CN107273640A - Hydraulic and Hydro-Power Engineering Schedule monitoring method based on three-dimensional digital model - Google Patents
Hydraulic and Hydro-Power Engineering Schedule monitoring method based on three-dimensional digital model Download PDFInfo
- Publication number
- CN107273640A CN107273640A CN201710559978.5A CN201710559978A CN107273640A CN 107273640 A CN107273640 A CN 107273640A CN 201710559978 A CN201710559978 A CN 201710559978A CN 107273640 A CN107273640 A CN 107273640A
- Authority
- CN
- China
- Prior art keywords
- model
- progress
- construction
- data
- hydraulic
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 238000000034 method Methods 0.000 title claims abstract description 26
- 238000012544 monitoring process Methods 0.000 title claims abstract description 20
- 238000013461 design Methods 0.000 claims abstract description 20
- 238000011161 development Methods 0.000 claims abstract description 13
- 238000004458 analytical method Methods 0.000 claims abstract description 7
- 238000005192 partition Methods 0.000 claims abstract description 4
- 238000010276 construction Methods 0.000 claims description 30
- 230000000007 visual effect Effects 0.000 claims description 13
- 230000002159 abnormal effect Effects 0.000 claims description 9
- 230000003111 delayed effect Effects 0.000 claims description 8
- 238000005516 engineering process Methods 0.000 claims description 6
- 230000008569 process Effects 0.000 claims description 5
- 239000003086 colorant Substances 0.000 claims description 4
- 238000012905 input function Methods 0.000 claims description 3
- 230000003993 interaction Effects 0.000 claims description 3
- 230000004048 modification Effects 0.000 claims description 3
- 238000012986 modification Methods 0.000 claims description 3
- 238000004088 simulation Methods 0.000 claims description 3
- 238000012800 visualization Methods 0.000 claims description 3
- 230000003442 weekly effect Effects 0.000 claims description 3
- 230000018109 developmental process Effects 0.000 description 10
- 238000007726 management method Methods 0.000 description 7
- 230000002452 interceptive effect Effects 0.000 description 3
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 description 3
- 230000008859 change Effects 0.000 description 2
- 238000005457 optimization Methods 0.000 description 2
- 230000004075 alteration Effects 0.000 description 1
- 230000008901 benefit Effects 0.000 description 1
- 230000007547 defect Effects 0.000 description 1
- 230000001934 delay Effects 0.000 description 1
- 238000004870 electrical engineering Methods 0.000 description 1
- 230000010354 integration Effects 0.000 description 1
- 230000009916 joint effect Effects 0.000 description 1
- 230000008520 organization Effects 0.000 description 1
- 238000007639 printing Methods 0.000 description 1
Classifications
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06F—ELECTRIC DIGITAL DATA PROCESSING
- G06F30/00—Computer-aided design [CAD]
- G06F30/10—Geometric CAD
- G06F30/13—Architectural design, e.g. computer-aided architectural design [CAAD] related to design of buildings, bridges, landscapes, production plants or roads
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q50/00—Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
- G06Q50/06—Energy or water supply
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06T—IMAGE DATA PROCESSING OR GENERATION, IN GENERAL
- G06T17/00—Three dimensional [3D] modelling, e.g. data description of 3D objects
Landscapes
- Engineering & Computer Science (AREA)
- Physics & Mathematics (AREA)
- Geometry (AREA)
- General Physics & Mathematics (AREA)
- Theoretical Computer Science (AREA)
- Business, Economics & Management (AREA)
- Computer Hardware Design (AREA)
- Economics (AREA)
- Health & Medical Sciences (AREA)
- Pure & Applied Mathematics (AREA)
- Public Health (AREA)
- Computational Mathematics (AREA)
- Mathematical Analysis (AREA)
- Mathematical Optimization (AREA)
- Civil Engineering (AREA)
- Evolutionary Computation (AREA)
- General Engineering & Computer Science (AREA)
- Architecture (AREA)
- Software Systems (AREA)
- Computer Graphics (AREA)
- Structural Engineering (AREA)
- Water Supply & Treatment (AREA)
- General Health & Medical Sciences (AREA)
- Human Resources & Organizations (AREA)
- Marketing (AREA)
- Primary Health Care (AREA)
- Strategic Management (AREA)
- Tourism & Hospitality (AREA)
- General Business, Economics & Management (AREA)
- Management, Administration, Business Operations System, And Electronic Commerce (AREA)
Abstract
