing flattening command system under Rainfall Disaster:Emergency commanding platform, put down with emergency command The power transmission line intelligent fault monitoring system of platform connection, lightning location system, transmission line information system, generalized information system, public gas As system, power network microclimate information system;
The power transmission line intelligent fault monitoring system provides the fault location information of repairing circuit to emergency commanding platform;
The lightning location system provides the thunderbolt situation information of line fault point periphery thunder and lightning to emergency commanding platform;
The transmission line information system provides trouble point upper boom tower basic condition and the week of circuit to emergency commanding platform Side landform, geomorphology information;
The generalized information system provides the graphical information of abort situation point and its associated circuitry, geographical seat to emergency commanding platform Cursor position information;
The Public meteorology system to emergency commanding platform provide fault zone currently with follow-up weather information;
The power network microclimate information system to emergency commanding platform provide trouble point circuit pass through transformer station inside and Surrounding enviroment weather information;
The emergency commanding platform system is stored in server, and the server connects fire wall;The fire wall passes through Network connecting radio base station;The wireless base station provides wireless signal to intelligent movable mobile phone end.
Further, the emergency commanding platform is the control and command platform of flattened management, collect fault message and User profile, and pass through applicative notifications repair personnel of the platform on wechat enterprise number, abort situation, fault type, faulty section The information such as domain environment, while the scene feedback of repair personnel is received, and cooperate with peripheral position repair personnel to carry out resource comprehensive association Adjust and arrange.All commanders, reception, all use of deployment information are visible per family on maneuvering platform, and can be between repair personnel mutually Carry out task coordinate.
Further, after user pays close attention to wechat enterprise number application corresponding to emergency commanding platform, as long as mobile phone is online, just it is in The constantly logging status of 24 hours;When the power transmission line intelligent fault monitoring system provides transmission line of electricity to emergency commanding platform Fault warning information:Time of casualty, tripping operation line name, accident are separate, nature of trouble, thunderbolt property, starting shaft tower are numbered, eventually Only shaft tower numbering, accident shaft tower are numbered, and corresponding warning information can be received by becoming on the mobile phone terminal of user, while in information clearly Rush to repair the failure shaft tower numbering of circuit;Platform meeting simultaneously is numbered according to the failure shaft tower received and time of failure information, New query statement is generated to be inquired about to described lightning location system;The thunderbolt object information inquired:Time, latitude, Longitude, electric current, counterattack, acquisition station number, are delivered on the emergency commanding platform by corresponding interface, and user passes through corresponding micro- Letter enterprise number can receive the result of inquiry;
While user is according to the fault warning information of reception:Trip line name, accident shaft tower numbering, generates new inquiry Instruct and inquired about to described transmission line information system, inquire the detail information of failure shaft tower:Turriform, location Shape, landforms, height, date of putting into operation;The information inquired is stored on the emergency commanding platform, and user passes through corresponding wechat Enterprise number receives the result of inquiry;
Meanwhile emergency commanding platform can be according to the fault warning information received:Trip line name, accident shaft tower volume Number, generate new query statement and inquired about to described generalized information system, inquire the detail location coordinate information of failure shaft tower, The coordinate information inquired is stored on the emergency commanding platform, and passes through the emergency commanding platform and wechat map interface Geographical position graphics are formed, user can realize the navigation in geographical position by corresponding wechat enterprise number;
Meanwhile the emergency commanding platform can need to carry out according to the position of fault geographic position name of storage, and user On the date of repairing, generate new query statement and inquired about automatically to described Public meteorology information, accurately inquire locality Weather information, user can quickly be known by corresponding wechat enterprise number;
On the basis of in the external environment condition data needed for all rapid rush-repairs, quickly association prepares, cammander is to pass through Emergency commanding platform is stated to carry out commanding assigning for instruction to the bottom-up employee for having paid close attention to platform and corresponding to wechat enterprise number;
Bottom-up employee will receive commander's command information by wechat enterprise number corresponding to platform:Task place, maintenance participate in Personnel, in place personnel;Meanwhile bottom-up employee is made whether to perform report in place and feedback to commander's instruction, report and feedback Data are sent by wechat enterprise number corresponding to platform to all command reception people, realize that the constantly division of labor of repairing task is coordinated.
Another object of the present invention is to provide a kind of electric network emergency repairing flattening commander system being used under Rainfall Disaster System operation method comprises the following steps:
Step 1, power transmission line intelligent fault monitoring system are found because of line tripping warning information caused by Rainfall Disaster Afterwards, information is sent to the emergency first-aid repair platform of the present invention by data-interface;
Step 2, after emergency first-aid repair platform receives the fault message of power transmission line intelligent fault monitoring system, from information Middle extraction time of failure data, and fault time data are sent to lightning location system;
Step 3, obtained according to fault time data from lightning location system and lightning fault specifically occurs in fault time Overhead line structures information;
Step 4, the overhead line structures information of acquisition is sent to transmission line information system and generalized information system;
Step 5, the detailed attribution information of overhead line structures is got from transmission line information system;
Step 6, by Step 1: the information that step 3 and step 5 are obtained carries out comprehensive associative combination, formation one Detailed line tripping fault related information.
Step 7, the detailed geographical location information of trouble point is got from generalized information system according to step 4 content;
Step 8, after the detailed geographical location information of trouble point is arranged into querying condition, respectively in Public meteorology information Inquired about in system and power network microclimate system;
Step 9, the Query Result of emergency first-aid repair platform obtaining step eight:Position weather information result;
