CN107178144A - Municipal rain, sewage pumping station automatic dredging system and dredging method - Google Patents

Municipal rain, sewage pumping station automatic dredging system and dredging method Download PDF

Info

Publication number
CN107178144A
CN107178144A CN201710575892.1A CN201710575892A CN107178144A CN 107178144 A CN107178144 A CN 107178144A CN 201710575892 A CN201710575892 A CN 201710575892A CN 107178144 A CN107178144 A CN 107178144A
Authority
CN
China
Prior art keywords
alluvial
collecting
tank
dams
water
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201710575892.1A
Other languages
Chinese (zh)
Other versions
CN107178144B (en
Inventor
陈欣悦
陈震生
陈欣瑞
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Skf Tianjin Intelligent Water System Co ltd
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201710575892.1A priority Critical patent/CN107178144B/en
Publication of CN107178144A publication Critical patent/CN107178144A/en
Application granted granted Critical
Publication of CN107178144B publication Critical patent/CN107178144B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E03WATER SUPPLY; SEWERAGE
    • E03FSEWERS; CESSPOOLS
    • E03F7/00Other installations or implements for operating sewer systems, e.g. for preventing or indicating stoppage; Emptying cesspools
    • EFIXED CONSTRUCTIONS
    • E03WATER SUPPLY; SEWERAGE
    • E03FSEWERS; CESSPOOLS
    • E03F5/00Sewerage structures
    • E03F5/10Collecting-tanks; Equalising-tanks for regulating the run-off; Laying-up basins
    • EFIXED CONSTRUCTIONS
    • E03WATER SUPPLY; SEWERAGE
    • E03FSEWERS; CESSPOOLS
    • E03F5/00Sewerage structures
    • E03F5/22Adaptations of pumping plants for lifting sewage

Landscapes

  • Health & Medical Sciences (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Engineering & Computer Science (AREA)
  • Hydrology & Water Resources (AREA)
  • Public Health (AREA)
  • Water Supply & Treatment (AREA)
  • Barrages (AREA)
  • Treatment Of Sludge (AREA)

Abstract

The present invention relates to a kind of municipal rain, sewage pumping station automatic dredging system, it is characterised in that:Including pumping plant and desilting equipment, the desilting equipment includes grid spotter, the quick release device that dams, suspension type alluvial lifting device, diving and drains pump;Above-mentioned pumping plant includes back with water inlet line, inlet gate well, grid pond, collecting-tank, lifting pump chamber, discharge pressure pond or flowing water Valve well and water outlet pipeline;In the side of collecting-tank provided with the cistern that dams;Correspondence dam cistern collecting-tank opposite side set alluvial received well, dam cistern and alluvial received well between collecting-tank bottom it is corresponding alluvial entrance location provided with deposit collector groove.The present invention can realize multi-faceted, multi-angle, multi-level dredging operation; and manpower is freed from heavy pumping plant collecting-tank desilting work, eliminated safe hidden trouble; reduce the energy consumption and maintenance cost of pumping station operation; the desilting of pumping plant collecting-tank is allowed to realize regular practice and coherentization as early as possible; dredging effect is good; social resources are saved, are the advantages of environmental protection is contributed.

