CN107165294A - A kind of heat-preservation shear wall truss building system and its construction method - Google Patents

A kind of heat-preservation shear wall truss building system and its construction method Download PDF

Info

Publication number
CN107165294A
CN107165294A CN201710604818.8A CN201710604818A CN107165294A CN 107165294 A CN107165294 A CN 107165294A CN 201710604818 A CN201710604818 A CN 201710604818A CN 107165294 A CN107165294 A CN 107165294A
Authority
CN
China
Prior art keywords
component
foundation
pipe column
steel pipe
heat
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201710604818.8A
Other languages
Chinese (zh)
Inventor
尹芬芳
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hunan New Energy Carpenter Materials Factory
Original Assignee
Hunan New Energy Carpenter Materials Factory
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hunan New Energy Carpenter Materials Factory filed Critical Hunan New Energy Carpenter Materials Factory
Priority to CN201710604818.8A priority Critical patent/CN107165294A/en
Publication of CN107165294A publication Critical patent/CN107165294A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/62Insulation or other protection; Elements or use of specified material therefor
    • E04B1/74Heat, sound or noise insulation, absorption, or reflection; Other building methods affording favourable thermal or acoustical conditions, e.g. accumulating of heat within walls
    • E04B1/76Heat, sound or noise insulation, absorption, or reflection; Other building methods affording favourable thermal or acoustical conditions, e.g. accumulating of heat within walls specifically with respect to heat only
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B2/00Walls, e.g. partitions, for buildings; Wall construction with regard to insulation; Connections specially adapted to walls
    • E04B2/56Load-bearing walls of framework or pillarwork; Walls incorporating load-bearing elongated members
    • E04B2/58Load-bearing walls of framework or pillarwork; Walls incorporating load-bearing elongated members with elongated members of metal
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04HBUILDINGS OR LIKE STRUCTURES FOR PARTICULAR PURPOSES; SWIMMING OR SPLASH BATHS OR POOLS; MASTS; FENCING; TENTS OR CANOPIES, IN GENERAL
    • E04H9/00Buildings, groups of buildings or shelters adapted to withstand or provide protection against abnormal external influences, e.g. war-like action, earthquake or extreme climate
    • E04H9/02Buildings, groups of buildings or shelters adapted to withstand or provide protection against abnormal external influences, e.g. war-like action, earthquake or extreme climate withstanding earthquake or sinking of ground
    • E04H9/021Bearing, supporting or connecting constructions specially adapted for such buildings

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Physics & Mathematics (AREA)
  • Electromagnetism (AREA)
  • Business, Economics & Management (AREA)
  • Emergency Management (AREA)
  • Environmental & Geological Engineering (AREA)
  • Acoustics & Sound (AREA)
  • Mechanical Engineering (AREA)
  • Building Environments (AREA)

Abstract

The present invention relates to technical field of buildings there is provided a kind of construction method of heat-preservation shear wall truss building system, including:Bed course reinforcement component or pile foundation reinforcement cage based on steel pipe column, reinforcement foundation component are set on reinforcement foundation component;Installation foundation joist steel rib component, is welded after foundation beam reinforcement component and steel pipe column falcon are connect;Wall body structure and joist steel rib component are installed, joist steel rib component is connected with wall body structure and steel pipe column, joist steel rib component is welded after being connect with steel pipe column falcon;To reinforcement foundation component casting concrete;To foundation beam reinforcement component casting concrete;To steel pipe column casting concrete;To joist steel rib component casting concrete;Laminated floor slab is installed, laminated floor slab is connected with joist steel rib component.Present invention also offers a kind of heat-preservation shear wall truss building system, heat-preservation shear wall truss building system heat-preservation shear wall truss building system construction method provided by the present invention, which is built, to be obtained, and properties are preferable.