Step 10, the detailed fault correlation that emergency first-aid repair platform combines according to position weather information result with step 6 are believed Breath, forms scientific and rational emergency first-aid repair job placement period planning;
Step 11, when emergency first-aid repair platform is according to the detailed fault correlation information being combined into and emergency first-aid repair job placement Between plan, by emergency first-aid repair Platform Server, link internet, transmit channel by wechat enterprise number, be sent automatically to institute Have on the intelligent movable mobile phone end of repair personnel;Repair personnel is to the fault message received and emergency first-aid repair job placement time It can carry out receiving feedback or advisory feedback, all feedback informations can pass through wechat enterprise number and transmit channel by emergency first-aid repair platform again Receive, store and be forwarded on the intelligent movable mobile phone end with commanding power personnel;Commanding can be in time according to feedback letter Breath, commander's instruction is resend, realize the flattened management operation of commander;Meanwhile all repair personnel can pass through wechat and look forward to Industry transmission channel obtains the every system data accessed on emergency first-aid repair platform, voluntarily checks, utilizes, lifting repairing work effect Rate.
Further, before described emergency commanding platform is built, if each repairing instruction publisher arranges issue and robbed The total time expended required for before repairing instruction is X1;
Specific execution step is as follows:The first step, supervised if user receives power transmission line intelligent failure by SMS The warning information that examining system is sent, and information is manually split, prepare the inquiry that different words is used in different system, It is A to need the consuming time;
Second step, if the text information that the first step is replicated, which is input to, inquires detailed thunderbolt letter in lightning location system Breath is, it is necessary to which it is B to expend the time;
3rd step, if by the first step replicate text information be input in transmission line information system inquire it is detailed by Failure shaft tower information is, it is necessary to which it is C to expend the time;
4th step, if by the first step replicate text information be input in generalized information system inquire it is detailed by failure shaft tower Geographical position coordinates are, it is necessary to which it is D to expend the time;
5th step, if being formed event by failure shaft tower geographical position coordinates information combination wechat map by what the 5th step inquired Barrier point position navigation is, it is necessary to which it is E to expend the time;
6th step, if by the 5th step inquire by failure shaft tower geographical location information and it is expected that emergency repair time is input to public affairs Corresponding weather information is inquired about in weather information altogether, it is necessary to it is F to expend the time, because optimal emergency repair time be decided by the meteorological date because Element is, it is necessary to carry out N wheel traversals;If, it is necessary to the total time X1=A+B+C+D+E+F* expended before each repairing instruction issue N。
Advantages of the present invention and good effect are:The integrated failure notification message of the present invention, Public meteorology information, the micro- gas of power network Image information, the intelligent repairing for carrying out emergency command arrange.According to fault type, the gas of trouble point sending zone is as situation, event Barrier point perimeter circuit tower structure and topography and geomorphology, build perfect emergency first-aid repair Precaution Tactics automatically:Rational meteorological condition The emergency first-aid repair instrument that the precautionary measures, topography and geomorphology required for time, overhead line structures structure determine.It is emergent by what is built automatically Precaution Tactics are rushed to repair, intelligent adjustment assigns repairing task to repair personnel, ensures the safe and stable, reliable, high of repairing work Effect operation.The practical application scene rushed to repair with reference to electric network emergency under Rainfall Disaster, there is provided obtain the condition of a disaster information, line whenever and wherever possible The instrument of road information and repairing place and environment information;The very first time allows emergency first-aid repair instruction to be communicated to specific repair personnel on hand, And it would know that whether instruction passes in place.Line repair personnel scene feedback is received in time, judges to provide to provide comprehensive commander Foundation.Direct interactive between enhancing repair personnel, the passivity of arrangement need to be commanded by reducing everything;Realize position of fault position Put, position of fault climate condition information, faulty line data, repair personnel geographical position combination reality, it is ensured that commander The reasonability of allotment, and the ability that repair personnel quickly reaches the spot.
Brief description of the drawings
Fig. 1 is the electric network emergency repairing flattening command system structure provided in an embodiment of the present invention being used under Rainfall Disaster Schematic diagram;
In figure:1st, emergency commanding platform;2nd, power transmission line intelligent fault monitoring system;3rd, lightning location system;4th, transmit electricity Line information system;5th, generalized information system;6th, Public meteorology system 6;7th, power network microclimate information system;8th, wireless base station;9th, it is mobile Mobile phone end;10th, fire wall;11st, server.
Fig. 2 is the electric network emergency repairing flattening command system operation provided in an embodiment of the present invention being used under Rainfall Disaster Method flow diagram.
Embodiment
In order to further understand the content, features and effects of the present invention, hereby enumerating following examples, and coordinate accompanying drawing Describe in detail as follows.
At present, after Rainfall Disaster occurs, all power networks rush to repair staff's field work out of doors, emergency first-aid repair instruction It is more that reception and registration process reports level, easily produces and omits and distortion., can not be fast after the repairing instruction of electric network emergency commander in chief is passed on Speed knows whether truly to be communicated to specific all repair personnel of a line.Lack in the circuit corrupted information that disaster relief and rescue process is found Visualization record, report instrument, traditional mode reporting by telephone describe it is unclear, report history be difficult to thumb.Disaster relief and rescue engineering, one Informant person lacks related disaster monitoring system Monitoring Data, and inquiry data level is more more, and data acquisition is not in time.The disaster relief Journey, mutual aid unmanageable between numerous teams, it is difficult coordinate, easily shift responsibility onto others, it is necessary to wait command centre's United Dispatching, reduce repairing effect Rate.Disaster relief carrying notebook computer is inconvenient to work out of doors, using based on intelligent mobile phone terminal equipment is more convenient, multipurpose.
The present invention is described in detail below in conjunction with the accompanying drawings.
