CN107292524A - Intelligent substation secondary safety measure automatic generation method and device - Google Patents
Intelligent substation secondary safety measure automatic generation method and device Download PDFInfo
- Publication number
- CN107292524A CN107292524A CN201710507347.9A CN201710507347A CN107292524A CN 107292524 A CN107292524 A CN 107292524A CN 201710507347 A CN201710507347 A CN 201710507347A CN 107292524 A CN107292524 A CN 107292524A
- Authority
- CN
- China
- Prior art keywords
- function
- intelligent substation
- loop
- information
- safety measure
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 238000000034 method Methods 0.000 title claims abstract description 17
- 230000000694 effects Effects 0.000 claims abstract description 28
- 238000004458 analytical method Methods 0.000 claims abstract description 16
- 238000013507 mapping Methods 0.000 claims abstract description 12
- 230000003068 static effect Effects 0.000 claims description 20
- 230000003287 optical effect Effects 0.000 claims description 12
- 241001269238 Data Species 0.000 claims description 7
- 230000001681 protective effect Effects 0.000 claims description 7
- 239000013589 supplement Substances 0.000 claims description 4
- 235000013399 edible fruits Nutrition 0.000 claims 1
- 238000012423 maintenance Methods 0.000 abstract description 13
- 238000009941 weaving Methods 0.000 abstract description 3
- 230000009467 reduction Effects 0.000 description 5
- 238000010276 construction Methods 0.000 description 3
- 230000008859 change Effects 0.000 description 2
- 230000001419 dependent effect Effects 0.000 description 2
- 239000013307 optical fiber Substances 0.000 description 2
- 230000009286 beneficial effect Effects 0.000 description 1
- 230000008901 benefit Effects 0.000 description 1
- 238000004364 calculation method Methods 0.000 description 1
- 238000004891 communication Methods 0.000 description 1
- 230000007547 defect Effects 0.000 description 1
- 238000013461 design Methods 0.000 description 1
- 230000005611 electricity Effects 0.000 description 1
- 230000008030 elimination Effects 0.000 description 1
- 238000003379 elimination reaction Methods 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
- 230000002708 enhancing effect Effects 0.000 description 1
- 239000000835 fiber Substances 0.000 description 1
- 230000005484 gravity Effects 0.000 description 1
- 238000007689 inspection Methods 0.000 description 1
- 230000010354 integration Effects 0.000 description 1
- 238000002955 isolation Methods 0.000 description 1
- 230000000670 limiting effect Effects 0.000 description 1
- 238000012986 modification Methods 0.000 description 1
- 230000004048 modification Effects 0.000 description 1
- 238000002360 preparation method Methods 0.000 description 1
- 238000012545 processing Methods 0.000 description 1
- 230000002829 reductive effect Effects 0.000 description 1
- 230000008521 reorganization Effects 0.000 description 1
- 230000008439 repair process Effects 0.000 description 1
- 238000012795 verification Methods 0.000 description 1
- 239000011800 void material Substances 0.000 description 1
- 230000003313 weakening effect Effects 0.000 description 1
Classifications
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q10/00—Administration; Management
- G06Q10/06—Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
- G06Q10/067—Enterprise or organisation modelling
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q10/00—Administration; Management
- G06Q10/06—Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
- G06Q10/063—Operations research, analysis or management
- G06Q10/0635—Risk analysis of enterprise or organisation activities
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q50/00—Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
- G06Q50/06—Energy or water supply
Landscapes
- Business, Economics & Management (AREA)
- Human Resources & Organizations (AREA)
- Engineering & Computer Science (AREA)
- Economics (AREA)
- Strategic Management (AREA)
- Entrepreneurship & Innovation (AREA)
- Theoretical Computer Science (AREA)
- Physics & Mathematics (AREA)
- Marketing (AREA)
- General Physics & Mathematics (AREA)
- General Business, Economics & Management (AREA)
- Tourism & Hospitality (AREA)
- Game Theory and Decision Science (AREA)
- Development Economics (AREA)
- Educational Administration (AREA)
- Health & Medical Sciences (AREA)
- Operations Research (AREA)
- Quality & Reliability (AREA)
- Water Supply & Treatment (AREA)
- Primary Health Care (AREA)
- Public Health (AREA)
- General Health & Medical Sciences (AREA)
- Management, Administration, Business Operations System, And Electronic Commerce (AREA)
Abstract
The problem of for existing hand weaving, the accuracy and low efficiency of the secondary safety measure ticket of check, the present invention provides a kind of intelligent substation secondary safety measure automatic generation method and device, belongs to intelligent substation secondary maintenance field.The present invention includes:According to intelligent substation, the step of setting up electrical secondary system model;Electrical secondary system model includes physical layer model, function layer model and logical layer model;According to the loop-type of intelligent substation, function layer model is matched with physical layer model, function layer model with the data between logical layer model, corresponding mapping relations step is generated;The step of substation information and facility information generation safety measure selected according to user;According to the electrical secondary system model of foundation, function and functional loop analysis to the safety measure of generation, the step of obtaining function effect result;According to the function effect result of acquisition, with reference to physical layer model and logical layer model, corresponding secondary safety measure is automatically generated.
