CN107143335A - 超深竖井的导孔施工方法 - Google Patents

超深竖井的导孔施工方法 Download PDF

Info

Publication number
CN107143335A
CN107143335A CN201710450332.3A CN201710450332A CN107143335A CN 107143335 A CN107143335 A CN 107143335A CN 201710450332 A CN201710450332 A CN 201710450332A CN 107143335 A CN107143335 A CN 107143335A
Authority
CN
China
Prior art keywords
drilling
directional
drill
bha
hole
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201710450332.3A
Other languages
English (en)
Inventor
刘传虎
王海涛
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Ge Zhou Ba Group Is Second Project Co Ltd
China Gezhouba Group No 2 Engineering Co Ltd
Original Assignee
China Ge Zhou Ba Group Is Second Project Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Ge Zhou Ba Group Is Second Project Co Ltd filed Critical China Ge Zhou Ba Group Is Second Project Co Ltd
Priority to CN201710450332.3A priority Critical patent/CN107143335A/zh
Publication of CN107143335A publication Critical patent/CN107143335A/zh
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D1/00Sinking shafts
    • E21D1/03Sinking shafts mechanically, e.g. by loading shovels or loading buckets, scraping devices, conveying screws
    • E21D1/06Sinking shafts mechanically, e.g. by loading shovels or loading buckets, scraping devices, conveying screws with shaft-boring cutters
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21BEARTH OR ROCK DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
    • E21B10/00Drill bits
    • E21B10/26Drill bits with leading portion, i.e. drill bits with a pilot cutter; Drill bits for enlarging the borehole, e.g. reamers
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21BEARTH OR ROCK DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
    • E21B47/00Survey of boreholes or wells
    • E21B47/02Determining slope or direction
    • E21B47/022Determining slope or direction of the borehole, e.g. using geomagnetism
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21BEARTH OR ROCK DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
    • E21B7/00Special methods or apparatus for drilling
    • E21B7/04Directional drilling
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21BEARTH OR ROCK DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
    • E21B7/00Special methods or apparatus for drilling
    • E21B7/04Directional drilling
    • E21B7/10Correction of deflected boreholes
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21BEARTH OR ROCK DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
    • E21B7/00Special methods or apparatus for drilling
    • E21B7/28Enlarging drilled holes, e.g. by counterboring
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D3/00Raising shafts, i.e. working upwards from the bottom

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Geology (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Physics & Mathematics (AREA)
  • Environmental & Geological Engineering (AREA)
  • Fluid Mechanics (AREA)
  • Mechanical Engineering (AREA)
  • Geophysics (AREA)
  • Earth Drilling (AREA)

Abstract

本发明超深竖井的导孔施工方法,包括:(1)施工准备;(2)定向钻机安装就位;(3)开孔钻具组合钻进;(4)正常钻具组合钻进:(5)测斜钻具组合钻进:(6)定向钻具组合钻进:(7)正常钻具组合钻进:(8)定向钻机拆除:(9)反井钻机安装就位。本明发施工方法能加快施工进度,提高施工精度,降低施工成本、安全、精确、快速。