As shown in figure 1, the electric network emergency repairing flattening commander system provided in an embodiment of the present invention being used under Rainfall Disaster System, is provided with:Emergency commanding platform 1, power transmission line intelligent fault monitoring system 2, the thunder and lightning being connected with emergency commanding platform are fixed Position system 3, transmission line information system 4, generalized information system 5, Public meteorology system 6, power network microclimate information system 7.
The power transmission line intelligent fault monitoring system provides the fault location information of repairing circuit to emergency commanding platform, The lightning location system provides the thunderbolt situation information of line fault point periphery thunder and lightning, the power transmission line to emergency commanding platform Road information system provides the trouble point upper boom tower basic condition and periphery landform, geomorphology information of circuit to emergency commanding platform;
The generalized information system 5 provides the graphical information of abort situation point and its associated circuitry, geographical seat to emergency commanding platform Cursor position information, the Public meteorology system provides fault zone currently with follow-up weather information to emergency commanding platform, described Power network microclimate information system provides trouble point circuit to emergency commanding platform and passes through transformer station inside and surrounding enviroment meteorology Information.
The emergency commanding platform system is stored in server 11, and the server connects fire wall 10;The fire wall Pass through network connecting radio base station 8;The wireless base station 8 provides wireless signal to intelligent movable mobile phone end 9.
The present invention is to rush to repair flattening command system, the integrated failure notification of the present invention for the electric network emergency under Rainfall Disaster Information, Public meteorology information, power network microclimate information, the intelligent repairing for carrying out emergency command arrange.According to fault type, therefore The gas of barrier point sending zone builds perfect emergent rob as situation, trouble point perimeter circuit tower structure and topography and geomorphology automatically Repair Precaution Tactics:The precautionary measures, emergent the robbing of topography and geomorphology decision required for rational meteorological condition time, overhead line structures structure Repair instrument.
By the emergency first-aid repair Precaution Tactics built automatically, intelligent adjustment assigns repairing task to repair personnel, ensures Rush to repair the safe and stable, reliable of work, Effec-tive Function.The practical application scene rushed to repair with reference to electric network emergency under Rainfall Disaster, is carried Supply to obtain the condition of a disaster information, line information and the instrument for rushing to repair place and environment information whenever and wherever possible;The very first time allows emergency first-aid repair Instruction is communicated to specific repair personnel on hand, and would know that whether instruction passes in place.Line repair personnel scene is received in time Feedback, judge to provide foundation to provide comprehensive commander.Direct interactive between enhancing repair personnel, peace need to be commanded by reducing everything The passivity of row;Realize position of fault position, position of fault climate condition information, faulty line data, repair personnel's geography position The combination reality put, it is ensured that the reasonability of command deployment, and the ability that repair personnel quickly reaches the spot.
The structure of the present invention is explained in detail below in conjunction with the accompanying drawings.
As shown in figure 1, the power transmission line intelligent malfunction monitoring being connected including emergency commanding platform 1, with emergency commanding platform 1 System 2, lightning location system 3, transmission line information system 4, generalized information system 5, Public meteorology system 6, power network microclimate information system System 7, the power transmission line intelligent fault monitoring system 2 provide the fault location information of repairing circuit, institute to emergency commanding platform 1 State the thunderbolt situation information that lightning location system 3 provides line fault point periphery thunder and lightning to emergency commanding platform 1, the power transmission line Road information system 4 provides the trouble point upper boom tower basic condition and periphery landform, geomorphology information of circuit to emergency commanding platform 1, The generalized information system 5 provides abort situation point and its graphical information, the geographical coordinate position of associated circuitry to emergency commanding platform 1 Information, the Public meteorology system 6 to emergency commanding platform 1 provide fault zone currently with follow-up weather information, the power network Microclimate information system 7 provides trouble point circuit to emergency commanding platform 1 and passes through transformer station inside and the meteorological letter of surrounding enviroment Breath.The system of emergency commanding platform 1 is stored in server 11, and the server 11 connects fire wall 10;The fire wall 10 Pass through network connecting radio base station 8;The wireless base station 8 provides wireless signal to intelligent movable mobile phone end 9.
The emergency commanding platform 1 is the control and command platform of a flattened management, collects fault message and user's letter Breath, and pass through applicative notifications repair personnel of the platform on wechat enterprise number, abort situation, fault type, fault zone environment Etc. information, while the scene feedback of repair personnel is received, and cooperate with peripheral position repair personnel to carry out resource comprehensive and coordinate to arrange. All commanders, reception, all use of deployment information are visible per family on maneuvering platform, and can carry out task mutually between repair personnel Coordinate.
The present invention relies on wechat enterprise number to apply the versatility of the mobile platform having, the convenience used and can be quick Platform application is extended into repair personnel's intelligent movable mobile phone end 9 inside all power networks.During repairing, cammander is only needed by certainly This dock door on body intelligent movable mobile phone end 9 in wechat enterprise number, repairing information can be sent directly in platform Each participates in personnel's intelligent movable mobile phone end 9 of repairing work.After command information is sent, repair personnel's intelligent movable mobile phone Will all there be prompt message and suggestion voice in end 9, and repair personnel checks that information will be recorded with no, and feeds back to the hair of command information The person of sending and the personnel of all participation activities know jointly.After certain time, the personnel to not checking command information in time, this hair The bright intelligent mobile mobile phone end 9 that will dial repair personnel in the form of phone automatically, repair personnel is reminded to check commander's letter Breath.Before repairing instruction transmission is not read, the indivedual repair personnel consulted can carry out live feedback to instruction and report instruction to send out The person of sending is appropriately modified, it is ensured that commander's direct orders and in time, it is correct.
