CN107194480A - A kind of maintenance management method for being used to realize building pipeline three-dimensional localization - Google Patents

A kind of maintenance management method for being used to realize building pipeline three-dimensional localization Download PDF

Info

Publication number
CN107194480A
CN107194480A CN201710594195.0A CN201710594195A CN107194480A CN 107194480 A CN107194480 A CN 107194480A CN 201710594195 A CN201710594195 A CN 201710594195A CN 107194480 A CN107194480 A CN 107194480A
Authority
CN
China
Prior art keywords
pipeline
building
sensor
dimensional
management method
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201710594195.0A
Other languages
Chinese (zh)
Inventor
武长斌
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Tianjin Sheng Yuan Hong Yu Technology Co Ltd
Original Assignee
Tianjin Sheng Yuan Hong Yu Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Tianjin Sheng Yuan Hong Yu Technology Co Ltd filed Critical Tianjin Sheng Yuan Hong Yu Technology Co Ltd
Priority to CN201710594195.0A priority Critical patent/CN107194480A/en
Publication of CN107194480A publication Critical patent/CN107194480A/en
Pending legal-status Critical Current

Links

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/20Administration of product repair or maintenance
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
    • G06Q50/06Energy or water supply
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06TIMAGE DATA PROCESSING OR GENERATION, IN GENERAL
    • G06T19/00Manipulating 3D models or images for computer graphics
    • G06T19/003Navigation within 3D models or images
    • HELECTRICITY
    • H04ELECTRIC COMMUNICATION TECHNIQUE
    • H04LTRANSMISSION OF DIGITAL INFORMATION, e.g. TELEGRAPHIC COMMUNICATION
    • H04L67/00Network arrangements or protocols for supporting network services or applications
    • H04L67/01Protocols
    • H04L67/02Protocols based on web technology, e.g. hypertext transfer protocol [HTTP]
    • H04L67/025Protocols based on web technology, e.g. hypertext transfer protocol [HTTP] for remote control or remote monitoring of applications
    • HELECTRICITY
    • H04ELECTRIC COMMUNICATION TECHNIQUE
    • H04LTRANSMISSION OF DIGITAL INFORMATION, e.g. TELEGRAPHIC COMMUNICATION
    • H04L67/00Network arrangements or protocols for supporting network services or applications
    • H04L67/01Protocols
    • H04L67/12Protocols specially adapted for proprietary or special-purpose networking environments, e.g. medical networks, sensor networks, networks in vehicles or remote metering networks

Landscapes

  • Engineering & Computer Science (AREA)
  • Business, Economics & Management (AREA)
  • General Physics & Mathematics (AREA)
  • Health & Medical Sciences (AREA)
  • Economics (AREA)
  • Human Resources & Organizations (AREA)
  • Theoretical Computer Science (AREA)
  • Physics & Mathematics (AREA)
  • Marketing (AREA)
  • General Health & Medical Sciences (AREA)
  • Signal Processing (AREA)
  • Computer Networks & Wireless Communication (AREA)
  • Software Systems (AREA)
  • General Business, Economics & Management (AREA)
  • Tourism & Hospitality (AREA)
  • Strategic Management (AREA)
  • Radar, Positioning & Navigation (AREA)
  • Quality & Reliability (AREA)
  • Remote Sensing (AREA)
  • Entrepreneurship & Innovation (AREA)
  • Computer Graphics (AREA)
  • Computer Hardware Design (AREA)
  • Operations Research (AREA)
  • Computing Systems (AREA)
  • Public Health (AREA)
  • Medical Informatics (AREA)
  • General Engineering & Computer Science (AREA)
  • Water Supply & Treatment (AREA)
  • Primary Health Care (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The present invention provides a kind of maintenance management method for being used to realize building pipeline three-dimensional localization, comprise the following steps, the electronic image for building the three-dimensional drawing of pipeline is transmitted to cloud server, building pipeline is per one detecting sensor of installation separated by a distance in construction wall, and it electrically connects control computer by signal wire;Test signal is transported to control computer by sensor;Control computer reports to cloud server automatically according to coding lookup bad point, and by coded data;Cloud server is alarmed, and alarm point position is sent to the mobile special equipment of specified maintenance personal, and cloud server is automatically by the surrounding buildingses pipeline three-dimensional model transmitting of building conduit failure point position to mobile special equipment;It is corresponding with building infield scape position that maintenance personal makes to move special equipment picture position, quickly to position bad point position.The beneficial effects of the invention are as follows:This is designed to quick and is accurately positioned bad point position, and its is simple to operate, with low cost, can be obviously improved pipeline maintenance efficiency.