Description

A kind of heat-preservation shear wall truss building system and its construction method
Technical field
The present invention relates to technical field of buildings, in particular to a kind of heat-preservation shear wall truss building system and its apply Work method.
Background technology
Heat-preservation shear wall is one kind in various wall structural systems.Heat-preserving building system mostly uses heat-preservation shear wall knot Structure is made, and existing heat-preserving building system has some shortcomings, and it is not very high to cause its various performance.Existing main cast System mainly includes brick mix structure, frame structure and frame-shear-wall structure.Mixed brick structure has as a drawback that:1st, it is only applicable to Less than 7 layers buildings, can not be used for long span building.2nd, the construction from it is great (unit weight be 2200~2500 kilograms/ Cubic meter) it can not also increase the usable floor area of building (thickness of wall body final size is 300mm).3rd, the rigidity of structure is poor, antidetonation Performance is low, thermal and insulating performance is poor.4th, cause construction rubbish many material used, construction is complicated, long construction period more.Frame Frame structure has as a drawback that:1st, the construction can not also increase from great (unit weight is 2200~2500 kilograms/cubic metre) The usable floor area of big building (thickness of wall body final size is 300mm).2nd, building globality poor, anti-seismic performance is low, insulation Heat-insulated, fire protecting performance is poor.3rd, cause that construction rubbish is more, construction is complicated, long construction period the material used more.Shear force of frame Wall has as a drawback that:1st, the structural construction can not also increase building from great (unit weight is 2200~2500 kilograms/cubic metre) The usable floor area of thing (thickness of wall body final size is 300mm).2nd, it is overall using ordinary reinforced concrete insulation, fire line Can be poor.3rd, cause that construction rubbish is more, construction is complicated, long construction period the material used more.
The content of the invention
The invention provides a kind of construction method of heat-preservation shear wall truss building system, it is intended to improves existing construction party The imperfect problem of heat-preserving building system performance that method is built.
Present invention also offers a kind of heat-preservation shear wall truss building system, it has a crack resistance, and it is excellent that anti-seismic performance is good etc. Point.
What the present invention was realized in:
A kind of construction method of heat-preservation shear wall truss building system, comprises the following steps:
Bed course reinforcement component or pile foundation reinforcing bar based on steel pipe column, reinforcement foundation component are set on reinforcement foundation component Cage;Installation foundation joist steel rib component, is welded after foundation beam reinforcement component and steel pipe column falcon are connect;Wall body structure and beam steel are installed Component, joist steel rib component is connected with wall body structure and steel pipe column, and joist steel rib component is welded after being connect with steel pipe column falcon;To basic steel Rib component casting concrete;To foundation beam reinforcement component casting concrete;To steel pipe column casting concrete;Poured to joist steel rib component Build concrete;Laminated floor slab is installed, laminated floor slab is connected with joist steel rib component.
Above-mentioned steps are not necessarily carried out successively without sequencing, " to reinforcement foundation component casting concrete;Xiang Ji Plinth joist steel rib component casting concrete;To steel pipe column casting concrete;To joist steel rib component casting concrete ", these steps Not necessarily sort after electrode welding process after joist steel rib component and steel pipe column falcon connect, casting concrete can be according to construction ring The construction custom adjustment of border and construction team.
Further, in preferred embodiments of the present invention, being set on reinforcement foundation component before steel pipe column also includes Building foundation is excavated on ground and concreting blinding layer is used, reinforcement foundation component is set on blinding layer.
Further, in preferred embodiments of the present invention, wall body structure is installed and referred to, is done using galvanizing double-layer wire Set hot-galvanized steel screen frame abdomen silk that wall frame is made into steel wire net rack, and on steel wire net rack, by wall frame and steel pipe Post falcon is welded after connecing, after then wall frame is connected with joist steel rib component, first first to reinforcement foundation component casting concrete, The casting concrete into wall frame again.
Further, in preferred embodiments of the present invention, joist steel rib component is with steel pipe column and wall frame using first Falcon is welded connection after connecing.
Further, in preferred embodiments of the present invention, the intensity of lightweight concrete is C2.5~C7.5, wall body structure Unit weight be 500~900 kilograms/cubic metre.
Further, in preferred embodiments of the present invention, poured in the forward direction reinforcement foundation component for installing wall body structure Concrete, pillar is obtained to steel pipe column casting concrete, and beam is obtained to joist steel rib component casting concrete;Install wall body structure refer to by Polylith prefabricated board is spliced to form wall body structure, and every piece of prefabricated board is anchored and truss connection with corresponding pillar or beam;Install During laminated floor slab, laminated floor slab is anchored with prefabricated board and truss is connected.
Further, in preferred embodiments of the present invention, install after laminated floor slab, build floor is poured on laminated floor slab and is mixed Solidifying soil, floorslab concrete is the high-performance light concrete that unit weight is 800 kilograms/cubic metre.
A kind of heat-preservation shear wall truss building system, the heat-preservation shear wall truss building system is sheared using above-mentioned insulation The construction method building of wall truss building system is formed, and building system includes foundation beam, beam, pillar, wall body structure and overlapping Floor, foundation beam is arranged at bottom, and beam is arranged at top, and pillar is connected perpendicular to foundation beam and beam and with foundation beam and beam, folds Close floor to be connected with beam, wall body structure is connected with foundation beam, beam, pillar, beam includes joist steel rib component, joist steel rib component has been poured Concrete, foundation beam includes foundation beam reinforcement component, and foundation beam reinforcement component has poured concrete, and pillar includes steel pipe column, steel Concrete is poured in tubing string, joist steel rib component and foundation beam reinforcement component are welded after being connect with steel pipe column falcon.
Further, in preferred embodiments of the present invention, wall body structure includes wall frame, and wall frame includes hot dip Poured in zinc double-layer wire rack and the hot-galvanized steel screen frame abdomen silk being connected with galvanizing double-layer wire rack, wall frame Concrete.
