CN107130603A - It is a kind of to refute the construction method that assembling boom pours concrete waterborne using idle side - Google Patents

It is a kind of to refute the construction method that assembling boom pours concrete waterborne using idle side Download PDF

Info

Publication number
CN107130603A
CN107130603A CN201710524953.1A CN201710524953A CN107130603A CN 107130603 A CN107130603 A CN 107130603A CN 201710524953 A CN201710524953 A CN 201710524953A CN 107130603 A CN107130603 A CN 107130603A
Authority
CN
China
Prior art keywords
concrete
boom
column
waterborne
construction
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201710524953.1A
Other languages
Chinese (zh)
Other versions
CN107130603B (en
Inventor
梁昆
张文锋
宋晓龙
丁俊吉
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
CCCC First Harbor Engineering Co Ltd
No 1 Engineering Co Ltd of CCCC First Harbor Engineering Co Ltd
Original Assignee
CCCC First Harbor Engineering Co Ltd
No 1 Engineering Co Ltd of CCCC First Harbor Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CCCC First Harbor Engineering Co Ltd, No 1 Engineering Co Ltd of CCCC First Harbor Engineering Co Ltd filed Critical CCCC First Harbor Engineering Co Ltd
Priority to CN201710524953.1A priority Critical patent/CN107130603B/en
Publication of CN107130603A publication Critical patent/CN107130603A/en
Application granted granted Critical
Publication of CN107130603B publication Critical patent/CN107130603B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D15/00Handling building or like materials for hydraulic engineering or foundations
    • E02D15/02Handling of bulk concrete specially for foundation or hydraulic engineering purposes

Landscapes

  • Engineering & Computer Science (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)

Abstract

The present invention is disclosed a kind of refuted using idle side and assembles the construction method that boom pours concrete waterborne, is belonged to technical field of building construction, including step one, is assembled boom;Step 2, boom casting concrete.The construction technology that the present invention is refuted using boom+ground pump+side, pour concrete effect waterborne more notable, improve efficiency of construction, accelerate construction speed, it is ensured that concrete Quality Control, it is especially waterborne when pouring cast-in-place pile concrete, its effect is more protruded, pile foundation concrete pouring quality is ensure that, site safety is in turn ensure that, the shock of limited reduction ship to operation platform.