Description

A kind of maintenance management method for being used to realize building pipeline three-dimensional localization
Technical field
Technical field is maintained the present invention relates to pipeline, is used to realize building pipeline three-dimensional localization more particularly, to one kind Maintenance management method.
Background technology
In recent years, as building building technology is growing, high-rise building quantity is more and more, then every in high-rise building Water supply, supply and power supply of individual indoor wall inside or outer wall etc. are required to install corresponding pipeline, can so protect The regular supply of water, gas and electricity is demonstrate,proved, normal life and work in building is enabled people to.
Because the building quantity in each city is more and more, so pipeline is installed circuit and will become increasingly complex accordingly. Therefore for pipeline service worker, it is very difficult how quickly to position pipeline bad point position because maintenance employee need by Level determination building position, house location, wall locations and conduit positions, so building pipeline bad point position determines that work extremely consumes When, this is that maintenance employee pipeline service work brings very big puzzlement.
As can be seen here, a kind of maintenance management method for being used to realize building pipeline three-dimensional localization how is worked out, can be fast Speed is simultaneously accurately positioned bad point position, and this method is simple to operate, with low cost, is that current those skilled in the art are urgently to be resolved hurrily Problem.
The content of the invention
In order to solve the above problems, the invention provides a kind of maintenance management side for being used to realize building pipeline three-dimensional localization Method.
A kind of maintenance management method for being used to realize building pipeline three-dimensional localization of the present invention, is mainly included the following steps that:
(a) electronic image for building the three-dimensional drawing of pipeline is inputted to input equipment, the input equipment is believed by network Number the electronic image is transmitted to cloud server, and server is saved backup beyond the clouds;
(b) the building pipeline is provided with for perceiving channel interior pressure change per separated by a distance in construction wall With the sensor of detection circuit operation, the sensor electrically connects the control calculating for building pipeline Central Control Room by signal wire It is parallel-connection structure between machine, the sensor;Test signal is constantly transported to the control and calculated by each sensor in a steady stream In machine, test signal just accordingly changes if pressure in pipeline changes, and such staff just can be by controlling to calculate Machine understands the working condition of building pipeline in real time;
(c) each sensor is provided with unique encodings, and the control computer can be according to the coding lookup to building The damage position of pipeline is built, and coded data is reported into the cloud server by network signal automatically;
(d) alarmed after the cloud server data processing, while showing the sensor building pipeline section Point position, and the point position for building conduit failure alarm is sent to the mobile special equipment of specified maintenance personal, the high in the clouds clothes Business device automatically will surrounding buildingses threedimensional model where building conduit failure point position and building pipeline three-dimensional model transmitting to maintenance people In the mobile special equipment of member;
(e) maintenance personal is reached behind building conduit failure point position, the picture position that the mobile special equipment passes through display screen Putting adjustment makes corresponding with building infield scape position with picture position, and is perceived building wall inner tube road by three-dimensional perspective mode Come, maintenance personal's movement mobile special equipment display picture, which is shown, to be moved, to reach building pipeline and point position alarm signal Breath is corresponding with wall space, quickly to position bad point position to be repaired.
Further, the input equipment is computer.
Further, the mobile special equipment is any one in smart mobile phone, tablet personal computer and virtual reality glasses Kind.
Further, the display screen of the mobile special equipment is LED display.
Further, the network signal is 3G, 4G network signal and/or WIFI network signal.
Further, the original material of the three-dimensional drawing of building pipeline includes building pipeline three dimensional design drawing and building Pipeline practice of construction drawing.
Further, the pipeline includes being water delivery pipeline, gas pipeline and circuit protection pipeline.
Further, it is internal in the mobile special equipment that electronic gyroscope, gravity sensing equipment, position sensing are installed Device and GPS positioning device, so as to the real-time adjustment of the mobile special equipment display screen position of display image, make it interior with building Scene is quickly corresponded to.
Further, the sensor includes hydraulic pressure sensor, power detection sensor and gas leakage detection sensor And the digiverter electrically connected with the sensor.
The present invention it is a kind of be used for realize building pipeline three-dimensional localization maintenance management method, compared with prior art with Lower advantage:
This is used to realize in the maintenance management method for building pipeline three-dimensional localization, passes through and combine the modernization network technology and pressure Power measuring technology causes the pressure in corresponding building pipeline section just can be from the control computer of Central Control Room once changed In real-time monitor delta data, and this method also by internet make cloud server will build pipeline alarm point position information and Correlation building threedimensional model, pipeline threedimensional model are sent directly to smart mobile phone etc. and move special equipment, consequently facilitating maintenance people Member is by the position of " pipeline map " quick positioning wall pipeline bad point in the display screen of mobile special equipment.Just because of bad point position Put that locking process is more quick, so the efficiency of pipeline maintenance work can be significantly improved.
