CN107273640A - Hydraulic and Hydro-Power Engineering Schedule monitoring method based on three-dimensional digital model - Google Patents

Hydraulic and Hydro-Power Engineering Schedule monitoring method based on three-dimensional digital model Download PDF

Info

Publication number
CN107273640A
CN107273640A CN201710559978.5A CN201710559978A CN107273640A CN 107273640 A CN107273640 A CN 107273640A CN 201710559978 A CN201710559978 A CN 201710559978A CN 107273640 A CN107273640 A CN 107273640A
Authority
CN
China
Prior art keywords
model
progress
construction
data
hydraulic
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201710559978.5A
Other languages
Chinese (zh)
Inventor
陶玉波
杨顺群
郭莉莉
刘增强
蔺志刚
王陆
梁春光
田丰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Yellow River Engineering Consulting Co Ltd
Original Assignee
Yellow River Engineering Consulting Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Yellow River Engineering Consulting Co Ltd filed Critical Yellow River Engineering Consulting Co Ltd
Priority to CN201710559978.5A priority Critical patent/CN107273640A/en
Publication of CN107273640A publication Critical patent/CN107273640A/en
Pending legal-status Critical Current

Links

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F30/00Computer-aided design [CAD]
    • G06F30/10Geometric CAD
    • G06F30/13Architectural design, e.g. computer-aided architectural design [CAAD] related to design of buildings, bridges, landscapes, production plants or roads
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
    • G06Q50/06Energy or water supply
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06TIMAGE DATA PROCESSING OR GENERATION, IN GENERAL
    • G06T17/00Three dimensional [3D] modelling, e.g. data description of 3D objects

Landscapes

  • Engineering & Computer Science (AREA)
  • Physics & Mathematics (AREA)
  • Geometry (AREA)
  • General Physics & Mathematics (AREA)
  • Theoretical Computer Science (AREA)
  • Business, Economics & Management (AREA)
  • Computer Hardware Design (AREA)
  • Economics (AREA)
  • Health & Medical Sciences (AREA)
  • Pure & Applied Mathematics (AREA)
  • Public Health (AREA)
  • Computational Mathematics (AREA)
  • Mathematical Analysis (AREA)
  • Mathematical Optimization (AREA)
  • Civil Engineering (AREA)
  • Evolutionary Computation (AREA)
  • General Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Software Systems (AREA)
  • Computer Graphics (AREA)
  • Structural Engineering (AREA)
  • Water Supply & Treatment (AREA)
  • General Health & Medical Sciences (AREA)
  • Human Resources & Organizations (AREA)
  • Marketing (AREA)
  • Primary Health Care (AREA)
  • Strategic Management (AREA)
  • Tourism & Hospitality (AREA)
  • General Business, Economics & Management (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The invention discloses a kind of Hydraulic and Hydro-Power Engineering Schedule monitoring method based on three-dimensional digital model, one, modeling:Read the two-dimentional drawing of hydraulic engineering or directly carry out Hydraulic Engineering Design, the establishment of model is carried out using CATIA Three-dimensional Design Softwares, modeling detail is more than LOD300;2nd, progress model partition:According to schedule, project demands and project characteristic, the first step is designed a model and is divided into progress model, the title to each progress model customizes specific identifier, and the progress model name after division is divided into two parts:Unique identifier and numeral;3rd, the progress model name after all divisions is set up into other fields afterwards as major key write into Databasce;4th, secondary development is carried out to Catia Composer Player, so that the need for meeting the typing of BIM progresses, deviation contrast, lags analysis and virtual construction function.

