CN107234586A - A kind of dismounting frock and assembly and disassembly methods suitable for phased array antenna transceiver module - Google Patents

A kind of dismounting frock and assembly and disassembly methods suitable for phased array antenna transceiver module Download PDF

Info

Publication number
CN107234586A
CN107234586A CN201710414777.6A CN201710414777A CN107234586A CN 107234586 A CN107234586 A CN 107234586A CN 201710414777 A CN201710414777 A CN 201710414777A CN 107234586 A CN107234586 A CN 107234586A
Authority
CN
China
Prior art keywords
transceiver module
pipe component
frock
series pipe
boosting
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201710414777.6A
Other languages
Chinese (zh)
Other versions
CN107234586B (en
Inventor
祝崇辉
李昌龙
石同武
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Aerospace Measurement Control Communication Institute
Original Assignee
Shanghai Aerospace Measurement Control Communication Institute
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Aerospace Measurement Control Communication Institute filed Critical Shanghai Aerospace Measurement Control Communication Institute
Priority to CN201710414777.6A priority Critical patent/CN107234586B/en
Publication of CN107234586A publication Critical patent/CN107234586A/en
Application granted granted Critical
Publication of CN107234586B publication Critical patent/CN107234586B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B25HAND TOOLS; PORTABLE POWER-DRIVEN TOOLS; MANIPULATORS
    • B25BTOOLS OR BENCH DEVICES NOT OTHERWISE PROVIDED FOR, FOR FASTENING, CONNECTING, DISENGAGING OR HOLDING
    • B25B27/00Hand tools, specially adapted for fitting together or separating parts or objects whether or not involving some deformation, not otherwise provided for
    • B25B27/14Hand tools, specially adapted for fitting together or separating parts or objects whether or not involving some deformation, not otherwise provided for for assembling objects other than by press fit or detaching same
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B25HAND TOOLS; PORTABLE POWER-DRIVEN TOOLS; MANIPULATORS
    • B25BTOOLS OR BENCH DEVICES NOT OTHERWISE PROVIDED FOR, FOR FASTENING, CONNECTING, DISENGAGING OR HOLDING
    • B25B11/00Work holders not covered by any preceding group in the subclass, e.g. magnetic work holders, vacuum work holders
    • B25B11/02Assembly jigs

Landscapes

  • Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • Quick-Acting Or Multi-Walled Pipe Joints (AREA)
  • Variable-Direction Aerials And Aerial Arrays (AREA)

Abstract

The invention discloses a kind of dismounting frock and assembly and disassembly methods suitable for phased array antenna transceiver module, series pipe component is carried out precise positioning by this method first by positioning tool, the guide for installing transceiver module is positioned by the alignment pin on positioning tool again, then using boosting frock by transceiver module Fast Installation in place, and fastened using the long spiro nail carried on transceiver module, realize the high-speed communication of the snap joint socket in the snap joint and series pipe component of transceiver module, also assembled afterwards using hand lathe turner and close the fast quick-detach that boosting frock realizes transceiver module.Using the assembly and disassembly methods and dismounting frock, the accurate connection of transceiver module and series pipe component can be achieved, it is to avoid seal failure caused by the dislocation of snap joint is damaged, the single dismounting to transceiver module can be achieved, it is laborsaving convenient.