Description

Municipal rain, sewage pumping station automatic dredging system and dredging method
Technical field
The invention belongs to municipal rain, sewage pumping station construction technique field, more particularly to a kind of municipal rain, sewage pumping station are certainly Dynamic desilting system and dredging method.
Background technology
At present, the rain in current some cities of China, sewage pumping station collecting-tank, generally existing siltation, hardened situation, Pumping station operation and proper drainage have been hampered, the daily life of the people, trip has been had influence on;Current techniques and solution are done Method:
1st, manpower is gone into the well desilting:Manpower is organized regularly to go into the well desilting, artificial lower well operations need the instrument being equipped with to include:Gas Physical examination measurement equipment, spade, cleaning shoe, rope, pail etc.;This kind of desilting mode has a following defect, and personnel go into the well potential safety hazard It is many, time-consuming, efficiency is low, and labor intensity is big, and regular not strong.
2nd, high pressure water flushing formula:Using the high-pressure hydraulic pump for being pre-installed in bottom of pond in pumping plant collecting-tank, pass through outlet pipeline Upper densely covered nozzle is rinsed, and the alluvial of deposition is activated, and is then aspirated, transported with dredge pump car multi-point;It is often high Water pump is by after silting, and desilting work can not just proceed, high pressure washing combination dredge pump car, and the continuity of practical operation is not By force, human input and labor intensity are all very big, and equipment operation and maintenance cost are high.
3rd, stirring-type:Mixing plant is installed in advance in pumping plant collecting-tank, allows the mud largely deposited to suspend by stirring, Muddy water is discharged to downstream pipe network or along River system by the feed pump for then starting pumping plant;Stir, lifted, discharge in this process not There is the basic source for solving mud, the burden of downstream drainage pipe network is increased on the contrary, it is in line black in addition with the implementation of river length Smelly water body has been not allowed to along River system.
For this provide it is a kind of manpower freed from heavy pumping plant collecting-tank desilting work, eliminated safe hidden trouble, reduce The energy consumption and maintenance cost of pumping station operation, allow the desilting of pumping plant collecting-tank to realize regular practice and coherentization as early as possible, save social resources, Municipal rain, sewage pumping station automatic dredging system and the dredging method contributed for environmental protection.
The content of the invention
Present invention technical problem present in solution known technology, which is provided, a kind of catchments manpower from heavy pumping plant Free, eliminate safe hidden trouble in the desilting work of pond, reduce the energy consumption and maintenance cost of pumping station operation, allow the desilting of pumping plant collecting-tank to use up Fast realize is made a practice of and coherentization, saves social resources, municipal rain, sewage pumping station automatic dredging system and the desilting of energy-conserving and environment-protective Method.
The present invention is adopted the technical scheme that to solve technical problem present in known technology:
A kind of municipal rain, sewage pumping station automatic dredging system, it is characterised in that:It is described clear including pumping plant and desilting equipment Silt equipment includes grid spotter, the quick release device that dams, suspension type alluvial lifting device, diving and drains pump;Above-mentioned pumping plant includes The municipal rain of connection, several back with water inlet line of sewage, the back with water inlet line connect the water inlet of inlet gate well, the inlet gate Inlet gate is installed, the inlet gate connects headstock gear, and the delivery port side of the inlet gate well sets grid pond in well, Grid canal is provided between adjacent grid pond, the grid pond abuts collecting-tank, the collecting-tank adjoining lifting pump chamber, in lifting Lifting pump group is installed in pump chamber;The lifting pump chamber adjoining discharge pressure pond or flowing water Valve well, each lifting pump group are equal Connect the water inlet of discharge pressure pond or flowing water Valve well, the delivery port connection water outlet of the discharge pressure pond or flowing water Valve well Pipeline;In the side of collecting-tank provided with cistern or the alluvial received well of damming, dam and be provided with and collection between cistern and collecting-tank The spilled water hole of pond connection;The opposite side of the corresponding cistern collecting-tank that dams sets dam cistern or alluvial received well, described Provided with the alluvial import connected with collecting-tank between alluvial received well and collecting-tank;The bottom of the alluvial received well, which is less than, dams The bottom of cistern, forms an effective trapped volume space;It is provided with the bottom for the cistern that dams and leads slope;The storage that dams Pond and alluvial received well between collecting-tank bottom it is corresponding alluvial entrance location provided with deposit collector groove, the alluvial collector groove With water inlet direction into being vertically arranged, the alluvial collector groove laterally deposits received well direction provided with the gradient from the cistern that dams;Institute The grid spotter stated is arranged in grid pond;The described quick release device that dams, which is arranged on, to dam in cistern;Described suspention Formula alluvial lifting device movable type is arranged in alluvial received well;Diving is installed in described alluvial received well and drains pump, institute State diving and drain pump position below alluvial reception bottom.
The present invention can also use following technical measures:
In collecting-tank training wall is provided with close to lifting pump chamber side.
It is provided with structure wall, the structure wall and is communicated with collecting-tank, discharge pressure pond or flowing water Valve well Hole.
The inlet gate well, grid pond, collecting-tank, the centre position of lifting pump chamber are provided with separation along Inlet and outlet water direction Wall, separates wall and inlet gate well, grid pond, collecting-tank, lifting pump chamber is divided into two independent units;The alluvial Collector groove is by separating two alluvial collector grooves that wall is separated on same center line;Two independent collecting-tank sides Alluvial received well is set respectively;The alluvial received well is correspondingly arranged with alluvial collector groove;The separation wall is provided with correspondence Alluvial collects groove location provided with two spilled water holes, and two spilled water holes are arranged above and below, and two spilled water holes are on same center line, One group of quick release device that dams is mounted on two spilled water holes,;
Deflector is set in the spilled water hole both sides on top, and the lower end of the deflector extends to the both sides of alluvial collector groove.
The quick release device that dams includes double-action hydraulic fast opening and closing, the hydraulic piston of the hydraulic pressure fast opening and closing The body that dams of bar connection, the body that dams is slidably mounted in frame, and the both sides of the frame are provided with chute, the body that dams Both sides are inserted into chute, are slided up and down in the presence of hydraulic pressure speed drives headstock gear along chute and are realized that speed is opened and Slow Close;The machine Frame is fixedly mounted on the wall of collecting-tank.
