CN107151959A - A kind of drill school place construction Craft - Google Patents
A kind of drill school place construction Craft Download PDFInfo
- Publication number
- CN107151959A CN107151959A CN201710463185.3A CN201710463185A CN107151959A CN 107151959 A CN107151959 A CN 107151959A CN 201710463185 A CN201710463185 A CN 201710463185A CN 107151959 A CN107151959 A CN 107151959A
- Authority
- CN
- China
- Prior art keywords
- construction
- coating
- road surface
- spraying
- paint
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Withdrawn
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01C—CONSTRUCTION OF, OR SURFACES FOR, ROADS, SPORTS GROUNDS, OR THE LIKE; MACHINES OR AUXILIARY TOOLS FOR CONSTRUCTION OR REPAIR
- E01C9/00—Special pavings; Pavings for special parts of roads or airfields
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Road Repair (AREA)
Abstract
A kind of drill school place construction Craft, construction technology is comprised the concrete steps that:Datum mark, then carry out the construction line-putting first, implements to clean road surface, remove dust, silt and water and oil stain, spray-applied primer, 300 μm of thickness, drying time 24H, sprays intermediate coat, 200 μm of thickness, drying time 15min, spray paint, 200 μm of thickness, drying time 72H, dry completion, adjustment maintenance, final acceptance of construction.The invention reaches that spraying is non-foaming, uninterrupted when spraying is per coating by the preparation before the road surface spray coating of place, the configuration of spraying equipment and the control of spraying process during operation;Prolonged wait is avoided in spraying process to cause that coating is dry and cracked, foaming, while Construction Cost is also reduced, applied in construction engineering technical field.
Description
Technical field
The present invention relates to a kind of drill school place construction Craft in construction engineering technical field.
Background technology
At present, with the fast development of China's economy, the highway construction cause of China has also obtained fast development, but carries
High driver's reply is because of moist earth's surface, vehicle caused by the wet road surface caused such as ice and snow day, rainy day, greasy weather and spraying water for brake etc.
Sideslip ability then needs driver greatly to improve the level of training.The necessity of driver sideslip training place:Sideslip training is aimed to solve the problem that
Driver tackles all-weather road situation, trains and improves wet-skid road surface on-slip point and stop technology, so as to drive energy in safe distance between vehicles
Positive braking is reached in enough premises placed in the middle do not breakked away.Produce the factor of wet-skid road surface:Black ice and rainy greasy weather on road, with
And muddy road surface etc..During similar dangerous situation, it is also possible to occur oils or chemical leakage to road surface, because lighter component
Leave greasy smooth evaporation quickly.This is that the driver for being difficult to be traveling has found in time, so that skidding, black ice are produced, it is also referred to as " dizzy
Light ice " or " cleaning ice and snow ", typically refer to be formed the ice face shallow layer such as glass of an embedding air bubble formation on surface,
It is very common on road.Although not being real black, because it is highly transparent, it is allowed to dark asphalt/granular-type road
Color pass through it.And snow, freezing dirt is compared, it is difficult to be arrived by driver observation, in addition, it often interlocks with wet and slippery road
's.Compared with the road ice of other forms, its unusual light, to impacted road surfaces, particularly motor vehicle and non-motor vehicle
Driving or pedestrian produce it is dangerous.Black ice species(Black ice category) include:(1)In low temperature(Less than 0 ° -18
℃ ), pair when vehicle exhaust moisture, spraying water for brake etc., which condenses in pavement of road, can form black ice.Black ice is used for describing sometimes
The road of any kind of ice formation, the road even in ponding less than solidification point becomes ice.(2)Black ice may form
Even in environment temperature it is more than 0 DEG C of freezing point water if long-time cold current suddenly after air is warm, makes the road great distance on surface low
In the temperature of freezing point." facing ice " is endangered at home, and particularly southern most area is widely present.Be traffic accident it is main because
One of element.Therefore, it is the new problem for being badly in need of solving to develop a kind of drill school place construction Craft.
The content of the invention
It is an object of the invention to provide a kind of drill school place construction Craft, the invention is sprayed by place road surface
The configuration and the control of spraying process of preparation, spraying equipment before painting, spraying is reached when spraying is per coating during operation
It is non-foaming, uninterrupted;Prolonged wait is avoided in spraying process to cause that coating is dry and cracked, foaming, while also reduction engineering is applied
Work cost.