Description

超深竖井的导孔施工方法
技术领域:
本发明涉及一种特别适用于水利、水电、建筑、矿山等露天超深竖井成孔施工的超深(300m以上)竖井的导孔施工方法,
背景技术:
在常规的竖井导孔施工中,反井钻机具有工作效率高、成型质量好、劳动强度低、安全风险小等优点,越来越多的被应用于水电工程竖井施工中。但是在高深竖井施工中,由于设备自身性能、操作手操作经验以及地质条件等因素的影响,反井钻机导孔施工精度难以满足要求,往往会产生较大的偏差,进而导致后期竖井施工困难,造成大量的超挖超填,甚至造成废井等,浪费了大量的施工工期和成本。
发明内容:
本发明的目的是为了克服反井钻机在超深竖井导孔施工中精度不高,偏斜较大的缺点,提供一种能加快施工进度,提高施工精度,降低施工成本的安全、精确、快速的超深竖井的施工方法。
本发明的目的是这样来实现的:
本发明超深竖井的导孔施工方法,包括以下步骤:
(1)施工准备;
(2)定向钻机安装就位;
(3)开孔钻具组合钻进;
在砼基础上预留环形孔槽,并将钻机进行认真找正,使钻孔中心、井口中心和动力头主轴中心重合,确保开孔垂直度,定向孔前20m采用开孔钻具组合进行钻进;
(4)正常钻具组合钻进:
定向孔20~50m采用正常钻进钻具组合进行钻进;
(5)测斜钻具组合钻进:
定向孔50m以上采用测斜钻具组合进行钻进,每9~11m进行1次测斜,测斜时保证钻机和钻杆处于静止状;
(6)定向钻具组合钻进:
根据定向孔钻进过程中随钻测斜仪得测出的顶角大小判断出的偏斜程度,通过方位角判断出偏斜的位置,一旦定向孔出现较大偏斜(30cm以上),应停止钻进,确定偏斜量和偏斜方位后更换定向钻具组合进行纠偏,纠偏完成后,采用定向钻具组合进行钻进,钻压、钻速和泵量同正常钻具组合;
(7)正常钻具组合钻进:
定向孔钻进至最后剩余9~11m时,更换正常钻进钻具组合,以防止在透孔时损坏测斜仪、钻铤;
(8)定向钻机拆除:
定向孔顺利贯通、满足精度要求后,将钻具全部提出向定孔外,将定向钻机拆除;
(9)反井钻机安装就位;
反井钻机及其辅助设备采用汽车吊配合人工安装,对反井钻机基础及设置井钻机扩孔,扩孔采用特制的钻头,防止扩孔过程中发生偏斜。
上述的定向钻具组合钻进时,定向钻具组合采用∅190mm牙轮钻头+∅165mm螺杆钻头+∅159mm无磁钻铤+ NC46悬挂短节+∅89mm高强度钻杆+∅73mm高强度钻杆,定向孔纠偏过程中钻压以控制工具面角为主,钻速为0r~10r/min,泵量为990 L/min,缸套∅140mm。
上述的开孔钻具组合钻进时,定向孔前20m采用开孔钻具组合进行钻进,钻具采用∅190mm牙轮钻头+∅159mm无磁钻铤+∅73mm短钻杆,钻进钻压为0.3~0.5 t,钻速为30~40r/min,泵量为990 L/min,缸套∅140mm。
上述的正常钻具组合钻进时,钻具采用∅190mm牙轮钻头+∅159mm无磁钻铤+∅89mm高强度钻杆+∅73mm高强度钻杆,钻进钻压为1.5~3.5 t,表土、风化岩段钻速为70~80 r/min,下部硬岩段钻速为50~60 r/min,泵量为990 L/min、缸套∅140mm,无磁钻铤为2根~4根。
上述的测斜钻具组合钻进步骤时:测斜钻具组合采用∅190mm牙轮钻头+∅159mm无磁钻铤+NC46悬挂短节+∅89mm高强度钻杆+∅73mm高强度钻杆,钻压、钻速和泵量与正常钻具组合钻进时相同。
本发明方法采用定向钻机具有随钻测斜、自动纠偏的功能。根据测斜仪测出的顶角大小可以判断出偏斜程度,通过方位角可以判断出偏斜的位置,确定了偏斜量和偏斜方位之后,施钻人员将更换定向钻具组合,主机发动机停止提供扭力,仅通过泥浆压力带动弯螺杆底部的泥浆马达旋转,带动牙轮钻头破岩,当钻孔被纠正至正常孔位时,恢复正常钻进模式进行钻进。
与传统单一反井钻机成孔相比超深竖井的导孔施工方法具有如下效果:
(1)采用定向钻机结合反井钻机进行高深竖井导孔的施工,可以有效的防止竖井偏斜,保证钻孔精度,实现竖井导孔一次性贯通成功;
(2)在反井钻机扩孔过程中采用特制的扩孔钻头,可以有效的防止反井钻机在扩孔过程中可能出现的偏斜问题;
(3)采用定向钻机结合反井钻机进行高深竖井导孔施工,可以降低由于竖井导孔偏斜导致的后期导井、全断面扩挖造成的施工工期延长、施工成本增加等问题;
(4)采用定向钻机结合反井钻机进行高深竖井施工,在一定程度上降低了对反井钻机性能的要求。
附图说明:
图1为定向钻机现场布置图。
图2为开孔钻具组合示意图。
图3为正常钻具组合示意图。
图4为测斜钻具组合示意图。
