CN107227741A - Basement supporting construction - Google Patents

Basement supporting construction Download PDF

Info

Publication number
CN107227741A
CN107227741A CN201710635355.1A CN201710635355A CN107227741A CN 107227741 A CN107227741 A CN 107227741A CN 201710635355 A CN201710635355 A CN 201710635355A CN 107227741 A CN107227741 A CN 107227741A
Authority
CN
China
Prior art keywords
suspension cable
concrete
arch brace
steel suspension
basement
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201710635355.1A
Other languages
Chinese (zh)
Other versions
CN107227741B (en
Inventor
朱奎
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Linyi Jiechuang Chemical Industrial Park Co ltd
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201810920784.8A priority Critical patent/CN108951654B/en
Priority to CN201710635355.1A priority patent/CN107227741B/en
Priority to CN201810927295.5A priority patent/CN108951655B/en
Priority to CN201810920743.9A priority patent/CN108930273B/en
Priority to CN201810920824.9A priority patent/CN108930274B/en
Publication of CN107227741A publication Critical patent/CN107227741A/en
Application granted granted Critical
Publication of CN107227741B publication Critical patent/CN107227741B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/02Foundation pits
    • E02D17/04Bordering surfacing or stiffening the sides of foundation pits
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2250/00Production methods
    • E02D2250/0046Production methods using prestressing techniques

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Rod-Shaped Construction Members (AREA)
  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)
  • Piles And Underground Anchors (AREA)

Abstract

The invention discloses a kind of basement supporting construction, it is characterized in that pulley is provided below in raft plate, pulley uses steel ball roller bearing, and pulley is arranged below steel plate, horizontal sleeper is provided below in steel plate, and horizontal sleeper uses the lumps of wood;Translation direction arrangement of the pulley along Wood construction thing;Have in the middle of pulley and weld anchor rib above bearing, bearing, new basis, new basis top laying rubber bed course are set at sliding in place position;It is brick loose tool that new foundation bottom, which is provided below below earthquake cushion, earthquake cushion,;The raft plate of Wood construction thing is set to couple with new basis using bar planting method in the corner of Wood construction thing.The present invention has the advantages that construction safety is reliable, cost is low.