Description

Hydraulic and Hydro-Power Engineering Schedule monitoring method based on three-dimensional digital model
Technical field
The present invention relates to Hydraulic and Hydro-Power Engineering Schedule monitoring method, more particularly, to the water conservancy water based on three-dimensional digital model Electrical engineering Schedule monitoring method.
Background technology
At present, Hydraulic and Hydro-Power Engineering(Road, tunnel, diversion tunnel, vertical shaft, inclined shaft, dam, sluice, factory building, spillway)Enter Spend that monitoring management is still not fine enough, though there is more ripe progress control method to support, but often occur that progress is delayed, work The situation of phase delay, by researching and analysing, following defect is primarily present in current Hydraulic and Hydro-Power Engineering progress control method:
First, construction program is excessively rigid, lacks optimization.It is main at present to use gunter drawing, network planning technique, with reference to Project, P3 Project Management Software carry out construction program formulation, management.Progress monitoring is carried out with such schedule, It is simply simple that the calculating duration is overlapped according to mechanical efficiency, when there is design alteration or execution conditions change, because Schedule lacks flexibility, to optimize and adjust very difficult, particularly when working sources, which exist, to be disturbed, it is difficult to calculate Duration, this just causes actual progress with planning far from each other, also implies that progress monitoring loses meaning.
Second, factors joint effect project progress, progress control work is difficult to exhaustive.With economy and engineering The development of technology, project scale extension, complexity increase, it is desirable to which manager, which takes into full account, various may influence project progress Factor.The combined influence of various factors, the progress that directly results in controls ineffective, duration under-reserve in advance, manages without normal plane face All arrive, the duration delays.
3rd, engineering participant is numerous, and on-site coordination workload is big.The characteristics of engineering project versatility, determines that needs are more Side participates in cooperation and completed.Respectively the side of taking part in building will also actively coordinate other participants except to carry out the construction task of itself team Work.Integrate insufficient, ineffecitive coordination and directly result in duration extension.For example, each subpackage unit that there is procedure connection coordinates not Power causes process portion to carry out in time;Construction section divides unreasonable, cross construction poor organization etc..
4th, progress, quality, the big management objectives of cost three are mutually restricted, it is difficult to balanced.In work progress, project pipe Manage three big targets to connect each other and mutually restriction, either objective changes, and will all cause remaining two big target to change. Working to tight deadlines means to increase cost, and the balanced degree of three decides the realization of project objective.In progress control of today, because Lack advanced technology and theories integration, it is difficult to optimization three big targets of balance.
The content of the invention
Present invention aims at provide a kind of Hydraulic and Hydro-Power Engineering Schedule monitoring method based on three-dimensional digital model.
To achieve the above object, the present invention takes following technical proposals:
Hydraulic and Hydro-Power Engineering Schedule monitoring method of the present invention based on three-dimensional digital model, with CATIA(French Da Suo companies A design software)Three-dimensional Design Software is carrier, and establishment designs a model, special according to the construction program and project Point, is divided into progress model by described design a model, carries out as steps described below:
The first step, modeling:Read the two-dimentional drawing of hydraulic engineering or directly carry out Hydraulic Engineering Design, utilize CATIA three dimensional designs Software carries out the establishment of model, in modeling process, is modeled using parametrization and templating, is easy to the modification of late design, builds Mould detail is more than LOD(Model fineness)300;
Second step, progress model partition:According to schedule, project demands and project characteristic, designing a model for the first step is drawn It is divided into progress model, the title to each progress model customizes specific identifier, the progress model name point after division For two parts:Unique identifier and numeral, are easy to distinguish each progress model;
3rd step, using the progress model name after all divisions as major key write into Databasce, other fields are set up afterwards, Other fields include plan engineering time, practice of construction time, sequence of construction, construction technology, pile No. or elevation, quality letter Breath, security information, exception record;
4th step, to Catia Composer Player(A displaying software of French Da Suo companies)Secondary development is carried out, its Corresponding ComposerPlayerActiveX(The plug-in unit of French a displaying software of Da Suo companies), broken away from CATIA designs flat Platform and Catia Composer Player display platforms, you can independent to carry out Embedded exploitation, and with API(Using journey Sequence DLL)Interface, with Microsoft Visual Studio(The development kit series of products of MS)Open Send out platform and network data base Sql Server(The Relational DBMS that MS releases)With reference to, so that Meet BIM(English Building Information Modeling abbreviation;BIM)Progress typing, deviation pair The need for, lags analysis and virtual construction function.