The invention discloses a kind of Hydraulic and Hydro-Power Engineering Schedule monitoring method based on three-dimensional digital model, one, modeling:Read the two-dimentional drawing of hydraulic engineering or directly carry out Hydraulic Engineering Design, the establishment of model is carried out using CATIA Three-dimensional Design Softwares, modeling detail is more than LOD300;2nd, progress model partition:According to schedule, project demands and project characteristic, the first step is designed a model and is divided into progress model, the title to each progress model customizes specific identifier, and the progress model name after division is divided into two parts:Unique identifier and numeral;3rd, the progress model name after all divisions is set up into other fields afterwards as major key write into Databasce;4th, secondary development is carried out to Catia Composer Player, so that the need for meeting the typing of BIM progresses, deviation contrast, lags analysis and virtual construction function.
Description
Technical field
The present invention relates to Hydraulic and Hydro-Power Engineering Schedule monitoring method, more particularly, to the water conservancy water based on three-dimensional digital model
Electrical engineering Schedule monitoring method.
Background technology
At present, Hydraulic and Hydro-Power Engineering(Road, tunnel, diversion tunnel, vertical shaft, inclined shaft, dam, sluice, factory building, spillway)Enter
Spend that monitoring management is still not fine enough, though there is more ripe progress control method to support, but often occur that progress is delayed, work
The situation of phase delay, by researching and analysing, following defect is primarily present in current Hydraulic and Hydro-Power Engineering progress control method:
First, construction program is excessively rigid, lacks optimization.It is main at present to use gunter drawing, network planning technique, with reference to
Project, P3 Project Management Software carry out construction program formulation, management.Progress monitoring is carried out with such schedule,
It is simply simple that the calculating duration is overlapped according to mechanical efficiency, when there is design alteration or execution conditions change, because
Schedule lacks flexibility, to optimize and adjust very difficult, particularly when working sources, which exist, to be disturbed, it is difficult to calculate
Duration, this just causes actual progress with planning far from each other, also implies that progress monitoring loses meaning.
Second, factors joint effect project progress, progress control work is difficult to exhaustive.With economy and engineering
The development of technology, project scale extension, complexity increase, it is desirable to which manager, which takes into full account, various may influence project progress
Factor.The combined influence of various factors, the progress that directly results in controls ineffective, duration under-reserve in advance, manages without normal plane face
All arrive, the duration delays.
3rd, engineering participant is numerous, and on-site coordination workload is big.The characteristics of engineering project versatility, determines that needs are more
Side participates in cooperation and completed.Respectively the side of taking part in building will also actively coordinate other participants except to carry out the construction task of itself team
Work.Integrate insufficient, ineffecitive coordination and directly result in duration extension.For example, each subpackage unit that there is procedure connection coordinates not
Power causes process portion to carry out in time;Construction section divides unreasonable, cross construction poor organization etc..
4th, progress, quality, the big management objectives of cost three are mutually restricted, it is difficult to balanced.In work progress, project pipe
Manage three big targets to connect each other and mutually restriction, either objective changes, and will all cause remaining two big target to change.
Working to tight deadlines means to increase cost, and the balanced degree of three decides the realization of project objective.In progress control of today, because
Lack advanced technology and theories integration, it is difficult to optimization three big targets of balance.
The content of the invention
Present invention aims at provide a kind of Hydraulic and Hydro-Power Engineering Schedule monitoring method based on three-dimensional digital model.