Description

Basement supporting construction
Technical field
The present invention relates to a kind of supporting construction, more particularly to a kind of basement supporting construction.
Background technology
Concrete is set when basement excavation is deeper to supportting to resist passive earth pressure, concrete is to supportting excessive setting not But engineering cost can be increased, and be unfavorable for cutting the earth, concrete can be very big to the horizontal axle power suffered by support, how both to have reduced mixed Solidifying soil can ensure that safety is the problem that engineering staff faces to the axle power of support again.But, how to be reduced in the case where ensuring secured premise Cost.
The content of the invention
The deficiencies in the prior art are solved it is an object of the invention to provide a kind of basement supporting construction.
The present invention sets arch brace in the middle part of basement, and arch brace area is 30~80m2, arch brace center is At the centre of form of basement geometry, arch brace is highly 500~700mm, and arch brace width is 250~300mm.
Basement set right-angled intersection to support beam, right-angled intersection to support beam crosspoint basement geometry the centre of form Place.Right-angled intersection is 600~800mm to support depth of beam, and right-angled intersection is 250~300mm to support beam width.
Arch brace and right-angled intersection set steel lattice column to support beam crossover sites, and steel lattice column insertion engineering pile 500~ 600mm, steel lattice column is higher by concrete and beared down on one top surface of the beam 0.7~0.9m of absolute altitude, and prestressed stretch-draw pier is set above steel lattice column.
Basement fender post uses cast-in-situ bored pile;Cast-in-situ bored pile periphery sets cement mixing pile water stopping curtain, cement The a diameter of 500mm of cement mixing pile that stirring pile water stopping curtain is used, adjacent cement mixing pile is mutually twisted 300~400mm; Concrete capping beam is set at the top of cast-in-situ bored pile, and concrete bears down on one beam width for 300mm, is highly 500~600mm;It is local When lower room cutting depth is more than or equal to 3.5m, concrete breast beam is set, and concrete breast beam set location is vertical in the middle part of basement It is identical with concrete capping beam in plane, concrete breast beam width is 300mm, is highly 500~600mm.
When basement cutting depth is less than or equal to 3.5m, vertical plane uses row's supporting construction, in right-angled intersection pair Support the span of beam top 1/8,1/4 span, 3/4 span and 7/8 span position and drawknot node on steel suspension cable is set, in right-angled intersection to support The span of beam bottom 3/8,1/2 span and 5/8 span position set drawknot node under steel suspension cable, and span refers to right-angled intersection to support here Beam is with concrete capping beam crosspoint and arch brace with right-angled intersection to the distance between support beam crosspoint.Steel suspension cable is using pre- Stress tension.
When basement cutting depth is more than 3.5m, vertical plane uses two row's supporting construction;First row supporting construction exists Right-angled intersection sets drawknot node on steel suspension cable to the span of support beam top 1/8,1/4 span, 3/4 span and 7/8 span position, ten The span of word cross-pair support beam bottom 3/8,1/2 span and 5/8 span position set drawknot node under steel suspension cable, and four corners set mixed Solidifying soil Bars In Poured Concrete Slab, concrete cast-in-situ plate suqare is more than or equal to 5m2, concrete cast-in-situ plate thickness is 12~15mm, and arrangement of reinforcement is using straight Footpath is 12~14mm;Because stress concentration occurs in four corners of first row supporting construction, there is provided concrete cast-in-place slab can Effectively to alleviate the stress at these positions.Second row supporting construction is arranged at the 1/2 of cutting depth, second row supporting construction Drawknot node on steel suspension cable is set to the span of support beam top 1/8,1/4 span, 3/4 span and 7/8 span position in right-angled intersection, Right-angled intersection sets drawknot node under steel suspension cable to the span of support beam bottom 3/8,1/2 span and 5/8 span position, and steel suspension cable is using pre- Stress tension;Steel pipe is set between arch brace and concrete capping beam to support.
When basement cutting depth is more than 3.5m, construction procedure includes:
(1) construction fender post;
(2) concrete capping beam is set at the top of fender post;
(3) when setting the Construction of Engineering Pile of steel lattice column, steel lattice column is inserted when engineering pile concrete is unhardened;
(4) first row arch brace and first row right-angled intersection are poured to support beam concrete;
(5) concrete cast-in-place slab of first row supporting construction is poured;
(6) the steel suspension cable drawknot node of first row supporting construction is set;Right-angled intersection is to support beam top main reinforcement welded suspending hook It is used as drawknot node on steel suspension cable;Drawknot node sets as follows under steel suspension cable:Right-angled intersection sets the small pipe of oblique plastics to supportting in beam, Steel suspension cable is in the small pipe of oblique plastics, and right-angled intersection is used as drawknot node under steel suspension cable to support beam bottom main reinforcement welded suspending hook;
(7) prestressed stretch-draw is carried out to the steel suspension cable of first row supporting construction;
Tension sequence is using as follows:Using three tensioning, first time tensioning parameter is using as follows:Pretensioning arch brace model Enclose the steel suspension cable of interior upper drawknot node, then between tensioning arch brace and concrete capping beam in the range of upper drawknot node steel suspension cable, Then the steel suspension cable of drawknot node, scope between last tensioning arch brace and concrete capping beam are descended in the range of tensioning arch brace The steel suspension cable of interior lower drawknot node, tension stress uses the 30% of total tension stress.Second of tensioning parameter is using as follows:Pretensioning The steel suspension cable of upper drawknot node in the range of arch brace, then between tensioning arch brace and concrete capping beam in the range of upper drawknot node Steel suspension cable, then in the range of tensioning arch brace lower drawknot node steel suspension cable, last tensioning arch brace bears down on one with concrete The steel suspension cable of lower drawknot node in the range of between beam, tension stress uses the 60% of total tension stress.Third time tensioning parameter is used It is as follows:The steel suspension cable of upper drawknot node in the range of pretensioning arch brace, then model between tensioning arch brace and concrete capping beam The steel suspension cable of interior upper drawknot node is enclosed, the steel suspension cable of drawknot node, last tensioning arch brace are then descended in the range of tensioning arch brace The steel suspension cable of lower drawknot node in the range of between concrete capping beam, tension stress uses the 100% of total tension stress.