Description
Technical field
The present invention relates to a kind of safety measure automatic generation method and device, more particularly to a kind of intelligent substation secondary peace
Full measure automatic generation method and device.
Background technology
Intelligent substation is used uniformly IEC61850 modelings and communicated, due to its technical system numerous and complicated, Form of Technique
It is totally different from normal station.With intelligent substation Large scale construction put into operation and related capital construction ability quick enhancing, at this stage
In terms of intelligent substation center of gravity is progressively transferred to O&M to be probed into by more ripe planning construction by each net, provincial company.Greatly
Amount intelligent substation gradually steps into the O&M stage, and this requires that the technological means of O&M must be simple enough, to reduce O&M work
Dependence of the operation maintenance personnel to equipment vendors in work, while requirement of the reduction to operation maintenance personnel technical capability;In addition, intelligent substation
Technical advantage need be fully utilized, during the operational efficiency and O&M to improve intelligent substation electricity net safety stable transport
Water-filling is put down.
Secondary maintenance safety measure is existing as the defect elimination after intelligent substation puts into operation, maintenance, upgrading and reorganization and expansion etc. is tackled
The technical guarantee of field work, to ensuring that the safety of the equipment of intelligent substation first and second and the stable operation of power network have important meaning
Justice.Pressing plate and loop are the primary operational objects in secondary maintenance safety measure, and using fiber optic communication and based on IEC
In the secondary system of intelligent substation of 61850 information modelings, " hardwire " visible in conventional substation becomes " optical fiber ",
" real terminal " becomes " empty terminal ", and " hard pressing plate " becomes " soft pressing plate ", and introduces the concept of " maintenance pressing plate " so that two
The association of minor loop and pressing plate is no longer directly perceived.More crucially all kinds of " soft pressing plates " and " maintenance pressing plate " between device interoperate
The influence of relation is also complicated more than normal station, these new changes to be engaged in intelligent substation secondary maintenance safety measure establishment,
The staff of execution brings very big difficulty.
At the scene, it is necessary to which secondary maintainer combines the design drawing of maintenance scene and concrete intelligence transformer station in real work
The secondary safety measure of paper hand woven.Because live secondary maintainer's technical merit is uneven and the inspection of intelligent substation O&M
Being continuously increased for workload is repaiied, complete hand weaving, the accuracy of the secondary safety measure ticket of check and efficiency can not be met
Real work needs, or even causes some security incidents, so how to ensure that intelligent substation secondary maintenance peace arranges the complete of ticket
Whole property and correctness, effectively mitigate field personnel's workload, and modular working human users reduce accident rate, shortened
The repair time is powered off, effective support is provided for intelligent substation maintenance work, it has also become be badly in need of in intelligent substation maintenance work
The problem of solution.
The content of the invention
The problem of for existing hand weaving, the accuracy and low efficiency of the secondary safety measure ticket of check, the present invention is provided
A kind of intelligent substation secondary safety measure automatic generation method and device.
The intelligent substation secondary safety measure automatic generation method and device of the present invention, methods described includes following step
Suddenly:
According to intelligent substation, the step of setting up electrical secondary system model;
The electrical secondary system model includes physical layer model, function layer model and logical layer model;
Physical layer model is matched somebody with somebody including IED, interchanger, light, the physical port and physical loop of intelligent substation;
Function layer model includes function group, function and the functional loop of intelligent substation;
Logical layer model includes the soft pressing plate, empty terminal and empty loop of intelligent substation;
According to the loop-type of intelligent substation, by function layer model and physical layer model, function layer model and logical layer
Data between model are matched, and generate corresponding mapping relations step;
The step of substation information and facility information generation safety measure selected according to user;
According to the electrical secondary system model of foundation, function and functional loop analysis to the safety measure of generation obtain function
The step of influenceing result;
According to the function effect result of acquisition, with reference to physical layer model and logical layer model, automatically generate corresponding secondary
Safety measure.
Preferably, it is described according to intelligent substation, electrical secondary system model step is set up, including:
By analyzing between the functional configuration of secondary system of intelligent substation protective relaying device and the device of electrical secondary system
Functional loop, constructing function layer model;
Physical layer model is set up by the optical cable inventory and SCD file of intelligent substation;
Logical layer model is set up by the optical cable inventory and SCD file of intelligent substation.