Sluicing hole site has been poured in second coagulation soil structured body, the second coagulation soil structure on the wall of collecting-tank Correspondence shelf position is embedded with the connector being fixedly connected with frame;Installation is prefabricated with the top collecting-tank wall of frame Platform, the hydraulic pressure fast opening and closing is inverted in the upper surface of erecting bed, and the liquid presses piston pole of hydraulic pressure fast opening and closing is vertically downward Extension, the body that dams is connected in the bottom of liquid presses piston pole.
The quick release device that dams includes double-action hydraulic fast opening and closing, the hydraulic piston of the hydraulic pressure fast opening and closing The body that dams of bar connection, the body that dams is slidably mounted on gantry stand, and the both sides of the gantry stand are provided with chute, described The dam both sides of body are inserted into chute, slide up and down that to realize that speed is opened gentle along chute in the presence of hydraulic pressure speed drives headstock gear Close;The side of the gantry stand is fixedly connected with first flange;Tapping pipe is embedded with the spilled water hole of collecting-tank;It is described to let out The delivery port of water pipe is provided with second flange;Second flange in the first flange and tapping pipe of the gantry stand passes through fastener It is fixedly connected;The body that dams is installed in the outlet of first flange;The hydraulic pressure fast opening and closing is inverted in the top of gantry stand, liquid The liquid presses piston pole of pressure fast opening and closing extends vertically downward, and the body that dams is connected in the bottom of liquid presses piston pole.
The suspension type alluvial lifting device is arranged on the top plate of alluvial received well, is connect in top plate both sides along alluvial The length direction of receipts well, which is provided with line slideway, the line slideway, is equipped with walking dolly, and drive is provided with the walking dolly Vertical top plate direction is provided with two on the travel driving unit that dynamic walking dolly is moved along line slideway, the walking dolly Riser, the lower end of the riser extends to the bottom upper position of alluvial received well, and the upper end of the riser is upwardly extended, Active wheels, the active wheels are installed between the upper end of two risers to rotate by driving member connection driving active wheels Device for revolving and driving;Driven wheels are installed between the bottom of the riser, pacified between the active wheels and driven wheels Equipped with belt, the outside of the belt uniformly mounted it is several scoop bucket, the bucket that scoops connects in lower limit position distance alluvial Receive 3~5cm of bottom of well alluvial received well;Correspondence scoops bucket position and is placed with receiving hopper on the walking dolly.
The present invention also provides a kind of dredging method based on above-mentioned municipal rain, sewage pumping station automatic dredging system, including becomes silted up The alluvial lifting operation of product collector groove dredging operation, grid pond dredging operation and water leg dredging operation and the collector groove that deposits
1), deposit collector groove dredging operation:Be first shut off the inlet gate of inlet gate well, at the same start water lift pump group and Diving in alluvial received well drains pump, drains the ponding of collecting-tank;Secondly, while operation is drained into retention cistern Water filling, making to dam produces liquid level difference between cistern and collecting-tank, dynamic condition is provided for later stage erosion and deposition;3rd, it is pre- when reaching When phase sets liquid level difference, start the quick release device that dams, the quick release device quick return in 2~5 seconds that dams is acted, and speed of damming is opened Device is located at the high-order water dammed in cistern and rushes at alluvial collector groove rapidly after opening, the alluvial of the interior deposition of alluvial collector groove exists Along alluvial collector groove flow direction alluvial received well in the presence of water impact;3rd, now, diving drains pump and is again started up draining Operation, the current erosion and deposition end of job;Remained if also had in silting and erosion, in the case where keeping dry pond state, pass through investigation mission outside the city or town water source Mode water filling into the cistern that dams, when reaching expected setting difference in the cistern that dams, carries out secondary erosion and deposition;
2), grid pond dredging operation:Under the state of dry pond, the certain of inlet gate opening of inlet gate well is opened Degree, using path flow velocity principle, the alluvial to grid bottom of pond portion carries out erosion and deposition;
3) lower section of pump group, is lifted in collecting-tank, pump chamber bottom is provided with the water conservancy diversion slope of 1.5% gradient, utilizes elevator pump The water hammering that water backflow during shutdown in lifting pipe is produced makes alluvial flow direction alluvial collector groove to pump chamber bottom erosion and deposition.
4) the alluvial lifting operation of alluvial collector groove:Alluvial received well bottom will be deposited on by starting suspension type alluvial lifting device The alluvial in portion is lifted, and is promoted to receiving hopper, after receiving hopper is fully loaded, receiving hopper is removed, and is changed a new receiving hopper and is Can continuously it receive.
The present invention has the advantages and positive effects of:Because the present invention uses above-mentioned technical proposal, it is possible to achieve multi-party Position, multi-angle, multi-level dredging operation, and manpower freed from heavy pumping plant collecting-tank desilting work, is eliminated safely Hidden danger, reduces the energy consumption and maintenance cost of pumping station operation, allows the desilting of pumping plant collecting-tank to realize regular practice and coherentization, desilting as early as possible Effect is good, saves social resources, is the advantages of environmental protection is contributed.
Brief description of the drawings
Fig. 1 is the structural representation of the embodiment of the present invention 1;
Fig. 2 is middle A-A sectional views;
Fig. 3 is B-B sectional views in Fig. 1;
Fig. 4 is C-C sectional views in Fig. 1;
Fig. 5 is the quick release device structural representation that dams;
Fig. 6 is quick release device mounting structure schematic diagram of damming;
Fig. 7 is another quick release device structural representation that dams;
Fig. 8 is the mounting structure schematic diagram of quick release device of damming described in Fig. 7;
Fig. 9 is suspension type alluvial lifting device structural representation;
Figure 10 is the pump station structure schematic diagram of embodiment 2.
In figure:100th, pumping plant;110th, back with water inlet line;120th, inlet gate well;121st, inlet gate;122nd, headstock gear; 130th, grid pond;131st, grid canal;140th, collecting-tank;141st, deposit collector groove;142nd, training wall;143rd, structure wall;144、 Wall;145th, second coagulation soil structured body;146th, connector;147th, erecting bed;145th, second coagulation soil structured body;146th, connect Part;147th, erecting bed;150th, pump chamber is lifted;151st, pump group is lifted;160th, discharge pressure pond;161st, structure wall;170th, water outlet Pipeline;180th, dam cistern;181st, spilled water hole;190th, deposit received well;191st, top plate;210th, grid spotter;220、 Dam quick release device;221st, double-action hydraulic fast opening and closing;222nd, dam body;223rd, frame;224th, chute;225th, gantry plane Frame;226th, first flange;227th, tapping pipe;228th, second flange;230th, suspension type alluvial lifting device;231st, line slideway; 232nd, walking dolly;233rd, travel driving unit;234th, riser;235th, active wheels;236th, driving member;237th, revolution driving Device;238th, driven wheels;239th, belt;2390th, bucket is scooped;2391st, receiving hopper;240th, diving drains pump;300th, dividing wall Body;310th, spilled water hole;
