CN107237270A - A kind of construction method of girder construction - Google Patents
A kind of construction method of girder construction Download PDFInfo
- Publication number
- CN107237270A CN107237270A CN201710587765.3A CN201710587765A CN107237270A CN 107237270 A CN107237270 A CN 107237270A CN 201710587765 A CN201710587765 A CN 201710587765A CN 107237270 A CN107237270 A CN 107237270A
- Authority
- CN
- China
- Prior art keywords
- shaped base
- flange plate
- construction
- lifting
- bed die
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
- E01D21/00—Methods or apparatus specially adapted for erecting or assembling bridges
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Bridges Or Land Bridges (AREA)
Abstract
The invention discloses a kind of construction method of girder construction, the U-shaped base of prefabricated girder construction, U-shaped base is lifted to bridge pier column, flange plate support and edge of a wing plate bed die are set up in the left and right sides of U-shaped base, based on U-shaped base, the upper reinforcement concrete of girder construction is poured in the U-type groove of U-shaped base, flange plate is poured based on the plate bed die of the edge of a wing, flange plate support and edge of a wing plate bed die are removed after flange plate solidification reaches intensity requirement.Construction method designed by the present invention without setting up support, is lifted, lifting construction is easy by the use of U-shaped base as bed die using conventional cranes.In-situ precast can simultaneously be done with pier stud construction, and the duration of critical circuits, short construction period are not influenceed.Auxiliary material includes precast pedestal and a small amount of flange plate support, and material consumption amount is smaller;Beam body installation can be carried out using common crane, lifting cost is low.With good economy, practicality and market application value.
Description
Technical field
The present invention relates to technical field of bridge construction, in particular to a kind of construction method of girder construction.
Background technology
Traditional bridge beam body is reinforced concrete slab structure, and span is usually no more than 12 meters, it is considered to for once it is cast-in-place into
Type is designed, and construction is more to carry out disposable cast-in-place construction using full framing, steel pipe limited bracket method.This construction method is applied to bridge
Lower construction can close traffic or for under-clearance is less demanding, the construction period requires the in the case of of taking it easy, but under bridge
The situation that traffic can not be closed, Clearance requirement of constructing is higher, the construction period is nervous, traditional design and construction method will be presented
Go out corresponding shortcoming.Fig. 6 show the girder construction of existing pouring construction, if prefabricated being hung whole across girder construction is disposable
Dress, need to select Large-scale Hoisting equipment, while economy is not high.It need to be set up according to the cast-in-place construction party rule of template on pier stud
Bed die and side form, carry out primary concreting construction, great in constructing amount, and template can be supported occupancy space under bridge for a long time,
Workload is big during later stage form removal simultaneously, removes also more difficult.
The content of the invention
There is provided one kind traffic under bridge can not be closed present invention aim to the deficiency for solving above-mentioned background technology, it is full
Foot construction Clearance requirement, short time limit, the construction method of the girder construction of good economy performance.
In order to achieve this, the construction method of the girder construction designed by the present invention, it is characterised in that:Prefabricated girder construction
U-shaped base, lift U-shaped base to bridge pier column, flange plate support and flange plate bottom set up in the left and right sides of U-shaped base
Mould, based on U-shaped base, pours the upper reinforcement concrete of girder construction, with flange plate bottom in the U-type groove of U-shaped base
Flange plate is poured based on mould, flange plate support and edge of a wing plate bed die are removed after flange plate solidification reaches intensity requirement.
The construction method of girder construction described above, comprises the following steps:
1), based on the cross section of girder construction, girder construction is divided into U-shaped base, the U of U-shaped base is arranged at
Upper reinforcement concrete and the part of flange plate three for being arranged at the U-shaped base left and right sides in type groove;
2), prefabricated U-shaped base, lifts U-shaped base to bridge pier column;
3) flange plate support and edge of a wing plate bed die, are set up in the left and right sides of U-shaped base;
4), based on U-shaped base, upper reinforcement concrete is poured in the U-type groove of U-shaped base, with edge of a wing plate bed die
Based on pour flange plate, after flange plate solidification reaches intensity requirement, remove flange plate support and edge of a wing plate bed die.