In addition, employing cloud server in this method, working equipment investment quantity is reduced, so significantly reducing prison Control cost.Only need to for the input equipment for inputting the three-dimensional drawing information of building pipeline, control computer, be used in this method The mobile special equipment that information is received can just complete pipeline positioning, thus this method has the advantages that application cost is cheap, just In promoting the use of.And because cloud server information storage is big, it, which can be stored, calculates each building pipeline bad point dimension Alert frequency is repaiied, this provides good directive function for the daily pipeline maintenance of maintenance personal.
Brief description of the drawings
Fig. 1 is structural representation of the invention.
Embodiment
In order to be better understood from the present invention, the present invention is further retouched with reference to specific embodiments and the drawings State.
As shown in figure 1, a kind of maintenance management method for being used to realize building pipeline three-dimensional localization, mainly including following step Suddenly:
(A) server sets up " three-dimensional map " of building pipeline beyond the clouds:
The electronic image for building the three-dimensional drawing of pipeline is inputted to input equipment such as computer etc., the input equipment passes through Network signal transmits the electronic image to cloud server, and server is saved backup beyond the clouds.The network letter Number be 3G, 4G network signal or WIFI network signal.More facilitated using wireless network signal mail message, this method should With will not be limited to by netting twine installation site.
Wherein, the original material of the three-dimensional drawing of building pipeline includes building pipeline three dimensional design drawing and building pipeline Practice of construction drawing.So closer to the actual conditions of building pipeline, modeled again again without staff and describe building one by one Pipeline route, so as to simplify the workload of building pipeline " three-dimensional map ".The pipeline includes being water delivery pipeline, gas pipeline And circuit protection pipeline.This makes it possible to make, building pipeline service worker inquiry in " three-dimensional map " of building pipeline is various Life service conduits, improve the function of building pipeline " three-dimensional map ".
(B) work of building pipeline " three-dimensional map " and application flow:
A) the building pipeline is provided with for perceiving channel interior pressure change per separated by a distance in construction wall And for detecting the sensor of circuitry operating conditions, the sensor main will include hydraulic pressure sensor, power detection sensor The digiverter electrically connected with gas leakage detection sensor and with the sensor.The digiverter passes through It is parallel-connection structure between the control computer of signal wire electrical connection building pipeline Central Control Room, the sensor;Each sensor will Test signal is constantly transported in the control computer in a steady stream, the test signal just phase if pressure in pipeline changes It should change, such staff just can understand the working condition of building pipeline in real time by control computer.
B) each sensor is provided with unique encodings, and the control computer can be according to the coding lookup to building The damage position of pipeline, and coded data is reported into the cloud server by network signal automatically.
C) alarmed after the cloud server data processing, while showing the point in the sensor building pipeline section Position, and the point position for building conduit failure alarm is sent to the mobile special equipment of specified maintenance personal, the cloud service Device automatically will surrounding buildingses threedimensional model and building pipeline three-dimensional model transmitting to maintenance personal where building conduit failure point position Mobile special equipment in.
D) maintenance personal is reached behind building conduit failure point position, the picture position that the mobile special equipment passes through display screen Adjustment makes corresponding with building infield scape position with picture position, and is perceived building wall inner tube road by three-dimensional perspective mode Come, maintenance personal's movement mobile special equipment display picture, which is shown, to be moved, to reach building pipeline and point position alarm signal Breath is corresponding with wall space, quickly to position bad point position to be repaired.
In order to improve display brightness, the energy-saving effect of the mobile special equipment display screen, so the movement is special The design of LED of equipment is LED display.In addition, the design can also significantly extend the service life of display screen.
(C) application building pipeline " three-dimensional map " carries out regular maintenance:
A) attendant's point of arrival position, GPS is automatically positioned building, and attendant voluntarily selects to be accurate to the room of maintenance Between, special equipment is moved using smart mobile phone, tablet personal computer, virtual reality glasses etc., current point position is downloaded from server automatically Building and pipeline threedimensional model.
B) Maintenance Engineer passes through the electronics in the mobile special equipment such as smart mobile phone, tablet personal computer, virtual reality glasses Gyroscope, gravity sensing equipment and position sensor and GPS location etc., carry out position correspondence, and lead to by scene in building Cross three-dimensional perspective mode pipeline, circuit drawing will perceive within the walls, workman's intelligent movable mobile phone, tablet personal computer, virtual reality Glasses etc., display drawing is moved, and to reach that the information such as pipeline, circuit are corresponding with wall space, being quickly found out to tie up The position repaiied.
Embodiments of the invention are described in detail above, but the content is only presently preferred embodiments of the present invention, It is not to be regarded as the practical range for limiting the present invention.All equivalent changes made according to the scope of the invention and improvement etc., all should Still belong within this patent covering scope.