Embodiment
In order to further understand the content, features and effects of the present invention, hereby enumerating following examples, and coordinate accompanying drawing Describe in detail as follows:
Embodiment 1, refers to Fig. 1 to Fig. 4, a kind of municipal rain, sewage pumping station automatic dredging system, including the He of pumping plant 100 Desilting equipment, the desilting equipment include grid spotter 210, the quick release device 220 that dams, suspension type alluvial lifting device 230, Diving drains pump 240;Above-mentioned pumping plant 100 includes the municipal rain of connection, several back with water inlet line 110 of sewage, and the back with water inlet line connects Tap into and inlet gate 121 is installed in the water inlet of sluice gate well 120, the inlet gate well, the inlet gate connection is opened Machine 122 is closed, headstock gear controls the opening and closing of inlet gate, and its operation principle belongs to known technology;The inlet gate well 120 delivery port side sets and grid canal 131 is provided between grid pond 130, adjacent grid pond, and the grid pond abuts collecting-tank 140, the collecting-tank adjoining lifting pump chamber 150 has lifting pump group 151 in elevator pump indoor location;The lifting pump chamber adjoining It is discharge pressure pond 160 in discharge pressure pond or flowing water Valve well, the present embodiment, each lifting pump group is all connected with discharge pressure The delivery port connection water outlet pipeline 170 of the water inlet in pond, the discharge pressure pond or flowing water Valve well;Set in the side of collecting-tank There is the cistern 180 that dams, dam between cistern and collecting-tank provided with the spilled water hole 181 connected with collecting-tank;The corresponding storage that dams The opposite side of pond collecting-tank sets alluvial received well 190, is provided with and connects with collecting-tank between the alluvial received well and collecting-tank Logical alluvial import, the bottom of the alluvial received well is less than the bottom for the cistern that dams, and forms an effective trapped volume Space;In the bottom for the cistern that dams provided with slope 181 is led, the bottom precipitation alluvial in the cistern that dams is prevented;The storage that dams Pond and alluvial received well between collecting-tank bottom it is corresponding alluvial entrance location provided with alluvial collector groove 141, it is described alluvial remittance Collection groove is with water inlet direction into being vertically arranged, and the alluvial collector groove laterally deposits received well direction provided with slope from the cistern that dams Degree;Described grid spotter 210 is arranged in grid pond 130;The described quick release device 220 that dams is arranged on the cistern that dams In 180;Described suspension type alluvial lifting device 230 is portable to be arranged in alluvial received well 190;Described alluvial received well Diving is inside installed and drains pump 240, the diving drains pump and is located at position below alluvial reception bottom.
In order to realize the guide functions in collecting-tank, training wall 142 is provided with close to lifting pump chamber side in collecting-tank 140.
In order to improve the intensity of pumping plant, in collecting-tank, discharge pressure pond or flowing water Valve well provided with structure wall 143, 161, hole is communicated with the structure wall.
Refer to Fig. 5 and Fig. 6, the above-mentioned quick release device 220 that dams includes double-action hydraulic fast opening and closing 221, position. The body 222 that dams of the liquid presses piston pole connection of the hydraulic pressure fast opening and closing, the stroke of hydraulic pressure fast opening and closing is more than the body that dams Effective travel 30%;The body that dams is slidably mounted in frame 223, and the both sides of the frame are provided with chute 224, described to dam The both sides of body are inserted into chute, are slided up and down in the presence of hydraulic pressure speed drives headstock gear along chute and are realized that speed is opened and Slow Close;Institute Frame 223 is stated to be fixedly mounted on the wall 144 of collecting-tank.Power is done in municipal rain, sewage pumping station using hydraulic station first Output center, is realized to the single control and multimachine joint control of quick open type cut-off equipment, and hand, to automatically control switching freely, running status real Shi Shangchuan;Using the backhaul of oil cylinder, the body that dams is opened within 2~5 seconds;The quick release device that dams have good economy performance, dependable performance, into The features such as this low cost, efficiency and service life further improve, reduce environmental pollution.
In order to not destroy collecting-tank wall, sluicing hole site has poured second coagulation soil structured body on the wall of collecting-tank 145, correspondence shelf position is embedded with the connector 146 being fixedly connected with frame in the second coagulation soil structure;In frame Erecting bed 147 is prefabricated with the collecting-tank wall of top, the hydraulic pressure fast opening and closing is inverted in the upper surface of erecting bed, and hydraulic pressure is fast The liquid presses piston pole of fast headstock gear 221 extends vertically downward, and the body 222 that dams is connected in the bottom of liquid presses piston pole.
On the premise of overall collecting-tank strength of wall body is not influenceed, the installation effectiveness for the quick release device that dams, speed of damming are improved Opening apparatus can also use following structure, refer to Fig. 7 and Fig. 8, the quick release device that dams quickly is opened including double-action hydraulic Machine 221 is closed, the body 222 that dams of the liquid presses piston pole connection of the hydraulic pressure fast opening and closing, the body that dams is slidably mounted on dragon In door frame 225, the both sides of the gantry stand 225 are provided with chute 224, and the both sides for damming body 222 are inserted into chute, Slided up and down in the presence of hydraulic pressure speed drives headstock gear along chute and realize that speed is opened and Slow Close;The side of the gantry stand 225 is consolidated Surely it is connected with first flange 226;Tapping pipe 227 is embedded with the spilled water hole of collecting-tank;The delivery port of the tapping pipe is provided with Second flange 228;The first flange of the gantry stand is fixedly connected with the second flange on tapping pipe by fastener; The outlet of one flange is installed by the body 222 that dams;The hydraulic pressure fast opening and closing is inverted in the top of gantry stand 225, and hydraulic pressure is quick The liquid presses piston pole of headstock gear extends vertically downward, and the body 222 that dams is connected in the bottom of liquid presses piston pole.