Specifically, method of the U-shaped base to bridge pier column is lifted in the step 2 is:Two before and after U-shaped base
Side sets one group of hoisting bracket respectively, and every group of hoisting bracket is included positioned at the lifting entablature of U-shaped base top surface and positioned at U-shaped bottom
The lifting sill of seat bottom surface, is fixedly connected between lifting entablature and lifting sill by fining twisted steel, horizontal in lifting
Beam connects loop wheel machine by steel wire rope, and loop wheel machine removes hoisting bracket after lifting by crane U-shaped base to bridge pier column.
It is preferred that, the lifting entablature is parallel with lifting sill, and lifting entablature is with lifting sill along steel
The transverse width direction of reinforced concrete plate section is set.
Further, every group of hoisting bracket is respectively arranged on the left side and the right side a fining twisted steel, the essence
The middle part for rolling screw-thread steel is located in U-shaped base, and two ends are each passed through lifting entablature and lifting sill is connected with lifting nut.
Specifically, the left and right sides of the lifting entablature is respectively fixed with a steel wire rope lock, the loop wheel machine passes through
Steel wire rope is connected with steel wire rope lock.
Specifically, the side of flange plate support and edge of a wing plate bed die is set up in the step 3 in the left and right sides of U-shaped base
Method is:The upper and lower part of the flange plate support is fixed in U-shaped base by screw rod, edge of a wing plate bed die is layed in the wing
On the top surface of listrium support.
More specifically, the two ends of the screw rod are each passed through the side wall and flange plate support of U-shaped base and are connected with positioning spiral shell
It is female.
The beneficial effects of the invention are as follows:Beam body divide into U-shaped base, upper reinforcement by the construction method designed by the present invention
Three parts of concrete and flange plate are constructed respectively, and U-shaped base is prefabricated construction, and U-shaped base is hung using conventional cranes
Dress, lifting construction is easy.Upper reinforcement concrete is poured by the use of U-shaped base as bed die, while U-shaped base is also flange plate branch
Frame and building for edge of a wing plate bed die are provided the foundation, without setting up support, and in-situ precast can simultaneously be done with pier stud construction, not shadow
Ring the duration of critical circuits, short construction period.Auxiliary material include precast pedestal and a small amount of flange plate support, material consumption amount compared with
It is small;Beam body installation can be carried out using common crane, lifting cost is low.Solve the traffic under bridge and can not close, headroom of constructing will
The problem of beam body is constructed under conditions of asking higher, construction period nervous, valency is applied with good economy, practicality and market
Value.
Brief description of the drawings
Fig. 1 is the lifting front view of U-shaped base in the present invention;
Fig. 2 is the lifting side view of U-shaped base in the present invention;
Fig. 3 is the top view of U-shaped floor installation flange plate support and bed die in the present invention;
Fig. 4 is the side view of U-shaped floor installation flange plate support and bed die in the present invention;
Fig. 5 is the side view of girder construction in the present invention;
Fig. 6 is the girder construction of one-piece casting in the prior art;
Wherein, 1-U-shaped base, 2-flange plate support, 3-edge of a wing plate bed die, 4-upper reinforcement concrete, 5-edge of a wing
Plate, 6-lifting entablature, 7-lifting sill, 8-fining twisted steel, 9-steel wire rope, 10-lifting nut, 11-steel wire
Cord lock button, 12-screw rod, 13-location nut.
Embodiment
The present invention is described in further detail with specific embodiment below in conjunction with the accompanying drawings.
The construction method of girder construction as shown in Fig. 1-5, comprises the following steps:
1), based on the cross section of girder construction, girder construction is divided into U-shaped base 1, U-shaped base 1 is arranged at
Upper reinforcement concrete 4 and the part of flange plate 5 three for being arranged at the U-shaped left and right sides of base 1 in U-type groove;
2), prefabricated U-shaped base 1, one group of hoisting bracket, every group of hoisting bracket are set in the front and rear sides of U-shaped base 1 respectively
Including the lifting entablature 6 positioned at the U-shaped top surface of base 1 and the lifting sill 7 positioned at the U-shaped bottom surface of base 1, entablature 6 is lifted
It is fixedly connected between lifting sill 7 by fining twisted steel 8, the left and right sides of lifting entablature 6 is respectively fixed with one
Steel wire rope lock 11, the loop wheel machine is connected by steel wire rope 9 with steel wire rope lock 11.Lifting entablature 6 is connected by steel wire rope 9
Loop wheel machine, loop wheel machine removes hoisting bracket after lifting by crane U-shaped base 1 to bridge pier column;
3), the upper and lower part of the flange plate support 2 is fixed in U-shaped base 1 by screw rod 12, the two of screw rod 12
The side wall and flange plate support 2 that end is each passed through U-shaped base 1 are connected with location nut 13, and edge of a wing plate bed die 3 is layed in into the edge of a wing
On the top surface of board mount 2.