Description

It is a kind of to refute the construction method that assembling boom pours concrete waterborne using idle side
Technical field
The present invention relates to a kind of construction method of concrete, and in particular to one kind is refuted assembling boom using idle side and poured The construction method of concrete waterborne, belongs to technical field of building construction.
Background technology
The conventional marine casting concrete of long piled wharf uses concrete mixer vessel mixed concrete, is characterized in that concrete is stirred Ship rental charge and dispatch with high, the supporting correlative charges of onsite application is higher;If offshore is relatively near and when can not dispatch mixer ship Harbour project, general use side, which refutes loop wheel machine and added, hangs the technique for pouring into mould, is characterized in that ship chartering is costly, speed of application Slowly high, are required to the concrete indices of cast in situs.
The content of the invention
In view of the above-mentioned problems of the prior art, the one kind of the invention that provides pours water using idle square assembling boom of refuting The construction method of upper concrete,, can timely, quickly on the premise of safety and quality is ensured using existing ship machine equipment Completion offshore concrete pour task, and construction cost is low.
To achieve these goals, one kind that the present invention is used refutes assembling boom using idle side and pours concrete waterborne Construction method, specifically include following steps,
Step one, boom is assembled;
1) selection space meets the place of use requirement on piling boat deck first, places truss upright-column base, base and first Plate weld is reinforced;
2)Carry out being provided with some spreaders one in the assembly of truss upright-column, column, column is lifted to upright post base and uses high-strength spiral shell Bolt reinforcement by connection, installs pump line in column, while setting multiple tracks bearing diagonal in column centre position, bearing diagonal uses steel welding Connect deck plating and column;
3)Assembled complete girder is sling, the pivoting support of girder bottom is saved into top connecting hole, Ran Houyong in alignment with support Bolt is fastened, and this connection is non-directional, and horizontal tower is installed by pivoting support on the top of column, Heng Tashang be provided with spreader two, Horizontal tower bearing diagonal one and horizontal tower bearing diagonal two, then install ballast box in one end of horizontal tower, and the other end installs steel wire rope;
4)After ballast box is lifted, now the pump line on cantilever is deployed by steel wire rope, will support section in vertical pump line with Girder feeding bent pipe is connected, and interface uses rubber ring seal;
5)Test run, tears place open with curved in the middle of big rope control concrete discharging opening and lever arm, is run one week in its maximum effect scope;
6)Ground pump concrete pump pipe is fixed with 90 ° of bend pipes below boom with pipe clamp, in adapter, checking in pump line is No to clean up, interface uses rubber washer, pump line to check bolt fastening situation after connecting, and so far completes the peace of boom Fill work;
Step 2, boom casting concrete;
1)Pile driving barge stays position, and pile driving barge is equipped with the tugboat scene of carrying out and stays position;
2)Casting concrete;
Whether the basic performance for 1. rechecking boom meets the requirements, and construction can be started by meeting after requiring;
2. the signal lamp and intercom of concreting are got out;
3. after feeding front pump slurry extraction washes away delivery pipe 10 minutes, concrete can progress into magazine feed, and mortar slowly subtracts It is few to arrive appropriate, normal work after 10 minutes;
4. during discharging opening change position, outlet is encased with a gunnysack, it is to avoid commerical ready-mixed concrete falls on the ground, to another Untied again on individual unloading position;
5. commerical ready-mixed concrete is poured finish after, pump line is cleaned up with mortar and clear water.
As an improvement, the top of the column is provided with reinforcement channel-section steel.
As an improvement, the specification of the ballast box is 1020 × 1020 × 800mm.
Gone on board compared to the pump truck in conventional art and enter mould construction with cage, the inventive method has advantages below:
1. side refutes has pile driving barge by oneself using company, it is not necessary to foreign payment lease expenses;
2. ground pump is own equipment, it is not necessary to separately purchased;
3. pile driving barge has 7 mouthfuls of windlass, for carrying out concreting, ship resistance to overturning is good, it is not easy to which shock has been poured Good component, is conducive to finished product protection;
4. because the boom side of being fixed on is refuted, being gone on board compared with pump truck, stability is good, and safety coefficient is high during construction;
5th, constructed compared to cage, speed of application can be greatly speeded up, reduce the construction period.
It is more notable that the present invention pours concrete effect waterborne using boom, improves efficiency of construction, accelerates construction Progress, it is ensured that concrete Quality Control.Especially waterborne when pouring cast-in-place pile concrete, its effect is more protruded, that is, is ensured Pile foundation concrete pouring quality, in turn ensure that site safety, the shock of limited reduction ship to operation platform.
Brief description of the drawings
Fig. 1 is the structural representation of truss upright-column in the present invention;
In figure:1st, column, 2, spreader one, 3, bearing diagonal, 4, pump line, 5, ballast box, 6, spreader two, 7, Heng Ta, 8, horizontal tower tiltedly props up Support one, 9, horizontal tower bearing diagonal two, 10, steel wire rope, 11, pivoting support, 12, channel-section steel.
Embodiment
It is right below by accompanying drawing and embodiment to make the object, technical solutions and advantages of the present invention of greater clarity The present invention is further elaborated.However, it should be understood that specific embodiment described herein is only to explain this hair Scope that is bright, being not intended to limit the invention.
Unless otherwise defined, all technical terms and scientific terminology used herein are led with belonging to the technology of the present invention The implication that the technical staff in domain is generally understood that is identical, and used term is intended merely to retouch in the description of the invention herein State the purpose of specific embodiment, it is not intended that in the limitation present invention.
It is a kind of to refute the construction method that assembling boom pours concrete waterborne using idle side, following steps are specifically included,