The object of the present invention is achieved like this:A kind of drill school place construction Craft, a kind of described training
School ground construction Craft is comprised the concrete steps that:
First, preparative work before construction:
1st, the precondition of the cleaning on road surface, coating and road surface strong bonded is to maintain the clean of contact surface, dust on road surface,
Silt and moisture are the principal elements for hindering paint adhesion, can be thorough using broom, scrubbing brush, gas burner according to different situations
Remove;
2nd, setting-out, the position indicated by design and figure get waterline on road surface with measurement apparatus, after setting-out is complete, should check whether
Correctly;
3rd, the preparation of construction machinery, is sprayed, 5KW generators one using Dutch schoonewil companies import equipment SBS mini
Group, 5.5KW air compressor machines one, one group of agitator, hair-dryer one, one, light truck car, steel ruler, tape measure, screwdriver, pliers, steel
Wire brush, broom;
2nd, product technology parameter in constructing:
1st, adhesive:Acrylic compounds;
2nd, volatilizable thing content:43%(512KG/L);
3rd, viscosity:30-40 seconds;
4th, consumption:300µm=0.3L/m2≈0.47kg/m2;
5;Amount of solid content:About 54%;
3rd, execution conditions:
Temperature when the 1st, constructing cannot be below 10 degrees Celsius, and relative humidity is below 85%;
2nd, coating has the shelf-life in itself, and storage temperature is not above 35 degrees Celsius;
3rd, road surface must be dried during scrawling, and meet water and solvent reduction reaction time and intensity, in order to avoid reduction paint adhesion;
4th, road should be cleaned, no floating dust, the debris such as greasy dirt.Coating should be sufficiently stirred for;
5th, after construction terminates, thoroughly cleaning machinery is answered;
6th, it should have been used after uncapping in 2 days;
7th, the special diluent for participating in reaction may can be used in thick, to obtain suitable spray viscosity in coating during low temperature
ACS-M 1-3% must not use other diluents to prevent coating surface from flocculating;
8th, inserts, repairing road surface dell or duck eye can suitably be used;
9th, diluent and curing agent and coating need to be placed on interior, can not be placed on it is outdoor it is outdoor be exposed to the sun, otherwise influence product quality;
4th, construction technology:
Construction technology is comprised the concrete steps that:
Datum mark, then carry out the construction line-putting first, implements to clean road surface, removes dust, silt and water and oil stain, spray bottom
Paint, 300 μm of thickness, drying time 24H sprays intermediate coat, 200 μm of thickness, drying time 15min, spray paint, the μ of thickness 200
M, drying time 72H, dry completion, adjustment maintenance, final acceptance of construction;
Condition needed for work progress:
1st, construct number 6-10 people, cleans road surface, line of fetching water, the 3-5 of falling coating people, stirring, driving, responsible equipment 3-5 people;
2nd, the road surface for needing to construct is protected, so that workmen cleans road surface;
3rd, dust, silt, moisture, the oil stain on road surface are thoroughly removed with sweeper, wire brush, sander;
4th, measured by design requirement, draw waterline, unwrapping wire positioning;
5th, in order to ensure construction quality of pavement, coating used must be using the product for reaching technical standard;
6th, priming paint, intermediate layer, finish paint must stir before;
7th, the mixed proportion of HSRoute Pox-Outdoor and the curing agent of POX 41 is 28:1, with original packing, 1 bag of curing agent
(0.85kg, 0.85kg/l)Add 1 barrel of coating(24kg, 1.57kg/l)In, it is sufficiently stirred for immediately after mixing;
8th, with Dutch schoonewil companies import equipment SBS mini spray-applied primers, 300 μm of drying time 24H of thickness, purpose
It is sealing ground and increase adhesive force;
9th, intermediate layer can use round brush roller coat, 200 μm of drying time 15min of thickness;
10th, finish paint is using the import equipment SBS mini sprayings of schoonewil companies of Holland, 200 μm of drying time 72H of thickness;
11st, this product can construct uses in pitch and cement surface.Surface should be dried, and be cleaned without floating dust and discrete particles, salt-free
And greasy dirt;Surface should have certain viscosity, old that coating should be removed, new pitch should time at least 8 weeks, in cement surface construction water
Muddy water content should be less than 4%;2 can be used:1 or 1:1 dilution, confining surface, the foaming phenomena for preventing the volatilization of cement steam from producing;
12nd, fresh concrete and the old concrete surface for having peeling need to use HSRoute primer systems before construction;It is real
Existing reliable adhesion between HSRoute indoor coatings and concrete surface is, it is necessary to 2 intermediate materials:Bottom in HSRoute rooms
Paint and HSRoute interfaces, and priming paint needs to be applied to two layers in HSRoute rooms.Drying time is in expression of drawing;
5th, spraying application equipment:
1st, intermediate layer is that cold paint can use spraying or roller coat, and finish paint is that schoonewil companies of Holland can be used to enter for two-component
Jaws equipment SBS mini equipment;Airless spraying, nozzle width need to be more than 0.021, and spray angle should be≤40 °, and machine need to contain 60 mesh
Screen pack;
A kind of operation principle of described drill school place construction Craft is to pass through the beam worker before the road surface spray coating of place
Make, the configuration of spraying equipment and the control of spraying process, reached when spraying is per coating during operation spraying it is non-foaming, not between
It is disconnected;Prolonged wait is avoided in spraying process to cause that coating is dry and cracked, bubble, while also reducing Construction Cost.