4), based on U-shaped base 1, upper reinforcement concrete 4 is poured in the U-type groove of U-shaped base 1, with flange plate bottom
Flange plate 5 is poured based on mould 3, after the solidification of flange plate 5 reaches intensity requirement, flange plate support 2 and edge of a wing plate bed die is removed
3。
Traditional girder construction, because the volume of traffic below is big, causes the steel of vehicle easily impact beam body construction in construction
Support, safety hazard is big.Apply man-hour requirement and reinforcing bar colligation is carried out in high-altitude, concrete cast-in-situ operation, difficulty of construction is big, the cycle
It is long.Auxiliary material includes support, prepressing materials, and integral material consumption is big, and cost is high.The present invention is by bridge beam body structure
Cross section carry out classifying rationally, be divided into above and below two parts, bottom is divided into U-shaped base 1, and top is divided into the upper of rectangular configuration
Portion's armored concrete 4.U-shaped base 1 carries out prefabricated at the scene, while carrying out colligation to the reinforcing bar of superstructure, speed of application is fast,
The engineering time is greatlyd save, lifting construction is carried out to U-shaped base 1 using conventional cranes, then bottom is used as by the use of U-shaped base 1
Mould carries out top cast-in-place construction, so that rack template expense is eliminated, and the more conducively guarantee of construction quality.
The above described is only a preferred embodiment of the present invention, not doing any formal to the structure of the present invention
Limitation.Any simple modification, equivalent variations and modification that every technical spirit according to the present invention is made to above example,
In the range of still falling within technical scheme.
Claims (8)
1. a kind of construction method of girder construction, it is characterised in that:The U-shaped base (1) of prefabricated girder construction, lifts U-shaped base
(1) on bridge pier column, flange plate support (2) and edge of a wing plate bed die (3) are set up in the left and right sides of U-shaped base (1), with U-shaped
Based on base (1), the upper reinforcement concrete (4) of girder construction is poured in the U-type groove of U-shaped base (1), with flange plate bottom
Flange plate (5) is poured based on mould (3), flange plate support (2) and the edge of a wing are removed after flange plate (5) solidification reaches intensity requirement
Plate bed die (3).
2. a kind of construction method of girder construction as claimed in claim 1, it is characterised in that:Comprise the following steps:
1), based on the cross section of girder construction, girder construction is divided into U-shaped base (1), U-shaped base (1) is arranged at
Upper reinforcement concrete (4) in U-type groove and the part of flange plate (5) three for being arranged at U-shaped base (1) left and right sides;
2), prefabricated U-shaped base (1), lifts U-shaped base (1) to bridge pier column;
3) flange plate support (2) and edge of a wing plate bed die (3), are set up in the left and right sides of U-shaped base (1);
4), based on U-shaped base (1), upper reinforcement concrete (4) is poured in the U-type groove of U-shaped base (1), with flange plate
Flange plate (5) is poured based on bed die (3), after flange plate (5) solidification reach intensity requirement after, remove flange plate support (2) and
Edge of a wing plate bed die (3).
3. a kind of construction method of girder construction as claimed in claim 2, it is characterised in that:Lifted in the step 2 U-shaped
Base (1) to the method on bridge pier column is:One group of hoisting bracket is set respectively in the front and rear sides of U-shaped base (1), every group is hung
Filling support includes the lifting entablature (6) and the lifting sill positioned at U-shaped base (1) bottom surface positioned at U-shaped base (1) top surface
(7), it is fixedly connected between lifting entablature (6) and lifting sill (7) by fining twisted steel (8), lifting entablature (6) leads to
Steel wire rope (9) connection loop wheel machine is crossed, loop wheel machine removes hoisting bracket after lifting by crane U-shaped base (1) to bridge pier column.