The present invention realizes the comprehensive association of trouble point information and automatic commander.By power transmission line intelligent fault monitoring system 2 After emergency commanding platform 1 being accessed with lightning location system 3, transmission line information system 4, generalized information system 5.By platform to power transmission line Circuit can carry out automatic 24 hours on-line uninterruptions commander under a situation arises in natural calamities such as heavy rains, work as power transmission line intelligent When the hair existing line of fault monitoring system 2 has tripping fault, power transmission line intelligent fault monitoring system 2 sends fault warning automatically To emergency commanding platform 1, emergency commanding platform 1 receives automatic lighting location when calling the failure to occur after fault message to be believed information Nearby overhead line structures information, position of failure point are geographical for breath, trouble point, and are combined into a detailed accident analysis information, pass through Emergency commanding platform 1 is sent to the intelligent movable mobile phone end 9 of circuit repairing staff.
As shown in Fig. 2 electric network emergency repairing flattening command system operation under Rainfall Disaster provided in an embodiment of the present invention Method comprises the following steps:
S101:After power transmission line intelligent fault monitoring system is found because of line tripping warning information caused by Rainfall Disaster, Information is sent to the emergency first-aid repair platform of the present invention by data-interface.
S102:After emergency first-aid repair platform receives the fault message of power transmission line intelligent fault monitoring system, from information Time of failure data are extracted, and fault time data are sent to lightning location system.
S103:Obtained according to fault time data from lightning location system and lightning fault specifically occurs in fault time Thunderbolt information.
S104:The overhead line structures information of acquisition is sent to transmission line information system and generalized information system.
S105:The detailed attribution information of overhead line structures is got from transmission line information system.
S106:The information that S101, S103 and S105 are obtained carries out comprehensive associative combination, forms a detailed line Road tripping fault related information.
S107:The detailed geographical location information of trouble point is got from generalized information system according to S104 contents, and combines wechat Map forms trouble point navigation.
S108:After the detailed geographical location information of trouble point is arranged into querying condition, respectively in Public meteorology information system Inquired about in system and power network microclimate system.
S109:Emergency first-aid repair platform obtains S108 Query Result:Position weather information result.
S110:The detailed fault correlation information that emergency first-aid repair platform combines according to position weather information result with S106, shape Into scientific and rational emergency first-aid repair job placement period planning.
S111:Finally, emergency first-aid repair platform is according to the detailed fault correlation information being combined into and emergency first-aid repair job placement Period planning, by emergency first-aid repair Platform Server, links internet, transmits channel by wechat enterprise number, is sent automatically to On the intelligent movable mobile phone end of all repair personnel.
S110 acquisition, the data arranged are put into the emergent plateform system and synchronize comprehensive association, can be calculated Go out the relatively reasonable emergency first-aid repair job placement time, and with power transmission line intelligent malfunction monitoring data, overhead line structures data, Fault point geographical position information, failure shaft tower details, emergency repair time point weather information store database server together In.
Before emergency commanding platform of the present invention construction, if each repairing instruction publisher arranges issue repairing The total time expended required for before instruction is X1.
Specific execution step is as follows:The first step, supervised if user receives power transmission line intelligent failure by SMS The warning information that examining system is sent, and information is manually split, prepare the inquiry that different words is used in different system, It is A to need the consuming time;
Second step, if the text information that the first step is replicated, which is input to, inquires detailed thunderbolt letter in lightning location system Breath is, it is necessary to which it is B to expend the time;
3rd step, if by the first step replicate text information be input in transmission line information system inquire it is detailed by Failure shaft tower information is, it is necessary to which it is C to expend the time;
4th step, if by the first step replicate text information be input in generalized information system inquire it is detailed by failure shaft tower Geographical position coordinates are, it is necessary to which it is D to expend the time;
5th step, if being formed event by failure shaft tower geographical position coordinates information combination wechat map by what the 5th step inquired Barrier point position navigation is, it is necessary to which it is E to expend the time;
6th step, if by the 5th step inquire by failure shaft tower geographical location information and it is expected that emergency repair time is input to public affairs Corresponding weather information is inquired about in weather information altogether, it is necessary to it is F to expend the time, because optimal emergency repair time be decided by the meteorological date because Element is, it is necessary to carry out N wheel traversals.Therefore set before each repairing instruction is issued, it is necessary to the total time X1=A+B+C+D+E expended +F*N。
If the computational methods of emergency commanding platform system service of the present invention are parallel processings, under above traditional mode 6 step computings almost handle simultaneously, therefore computational efficiency is at least 6 times manually calculated, realizes that trouble point is believed according to the present invention Comprehensive association and the method commanded automatically are ceased, it is necessary to the total time X2=X1/6 expended before each repairing instruction issue. So the time according to needed for electric network emergency repairing work commander's command content under usual Rainfall Disaster is 1 hour, use If after emergency commanding platform system service of the present invention, all emergency first-aid repair work commander's command contents prepare only to need 10 points Kind, efficiency improves 84%.
In S111, commanding can quickly adjust in time according to feedback information and resend commander's instruction, realize commander Flattened management operation.Meanwhile all repair personnel can pass through wechat enterprise number transmission channel and obtain emergency first-aid repair platform Every system data of upper access, is voluntarily checked, is utilized, lifting repairing operating efficiency.
It is described above to be only the preferred embodiments of the present invention, any formal limitation not is made to the present invention, Every technical spirit according to the present invention belongs to any simple modification made for any of the above embodiments, equivalent variations and modification In the range of technical solution of the present invention.