The present invention is characterized by its construction technology.
A kind of drill school place construction Craft compared with prior art, with passing through the standard before the road surface spray coating of place
Standby work, the configuration of spraying equipment and the control of spraying process, reach that spraying is non-foaming, no when spraying is per coating during operation
Interruption;Prolonged wait is avoided in spraying process to cause that coating is dry and cracked, foaming, while also reduction Construction Cost etc. is excellent
Point, will be widely used in construction engineering technical field.
Brief description of the drawings
The present invention is described in detail with reference to the accompanying drawings and examples.
Fig. 1 is the construction technology figure of the present invention.
Fig. 2 is present invention construction thickness and drying time structural representation.
Embodiment
Referring to the drawings, a kind of drill school place construction Craft, a kind of described drill school place pavement construction
Technique is comprised the concrete steps that:
First, preparative work before construction:
1st, the precondition of the cleaning on road surface, coating and road surface strong bonded is to maintain the clean of contact surface, dust on road surface,
Silt and moisture are the principal elements for hindering paint adhesion, can be thorough using broom, scrubbing brush, gas burner according to different situations
Remove;
2nd, setting-out, the position indicated by design and figure get waterline on road surface with measurement apparatus, after setting-out is complete, should check whether
Correctly;
3rd, the preparation of construction machinery, is sprayed, 5KW generators one using Dutch schoonewil companies import equipment SBS mini
Group, 5.5KW air compressor machines one, one group of agitator, hair-dryer one, one, light truck car, steel ruler, tape measure, screwdriver, pliers, steel
Wire brush, broom;
2nd, product technology parameter in constructing:
1st, adhesive:Acrylic compounds;
2nd, volatilizable thing content:43%(512KG/L);
3rd, viscosity:30-40 seconds;
4th, consumption:300µm=0.3L/m2≈0.47kg/m2;
5;Amount of solid content:About 54%;
3rd, execution conditions:
Temperature when the 1st, constructing cannot be below 10 degrees Celsius, and relative humidity is below 85%;
2nd, coating has the shelf-life in itself, and storage temperature is not above 35 degrees Celsius;
3rd, road surface must be dried during scrawling, and meet water and solvent reduction reaction time and intensity, in order to avoid reduction paint adhesion;
4th, road should be cleaned, no floating dust, the debris such as greasy dirt.Coating should be sufficiently stirred for;
5th, after construction terminates, thoroughly cleaning machinery is answered;
6th, it should have been used after uncapping in 2 days;
7th, the special diluent for participating in reaction may can be used in thick, to obtain suitable spray viscosity in coating during low temperature
ACS-M 1-3% must not use other diluents to prevent coating surface from flocculating;
8th, inserts, repairing road surface dell or duck eye can suitably be used;
9th, diluent and curing agent and coating need to be placed on interior, can not be placed on it is outdoor it is outdoor be exposed to the sun, otherwise influence product quality;
4th, construction technology:
Construction technology is comprised the concrete steps that:
Datum mark, then carry out the construction line-putting first, implements to clean road surface, removes dust, silt and water and oil stain, spray bottom
Paint, 300 μm of thickness, drying time 24H sprays intermediate coat, 200 μm of thickness, drying time 15min, spray paint, the μ of thickness 200
M, drying time 72H, dry completion, adjustment maintenance, final acceptance of construction;
Condition needed for work progress:
1st, construct number 6-10 people, cleans road surface, line of fetching water, the 3-5 of falling coating people, stirring, driving, responsible equipment 3-5 people;
2nd, the road surface for needing to construct is protected, so that workmen cleans road surface;
3rd, dust, silt, moisture, the oil stain on road surface are thoroughly removed with sweeper, wire brush, sander;
4th, measured by design requirement, draw waterline, unwrapping wire positioning;
5th, in order to ensure construction quality of pavement, coating used must be using the product for reaching technical standard;
6th, priming paint, intermediate layer, finish paint must stir before;
7th, the mixed proportion of HSRoute Pox-Outdoor and the curing agent of POX 41 is 28:1, with original packing, 1 bag of curing agent
(0.85kg, 0.85kg/l)Add 1 barrel of coating(24kg, 1.57kg/l)In, it is sufficiently stirred for immediately after mixing;
8th, with Dutch schoonewil companies import equipment SBS mini spray-applied primers, 300 μm of drying time 24H of thickness, purpose
It is sealing ground and increase adhesive force;
9th, intermediate layer can use round brush roller coat, 200 μm of drying time 15min of thickness;
10th, finish paint is using the import equipment SBS mini sprayings of schoonewil companies of Holland, 200 μm of drying time 72H of thickness;
11st, this product can construct uses in pitch and cement surface.Surface should be dried, and be cleaned without floating dust and discrete particles, salt-free
And greasy dirt;Surface should have certain viscosity, old that coating should be removed, new pitch should time at least 8 weeks, in cement surface construction water
Muddy water content should be less than 4%;2 can be used:1 or 1:1 dilution, confining surface, the foaming phenomena for preventing the volatilization of cement steam from producing;
12nd, fresh concrete and the old concrete surface for having peeling need to use HSRoute primer systems before construction;It is real
Existing reliable adhesion between HSRoute indoor coatings and concrete surface is, it is necessary to 2 intermediate materials:Bottom in HSRoute rooms
Paint and HSRoute interfaces, and priming paint needs to be applied to two layers in HSRoute rooms.Drying time is in expression of drawing;
5th, spraying application equipment:
1st, intermediate layer is that cold paint can use spraying or roller coat, and finish paint is that schoonewil companies of Holland can be used to enter for two-component
Jaws equipment SBS mini equipment;Airless spraying, nozzle width need to be more than 0.021, and spray angle should be≤40 °, and machine need to contain 60 mesh
Screen pack.