图5为定向钻进钻具组合示意图。
具体实施方式:
图1为定向钻机现场布置图。包括1#泥浆池1、2#泥浆池2、沉淀池3、钻杆堆放区4、钻孔中心5、钻机6、钻机后撤区域7。
参见图1~图5,本实施例超深竖井的导孔施工方法,包括以下步骤:
(1)施工准备:
施工准备包括供排水、供电、场地平整、定向钻机和反井钻机基础、循环水池、电气设备安装等工作内容;
施工前还必须完成钻井泥浆制备,并使泥浆充分循环;
(2)定向钻机安装就位:
定向钻机井架在井口附***台拼装,采用25t和50t汽车吊整体吊装,然后再进行钻机及辅助设备安装;
(3)开孔钻具组合钻进:
在砼基础上预留环形孔槽,并将钻机进行认真找正,使钻孔中心、井口中心和动力头主轴中心重合,确保开孔垂直度。定向孔前20m采用开孔钻具组合进行钻进。钻具采用∅190mm牙轮钻头8+∅159mm无磁钻铤9+∅73mm短钻杆10(2m)(参见图2)。钻进钻压为0.3~0.5 t,钻速为30~40r/min,泵量为990 L/min(∅140mm缸套);
(4)正常钻具组合钻进:
定向孔20~50m采用正常钻进钻具组合进行钻进,钻具采用∅190mm牙轮钻头8+∅159mm无磁钻铤9(2根~4根)+∅89mm高强度钻杆11+∅73mm高强度钻杆10(参见图3)。钻进钻压为1.5~3.5 t,表土、风化岩段钻速为70~80 r/min,下部硬岩段钻速为50~60 r/min,泵量为990 L/min(∅140mm缸套);
(5)测斜钻具组合钻进:
定向孔50m以后采用测斜钻具组合进行钻进,每10m进行1次测斜(30cm以上),测斜时保证钻机和钻杆处于静止状态。测斜钻具组合采用∅190mm牙轮钻头8+∅159mm无磁钻铤9+NC46悬挂短节12+∅89mm高强度钻杆11+∅73mm高强度钻杆10(参见图4)。钻压、钻速和泵量与正常钻具组合钻进时相同;
(6)定向钻具组合钻进:
根据定向孔钻进过程中随钻测斜仪得出的偏斜结果,一旦定向孔出现较大偏斜,应停止钻进,更换定向钻具组合进行纠偏。定向钻具组合采用∅190mm牙轮钻头8+∅165mm螺杆钻头13+∅159mm无磁钻铤9+ NC46悬挂短节12+∅89mm高强度钻杆11+∅73mm高强度钻杆10(参见图5)。定向孔纠偏过程中钻压以控制工具面角为主,钻速为0r~10r/min,泵量为990 L/min(∅140mm缸套),纠偏完成后,为节约更换钻具的时间,采用定向钻具组合进行钻进,钻压、钻速和泵量同正常钻具组合;
(7)正常钻具组合钻进:
定向孔钻进至最后剩余10m左右时,更换正常钻进钻具组合,以防止在透孔时损坏测斜仪、钻铤等;
(8)定向钻机拆除:
定向孔顺利贯通、满足精度要求后,将钻具全部提出孔外,采用50t汽车吊将定向钻机拆除;
(9)反井钻机安装就位:
反井钻机及其辅助设备采用50t汽车吊配合人工安装。测量队对反井钻机基础及设备安装进行测量校核。使用地脚螺栓对反井钻机底部横梁进行加固,以防止钻进过程中反井钻机可能发生的移位现象;
(10)扩孔:
正常扩孔条件下,反井钻机采用Ⅰ型扩孔钻头。当出现定向孔堵塞情况时,需要更换Ⅱ型扩孔钻头,采用循环水返渣的形式进行扩孔;
扩孔完成后,安装反拉钻头进行后续竖井导井施工。
本申请人曾在某水电站电缆竖井深度为374.32m,直径7.3m进行试验。竖井所在区域上部50m为第四纪坡积物,以下为石英片岩、云母片岩,岩层倾角为65~80°左右,并发育有多组节理裂隙,地下水丰富,钻孔过程中极易出现偏斜,成孔条件差。
为解决电缆井工期紧,地质条件复杂,成孔条件差的难题,采用定向钻机和反井钻机组合的形式进行电缆井导孔施工。首先, 采用定向钻机进行∅190mm的定向孔施工,然后采用BMC400型反井钻机通过特制的扩孔钻头,将∅190mm的定向孔扩大为∅270mm的导孔。 采用定向钻机进行定向孔施工,定向孔顺利贯通,平均钻孔强度为22m/d;采用反井钻机进行定向孔扩孔施工,扩孔施工顺利完成,平均扩孔强度为23.4m/d。
采用定向钻和反井钻机组合进行电缆井导孔施工,总施工工期为33天,平均施工强度为11.34m/d。采用反井钻机直接进行导孔施工,平均施工强度为7m/d,完成电缆井导孔施工约需工期53天。为电缆竖井导孔施工节约了20天时间。采用本方法最终形成的导孔累计偏斜量为1.21m,钻孔精度为0.32%。远小于反井钻机钻孔1%的精度要求。
上述实施例是对本发明的上述内容作进一步说明,但不应将此理解为本发明上述主题的范围仅限于上述实施例。凡基于上述内容所实现的技术均属于本发明的保护范围。

