CN107268536A - A kind of fill encloses sea, draining, does not fill to make somebody a mere figurehead and make ground construction process - Google Patents

A kind of fill encloses sea, draining, does not fill to make somebody a mere figurehead and make ground construction process Download PDF

Info

Publication number
CN107268536A
CN107268536A CN201710466766.2A CN201710466766A CN107268536A CN 107268536 A CN107268536 A CN 107268536A CN 201710466766 A CN201710466766 A CN 201710466766A CN 107268536 A CN107268536 A CN 107268536A
Authority
CN
China
Prior art keywords
fill
sea
make
land
draining
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201710466766.2A
Other languages
Chinese (zh)
Inventor
罗朝钦
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201710466766.2A priority Critical patent/CN107268536A/en
Publication of CN107268536A publication Critical patent/CN107268536A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B3/00Engineering works in connection with control or use of streams, rivers, coasts, or other marine sites; Sealings or joints for engineering works in general
    • E02B3/18Reclamation of land from water or marshes
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02ATECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE
    • Y02A10/00TECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE at coastal zones; at river basins

Landscapes

  • Engineering & Computer Science (AREA)
  • General Engineering & Computer Science (AREA)
  • Environmental & Geological Engineering (AREA)
  • Ocean & Marine Engineering (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Investigation Of Foundation Soil And Reinforcement Of Foundation Soil By Compacting Or Drainage (AREA)

Abstract

Sea, draining are enclosed the invention belongs to a kind of fill of building field, does not fill to make somebody a mere figurehead and makes ground construction process, it has advantages below than conventional marine reclamation land method:1st, reduction fills out extra large cost 90% and (is directly proportional to marine reclamation land area, i.e., epeirogenetic area is big, reduces the height of cost, the present invention is with epeirogenetic 10KM2Calculate).2nd, great accelerating construction progress;3rd, the underground space is made full use of;4th, area on the face of land is made full use of;5th, surrounding builds ditch and collects fresh water;6th, the crisis that low island small island country can be delayed to be submerged by sea-level rise.Enclose extra large draining, built on stilts epeirogenetic architectural engineering in the region that the present invention is adapted within coastal shallow sea and islands and reefs 20M depths.