Preferably, according to the electrical secondary system model of foundation, function and functional loop analysis to the safety measure of generation,
The step of obtaining function effect result, including:
According to the static data of electrical secondary system model, obtain related to the function and functional loop of the safety measure to generation
Physical loop and the step of empty loop;
Electrical secondary system model real-time device status information is generated according to online equipment state is obtained in real time, or has been stored
Status information the step of obtain electrical secondary system model real-time device status information,
It is alarm according to the equipment of real-time report, functional status information and switch status information acquisition electrical secondary system model
The step of information;
According to the information of acquisition, the functional loop of the safety measure of generation is calculated, function effect result is obtained
Step.
Preferably, the static data is obtained according to the SCD file of intelligent substation, ICD files, configuration template
, including real equipment information, equipment link information, the function letter of the whole station after adjustment are supplemented intelligent substation SCD file
Breath, functional loop, physical loop, physical port, empty loop, empty terminal, all static datas of exchanger information;
Real-time device status information includes the real-time status of all kinds of pressing plates of intelligent substation;
Alarm category information includes the equipment and functional status information, warning information and switch status information of real-time report.
Preferably, the step of substation information selected according to user and facility information generation safety measure, bag
Include:
According to voltage class, the mode of connection, interval type, device type information, the function that selected device is related to is obtained
And functional loop, and by function and functional loop, the step of obtaining the object for needing to isolate;
According to the isolated subject of acquisition, with reference to electrical secondary system model, the model related to the isolated subject, generation peace are obtained
The step of full measure.
The present invention also provides a kind of intelligent substation secondary safety measure automatic creation system, and the system includes following mould
Block:
According to intelligent substation, the module of electrical secondary system model is set up;
The electrical secondary system model includes physical layer model, function layer model and logical layer model;
Physical layer model is matched somebody with somebody including IED, interchanger, light, the physical port and physical loop of intelligent substation;
Function layer model includes function group, function and the functional loop of intelligent substation;
Logical layer model includes the soft pressing plate, empty terminal and empty loop of intelligent substation;
According to the loop-type of intelligent substation, by function layer model and physical layer model, function layer model and logical layer
Data between model are matched, and generate the module of corresponding mapping relations;
The substation information and facility information selected according to user generates the module of safety measure;
According to the electrical secondary system model of foundation, function and functional loop analysis to the safety measure of generation obtain function
Influence the module of result and influence degree;
According to the function effect result and influence degree of acquisition, with reference to physical layer model and logical layer model, automatically generate
The module of corresponding secondary safety measure.
Preferably, it is described according to intelligent substation, electrical secondary system model module is set up, including:
By analyzing between the functional configuration of secondary system of intelligent substation protective relaying device and the device of electrical secondary system
Functional loop, constructing function layer model;
Physical layer model is set up by the optical cable inventory and SCD file of intelligent substation;
Logical layer model is set up by the optical cable inventory and SCD file of intelligent substation.
Preferably, according to the electrical secondary system model of foundation, function and functional loop analysis to the safety measure of generation,
The module of function effect result is obtained, including:
According to the static data of electrical secondary system model, obtain related to the function and functional loop of the safety measure to generation
Physical loop and empty loop module;
Electrical secondary system model real-time device status information is generated according to online equipment state is obtained in real time, or has been stored
Status information obtain the module of electrical secondary system model real-time device status information,
It is alarm according to the equipment of real-time report, functional status information and switch status information acquisition electrical secondary system model
The module of information;
According to the information of acquisition, the functional loop of the safety measure of generation is calculated, function effect result is obtained
Module.
Preferably, the static data is obtained according to the SCD file of intelligent substation, ICD files, configuration template
, including real equipment information, equipment link information, the function letter of the whole station after adjustment are supplemented intelligent substation SCD file
Breath, functional loop, physical loop, physical port, empty loop, empty terminal, all static datas of exchanger information;
Real-time device status information includes the real-time status of all kinds of pressing plates of intelligent substation;
Alarm category information includes the equipment and functional status information, warning information and switch status information of real-time report.
Preferably, the substation information selected according to user and facility information generate the module of safety measure, bag
Include:
According to voltage class, the mode of connection, interval type, device type information, the function that selected device is related to is obtained
And functional loop, and by function and functional loop, obtain the module for the object for needing to isolate;
According to the isolated subject of acquisition, with reference to electrical secondary system model, the model related to the isolated subject, generation peace are obtained
The module of full measure.