A kind of operation principle of described drill school place construction Craft is to pass through the standard before the road surface spray coating of place
Standby work, the configuration of spraying equipment and the control of spraying process, reach that spraying is non-foaming, no when spraying is per coating during operation
Interruption;Prolonged wait is avoided in spraying process to cause that coating is dry and cracked, bubble, while also reducing Construction Cost.
Embodiment one
The minimum safe spacing of such vehicle is provided according to training object and country, with reference to actual conventional lane width design side
Slide field scrawles area.Such as dolly driver training, the small general width in track:3.5-3.75 rice, safe distance between vehicles regulation minimum 30
Rice.The minimum area of training place typically recommends 4 meters wide, 40 meters of length.In addition to entrance, side and Way out can set up on-slip
Band.Non-slip interior value imitates ice face, anti-skidding close to zero, and Anti-slip belt uses high anti-slip material.
First, preparative work before construction:
1st, the precondition of the cleaning on road surface, coating and road surface strong bonded is to maintain the clean of contact surface, dust on road surface,
Silt and moisture are the principal elements for hindering paint adhesion, can be thorough using broom, scrubbing brush, gas burner according to different situations
Remove;
2nd, setting-out, the position indicated by design and figure get waterline on road surface with measurement apparatus, after setting-out is complete, should check whether
Correctly;
3rd, the preparation of construction machinery, is sprayed, 5KW generators one using Dutch schoonewil companies import equipment SBS mini
Group, 5.5KW air compressor machines one, one group of agitator, hair-dryer one, one, light truck car, steel ruler, tape measure, screwdriver, pliers, steel
Wire brush, broom;
2nd, product technology parameter in constructing:
1st, adhesive:Acrylic compounds;
2nd, volatilizable thing content:43%(512KG/L);
3rd, viscosity:30-40 seconds;
4th, consumption:300µm=0.3L/m2≈0.47kg/m2;
5;Amount of solid content:About 54%;
3rd, execution conditions:
Temperature when the 1st, constructing cannot be below 10 degrees Celsius, and relative humidity is below 85%;
2nd, coating has the shelf-life in itself, and storage temperature is not above 35 degrees Celsius;
3rd, road surface must be dried during scrawling, and meet water and solvent reduction reaction time and intensity, in order to avoid reduction paint adhesion;
4th, road should be cleaned, no floating dust, the debris such as greasy dirt.Coating should be sufficiently stirred for;
5th, after construction terminates, thoroughly cleaning machinery is answered;
6th, it should have been used after uncapping in 2 days;
7th, the special diluent for participating in reaction may can be used in thick, to obtain suitable spray viscosity in coating during low temperature
ACS-M 1-3% must not use other diluents to prevent coating surface from flocculating;
8th, inserts, repairing road surface dell or duck eye can suitably be used;
9th, diluent and curing agent and coating need to be placed on interior, can not be placed on it is outdoor it is outdoor be exposed to the sun, otherwise influence product quality;
4th, construction technology:
Construction technology is comprised the concrete steps that:
Datum mark, then carry out the construction line-putting first, implements to clean road surface, removes dust, silt and water and oil stain, spray bottom
Paint, 300 μm of thickness, drying time 24H sprays intermediate coat, 200 μm of thickness, drying time 15min, spray paint, the μ of thickness 200
M, drying time 72H, dry completion, adjustment maintenance, final acceptance of construction;
Condition needed for work progress:
1st, construct number 6-10 people, cleans road surface, line of fetching water, the 3-5 of falling coating people, stirring, driving, responsible equipment 3-5 people;
2nd, the road surface for needing to construct is protected, so that workmen cleans road surface;
3rd, dust, silt, moisture, the oil stain on road surface are thoroughly removed with sweeper, wire brush, sander;
4th, measured by design requirement, draw waterline, unwrapping wire positioning;
5th, in order to ensure construction quality of pavement, coating used must be using the product for reaching technical standard;
6th, priming paint, intermediate layer, finish paint must stir before;
