Prior art keywords
sandbag
vertical rod
dam
piles
horizontal
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201710699493.6A
Other languages
Chinese (zh)
Inventor
张凌恺
董晖
董兰田
张峰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201710699493.6A priority Critical patent/CN107288098A/en
Publication of CN107288098A publication Critical patent/CN107288098A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B3/00Engineering works in connection with control or use of streams, rivers, coasts, or other marine sites; Sealings or joints for engineering works in general
    • E02B3/04Structures or apparatus for, or methods of, protecting banks, coasts, or harbours
    • E02B3/10Dams; Dykes; Sluice ways or other structures for dykes, dams, or the like
    • E02B3/106Temporary dykes
    • E02B3/108Temporary dykes with a filling, e.g. filled by water or sand

Landscapes

  • Engineering & Computer Science (AREA)
  • General Engineering & Computer Science (AREA)
  • Environmental & Geological Engineering (AREA)
  • Ocean & Marine Engineering (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Revetment (AREA)

Abstract

The present invention provides a kind of sandbag and piles up emergent flood control dam support securing device, including support, base shaft, dowel pin, preceding vertical rod, rear vertical rod, support bar, buckle nose and horizontal-associate bar.It is characterized in that in flood control dam or the region of building a dam that need to meet an urgent need, laterally arranging the stable frame by support and the assembling of horizontal-associate bar, base is filled out in framework and piles up the emergent dykes and dams of sandbag composition.The present invention compared with prior art, build interim dykes and dams it is more stable, more firmly, antiscour, anti-press capacity it is stronger, less using sandbag quantity, raising is built a dam efficiency and quality, reduces emergency personnel's working strength, thus has good application value.

Description

Sandbag piles up emergent flood control dam support securing device
First, technical field:
The invention belongs to emergent and deposit harness of controlling flood, it is steady that specifically a kind of sandbag piles up emergent flood control dam support It is fixedly mounted with and puts.
2nd, background technology:
Frequent flood overtopping risk and unrestrained dam phenomenon occur in the pool flood control of rivers lake, particular surroundings, location, plot or facility Also need to often build a dam interception flood temporarily, prior art mostly be filling sandbag pile up interim dykes and dams meet an urgent need.But existing this measure more Sandbag size inequality is irregular, piles up that uneven stability is poor, firmness is low, though overlying multiple layers, which are piled up, can improve reliability, But make natively it is pressed for time, the high flood fighters of labor intensity are difficult to tackle.More faced when particularly resisting torrent flood Sandbag, which is washed away, causes dam break risk.
3rd, the content of the invention:
The purpose of the present invention is to be consolidated for problem above and deficiency there is provided one kind and regular sandbag dykes and dams, and raising is built a dam The sandbag of efficiency and quality piles up emergent flood control dam support securing device.
The purpose of the present invention is achieved through the following technical solutions:
A kind of sandbag piles up emergent flood control dam support securing device, including support, base shaft, dowel pin, preceding vertical rod, rear vertical Bar, steady arm, buckle nose and horizontal-associate bar, it is characterized in that in the position laterally line of building a dam that need to meet an urgent need, being fixed by dowel pin and arranging branch Frame, and reinforced with horizontal-associate bar by the series connection of buckle nose, the frame space of group is being enclosed by base shaft, preceding vertical rod, rear vertical rod and horizontal-associate bar Interior filling piles up sandbag into dam, and oblique steady arm enhancing resistance intensity is set between rear vertical rod and base shaft.
Described sandbag piles up emergent flood control dam support securing device, becomes it is characterized in that building emergent dykes and dams and meeting turn Xiang Shi, adjacent stent uses the not parallel fixation more than or less than an angle of 90 degrees to arrange, and only assembles horizontal in preceding vertical rod or rear vertical rod Joining beam, dosage piles up sandbag reply.
The sandbag of the present invention piles up emergent flood control dam support securing device compared with prior art, have the characteristics that and Advantage:
1st, support and horizontal-associate bar use section steel manufacture, and material source is sufficient, and optional model is abundant, simple in construction make is held Easily, it is adapted to factorial praluction and deposit.
2nd, filling is piled up sandbag and built a dam in the frame space that group is enclosed by base shaft, preceding vertical rod, rear vertical rod and horizontal-associate bar, sandbag Neat firm, antiscour, anti-pressure ability are strong, can reduce sandbag consumption in the case of identical high wide dam body, improve operating efficiency.
3rd, after flood season, the support and horizontal-associate bar of dismounting can be laid in after arranging and apply again, more save, more environmentally friendly.
4th, illustrate:
Fig. 1 is that sandbag piles up the supporting structure side schematic view that emergent flood control dam supports securing device.
Fig. 2 is that sandbag piles up the support of emergent flood control dam support securing device, horizontal-associate bar combination front schematic view.
In figure:Vertical rod, 6 support bars, 7 buckle noses, 8 horizontal-associate bars behind vertical rod, 5 before 1 support, 2 base shafts, 3 dowel pins, 4.
5th, embodiment:
The present invention is illustrated in further detail below with reference to Figure of description:
As shown in figure 1, support 1 is by being attached at the base shaft 2 on ground, the preceding vertical rod 4 of the termination of base shaft 2 and middle leading portion vertically upward With the steady arm 6 of the stability of vertical rod 5 after rear vertical rod 5, oblique reinforcement, it is arranged at the two ends of base shaft 2 dowel pin 3 vertically downward and sets Constituted in preceding vertical rod 4 and multiple buckle noses 7 of the rear opposite side of vertical rod 5.Horizontal-associate bar 8 is that two ends are provided with and matched company with buckle nose 7 Connect the straight-bar of fixing lock tenon.
During practical application of controlling flood, moved towards along internal side of dyke or dam, using the length of horizontal-associate bar 8 as spacing, support is laid to both sides extension 1, dowel pin 3 is squeezed into soil layer and fixed, assembling horizontal-associate bar 8 by buckle nose 7 consolidates, in preceding vertical rod 4, rear vertical rod 5 and the frame of horizontal-associate bar 8 Filling assembles sandbag into dam in built on stilts.
It is the known technology of those skilled in the art in addition to the technical characteristic described in specification.

