CN107275978A - A kind of tower face operation guard method - Google Patents

A kind of tower face operation guard method Download PDF

Info

Publication number
CN107275978A
CN107275978A CN201710495853.0A CN201710495853A CN107275978A CN 107275978 A CN107275978 A CN 107275978A CN 201710495853 A CN201710495853 A CN 201710495853A CN 107275978 A CN107275978 A CN 107275978A
Authority
CN
China
Prior art keywords
shaft tower
dynamic ropes
tower
guard method
rope closing
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201710495853.0A
Other languages
Chinese (zh)
Inventor
孙权
高源�
高洪涛
倪春雨
胡鑫
钱勇
易立娟
李东明
黄微
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
State Grid Corp of China SGCC
State Grid Liaoning Electric Power Co Ltd
Original Assignee
State Grid Corp of China SGCC
State Grid Liaoning Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by State Grid Corp of China SGCC, State Grid Liaoning Electric Power Co Ltd filed Critical State Grid Corp of China SGCC
Priority to CN201710495853.0A priority Critical patent/CN107275978A/en
Publication of CN107275978A publication Critical patent/CN107275978A/en
Pending legal-status Critical Current

Links

Classifications

    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02GINSTALLATION OF ELECTRIC CABLES OR LINES, OR OF COMBINED OPTICAL AND ELECTRIC CABLES OR LINES
    • H02G1/00Methods or apparatus specially adapted for installing, maintaining, repairing or dismantling electric cables or lines
    • H02G1/02Methods or apparatus specially adapted for installing, maintaining, repairing or dismantling electric cables or lines for overhead lines or cables

Landscapes

  • Emergency Lowering Means (AREA)
  • Refuge Islands, Traffic Blockers, Or Guard Fence (AREA)

Abstract

The present invention relates to a kind of tower face operation guard method, a hanging point is aloft made at dynamic ropes center of rope closing knot first, under then dynamic ropes one end is thrown along shaft tower surface, the other end is along under side throwing in shaft tower, the landing of two ends fag end;Descender connects dynamic ropes and safety belt with drop device and carries out side working edge decline along shaft tower surface, until reaching ground;Reach behind ground, the two ends of dynamic ropes are intersected into stress, untie top rope closing knot, operation is finished.Effective guarantee is in shaft tower surface upkeep operation safety and improves operating efficiency, it is adaptable to shaft tower upkeep operation staffs training, is equally applicable to shaft tower assembling operation.

Description

A kind of tower face operation guard method
Technical field
Bar, which is stepped on, the present invention relates to a kind of power system transmission line does industry method, more particularly to a kind of tower face operation protection side Method.
Background technology
During the upkeep operations such as the mopping of shaft tower surface, bolt fastening, each shift position of operating personnel will tear hanging safety belt open Protection rope, it is largely physical to tear hanging safety belt consumption operator open repeatedly, and tears hanging safety belt open repeatedly and also increase potential safety hazard.
The content of the invention
The present invention, there is provided a kind of tower face operation guard method, is solved existing for above-mentioned problems of the prior art Have and the problem of bar operation is wasted time and energy, there is potential safety hazard is stepped in technology.
Technical scheme comprises the following steps:
Step 1, a hanging point is aloft made at dynamic ropes center of rope closing knot first, then dynamic ropes one end is along shaft tower surface Under throwing, the other end is along under side throwing in shaft tower, the landing of two ends fag end;
Step 2, descender connect dynamic ropes and safety belt with drop device and carry out side working edge decline along shaft tower surface, until arriving Up to ground;
Behind step 3, arrival ground, the two ends of dynamic ropes are intersected into stress, top rope closing knot is untied, operation is finished.
In described step 1, rope closing becomes tomfool's knot.
In described step 1, four main materials of shaft tower lay safety rope.
In described step 2, drop device is STOP drop devices.
Advantages of the present invention effect is as follows;
Effective guarantee is in shaft tower surface upkeep operation safety and improves operating efficiency, it is adaptable to shaft tower upkeep operation staffs training, It is equally applicable to shaft tower assembling operation.
Embodiment
Embodiment 1
On shaft tower surface(Mopping, bolt fastening)During operation, a hanging point is aloft made at dynamic ropes center of rope closing knot first, Rope closing knot is safe and reliable, under then dynamic ropes one end is thrown along shaft tower surface, and the other end is along under side throwing in shaft tower, two ends rope Head landing;Four main materials of shaft tower lay safety rope;Descender connects dynamic ropes and safety belt along shaft tower with " STOP " drop device Surface carries out side working edge decline, until reaching ground;Reach behind ground, dynamic ropes two ends are intersected into stress, untie top and restrict Knot, operation is finished.
Embodiment 2
When doing shaft tower maintenance training, first protection rope is reliably fixed in shaft tower lower end, trainer is along along shaft tower in training Orientation is put, and rope will be protected to be fixed on shaft or tower body in climbing, turning point tomfool's knot, protection rope one end along Under shaft tower surface is thrown, the other end is along under side throwing in shaft tower, the landing of two ends fag end;Student on safety belt by will latch in guarantor On shield rope, along above and below rope.
Embodiment 3
When shaft tower is assembled, generally safety rope, specific method be the same as Example 2 are laid in four main materials of shaft tower.