For different earth excavation depth and different spans, using different total stretching forces, as shown in table 1, different opens Dig depth or different spans determines total stretching force according to interpolation method.
Total stretching force under the different situations of table 1
(8) 2cm below earth excavation to second row supporting construction bottom absolute altitude;
(9) casting concrete waist rail;
(10) second row arch brace and right-angled intersection are poured to support beam concrete;
(11) steel pipe of second row supporting construction is set to support;
(12) the steel suspension cable drawknot node of second row supporting construction is set;Right-angled intersection is to support beam top main reinforcement welded suspending hook It is used as drawknot node on steel suspension cable;Drawknot node sets as follows under steel suspension cable:Right-angled intersection sets the small pipe of oblique plastics to supportting in beam, Steel suspension cable is in the small pipe of oblique plastics, and drawknot node is welded on right-angled intersection to support beam bottom main reinforcement under steel suspension cable;
(13) prestressed stretch-draw is carried out to the steel suspension cable of second row supporting construction;The steel suspension cable tensioning of second row supporting construction Parameter is identical with the steel suspension cable tensioning parameter of first row supporting construction;
(14) earthwork between second row arch brace and concrete breast beam is excavated to basement bottom board bottom absolute altitude;Retain the The earthwork is conducive to basement stable to form central island effect in the range of two row's arch braces;
(15) basement bottom board and sidewall of basement between second row arch brace and concrete breast beam are poured;In annulus The basement bottom board of support zone sets steel plate water stopper;
(16) earthwork is excavated in the range of second row arch brace to basement bottom board bottom absolute altitude;
(17) basement bottom board in the range of second row arch brace is poured;
(18) the steel suspension cable of second row supporting construction is first removed, then removes second row arch brace and right-angled intersection to support beam Concrete;
(19) the steel suspension cable of first row supporting construction is first removed, then removes first row arch brace and right-angled intersection to support beam Concrete.
When basement cutting depth is less than or equal to 3.5m, construction procedure includes:
(1) construction fender post;
(2) concrete capping beam is set at the top of fender post;
(3) when setting the Construction of Engineering Pile of steel lattice column, steel lattice column is inserted when engineering pile concrete is unhardened;
(4) arch brace and right-angled intersection are poured to support beam concrete;
(5) concrete cast-in-place slab of supporting construction is poured;
(6) the steel suspension cable drawknot node of supporting construction is set;Right-angled intersection is used as steel to support beam top main reinforcement welded suspending hook Drawknot node on suspension cable;Drawknot node sets as follows under steel suspension cable:Right-angled intersection in support beam to setting the small pipe of oblique plastics, steel suspension cable In the small pipe of oblique plastics, right-angled intersection is used as drawknot node under steel suspension cable to support beam bottom main reinforcement welded suspending hook;
(7) prestressed stretch-draw is carried out to the steel suspension cable of supporting construction;
Tension sequence is using as follows:Using three tensioning, first time tensioning parameter is using as follows:Pretensioning arch brace model Enclose the steel suspension cable of interior upper drawknot node, then between tensioning arch brace and concrete capping beam in the range of upper drawknot node steel suspension cable, Then the steel suspension cable of drawknot node, scope between last tensioning arch brace and concrete capping beam are descended in the range of tensioning arch brace The steel suspension cable of interior lower drawknot node, tension stress uses the 30% of total tension stress.Second of tensioning parameter is using as follows:Pretensioning The steel suspension cable of upper drawknot node in the range of arch brace, then between tensioning arch brace and concrete capping beam in the range of upper drawknot node Steel suspension cable, then in the range of tensioning arch brace lower drawknot node steel suspension cable, last tensioning arch brace bears down on one with concrete The steel suspension cable of lower drawknot node in the range of between beam, tension stress uses the 60% of total tension stress.Third time tensioning parameter is used It is as follows:The steel suspension cable of upper drawknot node in the range of pretensioning arch brace, then model between tensioning arch brace and concrete capping beam The steel suspension cable of interior upper drawknot node is enclosed, the steel suspension cable of drawknot node, last tensioning arch brace are then descended in the range of tensioning arch brace The steel suspension cable of lower drawknot node in the range of between concrete capping beam, tension stress uses the 100% of total tension stress.
(8) earthwork between arch brace and concrete capping beam is excavated to basement bottom board bottom absolute altitude;Retain annulus branch The earthwork is to form central island effect in the range of support;
(9) basement bottom board and sidewall of basement between arch brace and concrete capping beam are poured;In arch brace The basement bottom board at position sets steel plate water stopper;
(10) earthwork is excavated in the range of arch brace to basement bottom board bottom absolute altitude;
(11) basement bottom board in the range of arch brace is poured;
(12) the steel suspension cable of supporting construction is first removed, then removes arch brace and right-angled intersection to support beam concrete.
The present invention has the advantages that construction safety is reliable, cost is low.
Brief description of the drawings
Fig. 1, row's supporting construction elevational schematic view, Fig. 2, two row's supporting construction elevational schematic views, Fig. 3, row's supporting knot Structure floor map, Fig. 4, two row's supporting construction floor map, Fig. 5, right-angled intersection are to support beam bending moment envelope diagram.
In each accompanying drawing:1st, concrete capping beam, 2, right-angled intersection to support beam, 3, steel lattice column, 4, concrete cast-in-place slab, 5, Concrete breast beam, 6, steel pipe to support, 7, steel suspension cable, 8, prestressed stretch-draw pier.