7th, the mixed proportion of HSRoute Pox-Outdoor and the curing agent of POX 41 is 28:1, with original packing, 1 bag of curing agent
(0.85kg, 0.85kg/l)Add 1 barrel of coating(24kg, 1.57kg/l)In, it is sufficiently stirred for immediately after mixing;
8th, with Dutch schoonewil companies import equipment SBS mini spray-applied primers, 300 μm of drying time 24H of thickness, purpose
It is sealing ground and increase adhesive force;
9th, intermediate layer can use round brush roller coat, 200 μm of drying time 15min of thickness;
10th, finish paint is using the import equipment SBS mini sprayings of schoonewil companies of Holland, 200 μm of drying time 72H of thickness;
11st, this product can construct uses in pitch and cement surface.Surface should be dried, and be cleaned without floating dust and discrete particles, salt-free
And greasy dirt;Surface should have certain viscosity, old that coating should be removed, new pitch should time at least 8 weeks, in cement surface construction water
Muddy water content should be less than 4%;2 can be used:1 or 1:1 dilution, confining surface, the foaming phenomena for preventing the volatilization of cement steam from producing;
12nd, fresh concrete and the old concrete surface for having peeling need to use HSRoute primer systems before construction;It is real
Existing reliable adhesion between HSRoute indoor coatings and concrete surface is, it is necessary to 2 intermediate materials:Bottom in HSRoute rooms
Paint and HSRoute interfaces, and priming paint needs to be applied to two layers in HSRoute rooms.Drying time is in expression of drawing;
5th, spraying application equipment:
1st, intermediate layer is that cold paint can use spraying or roller coat, and finish paint is that schoonewil companies of Holland can be used to enter for two-component
Jaws equipment SBS mini equipment;Airless spraying, nozzle width need to be more than 0.021, and spray angle should be≤40 °, and machine need to contain 60 mesh
Screen pack.
A kind of operation principle of described drill school place construction Craft is to pass through the standard before the road surface spray coating of place
Standby work, the configuration of spraying equipment and the control of spraying process, reach that spraying is non-foaming, no when spraying is per coating during operation
Interruption;Prolonged wait is avoided in spraying process to cause that coating is dry and cracked, bubble, while also reducing Construction Cost.
Embodiment two
The minimum safe spacing of such vehicle is provided according to training object and country, with reference to actual conventional lane width design side
Slide field scrawles area.Such as dolly driver training, the small general width in track:3.5-3.75 rice, safe distance between vehicles regulation minimum 30
Rice.The minimum area of training place typically recommends 5 meters wide, 50 meters of length.In addition to entrance, side and Way out can set up on-slip
Band.Non-slip interior value imitates ice face, anti-skidding close to zero, and Anti-slip belt uses high anti-slip material.
First, preparative work before construction:
1st, the precondition of the cleaning on road surface, coating and road surface strong bonded is to maintain the clean of contact surface, dust on road surface,
Silt and moisture are the principal elements for hindering paint adhesion, can be thorough using broom, scrubbing brush, gas burner according to different situations
Remove;
2nd, setting-out, the position indicated by design and figure get waterline on road surface with measurement apparatus, after setting-out is complete, should check whether
Correctly;
3rd, the preparation of construction machinery, is sprayed, 5KW generators one using Dutch schoonewil companies import equipment SBS mini
Group, 5.5KW air compressor machines one, one group of agitator, hair-dryer one, one, light truck car, steel ruler, tape measure, screwdriver, pliers, steel
Wire brush, broom;
2nd, product technology parameter in constructing:
1st, adhesive:Acrylic compounds;
2nd, volatilizable thing content:43%(512KG/L);
3rd, viscosity:30-40 seconds;
4th, consumption:300µm=0.3L/m2≈0.47kg/m2;
5;Amount of solid content:About 54%;
3rd, execution conditions:
Temperature when the 1st, constructing cannot be below 10 degrees Celsius, and relative humidity is below 85%;
2nd, coating has the shelf-life in itself, and storage temperature is not above 35 degrees Celsius;