Claims (9)

1. a kind of maintenance management method for being used to realize building pipeline three-dimensional localization, it is characterised in that:Mainly include the following steps that:
(a) electronic image for building the three-dimensional drawing of pipeline is inputted to input equipment, the input equipment will by network signal The electronic image is transmitted to cloud server, and server is saved backup beyond the clouds;
(b) the building pipeline is provided with for perceiving channel interior pressure change and inspection per separated by a distance in construction wall The sensor of slowdown monitoring circuit working condition, the sensor electrically connects the control computer for building pipeline Central Control Room by signal wire, It is parallel-connection structure between the sensor;Test signal is constantly transported to the control computer by each sensor in a steady stream In, test signal just accordingly changes if pressure in pipeline changes, and such staff just can pass through control computer The working condition of building pipeline is understood in real time;
(c) each sensor is provided with unique encodings, and the control computer can be managed according to the coding lookup to building The damage position on road, and coded data is reported into the cloud server by network signal automatically;
(d) alarmed after the cloud server data processing, while the residing building pipeline points position of the sensor is shown, and The point position for building conduit failure alarm is sent to the mobile special equipment of specified maintenance personal, the cloud server is automatic Surrounding buildingses threedimensional model and the movement of building pipeline three-dimensional model transmitting to maintenance personal where conduit failure point position will be built In special equipment;
(e) maintenance personal reaches behind building conduit failure point position that the mobile special equipment is adjusted by the picture position of display screen It is whole make it is corresponding with building infield scape position with picture position, and by three-dimensional perspective mode by building wall inner tube Reuter regard out, Maintenance personal, which moves the mobile special equipment display picture and shown, to be moved, with reach building pipeline and point position warning message and The correspondence in wall space, quickly to position bad point position to be repaired.
2. the maintenance management method according to claim 1 for being used to realize building pipeline three-dimensional localization, it is characterised in that:Institute Input equipment is stated for computer.
3. the maintenance management method according to claim 1 for being used to realize building pipeline three-dimensional localization, it is characterised in that:Institute It is any one in smart mobile phone, tablet personal computer and virtual reality glasses to state mobile special equipment.
4. the maintenance management method according to claim 1 for being used to realize building pipeline three-dimensional localization, it is characterised in that:Institute The display screen for stating mobile special equipment is LED display.
5. the maintenance management method according to claim 1 for being used to realize building pipeline three-dimensional localization, it is characterised in that:Institute Network signal is stated for 3G, 4G network signal and/or WIFI network signal.