4. a kind of construction method of girder construction as claimed in claim 3, it is characterised in that:It is described lifting entablature (6) with
Lifting sill (7) is parallel, and lifting entablature (6) is with lifting sill (7) along the transverse width of armoured concrete slab section
Direction is set.
5. a kind of construction method of girder construction as claimed in claim 4, it is characterised in that:A left side for every group of hoisting bracket
Right both sides are respectively equipped with a fining twisted steel (8), and the middle part of the fining twisted steel (8) is located in U-shaped base (1),
Two ends are each passed through lifting entablature (6) and lifting sill (7) is connected with lifting nut (10).
6. a kind of construction method of girder construction as claimed in claim 5, it is characterised in that:The lifting entablature (6)
The left and right sides is respectively fixed with a steel wire rope lock (11), and the loop wheel machine is connected by steel wire rope (9) and steel wire rope lock (11)
Connect.
7. a kind of construction method of girder construction as claimed in claim 2, it is characterised in that:At U-shaped bottom in the step 3
The left and right sides of seat (1), which sets up flange plate support (2) and the method for edge of a wing plate bed die (3), is:By screw rod (12) by the wing
The upper and lower part of listrium support (2) is fixed in U-shaped base (1), and edge of a wing plate bed die (3) is layed in into flange plate support (2)
Top surface on.
8. a kind of construction method of girder construction as claimed in claim 7, it is characterised in that:The two ends of the screw rod (12) point
Not Chuan Guo U-shaped base (1) side wall and flange plate support (2) be connected with location nut (13).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710587765.3A CN107237270A (en) | 2017-07-18 | 2017-07-18 | A kind of construction method of girder construction |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710587765.3A CN107237270A (en) | 2017-07-18 | 2017-07-18 | A kind of construction method of girder construction |
Publications (1)
Publication Number | Publication Date |
---|---|
CN107237270A true CN107237270A (en) | 2017-10-10 |
Family
ID=59991629
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201710587765.3A Pending CN107237270A (en) | 2017-07-18 | 2017-07-18 | A kind of construction method of girder construction |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN107237270A (en) |
Cited By (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108221696A (en) * | 2018-02-02 | 2018-06-29 | 南昌大学 | A kind of special hoisting sling of prefabricated bridge |
CN109972512A (en) * | 2019-04-17 | 2019-07-05 | 浙江省交通规划设计研究院有限公司 | A kind of cast-in-situ construction method of profiled sheet-concrete combined bridge deck |
CN110359352A (en) * | 2019-08-02 | 2019-10-22 | 中冶长天国际工程有限责任公司 | A kind of prefabricated assembled T beam and construction method |
CN111719447A (en) * | 2020-07-31 | 2020-09-29 | 保利长大工程有限公司 | Novel hyperbolic arch bridge deck widening and reinforcing method |
CN111794074A (en) * | 2020-07-07 | 2020-10-20 | 浙江华东工程咨询有限公司 | Arch bridge concrete beam and beam forming method thereof |
CN113265949A (en) * | 2021-05-17 | 2021-08-17 | 中电建十一局工程有限公司 | Construction method of support-free concrete beam |
Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN1083885A (en) * | 1992-08-14 | 1994-03-16 | 特龙国际建筑技术有限公司 | The spanning of building the method for spanning and building thus |
CN201330112Y (en) * | 2008-11-04 | 2009-10-21 | 中铁六局集团有限公司 | Hoisting tool for hollow slab beam |
KR20110115349A (en) * | 2010-04-15 | 2011-10-21 | 삼성물산 주식회사 | Pier cap installation structure using precast concrete shell and construction method thereof |
CN102767141A (en) * | 2012-07-27 | 2012-11-07 | 中铁十一局集团有限公司 | Construction method for huge capping beam utilizing reinforced concrete thin wall as permanent formwork |
CN205576747U (en) * | 2016-04-14 | 2016-09-14 | 中交第二航务工程局有限公司 | Cast -in -place panel braced system of U type roof beam |
CN106592432A (en) * | 2016-11-29 | 2017-04-26 | 中铁十局集团有限公司 | Segmental mounting construction method of huge thin-wall precast capping beam housing |
-
2017