To achieve the above object, the present invention takes following technical proposals:
Hydraulic and Hydro-Power Engineering Schedule monitoring method of the present invention based on three-dimensional digital model, with CATIA(French Da Suo companies
A design software)Three-dimensional Design Software is carrier, and establishment designs a model, special according to the construction program and project
Point, is divided into progress model by described design a model, carries out as steps described below:
The first step, modeling:Read the two-dimentional drawing of hydraulic engineering or directly carry out Hydraulic Engineering Design, utilize CATIA three dimensional designs
Software carries out the establishment of model, in modeling process, is modeled using parametrization and templating, is easy to the modification of late design, builds
Mould detail is more than LOD(Model fineness)300;
Second step, progress model partition:According to schedule, project demands and project characteristic, designing a model for the first step is drawn
It is divided into progress model, the title to each progress model customizes specific identifier, the progress model name point after division
For two parts:Unique identifier and numeral, are easy to distinguish each progress model;
3rd step, using the progress model name after all divisions as major key write into Databasce, other fields are set up afterwards,
Other fields include plan engineering time, practice of construction time, sequence of construction, construction technology, pile No. or elevation, quality letter
Breath, security information, exception record;
4th step, to Catia Composer Player(A displaying software of French Da Suo companies)Secondary development is carried out, its
Corresponding ComposerPlayerActiveX(The plug-in unit of French a displaying software of Da Suo companies), broken away from CATIA designs flat
Platform and Catia Composer Player display platforms, you can independent to carry out Embedded exploitation, and with API(Using journey
Sequence DLL)Interface, with Microsoft Visual Studio(The development kit series of products of MS)Open
Send out platform and network data base Sql Server(The Relational DBMS that MS releases)With reference to, so that
Meet BIM(English Building Information Modeling abbreviation;BIM)Progress typing, deviation pair
The need for, lags analysis and virtual construction function.
The BIM functions are:Utilize the select in Sql Server databases(Selection)Sentence transfers major key " model name
The related BIM integrated information data of title ", show in the interaction of visual platform;
The progress input function is:Utilize the update in Sql Server databases(Update)Sentence updates newest reality
Progress data, while updating the color of correlation model in visualization engine, realizes visual monitoring;Major key " model name "
Corresponded with plan in database and practice of construction time field, be intended to write respective field, meter with actual progress data
Typing can be shifted to an earlier date by drawing progress data, and actual progress data are filled in work progress according to progress data daily or weekly;
The schedule variance is contrasted:Qualified Model Name field in the database is read, first in database
The model name of normal construction is read, condition is that actual progress data are not empty, is blueness by these model definitions;Secondly read
The advanced model name of progress, condition is that actual progress data are not empty, and target advance is more than the current date, by these moulds
Type is defined as green;The last delayed model name of Load Game, condition is that actual progress data are empty, and target advance is less than
These model definitions are red by the current date;Different colors represents different states;
The progress lags analysis function is:In typing actual progress, if any progress abnormal conditions, corresponding model is selected,
In the text box that these abnormal conditions write-in programs are provided, automatically write database after submission, and to related building word
Duan Guanlian;If delayed, the abnormal conditions submitted before the building, reading are clicked on, show that the building hysteresis reason is arranged
Table, according to these hysteresis reasons, is referred to for construction manager, formulates corresponding measure of overworking;
The virtual construction function is:According to existing target advance data or actual progress data, Microsoft is utilized
Visual Studio timer(Timer)Control, regards progress model as discrete event by certain cycle and gradually shows it
Show to come;According to the building course of the construction plan simulation reality of engineering project, found under virtual environment in work progress
The problem of there may be and risk, and the progress model and plan are adjusted and changed for problem, and then Optimizing construction
Plan.