Referring to Fig. 9, the suspension type alluvial lifting device 230 is arranged on the top plate 191 of alluvial received well, upper Length direction of the laminate both sides along alluvial received well, which is provided with line slideway 231, the line slideway, is equipped with walking dolly 232, The travel driving unit 233 that driving walking dolly is moved along line slideway, the walking dolly are installed on the walking dolly Upper vertical top plate direction is provided with two risers 234, and the lower end of the riser extends to the top position in bottom of alluvial received well Put, the upper end of the riser is upwardly extended, active wheels 235, the driving wheel are installed between the upper end of two risers Group connects the device for revolving and driving 237 that driving active wheels are rotated by driving member 236;The bottom of the riser 234 it Between install driven wheels 238, belt 239 is installed, the outside of the belt is uniform between the active wheels and driven wheels Mounted it is several scoop bucket 2390, it is described scoop bucket the bottom 3 of lower limit position distance alluvial received well alluvial received well~ 5cm;Correspondence scoops bucket position and is placed with receiving hopper 2391 on the walking dolly;Driven under the driving of travel driving unit whole The length direction of individual device along alluvial received well is moved, the scooping bucket and will be deposited on positioned at lower end extreme position in moving process Alluvial receive bottom alluvial dipped, after dipping on the effect belt of device for revolving and driving scoop bucket gradually with Alluvial motion upwards, when the alluvial for moving to upper extreme position and scooping bucket is gradually trickled down in the receiving hopper on walking dolly, when After receiving hopper is fully loaded, receiving hopper is removed, changing a new receiving hopper can continuously graft clay.
Embodiment 2, in order to improve the reasonability of pump station structure, it is ensured that still be able to run well during maintenance, in the water inlet Gate shaft 120, grid pond 130, collecting-tank 140, the centre position of lifting pump chamber 150 are provided with separation wall along Inlet and outlet water direction 300, separate wall and inlet gate well, grid pond, collecting-tank, lifting pump chamber are divided into two independent units;The alluvial Collector groove 141 is by separating two alluvial collector grooves that wall is separated on same center line;Two independent collecting-tanks Side sets alluvial received well 190 respectively;The alluvial received well is correspondingly arranged with alluvial collector groove;Set on the separation wall There is corresponding alluvial to collect groove location provided with two spilled water holes 310, two spilled water holes are in arrangement, and two spilled water holes are same up and down On center line, one group of quick release device 220 that dams is mounted on two spilled water holes;The unit of two such independence can replace Use, improve operating efficiency, extend the service life of equipment of pumping station;In order to ensure that top spilled water hole converges to alluvial to greatest extent Washing away for collection groove, deflector 320 is set in the spilled water hole both sides on top, and the lower end of the deflector extends to alluvial collector groove Both sides.
The present invention also provides a kind of dredging method based on above-mentioned municipal rain, sewage pumping station automatic dredging system, including becomes silted up The alluvial lifting operation of product collector groove dredging operation, grid pond dredging operation and water leg dredging operation and the collector groove that deposits
1), deposit collector groove dredging operation:Be first shut off the inlet gate of inlet gate well, at the same start water lift pump group and Diving in alluvial received well drains pump, drains the ponding of collecting-tank;Secondly, while operation is drained into retention cistern Water filling, making to dam produces liquid level difference between cistern and collecting-tank, dynamic condition is provided for later stage erosion and deposition;3rd, it is pre- when reaching When phase sets liquid level difference, start the quick release device that dams, the quick release device quick return in 2~5 seconds that dams is acted, and speed of damming is opened Device is located at the high-order water dammed in cistern and rushes at alluvial collector groove rapidly after opening, the alluvial of the interior deposition of alluvial collector groove exists Along alluvial collector groove flow direction alluvial received well in the presence of water impact;3rd, now, diving drains pump and is again started up draining Operation, the current erosion and deposition end of job;Remained if also had in silting and erosion, in the case where keeping dry pond state, pass through investigation mission outside the city or town water source Mode water filling into the cistern that dams, when reaching expected setting difference in the cistern that dams, carries out secondary erosion and deposition;Dam retaining Pond retaining can be fully utilized the pool inner water that catchments and be extracted by pump, and collecting-tank current level can also be used as main water During the expected setting value of water level deficiency in source, retention cistern, investigation mission outside the city or town water source can be borrowed give and supplement, until reaching that expection is set Definite value;After first time desilting is completed, when the cistern that dams needs refilling, the intake gate of inlet gate well can be first opened Door, when the water level of collecting-tank rises to certain liquid level, opens the body that dams, is the liquid dammed in cistern using the principle of linker Position is consistent with the liquid level in collecting-tank, now closes the body that dams, until spilled water hole is realized and closed by the body that dams, retains retaining During the expected setting value of water level deficiency in pond, investigation mission outside the city or town water source can be borrowed give and supplement, until reaching expected setting value;In addition not The rainwater that the cistern that dams during progress dredging operation can also be collected is as water source.
2), grid pond dredging operation:Under the state of dry pond, the certain of inlet gate opening of inlet gate well is opened Degree, using path flow velocity principle, the alluvial to grid bottom of pond portion carries out erosion and deposition;
3) lower section of pump group, is lifted in collecting-tank, pump chamber bottom is provided with the water conservancy diversion slope of 1.5% gradient, utilizes elevator pump The water hammering that water backflow during shutdown in lifting pipe is produced makes alluvial flow direction alluvial collector groove to pump chamber bottom erosion and deposition.
4) the alluvial lifting operation of alluvial collector groove:Alluvial received well bottom will be deposited on by starting suspension type alluvial lifting device The alluvial in portion is lifted, and is promoted to receiving hopper, after receiving hopper is fully loaded, receiving hopper is removed, and is changed a new receiving hopper and is Can continuously it receive.
Using above-mentioned technical proposal, it is possible to achieve multi-faceted, multi-angle, multi-level dredging operation, and by manpower from numerous Free, eliminate safe hidden trouble in the pumping plant collecting-tank desilting work of weight, reduce the energy consumption and maintenance cost of pumping station operation, allow pumping plant Regular practice and coherentization are realized in collecting-tank desilting as early as possible, and dredging effect is good, saving social resources, and it is excellent to be that environmental protection is contributed etc. Point.
It is described above to be only the preferred embodiments of the present invention, any formal limitation not is made to the present invention, Every technical spirit according to the present invention is belonged to any simple modification made for any of the above embodiments, equivalent variations and modification In the range of technical solution of the present invention.

