CN107338689A - Construction method for rubber wheel rail pivot turnout - Google Patents

Construction method for rubber wheel rail pivot turnout Download PDF

Info

Publication number
CN107338689A
CN107338689A CN201710592901.8A CN201710592901A CN107338689A CN 107338689 A CN107338689 A CN 107338689A CN 201710592901 A CN201710592901 A CN 201710592901A CN 107338689 A CN107338689 A CN 107338689A
Authority
CN
China
Prior art keywords
track switch
pivot
built
nose girder
pour
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201710592901.8A
Other languages
Chinese (zh)
Other versions
CN107338689B (en
Inventor
年胜利
管新权
王兴培
张夏
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Tiesiju Civil Engineering Group Co Ltd CTCE Group
Original Assignee
China Tiesiju Civil Engineering Group Co Ltd CTCE Group
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Tiesiju Civil Engineering Group Co Ltd CTCE Group filed Critical China Tiesiju Civil Engineering Group Co Ltd CTCE Group
Priority to CN201710592901.8A priority Critical patent/CN107338689B/en
Publication of CN107338689A publication Critical patent/CN107338689A/en
Application granted granted Critical
Publication of CN107338689B publication Critical patent/CN107338689B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01BPERMANENT WAY; PERMANENT-WAY TOOLS; MACHINES FOR MAKING RAILWAYS OF ALL KINDS
    • E01B29/00Laying, rebuilding, or taking-up tracks; Tools or machines therefor
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01BPERMANENT WAY; PERMANENT-WAY TOOLS; MACHINES FOR MAKING RAILWAYS OF ALL KINDS
    • E01B29/00Laying, rebuilding, or taking-up tracks; Tools or machines therefor
    • E01B29/005Making of concrete parts of the track in situ

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Machines For Laying And Maintaining Railways (AREA)

Abstract

The invention discloses a construction method of a rubber wheel track pivot turnout, which comprises the steps of firstly lofting a turnout foundation, then binding turnout steel bars, positioning and fixing embedded parts, arranging drain pipes, pouring turnout, installing directional trundles and roller assemblies, positioning and installing pivots of a straight beam and a curved strand guide beam, positioning and installing a tail end beam base, positioning and installing the straight beam, the curved strand guide beam and the tail end beam, and finally installing and connecting a motor and a guide chain. The invention accurately binds and pours the reinforcing steel bars, quickly positions and installs the straight beam, the curved strand guide beam and the tail end beam and connects the motors, and ensures that the constructed pivot turnout has good quality and high stability, thereby ensuring the safe line transfer of the train.