Advantage of the present invention is mainly reflected in:
1st, 4D of the Hydraulic and Hydro-Power Engineering field based on three-dimensional digital result of design is proposed(It is four-dimensional:Space coordinate X, Y, Z are timely
Between coordinate T)Schedule monitoring method, this method can be with cutting arbitrary section, and BIM information associations such as model and two-dimentional drawing, just
Understand design idea in user.
2nd, progress and actual progress typing network data base are intended in Hydraulic and Hydro-Power Engineering field, is joined with data and model
Conjunction is checked, realizes the contrast of schedule variance.
3rd, the interactive inquiry of virtual construction and other data is realized using man-machine interactive data inputting.
4th, Catia Composer Player work as water conservancy and hydropower as the main development platform and display platform of this method
Project progress need not re-create model when changing, and can greatly save the time and save rework cost, and it can pass through
3D animations and establishment interactive product document preferably pass on product information;Catia Composer Player secondary development is
Extension to its software function, can need to carry out customizing functions according to project characteristic or owner.
Brief description of the drawings
Fig. 1 is the monitoring method structural representation set up according to the inventive method.
Embodiment
Embodiments of the invention are elaborated below in conjunction with the accompanying drawings, the present embodiment using technical solution of the present invention before
Put and implemented, give detailed embodiment and specific operating process, but protection scope of the present invention is not limited to down
State embodiment.
As shown in figure 1, the Hydraulic and Hydro-Power Engineering Schedule monitoring method of the present invention based on three-dimensional digital model, with
CATIA(A design software of French Da Suo companies)Three-dimensional Design Software is carrier, and establishment designs a model, according to the engineering
Schedule and project characteristic, are divided into progress model by described design a model, implement and carry out as steps described below:
The first step, modeling:Read the two-dimentional drawing of hydraulic engineering or directly carry out Hydraulic Engineering Design, utilize CATIA three dimensional designs
Software carries out the establishment of model, in modeling process, is modeled using parametrization and templating, is easy to the modification of late design, builds
Mould detail is more than LOD(Model fineness)300;
Second step, progress model partition:According to schedule, project demands and project characteristic, designing a model for the first step is drawn
It is divided into progress model, the title to each progress model customizes specific identifier, the progress model name point after division
For two parts:Unique identifier and numeral, are easy to distinguish each progress model;
3rd step, using the progress model name after all divisions as major key write into Databasce, other fields are set up afterwards,
Other fields include plan engineering time, practice of construction time, sequence of construction, construction technology, pile No. or elevation, quality letter
Breath, security information, exception record etc.;
4th step, to Catia Composer Player(A displaying software of French Da Suo companies)Secondary development is carried out, its
Corresponding ComposerPlayerActiveX(The plug-in unit of French a displaying software of Da Suo companies), broken away from CATIA designs flat
Platform and Catia Composer Player display platforms, you can independent to carry out Embedded exploitation, and with API(Using journey
Sequence DLL)Interface, with Microsoft Visual Studio(The development kit series of products of MS)Open
Send out platform and network data base Sql Server(The Relational DBMS that MS releases)With reference to, so that
Meet BIM(English Building Information Modeling abbreviation;BIM)Progress typing, deviation pair
The need for the functions such as, lags analysis and virtual construction.