Claims (5)

1.超深竖井的导孔施工方法,包括以下步骤:
(1)施工准备;
(2)定向钻机安装就位;
(3)开孔钻具组合钻进;
在砼基础上预留环形孔槽,并将钻机进行认真找正,使钻孔中心、井口中心和动力头主轴中心重合,确保开孔垂直度,定向孔前20m采用开孔钻具组合进行钻进;
(4)正常钻具组合钻进:
定向孔20~50m采用正常钻进钻具组合进行钻进;
(5)测斜钻具组合钻进:
定向孔50m以上采用测斜钻具组合进行钻进,每9~11m进行1次测斜,测斜时保证钻机和钻杆处于静止状;
(6)定向钻具组合钻进:
根据定向孔钻进过程中随钻测斜仪得测出的顶角大小判断出的偏斜程度,通过方位角判断出偏斜的位置,一旦定向孔出现较大偏斜,应停止钻进,确定偏斜量和偏斜方位后更换定向钻具组合进行纠偏,纠偏完成后,采用定向钻具组合进行钻进,钻压、钻速和泵量同正常钻具组合;
(7)正常钻具组合钻进:
定向孔钻进至最后剩余9~11m时,更换正常钻进钻具组合,以防止在透孔时损坏测斜仪、钻铤;
(8)定向钻机拆除:
定向孔顺利贯通、满足精度要求后,将钻具全部提出向定孔外,将定向钻机拆除;
(9)反井钻机安装就位;
反井钻机及其辅助设备采用汽车吊配合人工安装,对反井钻机基础及设置井钻机扩孔,扩孔采用特制的钻头,防止扩孔过程中发生偏斜。
2.如权利要求1所述的超深竖井的导孔施工方法 ,其特征在于定向钻具组合钻进时,定向钻具组合采用∅190mm牙轮钻头+∅165mm螺杆钻头+∅159mm无磁钻铤+ NC46悬挂短节+∅89mm高强度钻杆+∅73mm高强度钻杆,定向孔纠偏过程中钻压以控制工具面角为主,钻速为0~10 r/min,泵量为990 L/min,缸套∅140mm。
3.如权利要求1或2所述的超深竖井的导孔施工方法,其特征在于开孔钻具组合钻进时,定向孔前20m采用开孔钻具组合进行钻进,钻具采用∅190mm牙轮钻头+∅159mm无磁钻铤+∅73mm短钻杆,钻进钻压为0.3~0.5 t,钻速为30~40r/min,泵量为990 L/min,缸套∅140mm。
4.如权利要求1或2所述的超深竖井的导孔施工方法,其特征在于正常钻具组合钻进时,钻具采用∅190mm牙轮钻头+∅159mm无磁钻铤+∅89mm高强度钻杆+∅73mm高强度钻杆,钻进钻压为1.5~3.5 t,表土、风化岩段钻速为70~80 r/min,下部硬岩段钻速为50~60 r/min,泵量为990 L/min、缸套∅140mm,无磁钻铤为2根~4根。
5.如权利要求1或2所述的超深竖井的导孔施工方法,其特征在于测斜钻具组合钻进步骤测斜钻具组合采用∅190mm牙轮钻头+∅159mm无磁钻铤+NC46悬挂短节+∅89mm高强度钻杆+∅73mm高强度钻杆,钻压、钻速和泵量与正常钻具组合钻进时相同。
CN201710450332.3A 2017-06-15 2017-06-15 超深竖井的导孔施工方法 Pending CN107143335A (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710450332.3A CN107143335A (zh) 2017-06-15 2017-06-15 超深竖井的导孔施工方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710450332.3A CN107143335A (zh) 2017-06-15 2017-06-15 超深竖井的导孔施工方法

Publications (1)

Publication Number Publication Date
CN107143335A true CN107143335A (zh) 2017-09-08