Further, in preferred embodiments of the present invention, the wall thickness of steel pipe column is 3-15mm, and the section of steel pipe column is chi The very little rectangle for 150-300mm × 150-300mm.
The beneficial effects of the invention are as follows:The heat-preservation shear wall truss building system that the present invention is obtained by above-mentioned design is applied Work method and high-performance building are Japanese, and high performance concrete will be poured in steel pipe column can strengthen the compactness of pillar, cracking resistance Property, impermeability, resistance to acids and bases and water proofing property, and then strengthen the compactness of heat-preservation shear wall truss building system, it is crack resistance, anti- Oozing property, resistance to acids and bases and water proofing property.And joist steel rib component and foundation beam reinforcement component are welded after being connect with steel pipe column falcon, increase The big rigidity and shock resistance of heat-preservation shear wall truss building system.And the structure is substantially without building waste, simple and fast of constructing And can effectively shorten construction period.
Brief description of the drawings
In order to illustrate more clearly of the technical scheme of embodiment of the present invention, it will use below required in embodiment Accompanying drawing be briefly described, it will be appreciated that the following drawings illustrate only certain embodiments of the present invention, therefore be not to be seen as It is the restriction to scope, for those of ordinary skill in the art, on the premise of not paying creative work, can be with root Other related accompanying drawings are obtained according to these accompanying drawings.
Fig. 1 is the structural representation for the heat-preservation shear wall truss building system that embodiment of the present invention is provided;
Fig. 2 be embodiment of the present invention provide heat-preservation shear wall truss building system non-casting concrete when structure show It is intended to;
Fig. 3 is the side structure schematic diagram that Fig. 1 central sills are connected with pillar;
Fig. 4 is the structural representation of wall frame in Fig. 2;
Fig. 5 is the structural representation of laminated floor slab and beam when overlooking.
Icon:100- heat-preservation shear wall truss building systems;110- foundation beams;111- foundation beam reinforcement components;120- beams; 121- joist steel rib components;130- pillars;131- steel pipe columns;140- wall body structures;141- wall frames;142- galvanizing clad steels Screen frame;143- hot-galvanized steel screen frames abdomen silk;150- laminated floor slabs;151- floorslab concretes layer;160- bases;161- bases Reinforcement component.
Embodiment
To make the purpose, technical scheme and advantage of embodiment of the present invention clearer, below in conjunction with present invention implementation Accompanying drawing in mode, the technical scheme in embodiment of the present invention is clearly and completely described, it is clear that described reality The mode of applying is a part of embodiment of the invention, rather than whole embodiments.Based on the embodiment in the present invention, ability The every other embodiment that domain those of ordinary skill is obtained under the premise of creative work is not made, belongs to the present invention The scope of protection.Therefore, the detailed description of embodiments of the present invention below to providing in the accompanying drawings, which is not intended to limit, wants The scope of the present invention of protection is sought, but is merely representative of the selected embodiment of the present invention.Based on the embodiment in the present invention, The every other embodiment that those of ordinary skill in the art are obtained under the premise of creative work is not made, belongs to this Invent the scope of protection.
In the description of the invention, it is to be understood that term " length ", " width ", " thickness ", " on ", " under ", " perpendicular Directly ", the orientation or position relationship of the instruction such as " level ", " top ", " bottom ", " interior ", " outer " are based on orientation shown in the drawings or position Relation is put, the description present invention is for only for ease of and simplifies description, rather than indicate or imply that the equipment or element of meaning are necessary With specific orientation, with specific azimuth configuration and operation, therefore it is not considered as limiting the invention.
In addition, term " first ", " second " are only used for describing purpose, and it is not intended that indicating or implying relative importance Or the implicit quantity for indicating indicated technical characteristic.Thus, define " first ", the feature of " second " can express or Implicitly include one or more this feature.In the description of the invention, " multiple " are meant that two or more, Unless otherwise specifically defined.
In the present invention, unless otherwise clearly defined and limited, term " installation ", " connected ", " connection ", " fixation " etc. Term should be interpreted broadly, for example, it may be fixedly connected or be detachably connected, or integrally;Can be that machinery connects Connect or electrically connect;Can be joined directly together, can also be indirectly connected to by intermediary, can be in two elements The connection in portion or the interaction relationship of two elements.For the ordinary skill in the art, can be according to specific feelings Condition understands the concrete meaning of above-mentioned term in the present invention.
In the present invention, unless otherwise clearly defined and limited, fisrt feature second feature it " on " or it " under " Can directly it be contacted including the first and second features, it is not direct contact but by it that can also include the first and second features Between other characterisation contact.Moreover, fisrt feature second feature " on ", " top " and " above " to include first special Levy directly over second feature and oblique upper, or be merely representative of fisrt feature level height higher than second feature.Fisrt feature exists Second feature " under ", " lower section " and " following " fisrt feature that includes are immediately below second feature and obliquely downward, or be merely representative of Fisrt feature level height is less than second feature.
As shown in Figure 1-Figure 3, the embodiments of the invention provide a kind of heat-preservation shear wall truss building system 100, it includes Foundation beam 110, beam 120, pillar 130, wall body structure 140 and laminated floor slab 150, foundation beam 110 are arranged at bottom, and beam 120 is set Top is placed in, pillar 130 is connected perpendicular to foundation beam 110 and beam 120 and with foundation beam 110 and beam 120, with reference to referring to the drawings 5, Laminated floor slab 150 is connected as one with beam 120, and wall body structure 140 is connected with foundation beam 110, beam 120, pillar 130, Liang120Bao Joist steel rib component 121 is included, joist steel rib component 121 has poured concrete, and foundation beam 110 includes foundation beam reinforcement component 111, basis Joist steel rib component 111 has poured concrete, and pillar 130 includes having poured concrete, beam steel in steel pipe column 131, steel pipe column 131 Component 121 and foundation beam reinforcement component 111 are welded after being connect with the falcon of steel pipe column 131.