Embodiment
Embodiment one
The present embodiment sets arch brace in the middle part of basement, and arch brace area is 50m2, arch brace center is ground At the centre of form of lower room geometry, arch brace is highly 600mm, and arch brace width is 300mm.
Basement set right-angled intersection to support beam 2, right-angled intersection to support beam 2 crosspoint basement geometry shape At the heart.Right-angled intersection is 700mm to the support height of beam 2, and right-angled intersection is 300mm to the support width of beam 2.
Arch brace sets steel lattice column 3, the insertion engineering pile of steel lattice column 3 to the support crossover sites of beam 2 with right-angled intersection 600mm, steel lattice column 3 is higher by the top surface absolute altitude 0.8m of concrete capping beam 1, and steel lattice column 3 sets prestressed stretch-draw pier 8 above.
Basement fender post uses cast-in-situ bored pile;Cast-in-situ bored pile periphery sets cement mixing pile water stopping curtain, cement The a diameter of 500mm of cement mixing pile that stirring pile water stopping curtain is used, adjacent cement mixing pile is mutually twisted 350mm;Drilling Concrete capping beam 1 is set at the top of bored concrete pile, and the width of concrete capping beam 1 is 300mm, is highly 600mm.
Basement cutting depth is 3m, and vertical plane uses row's supporting construction, in right-angled intersection to support beam 2 top 1/8 Span, 1/4 span, 3/4 span and 7/8 span position set drawknot node on steel suspension cable 7, in right-angled intersection to support beam 2 bottom 3/8 Span, 1/2 span and 5/8 span position set steel 7 times drawknot nodes of suspension cable, and the drawknot node set location of steel suspension cable 7 is according to moment of flexure Envelope diagram and obtain, these positions carry out prestressing force drawknot can make right-angled intersection to support the bending moment envelope diagram of beam 2 it is more reasonable; Right-angled intersection is converted to pulling force to the support axle power of beam 2 by the prestressing force drawknot of steel suspension cable 7 and pass to steel lattice column 3.Steel suspension cable 7 Using prestressed stretch-draw.Four corners set concrete cast-in-place slab 4, and the area of concrete cast-in-place slab 4 is 8m2, concrete cast-in-place slab 4 Thickness is 12~15mm, and arrangement of reinforcement uses a diameter of 12~14mm.
Construction procedure includes:
(1) construction fender post;
(2) concrete capping beam 1 is set at the top of fender post;
(3) when setting the Construction of Engineering Pile of steel lattice column 3, steel lattice column 3 is inserted when engineering pile concrete is unhardened;
(4) arch brace and right-angled intersection are poured to the support concrete of beam 2;
(5) concrete cast-in-place slab 4 of supporting construction is poured;
(6) drawknot node of steel suspension cable 7 of supporting construction is set;Right-angled intersection is to the support top main reinforcement welded suspending hook conduct of beam 2 Drawknot node on steel suspension cable 7;7 times drawknot nodes of steel suspension cable set as follows:Right-angled intersection sets the small pipe of oblique plastics to supportting in beam 2, Steel suspension cable 7 is in the small pipe of oblique plastics, and right-angled intersection is used as 7 times drawknots of steel suspension cable to the support bottom main reinforcement welded suspending hook of beam 2 Point;
(7) prestressed stretch-draw is carried out to the steel suspension cable 7 of supporting construction;
Tension sequence is using as follows:Using three tensioning, first time tensioning parameter is using as follows:Pretensioning arch brace model Enclose the steel suspension cable 7 of interior upper drawknot node, then between tensioning arch brace and concrete capping beam 1 in the range of upper drawknot node steel suspension cable 7, the steel suspension cable 7 of drawknot node is then descended in the range of tensioning arch brace, between last tensioning arch brace and concrete capping beam 1 In the range of lower drawknot node steel suspension cable 7, tension stress uses the 30% of total tension stress.Second of tensioning parameter is using as follows: The steel suspension cable 7 of upper drawknot node in the range of pretensioning arch brace, then between tensioning arch brace and concrete capping beam 1 in the range of The steel suspension cable 7 of upper drawknot node, then in the range of tensioning arch brace lower drawknot node steel suspension cable 7, last tensioning arch brace with The steel suspension cable 7 of lower drawknot node in the range of between concrete capping beam 1, tension stress uses the 60% of total tension stress.For the third time Tensioning parameter is using as follows:The steel suspension cable 7 of upper drawknot node in the range of pretensioning arch brace, then tensioning arch brace and concrete The steel suspension cable 7 of drawknot node in the range of between capping beam 1, then descends the steel suspension cable 7 of drawknot node, most in the range of tensioning arch brace The steel suspension cable 7 of lower drawknot node in the range of between post-stretching arch brace and concrete capping beam 1, tension stress should using total tensioning The 100% of power.Total stretching force uses 1.417MPa.
(8) earthwork between arch brace and concrete capping beam 1 is excavated to basement bottom board bottom absolute altitude;Retain annulus branch The earthwork is to form central island effect in the range of support;
(9) basement bottom board and sidewall of basement between arch brace and concrete capping beam 1 are poured;In arch brace The basement bottom board at position sets steel plate water stopper;
(10) earthwork is excavated in the range of arch brace to basement bottom board bottom absolute altitude;
(11) basement bottom board in the range of arch brace is poured;
(12) the steel suspension cable 7 of supporting construction is first removed, then removes arch brace and right-angled intersection to the support concrete of beam 2.
Embodiment two
The present embodiment sets arch brace in the middle part of basement, and arch brace area is 50m2, arch brace center is ground At the centre of form of lower room geometry, arch brace is highly 600mm, and arch brace width is 300mm.
Basement set right-angled intersection to support beam 2, right-angled intersection to support beam 2 crosspoint basement geometry shape At the heart.Right-angled intersection is 700mm to the support height of beam 2, and right-angled intersection is 300mm to the support width of beam 2.
Arch brace sets steel lattice column 3, the insertion engineering pile of steel lattice column 3 to the support crossover sites of beam 2 with right-angled intersection 600mm, steel lattice column 3 is higher by the top surface absolute altitude 0.8m of concrete capping beam 1, and steel lattice column 3 sets prestressed stretch-draw pier 8 above.