Description

A kind of dismounting frock and assembly and disassembly methods suitable for phased array antenna transceiver module
Technical field
It is applied to phased array antenna transceiver module the invention belongs to Phased Array Radar Antenna technical field, more particularly to one kind Dismounting frock and assembly and disassembly methods.
Background technology
Phased array antenna has that structure space is small, heat-generating components inside many and heat flow density is big, transceiver module array quantity Many the characteristics of.
The transmitting-receiving subassembly of powerful phased-array radar generally realizes radiating using liquid is cold.The snap joint of blindmate formula has The characteristics of fast insert-pull can be realized in the cold pipeline of liquid and is not revealed, is now widely used for the cold pipeline connection of liquid.Single pair of is fast In spite of certain amount of floating when quick coupling is used, but there is when many arrays are using multipair snap joint certain accumulated error, This is accomplished by having positioning accurate to the series pipe component where the transceiver module where snap joint plug and snap joint socket The requirement of degree.
The layout of the cold pipeline of box-type phased array antenna liquid, is symmetrically arranged use generally according to antenna array row unit Symmetrical arrangement.Cold drawing on transceiver module is the form of left and right plug, adds limited radar antenna internal structural space With the arrangement of many arrays, visual poor, operating space is limited when causing to dismount in Phased Array Radar Antenna for transceiver module.
The content of the invention
The technical problem to be solved in the present invention is to provide a kind of dismounting frock suitable for phased array antenna transceiver module and Assembly and disassembly methods, it can be realized to the precise positioning of transceiver module and quickly and easily to transceiver module progress peace installation and dismantling Unload.
In order to solve the above technical problems, the technical solution adopted by the present invention is:
The present invention provides a kind of dismounting frock suitable for phased array antenna transceiver module, and phased array antenna includes transmitting-receiving mould Block, series pipe component and casing, the series pipe component are arranged on the outside of the casing, and the transceiver module is located at In the casing and the quantity way of connect with the pipeline of the series pipe component of the transceiver module matches, each described in Transceiver module is connected with the series pipe component respectively;The dismounting frock includes positioning tool, boosting frock and hand lathe turner Dress, the positioning tool is used to position the series pipe component and the transceiver module;The boosting frock is used for will be described Transceiver module is plugged on the series pipe component;The hand lathe turner is filled for using cooperatively to dismount with the boosting frock The transceiver module.
Preferably, the positioning tool includes working plate, long spiro nail, guide, alignment pin and positioning cylinder, the working plate Both sides up and down respectively socket one described in long spiro nail, the long spiro nail be used for the working plate is fixedly connected with the casing;Institute State and two alignment pins and two positioning cylinders are set on the right side of working plate;The guide is arranged on the outer wall of the casing On, it passes through the positioning finger setting;The positioning cylinder is used to position the series pipe component.
Preferably, the boosting frock includes handle and boosting main body, rear end and the handle of the boosting main body Front end is fixedly and coaxially connected;The rear end of the boosting main body sets the first avoidance hole, and front end sets the second avoidance hole, and described first avoids Hole and described second avoids hole for being filled by the hand lathe turner;There is opening the side in the second avoidance hole, in " U " type, institute Opening is stated towards front end, two latches are set respectively in the both sides of the opening, the latch is used to make the boosting work One end of dress is fixed on the casing;The top of a radial arrangement is set between the first avoidance hole and the second avoidance hole Head, the top is used for the left side for abutting the transceiver module, by applying pressure to the handle, so that the top is pushed away The transceiver module is moved to be plugged on the series pipe component.
Preferably, there is the polygon fallen in one end of the hand lathe turner dress, the polygon is to be socketed in the length The head of screw, unscrews by rotating the other end of the hand lathe turner dress or tightens the long spiro nail.
The present invention also provides a kind of assembly and disassembly methods suitable for phased array antenna transceiver module simultaneously, and phased array antenna includes Transceiver module, series pipe component and casing, the series pipe component are arranged on the outside of the casing, the transmitting-receiving mould Block is located in the casing and the quantity way of being connected with the pipeline of the series pipe component of the transceiver module matches, often The individual transceiver module is connected with the series pipe component respectively;It is characterised in that it includes following steps:
S1, is positioned series pipe component using positioning tool;
S2, is positioned by the alignment pin on positioning tool to the guide for installing transceiver module;
Snap joint on the transceiver module, is pressed on series pipe component by S3 using boosting frock;
S4, maintains the operation of previous step, is filled using hand lathe turner and fastens the long spiro nail carried on transceiver module, completes to receive Send out the installation of module;
S5, withstood on transceiver module using boosting frock on the other hand, is filled and will be carried on transceiver module using hand lathe turner on the other hand Long spiro nail is unscrewed, until transceiver module is completed to dismantle.