The bottom of foundation beam 110 is additionally provided with basis 160, and basis 160 is by the casting concrete system of reinforcement foundation component 161 Into.
High performance concrete will be poured in steel pipe column 131 and can strengthen the compactness of pillar 130, crack resistance, impermeability, Resistance to acids and bases and water proofing property, so strengthen the compactness of heat-preservation shear wall truss building system 100, it is crack resistance, impermeability, resistance to Acid-base property and water proofing property.And joist steel rib component 121 and foundation beam reinforcement component 111 are welded then after being connect with the falcon of steel pipe column 131 Increase the rigidity and shock resistance of heat-preservation shear wall truss building system 100.And the structure, substantially without building waste, construction is simple It is quick and can effectively shorten construction period.
It refer to shown in accompanying drawing 4, further, wall body structure 140 includes wall frame 141, and wall frame 141 includes heat Zinc-plated double-layer wire rack 142 and the hot-galvanized steel screen frame abdomen silk 143 being connected with galvanizing double-layer wire rack 142, hot dip Zinc steel wire net rack abdomen silk 143, which is wound in galvanizing double-layer wire rack 142, wall frame 141, has poured concrete.Wall frame The concrete poured in frame 141 is high-performance light concrete.
High-performance light concrete reduces the deadweight of traditional architecture thing with being used in combination for wall frame 141, is built into This and can also improve the rigidity of wall body structure 140.
It should be noted that in other embodiments of the invention, wall body structure can also splice shape by polylith prefabricated board Into every piece of prefabricated board is connected with corresponding pillar or beam anchoring and truss.
Further, galvanizing double-layer wire rack 142 is made up of double-deck a diameter of 2.5~3.5mm hot-dip galvanizing steel wire, The diameter of hot-galvanized steel screen frame abdomen silk 143 is also 2.5~3.5mm.From the hot-dip galvanizing steel wire and hot-dip galvanizing steel wire of the size Rack abdomen silk 143 ensure that the fastness of wall while building cost is relatively low can also reach preferably effect.
Further, the thickness of wall body structure 140 is 150~200mm, and the thickness is ensureing not giving pillar 130 and base Under conditions of the excessive loads of plinth beam 110, heat insulation effect is best.
Further, the wall thickness of steel pipe column 131 is 3~15mm, the section of steel pipe column 131 be size be 150~300mm × 150~300mm rectangle.The obtained eager to do well in everything degree of pillar shock resistance is high after the casting concrete of steel pipe column 131 of the size.
Further, the spiral that the reinforcing bar that joist steel rib component 121 is selected is 12~25mm of diameter, the reinforcing bar of the size The intensity of beam 120 made from the obtained good toughness of joist steel rib component 121 is high.
Further, the reinforcing bar length that joist steel rib component 121 is selected is more than or equal to 6m, and the reinforcing bar more than or equal to 6m is Longer joist steel rib component 121 can be made and then can just make the longer obtained heat-preservation shear wall truss building system 100 of beam 120 Span could be bigger.
Further, the section of beam 120 is the rectangle that size is 300~500mm × 150~200mm, the beam during size 120 load-bearing property is good.
As shown in Figure 1 and Figure 5, further, first floor board concrete layer 151 is poured on laminated floor slab 150, floor is set Concrete layer 151 is conducive to strengthening the crack resistance of heat-preservation shear wall truss building system 100.
Present invention also offers a kind of building, the building is built including heat-preservation shear wall truss provided by the present invention System 100.
A kind of method for building the heat-preservation shear wall truss building system 100 that the embodiment of the present invention is provided, this method bag Include following steps:
Bed course reinforcement component based on S1, the setting steel pipe column 131 on reinforcement foundation component 161, reinforcement foundation component 161 Or pile foundation reinforcement cage.
Specifically, building foundation is excavated first, it is necessary to use cushion cap base below explanation, 8 layers of the building system built Plinth, less than 13 layers using artificial digging pile, more than 13 layers using machine drive piles basis;Then concreting blinding layer is used, The concrete is the high performance concrete that intensity is C30, and protective layer can also be set on blinding layer by having poured after blinding layer And waterproof layer, then reinforcement foundation component 161 is set on blinding layer again, steel pipe is set on reinforcement foundation component 161 Post 131.The reinforcement foundation component 161 can be that blinding layer reinforcing bar can also be pile foundation reinforcement cage, according to different constructions Mode and construction environment select different bases.
S2, installation foundation joist steel rib component 111, are welded after foundation beam reinforcement component 111 and the falcon of steel pipe column 131 are connect.
Specifically, use reinforcing bar that basic joist steel is made for the spiral that 12~25mm of diameter, length are more than or equal to 6m Rib component 111, the foundation beam reinforcement component 111 is welded after being connect with the falcon of steel pipe column 131, and the connection gimmick causes the base being eventually fabricated The connection of plinth beam 110 and pillar 130 is more firm, increases the crack resistance of system, foundation beam reinforcement component 111 and steel pipe column 131 After connecting, to the casting concrete of reinforcement foundation component 161, base is poured into foundation beam reinforcement component 111 after completing basis 160 Plinth beam concrete, foundation beam 110 then builds completion, and foundation beam concrete is also the high performance concrete that intensity is C30, its reclaimed water Mud uses C42.5 portland cements.
S3, installation wall body structure 140 and joist steel rib component 121, joist steel rib component 121 and wall body structure 140 and steel pipe Post 131 is connected, and joist steel rib component 121 is welded after being connect with the falcon of steel pipe column 131.
Specifically, wall body structure 140 is installed to refer to, the galvanizing double-layer wire rack 142 made using hot-dip galvanizing steel wire, And set hot-galvanized steel screen frame abdomen silk 143 that wall frame 141 is made on galvanizing double-layer wire rack 142, by wall frame Frame 141 is welded after being connect with the falcon of steel pipe column 131, now mounting rail reinforcement component 121, then by wall frame 141 and beam steel structure Part 121 is connected, and is welded after joist steel rib component 121 and the falcon of steel pipe column 131 are connect, then the casting concrete into wall frame 141, The casting concrete into steel pipe column 131, to the casting concrete of joist steel rib component 121.Pacify while mounting rail reinforcement component 121 Install the preheating embedding lines such as the water, electricity, gas of this building system.