Description

A kind of construction method of rubber tire rail pivot track switch
Technical field
The present invention relates to urban rail transit technology field, specifically a kind of construction side of rubber tire rail pivot track switch Method.
Background technology
Urban track traffic is very popular greatly with convenient, fast, green, handling capacity of passengers, and urban public transport instrument has Subway, light rail, short distance magnetic suspension, single track railway, automatic guide etc..Various countries are all attached great importance to by urban track traffic.With me State's urban track traffic it is growing, and the track traffic as city modern civilization is then its essential part.
Existing rubber tire rail project, using full-automatic unmanned driving's control model, train does not have independent drivers' cab, both ends Glass spacious and well-lighted is arranged to, can be that passenger brings different recreational tourism to experience.Rubber tire Track System is rail transport A kind of form, it employs the tire technology of road traffic.The wheel of train is no longer traditional steel wheel, be the substitute is Rubber wheel, its track walked also are different from traditional steel wheel rail.Rubber tire can reduce traveling noise, and radius of turn is more Small, track laying is flexible.During the system capacity is(It is low)Freight volume, an organic supplement can be done to the key network of communication lines in city.
Rubber tire rail vehicle running part uses electronic rubber tire and directive wheel, the wheel track walking manner with conventional rails traffic It is entirely different.The transportation system is full new transportation mode, and its pivot track switch is its crucial lane change equipment.Pivot track switch is one Kind ensure that train is pacified from wall scroll guided way to the device of wherein one progress guided selection of two intersection guided ways, pivot track switch Turn line entirely, the train for making to run on straight trip circuit and turnout turns mutually line, train is transferred to turnout or from turnout from straight way It is transferred to straight way.So pivot mounting turnout requires high, installation quality directly affects train and passes through speed and comfort of passenger.
The content of the invention
The technical problem to be solved in the present invention is to provide a kind of construction method of rubber tire rail pivot track switch, and it is constructed The pivot mounting turnout quality of construction is good, ensure that the safety of train turns line.
The technical scheme is that:
A kind of construction method of rubber tire rail pivot track switch, has specifically included following steps:
(1), the setting-out of track switch basis:Setting-out goes out track switch center line basis and poured and installation of embedded parts position first, goes out in setting-out Drilling implantation reinforcing bar and fixation on switch point position, in this, as concreting border, while mark on fixed reinforcing bar and mix Solidifying soil pours height;
(2), track switch reinforcing bar colligation:Track switch reinforcing bar colligation is carried out according to the switch point position of surveying and locating;
(3), built-in fitting positioning is fixed and drainpipe is laid:In each mount point position that built-in fitting setting-out goes out, with heightening locating support Built-in fitting height is oriented, measurement review built-in fitting elevation of top after the completion of adjustment, at built-in fitting bottom after meeting to set absolute altitude Drilling implantation reinforcing bar and fixation on portion's concrete, and an entirety is formed on built-in fitting bottom and the reinforcement welding of implantation;Draining Height is poured according to reserved foundation ditch to lay, it is met that the ponding in reserved foundation ditch smoothly flows into sump when pipe is laid;
(4), track switch pours:In step(2)The reinforcing bar surrounding shuttering and casting concrete of colligation enter mould;
(5), direction-caster and roller assembly installation:Direction-caster is installed in the middle part of straight beam and bent stock nose girder, in straight beam and bent stock The anterior installation roller assembly of nose girder;
(6), straight beam, the pivot location and installation of bent stock nose girder and tip beam base stand location installation:In step(4)Pour obtained base Drilling pours into anchoring adhesive to anchor bed bolt on plinth concrete, pivot is installed in straight beam and bent stock nose girder rear portion, first by pivot Round nut at the top of axle is screwed off, and removes upper axis bearing and upper plate of the pivot containing bearing, and pivot is moved into bent stock nose girder end The central shaft of end and pivot passes through the circular hole of bent stock nose girder end, installs upper plate, adjusts on supreme pivot location, lower plate and pivot Screw it is concentric, installation bolt and fixation, then upper axis bearing and the round nut at the top of pivot are connected finally screw spiral shell Bolt and round nut;According to the bolt hole point position coring and anchor bolt of surveying and locating when tip beam pedestal is installed, by end Beam pedestal is erected on anchor bolt, and adjustment base height is fixed after meeting design requirement;
(7), straight beam, the location and installation of bent stock nose girder and tip beam:After the completion of pivotal mounting, by straight beam with determining on bent stock nose girder It is moved to castor and roller assembly on pre-buried iron plate, tip beam is installed and adjusts end depth of beam and ensures tip beam center line Overlapped with center of turnout line, then adjust rail gap of the tip beam respectively between straight beam, bent stock nose girder, be finally welded on tip beam solid In reservation.
(8), motor connects with the installation of guide chain:Motor is arranged on design attitude, motor respectively by guide chain and straight beam, Bent stock nose girder connection, control track switch steering program realize that the straight stock of track switch turns bent stock or bent stock turns straight stock.
Described step(4)In track switch pour to be divided into and pour and pour for the second time for the first time;When pouring for the first time, track switch Except the installation site of reserved foundation ditch and track switch motor does not pour outer other positions one-shot forming in the range of pouring, pour height according to What measurement was laid pours the completion of height control point;After first time, track switch casting concrete intensity reached construction requirement, enter trade Trouble pours for the second time, pours carry out reserved foundation ditch and mounting position of motor concreting for the second time.