Further, the positioning tool includes working plate, long spiro nail and positioning cylinder, the both sides up and down of the working plate Two alignment pins and two positioning cylinders, the string are set on the right side of long spiro nail described in each socket one, the working plate Connection pipeline assembly is provided with the positioning hole matched with the positioning cylinder;
The step S1 comprises the following steps:
S11, is pre-fixed the working plate on the inwall of the casing by the long spiro nail;
S12, adjusts the position of the working plate, the positioning cylinder is respectively enterd the positioning of the series pipe component In hole, on the inwall that the working plate is fixed on to the casing by the long spiro nail;
S13, the series pipe component is fixed on the outer wall of the casing.
Further, the positioning tool includes setting two positioning on the right side of guide and alignment pin, the working plate Pin;
The step S2 comprises the following steps:
S21, the guide is inserted on the alignment pin, and then the guide is fixed on the outer wall of the casing;
S22, will be completed after location and installation, then the long spiro nail is twisted with the one-to-one guide of the alignment pin Pine, removes the positioning tool.
Further, the boosting frock includes handle and boosting main body, rear end and the handle of the boosting main body Front end be fixedly and coaxially connected;The rear end of the boosting main body sets the first avoidance hole, and front end sets the second avoidance hole;Described second keeps away Allow the side opening in hole, in " U " type, opening side sets in the both sides of opening two latches respectively towards front end; The top of a radial arrangement is set between the first avoidance hole and the second avoidance hole;
The step S3 comprises the following steps:
S31, the guide is directed at by the alignment pin of the transceiver module;
S32, two latches is connected to the side of the transceiver module, applies pressure at the handle, and then The transmitting-receiving template is promoted by the top, the snap joint that the snap joint is inserted in the series pipe component is inserted It is inserted into seat and by the alignment pin on the transceiver module on the guide.
Further, a kind of assembly and disassembly methods suitable for phased array antenna transceiver module, its step S4 includes:
When the boosting frock is kept in the state of force, the hand lathe turner dress avoids hole and described through described first The long spiro nail is tightened in second avoidance hole, on the inwall that the transceiver module is fixed on to the casing, so as to complete to described The installation of transceiver module.
Further, a kind of assembly and disassembly methods suitable for phased array antenna transceiver module, its step S5 includes:
In the state of the boosting frock keeps force, hand lathe turner dress avoids hole and described the through described first The long spiro nail is unscrewed in two avoidance holes, and then the transceiver module is extracted on the upside of the series pipe component, so as to complete Dismounting to the transceiver module.
Preferably, there is the polygon fallen in one end of the hand lathe turner dress, the polygon is to be socketed in the length The head of screw, unscrews by rotating the other end of the hand lathe turner dress or tightens the long spiro nail.
The advantageous effects that the technical solution adopted in the present invention is brought are:
The present invention is positioned before transceiver module installation using positioning tool, and transceiver module and tandem tube can be achieved The precise positioning of road component is installed, it is to avoid seal failure caused by the dislocation of snap joint is damaged;
The present invention can be achieved the single dismounting to transceiver module, save by the way that boosting frock and hand lathe turner dress are used cooperatively Power is convenient;
Many arrays of the present invention in phased array antenna, liquid-cooled transceiver module box house installation and lateral insert There is provided a kind of solution of synthesis under conditions of pulling out.
Certainly, any product for implementing the present invention it is not absolutely required to while reaching all the above advantage.
Brief description of the drawings
Fig. 1 is the structural representation of the positioning tool of one embodiment of the invention;
Fig. 2 is the structural representation of the boosting frock of one embodiment of the invention;
The structural representation that Fig. 3 fills for the hand lathe turner of one embodiment of the invention;
Profile when Fig. 4 is implemented for the positioning tool of one embodiment of the invention;
Fig. 5 dismounts profile during transceiver module for the dismounting frock of one embodiment of the invention;
Fig. 6 is a kind of flow chart of assembly and disassembly methods suitable for phased array antenna transceiver module of one embodiment of the invention.
In figure, 1- positioning tools, 2- boosting frocks, 3- hands lathe turner dress, 4- transceiver modules;5- series pipe components;6- casees Body;11- working plates;12- long spiro nails;13- guidees;14- alignment pins;15- positions cylinder;21- handles;22- first avoids hole; 23- comes directly towards;24- second avoids hole;25- latches;151- locating surfaces.
Embodiment
To make the object, technical solutions and advantages of the present invention clearer, below in conjunction with each reality of the accompanying drawing to the present invention The mode of applying is explained in detail.