The concrete poured into wall frame 141 uses intensity for C2.5~C7.5 lightweight concrete, after building up The unit weight of wall body structure 140 is 500~900 kilograms/cubic metre.Using lightweight concrete so that the unit weight of wall body structure 140 not As for too high, make the load of pillar 130 little, increase the antidetonation crack resistance of system.Joist steel rib component 121 uses reinforcing bar for diameter The spiral that 12~25mm, length are more than or equal to 6m is made.Poured into steel pipe column 131 and joist steel rib component 121 strong The high performance concrete for C30 is spent, wherein cement uses C42.5 portland cements, and intensity is built up for C30 high performance concrete System have the advantages that high cracking resistance, high compactness, high waterproof, acid and alkali-resistance are strong and can about save 10% cement.
It should be noted that in other embodiments of the invention, wall body structure is spliced to form according to polylith prefabricated board, So its form of construction work is then:Just to reinforcement foundation component casting concrete before wall body structure is installed, poured to steel pipe column Concrete obtains pillar, and beam is obtained to joist steel rib component casting concrete;Wall body structure is installed to refer to polylith prefabricated board being spliced to form Wall body structure, every piece of prefabricated board is anchored and truss connection with corresponding pillar or beam;When laminated floor slab is installed, laminated floor slab It is connected with prefabricated board anchoring and truss.
S4, installation laminated floor slab 150, laminated floor slab 150 are connected with joist steel rib component 121.
Specifically, it is then beam 120 to have poured the joist steel rib component 121 after concrete, and laminated floor slab is installed on beam 120 150, and laminated floor slab 150 is connected with beam 120.Further, install after laminated floor slab 150, in laminated floor slab 150 On pour floorslab concrete with formed floorslab concrete layer 151, floorslab concrete is the high property that unit weight is 800 kilograms/cubic metre Can lightweight concrete.
After floor concrete casting is complete, continues the above-mentioned construction procedure of installation upper strata steel pipe column repetition and build top floor, directly To building to roof girder.This building system, which is continued to build, also to be included building stair as building, installs roofing template, installs The built-in fittings such as roofing reinforcing bar, pour the thick unit weights of 100mm for 800 kilograms high-performance light concrete, installed using waterproof mortar Watt.
It should be noted that in other embodiments of the present invention, pouring for each reinforcement component concrete can be according to construction The factor adjustment such as progress, each construction team construction custom and construction environment pour order.Can install structure to pour immediately, Can also be poured together after all reinforcement components of whole system install connection, for example, can install reinforcement foundation component immediately Casting concrete installation foundation beam building concrete immediately again, is further continued for installing steel pipe column, installs steel pipe column then immediately Placing concrete, is carried out successively;Reinforcement foundation component and foundation beam reinforcement component can also be installed then to reinforcement foundation component With foundation beam reinforcement component placing concrete, then steel pipe column, joist steel rib component and wall frame are installed again, after installing again To a variety of forms of construction work such as steel pipe column, joist steel rib component and wall frame casting concretes.
In summary, the concrete that heat-preservation shear wall truss Building architecture part basis, pillar, beam etc. are poured is equal Using C30 high performance concretes, (cement uses C42.5 portland cements, and adds nanometer building materials reinforcing agent etc., can improve coagulation Soil 10~20% intensity, increase the function such as its compactness, cracking resistance, impervious, acid and alkali-resistance, waterproof), existing brick mix structure knot Structure use build brick (post beam therebetween is only constructional column and collar tie beam, and concrete uses C20 normal concretes) by laying bricks or stones can not It is integrally formed whole building;Frame structure structure division uses that post beam floor is cast-in-place, frame-shear-wall structure structural portion Divide to use and pour post beam floor wall etc., frame structure, shear wall structure beam column are that large scale makes post beam protrude wall Influence reduction usable floor area attractive in appearance, three of the above structure wall is 300mm thick (building brick or casting concrete by laying bricks or stones) and of the invention It is only 150~200mm that the wall of the heat-preservation shear wall truss building system of proposition, which builds up back wall thickness,;Heat-preservation shear wall of the present invention Truss building system pillar uses wall thickness for 3mm to 10mm, cross dimensions for 150~300mm × 150~300mm square or The rigidity of structure of rectangle steel tubing string (pouring C30 high performance concretes in pipe) this kind of concrete-filled steel tubular column is with size ordinary steel 4~6 times of reinforced concrete, its compression strength is 2.5~3 times with size regular reinforcement coagulation pillar, and its torsional strength is same 3 times or so of size ordinary reinforced concrete;This building body binder is using reinforcing bar or shaped steel (it is to use that span, which is more than 6 meters) and steel Pipe carries out electric welding falcon and connect, and the cross dimensions of beam is 300~500mm × 150~200mm;Wall uses unit weight for 500~900 Steel wire net rack high-performance light concrete (intensity the be C2.5~7.5) prefabricated board of kilogram/cubic metre and with pillar, beam, floor Truss is carried out to link into an integrated entity;This building system floor uses laminated floor slab;This building system roof boarding and gutter plate and other Part carries out truss and linked into an integrated entity, and roofing uses unit weight for the high-performance light concreting of 800 kilograms/cubic metre;By This visible heat-preservation shear wall truss building system proposed by the present invention is than brick mix structure, frame structure, heat-preservation shear wall structure phase Than this building system major advantage has:
It is a, antidetonation, waterproof, insulation, heat-insulated, sound insulation, fire prevention, weatherability, structure-integrated.
B, deadweight are only pass logical building deadweight 40% or so.
C, substantially without building waste, simple and fast of constructing, construction period shortens 2/3.
D, integrated cost reduction by 30% or so.
E, 60% building component are processed in plant produced, low to the skill set requirements of workmen.
F, synthesis energy saving more than 65%.
G, increase construction area 6~8%.
H, the building for being adapted to each field, earthquake territory, the torrid zone, low-temperature space, to insulation, it is heat-insulated, fire prevention etc. have especially It is required that building.
The preferred embodiment of the present invention is the foregoing is only, is not intended to limit the invention, for this area For technical staff, the present invention can have various modifications and variations.Within the spirit and principles of the invention, that is made is any Modification, equivalent substitution, improvement etc., should be included in the scope of the protection.