Basement fender post uses cast-in-situ bored pile;Cast-in-situ bored pile periphery sets cement mixing pile water stopping curtain, cement The a diameter of 500mm of cement mixing pile that stirring pile water stopping curtain is used, adjacent cement mixing pile is mutually twisted 350mm;Drilling Concrete capping beam 1 is set at the top of bored concrete pile, and the width of concrete capping beam 1 is 300mm, is highly 600mm;When basement is excavated When depth is more than or equal to 3.5m, concrete breast beam 5 is set, and the set location of concrete breast beam 5 is in vertical plane in the middle part of basement It is identical with concrete capping beam 1, the width of concrete breast beam 5 is 300mm, is highly 600mm.
When basement cutting depth is 4.8m, vertical plane uses two row's supporting construction;First row supporting construction is in cross The span of 2 top of cross-pair support beam 1/8,1/4 span, 3/4 span and 7/8 span position set drawknot node on steel suspension cable 7, in cross The span of 2 bottom of cross-pair support beam 3/8,1/2 span and 5/8 span position set steel 7 times drawknot nodes of suspension cable, and four corners set mixed Solidifying soil Bars In Poured Concrete Slab 4, the area of concrete cast-in-place slab 4 is 8m2, the thickness of concrete cast-in-place slab 4 is 12~15mm, and arrangement of reinforcement is using a diameter of 12~14mm.Second row supporting construction is arranged at the 1/2 of cutting depth, and second row supporting construction is in right-angled intersection to support beam 2 The span of top 1/8,1/4 span, 3/4 span and 7/8 span position set drawknot node on steel suspension cable 7, in right-angled intersection to support beam 2 The span of bottom 3/8,1/2 span and 5/8 span position set steel 7 times drawknot nodes of suspension cable, and steel suspension cable 7 uses prestressed stretch-draw. Steel pipe is set between arch brace and concrete capping beam 1 to support 6.
Construction procedure includes:
(1) construction fender post;
(2) concrete capping beam 1 is set at the top of fender post;
(3) when setting the Construction of Engineering Pile of steel lattice column 3, steel lattice column 3 is inserted when engineering pile concrete is unhardened;
(4) first row arch brace and first row right-angled intersection are poured to the support concrete of beam 2;
(5) concrete cast-in-place slab 4 of first row supporting construction is poured;
(6) drawknot node of steel suspension cable 7 of first row supporting construction is set;Right-angled intersection is hung to the top main reinforcement welding of support beam 2 Hook is used as drawknot node on steel suspension cable 7;7 times drawknot nodes of steel suspension cable set as follows:Right-angled intersection in support beam 2 to setting oblique plastics small Pipe, steel suspension cable 7 is in the small pipe of oblique plastics, and right-angled intersection is to the support bottom main reinforcement welded suspending hook of beam 2 as under steel suspension cable 7 Drawknot node;
(7) prestressed stretch-draw is carried out to the steel suspension cable 7 of first row supporting construction;
Tension sequence is using as follows:Using three tensioning, first time tensioning parameter is using as follows:Pretensioning arch brace model Enclose the steel suspension cable 7 of interior upper drawknot node, then between tensioning arch brace and concrete capping beam 1 in the range of upper drawknot node steel suspension cable 7, the steel suspension cable 7 of drawknot node is then descended in the range of tensioning arch brace, between last tensioning arch brace and concrete capping beam 1 In the range of lower drawknot node steel suspension cable 7, tension stress uses the 30% of total tension stress.Second of tensioning parameter is using as follows: The steel suspension cable 7 of upper drawknot node in the range of pretensioning arch brace, then between tensioning arch brace and concrete capping beam 1 in the range of The steel suspension cable 7 of upper drawknot node, then in the range of tensioning arch brace lower drawknot node steel suspension cable 7, last tensioning arch brace with The steel suspension cable 7 of lower drawknot node in the range of between concrete capping beam 1, tension stress uses the 60% of total tension stress.For the third time Tensioning parameter is using as follows:The steel suspension cable 7 of upper drawknot node in the range of pretensioning arch brace, then tensioning arch brace and concrete The steel suspension cable 7 of drawknot node in the range of between capping beam 1, then descends the steel suspension cable 7 of drawknot node, most in the range of tensioning arch brace The steel suspension cable 7 of lower drawknot node in the range of between post-stretching arch brace and concrete capping beam 1, tension stress should using total tensioning The 100% of power.Total stretching force uses 0.907MPa.
(8) 2cm below earth excavation to second row supporting construction bottom absolute altitude;
(9) casting concrete waist rail 5;
(10) second row arch brace and right-angled intersection are poured to the support concrete of beam 2;
(11) steel pipe of second row supporting construction is set to support 6;
(12) drawknot node of steel suspension cable 7 of second row supporting construction is set;Right-angled intersection is hung to the top main reinforcement welding of support beam 2 Hook is used as drawknot node on steel suspension cable 7;7 times drawknot nodes of steel suspension cable set as follows:Right-angled intersection in support beam 2 to setting oblique plastics small Pipe, steel suspension cable 7 is in the small pipe of oblique plastics, and 7 times drawknot nodes of steel suspension cable are welded on right-angled intersection to the support main steel in the bottom of beam 2 Muscle;
(13) prestressed stretch-draw is carried out to the steel suspension cable 7 of second row supporting construction;The steel suspension cable of second row supporting construction 7 Draw parameter identical with the tensioning parameter of steel suspension cable 7 of first row supporting construction;
(14) earthwork between second row arch brace and concrete breast beam 5 is excavated to basement bottom board bottom absolute altitude;Retain The earthwork is conducive to basement stable to form central island effect in the range of second row arch brace;
(15) basement bottom board and sidewall of basement between second row arch brace and concrete breast beam 5 are poured;In circle The basement bottom board of ring support zone sets steel plate water stopper;
(16) earthwork is excavated in the range of second row arch brace to basement bottom board bottom absolute altitude;
(17) basement bottom board in the range of second row arch brace is poured;
(18) the steel suspension cable 7 of second row supporting construction is first removed, then removes second row arch brace and right-angled intersection to support The concrete of beam 2;
(19) the steel suspension cable 7 of first row supporting construction is first removed, then removes first row arch brace and right-angled intersection to support The concrete of beam 2.