Fig. 1 to Fig. 5 is refer to, a kind of dismounting frock suitable for phased array antenna transceiver module, phased array antenna includes Transceiver module 4, series pipe component 5 and casing 6, series pipe component 5 are arranged on the outside of casing 6, and transceiver module 4 is located at In casing 6 and the quantity way of being connected with the pipeline of series pipe component 5 of transceiver module 4 matches, each transceiver module 4 includes Two transmitting-receiving subassemblies and a cold drawing, two transmitting-receiving subassemblies are folded in the left and right sides of cold drawing, and cold drawing connects with series pipe component 5 Connect;The dismounting frock fills 3 including positioning tool 1, boosting frock 2 and hand lathe turner, and positioning tool 1 is used to position series pipe group Part 5 and transceiver module 4;Boosting frock 2 is used to transceiver module 4 being plugged into series pipe component 5;Hand lathe turner fill 3 be used for Boosting frock 2 uses cooperatively to dismount transceiver module 4.In the present embodiment, positioning tool 1, boosting frock 2 and hand lathe turner, which fill 3, is It is used for dismantling and installing phased array antenna together.Further, dismounting transceiver module 4 refers to dismantle and installs transceiver module 4, After transceiver module 4 is plugged into series pipe component 5, hand lathe turner, which fills 3 and used cooperatively with boosting frock 2, consolidates transceiver module 4 It is scheduled on the inwall of casing 6 or unscrews to pull out the side of transceiver module 4 from the inwall of casing 6.Also, it is understood that be The quantity of positioning tool 1 is also identical with the pipeline series connection way of series pipe component 5.
The present invention is especially suitable for the installation of many arrays, liquid-cooled transceiver module inside casing 6 in phased array antenna And positioning and installation under the conditions of lateral plug.Using the dismounting frock, transceiver module 4 and series pipe component 5 can be achieved On accurate connection, it is to avoid transceiver module 4 because misplace it is damaged caused by seal failure;It can be achieved to tear one of transceiver module 4 open Dress, it is laborsaving convenient.
As shown in figure 1, positioning tool 1 includes working plate 11, long spiro nail 12, guide 13, alignment pin 14 and positioning cylinder 15, Respectively socket one long spiro nail 12, i.e. long spiro nail 12 is that the form for running through and not falling off is socketed in working plate for the both sides up and down of working plate 11 On 11, long spiro nail 12, which is connected through a screw thread, is fixedly connected with working plate 11 with casing 6.The right side of working plate 11 is provided with two positioning Pin 14 and two positioning cylinders 15, when positioning tool 1 is loaded in casing 6, positioning cylinder 15 is used to position series pipe Component 5, and after the acquisition positioning of series pipe component 5 is fixedly mounted on the outer wall of casing 6, guide 13 is fixed by alignment pin 14 Position is so as to be fixedly mounted on the outer wall of casing 6.It should be appreciated that the quantity more than one of positioning tool 1 and be used for simultaneously Position a series pipe component 5.
As shown in Fig. 2 boosting frock 2 includes handle 21 and boosting main body, boosting main body and handle 21 are coaxially connected and help The rear end for pushing away main body is fixedly connected with the front end of handle 21, and the rear end of boosting main body sets the first avoidance hole 22, and front end sets second and kept away Allow hole 24, the first avoidance hole 22 and second, which avoids hole 24, to be used to fill 3 by hand lathe turner.There is opening the side in the second avoidance hole 24, In " U " type, it is open towards front end, two latches 25 is set respectively in the both sides of opening, latch 25 is used to make the one of boosting frock 2 End is connected on casing 6.The top 23 of a radial arrangement is set between first avoidance hole 22 and second avoidance hole 24, top 23 is used for Abut the left side of transceiver module 4.When one end of boosting frock 2 is connected on casing 6, top 23 is connected to a left side for transceiver module 4 Side, to the other end of boosting frock 2, i.e. handle 21, applies the pressure along the snap joint axial direction on transceiver module 4, utilizes thick stick Rod principle can realize the screen resilience for overcoming the snap joint socket when installing transceiver module 4, and transceiver module 4 can be helped to be encased in In series pipe component 5.
As shown in figure 3, it is in " fourth " font that hand lathe turner, which fills 3, there is the hexagon fallen in one end that hand lathe turner fills 3, six side Shape is used for the head for being socketed in long spiro nail 12, by rotating the other end that hand lathe turner fills 3, so as to tighten or unscrew long spiro nail 12.It should be noted that working plate 11 is similar to the cold drawing of transceiver module 4, its difference is, is provided with cold drawing and series pipe The runner that component 5 is connected, and the plate of positioning tool 1 does not have runner;The right side of cold drawing is provided with two snap joints, and working plate 11 Side provided with two positioning cylinders 15.3 are filled with lathe turner in one's hands during transceiver module 4 is mounted and dismounted, work is positioned Fill 1 and transceiver module 4 quantity it is identical with the pipeline of series pipe component 5 series connection way.
As shown in fig. 6, a kind of assembly and disassembly methods suitable for phased array antenna transceiver module, phased array antenna includes transmitting-receiving mould Block 4, series pipe component 5 and casing 6, series pipe component 5 are arranged on the outside of casing 6, and transceiver module 4 is located at casing 6 Interior and transceiver module 4 quantity way of being connected with the pipeline of series pipe component 5 matches, and each transceiver module 4 includes two Transmitting-receiving subassembly and a cold drawing, two transmitting-receiving subassemblies are folded in the left and right sides of cold drawing, and cold drawing is connected with series pipe component 5;Should Assembly and disassembly methods its comprise the following steps:S1, is positioned series pipe component 5 using positioning tool 1;S2, by positioning work 14 pairs of the alignment pin filled on 1 is positioned for installing the guide 13 of transceiver module 4;S3, using boosting frock 2 by cold drawing On snap joint press-in series pipe component 5;S4, maintains the operation of previous step, 3 is filled by transceiver module 4 using hand lathe turner The long spiro nail 12 carried is fastened, and completes the installation of transceiver module 4;S5, withstands on the cold of transceiver module 4 using boosting frock 2 on the other hand On plate, fill 3 using hand lathe turner on the other hand and unscrew the long spiro nail 12 carried on transceiver module 4, until transceiver module 4 is completed to tear open Unload.In the present embodiment, step S1 to step S4 is location and installation flow, and step S5 is dismounting flow.It is appreciated that step The quantity more than one of positioning tool 1 in S1, its quantity is identical with the pipeline series connection way of series pipe component 5, and simultaneously For positioning a series pipe component 5.