Step one, boom is assembled;
1) selection space meets the place of use requirement on piling boat deck first, places truss upright-column base, base and first Plate weld is reinforced;
2)The assembly of truss upright-column is carried out, as shown in figure 1, being provided with some spreaders 1 in column 1, column 1 is lifted to column bottom Seat uses high-strength bolt reinforcement by connection, pump line 4 is installed in column 1, while in order to ensure the stabilization of truss upright-column, in column 1 Centre position sets multiple tracks bearing diagonal 3, and bearing diagonal 3 welds deck plating and column 1 using shaped steel;
3)Assembled complete girder is sling, the pivoting support of girder bottom is saved into top connecting hole, Ran Houyong in alignment with support Bolt is fastened, and this connection is non-directional, is installed on the top of column 1 by pivoting support 11 and is provided with horizontal stroke on horizontal tower 7, horizontal tower 7 Post 26, horizontal tower bearing diagonal 1 and horizontal tower bearing diagonal 29, then install ballast box 5 in one end of horizontal tower 7, and the other end installs steel Cord 10;
4)After the lifting of ballast box 5 is good, now the pump line 4 on cantilever is deployed by steel wire rope 10, will support the vertical pump in section Pipe is connected with girder feeding bent pipe, and it is tight that interface uses rubber ring seal, concrete pump pipe to reexamine bolt after connecting Gu whether situation tightens, rechecked if necessary using torque spanner;
5)Test run, tears place open with curved in the middle of big rope control concrete discharging opening and lever arm, is run one week in its maximum effect scope, cloth Material bar stability, security, cloth scope etc. meet the requirements;
6)Ground pump concrete pump pipe is fixed with 90 ° of bend pipes below boom with pipe clamp, in adapter, it is necessary to exhaustive test Whether cleaned up in pump line, interface must use rubber washer, pump line should reexamine bolt fastening situation after connecting;
After the completion of above-mentioned work, that is, the installment work of boom is completed, be then connected, be completed with concrete pumping pipeline Safety inspection group is inspected for acceptance afterwards, and acceptance(check) can put into cloth work after providing each group member's signature of record of acceptance Industry.
Wherein, assembling boom material requested is as shown in table 1 below.
Table 1 assembles boom material requested
Sequence number Title Specification Unit Quantity
1 Column 56 × 56 × 5.0 angle steel 8000mm 4
2 Spreader one 50 × 50 × 4.0 angle steel 600mm 32
3 Bearing diagonal 40 × 40 × 4.0 angle steel 800mm 32
4 Pump line 125mm pump lines 8000mm 1
5 Ballast box 1020×1020×800mm 1
6 Spreader two 14# channel-section steels 300mm 14
7 Horizontal tower 16# channel-section steels 10869mm 2
8 Horizontal tower bearing diagonal one 50 × 50 × 4mm angle steel 2700mm 2
9 Horizontal tower bearing diagonal two 50 × 50 × 4mm angle steel 5700mm 2
10 Steel wire rope ∅:12mm 20m 1
11 Pivoting support 315 bearings 1
12 Channel-section steel 160×60×4mm 4000mm 4
Step 2, boom casting concrete;
1)Pile driving barge is equipped with the special tugboat scene of carrying out and stays position, and position should be according to needing pouring structure planar dimension, pipe arrangement situation etc. Consider, it is desirable to which apparatus for distributing should be able to cover total plane, and energy is uniform, promptly carry out cloth, equipment should be firm, steady Determine and do not influence the normal operating of other processes;
When using fixed boom operation, ship machine, which stays position, should will pour position as much as possible in the work of fixed boom In the range of, it is to avoid carrying out secondary position of staying can complete to pour;
2)Casting concrete;
Boom construction point:
Whether the basic performance for 1. rechecking boom is met the requirements, and commerical ready-mixed concrete discharging opening is controlled with big rope, and in the middle of lever arm It is curved to tear place open, run one week in its maximum effect scope, construction can be started by meeting after requiring;
2. the signal lamp and intercom of concreting are got out, it is ensured that the lamp pump that goes out stops, halt it is vertical stop, foreground pours a little necessary Halt, turn off the light within 4 seconds in advance, communication must set special messenger's progress, when carrying on construction work at night, the people of control concrete must mix torch, see Clear concreting height and concrete quality;
3. after feeding front pump slurry extraction washes away delivery pipe 10 minutes, concrete can progress into magazine feed, and mortar slowly subtracts It is few to arrive appropriate, 10 minutes or so can normal work;
4. during discharging opening change position, outlet is encased with a gunnysack, it is to avoid commerical ready-mixed concrete falls on the ground, arrives another Untied again on unloading position;
5. commerical ready-mixed concrete is poured finish after, it is necessary to pump line is cleaned up with mortar and clear water, it is to avoid pipe inner concrete condense Generation plugging phenomenon.
As the improvement of embodiment, the top of the column 1 is provided with reinforcement channel-section steel 12, and overall construction intensity is high, consolidates Property is good.
Through analysis contrast, boom casting concrete technique of the invention is gone on board compared with concrete mixer hangs filling work with loop wheel machine Skill, saves equipment leasing expense, while also saving the time that ship repeatedly stays position, greatly improves cast concrete cast speed Degree, the duration of pouring significantly reduces, and is effectively guaranteed the casting quality of concrete.
Secondly, refute assembling boom using idle side and pour that concrete engineering method efficiency of construction waterborne is high, safe and reliable, economy Benefit is obvious;Boom assembling is quick and easy, adapts to most harbour over-water construction projects, especially Cambodia area There is a serious shortage in the supply for the ship such as mixer ship machine equipment, dispatches costly from domestic or other countries.Therefore, refute and set using existing idle side It is standby by rational design and to transform, it is capable of the construction task of more outstanding completion Wharf Engineering concreting waterborne, it is right Correlation engineering has certain reference directive function.
The foregoing is merely illustrative of the preferred embodiments of the present invention, is not intended to limit the invention, all essences in the present invention Any modification, equivalent substitution or improvement made within refreshing and principle etc., should be included in the scope of the protection.