The BIM functions are:Utilize the select in Sql Server databases(Selection)Sentence transfers major key " model name
The related BIM integrated information data of title ", show in the interaction of visual platform;
The progress input function is:Utilize the update in Sql Server databases(Update)Sentence updates newest reality
Progress data, while updating the color of correlation model in visualization engine, realizes visual monitoring;Major key " model name "
Corresponded with plan in database and practice of construction time field, be intended to write respective field, meter with actual progress data
Typing can be shifted to an earlier date by drawing progress data, and actual progress data are filled in work progress according to progress data daily or weekly;
The schedule variance is contrasted:Qualified Model Name field in the database is read, first in database
The model name of normal construction is read, condition is that actual progress data are not empty, is blueness by these model definitions;Secondly read
The advanced model name of progress, condition is that actual progress data are not empty, and target advance is more than the current date, by these moulds
Type is defined as green;The last delayed model name of Load Game, condition is that actual progress data are empty, and target advance is less than
These model definitions are red by the current date;Different colors represents different states;
The progress lags analysis function is:In typing actual progress, if any progress abnormal conditions, corresponding model is selected,
In the text box that these abnormal conditions write-in programs are provided, automatically write database after submission, and to related building word
Duan Guanlian;If delayed, the abnormal conditions submitted before the building, reading are clicked on, show that the building hysteresis reason is arranged
Table, according to these hysteresis reasons, is referred to for construction manager, formulates corresponding measure of overworking;
The virtual construction function is:According to existing target advance data or actual progress data, Microsoft is utilized
Visual Studio timer(Timer)Control, regards progress model as discrete event by certain cycle and gradually shows it
Show to come;According to the building course of the construction plan simulation reality of engineering project, found under virtual environment in work progress
The problem of there may be and risk, and the progress model and plan are adjusted and changed for problem, and then Optimizing construction
Plan.
The present invention can be combined with information management system:In the management of engineering construction of modernization, the construction stage is often
Engineering information management system can be carried out, these systems include substantial amounts of file and data, including quality, progress, safety, investment etc.
Deng being linked up in initial stage of development and Development of Management Information System person, how framework database is so as to preferably used in other systems.
In 4D Schedule monitoring methods, model is combined with these files or data, along with foregoing BIM functions, you can shape
Into 4D BIM models, engineering forms electronic document after terminating and consigns to owner.
The present invention can also develop other miscellaneous functions;After major function has been developed, carry out other functional developments with
Aid in the realization of major function, including user right, hiding/display, placed in the middle, printing, view, video playback, the quick dish of right button
It is single etc..These functions are also based on API the and Microsoft Visual of Catia Composer Player openings
Studio basic control is developed jointly.
To the 4D(It is four-dimensional:Space coordinate X, Y, Z and time coordinate T)The explanation of Schedule monitoring:
Assuming that certain is building the main building thing arched concrete dam of Hydraulic and Hydro-Power Engineering, crest elevation 1265m is designed, up to now,
It should construct according to plan to 1230m, practice of construction to 1226m, then can intuitively be looked on threedimensional model using this method
Ask target advance up to now(Only show the model of below 1230m elevations), actual progress(Only display below 1226m is high
The model of journey)And schedule variance(1226m represents delayed model to 1230m elevations with other colors)Etc. information.
Claims (2)
1. a kind of Hydraulic and Hydro-Power Engineering Schedule monitoring method based on three-dimensional digital model, using CATIA Three-dimensional Design Softwares as load
Body, establishment is designed a model, and according to the construction program and project characteristic, described design a model is divided into progress model,
Carry out as steps described below:
The first step, modeling:Read the two-dimentional drawing of hydraulic engineering or directly carry out Hydraulic Engineering Design, utilize CATIA three dimensional designs
Software carries out the establishment of model, in modeling process, is modeled using parametrization and templating, is easy to the modification of late design, builds
Mould detail is more than LOD300;
Second step, progress model partition:According to schedule, project demands and project characteristic, designing a model for the first step is drawn
It is divided into progress model, the title to each progress model customizes specific identifier, the progress model name point after division
For two parts:Unique identifier and numeral, are easy to distinguish each progress model;
3rd step, using the progress model name after all divisions as major key write into Databasce, other fields are set up afterwards,
Other fields include plan engineering time, practice of construction time, sequence of construction, construction technology, pile No. or elevation, quality letter
Breath, security information, exception record;
4th step, to Catia Composer Player carry out secondary development, its corresponding ComposerPlayerActiveX,
Break away from CATIA design platforms and Catia Composer Player display platforms, you can independent to carry out Embedded exploitation,
And with api interface, combined with Microsoft Visual Studio development platforms and network data base Sql Server,
The need for meeting the typing of BIM progresses, deviation contrast, lags analysis and virtual construction function.