Described step(2)In track switch reinforcing bar process of binding, corresponding site reinforcing bar length is adjusted according to on-site actual situations And arrangement of reinforcement quantity, built-in fitting and drainpipe cut-out or bending reinforcing steel bar are run into avoid.
The number of steel bars being implanted into after being drilled on described built-in fitting lower concrete is adjusted according to built-in fitting length.
Advantages of the present invention:
The present invention carries out reinforcing bar colligation and pouring molding exactly, and is rapidly determined straight beam, bent stock nose girder and tip beam Motor is mounted and connected in position, ensure that the pivot track switch quality of construction is good, stability is high, ensures that the safety of train turns Line.
Embodiment
The technical scheme in the embodiment of the present invention will be clearly and completely described below, it is clear that described implementation Example only part of the embodiment of the present invention, rather than whole embodiments.It is common based on the embodiment in the present invention, this area The every other embodiment that technical staff is obtained under the premise of creative work is not made, belong to the model that the present invention protects Enclose.
A kind of construction method of rubber tire rail pivot track switch, has specifically included following steps:
(1), the setting-out of track switch basis:Setting-out goes out track switch center line basis and poured and installation of embedded parts position first, goes out in setting-out Drilling implantation reinforcing bar and fixation on switch point position, in this, as concreting border, while mark on fixed reinforcing bar and mix Solidifying soil pours height;
(2), track switch reinforcing bar colligation:Track switch reinforcing bar colligation is carried out according to the switch point position of surveying and locating;Track switch reinforcing bar process of binding In, corresponding site reinforcing bar length and arrangement of reinforcement quantity are adjusted according to on-site actual situations, runs into built-in fitting and drainpipe cut-out or curved Reinforcing bar is rolled over to avoid;
(3), built-in fitting positioning is fixed and drainpipe is laid:In each mount point position that built-in fitting setting-out goes out, with heightening locating support Built-in fitting height is oriented, measurement review built-in fitting elevation of top after the completion of adjustment, at built-in fitting bottom after meeting to set absolute altitude Drilling implantation reinforcing bar and fixation, the number of steel bars of implantation are adjusted according to built-in fitting length on portion's concrete, and by built-in fitting Bottom and the reinforcement welding of implantation form an entirety;Height is poured according to reserved foundation ditch to lay, make it full when drainpipe is laid Ponding in the reserved foundation ditch of foot can smoothly flow into sump;
(4), track switch pours:In step(2)The reinforcing bar surrounding shuttering and casting concrete of colligation enter mould;Track switch, which pours, is divided into One-time-concreting and pour for the second time;For the first time when pouring, track switch pour in the range of except the installation position of reserved foundation ditch and track switch motor Put and do not pour outer other positions one-shot forming, pour the height control point that pours that height is laid according to measurement and complete;When for the first time After track switch casting concrete intensity reaches construction requirement, carry out track switch and pour for the second time, pour for the second time carry out reserved foundation ditch and Mounting position of motor concreting;
(5), direction-caster and roller assembly installation:Direction-caster is installed in the middle part of straight beam and bent stock nose girder, in straight beam and bent stock The anterior installation roller assembly of nose girder;
(6), straight beam, the pivot location and installation of bent stock nose girder and tip beam base stand location installation:In step(4)Pour obtained base Drilling pours into anchoring adhesive to anchor bed bolt on plinth concrete, pivot is installed in straight beam and bent stock nose girder rear portion, first by pivot Round nut at the top of axle is screwed off, and removes upper axis bearing and upper plate of the pivot containing bearing, and pivot is moved into bent stock nose girder end The central shaft of end and pivot passes through the circular hole of bent stock nose girder end, installs upper plate, adjusts on supreme pivot location, lower plate and pivot Screw it is concentric, installation bolt and fixation, then upper axis bearing and the round nut at the top of pivot are connected finally screw spiral shell Bolt and round nut;According to the bolt hole point position coring and anchor bolt of surveying and locating when tip beam pedestal is installed, by end Beam pedestal is erected on anchor bolt, and adjustment base height is fixed after meeting design requirement;
(7), straight beam, the location and installation of bent stock nose girder and tip beam:After the completion of pivotal mounting, by straight beam with determining on bent stock nose girder It is moved to castor and roller assembly on pre-buried iron plate, tip beam is installed and adjusts end depth of beam and ensures tip beam center line Overlapped with center of turnout line, then adjust rail gap of the tip beam respectively between straight beam, bent stock nose girder, be finally welded on tip beam solid In reservation.
(8), motor connects with the installation of guide chain:Motor is arranged on design attitude, motor respectively by guide chain and straight beam, Bent stock nose girder connection, control track switch steering program realize that the straight stock of track switch turns bent stock or bent stock turns straight stock.
Although an embodiment of the present invention has been shown and described, for the ordinary skill in the art, can be with A variety of changes, modification can be carried out to these embodiments, replace without departing from the principles and spirit of the present invention by understanding And modification, the scope of the present invention is defined by the appended.