Claims (3)

1. a kind of refute the construction method that assembling boom pours concrete waterborne using idle side, it is characterised in that specifically includes Following steps,
Step one, boom is assembled;
1) selection space meets the place of use requirement on piling boat deck first, places truss upright-column base, base and first Plate weld is reinforced;
2)Carry out the assembly of truss upright-column, column(1)It is interior to be provided with some spreaders one(2), by column(1)Lifting to upright post base is adopted High-strength bolt reinforcement by connection is used, in column(1)Interior installation pump line(4), while in column(1)Centre position sets multiple tracks bearing diagonal (3), bearing diagonal(3)Deck plating and column are welded using shaped steel(1);
3)Assembled complete girder is sling, the pivoting support of girder bottom is saved into top connecting hole, Ran Houyong in alignment with support Bolt is fastened, and this connection is non-directional, in column(1)Top pass through pivoting support(11)Horizontal tower is installed(7), horizontal tower(7)On It is provided with spreader two(6), horizontal tower bearing diagonal one(8)With horizontal tower bearing diagonal two(9), then in Heng Ta(7)One end install counterweight Case(5), other end installation steel wire rope(10);
4)Treat ballast box(5)Lift after getting well, now the pump line on cantilever(4)Pass through steel wire rope(10)Expansion, by support section Vertical pump line is connected with girder feeding bent pipe, and interface uses rubber ring seal;
5)Test run, tears place open with curved in the middle of big rope control concrete discharging opening and lever arm, is run one week in its maximum effect scope;
6)Ground pump concrete pump pipe is fixed with 90 ° of bend pipes below boom with pipe clamp, in adapter, checking in pump line is No to clean up, interface uses rubber washer, pump line to check bolt fastening situation after connecting, and so far completes the peace of boom Fill work;
Step 2, boom casting concrete;
1)Pile driving barge stays position, and pile driving barge is equipped with the tugboat scene of carrying out and stays position;
2)Casting concrete;
Whether the basic performance for 1. rechecking boom meets the requirements, and construction can be started by meeting after requiring;
2. the signal lamp and intercom of concreting are got out;
3. after feeding front pump slurry extraction washes away delivery pipe 10 minutes, concrete can progress into magazine feed, and mortar slowly subtracts It is few to arrive appropriate, normal work after 10 minutes;
4. during discharging opening change position, outlet is encased with a gunnysack, it is to avoid commerical ready-mixed concrete falls on the ground, to another Untied again on individual unloading position;
5. commerical ready-mixed concrete is poured finish after, pump line is cleaned up with mortar and clear water.
2. a kind of refuted using idle side according to claim 1 assembles the construction method that boom pours concrete waterborne, Characterized in that, the column(1)Top be provided with reinforcement channel-section steel(12).
3. a kind of refuted using idle side according to claim 1 assembles the construction method that boom pours concrete waterborne, Characterized in that, the ballast box(5)Specification be 1020 × 1020 × 800mm.
CN201710524953.1A 2017-06-30 2017-06-30 It is a kind of to refute the construction method that assembling boom pours concrete waterborne using idle side Active CN107130603B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710524953.1A CN107130603B (en) 2017-06-30 2017-06-30 It is a kind of to refute the construction method that assembling boom pours concrete waterborne using idle side

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710524953.1A CN107130603B (en) 2017-06-30 2017-06-30 It is a kind of to refute the construction method that assembling boom pours concrete waterborne using idle side

Publications (2)

Publication Number Publication Date
CN107130603A true CN107130603A (en) 2017-09-05
CN107130603B CN107130603B (en) 2019-10-11

Family

ID=59737271

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710524953.1A Active CN107130603B (en) 2017-06-30 2017-06-30 It is a kind of to refute the construction method that assembling boom pours concrete waterborne using idle side

Country Status (1)

Country Link
CN (1) CN107130603B (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109162279A (en) * 2018-10-09 2019-01-08 长江勘测规划设计研究有限责任公司 With the distribution device that can continuously put in storage and its construction method of tower crane cooperation
CN112478100A (en) * 2020-12-18 2021-03-12 览越工程管理咨询有限公司 Method for building concrete spherical underwater building