Description

A kind of fill encloses sea, draining, does not fill to make somebody a mere figurehead and make ground construction process
First, the invention belongs to a kind of fill of building field enclose sea, draining, do not fill it is built on stilts make (i.e. epeirogenetic) building side Method.
2nd, state of the art
When current China and world coastal cities and island marine reclamation land construction, generally using two methods:One kind is first Fill out (to the substantial amounts of cubic metre of earth and stone of marine site throwing), then lining cutting fill;Two be the backward interior cubic meter of stone that bankets of first lining cutting fill;Two methods Fill the substantial amounts of cubic metre of earth and stone (the whole spaces for occupying underground) in the marine site that ground will be made to needs.When level land is filled into marine site Afterwards, then on the cubic metre of earth and stone level land filled the basic cubic metre of earth and stone of building, repeated work, increase construction costs and construction work are excavated Phase.
3rd, the purpose of the present invention is:
A kind of safe and reliable, saving great amount of investment is provided, accelerating construction progress makes full use of the underground space, suited measures to local conditions The built on stilts land formed of utilization fill enclose sea, draining, do not fill it is built on stilts make construction process.
4th, concrete technical scheme of the invention is:
1st, sea is enclosed in first fill:Banking material should use reinforced concrete;And should have enough intensity, rigidity and stably Property;Fill must have good water proofing property, can separate the seawater of both sides completely;Height at the top of fill is preferably higher than sea level 5M More than, to prevent wave from rushing to dike face.Sea is enclosed in fill three kinds of forms:Extra large (accompanying drawing 1), island submerged reef four are enclosed in bay one side fill Zhou Zhudi encloses extra large (accompanying drawing 2), is enclosed extra large (accompanying drawing 3) along the face fill of land three;Current invention assumes that to enclose extra large (accompanying drawing along the face fill of land three 3)。
The 2nd, the large-scale pumping station in many places is set on the dykes and dams after fill is closed up, drains fill and encloses sea and close up rear inner side marine site Seawater, makes the marine site form a nonirrigated farmland (construction for being easy to any building).
3rd, enclose on the nonirrigated farmland for draining seawater in extra large scope, be in full swing every building operation by planning and designing in fill;Respectively ± 0.00 ground of item building is preferably highly remained basically stable with fill, i.e., higher than more than sea level 5M.One piece is collectively forming higher than sea More than plane 5M land.Less than ± 0.00 part is all using frame-type frame-shear structure form, and it is empty to form huge underground Between.
5th, it is an advantage of the invention that:
1st, reclamation cost 90% is reduced.
Extra large mode is enclosed by (accompanying drawing 3) to illustrate.
1. state of the art is pressed, that fills 10 square kilometres (1,000 ten thousand square metres are counted 15000 mu) makes ground engineering, averagely Depth is filled by 10 meters of calculating, then needs to fill the billion cubic meter of cubic metre of earth and stone material 1, it is assumed that (quick-fried by yuan/cubic metre of cubic metre of earth and stone material 80 Break, excavate, transport, fill), then need the RMB of the expense of filling 8,000,000,000, i.e., every mu of yuan/mu of cost 53.33 ten thousand, 800 yuan/flat Square rice.
If 2. enclosing sea by the fill of the present invention, the method do not filled out only is enclosed, only embankment construction costs need to be calculated:Embankment overall length 3163 meters × 3 faces (simultaneously by land)=9489 meter, embankment thickness is tentative 6 meters, and height is tentative 10 meters, then embankment concrete consumption:9489 × 6 × 10=569340m3, it is to fill 1/175 (the 1 billion cubic meter ÷ 569340 cubic metres=175.6) for making ground earthwork.
The concrete analysis of prices:569340m3× 1000 yuan/cubic metre (material, machinery, artificial, transport, formwork cost)=5.7 Hundred million yuans.
The reinforcing bar analysis of prices:Reinforcing bar content is calculated by the 0.4% of concrete volume.
Ton/cubic metre=18000 ton of (569340 × 0.4%=2277.36 cubic metres) × 7.85
18000 tons × 9000 yuan/ton (material, machinery, artificial, transport)=1.62 hundred million yuans
Draining cost after embankment:1 billion cubic meter × 0.6 yuan/cubic metre=0.6 hundred million yuans
Embankment, draining total cost:5.7 hundred million+1.6 hundred million+0.6 hundred million=8.0 hundred million yuans
It is original 8/80=1/10. for filling out extra large cubic metre of earth and stone method cost
Every mu of yuan/mu of cost 5.33 ten thousand is converted into, per yuan/square metre of construction cost per square meter 80.
2nd, speed up the work, shown during by the analysis of prices above, embankment engineering volume is only fill out extra large volume 1/ 175, this just considerably reduces the excavation of material reclamation, transports, fills and (be particularly away from land island and seem more important), pole Big accelerating construction progress, only encloses the foundation excavation do not filled out when reducing all kinds of construction;During the foundation construction of all kinds of buildings It is dry operation, accelerates later stage construction project progress.
3rd, the present invention, which only encloses not filling out, can make full use of the huge space of underground after draining:It is light that lowermost layer can be reservoir stock Water, life, fire cistern sewage disposal etc..Negative one layer can be all kinds of warehouses, garage, subway, highway, air-raid shelter etc..
4th, aboveground area is made full use of:
Can be done along dike can build all kinds of houses, airport, square, street in Steam Ship Wharf, goods yard, highway, dike, carrying out can after soil Do garden and farmland.
5th, fresh water is collected:Surrounding builds collecting gutter and collects rainwater (fresh water) deposit groundwater reservoir, and the army and the people's production is solved after purification Domestic water, the island for being particularly away from land seem to be still important, and 10 square kilometres of collective areas collect fresh water (with Hainan Exemplified by province) 1800 ten thousand steres, it is available for 400,000 people's domestic waters of 1 year.
6th, the built on stilts epeirogenetic method of the present invention can tackle low altitude area, the national danger flooded by sea-level rise.
6th, illustrate
Fig. 1 is that the built on stilts epeirogenetic floor map in sea is enclosed in bay;Fig. 2 is that the built on stilts epeirogenetic floor map in sea is enclosed in islands and reefs marine site; Fig. 3 is to make ground level schematic diagram by the gusset of land one sea is built on stilts;Fig. 4 is Fig. 3 A-A cut-away views.
Connection with figures is illustrated below:1. it is armored concrete fill in the accompanying drawings, top is higher than more than sea level 5M, Fill should have good intensity, rigidity and stability, and fill separates the seawater of both sides completely;2. it is that inner side is drained after seawater Nonirrigated farmland, can by all kinds of buildings of planning construction basis;3. be marine site and sea level, at the top of the preferably less than fill of sea level 5M with On, to avoid wave from pouring into fill top and land;4. it is nature land, he is basic point and the dependence that sea is enclosed in fill;9. it is seabed Rock 10. on framework or frame-shear structure, to the huge space of with constituting new epeirogenetic below ground, and support on the face of land Any building;10. it is marine rock ground;(11) it is minus two layers of fresh groundwater storehouse;(12) it is collecting gutter, collects day rainfall water It is stored in minus two layers of groundwater reservoir;7. it is negative one layer ground, preferably higher than sea level 1M, negative one layer can make warehouse, garage, people's air defense and ground Lower network of communication lines etc.;6. be overhead framework frame-shear structure 9. on the ground higher than more than sea level 5M, he is high by all kinds of buildings The close ground of degree constitutes new land;5. be build ground 6. on all kinds of buildings.