Claims (10)

1. a kind of construction method of heat-preservation shear wall truss building system, it is characterised in that comprise the following steps:
Bed course reinforcement component or pile foundation reinforcing bar based on steel pipe column, the reinforcement foundation component are set on reinforcement foundation component Cage;
Installation foundation joist steel rib component, is welded after the foundation beam reinforcement component and the steel pipe column falcon are connect;
Wall body structure and joist steel rib component are installed, the joist steel rib component is connected with the wall body structure and the steel pipe column, The joist steel rib component is welded after being connect with the steel pipe column falcon;
To the reinforcement foundation component casting concrete;To the foundation beam reinforcement component casting concrete;To the steel pipe column Casting concrete;To the joist steel rib component casting concrete;
Laminated floor slab is installed, the laminated floor slab is connected with the joist steel rib component.
2. the construction method of heat-preservation shear wall truss building system according to claim 1, it is characterised in that in the base Set on plinth reinforcement component and ground excavation building foundation is additionally included in before the steel pipe column and using concreting base mat Layer, sets reinforcement foundation component on blinding layer.
3. the construction method of heat-preservation shear wall truss building system according to claim 1, it is characterised in that install described Wall body structure refers to, makes steel wire net rack using galvanizing double-layer wire, and set hot-dip galvanizing steel wire on the steel wire net rack Wall frame is made in rack abdomen silk, is welded after the wall frame and the steel pipe column falcon are connect, then by the wall frame After being connected with the joist steel rib component, first first to the reinforcement foundation component casting concrete, then into the wall frame Pour lightweight concrete.
4. the construction method of heat-preservation shear wall truss building system according to claim 3, it is characterised in that the joist steel Rib component is welded after being connect with the steel pipe column and the wall frame using first falcon and is connected.
5. the construction method of heat-preservation shear wall truss building system according to claim 3, it is characterised in that the lightweight The intensity of concrete is C2.5~C7.5, and the unit weight of the wall body structure is 500~900 kilograms/cubic metre.
6. the construction method of heat-preservation shear wall truss building system according to claim 1, it is characterised in that installing institute Reinforcement foundation component casting concrete described in the forward direction of wall body structure is stated, pillar is obtained to the steel pipe column casting concrete, to institute State joist steel rib component casting concrete and obtain beam;The wall body structure is installed to refer to polylith prefabricated board being spliced to form wall body structure, Every piece of prefabricated board is anchored and truss connection with the corresponding pillar or the beam;It is described when the laminated floor slab is installed Laminated floor slab is anchored with the prefabricated board and truss is connected.
7. the construction method of heat-preservation shear wall truss building system according to claim 1, it is characterised in that install described After laminated floor slab, floorslab concrete is poured on the laminated floor slab, the floorslab concrete is that unit weight is 800 kilograms/cube The high-performance light concrete of rice.
8. a kind of heat-preservation shear wall truss building system, it is characterised in that the heat-preservation shear wall truss building system is using such as The construction method building of heat-preservation shear wall truss building system described in claim 1 is formed, and the building system includes basis Beam, beam, pillar, wall body structure and laminated floor slab, the foundation beam are arranged at bottom, and the beam is arranged at top, the post Son is connected perpendicular to the foundation beam and the beam and with the foundation beam and the beam, and the laminated floor slab connects with the beam Connect, the wall body structure is connected with the foundation beam, the beam, the pillar, the beam includes joist steel rib component, the joist steel Rib component has poured concrete, and the foundation beam includes foundation beam reinforcement component, and the foundation beam reinforcement component has poured coagulation Soil, the pillar includes having poured concrete, the joist steel rib component and the basic beam steel in steel pipe column, the steel pipe column Component is welded after being connect with the steel pipe column falcon.
9. heat-preservation shear wall truss building system according to claim 8, it is characterised in that the wall body structure includes wall Body framework, the wall frame includes galvanizing double-layer wire rack and the hot dip being connected with the galvanizing double-layer wire rack Concrete has been poured in zinc steel wire net rack abdomen silk, the wall frame.
10. heat-preservation shear wall truss building system according to claim 8, it is characterised in that the wall thickness of steel pipe column is 3- 15mm, the section of the steel pipe column is the rectangle that size is 150-300mm × 150-300mm.
CN201710604818.8A 2017-07-24 2017-07-24 A kind of heat-preservation shear wall truss building system and its construction method Pending CN107165294A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710604818.8A CN107165294A (en) 2017-07-24 2017-07-24 A kind of heat-preservation shear wall truss building system and its construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710604818.8A CN107165294A (en) 2017-07-24 2017-07-24 A kind of heat-preservation shear wall truss building system and its construction method