2. the Hydraulic and Hydro-Power Engineering Schedule monitoring method based on three-dimensional digital model according to claim 1, it is characterised in that:
The BIM functions are:Major key " model name " correlation is transferred using the select sentences in Sql Server databases
BIM integrated information data, show in the interaction of visual platform;
The progress input function is:Newest actual progress number is updated using the update sentences in Sql Server databases
According to, at the same in visualization engine update correlation model color, realize visual monitoring;Major key " model name " and data
Plan and practice of construction time field are corresponded in storehouse, are intended to write respective field, target advance with actual progress data
Data can shift to an earlier date typing, and actual progress data are filled in work progress according to progress data daily or weekly;
The schedule variance is contrasted:Qualified Model Name field in the database is read, first in database
The model name of normal construction is read, condition is that actual progress data are not empty, is blueness by these model definitions;Secondly read
The advanced model name of progress, condition is that actual progress data are not empty, and target advance is more than the current date, by these moulds
Type is defined as green;The last delayed model name of Load Game, condition is that actual progress data are empty, and target advance is less than
These model definitions are red by the current date;Different colors represents different states;
The progress lags analysis function is:In typing actual progress, if any progress abnormal conditions, corresponding model is selected,
In the text box that these abnormal conditions write-in programs are provided, automatically write database after submission, and to related building word
Duan Guanlian;If delayed, the abnormal conditions submitted before the building, reading are clicked on, show that the building hysteresis reason is arranged
Table, according to these hysteresis reasons, is referred to for construction manager, formulates corresponding measure of overworking;
The virtual construction function is:According to existing target advance data or actual progress data, Microsoft is utilized
Visual Studio timer controls, regard progress model as discrete event by certain cycle and gradually show it;
According to the building course of the construction plan simulation reality of engineering project, find to there may be in work progress under virtual environment
The problem of and risk, and the progress model and plan are adjusted and changed for problem, and then Optimizing construction plan.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710559978.5A CN107273640A (en) | 2017-07-11 | 2017-07-11 | Hydraulic and Hydro-Power Engineering Schedule monitoring method based on three-dimensional digital model |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710559978.5A CN107273640A (en) | 2017-07-11 | 2017-07-11 | Hydraulic and Hydro-Power Engineering Schedule monitoring method based on three-dimensional digital model |
Publications (1)
Publication Number | Publication Date |
---|---|
CN107273640A true CN107273640A (en) | 2017-10-20 |
Family
ID=60071864
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201710559978.5A Pending CN107273640A (en) | 2017-07-11 | 2017-07-11 | Hydraulic and Hydro-Power Engineering Schedule monitoring method based on three-dimensional digital model |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN107273640A (en) |
Cited By (13)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108537877A (en) * | 2018-03-07 | 2018-09-14 | 北京中科紫宸睿达科技有限公司 | Visualizing monitor interface customizing generation method based on threedimensional model and device |
CN108536984A (en) * | 2018-04-19 | 2018-09-14 | 广东电网有限责任公司 | A kind of information infrastructure intermediate item progress three-dimensional visualization method |
CN109271701A (en) * | 2018-09-11 | 2019-01-25 | 中国铁路设计集团有限公司 | A kind of water supply and drainage BIM forward design method based on up to cable system |