Claims (3)

1. a kind of fill encloses sea, draining, does not fill to make somebody a mere figurehead and make ground construction process:Shallow sea within coastal and 20 meters of the islands and reefs depth of water Sea is enclosed in region, fill, is drained fill and is enclosed seawater in extra large scope, is allowed to form a nonirrigated farmland, is then maked somebody a mere figurehead at this on nonirrigated farmland Build and form new land.It is characterized in that:Enclose sea by the marine site fill of the built on stilts epeirogenetic of planning, by seawater inside and outside dike completely every It is disconnected;Fill is higher than more than sea level 5M, to prevent wave to swarm dike face;Then on the seabed nonirrigated farmland for draining seawater, from basis Start to build all kinds of buildings using framework or frame-shear structure, make ± 0.00 to be higher than more than sea level 5M, ± 0.00 below ground Form a huge underground space.Make the armored concrete ground of owned building close, and higher than more than sea level 5M, and Form new land.
2. according to claim 1 make somebody a mere figurehead makes ground construction process, it is characterized in that making full use of the underground space on new epeirogenetic ground: Minus two layers are made fresh water reservoir, and negative one layer can make warehouse, people's air defense, traffic etc.;Higher than land more than sea level 5M, harbour, machine can be made The various uses such as field, house, farmland.
3. newly making the method that built on stilts land is higher than more than sea level 5M according to claim 1, reply low altitude area island can be continued The danger that small island, area, country are submerged by sea-level rise.
CN201710466766.2A 2017-06-15 2017-06-15 A kind of fill encloses sea, draining, does not fill to make somebody a mere figurehead and make ground construction process Pending CN107268536A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710466766.2A CN107268536A (en) 2017-06-15 2017-06-15 A kind of fill encloses sea, draining, does not fill to make somebody a mere figurehead and make ground construction process

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710466766.2A CN107268536A (en) 2017-06-15 2017-06-15 A kind of fill encloses sea, draining, does not fill to make somebody a mere figurehead and make ground construction process

Publications (1)

Publication Number Publication Date
CN107268536A true CN107268536A (en) 2017-10-20

Family

ID=60069097

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710466766.2A Pending CN107268536A (en) 2017-06-15 2017-06-15 A kind of fill encloses sea, draining, does not fill to make somebody a mere figurehead and make ground construction process