Above-mentioned technical characteristic can in any suitable manner be combined or substituted by equivalent technical characteristic, as long as can reach
To the purpose of the present invention.
The beneficial effects of the present invention are substation information and the facility information generation that the present invention can be selected according to user
Safety measure, obtains the function effect result of the safety measure of generation, automatically generates secondary safety according to function effect result and arrange
Apply, reduce artificial computation complexity, reduce certain error probability.
Brief description of the drawings
Fig. 1 is the schematic flow sheet of the intelligent substation secondary safety measure automatic generation method of the present invention.
Embodiment
Below in conjunction with the accompanying drawing in the embodiment of the present invention, the technical scheme in the embodiment of the present invention is carried out clear, complete
Site preparation is described, it is clear that described embodiment is only a part of embodiment of the invention, rather than whole embodiments.It is based on
Embodiment in the present invention, those of ordinary skill in the art obtained on the premise of creative work is not made it is all its
His embodiment, belongs to the scope of protection of the invention.
It should be noted that in the case where not conflicting, the embodiment in the present invention and the feature in embodiment can phases
Mutually combination.
The invention will be further described with specific embodiment below in conjunction with the accompanying drawings, but not as limiting to the invention.
As shown in figure 1, the intelligent substation secondary safety measure automatic generation method of present embodiment, including following step
Suddenly:
According to intelligent substation, the step of setting up electrical secondary system model;
The electrical secondary system model includes physical layer model, function layer model and logical layer model;
Physical layer model is matched somebody with somebody including IED, interchanger, light, the physical port and physical loop of intelligent substation;
Function layer model includes function group, function and the functional loop of intelligent substation;
Logical layer model includes the soft pressing plate, empty terminal and empty loop of intelligent substation;
According to the loop-type of intelligent substation, by function layer model and physical layer model, function layer model and logical layer
Data between model are matched, and generate corresponding mapping relations step:
Determined by parsing SCD file the real equipment information of whole station, equipment link information, function information, functional loop,
Physical loop, physical port, empty loop, empty port, exchanger information etc., this type of information is comprising all from SCD, ICD, configuration mould
Plate etc. collects obtained all static datas.The function or type specification of various information are stored by sqlite databases
And invoking upon mapping;
Using protecting corresponding control word, functional loop to carry out defencive function logical deduction by reasoning calculating, service work is determined
Isolation range.By calling the empty loop in database and empty terminal, functional loop and function point, soft pressing plate and function point, void
Loop is corresponding with the logical relation of functional loop, realizes the soft pressing plate, empty terminal and empty loop and function layer function of logical layer
Logical mappings between the defencive function of group, function and functional loop, and by being protected to the logic corresponding relation called
The deduction that function is realized determines the correctness called, if being unsatisfactory for requiring, needs to be matched again, finally thereby determines that each
The safety measure of class service work;
By calling the physical loop in database and functional loop, physical loop and physical port, equipment and physics end
The mutual corresponding relation of the various information of mouth, realizes function layer function group, function and functional loop and the IED of physical layer, hands over
Change planes, light with etc. correspondence mappings between equipment, and the physical port of device, physical loop, thereby determine that defencive function every
From realize it needs to be determined that equipment, physical port and physical loop, and finally determine every safety measure realize needed for it is specific
Device type and mode of operation.
By two above mapping relations finally determine the safety measure of every service work it is regular with specific device type,
Mapping between mode of operation, realizes the generation of safety measure;
The step of substation information and facility information generation safety measure selected according to user;
According to the electrical secondary system model of foundation, function and functional loop analysis to the safety measure of generation obtain function
The step of influenceing result;
According to the function effect result of acquisition, with reference to physical layer model and logical layer model, automatically generate corresponding secondary
Safety measure.
It is described that electrical secondary system model step is set up according to intelligent substation, including:
By analyzing between the functional configuration of secondary system of intelligent substation protective relaying device and the device of electrical secondary system
Functional loop, constructing function layer model;
Physical layer model is set up by the optical cable inventory and SCD file of intelligent substation;
Logical layer model is set up by the optical cable inventory and SCD file of intelligent substation.
The electrical secondary system model that present embodiment is set up, analysis is provided for the function and functional loop of the safety measure of generation
Function, the substation information selected according to user and facility information generation safety measure, obtain the function of the safety measure of generation
Result is influenceed, secondary safety measure is automatically generated according to function effect result, artificial computation complexity is reduced, reduction is certain to go out
Wrong probability.