3rd, road surface must be dried during scrawling, and meet water and solvent reduction reaction time and intensity, in order to avoid reduction paint adhesion;
4th, road should be cleaned, no floating dust, the debris such as greasy dirt.Coating should be sufficiently stirred for;
5th, after construction terminates, thoroughly cleaning machinery is answered;
6th, it should have been used after uncapping in 2 days;
7th, the special diluent for participating in reaction may can be used in thick, to obtain suitable spray viscosity in coating during low temperature
ACS-M 1-3% must not use other diluents to prevent coating surface from flocculating;
8th, inserts, repairing road surface dell or duck eye can suitably be used;
9th, diluent and curing agent and coating need to be placed on interior, can not be placed on it is outdoor it is outdoor be exposed to the sun, otherwise influence product quality;
4th, construction technology:
Construction technology is comprised the concrete steps that:
Datum mark, then carry out the construction line-putting first, implements to clean road surface, removes dust, silt and water and oil stain, spray bottom
Paint, 300 μm of thickness, drying time 24H sprays intermediate coat, 200 μm of thickness, drying time 15min, spray paint, the μ of thickness 200
M, drying time 72H, dry completion, adjustment maintenance, final acceptance of construction;
Condition needed for work progress:
1st, construct number 6-10 people, cleans road surface, line of fetching water, the 3-5 of falling coating people, stirring, driving, responsible equipment 3-5 people;
2nd, the road surface for needing to construct is protected, so that workmen cleans road surface;
3rd, dust, silt, moisture, the oil stain on road surface are thoroughly removed with sweeper, wire brush, sander;
4th, measured by design requirement, draw waterline, unwrapping wire positioning;
5th, in order to ensure construction quality of pavement, coating used must be using the product for reaching technical standard;
6th, priming paint, intermediate layer, finish paint must stir before;
7th, the mixed proportion of HSRoute Pox-Outdoor and the curing agent of POX 41 is 28:1, with original packing, 1 bag of curing agent
(0.85kg, 0.85kg/l)Add 1 barrel of coating(24kg, 1.57kg/l)In, it is sufficiently stirred for immediately after mixing;
8th, with Dutch schoonewil companies import equipment SBS mini spray-applied primers, 300 μm of drying time 24H of thickness, purpose
It is sealing ground and increase adhesive force;
9th, intermediate layer can use round brush roller coat, 200 μm of drying time 15min of thickness;
10th, finish paint is using the import equipment SBS mini sprayings of schoonewil companies of Holland, 200 μm of drying time 72H of thickness;
11st, this product can construct uses in pitch and cement surface.Surface should be dried, and be cleaned without floating dust and discrete particles, salt-free
And greasy dirt;Surface should have certain viscosity, old that coating should be removed, new pitch should time at least 8 weeks, in cement surface construction water
Muddy water content should be less than 4%;2 can be used:1 or 1:1 dilution, confining surface, the foaming phenomena for preventing the volatilization of cement steam from producing;
12nd, fresh concrete and the old concrete surface for having peeling need to use HSRoute primer systems before construction;It is real
Existing reliable adhesion between HSRoute indoor coatings and concrete surface is, it is necessary to 2 intermediate materials:Bottom in HSRoute rooms
Paint and HSRoute interfaces, and priming paint needs to be applied to two layers in HSRoute rooms.Drying time is in expression of drawing;
5th, spraying application equipment:
1st, intermediate layer is that cold paint can use spraying or roller coat, and finish paint is that schoonewil companies of Holland can be used to enter for two-component
Jaws equipment SBS mini equipment;Airless spraying, nozzle width need to be more than 0.021, and spray angle should be≤40 °, and machine need to contain 60 mesh
Screen pack.
A kind of operation principle of described drill school place construction Craft is to pass through the standard before the road surface spray coating of place
Standby work, the configuration of spraying equipment and the control of spraying process, reach that spraying is non-foaming, no when spraying is per coating during operation
Interruption;Prolonged wait is avoided in spraying process to cause that coating is dry and cracked, bubble, while also reducing Construction Cost.