Claims (5)

1. a kind of electric network emergency repairing flattening command system being used under Rainfall Disaster, it is characterised in that described to be used for heavy rain Electric network emergency repairing flattening command system under disaster is provided with:Emergency commanding platform, be connected with emergency commanding platform it is defeated Electric line intelligent fault monitoring system, lightning location system, transmission line information system, generalized information system, Public meteorology system, electricity Net microclimate information system;
The power transmission line intelligent fault monitoring system provides the fault location information of repairing circuit to emergency commanding platform;
The lightning location system provides the thunderbolt situation information of line fault point periphery thunder and lightning to emergency commanding platform;
The transmission line information system provides the trouble point upper boom tower basic condition and circumferentially of circuit to emergency commanding platform Shape, geomorphology information;
The generalized information system provides graphical information, the geographical coordinate position of abort situation point and its associated circuitry to emergency commanding platform Confidence ceases;
The Public meteorology system to emergency commanding platform provide fault zone currently with follow-up weather information;
The power network microclimate information system provides trouble point circuit to emergency commanding platform and passes through transformer station inside and periphery Environment weather information;
The emergency commanding platform system is stored in server, and the server connects fire wall;The fire wall passes through network Connect wireless base station;The wireless base station provides wireless signal to intelligent movable mobile phone end.
2. the electric network emergency repairing flattening command system being used for as claimed in claim 1 under Rainfall Disaster, it is characterised in that institute Control and command platform of the emergency commanding platform for a flattened management is stated, collects fault message and user profile, and by flat The information such as applicative notifications repair personnel of the platform on wechat enterprise number, abort situation, fault type, fault zone environment, simultaneously The scene feedback of repair personnel is received, and cooperates with peripheral position repair personnel to carry out resource comprehensive and coordinates to arrange;On maneuvering platform All commanders, reception, all use of deployment information are visible per family, and can carry out task coordinate mutually between repair personnel.
3. the electric network emergency repairing flattening command system being used for as claimed in claim 1 under Rainfall Disaster, it is characterised in that use After wechat enterprise number application corresponding to family concern emergency commanding platform, as long as mobile phone is online, just in the constantly login of 24 hours State;When the power transmission line intelligent fault monitoring system provides transmission line malfunction warning information to emergency commanding platform:Thing Therefore time, tripping operation line name, accident are separate, nature of trouble, thunderbolt property, starting shaft tower numbering, terminate shaft tower numbering, accident Shaft tower is numbered, and corresponding warning information can be received by becoming on the mobile phone terminal of user, while the failure of circuit is clearly rushed to repair in information Shaft tower is numbered;Platform can generate new inquiry and refer to according to the failure shaft tower numbering and time of failure information received simultaneously Make to described lightning location system and being inquired about;The thunderbolt object information inquired:Time, latitude, longitude, electric current, counterattack, Acquisition station number, it is delivered to by corresponding interface on the emergency commanding platform, user can be received by corresponding wechat enterprise number To the result of inquiry;
While user is according to the fault warning information of reception:Trip line name, accident shaft tower numbering, generates new query statement Inquired about to described transmission line information system, inquire the detail information of failure shaft tower:Turriform, place landform, Landforms, height, date of putting into operation;The information inquired is stored on the emergency commanding platform, and user is looked forward to by corresponding wechat Industry number receives the result of inquiry;
Meanwhile emergency commanding platform can be according to the fault warning information received:Trip line name, accident shaft tower numbering, raw Cheng Xin query statement is inquired about to described generalized information system, is inquired the detail location coordinate information of failure shaft tower, is inquired Coordinate information be stored on the emergency commanding platform, and pass through the emergency commanding platform and wechat map interface and form ground Location graphic conversion is managed, user can realize the navigation in geographical position by corresponding wechat enterprise number;
Meanwhile the emergency commanding platform can need to be rushed to repair according to the position of fault geographic position name of storage, and user Date, generate new query statement and inquired about automatically to described Public meteorology information, accurately inquire locality meteorology Information, user can quickly be known by corresponding wechat enterprise number;
The external environment condition data needed for all rapid rush-repairs quickly association prepare on the basis of, cammander with by it is described should Anxious maneuvering platform carries out commanding assigning for instruction to the bottom-up employee for having paid close attention to platform and corresponding to wechat enterprise number;