Claims (2)

1. a kind of sandbag piles up emergent flood control dam support securing device, including support, base shaft, dowel pin, preceding vertical rod, rear vertical rod, Steady arm, buckle nose and horizontal-associate bar, it is characterized in that in the position laterally line of building a dam that need to meet an urgent need, fixed by dowel pin and arrange support, And reinforced with horizontal-associate bar by the series connection of buckle nose, filled in the frame space for enclosing group by base shaft, preceding vertical rod, rear vertical rod and horizontal-associate bar Fill out and pile up sandbag into dam, oblique steady arm enhancing resistance intensity is set between rear vertical rod and base shaft.
2. sandbag according to claim 1 piles up emergent flood control dam support securing device, it is characterized in that building emergent dike When dam meets turn deflecting, adjacent stent is used to be arranged more than or less than the not parallel fixation of an angle of 90 degrees, only preceding vertical rod or after Horizontal-associate bar is assembled in vertical rod, dosage piles up sandbag reply.
CN201710699493.6A 2017-08-16 2017-08-16 Sandbag piles up emergent flood control dam support securing device Pending CN107288098A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710699493.6A CN107288098A (en) 2017-08-16 2017-08-16 Sandbag piles up emergent flood control dam support securing device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710699493.6A CN107288098A (en) 2017-08-16 2017-08-16 Sandbag piles up emergent flood control dam support securing device

Publications (1)

Publication Number Publication Date
CN107288098A true CN107288098A (en) 2017-10-24

Family

ID=60106925

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710699493.6A Pending CN107288098A (en) 2017-08-16 2017-08-16 Sandbag piles up emergent flood control dam support securing device

Country Status (1)