Claims (7)

1. a kind of basement supporting construction, it is characterized in that set arch brace in the middle part of basement, arch brace area is 30~ 80m2, arch brace center is that at the centre of form of basement geometry, arch brace is highly 500~700mm, and arch brace is wide Spend for 250~300mm;
Basement sets right-angled intersection to support beam, and right-angled intersection is to supportting the crosspoint of beam at the centre of form of basement geometry; Right-angled intersection is 600~800mm to support depth of beam, and right-angled intersection is 250~300mm to support beam width;
Arch brace and right-angled intersection set steel lattice column to support beam crossover sites, and steel lattice column insertion engineering pile 500~ 600mm, steel lattice column is higher by concrete and beared down on one top surface of the beam 0.7~0.9m of absolute altitude, and prestressed stretch-draw pier is set above steel lattice column;
Basement fender post uses cast-in-situ bored pile;Cast-in-situ bored pile periphery sets cement mixing pile water stopping curtain;Drill-pouring Stake top portion sets concrete capping beam, and concrete bears down on one beam width for 300mm, is highly 500~600mm;When basement is excavated When depth is more than or equal to 3.5m, concrete breast beam is set in the middle part of basement, concrete breast beam set location in vertical plane with Concrete capping beam is identical, and concrete breast beam width is 300mm, is highly 500~600mm;
When basement cutting depth is less than or equal to 3.5m, vertical plane uses row's supporting construction, in right-angled intersection to support beam The span of top 1/8,1/4 span, 3/4 span and 7/8 span position set drawknot node on steel suspension cable, in right-angled intersection under support beam The span of portion 3/8,1/2 span and 5/8 span position set drawknot node under steel suspension cable;Steel suspension cable uses prestressed stretch-draw;Four angles Portion sets concrete cast-in-place slab;
When basement cutting depth is more than 3.5m, vertical plane uses two row's supporting construction;First row supporting construction is in cross The span of cross-pair support beam top 1/8,1/4 span, 3/4 span and 7/8 span position set drawknot node on steel suspension cable, are handed in cross Fork sets drawknot node under steel suspension cable to the span of support beam bottom 3/8,1/2 span and 5/8 span position, and four corners set concrete Bars In Poured Concrete Slab;Second row supporting construction is arranged at the 1/2 of cutting depth, and second row supporting construction is in right-angled intersection to support beam top 1/8 span, 1/4 span, 3/4 span and 7/8 span position set drawknot node on steel suspension cable, in right-angled intersection to support beam bottom 3/ 8 spans, 1/2 span and 5/8 span position set drawknot node under steel suspension cable, and steel suspension cable uses prestressed stretch-draw;In arch brace Steel pipe is set between concrete capping beam to support.
2. basement supporting construction according to claim 1, it is characterized in that the water that cement mixing pile water stopping curtain is used The a diameter of 500mm of mud mixing pile, adjacent cement mixing pile is mutually twisted 300~400mm.
3. basement supporting construction according to claim 1, it is characterized in that concrete cast-in-situ plate suqare is more than or equal to 5m2.It is mixed It is 12~15mm to coagulate native cast-in-place plate thickness, and arrangement of reinforcement uses a diameter of 12~14mm.
4. basement supporting construction according to claim 1, it is characterized in that when basement cutting depth is more than 3.5m, applying Work step includes suddenly:
(1) construction fender post;
(2) concrete capping beam is set at the top of fender post;
(3) when setting the Construction of Engineering Pile of steel lattice column, steel lattice column is inserted when engineering pile concrete is unhardened;
(4) first row arch brace and first row right-angled intersection are poured to support beam concrete;
(5) concrete cast-in-place slab of first row supporting construction is poured;
(6) the steel suspension cable drawknot node of first row supporting construction is set;Right-angled intersection is to support beam top main reinforcement welded suspending hook conduct Drawknot node on steel suspension cable;Drawknot node sets as follows under steel suspension cable:Right-angled intersection in support beam to setting the small pipe of oblique plastics, and steel hangs Rope is in the small pipe of oblique plastics, and right-angled intersection is used as drawknot node under steel suspension cable to support beam bottom main reinforcement welded suspending hook;
(7) prestressed stretch-draw is carried out to the steel suspension cable of first row supporting construction;
(8) 2cm below earth excavation to second row supporting construction bottom absolute altitude;
(9) casting concrete waist rail;
(10) second row arch brace and right-angled intersection are poured to support beam concrete;
(11) steel pipe of second row supporting construction is set to support;
(12) the steel suspension cable drawknot node of second row supporting construction is set;Right-angled intersection is to support beam top main reinforcement welded suspending hook conduct Drawknot node on steel suspension cable;Drawknot node sets as follows under steel suspension cable:Right-angled intersection in support beam to setting the small pipe of oblique plastics, and steel hangs Rope is in the small pipe of oblique plastics, and drawknot node is welded on right-angled intersection to support beam bottom main reinforcement under steel suspension cable;
(13) prestressed stretch-draw is carried out to the steel suspension cable of second row supporting construction;The steel suspension cable tensioning parameter of second row supporting construction It is identical with the steel suspension cable tensioning parameter of first row supporting construction;
(14) earthwork between second row arch brace and concrete breast beam is excavated to basement bottom board bottom absolute altitude;Retain second row The earthwork is conducive to basement stable to form central island effect in the range of arch brace;
(15) basement bottom board and sidewall of basement between second row arch brace and concrete breast beam are poured;In arch brace The basement bottom board at position sets steel plate water stopper;
(16) earthwork is excavated in the range of second row arch brace to basement bottom board bottom absolute altitude;
(17) basement bottom board in the range of second row arch brace is poured;
(18) the steel suspension cable of second row supporting construction is first removed, then removes second row arch brace and right-angled intersection to support beam coagulation Soil;
(19) the steel suspension cable of first row supporting construction is first removed, then removes first row arch brace and right-angled intersection to support beam coagulation Soil.
5. basement supporting construction according to claim 1, it is characterized in that when basement cutting depth is less than or equal to 3.5m When, construction procedure includes:
(1) construction fender post;
(2) concrete capping beam is set at the top of fender post;
(3) when setting the Construction of Engineering Pile of steel lattice column, steel lattice column is inserted when engineering pile concrete is unhardened;
(4) first row arch brace and first row right-angled intersection are poured to support beam concrete;
(5) concrete cast-in-place slab of first row supporting construction is poured;
(6) the steel suspension cable drawknot node of first row supporting construction is set;Right-angled intersection is to support beam top main reinforcement welded suspending hook conduct Drawknot node on steel suspension cable;Drawknot node sets as follows under steel suspension cable:Right-angled intersection in support beam to setting the small pipe of oblique plastics, and steel hangs Rope is in the small pipe of oblique plastics, and right-angled intersection is used as drawknot node under steel suspension cable to support beam bottom main reinforcement welded suspending hook;
(7) prestressed stretch-draw is carried out to the steel suspension cable of first row supporting construction;
(8) earthwork between arch brace and concrete capping beam is excavated to basement bottom board bottom absolute altitude;Retain arch brace model The interior earthwork is enclosed to form central island effect;
(9) basement bottom board and sidewall of basement between arch brace and concrete capping beam are poured;At arch brace position Basement bottom board set steel plate water stopper;
(10) earthwork is excavated in the range of arch brace to basement bottom board bottom absolute altitude;
(11) basement bottom board in the range of arch brace is poured.
(12) the steel suspension cable of supporting construction is first removed, then removes arch brace and right-angled intersection to support beam concrete.
6. basement supporting construction according to claim 1, it is characterized in that tension sequence is using as follows:Using three times Draw, first time tensioning parameter is using as follows:The steel suspension cable of upper drawknot node in the range of pretensioning arch brace, then tensioning arch brace The steel suspension cable of upper drawknot node in the range of between concrete capping beam, then the steel of lower drawknot node hangs in the range of tensioning arch brace Rope, between last tensioning arch brace and concrete capping beam in the range of lower drawknot node steel suspension cable, tension stress is using total The 30% of tension;Second of tensioning parameter is using as follows:The steel suspension cable of upper drawknot node in the range of pretensioning arch brace, then open The steel suspension cable of upper drawknot node in the range of between arch brace and concrete capping beam is drawn, is then pulled down in the range of tensioning arch brace The steel suspension cable of node, between last tensioning arch brace and concrete capping beam in the range of lower drawknot node steel suspension cable, tensioning should Power uses the 60% of total tension stress;Third time tensioning parameter is using as follows:Upper drawknot node in the range of pretensioning arch brace The steel suspension cable of drawknot node is gone up in the range of between steel suspension cable, then tensioning arch brace and concrete capping beam, then tensioning annulus branch The steel suspension cable of lower drawknot node in the range of support, between last tensioning arch brace and concrete capping beam in the range of lower drawknot node steel Suspension cable, tension stress uses the 100% of total tension stress.
7. basement supporting construction according to claim 1, it is characterized in that for different earth excavation depth and it is different across Degree, using different total stretching forces, as shown in table 1, different cutting depths or different spans are determined according to interpolation method Total stretching force;
Total stretching force under the different situations of table 1
CN201710635355.1A 2017-07-30 2017-07-30 Basement supporting construction Active CN107227741B (en)