6. the maintenance management method according to claim 1 for being used to realize building pipeline three-dimensional localization, it is characterised in that:Institute Stating the original material of the three-dimensional drawing of building pipeline includes building pipeline three dimensional design drawing and building pipeline practice of construction drawing.
7. the maintenance management method according to claim 1 for being used to realize building pipeline three-dimensional localization, it is characterised in that:Institute Stating pipeline includes being water delivery pipeline, gas pipeline and circuit protection pipeline.
8. being used for according to any one in claim 1-7 realizes the maintenance management method of building pipeline three-dimensional localization, It is characterized in that:In the mobile special equipment it is internal be provided with electronic gyroscope, gravity sensing equipment, position sensor and GPS positioning device, so as to the real-time adjustment of the mobile special equipment display screen position of display image, makes itself and building infield scape Quick correspondence.
9. the maintenance management method according to claim 8 for being used to realize building pipeline three-dimensional localization, it is characterised in that:Institute Sensor is stated including hydraulic pressure sensor, power detection sensor and gas leakage detection sensor and is electrically connected with the sensor The digiverter connect.
CN201710594195.0A 2017-07-20 2017-07-20 A kind of maintenance management method for being used to realize building pipeline three-dimensional localization Pending CN107194480A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710594195.0A CN107194480A (en) 2017-07-20 2017-07-20 A kind of maintenance management method for being used to realize building pipeline three-dimensional localization

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710594195.0A CN107194480A (en) 2017-07-20 2017-07-20 A kind of maintenance management method for being used to realize building pipeline three-dimensional localization

Publications (1)

Publication Number Publication Date
CN107194480A true CN107194480A (en) 2017-09-22

Family

ID=59884455

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710594195.0A Pending CN107194480A (en) 2017-07-20 2017-07-20 A kind of maintenance management method for being used to realize building pipeline three-dimensional localization

Country Status (1)

Country Link
CN (1) CN107194480A (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107635293A (en) * 2017-11-01 2018-01-26 广州供电局有限公司 A kind of equipment three-dimensional remote commands maintenance system
CN108132535A (en) * 2017-12-29 2018-06-08 苏州库浩斯信息科技有限公司 AR glasses and system applied to electric power detection
CN108183685A (en) * 2017-12-28 2018-06-19 阳光电源股份有限公司 For photovoltaic plant O&M and the mobile equipment and system of diagnosis
CN109838694A (en) * 2019-01-02 2019-06-04 固安京蓝云科技有限公司 The monitoring method and device of irrigation pipeline
CN112437408A (en) * 2020-11-13 2021-03-02 江苏宁创智能科技有限公司 Curtain wall positioning method and system
CN113744512A (en) * 2021-08-31 2021-12-03 中国一冶集团有限公司 Engineering comprehensive pipeline positioning system

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2002197126A (en) * 2000-10-19 2002-07-12 Matsumoto Tochi Tatemono Kk Building design construction managing system
CN106228208A (en) * 2016-07-21 2016-12-14 重庆工程职业技术学院 Control system based on BIM and method
CN106706041A (en) * 2017-03-08 2017-05-24 天津梅迪亚科技有限公司 Control system for metro integrated pipe network based on virtual reality technology