CN109377066A (en) * | 2018-10-31 | 2019-02-22 | 广西路桥工程集团有限公司 | A kind of live Schedule monitoring system and method based on threedimensional model |
CN109472104A (en) * | 2018-11-21 | 2019-03-15 | 国网河北省电力有限公司建设公司 | A kind of 500KV substation VR Construction simulation method and device |
CN110119565A (en) * | 2019-05-08 | 2019-08-13 | 中铁八局集团建筑工程有限公司 | A method of quick association and displaying based on BIM model and project programme |
CN110852696A (en) * | 2019-10-08 | 2020-02-28 | 上海建工五建集团有限公司 | Project progress monitoring method and system |
CN112785046A (en) * | 2021-01-05 | 2021-05-11 | 上海海事大学 | Multisource hydraulic engineering image information system |
CN112818459A (en) * | 2021-03-12 | 2021-05-18 | 黄河勘测规划设计研究院有限公司 | BIM and Gantt chart-based visual progress management method for engineering construction period |
CN113095609A (en) * | 2019-12-23 | 2021-07-09 | 北京博超时代软件有限公司 | Risk prompt previewing method, device and equipment |
CN113158317A (en) * | 2021-05-11 | 2021-07-23 | 温州广信工程管理有限公司 | Civil engineering virtual model and modeling method |
CN113450358A (en) * | 2021-09-01 | 2021-09-28 | 国能大渡河大数据服务有限公司 | Progress control method and system for hydropower basin step development and construction |
CN113778438A (en) * | 2021-08-04 | 2021-12-10 | 中国二十冶集团有限公司 | Progress plan construction method based on engineering management and control platform |
Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US20130335413A1 (en) * | 2012-06-13 | 2013-12-19 | National Chiao Tung University | System and method for estimating construction duration |
CN105184505A (en) * | 2015-09-24 | 2015-12-23 | 武汉英思工程科技股份有限公司 | Digital management method and system used for water conservancy and hydropower engineering construction process |
CN105354653A (en) * | 2015-08-26 | 2016-02-24 | 吕曼 | Intelligent management system for engineering construction project |
CN106022979A (en) * | 2016-05-13 | 2016-10-12 | 郑州双杰科技股份有限公司 | BIM-based water conservancy and hydropower project management cloud platform and application method thereof |
-
2017
- 2017-07-11 CN CN201710559978.5A patent/CN107273640A/en active Pending
Patent Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US20130335413A1 (en) * | 2012-06-13 | 2013-12-19 | National Chiao Tung University | System and method for estimating construction duration |
CN105354653A (en) * | 2015-08-26 | 2016-02-24 | 吕曼 | Intelligent management system for engineering construction project |
CN105184505A (en) * | 2015-09-24 | 2015-12-23 | 武汉英思工程科技股份有限公司 | Digital management method and system used for water conservancy and hydropower engineering construction process |
CN106022979A (en) * | 2016-05-13 | 2016-10-12 | 郑州双杰科技股份有限公司 | BIM-based water conservancy and hydropower project management cloud platform and application method thereof |
Non-Patent Citations (6)
Title |
---|
XUE LI 等: "Research on Construction Schedule Management Based on BIM Technology", 《PROCEDIA ENGINEERING》 * |
崔晓润: "建设工程全生命期BIM 研究与应用", 《居业》 * |
*** 等: "BIM技术在邢汾高速公路工程建设中的研究和应用", 《施工技术》 * |
林伟 等: "BIM 在小南海水电站施工组织设计中的应用", 《水电与新能源》 * |
蔺志刚 等: "凯乐塔水电站BIM技术应用", 《土木建筑工程信息技术》 * |
金睿: "《建筑施工企业BIM应用基础教程》", 31 May 2016, 浙江工商大学出版社 * |
Cited By (14)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108537877A (en) * | 2018-03-07 | 2018-09-14 | 北京中科紫宸睿达科技有限公司 | Visualizing monitor interface customizing generation method based on threedimensional model and device |
CN108536984A (en) * | 2018-04-19 | 2018-09-14 | 广东电网有限责任公司 | A kind of information infrastructure intermediate item progress three-dimensional visualization method |
CN109271701B (en) * | 2018-09-11 | 2023-05-12 | 中国铁路设计集团有限公司 | Water supply and drainage BIM forward design method based on reach system |
CN109271701A (en) * | 2018-09-11 | 2019-01-25 | 中国铁路设计集团有限公司 | A kind of water supply and drainage BIM forward design method based on up to cable system |
CN109377066A (en) * | 2018-10-31 | 2019-02-22 | 广西路桥工程集团有限公司 | A kind of live Schedule monitoring system and method based on threedimensional model |