The present invention is especially suitable for the installation of many arrays, liquid-cooled transceiver module 4 inside casing 6 in phased array antenna And positioning and installation under the conditions of lateral plug.Using this method, snap joint and the series pipe of transceiver module 4 can be achieved The accurate connection of component 5, it is to avoid seal failure caused by the dislocation of snap joint is damaged;Can be achieved to transceiver module 4 one Dismounting, it is laborsaving convenient.
Please comprehensive reference Fig. 1 to Fig. 6, positioning tool 1 include working plate 11, long spiro nail 12 and positioning cylinder 15, working plate 11 both sides up and down are respectively socketed a long spiro nail 12, and the right side of working plate 11 sets two alignment pins 14 and two positioning cylinders 15, string Connection pipeline assembly 5 is provided with the positioning hole matched with positioning cylinder 15;
Step S1 comprises the following steps:S11, is pre-fixed working plate 11 on the inwall of casing 6 by long spiro nail 12; S12, adjusts the position of working plate 11, positioning cylinder 15 is respectively enterd in the positioning hole of series pipe component 5, pass through long spiro nail 12 are fixed on working plate 11 on the inwall of casing 6;On S13, the outer wall that series pipe component 5 is fixed on to casing 6.This implementation In example, positioning cylinder 15 matches with the positioning hole shape on series pipe component 5, and positioning cylinder 15 is provided with locating surface 151, When locating surface 151 is fully entered in positioning hole, the positioning to series pipe component 5 is completed.
Positioning tool 1 includes guide 13 and alignment pin 14, and the right side of working plate 11 sets two alignment pins 14;
Step S2 comprises the following steps:S21, guide 13 is inserted on alignment pin 14, and guide 13 then is fixed on into casing 6 Outer wall on;S22, will be completed after location and installation with the one-to-one guide of alignment pin 14 13, then long spiro nail 12 is unscrewed, and be removed Positioning tool 1.In the present embodiment, guide 13 is positioned by the alignment pin 14 on positioning tool 1, so that guide 13 be determined Position is arranged on the outer wall of casing 6.
With reference to shown in Fig. 2, boosting frock 2 is included before handle 21 and boosting main body, the rear end of boosting main body and handle 21 End is fixedly and coaxially connected;The rear end of boosting main body sets the first avoidance hole 22, and front end sets the second avoidance hole 24;Second avoids hole 24 One side opening, in " U " type, opening side sets in the both sides of opening two latches 25 respectively towards front end;First avoids The top 23 of a radial arrangement is set between the avoidance hole 24 of hole 22 and second;
Step S3 comprises the following steps:S31, guide 13 is directed at by the alignment pin 14 of transceiver module 4;S32, by two latches 25 are connected to the left side of cold drawing, apply pressure at handle 21, and then promote cold drawing by top 23, make snap joint insertion string It is inserted into snap joint socket in connection pipeline assembly 5 and by the alignment pin 14 on cold drawing on guide 13.In the present embodiment, Cold drawing, which is provided with snap joint, series pipe component 5, is provided with snap joint socket, and boosting frock 2, which can be realized, overcomes installation The screen resilience of snap joint socket during transceiver module 4, helps transceiver module 4 to be encased in series pipe component 5, and determining on cold drawing The position insertion guide 13 of pin 14, two guidees 13 can be realized to be accurately positioned to the alignment pin 14 of cold drawing, that is, is realized to transmitting-receiving Module 4 is accurately positioned.
Wherein step S4 includes:
When boosting frock 2 is kept in the state of force, hand lathe turner fills 3 through first and avoids the avoidance hole 24 of hole 22 and second Long spiro nail 12 is tightened, on the inwall that transceiver module 4 is fixed on to casing 6, so as to complete the installation to transceiver module 4.
Wherein step S5 includes:
In the state of boosting frock 2 keeps force, hand lathe turner fills 3 and twisted through the first avoidance hole 22 and second avoidance hole 24 Loose long spiro nail 12, and then transceiver module 4 is extracted from the upside of series pipe component 5, so as to complete the dismounting to transceiver module 4.
There is the polygon fallen in one end that hand lathe turner fills 3, and head of the polygon to be socketed in long spiro nail 12 passes through rotation Lathe turner is changed hands to fill 3 other end to unscrew or tighten long spiro nail 12.
It should be noted that the working plate 11 in the assembly and disassembly methods is similar to the cold drawing of transceiver module 4, its difference is, Provided with the runner being connected with series pipe component 5 in cold drawing, and working plate 11 is without runner;The right side of cold drawing is fast provided with two Quick coupling, and the side of working plate 11 is provided with two positioning cylinders 15.Used during transceiver module 4 is mounted and dismounted Hand lathe turner fills 3, and the quantity of positioning tool 1 and transceiver module 4 is identical with the pipeline series connection way of series pipe component 5.
The foregoing is only a preferred embodiment of the present invention, but protection scope of the present invention be not limited thereto, Any one skilled in the art the invention discloses technical scope in, the change or replacement that can be readily occurred in, It should all be included within the scope of the present invention.Therefore, protection scope of the present invention should be with scope of the claims It is defined.