The BIM functions are:Utilize the select in Sql Server databases(Selection)Sentence transfers major key " model name The related BIM integrated information data of title ", show in the interaction of visual platform;
The progress input function is:Utilize the update in Sql Server databases(Update)Sentence updates newest reality Progress data, while updating the color of correlation model in visualization engine, realizes visual monitoring;Major key " model name " Corresponded with plan in database and practice of construction time field, be intended to write respective field, meter with actual progress data Typing can be shifted to an earlier date by drawing progress data, and actual progress data are filled in work progress according to progress data daily or weekly;
The schedule variance is contrasted:Qualified Model Name field in the database is read, first in database The model name of normal construction is read, condition is that actual progress data are not empty, is blueness by these model definitions;Secondly read The advanced model name of progress, condition is that actual progress data are not empty, and target advance is more than the current date, by these moulds Type is defined as green;The last delayed model name of Load Game, condition is that actual progress data are empty, and target advance is less than These model definitions are red by the current date;Different colors represents different states;
The progress lags analysis function is:In typing actual progress, if any progress abnormal conditions, corresponding model is selected, In the text box that these abnormal conditions write-in programs are provided, automatically write database after submission, and to related building word Duan Guanlian;If delayed, the abnormal conditions submitted before the building, reading are clicked on, show that the building hysteresis reason is arranged Table, according to these hysteresis reasons, is referred to for construction manager, formulates corresponding measure of overworking;
The virtual construction function is:According to existing target advance data or actual progress data, Microsoft is utilized Visual Studio timer(Timer)Control, regards progress model as discrete event by certain cycle and gradually shows it Show to come;According to the building course of the construction plan simulation reality of engineering project, found under virtual environment in work progress The problem of there may be and risk, and the progress model and plan are adjusted and changed for problem, and then Optimizing construction Plan.
Advantage of the present invention is mainly reflected in:
1st, 4D of the Hydraulic and Hydro-Power Engineering field based on three-dimensional digital result of design is proposed(It is four-dimensional:Space coordinate X, Y, Z are timely Between coordinate T)Schedule monitoring method, this method can be with cutting arbitrary section, and BIM information associations such as model and two-dimentional drawing, just Understand design idea in user.
2nd, progress and actual progress typing network data base are intended in Hydraulic and Hydro-Power Engineering field, is joined with data and model Conjunction is checked, realizes the contrast of schedule variance.
3rd, the interactive inquiry of virtual construction and other data is realized using man-machine interactive data inputting.
4th, Catia Composer Player work as water conservancy and hydropower as the main development platform and display platform of this method Project progress need not re-create model when changing, and can greatly save the time and save rework cost, and it can pass through 3D animations and establishment interactive product document preferably pass on product information;Catia Composer Player secondary development is Extension to its software function, can need to carry out customizing functions according to project characteristic or owner.
Brief description of the drawings
Fig. 1 is the monitoring method structural representation set up according to the inventive method.
Embodiment
Embodiments of the invention are elaborated below in conjunction with the accompanying drawings, the present embodiment using technical solution of the present invention before Put and implemented, give detailed embodiment and specific operating process, but protection scope of the present invention is not limited to down State embodiment.
As shown in figure 1, the Hydraulic and Hydro-Power Engineering Schedule monitoring method of the present invention based on three-dimensional digital model, with CATIA(A design software of French Da Suo companies)Three-dimensional Design Software is carrier, and establishment designs a model, according to the engineering Schedule and project characteristic, are divided into progress model by described design a model, implement and carry out as steps described below:
The first step, modeling:Read the two-dimentional drawing of hydraulic engineering or directly carry out Hydraulic Engineering Design, utilize CATIA three dimensional designs Software carries out the establishment of model, in modeling process, is modeled using parametrization and templating, is easy to the modification of late design, builds Mould detail is more than LOD(Model fineness)300;
Second step, progress model partition:According to schedule, project demands and project characteristic, designing a model for the first step is drawn It is divided into progress model, the title to each progress model customizes specific identifier, the progress model name point after division For two parts:Unique identifier and numeral, are easy to distinguish each progress model;