CN109472104A (en) * | 2018-11-21 | 2019-03-15 | 国网河北省电力有限公司建设公司 | A kind of 500KV substation VR Construction simulation method and device |
CN110119565A (en) * | 2019-05-08 | 2019-08-13 | 中铁八局集团建筑工程有限公司 | A method of quick association and displaying based on BIM model and project programme |
CN110852696A (en) * | 2019-10-08 | 2020-02-28 | 上海建工五建集团有限公司 | Project progress monitoring method and system |
CN113095609A (en) * | 2019-12-23 | 2021-07-09 | 北京博超时代软件有限公司 | Risk prompt previewing method, device and equipment |
CN112785046A (en) * | 2021-01-05 | 2021-05-11 | 上海海事大学 | Multisource hydraulic engineering image information system |
CN112818459A (en) * | 2021-03-12 | 2021-05-18 | 黄河勘测规划设计研究院有限公司 | BIM and Gantt chart-based visual progress management method for engineering construction period |
CN113158317A (en) * | 2021-05-11 | 2021-07-23 | 温州广信工程管理有限公司 | Civil engineering virtual model and modeling method |
CN113778438A (en) * | 2021-08-04 | 2021-12-10 | 中国二十冶集团有限公司 | Progress plan construction method based on engineering management and control platform |
CN113450358A (en) * | 2021-09-01 | 2021-09-28 | 国能大渡河大数据服务有限公司 | Progress control method and system for hydropower basin step development and construction |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN107273640A (en) | Hydraulic and Hydro-Power Engineering Schedule monitoring method based on three-dimensional digital model | |
CN107818198A (en) | A kind of science of bridge building management platform based on BIM technology | |
CN101739478B (en) | Spacecraft assembly simulation technique-based virtual assembly system and virtual assembly method | |
CN110210097B (en) | Metal roof optimized construction method based on BIM technology | |
CN105117573B (en) | Auto hydraulic model building method based on CAD drainage pipeline networks drawing informations | |
CN106803150A (en) | Municipal Engineering Construction progress msg management method and system based on BIM | |
CN104778753B (en) | The three-dimensional modeling implementation method of bridge reinforcement | |
CN106372293A (en) | Three-dimensional reference line-based BIM creation method for building | |
CN102034152A (en) | SOA (Service Oriented Architecture) based heterogeneous software system data integration method and system | |
CN107516161A (en) | A kind of project progress management-control method based on BIM | |
CN110990914A (en) | BIM technology-based large boiler installation method | |
CN113536421A (en) | BIM-based port planning collaborative analysis method and system | |
CN111105080A (en) | Construction progress prediction method and system based on BIM (building information modeling) | |
CN109446372A (en) | The schema differences control methods in Process in Cooperative Design based on BIM model | |
CN101009001B (en) | Method and system for implementing four-dimensional visualization of engineering model | |
CN107808414A (en) | A kind of virtual foundation ditch excavation method of above and below ground three-dimensional integratedization | |
CN105243237A (en) | Assembly technology structure tree and building method thereof | |
CN109740245A (en) | A kind of application method in the prefabricated middle BIM technology of bar desk Combinatorial resolution | |
CN117035700A (en) | BIM-based hydraulic and hydroelectric engineering forward collaborative design method | |
Li | Brief analysis of the application and limitation of BIM in project life cycle management | |
CN108846220A (en) | A kind of visualization building illumination design method and its system | |
CN105259783A (en) | Visual preview system for water-and-power engineering construction process | |
Mosad Ibrahim et al. | The effect of using building information modeling system at design phase to create high-efficiency projects | |
Peng et al. | Research on the influence of BIM technology on engineering project management and its development countermeasures in the New Period | |
Wu | Application of BIM+ big data in the whole life cycle of engineering project |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20171020 |
|