Claims (4)

  1. A kind of 1. construction method of rubber tire rail pivot track switch, it is characterised in that:Following steps are specifically included:
    (1), the setting-out of track switch basis:Setting-out goes out track switch center line basis and poured and installation of embedded parts position first, goes out in setting-out Drilling implantation reinforcing bar and fixation on switch point position, in this, as concreting border, while mark on fixed reinforcing bar and mix Solidifying soil pours height;
    (2), track switch reinforcing bar colligation:Track switch reinforcing bar colligation is carried out according to the switch point position of surveying and locating;
    (3), built-in fitting positioning is fixed and drainpipe is laid:In each mount point position that built-in fitting setting-out goes out, with heightening locating support Built-in fitting height is oriented, measurement review built-in fitting elevation of top after the completion of adjustment, at built-in fitting bottom after meeting to set absolute altitude Drilling implantation reinforcing bar and fixation on portion's concrete, and an entirety is formed on built-in fitting bottom and the reinforcement welding of implantation;Draining Height is poured according to reserved foundation ditch to lay, it is met that the ponding in reserved foundation ditch smoothly flows into sump when pipe is laid;
    (4), track switch pours:In step(2)The reinforcing bar surrounding shuttering and casting concrete of colligation enter mould;
    (5), direction-caster and roller assembly installation:Direction-caster is installed in the middle part of straight beam and bent stock nose girder, in straight beam and bent stock The anterior installation roller assembly of nose girder;
    (6), straight beam, the pivot location and installation of bent stock nose girder and tip beam base stand location installation:In step(4)Pour obtained base Drilling pours into anchoring adhesive to anchor bed bolt on plinth concrete, pivot is installed in straight beam and bent stock nose girder rear portion, first by pivot Round nut at the top of axle is screwed off, and removes upper axis bearing and upper plate of the pivot containing bearing, and pivot is moved into bent stock nose girder end The central shaft of end and pivot passes through the circular hole of bent stock nose girder end, installs upper plate, adjusts on supreme pivot location, lower plate and pivot Screw it is concentric, installation bolt and fixation, then upper axis bearing and the round nut at the top of pivot are connected finally screw spiral shell Bolt and round nut;According to the bolt hole point position coring and anchor bolt of surveying and locating when tip beam pedestal is installed, by end Beam pedestal is erected on anchor bolt, and adjustment base height is fixed after meeting design requirement;
    (7), straight beam, the location and installation of bent stock nose girder and tip beam:After the completion of pivotal mounting, by straight beam with determining on bent stock nose girder It is moved to castor and roller assembly on pre-buried iron plate, tip beam is installed and adjusts end depth of beam and ensures tip beam center line Overlapped with center of turnout line, then adjust rail gap of the tip beam respectively between straight beam, bent stock nose girder, be finally welded on tip beam solid In reservation;
    (8), motor connects with the installation of guide chain:Motor is arranged on design attitude, motor passes through guide chain and straight beam, bent stock respectively Nose girder connects, and control track switch steering program realizes that the straight stock of track switch turns bent stock or bent stock turns straight stock.
  2. A kind of 2. construction method of rubber tire rail pivot track switch according to claim 1, it is characterised in that:Described Step(4)In track switch pour to be divided into and pour and pour for the second time for the first time;For the first time when pouring, track switch pour in the range of except pre- Stay the installation site of foundation ditch and track switch motor not pour outer other positions one-shot forming, pour height and poured according to what measurement was laid Complete at height control point;After first time, track switch casting concrete intensity reached construction requirement, carry out track switch and pour for the second time, the Secondary pour carries out reserved foundation ditch and mounting position of motor concreting.
  3. A kind of 3. construction method of rubber tire rail pivot track switch according to claim 1, it is characterised in that:Described Step(2)In track switch reinforcing bar process of binding, corresponding site reinforcing bar length and arrangement of reinforcement quantity are adjusted according to on-site actual situations, is run into Built-in fitting and drainpipe cut-out or bending reinforcing steel bar are to avoid.
  4. A kind of 4. construction method of rubber tire rail pivot track switch according to claim 1, it is characterised in that:Described The number of steel bars being implanted into after being drilled on built-in fitting lower concrete is adjusted according to built-in fitting length.
CN201710592901.8A 2017-07-19 2017-07-19 Construction method for rubber wheel rail pivot turnout Active CN107338689B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710592901.8A CN107338689B (en) 2017-07-19 2017-07-19 Construction method for rubber wheel rail pivot turnout

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710592901.8A CN107338689B (en) 2017-07-19 2017-07-19 Construction method for rubber wheel rail pivot turnout

Publications (2)

Publication Number Publication Date
CN107338689A true CN107338689A (en) 2017-11-10
CN107338689B CN107338689B (en) 2019-01-18