Priority Applications (5)

Application Number Priority Date Filing Date Title
CN201810920784.8A CN108951654B (en) 2017-07-30 2017-07-30 Support construction method for basements with different excavation depths
CN201710635355.1A CN107227741B (en) 2017-07-30 2017-07-30 Basement supporting construction
CN201810927295.5A CN108951655B (en) 2017-07-30 2017-07-30 Basement supporting structure under prestress tensioning condition
CN201810920743.9A CN108930273B (en) 2017-07-30 2017-07-30 Basement supporting construction method
CN201810920824.9A CN108930274B (en) 2017-07-30 2017-07-30 Basement supporting construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710635355.1A CN107227741B (en) 2017-07-30 2017-07-30 Basement supporting construction

Related Child Applications (4)

Application Number Title Priority Date Filing Date
CN201810920784.8A Division CN108951654B (en) 2017-07-30 2017-07-30 Support construction method for basements with different excavation depths
CN201810927295.5A Division CN108951655B (en) 2017-07-30 2017-07-30 Basement supporting structure under prestress tensioning condition
CN201810920824.9A Division CN108930274B (en) 2017-07-30 2017-07-30 Basement supporting construction method
CN201810920743.9A Division CN108930273B (en) 2017-07-30 2017-07-30 Basement supporting construction method

Publications (2)

Publication Number Publication Date
CN107227741A true CN107227741A (en) 2017-10-03
CN107227741B CN107227741B (en) 2018-12-14

Family

ID=59956648

Family Applications (5)

Application Number Title Priority Date Filing Date
CN201810920784.8A Active CN108951654B (en) 2017-07-30 2017-07-30 Support construction method for basements with different excavation depths
CN201810927295.5A Active CN108951655B (en) 2017-07-30 2017-07-30 Basement supporting structure under prestress tensioning condition
CN201810920824.9A Active CN108930274B (en) 2017-07-30 2017-07-30 Basement supporting construction method
CN201710635355.1A Active CN107227741B (en) 2017-07-30 2017-07-30 Basement supporting construction
CN201810920743.9A Active CN108930273B (en) 2017-07-30 2017-07-30 Basement supporting construction method

Family Applications Before (3)

Application Number Title Priority Date Filing Date
CN201810920784.8A Active CN108951654B (en) 2017-07-30 2017-07-30 Support construction method for basements with different excavation depths
CN201810927295.5A Active CN108951655B (en) 2017-07-30 2017-07-30 Basement supporting structure under prestress tensioning condition
CN201810920824.9A Active CN108930274B (en) 2017-07-30 2017-07-30 Basement supporting construction method

Family Applications After (1)

Application Number Title Priority Date Filing Date
CN201810920743.9A Active CN108930273B (en) 2017-07-30 2017-07-30 Basement supporting construction method

Country Status (1)

Country Link
CN (5) CN108951654B (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108487261A (en) * 2018-04-10 2018-09-04 江西科技学院 A kind of arch steel structure support
CN107605172B (en) * 2017-10-16 2020-04-17 叶长青 Construction method for reinforcing structure of concrete roof beam

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110397042A (en) * 2019-07-13 2019-11-01 济邦建设集团有限公司 A kind of support system of deep basal pit

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20110024554A (en) * 2009-09-02 2011-03-09 (주)이랜드건설 Support structures for retaining wall and construction method thereof
CN102828520A (en) * 2012-09-11 2012-12-19 中煤科工集团武汉设计研究院中汉岩土工程分公司 Ring-shaped inner supporting structure used in deep peat soil deep foundation pit
KR20150060081A (en) * 2013-11-25 2015-06-03 (주)써포텍 Waling structure for innovative prestressed scaffolding
CN104727324A (en) * 2015-03-20 2015-06-24 朱奎 Support construction method of irregular basement
CN105421468A (en) * 2015-11-24 2016-03-23 叶长青 Basement support without concrete diagonal brace
KR20160057747A (en) * 2014-11-14 2016-05-24 우경기술주식회사 Prestressed wale for temporary facility
CN105862878A (en) * 2016-05-30 2016-08-17 建研地基基础工程有限责任公司 Supporting system for deep foundation pit
CN105926637A (en) * 2016-06-28 2016-09-07 吴龙梁 Prestressing force support system for protecting existing subway and design and construction method