Claims (10)

1. a kind of municipal rain, sewage pumping station automatic dredging system, it is characterised in that:Including pumping plant and desilting equipment, the desilting Equipment includes grid spotter, the quick release device that dams, suspension type alluvial lifting device, diving and drains pump;
Above-mentioned pumping plant includes the municipal rain of connection, several back with water inlet line of sewage, and the back with water inlet line connects entering for inlet gate well Inlet gate is installed, the inlet gate connects headstock gear in the mouth of a river, the inlet gate well, the inlet gate well goes out Mouth of a river side sets and grid canal is provided between grid pond, adjacent grid pond, and the grid pond abuts collecting-tank, and the collecting-tank is adjacent Lifting pump chamber is connect, has lifting pump group in elevator pump indoor location;The lifting pump chamber adjoining discharge pressure pond or flowing water Valve Well, each lifting pump group is all connected with the water inlet of discharge pressure pond or flowing water Valve well, the discharge pressure pond or flowing water Valve The delivery port connection water outlet pipeline of well;
In the side of collecting-tank provided with cistern or the alluvial received well of damming, dam and be provided between cistern and collecting-tank with catchmenting The spilled water hole of pond connection;The opposite side of the corresponding cistern collecting-tank that dams sets dam cistern or alluvial received well, the silt Provided with the alluvial import connected with collecting-tank between product received well and collecting-tank;
The bottom of the alluvial received well is less than the bottom for the cistern that dams, and forms an effective trapped volume space;Cutting The bottom of stream cistern, which is provided with, leads slope;
It is described dam cistern and alluvial received well between collecting-tank bottom it is corresponding alluvial entrance location provided with deposit collector groove, The alluvial collector groove with water inlet direction into being vertically arranged, the alluvial collector groove oneself the cistern that dams laterally deposit received well side To provided with the gradient;
Described grid spotter is arranged in grid pond;
The described quick release device that dams, which is arranged on, to dam in cistern;
Described suspension type alluvial lifting device movable type is arranged in alluvial received well;
Diving is installed in described alluvial received well and drains pump, the diving drains pump and is located at position below alluvial reception bottom Put.
2. municipal rain according to claim 1, sewage pumping station automatic dredging system, it is characterised in that:Leaned in collecting-tank Nearly lifting pump chamber side is provided with training wall.
3. municipal rain according to claim 1, sewage pumping station automatic dredging system, it is characterised in that:In collecting-tank, water outlet It is provided with pressure tank or flowing water Valve well on structure wall, the structure wall and is communicated with hole.
4. municipal rain according to claim 1, sewage pumping station automatic dredging system, it is characterised in that:The inlet gate Well, grid pond, collecting-tank, the centre position of lifting pump chamber are provided with separation wall along Inlet and outlet water direction, and separating wall will intake Gate shaft, grid pond, collecting-tank, lifting pump chamber are divided into two independent units;The alluvial collector groove is by separating wall It is separated into two alluvial collector grooves on same center line;Two independent collecting-tank sides set alluvial to receive respectively Well;The alluvial received well is correspondingly arranged with alluvial collector groove;The separation wall collects groove location provided with correspondence alluvial and set There are two spilled water holes, two spilled water holes are in arrangement, and two spilled water holes are on same center line up and down, on two spilled water holes One group of quick release device that dams is installed.
5. municipal rain according to claim 4, sewage pumping station automatic dredging system, it is characterised in that:Sluicing on top Hole both sides set deflector, and the lower end of the deflector extends to the both sides of alluvial collector groove.
6. municipal rain according to claim 1, sewage pumping station automatic dredging system, it is characterised in that:The speed of damming is opened Device includes double-action hydraulic fast opening and closing, and the body that dams of the liquid presses piston pole connection of the hydraulic pressure fast opening and closing is described The body that dams is slidably mounted in frame, and the both sides of the frame are provided with chute, and the both sides of the body that dams are inserted into chute, Hydraulic pressure speed, which is opened to slide up and down along chute in the presence of headstock gear, realizes that speed is opened and Slow Close;The frame is fixedly mounted on collecting-tank On wall.
7. municipal rain according to claim 6, sewage pumping station automatic dredging system, it is characterised in that:In the wall of collecting-tank On body sluicing hole site poured in second coagulation soil structured body, the second coagulation soil structure correspondence shelf position be embedded with The connector that frame is fixedly connected;Erecting bed, the hydraulic pressure fast opening and closing are prefabricated with the top collecting-tank wall of frame The upper surface of erecting bed is inverted in, the liquid presses piston pole of hydraulic pressure fast opening and closing extends vertically downward, under liquid presses piston pole End connects the body that dams.