According to the electrical secondary system model of foundation, function and functional loop analysis to the safety measure of generation obtain function
The step of influenceing result, including:
According to the static data of electrical secondary system model, obtain related to the function and functional loop of the safety measure to generation
Physical loop and the step of empty loop;
Electrical secondary system model real-time device status information is generated according to online equipment state is obtained in real time, or has been stored
Status information the step of obtain electrical secondary system model real-time device status information,
It is alarm according to the equipment of real-time report, functional status information and switch status information acquisition electrical secondary system model
The step of information;
This step is the safety measure of generation to be previewed and perform function, and safety measure is loaded, and obtains pressure
Static models data, real-time device status information and the alarm category information of plate;
According to the information of acquisition, the functional loop of the safety measure of generation is calculated, function effect result is obtained
Step;
This step is to carry out integration processing to obtaining information, obtains functional loop description, starts function and expiry feature,
According to existing state computation formula, verification rule, functional loop state value and functional loop last time formula meter
The end value of calculation, last computation timestamp, obtain specific function effect result.
How present embodiment obtains function effect result if show in particular, function effect is obtained by function effect analysis
As a result it is divided into normal function, disabler or function reduction, failure and the function of weakening are isolated and continued along functional loop
Calculate analysis and search other functions, until finding normal function, and pointing out to all failures and reduction.In order to isolate
The function and functional loop of all failures and reduction need to calculate the corresponding physical layer logic layer data of analytic function layer, finally
Safety measure is realized by the operation of physical layer or logical layer.Such as pulling out optical fiber, disconnect pressing plate.It is as shown below, displaying
Be stoppage in transit line protective devices.
The static data is obtained according to the SCD file of intelligent substation, ICD files, configuration template, including to intelligence
The real equipment information of whole station that can be after the supplement adjustment of transformer station SCD file, equipment link information, function information, functional loop,
Physical loop, physical port, empty loop, empty terminal, all static datas of exchanger information;
Have recorded simultaneously in the category information empty loop and empty terminal, physical loop and physical port, functional loop and function,
Equipment and function, functional loop and empty loop, physical loop and functional loop, physical loop and physical port, equipment and physics
The mutual corresponding relation of the various information of port.
Real-time device status information includes the real-time status of all kinds of pressing plates of intelligent substation, and such state is by single state
Module is provided or service is provided, is typically generated or dependent on stored export by obtaining online equipment state in real time
Status information is obtained;
Alarm category information includes the equipment and functional status information, warning information and switch status information of real-time report,
This type of information is generally collecting for the information of dynamic change in running, and associates with equipment not close information.
The step of substation information selected according to user and facility information generation safety measure, including:
According to voltage class, the mode of connection, interval type, device type information, the function that selected device is related to is obtained
And functional loop, and by function and functional loop, the step of obtaining the object for needing to isolate;
According to the isolated subject of acquisition, with reference to electrical secondary system model, the model related to the isolated subject, generation peace are obtained
The step of full measure.
Present embodiment gives a kind of intelligent substation secondary safety measure automatic creation system, including following mould
Block:
According to intelligent substation, the module of electrical secondary system model is set up;
The electrical secondary system model includes physical layer model, function layer model and logical layer model;
Physical layer model is matched somebody with somebody including IED, interchanger, light, the physical port and physical loop of intelligent substation;
Function layer model includes function group, function and the functional loop of intelligent substation;
Logical layer model includes the soft pressing plate, empty terminal and empty loop of intelligent substation;
According to the loop-type of intelligent substation, by function layer model and physical layer model, function layer model and logical layer
Data between model are matched, and generate the module of corresponding mapping relations;
The substation information and facility information selected according to user generates the module of safety measure;
According to the electrical secondary system model of foundation, function and functional loop analysis to the safety measure of generation obtain function
Influence the module of result and influence degree;
According to the function effect result and influence degree of acquisition, with reference to physical layer model and logical layer model, automatically generate
The module of corresponding secondary safety measure.
It is described according to intelligent substation in preferred embodiment, electrical secondary system model module is set up, including:
By analyzing between the functional configuration of secondary system of intelligent substation protective relaying device and the device of electrical secondary system
Functional loop, constructing function layer model;
Physical layer model is set up by the optical cable inventory and SCD file of intelligent substation;
Logical layer is set up by the optical cable inventory and SCD file of intelligent substation.
In preferred embodiment, according to the electrical secondary system model of foundation, to the function and functional loop of the safety measure of generation
Analysis, obtains the module of function effect result, including:
According to the static data of electrical secondary system model, obtain related to the function and functional loop of the safety measure to generation
Physical loop and empty loop module;
According to obtaining online equipment state generation in real time or obtain two dependent on stored export status information
Subsystem model real-time device status information module,
It is alarm according to the equipment of real-time report, functional status information and switch status information acquisition electrical secondary system model
Information module;
According to the information of acquisition, the functional loop of the safety measure of generation is calculated, function effect result is obtained
Module.