Bottom-up employee will receive commander's command information by wechat enterprise number corresponding to platform:Task place, maintenance participant, Personnel in place;Meanwhile bottom-up employee is made whether to perform report in place and feedback to commander's instruction, report is led to feedback data Cross wechat enterprise number corresponding to platform to send to all command reception people, realize that the constantly division of labor of repairing task is coordinated.
4. a kind of electric network emergency repairing flattening command system operation method being used for as claimed in claim 1 under Rainfall Disaster, Characterized in that, the electric network emergency repairing flattening command system operation method being used under Rainfall Disaster includes following step Suddenly:
Step 1, will after power transmission line intelligent fault monitoring system is found because of line tripping warning information caused by Rainfall Disaster Information is sent to the emergency first-aid repair platform of the present invention by data-interface;
Step 2, after emergency first-aid repair platform receives the fault message of power transmission line intelligent fault monitoring system, carried from information Time of failure data are taken, and fault time data are sent to lightning location system;
Step 3, the line that lightning fault specifically occurs in fault time is obtained from lightning location system according to fault time data Line pole tower information;
Step 4, the overhead line structures information of acquisition is sent to transmission line information system and generalized information system;
Step 5, the detailed attribution information of overhead line structures is got from transmission line information system;
Step 6, by Step 1: the information that step 3 and step 5 are obtained carries out comprehensive associative combination, formation one is in detail Line tripping fault related information;
Step 7, the detailed geographical location information of trouble point is got from generalized information system according to step 4 content;
Step 8, after the detailed geographical location information of trouble point is arranged into querying condition, respectively in Public meteorology information system Inquired about with power network microclimate system;
Step 9, the Query Result of emergency first-aid repair platform obtaining step eight:Position weather information result;
Step 10, the detailed fault correlation information that emergency first-aid repair platform combines according to position weather information result with step 6, shape Into scientific and rational emergency first-aid repair job placement period planning;
Step 11, emergency first-aid repair platform are counted according to the detailed fault correlation information being combined into and emergency first-aid repair job placement time Draw, by emergency first-aid repair Platform Server, link internet, transmit channel by wechat enterprise number, be sent automatically to all rob Repair on the intelligent movable mobile phone end of personnel;Repair personnel can enter to the fault message received and emergency first-aid repair job placement time Row receives feedback or advisory feedback, and all feedback informations can pass through wechat enterprise number transmission channel and be connect by emergency first-aid repair platform again Receive, store and be forwarded on the intelligent movable mobile phone end with commanding power personnel;Commanding can in time according to feedback information, Commander's instruction is resend, realizes the flattened management operation of commander;Meanwhile all repair personnel can pass through wechat enterprise number Transmission channel obtains the every system data accessed on emergency first-aid repair platform, voluntarily checks, utilizes, lifting repairing operating efficiency.
5. the electric network emergency repairing flattening command system operation method being used for as claimed in claim 4 under Rainfall Disaster, it is special Sign is,
Before described emergency commanding platform is built, if each repairing instruction publisher arranges institute before issue repairing instruction The total time for needing to expend is X1;
Specific execution step is as follows:The first step, if user receives power transmission line intelligent malfunction monitoring system by SMS Unite the warning information that sends, and information manually split, prepare different words for the inquiry in different system, it is necessary to The consuming time is A;
Second step, if the text information that the first step is replicated, which is input to, inquires detailed thunderbolt information in lightning location system, It is B to need the consuming time;
3rd step, if by the first step replicate text information be input in transmission line information system inquire it is detailed by failure Shaft tower information is, it is necessary to which it is C to expend the time;
4th step, if the text information that the first step is replicated be input in generalized information system inquire it is detailed geographical by failure shaft tower Position coordinates is, it is necessary to which it is D to expend the time;
5th step, if being formed trouble point by failure shaft tower geographical position coordinates information combination wechat map by what the 5th step inquired Navigate, it is necessary to which it is E to expend the time position;
6th step, if by the 5th step inquire by failure shaft tower geographical location information and it is expected that emergency repair time is input to public gas Corresponding weather information is inquired about in image information, it is necessary to it be F to expend the time, because optimal emergency repair time is decided by meteorological date factor, need Carry out N wheel traversals;If, it is necessary to the total time X1=A+B+C+D+E+F*N expended before each repairing instruction issue.
CN201710587484.8A 2017-07-18 2017-07-18 For the electric network emergency repairing flattening command system and method under Rainfall Disaster Pending CN107358562A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710587484.8A CN107358562A (en) 2017-07-18 2017-07-18 For the electric network emergency repairing flattening command system and method under Rainfall Disaster