8. municipal rain according to claim 1, sewage pumping station automatic dredging system, it is characterised in that:The speed of damming is opened Device includes double-action hydraulic fast opening and closing, and the body that dams of the liquid presses piston pole connection of the hydraulic pressure fast opening and closing is described The body that dams is slidably mounted on gantry stand, and the both sides of the gantry stand are provided with chute, and the both sides of the body that dams are inserted into In chute, slided up and down in the presence of hydraulic pressure speed drives headstock gear along chute and realize that speed is opened and Slow Close;The one of the gantry stand Side is fixedly connected with first flange;Tapping pipe is embedded with the spilled water hole of collecting-tank;The delivery port of the tapping pipe is provided with the Two flanges;The first flange of the gantry stand is fixedly connected with the second flange on tapping pipe by fastener;In the first method Blue outlet is installed by the body that dams;The hydraulic pressure fast opening and closing is inverted in the top of gantry stand, the liquid of hydraulic pressure fast opening and closing Pressure piston rod extends vertically downward, and the body that dams is connected in the bottom of liquid presses piston pole.
9. municipal rain according to claim 1, sewage pumping station automatic dredging system, it is characterised in that:The suspension type is become silted up Product lifting device is arranged on the top plate of alluvial received well, and in top plate both sides, the length direction along alluvial received well is provided with straight It is equipped with line guide rail, the line slideway on walking dolly, the walking dolly and driving walking dolly is installed along line slideway Vertical top plate direction is provided with two risers, the lower end of the riser on mobile travel driving unit, the walking dolly Extend to the bottom upper position of alluvial received well, the upper end of the riser upwardly extends, the upper end of two risers it Between install active wheels, the active wheels pass through driving member connection driving active wheels rotate device for revolving and driving;Institute Driven wheels are installed between the bottom for stating riser, belt, the belt are installed between the active wheels and driven wheels Outside uniformly mounted it is several scoop bucket, the bucket that scoops deposits the bottom of received well in lower limit position distance alluvial received well 3~5cm of portion;Correspondence scoops bucket position and is placed with receiving hopper on the walking dolly.
10. it is a kind of based on it is above-mentioned according to any described municipal rain of claim 1 to 9, sewage pumping station automatic dredging system it is clear Silt method, it is characterised in that:Including alluvial collector groove dredging operation, grid pond dredging operation and water leg dredging operation and The alluvial lifting operation of alluvial collector groove:
1), deposit collector groove dredging operation:The inlet gate of inlet gate well is first shut off, while starting water lift pump group and alluvial Diving in received well drains pump, drains the ponding of collecting-tank;Secondly, noted while operation is drained into retention cistern Water, making to dam produces liquid level difference between cistern and collecting-tank, dynamic condition is provided for later stage erosion and deposition;3rd, when reaching expection When setting liquid level difference, start the quick release device that dams, the quick release device quick return in 2~5 seconds that dams is acted, and speed of damming opens dress Put and be located at the high-order water that dams in cistern after opening and rush at the alluvial of deposition in alluvial collector groove, alluvial collector groove rapidly in water Along alluvial collector groove flow direction alluvial received well in the presence of stream impact;3rd, now, diving drains pump and is again started up draining work Industry, the current erosion and deposition end of job;Remained if also had in silting and erosion, in the case where keeping dry pond state, pass through the side at investigation mission outside the city or town water source Formula water filling into the cistern that dams, when reaching expected setting difference in the cistern that dams, carries out secondary erosion and deposition;
2), grid pond dredging operation:Under the state of dry pond, certain aperture that the inlet gate of inlet gate well is opened, profit With path flow velocity principle, the alluvial to grid bottom of pond portion carries out erosion and deposition;
3) lower section of pump group, is lifted in collecting-tank, pump chamber bottom is provided with the water conservancy diversion slope of 1.5% gradient, shut down using elevator pump When lifting pipe in water backflow produce water hammering to pump chamber bottom erosion and deposition, make alluvial flow direction alluvial collector groove.
4) the alluvial lifting operation of alluvial collector groove:Start suspension type alluvial lifting device and receive bottom by alluvial is deposited on Alluvial is lifted, and is promoted to receiving hopper, after receiving hopper is fully loaded, receiving hopper is removed, and changing a new receiving hopper can connect Continued access is received.
CN201710575892.1A 2017-07-14 2017-07-14 Automatic dredging system and method for municipal rainwater and sewage pump station Active CN107178144B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710575892.1A CN107178144B (en) 2017-07-14 2017-07-14 Automatic dredging system and method for municipal rainwater and sewage pump station