Family

ID=60216035

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710592901.8A Active CN107338689B (en) 2017-07-19 2017-07-19 Construction method for rubber wheel rail pivot turnout

Country Status (1)

Country Link
CN (1) CN107338689B (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112779827A (en) * 2020-12-31 2021-05-11 中车浦镇庞巴迪运输***有限公司 Method and tool for installing rubber wheel rail guide rail

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20030071133A1 (en) * 1993-06-30 2003-04-17 Girouard Gerald D. Numerically controlled cross-tie pre-plating system
JP2012180691A (en) * 2011-03-02 2012-09-20 Keikyu Kensetsu Co Ltd Method and equipment for relocating turnout and track panel
CN105329259A (en) * 2015-12-10 2016-02-17 南车株洲电力机车有限公司 Guiding device and guiding method of rail transit vehicle
CN105350409A (en) * 2015-11-23 2016-02-24 中铁四局集团有限公司 Construction method for urban rail transit long sleeper type steel spring floating slab track bed turnout

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20030071133A1 (en) * 1993-06-30 2003-04-17 Girouard Gerald D. Numerically controlled cross-tie pre-plating system
JP2012180691A (en) * 2011-03-02 2012-09-20 Keikyu Kensetsu Co Ltd Method and equipment for relocating turnout and track panel
CN105350409A (en) * 2015-11-23 2016-02-24 中铁四局集团有限公司 Construction method for urban rail transit long sleeper type steel spring floating slab track bed turnout
CN105329259A (en) * 2015-12-10 2016-02-17 南车株洲电力机车有限公司 Guiding device and guiding method of rail transit vehicle

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
史海鸥,罗燕萍: "广州珠江新城旅客自动输送***(APM)设计特点", 《都市快轨交通》 *
李京增等: "现代有轨电车轨道结构探测", 《现代城市轨道交通》 *

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112779827A (en) * 2020-12-31 2021-05-11 中车浦镇庞巴迪运输***有限公司 Method and tool for installing rubber wheel rail guide rail

Also Published As

Publication number Publication date
CN107338689B (en) 2019-01-18

Similar Documents

Publication Publication Date Title
CN105386778B (en) Tunnel excavation lining construction chassis and tunnel excavation lining construction method
CN101215814B (en) Laying construction method and device for double-block type ballastless track sleeper
CN108374296A (en) The construction method of straddle type monorail rail tracks installation
CN106958186A (en) The construction method of bridge floor body, bridge and bridge
CN103321111A (en) Tramcar track continuous-laying construction method
JP2000064209A (en) Assembling method for fixed track line
CN108687950A (en) A kind of prefabricated trolley of pipe gallery and piping lane method for prefabricating
CN108505445A (en) A kind of overbridge roof beam structure bridge construction method
CN109469094A (en) Super High bottom plate interpolation fashioned iron column construction method and fixed structure
CN202659247U (en) Back templates and combined steel die for tunnel inverted arch construction
CN105525571A (en) Construction method of anti-collision wall
CN107338689A (en) Construction method for rubber wheel rail pivot turnout
CN209907210U (en) Integral pouring template system for T-shaped beam sidewalk board and sound barrier base
WO2011120186A1 (en) Track system for magnetic suspension passenger traffic line
CN107190594B (en) Construction method of rubber wheel rail guide rail
KR102161144B1 (en) Height-adjustable transporter for bridge construction and bridge construction method using it
CN209243470U (en) A kind of connection structure of track girder and shield duct piece
CN110593105A (en) Rotation and translation phase-shifting combined incremental launching type rotation translation system and bridge construction method
CN111235977A (en) Side floating type rail transit guide beam
CN110512921A (en) Overhaul assembling structure, train overhaul platform and its construction method of column
CN202628118U (en) Formwork trolley for long and large box culvert
CN206279450U (en) A kind of urban viaduct precast concrete suspending board anticollision wall device
CN106758886B (en) A kind of method of the existing bridges and culverts structure of novel dismounting
CN109457558A (en) A kind of beam-rail integration medium-and low-speed maglev track girder
CN211285271U (en) Pull-type rotating body translation system combining rotating body and translation phase shifting

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
CP02 Change in the address of a patent holder
CP02 Change in the address of a patent holder

Address after: Wangjiang Road in Baohe District of Hefei city of Anhui Province, No. 96 230023

Patentee after: CHINA TIESIJU CIVIL ENGINEERING GROUP Co.,Ltd.