Country Link
CN (1) CN107288098A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108978584A (en) * 2018-08-09 2018-12-11 黄河水利委员会黄河水利科学研究院 A kind of emergency control method of dike breach
CN109056641A (en) * 2018-04-03 2018-12-21 翟鼎文 Multifunctional movable dike
CN110184996A (en) * 2019-06-17 2019-08-30 华北水利水电大学 Dykes and dams safeguard of the hydraulic engineering with multi-point support

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103243725A (en) * 2013-04-26 2013-08-14 中铁隧道集团有限公司 Offshore foundation pit cofferdam construction technology
CN105421292A (en) * 2015-12-24 2016-03-23 天津大学 Temporary water-retaining dam built through geotextile filling bags and steel frame supporting systems
CN205475082U (en) * 2016-01-22 2016-08-17 华能澜沧江水电股份有限公司糯扎渡水电厂 Emergent manger plate sand box
CN106759098A (en) * 2016-12-19 2017-05-31 绵竹市莫尔企业管理服务有限公司 A kind of hydraulic engineering flood control case

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103243725A (en) * 2013-04-26 2013-08-14 中铁隧道集团有限公司 Offshore foundation pit cofferdam construction technology
CN105421292A (en) * 2015-12-24 2016-03-23 天津大学 Temporary water-retaining dam built through geotextile filling bags and steel frame supporting systems
CN205475082U (en) * 2016-01-22 2016-08-17 华能澜沧江水电股份有限公司糯扎渡水电厂 Emergent manger plate sand box
CN106759098A (en) * 2016-12-19 2017-05-31 绵竹市莫尔企业管理服务有限公司 A kind of hydraulic engineering flood control case

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109056641A (en) * 2018-04-03 2018-12-21 翟鼎文 Multifunctional movable dike
CN108978584A (en) * 2018-08-09 2018-12-11 黄河水利委员会黄河水利科学研究院 A kind of emergency control method of dike breach
CN110184996A (en) * 2019-06-17 2019-08-30 华北水利水电大学 Dykes and dams safeguard of the hydraulic engineering with multi-point support
CN110184996B (en) * 2019-06-17 2021-03-23 华北水利水电大学 Dykes and dams protective equipment with multiple spot is supported for hydraulic engineering

Similar Documents

Publication Publication Date Title
CN107288098A (en) Sandbag piles up emergent flood control dam support securing device
CN203796285U (en) Tunnel supporting structure with steel frames
CN203654295U (en) Single-leg inclined strut reinforced foundation pit supporting structure
CN202644551U (en) Steel pipe pile cofferdam structure
CN105648981A (en) Steel reinforcement cage used for flood fighting and emergency rescues
CN207452895U (en) A kind of high slope anchored pile supporting
CN112195859A (en) Hydraulic engineering is with interim reinforcement flood control dykes and dams
CN102444141A (en) Object-accommodating bag group, production method thereof and formed retaining wall
CN201778303U (en) Flood-control intercepting steel mesh
CN102277875A (en) Composite supporting structure between piles
CN203007977U (en) Composite protective structure for reinforced net-plane stopping wall
CN204645058U (en) A kind ofly be provided with the H type Double-row-piles Structure adding core rotary churning pile
CN204212165U (en) A kind of venetian blind type steel bar concrete link plate for afforesting based on antislide pile
CN109868789A (en) A kind of sea dike revetment ecological reconstruction structure
CN212427191U (en) Reinforced corrugated concrete retaining wall
CN209741783U (en) Opposite-pull type sand gravel water retaining guide wall
CN211472387U (en) Hydraulic engineering bank protection reinforcing apparatus
CN203684221U (en) Screw pile anchorage structure for sheet-pile wharf
CN110080165A (en) A kind of arch thin-wall construction checkdam and its application method that can quickly construct
CN214460563U (en) Building foundation new material foundation structure
CN214741371U (en) Tunnel country rock reinforced structure for hydraulic engineering
CN205296062U (en) Reinforced shore -fixing retaining wall
CN212983768U (en) Hydraulic engineering slope net convenient to equipment
CN210562227U (en) High-resistance slope protection net
CN104762975A (en) h-shaped double-row pile structure provided with core-entraining jet grouting pile

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20171024