Claims (11)

1. a kind of dismounting frock suitable for phased array antenna transceiver module, phased array antenna includes transceiver module, series pipe Component and casing, the series pipe component are arranged on the outside of the casing, and the transceiver module is located in the casing And the quantity of transceiver module way of being connected with the pipeline of the series pipe component matches, each transceiver module point It is not connected with the series pipe component;It is characterized in that:Including positioning tool, boosting frock and hand lathe turner dress, the positioning Frock is used to position the series pipe component and the transceiver module;The boosting frock is used for the transceiver module grafting Onto the series pipe component;The hand lathe turner is filled for using cooperatively to dismount the transmitting-receiving mould with the boosting frock Block.
2. a kind of dismounting frock suitable for phased array antenna transceiver module as claimed in claim 1, it is characterised in that:It is described Positioning tool includes working plate, long spiro nail, guide, alignment pin and positioning cylinder, the respectively socket one of both sides up and down of the working plate The long spiro nail, the long spiro nail is used to the working plate being fixedly connected with the casing;Two are set on the right side of the working plate The individual alignment pin and two positioning cylinders;The guide is arranged on the outer wall of the casing, and it passes through the positioning Finger setting;The positioning cylinder is used to position the series pipe component.
3. a kind of dismounting frock suitable for phased array antenna transceiver module as claimed in claim 2, it is characterised in that:It is described Boosting frock includes handle and boosting main body, and the rear end and the front end of the handle of the boosting main body are fixedly and coaxially connected;Institute The rear end for stating boosting main body sets the first avoidance hole, and front end sets the second avoidance hole, and described first, which avoids hole and described second, avoids hole For being filled by the hand lathe turner;There is opening the side in the second avoidance hole, and in " U " type, the opening is towards front end, in institute The both sides for stating opening set two latches respectively, and the latch is used to make one end of the boosting frock be fixed on the case On body;The top of a radial arrangement is set between the first avoidance hole and the second avoidance hole, the top is used to abut institute The left side of transceiver module is stated, by applying pressure to the handle, so that the top promotes the transceiver module to be plugged into On the series pipe component.
4. a kind of dismounting frock suitable for phased array antenna transceiver module as claimed in claim 3, it is characterised in that:It is described There is the polygon fallen in one end of hand lathe turner dress, and head of the polygon to be socketed in the long spiro nail passes through rotation The other end of hand lathe turner dress is unscrewed or tightens the long spiro nail.
5. a kind of assembly and disassembly methods suitable for phased array antenna transceiver module, phased array antenna includes transceiver module, series pipe Component and casing, the series pipe component are arranged on the outside of the casing, and the transceiver module is located in the casing And the quantity of transceiver module way of being connected with the pipeline of the series pipe component matches, each transceiver module point It is not connected with the series pipe component;It is characterised in that it includes following steps:
S1, is positioned series pipe component using positioning tool;
S2, is positioned by the alignment pin on positioning tool to the guide for installing transceiver module;
Snap joint on the transceiver module, is pressed on series pipe component by S3 using boosting frock;
S4, maintains the operation of previous step, is filled using hand lathe turner and fastens the long spiro nail carried on transceiver module, completes transmitting-receiving mould The installation of block;
S5, is withstood on transceiver module using boosting frock on the other hand, fills the long spiral shell that will be carried on transceiver module using hand lathe turner on the other hand Nail is unscrewed, until transceiver module is completed to dismantle.