Claims (2)
1. a kind of drill school place construction Craft, it is characterised in that:A kind of described drill school place pavement construction
Technique is comprised the concrete steps that:
Preparative work before construction:
1st, the precondition of the cleaning on road surface, coating and road surface strong bonded is to maintain the clean of contact surface, dust on road surface,
Silt and moisture are the principal elements for hindering paint adhesion, can be thorough using broom, scrubbing brush, gas burner according to different situations
Remove;
2nd, setting-out, the position indicated by design and figure get waterline on road surface with measurement apparatus, after setting-out is complete, should check whether
Correctly;
3rd, the preparation of construction machinery, is sprayed, 5KW generators one using Dutch schoonewil companies import equipment SBS mini
Group, 5.5KW air compressor machines one, one group of agitator, hair-dryer one, one, light truck car, steel ruler, tape measure, screwdriver, pliers, steel
Wire brush, broom;
2nd, product technology parameter in constructing:
1st, adhesive:Acrylic compounds;
2nd, volatilizable thing content:43%(512KG/L);
3rd, viscosity:30-40 seconds;
4th, consumption:300µm=0.3L/m2≈0.47kg/ m2;
5;Amount of solid content:About 54%;
3rd, execution conditions:
Temperature when the 1st, constructing cannot be below 10 degrees Celsius, and relative humidity is below 85%;
2nd, coating has the shelf-life in itself, and storage temperature is not above 35 degrees Celsius;
3rd, road surface must be dried during scrawling, and meet water and solvent reduction reaction time and intensity, in order to avoid reduction paint adhesion;
4th, road should be cleaned, no floating dust, the debris such as greasy dirt;
Coating should be sufficiently stirred for;
5th, after construction terminates, thoroughly cleaning machinery is answered;
6th, it should have been used after uncapping in 2 days;
7th, the special diluent for participating in reaction may can be used in thick, to obtain suitable spray viscosity in coating during low temperature
ACS-M 1-3% must not use other diluents to prevent coating surface from flocculating;
8th, inserts, repairing road surface dell or duck eye can suitably be used;
9th, diluent and curing agent and coating need to be placed on interior, can not be placed on it is outdoor it is outdoor be exposed to the sun, otherwise influence product quality;
4th, construction technology:
Construction technology is comprised the concrete steps that:
Datum mark, then carry out the construction line-putting first, implements to clean road surface, removes dust, silt and water and oil stain, spray bottom
Paint, 300 μm of thickness, drying time 24H sprays intermediate coat, 200 μm of thickness, drying time 15min, spray paint, the μ of thickness 200
M, drying time 72H, dry completion, adjustment maintenance, final acceptance of construction;
Condition needed for work progress:
1st, construct number 6-10 people, cleans road surface, line of fetching water, the 3-5 of falling coating people, stirring, driving, responsible equipment 3-5 people;
2nd, the road surface for needing to construct is protected, so that workmen cleans road surface;
3rd, dust, silt, moisture, the oil stain on road surface are thoroughly removed with sweeper, wire brush, sander;
4th, measured by design requirement, draw waterline, unwrapping wire positioning;
5th, in order to ensure construction quality of pavement, coating used must be using the product for reaching technical standard;
6th, priming paint, intermediate layer, finish paint must stir before;
7th, the mixed proportion of HSRoute Pox-Outdoor and the curing agent of POX 41 is 28:1, with original packing, 1 bag of curing agent
(0.85kg, 0.85kg/l)Add 1 barrel of coating(24kg, 1.57kg/l)In, it is sufficiently stirred for immediately after mixing;
8th, with Dutch schoonewil companies import equipment SBS mini spray-applied primers, 300 μm of drying time 24H of thickness, purpose
It is sealing ground and increase adhesive force;
9th, intermediate layer can use round brush roller coat, 200 μm of drying time 15min of thickness;
10th, finish paint is using the import equipment SBS mini sprayings of schoonewil companies of Holland, 200 μm of drying time 72H of thickness;
11st, this product can construct uses in pitch and cement surface;
Surface should be dried, and be cleaned without floating dust and discrete particles, salt-free and greasy dirt;Surface should have certain viscosity, old that coating should
Remove, new pitch should time at least 8 weeks, constructing cement water content in cement surface should be less than 4%;2 can be used:1 or 1:1 dilution, envelope
Surface is closed, the foaming phenomena for preventing the volatilization of cement steam from producing;
12nd, fresh concrete and the old concrete surface for having peeling need to use HSRoute primer systems before construction;It is real
Existing reliable adhesion between HSRoute indoor coatings and concrete surface is, it is necessary to 2 intermediate materials:Bottom in HSRoute rooms
Paint and HSRoute interfaces, and priming paint needs to be applied to two layers in HSRoute rooms;
Drying time is in expression of drawing;
5th, spraying application equipment:
1st, intermediate layer is that cold paint can use spraying or roller coat, and finish paint is that schoonewil companies of Holland can be used to enter for two-component
Jaws equipment SBS mini equipment;Airless spraying, nozzle width need to be more than 0.021, and spray angle should be≤40 °, and machine need to contain 60 mesh
Screen pack.