In preferred embodiment, the static data is obtained according to the SCD file of intelligent substation, ICD files, configuration template
Arrive, including supplement intelligent substation SCD file real equipment information, equipment link information, the function of the whole station after adjustment
Information, functional loop, physical loop, physical port, empty loop, empty terminal, all static datas of exchanger information;
Real-time device status information includes the real-time status of all kinds of pressing plates of intelligent substation;
Alarm category information includes the equipment and functional status information, warning information and switch status information of real-time report.
In preferred embodiment, the substation information selected according to user and facility information generate the mould of safety measure
Block, including:
According to voltage class, the mode of connection, interval type, device type information, the function that selected device is related to is obtained
And functional loop, and by function and functional loop, obtain the module for the object for needing to isolate;
According to the isolated subject of acquisition, with reference to electrical secondary system model, the model related to the isolated subject, generation peace are obtained
The module of full measure.
Although describing the present invention herein with reference to specific embodiment, it should be understood that, these realities
Apply the example that example is only principles and applications.It should therefore be understood that can be carried out to exemplary embodiment
Many modifications, and can be designed that other arrangements, the spirit of the invention limited without departing from appended claims
And scope.It should be understood that can be by way of different from described by original claim come with reference to different appurtenances
Profit is required and feature specifically described herein.It will also be appreciated that the feature with reference to described by separate embodiments can be used
In other described embodiments.
Claims (10)
1. a kind of intelligent substation secondary safety measure automatic generation method, it is characterised in that methods described comprises the following steps:
According to intelligent substation, the step of setting up electrical secondary system model;
The electrical secondary system model includes physical layer model, function layer model and logical layer model;
Physical layer model is matched somebody with somebody including IED, interchanger, light, the physical port and physical loop of intelligent substation;
Function layer model includes function group, function and the functional loop of intelligent substation;
Logical layer model includes the soft pressing plate, empty terminal and empty loop of intelligent substation;
According to the loop-type of intelligent substation, by function layer model and physical layer model, function layer model and logical layer model
Between data matched, generate corresponding mapping relations step;
The step of substation information and facility information generation safety measure selected according to user;
According to the electrical secondary system model of foundation, function and functional loop analysis to the safety measure of generation obtain function effect
As a result the step of;
According to the function effect result of acquisition, with reference to physical layer model and logical layer model, corresponding secondary safety is automatically generated
Measure.
2. a kind of intelligent substation secondary safety measure automatic generation method according to claim 1, it is characterised in that institute
State according to intelligent substation, set up electrical secondary system model step, including:
By analyzing the work(between the functional configuration of secondary system of intelligent substation protective relaying device and the device of electrical secondary system
Can loop, constructing function layer model;
Physical layer model is set up by the optical cable inventory and SCD file of intelligent substation;
Logical layer model is set up by the optical cable inventory and SCD file of intelligent substation.
3. a kind of intelligent substation secondary safety measure automatic generation method according to claim 1 or 2, its feature exists
According to the electrical secondary system of foundation, function and functional loop analysis to the safety measure of generation obtain function effect result
Step, including:
According to the static data of electrical secondary system model, the thing related to the function and functional loop of the safety measure to generation is obtained
The step of managing loop and empty loop;
Electrical secondary system model real-time device status information, or the shape stored are generated according to online equipment state is obtained in real time
The step of state information obtains electrical secondary system model real-time device status information,
It is warning information according to the equipment of real-time report, functional status information and switch status information acquisition electrical secondary system model
The step of;
According to the information of acquisition, the functional loop of the safety measure of generation is calculated, the step of obtaining function effect result.
4. a kind of intelligent substation secondary safety measure automatic generation method according to claim 3, it is characterised in that institute
Stating static data is obtained according to the SCD file of intelligent substation, ICD files, configuration template, including to intelligent substation
The real equipment information of whole station after SCD file supplement adjustment, equipment link information, function information, functional loop, physics are returned
Road, physical port, empty loop, empty terminal, all static datas of exchanger information;
Real-time device status information includes the real-time status of all kinds of pressing plates of intelligent substation;
Alarm category information includes the equipment and functional status information, warning information and switch status information of real-time report.
5. a kind of intelligent substation secondary safety measure automatic generation method according to claim 3, it is characterised in that institute
The step of stating the substation information selected according to user and facility information generation safety measure, including:
According to voltage class, the mode of connection, interval type, device type information, function and work(that selected device is related to are obtained
Energy loop, and by function and functional loop, the step of obtaining the object for needing to isolate;
According to the isolated subject of acquisition, with reference to electrical secondary system model, the model related to the isolated subject is obtained, generation safety is arranged
The step of applying.