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710587484.8A CN107358562A (en) 2017-07-18 2017-07-18 For the electric network emergency repairing flattening command system and method under Rainfall Disaster

Publications (1)

Publication Number Publication Date
CN107358562A true CN107358562A (en) 2017-11-17

Family

ID=60285022

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710587484.8A Pending CN107358562A (en) 2017-07-18 2017-07-18 For the electric network emergency repairing flattening command system and method under Rainfall Disaster

Country Status (1)

Country Link
CN (1) CN107358562A (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108805303A (en) * 2018-06-19 2018-11-13 南方电网科学研究院有限责任公司 A kind of transmission tower emergency first-aid repair method and system
CN109741208A (en) * 2018-12-14 2019-05-10 广州供电局有限公司 Large area blackout emergency first-aid repair scheme determines method and apparatus
CN110543952A (en) * 2019-08-28 2019-12-06 国网山东省电力公司 power grid fault auxiliary decision system combined with ranging information and implementation method thereof
US20220132290A1 (en) * 2020-10-28 2022-04-28 Tg-17, Llc Systems and methods for generating emergency response

Citations (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2008027315A (en) * 2006-07-24 2008-02-07 Hitachi East Japan Solutions Ltd Physical distribution network evaluation support method, physical distribution network evaluation support program and physical distribution network evaluation support apparatus
US20080150736A1 (en) * 2006-12-20 2008-06-26 Hsin-Fa Fang Management system with real-time interaction for enviromental monitoring and method thereof
CN102118021A (en) * 2010-01-05 2011-07-06 华北电力科学研究院有限责任公司 Transmission line three-dimensional panoramic model-based fault processing method and system
CN104655986A (en) * 2015-02-26 2015-05-27 国家电网公司 Method for judging lightning stroke fault point of tripped transmission line
CN104809663A (en) * 2015-05-07 2015-07-29 海南电力技术研究院 Power professional technique service assurance surveillance system and method
CN104931851A (en) * 2015-05-22 2015-09-23 广西电网有限责任公司电力科学研究院 Transmission line lightning fault intelligent analysis platform and analysis method
CN105116292A (en) * 2015-09-09 2015-12-02 广东电网有限责任公司电力科学研究院 Line lightning strike fault point locating method and system
CN105590160A (en) * 2015-10-30 2016-05-18 国网山东省电力公司青岛供电公司 Three-dimensional emergency command method and system on the basis of GIS
CN105894397A (en) * 2016-04-26 2016-08-24 山东智洋电气股份有限公司 Power transmission line management system based on WeChat platform
CN105915441A (en) * 2016-05-20 2016-08-31 国家电网公司 WeChat repair method based on distribution network emergency repair command system
CN105956105A (en) * 2016-05-04 2016-09-21 国网山东省电力公司青岛供电公司 Mobile application method and device, mobile terminal as well as an emergency system