2. a kind of drill school place construction Craft according to claim 1, it is characterised in that:A kind of described instruction
To practice the operation principle of school ground construction Craft be, is matched somebody with somebody by the preparation before the road surface spray coating of place, spraying equipment
The control with spraying process is put, reaches that spraying is non-foaming, uninterrupted during operation when spraying is per coating;Avoid in spraying process
In prolonged wait cause that coating is dry and cracked, bubble, while also reducing Construction Cost.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710463185.3A CN107151959A (en) | 2017-06-19 | 2017-06-19 | A kind of drill school place construction Craft |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710463185.3A CN107151959A (en) | 2017-06-19 | 2017-06-19 | A kind of drill school place construction Craft |
Publications (1)
Publication Number | Publication Date |
---|---|
CN107151959A true CN107151959A (en) | 2017-09-12 |
Family
ID=59794935
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201710463185.3A Withdrawn CN107151959A (en) | 2017-06-19 | 2017-06-19 | A kind of drill school place construction Craft |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN107151959A (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN112924656A (en) * | 2021-03-17 | 2021-06-08 | 哈尔滨工业大学 | Temperature-adjustable and pressure-adjustable foam light soil bubble attenuation testing device and method |
CN113399171A (en) * | 2020-03-17 | 2021-09-17 | 广东博智林机器人有限公司 | Dynamic mixed painting device and working method thereof, and painting robot |
Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103469712A (en) * | 2013-09-30 | 2013-12-25 | 济南城建集团有限公司 | Method for paving anti-rut anti-skid pavement coating |
CN103669152A (en) * | 2013-11-04 | 2014-03-26 | 沈阳市政集团有限公司 | Road surface construction method of ultrathin stone mastic asphalt mixture |
CN104747204A (en) * | 2015-01-20 | 2015-07-01 | 广东省建筑工程集团有限公司 | Construction technology for foundation slab sliding layer of super-long tunnel |
CN205711601U (en) * | 2016-03-18 | 2016-11-23 | 广州昇美材料科技有限公司 | A kind of super viscous wearing course paving structure of cement pavement enhancement mode |
-
2017
- 2017-06-19 CN CN201710463185.3A patent/CN107151959A/en not_active Withdrawn
Patent Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103469712A (en) * | 2013-09-30 | 2013-12-25 | 济南城建集团有限公司 | Method for paving anti-rut anti-skid pavement coating |
CN103669152A (en) * | 2013-11-04 | 2014-03-26 | 沈阳市政集团有限公司 | Road surface construction method of ultrathin stone mastic asphalt mixture |
CN104747204A (en) * | 2015-01-20 | 2015-07-01 | 广东省建筑工程集团有限公司 | Construction technology for foundation slab sliding layer of super-long tunnel |
CN205711601U (en) * | 2016-03-18 | 2016-11-23 | 广州昇美材料科技有限公司 | A kind of super viscous wearing course paving structure of cement pavement enhancement mode |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN113399171A (en) * | 2020-03-17 | 2021-09-17 | 广东博智林机器人有限公司 | Dynamic mixed painting device and working method thereof, and painting robot |
CN112924656A (en) * | 2021-03-17 | 2021-06-08 | 哈尔滨工业大学 | Temperature-adjustable and pressure-adjustable foam light soil bubble attenuation testing device and method |
CN112924656B (en) * | 2021-03-17 | 2022-11-18 | 哈尔滨工业大学 | Temperature-adjustable and pressure-adjustable foam light soil bubble attenuation testing device and method |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
AU714356B2 (en) | Peelable floor coating systems | |
CN110735371B (en) | Weather-resistant colored resin cover and preparation method thereof | |
KR101177349B1 (en) | Paint composition concrete | |
CN107442369A (en) | Oil paint coating construction method under hot and humid environment | |
CN107151959A (en) | A kind of drill school place construction Craft | |
AU783067B2 (en) | A method of improving the drying time of a thick coating | |
CN107090231A (en) | A kind of application of imitative ice and snow road in driving school trains | |
CN104131551A (en) | Anticorrosion coating of precast pile foundation for silt soil complicated geology and method | |
CN112029395A (en) | Stain-resistant reflective coating and use method thereof | |
US8197593B2 (en) | Low-temperature cure inorganic compositions | |
KR200423508Y1 (en) | A Road Layer of Skid Prevent and a Spread Unit | |
CN105598011A (en) | Method for rapidly repairing defect on outer surface of automobile through weathered stone | |
KR200420495Y1 (en) | A Sliding Keeping Unit Using Vehicles | |
CN204185846U (en) | The prefabricated pile foundation of a kind of mud soil property complicated geological | |
KR101524202B1 (en) | Construction method, and architectural clear epoxy pavement materials having the same | |
JP3794773B2 (en) | Pattern transfer method for roads and floors | |
Maasberg et al. | Application Core Curriculum: 1,000–55,000 psi | |
StreetBond et al. | D. StreetBond® QS Concrete Primer or StreetBond® WB Concrete Primer are the only | |
JP3796579B2 (en) | Weather-resistant steel coating composition and coating method | |
Marrion et al. | Application and applications | |
Antolik | NEWS FROM THE TRACKER | |
CN107936717A (en) | A kind of aqueous anticorrosion paint for overpass | |
Brownstein | Inorganic polymer fiber composites for protection of structures | |
Fraser | Painting of Railroad Bridges and Structures | |
KR20230084708A (en) | Abrasion resistance flooring construction method for concrete and, flooring to be constructed thereby |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
WW01 | Invention patent application withdrawn after publication | ||
WW01 | Invention patent application withdrawn after publication |
Application publication date: 20170912 |