6. a kind of intelligent substation secondary safety measure automatic creation system, it is characterised in that the system includes following module:
According to intelligent substation, the module of electrical secondary system model is set up;
The electrical secondary system model includes physical layer model, function layer model and logical layer model;
Physical layer model is matched somebody with somebody including IED, interchanger, light, the physical port and physical loop of intelligent substation;
Function layer model includes function group, function and the functional loop of intelligent substation;
Logical layer model includes the soft pressing plate, empty terminal and empty loop of intelligent substation;
According to the loop-type of intelligent substation, by function layer model and physical layer model, function layer model and logical layer model
Between data matched, generate the module of corresponding mapping relations;
The substation information and facility information selected according to user generates the module of safety measure;
According to the electrical secondary system model of foundation, function and functional loop analysis to the safety measure of generation obtain function effect
As a result with the module of influence degree;
According to the function effect result and influence degree of acquisition, with reference to physical layer model and logical layer model, automatically generate corresponding
Secondary safety measure module.
7. a kind of intelligent substation secondary safety measure automatic creation system according to claim 6, it is characterised in that institute
State according to intelligent substation, set up electrical secondary system model module, including:
By analyzing the work(between the functional configuration of secondary system of intelligent substation protective relaying device and the device of electrical secondary system
Can loop, constructing function layer model;
Physical layer model is set up by the optical cable inventory and SCD file of intelligent substation;
Logical layer is set up by the optical cable inventory and SCD file of intelligent substation.
8. a kind of intelligent substation secondary safety measure automatic creation system according to claim 6 or 7, its feature exists
According to the electrical secondary system model of foundation, function and functional loop analysis to the safety measure of generation obtain function effect knot
The module of fruit, including:
According to the static data of electrical secondary system model, the thing related to the function and functional loop of the safety measure to generation is obtained
Manage the module in loop and empty loop;
Electrical secondary system model real-time device status information, or the shape stored are generated according to online equipment state is obtained in real time
State information obtains the module of electrical secondary system model real-time device status information,
It is warning information according to the equipment of real-time report, functional status information and switch status information acquisition electrical secondary system model
Module;
According to the information of acquisition, the functional loop of the safety measure of generation is calculated, the module of function effect result is obtained.
9. a kind of intelligent substation secondary safety measure automatic creation system according to claim 8, it is characterised in that institute
Stating static data is obtained according to the SCD file of intelligent substation, ICD files, configuration template, including to intelligent substation
The real equipment information of whole station after SCD file supplement adjustment, equipment link information, function information, functional loop, physics are returned
Road, physical port, empty loop, empty terminal, all static datas of exchanger information;
Real-time device status information includes the real-time status of all kinds of pressing plates of intelligent substation;
Alarm category information includes the equipment and functional status information, warning information and switch status information of real-time report.
10. a kind of intelligent substation secondary safety measure automatic creation system according to claim 8, it is characterised in that
The substation information selected according to user and facility information generate the module of safety measure, including:
According to voltage class, the mode of connection, interval type, device type information, function and work(that selected device is related to are obtained
Energy loop, and pass through function and functional loop, obtain the module for the object for needing to isolate;
According to the isolated subject of acquisition, with reference to electrical secondary system model, the model related to the isolated subject is obtained, generation safety is arranged
The module applied.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710507347.9A CN107292524A (en) | 2017-06-28 | 2017-06-28 | Intelligent substation secondary safety measure automatic generation method and device |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710507347.9A CN107292524A (en) | 2017-06-28 | 2017-06-28 | Intelligent substation secondary safety measure automatic generation method and device |
Publications (1)
Publication Number | Publication Date |
---|---|
CN107292524A true CN107292524A (en) | 2017-10-24 |
Family
ID=60098646
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201710507347.9A Pending CN107292524A (en) | 2017-06-28 | 2017-06-28 | Intelligent substation secondary safety measure automatic generation method and device |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN107292524A (en) |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109191327A (en) * | 2018-09-03 | 2019-01-11 | 贵州电网有限责任公司六盘水供电局 | A kind of intelligent substation secondary safety measure implementation process record and back method |