Patent Citations (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2008027315A (en) * 2006-07-24 2008-02-07 Hitachi East Japan Solutions Ltd Physical distribution network evaluation support method, physical distribution network evaluation support program and physical distribution network evaluation support apparatus
US20080150736A1 (en) * 2006-12-20 2008-06-26 Hsin-Fa Fang Management system with real-time interaction for enviromental monitoring and method thereof
CN102118021A (en) * 2010-01-05 2011-07-06 华北电力科学研究院有限责任公司 Transmission line three-dimensional panoramic model-based fault processing method and system
CN104655986A (en) * 2015-02-26 2015-05-27 国家电网公司 Method for judging lightning stroke fault point of tripped transmission line
CN104809663A (en) * 2015-05-07 2015-07-29 海南电力技术研究院 Power professional technique service assurance surveillance system and method
CN104931851A (en) * 2015-05-22 2015-09-23 广西电网有限责任公司电力科学研究院 Transmission line lightning fault intelligent analysis platform and analysis method
CN105116292A (en) * 2015-09-09 2015-12-02 广东电网有限责任公司电力科学研究院 Line lightning strike fault point locating method and system
CN105590160A (en) * 2015-10-30 2016-05-18 国网山东省电力公司青岛供电公司 Three-dimensional emergency command method and system on the basis of GIS
CN105894397A (en) * 2016-04-26 2016-08-24 山东智洋电气股份有限公司 Power transmission line management system based on WeChat platform
CN105956105A (en) * 2016-05-04 2016-09-21 国网山东省电力公司青岛供电公司 Mobile application method and device, mobile terminal as well as an emergency system
CN105915441A (en) * 2016-05-20 2016-08-31 国家电网公司 WeChat repair method based on distribution network emergency repair command system

Non-Patent Citations (6)

* Cited by examiner, † Cited by third party
Title
中国地质环境监测院: "应急通信平台建设", 《地质灾害防治信息化建设理论与技术方法》 *
余尔汶: "基于GIS平台的配电网应急抢修***", 《供用电》 *
孙健: "基于微信公众平台的智能供电服务方式应用研究", 《中国优秀硕士学位论文全文数据库经济与管理科学辑》 *
工会干部新媒体实用手册编写组: "政务微信发展状况", 《工会干部新媒体实用手册》 *
廖伟华: "基于微信公众平台的应急指挥***研究及应用", 《电子测试》 *
陈光伟: "启动应急预案", 《铁路信息***应用技术》 *

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108805303A (en) * 2018-06-19 2018-11-13 南方电网科学研究院有限责任公司 A kind of transmission tower emergency first-aid repair method and system
CN109741208A (en) * 2018-12-14 2019-05-10 广州供电局有限公司 Large area blackout emergency first-aid repair scheme determines method and apparatus
CN109741208B (en) * 2018-12-14 2021-08-10 广东电网有限责任公司广州供电局 Method and device for determining emergency repair scheme of large-area power failure accident
CN110543952A (en) * 2019-08-28 2019-12-06 国网山东省电力公司 power grid fault auxiliary decision system combined with ranging information and implementation method thereof
US20220132290A1 (en) * 2020-10-28 2022-04-28 Tg-17, Llc Systems and methods for generating emergency response
US11653192B2 (en) * 2020-10-28 2023-05-16 Tg-17, Llc Systems and methods for generating emergency response

Similar Documents

Publication Publication Date Title
CN103558827B (en) Mine emergency communication for command and management information system
CN103837796B (en) The transmission line malfunction visualization report method of a kind of sing on web and GIS and system
CN104951585B (en) A kind of typhoon method for early warning and device based on grid equipment
US9164663B1 (en) Monitoring and reporting system for an electric power distribution and/or collection system
CN107292989A (en) High voltage power transmission cruising inspection system based on 3DGIS technologies
CN107358562A (en) For the electric network emergency repairing flattening command system and method under Rainfall Disaster
CN103150914B (en) The visual intelligent traffic weather monitoring of sing on web GIS, pre-warning management system
CN106875114A (en) The SMS platform optimization system and method for distribution repairing maneuvering platform
CN106815647A (en) A kind of high efficiency distribution network failure repairing system and method based on data analysis
CN106056272A (en) Power grid programming, management and controlling method and system based on mobile GIS
CN104835085A (en) Tourism operation supervision and safety emergency management linkage command platform system
CN105160593A (en) Power transmission and transformation equipment multidimensional heterogeneous data fusion method and system facing big data
US20210294826A1 (en) Modeling Analysis Method for Equipment Management Network and Electronic Equipment
CN105023200A (en) Power emergency drilling system and emergency drilling method thereof
CN103064895B (en) Based on the communication resource management system computer generating method of GIS
CN114186834A (en) Smart city system
CN103150598B (en) Processing system and method for sudden failure of power transmission network
CN101902345A (en) Digital city management system
CN101901394A (en) Multilevel digital city supervisory system based on 3S
CN104217384A (en) A nuclear accident emergency processing and auxiliary decision support system
CN108304983A (en) Management platform is repaiied in a kind of oil and gas pipeline inspection acquired based on unmanned plane and network communication technology data
CN110570057A (en) petrochemical enterprise emergency resource management and scheduling system and method
CN104951992B (en) The longitudinal correlating method of electric power based on GIS-meteorology and system
CN112365246A (en) AI + GIS + BIM-based intelligent pipe gallery comprehensive management platform
JP4637729B2 (en) Information processing method, information processing apparatus, and program

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20171117

RJ01 Rejection of invention patent application after publication