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH08170343A (en) * 1994-12-16 1996-07-02 Fujita Corp Finishing construction method of underwater rubble mound
CN2285337Y (en) * 1996-08-23 1998-07-01 ***长沙建设机械研究院 Manual concrete distributing lover
JP2000017644A (en) * 1998-07-01 2000-01-18 Kansai Electric Power Co Inc:The Installation method of underwater structure
CN201730053U (en) * 2010-04-15 2011-02-02 上海建工(集团)总公司 Symmetric concrete casting device for box girder over water
CN104060545A (en) * 2014-07-10 2014-09-24 中交二航局第四工程有限公司 Overwater suspension cable trestle capable of being used for pumping concrete and construction method and application thereof
CN206143774U (en) * 2016-10-15 2017-05-03 中铁四局集团有限公司 Assembling wharf boat overwater operation platform

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH08170343A (en) * 1994-12-16 1996-07-02 Fujita Corp Finishing construction method of underwater rubble mound
CN2285337Y (en) * 1996-08-23 1998-07-01 ***长沙建设机械研究院 Manual concrete distributing lover
JP2000017644A (en) * 1998-07-01 2000-01-18 Kansai Electric Power Co Inc:The Installation method of underwater structure
CN201730053U (en) * 2010-04-15 2011-02-02 上海建工(集团)总公司 Symmetric concrete casting device for box girder over water
CN104060545A (en) * 2014-07-10 2014-09-24 中交二航局第四工程有限公司 Overwater suspension cable trestle capable of being used for pumping concrete and construction method and application thereof
CN206143774U (en) * 2016-10-15 2017-05-03 中铁四局集团有限公司 Assembling wharf boat overwater operation platform

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
曹正亮: "混凝土水上浇筑技术在柬埔寨上丁湄公河大桥施工中的应用", 《建筑施工》 *
程旭东 等: "工程方驳改搅拌船的技术思路及工艺", 《中国水运》 *

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109162279A (en) * 2018-10-09 2019-01-08 长江勘测规划设计研究有限责任公司 With the distribution device that can continuously put in storage and its construction method of tower crane cooperation
CN112478100A (en) * 2020-12-18 2021-03-12 览越工程管理咨询有限公司 Method for building concrete spherical underwater building

Also Published As

Publication number Publication date
CN107130603B (en) 2019-10-11

Similar Documents

Publication Publication Date Title
CN101619630B (en) Mounting method of steel chimney and implementary jacking device
CN101832049A (en) Concrete-structured conjoined cylindrical shell construction device and method therefor
CN107100193B (en) A kind of construction technology for blower cushion cap
CN106677258A (en) Installing process of offshore water taking head caisson of power plant
CN106012960A (en) Assembly type long piled wharf upper structure system and construction method thereof
CN107130603B (en) It is a kind of to refute the construction method that assembling boom pours concrete waterborne using idle side
CN107152032A (en) The template system and the construction method of cushion cap of a kind of bearing platform construction for offshore wind farm
CN107882055A (en) A kind of construction method of blower fan cushion cap
CN211849244U (en) Novel assembled high-pile beam-slab wharf structure
CN101858059A (en) Construction method of erecting prestressed concrete beam on river
CN101962946A (en) Method for arranging hoisting points and floating-supported conduit frame with skirt pile sleeves
CN108570974B (en) Prefabricated fishway groove of bottom plate
CN110172995B (en) Grouting construction system and method for large-diameter single-pile steel pipe pile interpolation transition section
CN209795746U (en) novel assembled is tied and is leaned on ship device
CN209469875U (en) A kind of concrete pump pipe bending place support device
CN216194899U (en) Bearing platform prefabricated structure and bearing platform foundation
CN206680096U (en) One kind is used for restricted clearance hanging apparatus
CN108978690A (en) A kind of bridge steel cofferdam decentralization stand construction method
CN112412154B (en) Ultra-high voltage transmission line construction process with floating type overwater platform as operation surface
CN106192767B (en) A kind of device and construction method that can improve bottom concrete bearing capacity
CN210341975U (en) Major diameter single pile steel-pipe pile interpolation changeover portion grouting construction system
CN214738234U (en) Modular breakwater dyke head navigation light stake foundation structure
CN211368578U (en) High stake combination wharf structure of sheet pile
CN113818477A (en) Bearing platform prefabricated structure, bearing platform foundation and construction method thereof
CN113431081A (en) Integral ship-leaning anti-collision structure of offshore wind power multi-pile foundation and construction method

Legal Events

Date Code Title Description