CN110350660A (en) * | 2019-07-12 | 2019-10-18 | 国电南瑞科技股份有限公司 | A kind of relay protection function pressing plate in-service monitoring method and system |
CN110796371A (en) * | 2019-10-30 | 2020-02-14 | 国网重庆市电力公司电力科学研究院 | Intelligent substation safety measure checking method |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102437655A (en) * | 2012-01-11 | 2012-05-02 | 温州电力局 | Analogue display method and system of virtual terminals of intelligent substation |
CN103296755A (en) * | 2013-05-10 | 2013-09-11 | 国家电网公司 | Network online monitoring system for transformer substation |
CN103514336A (en) * | 2013-10-18 | 2014-01-15 | 国家电网公司 | Intelligent substation optical cable connection automatic design method based on virtual-true mapping mode |
CN106066888A (en) * | 2016-06-12 | 2016-11-02 | 浙江浙电经济技术研究院有限公司 | The source database building method of transformer station secondary system and deficiency and excess corresponding method |
CN106532932A (en) * | 2016-10-10 | 2017-03-22 | 国网上海市电力公司 | Secondary virtual loop visualization system based on SCD complete model, and operation method |
-
2017
- 2017-06-28 CN CN201710507347.9A patent/CN107292524A/en active Pending
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102437655A (en) * | 2012-01-11 | 2012-05-02 | 温州电力局 | Analogue display method and system of virtual terminals of intelligent substation |
CN103296755A (en) * | 2013-05-10 | 2013-09-11 | 国家电网公司 | Network online monitoring system for transformer substation |
CN103514336A (en) * | 2013-10-18 | 2014-01-15 | 国家电网公司 | Intelligent substation optical cable connection automatic design method based on virtual-true mapping mode |
CN106066888A (en) * | 2016-06-12 | 2016-11-02 | 浙江浙电经济技术研究院有限公司 | The source database building method of transformer station secondary system and deficiency and excess corresponding method |
CN106532932A (en) * | 2016-10-10 | 2017-03-22 | 国网上海市电力公司 | Secondary virtual loop visualization system based on SCD complete model, and operation method |
Non-Patent Citations (1)
Title |
---|
李辉等: "基于SCD对象模型的智能变电站二次检修安全措施生成方法研究", 《湖南电力》 * |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109191327A (en) * | 2018-09-03 | 2019-01-11 | 贵州电网有限责任公司六盘水供电局 | A kind of intelligent substation secondary safety measure implementation process record and back method |
CN109191327B (en) * | 2018-09-03 | 2021-07-09 | 贵州电网有限责任公司 | Intelligent substation secondary safety measure implementation process recording and playback method |
CN110350660A (en) * | 2019-07-12 | 2019-10-18 | 国电南瑞科技股份有限公司 | A kind of relay protection function pressing plate in-service monitoring method and system |
CN110796371A (en) * | 2019-10-30 | 2020-02-14 | 国网重庆市电力公司电力科学研究院 | Intelligent substation safety measure checking method |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN103762723B (en) | Method and system for managing a power grid | |
CN104123271B (en) | Intelligent substation secondary design system based on Excel | |
CN101236575B (en) | Black start assistant decision making support/training system and its method | |
CN103761624A (en) | Implementing method of integrated power grid dispatching operation intelligent mistaken-early-warning preventing system | |
CN103578039B (en) | A kind of power networks risk prewarning analysis system | |
CN104463696A (en) | Power grid operating risk recognition and prevention method and system | |
CN104242454A (en) | Power monitoring system of rail transit power supply system | |
CN107092222A (en) | Power grid regulation operational administrative system based on the integration of anti-error check analysis | |
CN107451737A (en) | A kind of big data O2O check of drawings cloud platform management systems examined for engineering construction figure | |
CN106971663A (en) | A kind of wind power plant analogue system and method | |
CN107292524A (en) | Intelligent substation secondary safety measure automatic generation method and device | |
CN107085772A (en) | A kind of major network work of electric power system ticket anticipation management system and method | |
CN104821662A (en) | Multidimensional intelligent anti-misoperation system and method | |
CN107067081A (en) | Substation secondary maintenance safety measure generation method based on many object models | |
CN106779508A (en) | Secondary system of intelligent substation safety measure analogue simulation and O&M control platform | |
CN106296467A (en) | A kind of method generating operation order | |
CN107767122A (en) | A kind of electric operation ticket method of calibration | |
CN107045706A (en) | Intelligent substation secondary safety measure operation order automatic generation method | |
CN110196852A (en) | Regulation cloud grid model data management method and system based on metadata management | |
CN105184490A (en) | Power grid dispatching operation process risk auxiliary pre-control system | |
CN110335008A (en) | A kind of net source coordination management method and platform for dispatching of power netwoks | |
CN107871176A (en) | The safety-optimized method and system of secondary device applied to IEC61850 information modelings | |
CN105186686A (en) | Full network topology-based power grid dispatching intelligent anti-error strategy system | |
CN107133883A (en) | Based on the intelligent substation safety measure automatic generation method and device that safety measure is semantic | |
CN104898460B (en) | Suitable for the online static security analysis system of districted dispatch system |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20171024 |