Claims (4)

1. a kind of tower face operation guard method, it is characterised in that comprise the following steps:
Step 1, a hanging point is aloft made at dynamic ropes center of rope closing knot first, then dynamic ropes one end is along shaft tower surface Under throwing, the other end is along under side throwing in shaft tower, the landing of two ends fag end;
Step 2, descender connect dynamic ropes and safety belt with drop device and carry out side working edge decline along shaft tower surface, until arriving Up to ground;
Behind step 3, arrival ground, the two ends of dynamic ropes are intersected into stress, top rope closing knot is untied, operation is finished.
2. a kind of tower face operation guard method according to claim 1, it is characterised in that in described step 1, rope closing knot For tomfool's knot.
3. a kind of tower face operation guard method according to claim 1, it is characterised in that in described step 1, shaft tower four Individual main material lays safety rope.
4. a kind of tower face operation guard method according to claim 1, it is characterised in that in described step 2, drop device For STOP drop devices.
CN201710495853.0A 2017-06-26 2017-06-26 A kind of tower face operation guard method Pending CN107275978A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710495853.0A CN107275978A (en) 2017-06-26 2017-06-26 A kind of tower face operation guard method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710495853.0A CN107275978A (en) 2017-06-26 2017-06-26 A kind of tower face operation guard method

Publications (1)

Publication Number Publication Date
CN107275978A true CN107275978A (en) 2017-10-20

Family

ID=60069306

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710495853.0A Pending CN107275978A (en) 2017-06-26 2017-06-26 A kind of tower face operation guard method

Country Status (1)

Country Link
CN (1) CN107275978A (en)

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2000092638A (en) * 1998-09-08 2000-03-31 Tekuseru:Kk Taping equipment
CN101143249A (en) * 2007-07-25 2008-03-19 深圳海油人力资源服务公司 Spherical tank inner surface approaching system
CN201727854U (en) * 2010-05-28 2011-02-02 刘文辉 Rope brake descender
CN201959429U (en) * 2011-02-12 2011-09-07 刘文辉 Protector for high-rise escape
CN103227431A (en) * 2013-03-19 2013-07-31 国家电网公司 Method for replacing insulator chains in 220 kV long-span high tower in live working
CN103618248A (en) * 2013-11-28 2014-03-05 国家电网公司 Direct current high-tension transmission line maintenance method and special safety hanging seat
CN104338256A (en) * 2013-08-07 2015-02-11 王奎臣 Fire and earthquake escape device

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2000092638A (en) * 1998-09-08 2000-03-31 Tekuseru:Kk Taping equipment
CN101143249A (en) * 2007-07-25 2008-03-19 深圳海油人力资源服务公司 Spherical tank inner surface approaching system
CN201727854U (en) * 2010-05-28 2011-02-02 刘文辉 Rope brake descender
CN201959429U (en) * 2011-02-12 2011-09-07 刘文辉 Protector for high-rise escape
CN103227431A (en) * 2013-03-19 2013-07-31 国家电网公司 Method for replacing insulator chains in 220 kV long-span high tower in live working
CN104338256A (en) * 2013-08-07 2015-02-11 王奎臣 Fire and earthquake escape device
CN103618248A (en) * 2013-11-28 2014-03-05 国家电网公司 Direct current high-tension transmission line maintenance method and special safety hanging seat

Similar Documents

Publication Publication Date Title
CN102064493B (en) Method for paying off overhead transmission line by unmanned helicopter
CN205666589U (en) Wire deicing instrument
CN107514946A (en) A kind of explosion isolation protecting device of convenient use
CN203742194U (en) Prestressed steel wire rope encircling reinforcing device of concrete beam
CN107275978A (en) A kind of tower face operation guard method
CN106577168B (en) Climbing-free safety rope tying device for tree cutting
CN205367562U (en) Coaster slowly falls in electric line heavy object
CN206471750U (en) A kind of across obstacle Poling Construction protection structure
CN203722136U (en) Insulation rope net apparatus for railway crossing tension stringing construction
CN203736798U (en) Auxiliary pedal for climbing steel pylon
CN207597288U (en) A kind of reinforcement curtain guides protection network
CN205986048U (en) Quick detach formula chain anti -bird thorn
CN204919488U (en) A damping formula block a river line for blocking superelevation ship
CN204265376U (en) A kind of electric pole material lifting device
CN107558793A (en) Multilayer cross-arm lifting installation method and its specific purpose tool on a kind of overhead transmission line electric pole
CN207039065U (en) A kind of transmission line of electricity block device with positioner
CN206722440U (en) Protection device for constructor walking in steel beam construction operation
CN107913479A (en) The rescue mode of the oblique rope bridge-type of high-voltage power line conductive line bar tower trapped person
CN104393524B (en) Avoid setting up using aerial earth wire extension pulley group job and cross over frame construction method
CN202627951U (en) Anti-falling rope ladder
CN203406560U (en) Pulley capable of increasing frictional resistance
CN207258649U (en) A kind of power-off protective device for sealing-tape machine rubber belt from deviating
CN201792535U (en) Antiskid plate
CN201551754U (en) Warehouse operation safety protection device
CN105207119B (en) Electrified span construction method for high-voltage wires and protective device of construction

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20171020

RJ01 Rejection of invention patent application after publication