- 2017-07-18 CN CN201710587765.3A patent/CN107237270A/en active Pending
Patent Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN1083885A (en) * | 1992-08-14 | 1994-03-16 | 特龙国际建筑技术有限公司 | The spanning of building the method for spanning and building thus |
CN201330112Y (en) * | 2008-11-04 | 2009-10-21 | 中铁六局集团有限公司 | Hoisting tool for hollow slab beam |
KR20110115349A (en) * | 2010-04-15 | 2011-10-21 | 삼성물산 주식회사 | Pier cap installation structure using precast concrete shell and construction method thereof |
CN102767141A (en) * | 2012-07-27 | 2012-11-07 | 中铁十一局集团有限公司 | Construction method for huge capping beam utilizing reinforced concrete thin wall as permanent formwork |
CN205576747U (en) * | 2016-04-14 | 2016-09-14 | 中交第二航务工程局有限公司 | Cast -in -place panel braced system of U type roof beam |
CN106592432A (en) * | 2016-11-29 | 2017-04-26 | 中铁十局集团有限公司 | Segmental mounting construction method of huge thin-wall precast capping beam housing |
Cited By (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108221696A (en) * | 2018-02-02 | 2018-06-29 | 南昌大学 | A kind of special hoisting sling of prefabricated bridge |
CN109972512A (en) * | 2019-04-17 | 2019-07-05 | 浙江省交通规划设计研究院有限公司 | A kind of cast-in-situ construction method of profiled sheet-concrete combined bridge deck |
CN110359352A (en) * | 2019-08-02 | 2019-10-22 | 中冶长天国际工程有限责任公司 | A kind of prefabricated assembled T beam and construction method |
CN111794074A (en) * | 2020-07-07 | 2020-10-20 | 浙江华东工程咨询有限公司 | Arch bridge concrete beam and beam forming method thereof |
CN111719447A (en) * | 2020-07-31 | 2020-09-29 | 保利长大工程有限公司 | Novel hyperbolic arch bridge deck widening and reinforcing method |
CN113265949A (en) * | 2021-05-17 | 2021-08-17 | 中电建十一局工程有限公司 | Construction method of support-free concrete beam |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN107237270A (en) | A kind of construction method of girder construction | |
CN104695337B (en) | Self-lifting sliding and turnover construction system and construction method | |
CN105804395B (en) | Stair continuously poured in one molding construction method based on monoblock type typified form | |
CN206267422U (en) | A kind of assembly concrete superposed column | |
CN105256713A (en) | Semi-assembly steel-concrete composite beam and construction method thereof | |
CN107905114A (en) | A kind of construction method of large span Successive interference cancellation | |
CN105971276A (en) | Integral aluminum formwork stair one-step continuous pouring forming structure and construction method | |
CN107268455B (en) | Concrete girder gooseneck composite structure beam cradle construction method | |
CN206109960U (en) | Steel that can be under construction fast concrete integrated configuration bridge | |
CN205100082U (en) | Prefabricated assembly type steel reinforced concrete combination beam bridge | |
CN201942994U (en) | Bridge bearing pad | |
CN108560842A (en) | With the precast concrete stair section of multipurpose hole and its preparation and application | |
CN109025262B (en) | Construction method for one-time pouring forming of concrete flanging | |
CN216689076U (en) | A prefabricated apron that is used for hollow mound top to pour construction | |
CN207620184U (en) | A kind of superimposed sheet construction system | |
CN110005053A (en) | One kernel texture assembly assembling frame structure and its method of construction | |
CN109763658A (en) | A kind of support device and its construction method for arrangement material distributing machine in elevator | |
CN206655477U (en) | wall hole template | |
CN210622367U (en) | Prestressed concrete hollow slab reinforcing device | |
CN205296821U (en) | Oblique roofing formwork system of heavy grade cast in situ concrete | |
CN210530314U (en) | Formwork frame is pour to steel concrete combination shear wall T type node | |
CN106836644A (en) | A kind of method of construction of reinforced column | |
CN207348880U (en) | A kind of tunnel center gutter formed molding board | |
CN207228407U (en) | A kind of prefabricated partition wall of the staircase with installation base | |
CN108979142B (en) | Hang mould and pour construction structures |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20171010 |