Publications (1)

Publication Number Publication Date
CN107165294A true CN107165294A (en) 2017-09-15

Family

ID=59817399

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710604818.8A Pending CN107165294A (en) 2017-07-24 2017-07-24 A kind of heat-preservation shear wall truss building system and its construction method

Country Status (1)

Country Link
CN (1) CN107165294A (en)

Citations (15)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2002227188A (en) * 2001-01-31 2002-08-14 Yoriko Masuda Ring assembly for reinforced cage and reinforced cage assembling method as well as reinforced cage connecting method
KR20090058919A (en) * 2007-12-05 2009-06-10 동부건설 주식회사 Reinforced concrete structure
CN102561552A (en) * 2011-12-31 2012-07-11 北京工业大学 Steel tube concrete shear wall comprising vertical soft steel energy consuming straps with horizontal seams and manufacturing method
CN102704593A (en) * 2012-05-25 2012-10-03 北京工业大学 Steel tube reinforced concrete composite column-steel beam-lattice steel support shear wall and manufacturing method
CN102704592A (en) * 2012-06-18 2012-10-03 北京交通大学 Damping control method for existing frame structure
CN102797301A (en) * 2012-08-20 2012-11-28 宁波荣山新型材料有限公司 Low-temperature foam glass/steel wire net frame composite heat insulating plate and preparation method thereof
CN202644752U (en) * 2011-11-15 2013-01-02 赵仲星 Thermal insulation wallboard
CN103397696A (en) * 2013-08-16 2013-11-20 威海建设集团股份有限公司 Building adopting aseismatic precasted reinforcing steel truss shear wall composite structure
CN103711233A (en) * 2013-12-30 2014-04-09 北京工业大学 Reinforced concrete-filled steel tube frame steel plate composite shear wall with built-in concealed bracings and manufacturing method
CN103883035A (en) * 2014-03-21 2014-06-25 北京工业大学 Shear wall formed by embedding energy-dissipation bars between frame and wall with inbuilt multiple H-shaped steel plates and construction method
CN203866966U (en) * 2014-05-23 2014-10-08 浙江东南网架股份有限公司 Novel assembly type frame core tube steel structure residential housing system
CN104452749A (en) * 2014-11-17 2015-03-25 杭州江润科技有限公司 Construction method of reinforced concrete current-poured pile
CN204282348U (en) * 2014-11-17 2015-04-22 中大建设有限公司 A kind of reinforced concrete cast-in-situ pile tube
CN205369583U (en) * 2015-12-21 2016-07-06 济南捷源新材料有限公司 Take heat preservation composite wall of structure hole or window
CN206016309U (en) * 2015-12-29 2017-03-15 山东远博建筑科技有限公司 A kind of overall assembled building system