Country Status (1)

Country Link
CN (1) CN107268536A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109129883A (en) * 2018-10-08 2019-01-04 励土峰 A kind of method for manufacturing for filling out extra large unit
CN110080169A (en) * 2019-04-03 2019-08-02 温州大学 A kind of construction method reclaimed fields from the sea utilized based on basement

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103590370A (en) * 2013-06-09 2014-02-19 罗朝钦 Sea enclosing, draining and land reclaiming construction method
CN103953004A (en) * 2014-05-14 2014-07-30 刘红静 Stepped multilevel sea reclamation method and sea reclamation dams provided with downward insertion caissons
CN106609506A (en) * 2015-10-23 2017-05-03 天津市北斗海洋信息科技有限公司 Method for sea reclamation by using caissons

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103590370A (en) * 2013-06-09 2014-02-19 罗朝钦 Sea enclosing, draining and land reclaiming construction method
CN103953004A (en) * 2014-05-14 2014-07-30 刘红静 Stepped multilevel sea reclamation method and sea reclamation dams provided with downward insertion caissons
CN106609506A (en) * 2015-10-23 2017-05-03 天津市北斗海洋信息科技有限公司 Method for sea reclamation by using caissons

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109129883A (en) * 2018-10-08 2019-01-04 励土峰 A kind of method for manufacturing for filling out extra large unit
CN110080169A (en) * 2019-04-03 2019-08-02 温州大学 A kind of construction method reclaimed fields from the sea utilized based on basement
CN110080169B (en) * 2019-04-03 2020-11-24 温州大学 Construction method for building land by enclosing sea based on basement utilization
US11566390B2 (en) * 2019-04-03 2023-01-31 Wenhou University Construction method of reclaiming land from the sea based on basement utilization

Similar Documents

Publication Publication Date Title
CN102345300A (en) Construction method of underground structures of seacoasts and artificial islands
CN103924602B (en) Deep Thick Soft Ground foundation ditch construction method
CN103147464A (en) Pressure-releasing structure of basement anti-floating plate and construction method thereof
CN108612117A (en) A kind of seabed water-retaining structure across municipal tunnel greatly and construction method
CN104328766A (en) Ecological stone cage net box retaining wall and construction method
CN1948639A (en) Water taking gallery of self flow type for underground reservoir
CN103334452B (en) A kind of underground construction mixed construction method
CN107916646A (en) A kind of rain-flood resources amount of taping the latent power evaluation method
CN101761069B (en) Construction method of three-in-one underground diaphragm wall
CN107268536A (en) A kind of fill encloses sea, draining, does not fill to make somebody a mere figurehead and make ground construction process
CN112411514A (en) Ecological wind-prevention and sand-fixation system for railway protection
CN208266896U (en) A kind of seabed water-retaining structure across municipal tunnel greatly
CN107165640A (en) Tunnels and underground engineering surely builds method certainly
CN208023600U (en) A kind of caisson structure suitable for complex environment
CN203007967U (en) Photovoltaic plant component bracket foundation for plateau Gobi sandy soil regions
CN103590370A (en) Sea enclosing, draining and land reclaiming construction method
CN102561250A (en) Water delivery and storage method and siphon system
CN204238176U (en) Ecotypic Stone Mesh-box net cage barricade
CN107083729A (en) One kind stores permeable module and preparation method thereof
CN103306290A (en) Quick re-freezing and backfilling construction method for foundation ground of tower foundation in frozen ground area
CN203256675U (en) Wall pile framework structure
CN207176874U (en) A kind of pavement comprehensive pipe network and drainage system
CN216515616U (en) Deep foundation pit waterproof combined structure suitable for three-side riverside shallow bedrock stratum containing quicksand
CN110528539A (en) A kind of Construction of Civil Engineering method quickly handling mud-rock flow, landslide collapsing using weatherability woven bag
CN214033660U (en) Ecological wind-prevention and sand-fixation system for railway protection

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20171020

RJ01 Rejection of invention patent application after publication