Family Cites Families (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2835351Y (en) * 2005-10-14 2006-11-08 浙江中成建工集团有限公司 Horizontal supporting structure for reinforced concrete loop truss in deep foundation pit
CN101615212B (en) * 2009-07-28 2011-10-26 武汉理工大学 Simplified design calculation method of piling-inner supporting system
CN101666095B (en) * 2009-09-11 2011-11-23 温州市金誉建设监理有限公司 Irregular foundation pit support and construction method
CN102660955B (en) * 2012-05-17 2015-05-13 上海强劲地基工程股份有限公司 Quick construction method for foundation pit slope support
CN203834487U (en) * 2014-04-10 2014-09-17 中国十五冶金建设集团有限公司 Section steel inner brace and Lassen pile support for excavation of dumbbell-shaped deep and large foundation pit
CN105887891A (en) * 2016-04-16 2016-08-24 朱奎 Deep basement supporting construction method

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20110024554A (en) * 2009-09-02 2011-03-09 (주)이랜드건설 Support structures for retaining wall and construction method thereof
CN102828520A (en) * 2012-09-11 2012-12-19 中煤科工集团武汉设计研究院中汉岩土工程分公司 Ring-shaped inner supporting structure used in deep peat soil deep foundation pit
KR20150060081A (en) * 2013-11-25 2015-06-03 (주)써포텍 Waling structure for innovative prestressed scaffolding
KR20160057747A (en) * 2014-11-14 2016-05-24 우경기술주식회사 Prestressed wale for temporary facility
CN104727324A (en) * 2015-03-20 2015-06-24 朱奎 Support construction method of irregular basement
CN105421468A (en) * 2015-11-24 2016-03-23 叶长青 Basement support without concrete diagonal brace
CN105862878A (en) * 2016-05-30 2016-08-17 建研地基基础工程有限责任公司 Supporting system for deep foundation pit
CN105926637A (en) * 2016-06-28 2016-09-07 吴龙梁 Prestressing force support system for protecting existing subway and design and construction method

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107605172B (en) * 2017-10-16 2020-04-17 叶长青 Construction method for reinforcing structure of concrete roof beam
CN108487261A (en) * 2018-04-10 2018-09-04 江西科技学院 A kind of arch steel structure support

Also Published As

Publication number Publication date
CN108951655A (en) 2018-12-07
CN107227741B (en) 2018-12-14
CN108930274A (en) 2018-12-04
CN108951654B (en) 2020-09-15
CN108951655B (en) 2020-09-15
CN108930273A (en) 2018-12-04
CN108930274B (en) 2020-10-27
CN108951654A (en) 2018-12-07
CN108930273B (en) 2020-09-15

Similar Documents

Publication Publication Date Title
CN103485363B (en) Three-dimensional continuous frame formula reinforced concrete structure retaining wall
CN104389313A (en) Positioning perpendicularity adjusting device and method of dual-spliced I-shaped steel latticed column
CN105951747B (en) A kind of construction method of the pre-buried lattice column of contrary sequence method
CN107313431A (en) Close on not contour foundation ditch method for synchronously constructing
CN105587320B (en) Rich water sand-pebble layer abnormal shape deep shaft structural system and its construction method
CN103938634B (en) A kind of deep foundation pit supporting structure and construction method
CN203174619U (en) Reverse raft concrete terrace
CN102864781A (en) Foundation pit supporting method utilizing inclined piles
CN206467667U (en) Suspended net shotcrete building enclosure between a kind of stake of use expansion type fixation reinforced mesh
CN107227741A (en) Basement supporting construction
CN108360535A (en) Foundation pit supporting construction based on campshed and inner support and its construction method
CN112195779A (en) Multifunctional trestle construction method suitable for thick pebble layer
CN101718098A (en) Micro-pile combined dug composite foundation and construction method thereof
CN109610473A (en) A kind of construction method of the large-scale pool structure foundation pit supporting system of municipal administration
CN205576990U (en) Cross section and wear bridge pier tunnel slip casting supporting construction
CN107299640A (en) A kind of variable cross-section well shaft type ground continuous wall base and its construction method
CN209339171U (en) A kind of transmission line of electricity assembled sheet pile composite foundation
CN208167770U (en) Assembled drilledpier foundation
CN111042161A (en) Slope collapse high slope flexible processing structure and construction method thereof
CN207244633U (en) Brick retaining wall steel bar girder hardened system on foundation pit enclosure top beam
CN216515701U (en) Miniature stake raft board combination foundation structure
CN203498863U (en) Three-dimensional continuous-frame-type reinforced concrete structural retaining wall
CN206667263U (en) A kind of foundation pit supporting construction
CN207260158U (en) One layer of basement supporting construction
CN101851931B (en) Sinking well with secondary support device and construction method thereof

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
TR01 Transfer of patent right

Effective date of registration: 20201123

Address after: No. 100, North Ring Road, Hede Town, Sheyang County, Yancheng City, Jiangsu Province

Patentee after: Gu Yaobin

Address before: 325000 Jinchuan Road, Tianhe street, Wenzhou economic and Technological Development Zone, Wenzhou City, Zhejiang Province, No. 4

Patentee before: Ye Changqing

TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20230109

Address after: 276100 1 Kaiyuan Road, economic development zone, Tancheng County, Linyi City, Shandong Province

Patentee after: Linyi Jiechuang Chemical Industrial Park Co.,Ltd.

Address before: No. 100, North Ring Road, Hede Town, Sheyang County, Yancheng City, Jiangsu Province

Patentee before: Gu Yaobin

TR01 Transfer of patent right