Patent Citations (15)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2002227188A (en) * 2001-01-31 2002-08-14 Yoriko Masuda Ring assembly for reinforced cage and reinforced cage assembling method as well as reinforced cage connecting method
KR20090058919A (en) * 2007-12-05 2009-06-10 동부건설 주식회사 Reinforced concrete structure
CN202644752U (en) * 2011-11-15 2013-01-02 赵仲星 Thermal insulation wallboard
CN102561552A (en) * 2011-12-31 2012-07-11 北京工业大学 Steel tube concrete shear wall comprising vertical soft steel energy consuming straps with horizontal seams and manufacturing method
CN102704593A (en) * 2012-05-25 2012-10-03 北京工业大学 Steel tube reinforced concrete composite column-steel beam-lattice steel support shear wall and manufacturing method
CN102704592A (en) * 2012-06-18 2012-10-03 北京交通大学 Damping control method for existing frame structure
CN102797301A (en) * 2012-08-20 2012-11-28 宁波荣山新型材料有限公司 Low-temperature foam glass/steel wire net frame composite heat insulating plate and preparation method thereof
CN103397696A (en) * 2013-08-16 2013-11-20 威海建设集团股份有限公司 Building adopting aseismatic precasted reinforcing steel truss shear wall composite structure
CN103711233A (en) * 2013-12-30 2014-04-09 北京工业大学 Reinforced concrete-filled steel tube frame steel plate composite shear wall with built-in concealed bracings and manufacturing method
CN103883035A (en) * 2014-03-21 2014-06-25 北京工业大学 Shear wall formed by embedding energy-dissipation bars between frame and wall with inbuilt multiple H-shaped steel plates and construction method
CN203866966U (en) * 2014-05-23 2014-10-08 浙江东南网架股份有限公司 Novel assembly type frame core tube steel structure residential housing system
CN104452749A (en) * 2014-11-17 2015-03-25 杭州江润科技有限公司 Construction method of reinforced concrete current-poured pile
CN204282348U (en) * 2014-11-17 2015-04-22 中大建设有限公司 A kind of reinforced concrete cast-in-situ pile tube
CN205369583U (en) * 2015-12-21 2016-07-06 济南捷源新材料有限公司 Take heat preservation composite wall of structure hole or window
CN206016309U (en) * 2015-12-29 2017-03-15 山东远博建筑科技有限公司 A kind of overall assembled building system

Similar Documents

Publication Publication Date Title
CN107476476B (en) One kind is greatly across steel bar truss floor support plate and reinforced beam combination constructing method thereof
CN105781125B (en) A kind of installation method of assembled architecture
CN206308796U (en) A kind of post insertion prefabricated PC concrete frame frame system
CN103397696B (en) Shatter-proof, prefabricated steel bar girder shear wall Temperature Variation In Buildings of Mixed Structures thing
CN106499051A (en) A kind of post insertion prefabricated PC concrete frame frame system and its construction method
CN108343257B (en) Construction method for additionally installing elevator in existing multi-storey house
CN107989227A (en) A kind of assembled steel reinforced concrete shear walls structure and its preparation and installation method
CN108060746A (en) A kind of prefabricated PC concrete large-span frame system and its construction method
CN105649360A (en) Integral assembling type building system and installing method
CN203475598U (en) Shock-proof prefabricated building of steel bar truss shearing wall composite structure
CN106245753A (en) A kind of armored concrete linked system of prefabricated structural wall board
CN103982041A (en) Method for constructing reinforced-concrete prefabricated element fabricated building with frame structure system
CN207538322U (en) A kind of prefabricated PC concrete frame frame system
CN108005304A (en) A kind of prefabricated PC concrete frame frame system and its construction method
CN102140842B (en) Industrial construction method for multistory residence system with clamp die frame core wall self-bearing structure
CN108005264A (en) A kind of steel framework constraint precast reinforced concrete shear wall structure and preparation and installation method
CN207739674U (en) A kind of assembled Residential System of Steel-concrete Composite Structure
CN103306497B (en) Shock prevention and strengthening construction method for existing brickwork dwelling house fabricated structure
CN111549826A (en) Interception construction method for post-cast strip prefabricated formwork in raft of main building
CN215166634U (en) Assembly type building wallboard connecting structure
CN110439291A (en) A kind of assembled production and construction method suitable for low-rise building
CN110644646A (en) Split-level grouting sleeve connected assembled shear wall system
CN110106915A (en) One kind exempts from that support is inverse to make underground engineering construction method and underground construction structure
CN105649259B (en) A kind of wallboard structural system of the dark framework of band of precast concrete wall panel and its structure
CN207314664U (en) A kind of assembling prefabricated reinforced concrete column and assembled combination frame building system

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20170915

RJ01 Rejection of invention patent application after publication