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710575892.1A CN107178144B (en) 2017-07-14 2017-07-14 Automatic dredging system and method for municipal rainwater and sewage pump station

Publications (2)

Publication Number Publication Date
CN107178144A true CN107178144A (en) 2017-09-19
CN107178144B CN107178144B (en) 2023-03-31

Family

ID=59838461

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710575892.1A Active CN107178144B (en) 2017-07-14 2017-07-14 Automatic dredging system and method for municipal rainwater and sewage pump station

Country Status (1)

Country Link
CN (1) CN107178144B (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108560694A (en) * 2018-03-12 2018-09-21 上海市城市建设设计研究总院(集团)有限公司 Rainfall pumping station with test run function
CN113090325A (en) * 2021-03-17 2021-07-09 中铁大桥勘测设计院集团有限公司 Construction method for tunnel drainage ditch

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1602989A (en) * 2003-09-29 2005-04-06 张西林 Silt collection device
CN203498996U (en) * 2013-09-25 2014-03-26 合肥市市政设计院有限公司 Sewage pumping station forebay structure convenient for desilting
CN103768839A (en) * 2014-01-21 2014-05-07 化工部长沙设计研究院 Multifunctional mine sedimentation tank capable of realizing all-weather continuous work
CN104174191A (en) * 2014-08-18 2014-12-03 南京工业大学 Integrated grit chamber for treating rainwater and treatment method
CN104532947A (en) * 2015-01-04 2015-04-22 上海市城市建设设计研究总院 Underground open-type storage pond
JP2016007564A (en) * 2014-06-24 2016-01-18 クボタ環境サ−ビス株式会社 Sand pumping method and sand settling facility
CN206971370U (en) * 2017-07-14 2018-02-06 陈震生 Municipal rain, sewage pumping station automatic dredging system

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1602989A (en) * 2003-09-29 2005-04-06 张西林 Silt collection device
CN203498996U (en) * 2013-09-25 2014-03-26 合肥市市政设计院有限公司 Sewage pumping station forebay structure convenient for desilting
CN103768839A (en) * 2014-01-21 2014-05-07 化工部长沙设计研究院 Multifunctional mine sedimentation tank capable of realizing all-weather continuous work
JP2016007564A (en) * 2014-06-24 2016-01-18 クボタ環境サ−ビス株式会社 Sand pumping method and sand settling facility
CN104174191A (en) * 2014-08-18 2014-12-03 南京工业大学 Integrated grit chamber for treating rainwater and treatment method
CN104532947A (en) * 2015-01-04 2015-04-22 上海市城市建设设计研究总院 Underground open-type storage pond
CN206971370U (en) * 2017-07-14 2018-02-06 陈震生 Municipal rain, sewage pumping station automatic dredging system

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
马旭东等: "排水泵站沉积泥砂处理***的研究与应用", 《中国给水排水》 *

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108560694A (en) * 2018-03-12 2018-09-21 上海市城市建设设计研究总院(集团)有限公司 Rainfall pumping station with test run function
CN113090325A (en) * 2021-03-17 2021-07-09 中铁大桥勘测设计院集团有限公司 Construction method for tunnel drainage ditch

Also Published As

Publication number Publication date
CN107178144B (en) 2023-03-31

Similar Documents

Publication Publication Date Title
CN110512674B (en) River dredging screening dredging method and equipment
CN206971370U (en) Municipal rain, sewage pumping station automatic dredging system
CN206971364U (en) Municipal rain, sewage pumping station
CN202689175U (en) Water collecting well desilting system
CN206971368U (en) Municipal rain, sewage pumping station sludge lifting system
CN107178144A (en) Municipal rain, sewage pumping station automatic dredging system and dredging method
CN107178143A (en) Municipal rain, sewage pumping station sludge lifting system
CN107806170A (en) First rain storage pond flap type flusher, its control method and first rain storage pond
CN206971367U (en) Municipal rain, sewage pumping station open Accrete clearing device with speed of damming
CN209941857U (en) Building site rainwater recycle system
CN106758799A (en) For the system for reclaiming rainwater and its construction method of sponge urban interchange
CN107558571B (en) Municipal drainage pipeline
CN113914447A (en) Waterlogging drainage pump station and construction method thereof
CN105442686B (en) Integrated sewage water/rainwater-collecting and conveying device
CN105350593B (en) Dam body upstream face sand discharge dredging method
CN204676677U (en) Silting blocking formula inverted-siphon sewer system
CN115110555B (en) Non-return drainage device for rapidly pumping and draining accumulated water of foundation pit and construction method
CN113529902B (en) Combined type rainwater and sewage inspection well and environment-friendly diversion method
CN110528474A (en) A kind of automation hydroelectric generation sluice gate
Auel et al. Sediment management in the Solis reservoir using a bypass tunnel
CN110217908A (en) A kind of industrial tail water environment protection treating system
CN214784082U (en) Large-scale deep basal pit engineering drainage system
CN109056965A (en) The governing system and method for the pipeline being connected to natural water
CN107837958A (en) One kind is used for water conservancy equipment production vibrations sand washer
CN207436227U (en) First rain storage pond flap type flusher and first rain storage pond

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
TA01 Transfer of patent application right

Effective date of registration: 20200611

Address after: 300382 building E83, No.1, Sizhi Road, Xuefu Industrial Zone, Xiqing District, Tianjin

Applicant after: SKF (Tianjin) Intelligent Water System Co.,Ltd.

Address before: Lutai Town, Tianjin city Ninghe County 301500 Jin Yu branch cotton company compound

Applicant before: Chen Zhensheng

TA01 Transfer of patent application right
GR01 Patent grant
GR01 Patent grant
CP02 Change in the address of a patent holder

Address after: 301500, 1500 meters west of the Independent Village Committee in Dabeijiangu Town, Ninghe District, Tianjin City

Patentee after: SKF (Tianjin) Intelligent Water System Co.,Ltd.

Address before: Building E83, No. 1 Sizhi Road, Xuefu Industrial Zone, Xiqing District, Tianjin, 300382

Patentee before: SKF (Tianjin) Intelligent Water System Co.,Ltd.

CP02 Change in the address of a patent holder