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2002197126A (en) * 2000-10-19 2002-07-12 Matsumoto Tochi Tatemono Kk Building design construction managing system
CN106228208A (en) * 2016-07-21 2016-12-14 重庆工程职业技术学院 Control system based on BIM and method
CN106706041A (en) * 2017-03-08 2017-05-24 天津梅迪亚科技有限公司 Control system for metro integrated pipe network based on virtual reality technology

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107635293A (en) * 2017-11-01 2018-01-26 广州供电局有限公司 A kind of equipment three-dimensional remote commands maintenance system
CN107635293B (en) * 2017-11-01 2018-09-04 广州供电局有限公司 A kind of equipment three-dimensional remote commander maintenance system
CN108183685A (en) * 2017-12-28 2018-06-19 阳光电源股份有限公司 For photovoltaic plant O&M and the mobile equipment and system of diagnosis
CN108132535A (en) * 2017-12-29 2018-06-08 苏州库浩斯信息科技有限公司 AR glasses and system applied to electric power detection
CN109838694A (en) * 2019-01-02 2019-06-04 固安京蓝云科技有限公司 The monitoring method and device of irrigation pipeline
CN109838694B (en) * 2019-01-02 2021-02-02 好农易电子商务有限公司 Method and device for monitoring irrigation pipeline
CN112437408A (en) * 2020-11-13 2021-03-02 江苏宁创智能科技有限公司 Curtain wall positioning method and system
CN112437408B (en) * 2020-11-13 2023-12-22 江苏宁创智能科技有限公司 Curtain wall positioning method and system
CN113744512A (en) * 2021-08-31 2021-12-03 中国一冶集团有限公司 Engineering comprehensive pipeline positioning system

Similar Documents

Publication Publication Date Title
CN107194480A (en) A kind of maintenance management method for being used to realize building pipeline three-dimensional localization
CN107327707B (en) A kind of water supply network monitoring management method and system
CN108628237A (en) A kind of underground pipe gallery environmental unit operation monitoring system
CN105484799B (en) The underground floods alarm method monitored based on image and sump
CN106569466A (en) Building electric equipment operation state monitoring method, device and system
CN102635786A (en) Online real-time monitoring system for an embedded delivery pipeline
CN103366246A (en) Electrical geographic information service platform system
KR101719320B1 (en) Monitoring system of water level for prevention of disaster
CN109239697A (en) One kind being based on three-dimensional visualization employee real-time positioning system and method
CN105351754A (en) Urban underground comprehensive pipe gallery intelligent monitoring system
CN105569732B (en) The coal mine floods alarm method monitored based on image and hydrographic data
CN103076001A (en) Method and device for automatically monitoring subgrade settlement
CN108769918A (en) A kind of upper and lower personnel positioning navigation system of the accurate recovery well in deep of combination Internet of Things
CN107588329A (en) A kind of water supply pipe real-time monitoring system
CN105929820B (en) A kind of intelligent robot localization method
CN106404274A (en) Wireless monitoring technology based early warning system and method for high-rise floor construction pump pipe clogging
CN106338275B (en) A kind of intelligence ocean platform system
CN104484988A (en) Automatic space structure health monitoring system based on curved-surface wall-climbing robot sensor
CN104569909A (en) Indoor positioning system and method
CN111970382A (en) Iron tower safety monitoring and early warning system
CN110674543B (en) Three-dimensional visual gas-related operation safety control system and implementation method
CN111536437A (en) Wisdom water affairs terminal that multisensor fuses
CN102647447A (en) Online real-time monitoring system of novel pre-buried pipeline
CN105449859B (en) The methods of exhibiting of panorama intelligent power system based on Away3D engines
CN206440987U (en) Property installations and facilities remote monitoring platform

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20170922