6. a kind of assembly and disassembly methods suitable for phased array antenna transceiver module as claimed in claim 5, it is characterised in that:It is described Positioning tool includes working plate, long spiro nail and positioning cylinder, and the both sides up and down of the working plate are respectively socketed long spiro nail, institute described in one State and two alignment pins and two positioning cylinders set on the right side of working plate, the series pipe component be provided with it is described The positioning hole that positioning cylinder matches;
The step S1 comprises the following steps:
S11, is pre-fixed the working plate on the inwall of the casing by the long spiro nail;
S12, adjusts the position of the working plate, the positioning cylinder is respectively enterd the positioning hole of the series pipe component It is interior, on the inwall that the working plate is fixed on to the casing by the long spiro nail;
S13, the series pipe component is fixed on the outer wall of the casing.
7. a kind of assembly and disassembly methods suitable for phased array antenna transceiver module as claimed in claim 6, it is characterised in that:It is described Positioning tool includes setting two alignment pins on the right side of guide and alignment pin, the working plate;
The step S2 comprises the following steps:
S21, the guide is inserted on the alignment pin, and then the guide is fixed on the outer wall of the casing;
S22, will be completed after location and installation with the one-to-one guide of the alignment pin, then the long spiro nail is unscrewed, and be taken Under the positioning tool.
8. a kind of assembly and disassembly methods suitable for phased array antenna transceiver module as claimed in claim 7, it is characterised in that:It is described Boosting frock includes handle and boosting main body, and the rear end and the front end of the handle of the boosting main body are fixedly and coaxially connected;Institute The rear end for stating boosting main body sets the first avoidance hole, and front end sets the second avoidance hole;Described second avoids a side opening in hole, in " U " Type, opening side sets in the both sides of opening two latches respectively towards front end;Described first avoids hole and described The top of a radial arrangement is set between second avoidance hole;
The step S3 comprises the following steps:
S31, the guide is directed at by the alignment pin of the transceiver module;
S32, two latches is connected to the side of the transceiver module, applies pressure at the handle, and then pass through The top promotes the transmitting-receiving template, the snap joint is inserted in the snap joint socket in the series pipe component And the alignment pin on the transceiver module is inserted on the guide.
9. a kind of assembly and disassembly methods suitable for phased array antenna transceiver module as claimed in claim 8, it is characterised in that described Step S4 includes:
When the boosting frock is kept in the state of force, the hand lathe turner dress avoids hole and described second through described first Avoid hole and tighten the long spiro nail, on the inwall that the transceiver module is fixed on to the casing, so as to complete to the transmitting-receiving The installation of module.
10. a kind of assembly and disassembly methods suitable for phased array antenna transceiver module as claimed in claim 5, it is characterised in that institute Stating step S5 includes:
In the state of the boosting frock keeps force, the hand lathe turner dress is kept away through the described first avoidance hole and described second Allow hole to unscrew the long spiro nail, and then the transceiver module is extracted on the upside of the series pipe component, so as to complete to institute State the dismounting of transceiver module.
11. a kind of assembly and disassembly methods suitable for phased array antenna transceiver module as claimed in claim 5, it is characterised in that:Institute Stating one end of hand lathe turner dress has the polygon fallen in, and head of the polygon to be socketed in the long spiro nail passes through rotation Turn the other end of the hand lathe turner dress to unscrew or tighten the long spiro nail.
CN201710414777.6A 2017-06-05 2017-06-05 A kind of dismounting tooling and assembly and disassembly methods suitable for phased array antenna transceiver module Active CN107234586B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710414777.6A CN107234586B (en) 2017-06-05 2017-06-05 A kind of dismounting tooling and assembly and disassembly methods suitable for phased array antenna transceiver module