3rd step, using the progress model name after all divisions as major key write into Databasce, other fields are set up afterwards, Other fields include plan engineering time, practice of construction time, sequence of construction, construction technology, pile No. or elevation, quality letter Breath, security information, exception record etc.;
4th step, to Catia Composer Player(A displaying software of French Da Suo companies)Secondary development is carried out, its Corresponding ComposerPlayerActiveX(The plug-in unit of French a displaying software of Da Suo companies), broken away from CATIA designs flat Platform and Catia Composer Player display platforms, you can independent to carry out Embedded exploitation, and with API(Using journey Sequence DLL)Interface, with Microsoft Visual Studio(The development kit series of products of MS)Open Send out platform and network data base Sql Server(The Relational DBMS that MS releases)With reference to, so that Meet BIM(English Building Information Modeling abbreviation;BIM)Progress typing, deviation pair The need for the functions such as, lags analysis and virtual construction.
The BIM functions are:Utilize the select in Sql Server databases(Selection)Sentence transfers major key " model name The related BIM integrated information data of title ", show in the interaction of visual platform;
The progress input function is:Utilize the update in Sql Server databases(Update)Sentence updates newest reality Progress data, while updating the color of correlation model in visualization engine, realizes visual monitoring;Major key " model name " Corresponded with plan in database and practice of construction time field, be intended to write respective field, meter with actual progress data Typing can be shifted to an earlier date by drawing progress data, and actual progress data are filled in work progress according to progress data daily or weekly;
The schedule variance is contrasted:Qualified Model Name field in the database is read, first in database The model name of normal construction is read, condition is that actual progress data are not empty, is blueness by these model definitions;Secondly read The advanced model name of progress, condition is that actual progress data are not empty, and target advance is more than the current date, by these moulds Type is defined as green;The last delayed model name of Load Game, condition is that actual progress data are empty, and target advance is less than These model definitions are red by the current date;Different colors represents different states;
The progress lags analysis function is:In typing actual progress, if any progress abnormal conditions, corresponding model is selected, In the text box that these abnormal conditions write-in programs are provided, automatically write database after submission, and to related building word Duan Guanlian;If delayed, the abnormal conditions submitted before the building, reading are clicked on, show that the building hysteresis reason is arranged Table, according to these hysteresis reasons, is referred to for construction manager, formulates corresponding measure of overworking;
The virtual construction function is:According to existing target advance data or actual progress data, Microsoft is utilized Visual Studio timer(Timer)Control, regards progress model as discrete event by certain cycle and gradually shows it Show to come;According to the building course of the construction plan simulation reality of engineering project, found under virtual environment in work progress The problem of there may be and risk, and the progress model and plan are adjusted and changed for problem, and then Optimizing construction Plan.
The present invention can be combined with information management system:In the management of engineering construction of modernization, the construction stage is often Engineering information management system can be carried out, these systems include substantial amounts of file and data, including quality, progress, safety, investment etc. Deng being linked up in initial stage of development and Development of Management Information System person, how framework database is so as to preferably used in other systems. In 4D Schedule monitoring methods, model is combined with these files or data, along with foregoing BIM functions, you can shape Into 4D BIM models, engineering forms electronic document after terminating and consigns to owner.
The present invention can also develop other miscellaneous functions;After major function has been developed, carry out other functional developments with Aid in the realization of major function, including user right, hiding/display, placed in the middle, printing, view, video playback, the quick dish of right button It is single etc..These functions are also based on API the and Microsoft Visual of Catia Composer Player openings Studio basic control is developed jointly.
To the 4D(It is four-dimensional:Space coordinate X, Y, Z and time coordinate T)The explanation of Schedule monitoring:
Assuming that certain is building the main building thing arched concrete dam of Hydraulic and Hydro-Power Engineering, crest elevation 1265m is designed, up to now, It should construct according to plan to 1230m, practice of construction to 1226m, then can intuitively be looked on threedimensional model using this method Ask target advance up to now(Only show the model of below 1230m elevations), actual progress(Only display below 1226m is high The model of journey)And schedule variance(1226m represents delayed model to 1230m elevations with other colors)Etc. information.

Claims (2)

1. a kind of Hydraulic and Hydro-Power Engineering Schedule monitoring method based on three-dimensional digital model, using CATIA Three-dimensional Design Softwares as load Body, establishment is designed a model, and according to the construction program and project characteristic, described design a model is divided into progress model, Carry out as steps described below:
The first step, modeling:Read the two-dimentional drawing of hydraulic engineering or directly carry out Hydraulic Engineering Design, utilize CATIA three dimensional designs Software carries out the establishment of model, in modeling process, is modeled using parametrization and templating, is easy to the modification of late design, builds Mould detail is more than LOD300;
Second step, progress model partition:According to schedule, project demands and project characteristic, designing a model for the first step is drawn It is divided into progress model, the title to each progress model customizes specific identifier, the progress model name point after division For two parts:Unique identifier and numeral, are easy to distinguish each progress model;
3rd step, using the progress model name after all divisions as major key write into Databasce, other fields are set up afterwards, Other fields include plan engineering time, practice of construction time, sequence of construction, construction technology, pile No. or elevation, quality letter Breath, security information, exception record;
4th step, to Catia Composer Player carry out secondary development, its corresponding ComposerPlayerActiveX, Break away from CATIA design platforms and Catia Composer Player display platforms, you can independent to carry out Embedded exploitation, And with api interface, combined with Microsoft Visual Studio development platforms and network data base Sql Server, The need for meeting the typing of BIM progresses, deviation contrast, lags analysis and virtual construction function.
2. the Hydraulic and Hydro-Power Engineering Schedule monitoring method based on three-dimensional digital model according to claim 1, it is characterised in that:
The BIM functions are:Major key " model name " correlation is transferred using the select sentences in Sql Server databases BIM integrated information data, show in the interaction of visual platform;
The progress input function is:Newest actual progress number is updated using the update sentences in Sql Server databases According to, at the same in visualization engine update correlation model color, realize visual monitoring;Major key " model name " and data Plan and practice of construction time field are corresponded in storehouse, are intended to write respective field, target advance with actual progress data Data can shift to an earlier date typing, and actual progress data are filled in work progress according to progress data daily or weekly;
The schedule variance is contrasted:Qualified Model Name field in the database is read, first in database The model name of normal construction is read, condition is that actual progress data are not empty, is blueness by these model definitions;Secondly read The advanced model name of progress, condition is that actual progress data are not empty, and target advance is more than the current date, by these moulds Type is defined as green;The last delayed model name of Load Game, condition is that actual progress data are empty, and target advance is less than These model definitions are red by the current date;Different colors represents different states;
The progress lags analysis function is:In typing actual progress, if any progress abnormal conditions, corresponding model is selected, In the text box that these abnormal conditions write-in programs are provided, automatically write database after submission, and to related building word Duan Guanlian;If delayed, the abnormal conditions submitted before the building, reading are clicked on, show that the building hysteresis reason is arranged Table, according to these hysteresis reasons, is referred to for construction manager, formulates corresponding measure of overworking;
The virtual construction function is:According to existing target advance data or actual progress data, Microsoft is utilized Visual Studio timer controls, regard progress model as discrete event by certain cycle and gradually show it; According to the building course of the construction plan simulation reality of engineering project, find to there may be in work progress under virtual environment The problem of and risk, and the progress model and plan are adjusted and changed for problem, and then Optimizing construction plan.
CN201710559978.5A 2017-07-11 2017-07-11 Hydraulic and Hydro-Power Engineering Schedule monitoring method based on three-dimensional digital model Pending CN107273640A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710559978.5A CN107273640A (en) 2017-07-11 2017-07-11 Hydraulic and Hydro-Power Engineering Schedule monitoring method based on three-dimensional digital model

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710559978.5A CN107273640A (en) 2017-07-11 2017-07-11 Hydraulic and Hydro-Power Engineering Schedule monitoring method based on three-dimensional digital model

Publications (1)

Publication Number Publication Date
CN107273640A true CN107273640A (en) 2017-10-20

Family

ID=60071864

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710559978.5A Pending CN107273640A (en) 2017-07-11 2017-07-11 Hydraulic and Hydro-Power Engineering Schedule monitoring method based on three-dimensional digital model

Country Status (1)

Country Link
CN (1) CN107273640A (en)

Cited By (13)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108537877A (en) * 2018-03-07 2018-09-14 北京中科紫宸睿达科技有限公司 Visualizing monitor interface customizing generation method based on threedimensional model and device
CN108536984A (en) * 2018-04-19 2018-09-14 广东电网有限责任公司 A kind of information infrastructure intermediate item progress three-dimensional visualization method
CN109271701A (en) * 2018-09-11 2019-01-25 中国铁路设计集团有限公司 A kind of water supply and drainage BIM forward design method based on up to cable system
CN109377066A (en) * 2018-10-31 2019-02-22 广西路桥工程集团有限公司 A kind of live Schedule monitoring system and method based on threedimensional model
CN109472104A (en) * 2018-11-21 2019-03-15 国网河北省电力有限公司建设公司 A kind of 500KV substation VR Construction simulation method and device
CN110119565A (en) * 2019-05-08 2019-08-13 中铁八局集团建筑工程有限公司 A method of quick association and displaying based on BIM model and project programme
CN110852696A (en) * 2019-10-08 2020-02-28 上海建工五建集团有限公司 Project progress monitoring method and system
CN112785046A (en) * 2021-01-05 2021-05-11 上海海事大学 Multisource hydraulic engineering image information system
CN112818459A (en) * 2021-03-12 2021-05-18 黄河勘测规划设计研究院有限公司 BIM and Gantt chart-based visual progress management method for engineering construction period
CN113095609A (en) * 2019-12-23 2021-07-09 北京博超时代软件有限公司 Risk prompt previewing method, device and equipment
CN113158317A (en) * 2021-05-11 2021-07-23 温州广信工程管理有限公司 Civil engineering virtual model and modeling method
CN113450358A (en) * 2021-09-01 2021-09-28 国能大渡河大数据服务有限公司 Progress control method and system for hydropower basin step development and construction
CN113778438A (en) * 2021-08-04 2021-12-10 中国二十冶集团有限公司 Progress plan construction method based on engineering management and control platform

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20130335413A1 (en) * 2012-06-13 2013-12-19 National Chiao Tung University System and method for estimating construction duration
CN105184505A (en) * 2015-09-24 2015-12-23 武汉英思工程科技股份有限公司 Digital management method and system used for water conservancy and hydropower engineering construction process
CN105354653A (en) * 2015-08-26 2016-02-24 吕曼 Intelligent management system for engineering construction project
CN106022979A (en) * 2016-05-13 2016-10-12 郑州双杰科技股份有限公司 BIM-based water conservancy and hydropower project management cloud platform and application method thereof

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20130335413A1 (en) * 2012-06-13 2013-12-19 National Chiao Tung University System and method for estimating construction duration
CN105354653A (en) * 2015-08-26 2016-02-24 吕曼 Intelligent management system for engineering construction project
CN105184505A (en) * 2015-09-24 2015-12-23 武汉英思工程科技股份有限公司 Digital management method and system used for water conservancy and hydropower engineering construction process
CN106022979A (en) * 2016-05-13 2016-10-12 郑州双杰科技股份有限公司 BIM-based water conservancy and hydropower project management cloud platform and application method thereof

Non-Patent Citations (6)

* Cited by examiner, † Cited by third party
Title
XUE LI 等: "Research on Construction Schedule Management Based on BIM Technology", 《PROCEDIA ENGINEERING》 *
崔晓润: "建设工程全生命期BIM 研究与应用", 《居业》 *
*** 等: "BIM技术在邢汾高速公路工程建设中的研究和应用", 《施工技术》 *
林伟 等: "BIM 在小南海水电站施工组织设计中的应用", 《水电与新能源》 *
蔺志刚 等: "凯乐塔水电站BIM技术应用", 《土木建筑工程信息技术》 *
金睿: "《建筑施工企业BIM应用基础教程》", 31 May 2016, 浙江工商大学出版社 *

Cited By (14)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108537877A (en) * 2018-03-07 2018-09-14 北京中科紫宸睿达科技有限公司 Visualizing monitor interface customizing generation method based on threedimensional model and device
CN108536984A (en) * 2018-04-19 2018-09-14 广东电网有限责任公司 A kind of information infrastructure intermediate item progress three-dimensional visualization method
CN109271701B (en) * 2018-09-11 2023-05-12 中国铁路设计集团有限公司 Water supply and drainage BIM forward design method based on reach system
CN109271701A (en) * 2018-09-11 2019-01-25 中国铁路设计集团有限公司 A kind of water supply and drainage BIM forward design method based on up to cable system
CN109377066A (en) * 2018-10-31 2019-02-22 广西路桥工程集团有限公司 A kind of live Schedule monitoring system and method based on threedimensional model
CN109472104A (en) * 2018-11-21 2019-03-15 国网河北省电力有限公司建设公司 A kind of 500KV substation VR Construction simulation method and device
CN110119565A (en) * 2019-05-08 2019-08-13 中铁八局集团建筑工程有限公司 A method of quick association and displaying based on BIM model and project programme
CN110852696A (en) * 2019-10-08 2020-02-28 上海建工五建集团有限公司 Project progress monitoring method and system
CN113095609A (en) * 2019-12-23 2021-07-09 北京博超时代软件有限公司 Risk prompt previewing method, device and equipment
CN112785046A (en) * 2021-01-05 2021-05-11 上海海事大学 Multisource hydraulic engineering image information system
CN112818459A (en) * 2021-03-12 2021-05-18 黄河勘测规划设计研究院有限公司 BIM and Gantt chart-based visual progress management method for engineering construction period
CN113158317A (en) * 2021-05-11 2021-07-23 温州广信工程管理有限公司 Civil engineering virtual model and modeling method
CN113778438A (en) * 2021-08-04 2021-12-10 中国二十冶集团有限公司 Progress plan construction method based on engineering management and control platform
CN113450358A (en) * 2021-09-01 2021-09-28 国能大渡河大数据服务有限公司 Progress control method and system for hydropower basin step development and construction

Similar Documents

Publication Publication Date Title
CN107273640A (en) Hydraulic and Hydro-Power Engineering Schedule monitoring method based on three-dimensional digital model
CN107818198A (en) A kind of science of bridge building management platform based on BIM technology
CN101739478B (en) Spacecraft assembly simulation technique-based virtual assembly system and virtual assembly method
CN110210097B (en) Metal roof optimized construction method based on BIM technology
CN105117573B (en) Auto hydraulic model building method based on CAD drainage pipeline networks drawing informations
CN106803150A (en) Municipal Engineering Construction progress msg management method and system based on BIM
CN104778753B (en) The three-dimensional modeling implementation method of bridge reinforcement
CN106372293A (en) Three-dimensional reference line-based BIM creation method for building
CN102034152A (en) SOA (Service Oriented Architecture) based heterogeneous software system data integration method and system
CN107516161A (en) A kind of project progress management-control method based on BIM
CN110990914A (en) BIM technology-based large boiler installation method
CN113536421A (en) BIM-based port planning collaborative analysis method and system
CN111105080A (en) Construction progress prediction method and system based on BIM (building information modeling)
CN109446372A (en) The schema differences control methods in Process in Cooperative Design based on BIM model
CN101009001B (en) Method and system for implementing four-dimensional visualization of engineering model
CN107808414A (en) A kind of virtual foundation ditch excavation method of above and below ground three-dimensional integratedization
CN105243237A (en) Assembly technology structure tree and building method thereof
CN109740245A (en) A kind of application method in the prefabricated middle BIM technology of bar desk Combinatorial resolution
CN117035700A (en) BIM-based hydraulic and hydroelectric engineering forward collaborative design method
Li Brief analysis of the application and limitation of BIM in project life cycle management
CN108846220A (en) A kind of visualization building illumination design method and its system
CN105259783A (en) Visual preview system for water-and-power engineering construction process
Mosad Ibrahim et al. The effect of using building information modeling system at design phase to create high-efficiency projects
Peng et al. Research on the influence of BIM technology on engineering project management and its development countermeasures in the New Period
Wu Application of BIM+ big data in the whole life cycle of engineering project

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20171020

RJ01 Rejection of invention patent application after publication