Family

ID=59782427

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710450332.3A Pending CN107143335A (zh) 2017-06-15 2017-06-15 超深竖井的导孔施工方法

Country Status (1)

Country Link
CN (1) CN107143335A (zh)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111441718A (zh) * 2020-04-10 2020-07-24 中国水利水电第一工程局有限公司 大断面陡坡长斜井高精度导井开挖施工方法、***及应用
CN113445916A (zh) * 2021-08-11 2021-09-28 中冀建勘集团有限公司 一种用于小直径深井基岩段扫孔纠偏的施工方法

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201110127Y (zh) * 2007-12-18 2008-09-03 上海中曼石油天然气集团有限公司 适用于快速钻井的钻具组合
CN201386509Y (zh) * 2009-04-30 2010-01-20 中国石油集团川庆钻探工程有限公司钻采工艺技术研究院 用于接力传输随钻测量装置的钻具组合
CN104847263A (zh) * 2015-04-30 2015-08-19 中煤科工集团西安研究院有限公司 煤层气远端对接水平井钻井方法
CN105888549A (zh) * 2015-06-26 2016-08-24 山东科技大学 一种千米深l型地面预注浆钻孔用钻具组合及钻孔工艺

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201110127Y (zh) * 2007-12-18 2008-09-03 上海中曼石油天然气集团有限公司 适用于快速钻井的钻具组合
CN201386509Y (zh) * 2009-04-30 2010-01-20 中国石油集团川庆钻探工程有限公司钻采工艺技术研究院 用于接力传输随钻测量装置的钻具组合
CN104847263A (zh) * 2015-04-30 2015-08-19 中煤科工集团西安研究院有限公司 煤层气远端对接水平井钻井方法
CN105888549A (zh) * 2015-06-26 2016-08-24 山东科技大学 一种千米深l型地面预注浆钻孔用钻具组合及钻孔工艺

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
王彬彬: "深竖井反井法先导孔快速施工技术研究", 《铁道建筑技术》 *

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111441718A (zh) * 2020-04-10 2020-07-24 中国水利水电第一工程局有限公司 大断面陡坡长斜井高精度导井开挖施工方法、***及应用
CN113445916A (zh) * 2021-08-11 2021-09-28 中冀建勘集团有限公司 一种用于小直径深井基岩段扫孔纠偏的施工方法

Similar Documents

Publication Publication Date Title
CN105888551B (zh) 反井法一次钻成长斜井凿井工艺
CN110778272B (zh) 大管径热网管道非开挖方式敷设施工方法
CN110409461A (zh) 一种基于装配式大直径管桩的基坑支护施工方法
CN103643918B (zh) 一种针对奥陶系灰岩矿区的寻找及防止矿井渗水的方法
CN103835661B (zh) 一种局部开挖预支护反井钻井工艺
CN109098661B (zh) 水电站河谷的双向成对跨江大顶角斜孔钻探方法
CN104295239A (zh) 一种旋挖钻机硬岩地层成孔的方法
CN104832119A (zh) 开窗侧钻短半径水平井及反循环固井堵水方法
CN101818644A (zh) 矿山竖井井筒一钻成井钻井法凿井工艺
CN105064336A (zh) 一种三段式扩底桩的成孔施工方法
CN109024719B (zh) 一种桩侧扰动降阻建筑物纠倾法
CN103266603A (zh) 一种预应力混凝土异形桩预钻成孔扩底注浆施工工法
CN102562087B (zh) 水钻跟进管棚施工方法
CN103134236A (zh) 一种地源热泵地下换热器倾斜埋设的施工方法
CN208024341U (zh) 一种旋挖桩***
CN110700293B (zh) 深水斜岩环境下旋挖引孔钢板桩围堰施工方法
CN110984132B (zh) 复杂地质条件下地下连续墙成槽的施工方法
CN107143335A (zh) 超深竖井的导孔施工方法
CN104453705A (zh) 大孔径灌注桩旋挖钻机二次成孔方法
CN112360468B (zh) 竖井溜渣井开挖支护方法
CN204401612U (zh) 一种超大直径全钢护筒干作业成孔灌注桩施工装置
CN110241731A (zh) 一种在海底内形成嵌岩桩基础的方法
CN103643674B (zh) 卵石层砂岩地质条件下的立柱桩施工方法
CN205605114U (zh) 一种喀斯特岩溶地区预应力锚索钻孔装置
CN112815144A (zh) 人工顶管施工工艺

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20170908

WD01 Invention patent application deemed withdrawn after publication