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710414777.6A CN107234586B (en) 2017-06-05 2017-06-05 A kind of dismounting tooling and assembly and disassembly methods suitable for phased array antenna transceiver module

Publications (2)

Publication Number Publication Date
CN107234586A true CN107234586A (en) 2017-10-10
CN107234586B CN107234586B (en) 2018-10-19

Family

ID=59985804

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710414777.6A Active CN107234586B (en) 2017-06-05 2017-06-05 A kind of dismounting tooling and assembly and disassembly methods suitable for phased array antenna transceiver module

Country Status (1)

Country Link
CN (1) CN107234586B (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109216935A (en) * 2018-08-24 2019-01-15 中国电子科技集团公司第二十九研究所 A kind of integrated assembly method of millimeter wave phased array

Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US5680689A (en) * 1995-11-13 1997-10-28 Holladay; Ray S. Hub removal tool and method
US5680686A (en) * 1996-01-17 1997-10-28 Branick Industries, Inc. Strut spring compressor having floating compression head
US5689870A (en) * 1995-09-18 1997-11-25 Robey; Peter D. Valve spring compressor tool
US5694675A (en) * 1996-04-02 1997-12-09 Chrysler Corporation Method of centering a vehicle latch striker
US5694689A (en) * 1995-09-15 1997-12-09 Filipowers; Zbigniew Method of mainspring removal tool for mainspring removal
CN1262162A (en) * 1999-01-27 2000-08-09 伊兹帕尔公司 Tool and eccentric tool for trapping and detaching unidirectional fixer
CN2402797Y (en) * 1999-08-18 2000-10-25 温振生 Power clamp clamping mechanism
CN2403550Y (en) * 1999-12-01 2000-11-01 北京友朋实业发展公司 Split head restraints conduit pipe cup joint press fit device
CN2409018Y (en) * 2000-01-27 2000-12-06 大连机车车辆厂 Hydraulic drawing machine for bolt of cylinder head
CN2409019Y (en) * 2000-01-27 2000-12-06 大连机车车辆厂 Hydraulic drawing machine for bolt of main bearing of diesel engine

Patent Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US5694689A (en) * 1995-09-15 1997-12-09 Filipowers; Zbigniew Method of mainspring removal tool for mainspring removal
US5689870A (en) * 1995-09-18 1997-11-25 Robey; Peter D. Valve spring compressor tool
US5680689A (en) * 1995-11-13 1997-10-28 Holladay; Ray S. Hub removal tool and method
US5680686A (en) * 1996-01-17 1997-10-28 Branick Industries, Inc. Strut spring compressor having floating compression head
US5694675A (en) * 1996-04-02 1997-12-09 Chrysler Corporation Method of centering a vehicle latch striker
CN1262162A (en) * 1999-01-27 2000-08-09 伊兹帕尔公司 Tool and eccentric tool for trapping and detaching unidirectional fixer
CN2402797Y (en) * 1999-08-18 2000-10-25 温振生 Power clamp clamping mechanism
CN2403550Y (en) * 1999-12-01 2000-11-01 北京友朋实业发展公司 Split head restraints conduit pipe cup joint press fit device
CN2409018Y (en) * 2000-01-27 2000-12-06 大连机车车辆厂 Hydraulic drawing machine for bolt of cylinder head
CN2409019Y (en) * 2000-01-27 2000-12-06 大连机车车辆厂 Hydraulic drawing machine for bolt of main bearing of diesel engine

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109216935A (en) * 2018-08-24 2019-01-15 中国电子科技集团公司第二十九研究所 A kind of integrated assembly method of millimeter wave phased array
CN109216935B (en) * 2018-08-24 2020-07-17 中国电子科技集团公司第二十九研究所 Millimeter wave phased array integrated assembly method

Also Published As

Publication number Publication date
CN107234586B (en) 2018-10-19

Similar Documents

Publication Publication Date Title
CN107234586A (en) A kind of dismounting frock and assembly and disassembly methods suitable for phased array antenna transceiver module
CN207316286U (en) A kind of flange for connecting different size extension tube attacheds
US20070125541A1 (en) Threaded connector for well servicing applications
CN205508291U (en) Concatenation formula LED display screen
CN107984427A (en) A kind of aero-engine is with disassembling bushing device and application method in blind hole
CN110697018B (en) Unmanned aerial vehicle wing and fuselage connecting device
CN106438619A (en) Fastener installation in composite panels with fastener insert
CN102814794A (en) Drilling-riveting fastener
CN204893352U (en) Device is extracted to self compensating briquetting lockpin of auto steering machine assembly usefulness
CN207942223U (en) A kind of RV speed reducers planet carrier clamp for machining
CN104416531B (en) The method for dismounting and extracting tool of plunger type pipe joint
CN113751764B (en) Bushing type radiator core subassembly drill jig and drilling method
CN204064659U (en) Flame-proof electric motor test unit
CN113231988A (en) Special tool for disassembling and assembling hydraulic coupler
CN209340706U (en) The connection of hydraulic fluid port compact and sealing device and articulated truck
CN208707486U (en) A kind of level-meter of motor installation
CN217951545U (en) Cutting ferrule formula connects seal structure
CN202763803U (en) Drilling and riveting fastener
CN107902104B (en) Dismounting method for press-in type lubricating joint of airplane
CN206445385U (en) A kind of beam and the attachment structure of cable front connector
CN217833536U (en) Dismounting tool for short pump plunger of well cementation pump
CN104668882A (en) Torsional damper and mounting method thereof
CN114646460B (en) Accurate testing device and method for piston cooling spray pipe
CN215358235U (en) Liquid couple drawing tool and liquid couple press-fitting tool
CN210343922U (en) Double-guide-rod positioning jacking mechanism

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant