CN107069679A - A kind of symmetrical bipolar MMC DC sides monopolar grounding fault is passed through and restoration methods - Google Patents

A kind of symmetrical bipolar MMC DC sides monopolar grounding fault is passed through and restoration methods Download PDF

Info

Publication number
CN107069679A
CN107069679A CN201710199650.7A CN201710199650A CN107069679A CN 107069679 A CN107069679 A CN 107069679A CN 201710199650 A CN201710199650 A CN 201710199650A CN 107069679 A CN107069679 A CN 107069679A
Authority
CN
China
Prior art keywords
mrow
mmc
current
msup
pole
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201710199650.7A
Other languages
Chinese (zh)
Other versions
CN107069679B (en
Inventor
林磊
何震
胡家兵
徐晨
胡凯
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Huazhong University of Science and Technology
Original Assignee
Huazhong University of Science and Technology
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Huazhong University of Science and Technology filed Critical Huazhong University of Science and Technology
Priority to CN201710199650.7A priority Critical patent/CN107069679B/en
Publication of CN107069679A publication Critical patent/CN107069679A/en
Application granted granted Critical
Publication of CN107069679B publication Critical patent/CN107069679B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02HEMERGENCY PROTECTIVE CIRCUIT ARRANGEMENTS
    • H02H7/00Emergency protective circuit arrangements specially adapted for specific types of electric machines or apparatus or for sectionalised protection of cable or line systems, and effecting automatic switching in the event of an undesired change from normal working conditions
    • H02H7/26Sectionalised protection of cable or line systems, e.g. for disconnecting a section on which a short-circuit, earth fault, or arc discharge has occured
    • H02H7/268Sectionalised protection of cable or line systems, e.g. for disconnecting a section on which a short-circuit, earth fault, or arc discharge has occured for dc systems

Landscapes

  • Inverter Devices (AREA)

Abstract

The present invention proposes a kind of symmetrical bipolar MMC DC sides monopolar grounding fault and passed through and restoration methods.The present invention by the cooperation of dc circuit breaker and transverter, realize to direct fault current cut-off and power recovery, protect the safe operation of transverter.Coordinate the active power shortage of current conversion station during reducing failure by perfecting the active power and reactive power of pole and failure pole, while providing specified reactive power to power network, reduce impact of the failure to AC system;Pass through the active control to the upper and lower bridge arm reference voltage common mode component of transverter, it is to avoid the risk that transverter current surge stress excessive caused by unsuccessful reclosing is brought to system safety operation.Both positive and negative polarity dc bus can be regarded as based on the bipolar short trouble of symmetrical bipolar MMC DC sides generation a kind of special circumstances of monopolar grounding fault occur respectively, therefore the present invention can be additionally used in symmetrical bipolar MMC DC sides and occur the processing of bipolar short trouble.

Description

A kind of symmetrical bipolar MMC DC sides monopolar grounding fault is passed through and restoration methods
Technical field
The invention belongs to flexible high pressure DC transmission system DC error protection field, more particularly, to a kind of symmetrical Bipolar MMC DC sides monopolar grounding fault is passed through and restoration methods.
Background technology
The problems such as due to energy shortage and environmental protection, increasingly highlights, and the novel renewable energy such as wind-force and solar energy generates electricity The ratio that amount accounts for gross generation gradually increases.In China, wind energy, solar energy equal energy source have focused largely on remote districts, caused The location distribution of the energy and load is unbalanced, it is necessary to long range, Large Copacity conveying electric energy.Applied to long range, great Rong During amount transmission of electricity, the cost and reactive loss of high-voltage AC transmission system increase sharply with the increase of transmission distance.Therefore, high pressure HVDC Transmission Technology gradually causes the concern of domestic and foreign scholars, and has obtained rapid development.
D.C. high voltage transmission HVDC based on voltage source type converter VSC (Voltage Source Converter) (High-Voltage Direct-Current) technology has relative to Traditional DC technology of transmission of electricity:Without reactive-load compensation, do not have Commutation failure risk, can be caused domestic and foreign scholars and is widely closed with advantages such as the active and reactive powers of separately adjustable system Note.Compared to traditional two level and three-level topology structure, modularization multi-level converter MMC (Modular Multilevel Converter) there is structure height modularization, be easy to extension, without multi-winding isolation transformer and output electricity The low advantage of harmonic wave is pressed, is applied in Practical Project, the end of Zhoushan five of such as the Transbay engineerings in the U.S., China is flexible DC transmission engineering.
Symmetrical bipolar connection plan is one of main Main Wire Connection Scheme of current MMC-HVDC systems.Symmetrical bipolar MMC phases Have the advantages that the method for operation is flexible, transmission capacity is big, reliability is high, bipolar individually controllable than symmetrical monopolar MMC.It is symmetrical bipolar MMC is in DC side both positive and negative polarity neutral earthing, and both positive and negative polarity is relatively independent.When a pole of system hinders out of service for some reason, Ling Yiji Normal operation is remained to, and keeps the specified transmission capacity of half.The current symmetrical bipolar DC transmission engineering put into operation has Xiamen Flexible DC power transmission engineering.
However, the protection of symmetrical bipolar MMC direct currents side pole fault to ground is still the significant challenge in Practical Project.It is existing MMC-HVDC systems in it is many using devices are few, cost economic half-bridge submodule HBSM (Half-Bridge SM).Due to HBSM does not have DC Line Fault self-cleaning ability, then system can produce excessive fault current.This not only can be to the device of transverter Part is caused damage, and larger impact can be also produced to AC system, the stability of AC system is influenceed.In the prior art, handle Symmetrical bipolar MMC DC sides monopolar grounding fault mainly has following several method:
1) using the submodule with DC Line Fault Scavenging activity.After monopolar grounding fault occurs for DC side, submodule Locking immediately.Setting up backward voltage by submodule electric capacity forces fault current to be decayed rapidly.But the submodule that this method is used Block needs extra switching device to cause construction cost higher compared to half-bridge MMC, and running wastage is larger.During failure, the change of current Device locking is big to the power rush of AC system.
2) high voltage DC breaker is used.When monopolar grounding fault occurs for DC side, dc circuit breaker, which is performed, cut-offs behaviour Make to cut-off direct fault current.In this way during failure, because failure is extremely out of service, cause what system was transmitted Rated active power have lost half so that active power shortage is big.Meanwhile, when dc circuit breaker attempts reclosing, if weight Close a floodgate and fail, then failure pole is equivalent to occurring " second short circuit ", and huge surge current stress will endanger transverter safe operation.
In summary, when handling symmetrical bipolar MMC generations monopolar grounding fault using HVDC short-circuiting device, exist active Power shortage is big, the problem of surge current stress is big during reclosing.
The content of the invention
For the disadvantages described above or Improvement requirement of prior art, the invention provides the event over the ground of symmetrical bipolar MMC direct currents pole The traversing method and recovery policy of barrier, it is intended to solve prior art active power shortage during direct current side pole fault to ground it is big with And during dc circuit breaker reclosing the problem of surge current stress is big.
To achieve the above object, the present invention proposes that a kind of symmetrical bipolar MMC DC sides monopolar grounding fault is passed through and recovered Method.The DC transmission system that the present invention is applicable is included comprising two connection transformers, two MMC and two dc bus, Symmetrical bipolar MMC is in DC side both positive and negative polarity neutral earthing.The MMC includes A, B, C three-phase, and upper and lower two bridge arms are included per phase, Each bridge arm is made up of n half-bridge sub-module cascade, one bridge arm inductance of concatenation.The half-bridge submodule is by two IGBT and two Individual antiparallel diode, one electric capacity of connection is constituted, and the half-bridge submodule, which also includes one, is used for the brilliant lock of error protection Pipe.Every described dc bus concatenates a smoothing reactor and a dc circuit breaker;It is assumed that being sent out in described positive pole Raw monopolar grounding fault, then claim just extremely failure pole, and negative pole is perfects pole.It is characterised in that it includes following steps:
(1) differentiate whether MMC DC sides occur monopolar grounding fault;
It is then to perform following act:Failure pole MMC block signals are sent, are made in all half-bridge submodules of failure pole MMC IGBT is all off, to block the discharge path of the half-bridge submodule electric capacity;The bypass IGCT for sending half-bridge submodule is led Messenger, bypasses antiparallel diode in the half-bridge submodule, to protect anti-paralleled diode;The direct current of failure pole is broken Road device sends open command, blocks the short circuit path of AC network;
Otherwise system keeps stable state control model;
The MMC refers to modularization multi-level converter;
(2) after bus direct fault current decays to zero, failure pole MMC unlocking signals is sent, failure pole is transferred to STATCOM operational modes, reactive power support is persistently provided to AC;
(3) when dc bus goes free process to terminate, that is, when recovering dielectric level, to the dc circuit breaker on dc bus Send reclosing signal;
(4) whether the surge current stress of Judging fault pole dc bus is excessive;
It is to show that temporary fault is not eliminated, is sent to the dc circuit breaker and back off signal, isolated fault Point;Go to step (5);
Otherwise show that temporary fault has been eliminated, send progressively recovery power transmission signal to failure pole MMC, make its turn Enter stable state control model;Turn to terminate;
(5) judge whether the dc circuit breaker is more than presetting excessively stream number of times by the number of times of electric current overrate; It is MMC is kept STATCOM operational modes, direct-current short circuit device no longer carries out reclosing trial, turns to terminate;Otherwise go to step (1);Presetting excessively stream number of times takes 2~3 times.
The traversing method and recovery policy for the symmetrical MMC monopolar grounding faults that the present invention is provided are by transverter and direct current What breaker cooperation was realized.During failure, locking transverter cut-offs dc circuit breaker to protect the peace of failure pole transverter Row for the national games.In the case where considering the limitation of multi-constraint condition, coordinate to match somebody with somebody by perfecting the active power and reactive power of pole and failure pole Close, overload is run on when making to perfect extremely short, reduce power shortage of the system during failure.Meanwhile, run failure pole In STATCOM states persistently to provide reactive power support to AC and reduce impact to AC system.By to MMC transverters The active control of upper and lower bridge arm reference voltage common mode component, can effectively be reduced because of the wave that dc circuit breaker unsuccessful reclosing is produced Gush current-rising-rate.
Preferably, the step (2) includes following sub-step:
(2-1) is pressed according to converter power transformer capacity, MMC bridge arms through-current capability, half-bridge submodule, submodule capacitor voltage Fluctuation and DC line overload capacity constraints, try to achieve the active power for perfecting pole MMC and reactive power operation region; In the active power and reactive power operation region, adjustment perfects pole MMC stable operations operating point, it is run on mistake in short-term Carry, with transmitting active power as much as possible, so as to make up the power shortage of monopolar grounding fault;
(2-2) transmits twice of rated reactive power signal during being emitted in failure to the failure pole MMC, make described strong The rated reactive power of full pole MMC required transmission in the steady state is undertaken by failure pole MMC.
Preferably, the restrictive condition of converter power transformer capacity is described in the step (2-1):
The transmission capacity S of active-power P, reactive power Q and converter power transformer that transverter is transmittedmaxMeet:
P2+Q2< Smax 2
Wherein, active-power P, reactive power Q are respectively the active and reactive power that MMC is flowed to from PCC, SmaxFor the change of current The maximum transfer capacity of transformer.
Preferably, the restrictive condition of MMC bridge arm through-current capabilities is described in the step (2-1):
Each bridge arm current is met:
Wherein, IlimFor the maximum current capacity of each IGBT in submodule, UdcFor single MMC DC bus-bar voltage, Usm For ac bus voltage magnitude;Rectification direction is positive direction.
Preferably, the restrictive condition that each half-bridge submodule is pressed in the step (2-1) is:
The DC component of each bridge arm current is necessarily less than AC compounent;I.e. active-power P and reactive power Q are met:
Preferably, the restrictive condition of voltage fluctuation of capacitor is in each submodule:
During MMC steady-state operations, voltage fluctuation of capacitor no more than the permitted maximum range of submodule, i.e.,:
Wherein, N is submodule quantity, and C is submodule capacitance, UcFor submodule rated voltage, k modulates for built-in potential Than submodule capacitor voltage fluctuation percentageIts maximum is εmax.Transverter institute The reactive power Q of transmissioncBy the difference of Q and AC equivalent inductance the L reactive power consumedI.e.XLFor the induction reactance X of AC equivalent inductanceL=ω L, ω are angular frequency.
Preferably, DC line overload capacity described in the step (2-1) is met:
The short-time overload capacity limit of DC current no more than DC line, i.e.,
Wherein, idcFor DC bus current, idc_maxFor the DC line short-time overload capacity limit.
Preferably, after the step (2-1), step (2-2), following steps are also performed:
(2-3) is superimposed auxiliary voltage on the upper and lower bridge arm reference voltages of MMCMake the upper and lower bridges of MMC Arm voltage is:The superposition auxiliary voltage reduces the rising of surge current Rate, the risk brought with the current surge stress for avoiding transverter excessive caused by unsuccessful reclosing to system safety operation;
Wherein, δ is PCC point built-in potentials evRelative to ac bus voltage usPhase difference, idcFor failure dc bus electricity Stream (rectification direction is positive direction),For DC current reference value, R (R>0) it is damped coefficient, up_upFor bridge arm voltage on MMC, up_downFor bridge arm voltage under MMC;If dc circuit breaker reclosing success, due to the presence of the flat ripple reactance of direct current, idcIt will not go out Existing surge current, therefore cut-off stream current reference valueIf dc circuit breaker unsuccessful reclosing, surge current idcOn rapid Rise.
In the present invention, when dc circuit breaker unsuccessful reclosing, (i.e. active resistance can be suppressed by the active control of transverter Buddhist nun control) system produce huge surge current stress.
In general, by the contemplated above technical scheme of the present invention compared with prior art, with following beneficial effect Really:
Direct fault current is cut-off 1. being realized by the cooperation of dc circuit breaker and transverter, protection transverter Safe operation.After Failure elimination, the foundation of DC voltage and the recovery of power are realized.
2. during failure, make to perfect pole meeting converter power transformer capacity, bridge arm through-current capability, half-bridge submodule and press need Ask, submodule capacitor voltage fluctuation and the several aspects of DC line overload capacity constraints under, run on short-time overload shape State, with transmitting active power as much as possible, so that the power shortage of monopolar grounding fault is made up, while changing the transmission of failure pole Flow whole rated reactive powers needed for station.Event is reduced by active power and the reactive power cooperation for perfecting pole and failure pole The active power shortage of current conversion station during barrier, while providing specified reactive power to power network, reduces failure to AC system Impact.
3. during failure, by the active control to the upper and lower bridge arm reference voltage common mode components of MMC, effectively reduce The climbing of surge current, it is to avoid transverter current surge stress excessive caused by unsuccessful reclosing gives system safety Run the risk brought.
4. due to based on symmetrical bipolar MMC in DC side both positive and negative polarity neutral earthing, DC side occur it is bipolar it is short-circuit can Regard both positive and negative polarity dc bus as and a kind of special circumstances of monopolar grounding fault occur respectively.Therefore, base proposed by the invention Passed through in symmetrical bipolar MMC DC side monopolar grounding fault and recovery policy is equally applicable to symmetrical bipolar MMC DC sides The bipolar short trouble of generation.
Brief description of the drawings
Fig. 1 is the symmetrical bipolar MMC flexible direct-current system topology schematic of both-end;
Fig. 2 is symmetrical bipolar half-bridge MMC topological structure and monopolar grounding fault schematic diagram;
Fig. 3 DC side monopolar grounding faults are passed through and recovery policy flow chart;
Fig. 4 is surge current stress optimization control block diagram;
Active-power P and reactive power Q can range of operation schematic diagrames during Fig. 5 is failure;
Wherein, Fig. 5 (a) considers converter power transformer capacity and the active power and reactive power of the limitation of bridge arm through-current capability Can range of operation schematic diagram;Fig. 5 (b) considers the active power for the limitation that converter power transformer capacity is fluctuated with submodule capacitor voltage Can range of operation schematic diagram with reactive power;Fig. 5 (c) considers converter power transformer capacity and the limitation of DC line overload capacity Active power and reactive power can range of operation schematic diagrames;
Fig. 6 is to perfect pole and failure pole active reactive Power operation scope schematic diagram during failure under many limiting factors;
Fig. 7 is that the symmetrical bipolar semi-bridge type MMC DC Line Faults for being not introduced into the control of surge current stress optimization pass through emulation knot Really;Wherein, Fig. 7 (A) representing faults pole, Fig. 7 (B), which is represented, perfects pole.
Wherein, Fig. 7 (A1) be failure pole DC bus-bar voltage (kV), Fig. 7 (A2) be failure pole DC bus current (kA), Fig. 7 (A3) is that active and reactive power (MW/MVar), Fig. 7 (A4) of the PCC points transmission of failure pole are failure pole ac-side currents (kA), Fig. 7 (A5) is that failure pole upper and lower bridge arm submodule capacitor voltage (kV), Fig. 7 (A6) are the bridge arm currents of failure pole six (kA);Fig. 7 (B1) is that to perfect pole DC bus-bar voltage (kV), Fig. 7 (B2) be to perfect pole DC bus current (kA), Fig. 7 (B3) It is that to perfect the active of pole PCC points transmission with reactive power (MW/MVar), Fig. 7 (B4) be to perfect pole ac-side current (kA), Fig. 7 (B5) it is that to perfect pole upper and lower bridge arm submodule capacitor voltage (kV), Fig. 7 (B6) be to perfect the bridge arm current (kA) of pole six;
Fig. 8 is that the symmetrical bipolar semi-bridge type MMC DC Line Faults for introducing surge current stress optimization control strategy pass through emulation As a result.
Embodiment
In order to make the purpose , technical scheme and advantage of the present invention be clearer, it is right below in conjunction with drawings and Examples The present invention is further elaborated.It should be appreciated that specific embodiment described herein is only to explain the present invention, not For limiting the present invention.As long as in addition, technical characteristic involved in each embodiment of invention described below that Not constituting conflict between this can just be mutually combined.
The present invention describes symmetrical bipolar MMC monopolar grounding faults by taking the symmetrical bipolar MMC of both-end as an example and passed through and recovery policy. Fig. 1 is the symmetrical bipolar MMC system topology schematics of both-end, includes two current conversion stations.Each current conversion station is using symmetrical bipolar master The mode of connection, as shown in Figure 2.Symmetrical bipolar MMC includes two connection transformers, two in DC side both positive and negative polarity neutral earthing MMC and two dc bus.Every dc bus concatenates a smoothing reactor and a dc circuit breaker;Each MMC bags Containing A, B, C three-phase, per upper and lower two bridge arms are mutually included, each bridge arm concatenates a bridge arm electricity by N number of half-bridge sub-module cascade Sense is constituted.Semi-bridge type MMC topological structure schematic diagram, as shown in Figure 3.Half-bridge submodule is antiparallel by two IGBT and two Diode, one electric capacity of connection are constituted, and described half-bridge submodule, which also includes one, is used for the IGCT of error protection.It is assumed that Monopolar grounding fault occurs for described positive pole, then claims just extremely failure pole, and negative pole is perfects pole.
Fault traversing of the present invention and recovery policy are related to cooperation such as Fig. 4 institutes of transverter and dc circuit breaker Show, specifically include following steps:
(1) differentiate whether MMC DC sides occur monopolar grounding fault, be then to perform following act:Failure pole MMC is sent to close Lock signal, makes IGBT in all half-bridge submodules of failure pole MMC all off, to block the electric discharge of the half-bridge submodule electric capacity Path;The bypass turn on thyristors signal of half-bridge submodule is sent, antiparallel diode in the half-bridge submodule is bypassed, with Protect anti-paralleled diode;Open command is sent to the dc circuit breaker of failure pole, the short circuit path of AC network is blocked;Otherwise System keeps stable state control model;The MMC refers to modularization multi-level converter;
(2) after bus direct fault current decays to zero, failure pole MMC unlocking signals is sent, failure pole is transferred to STATCOM operational modes, reactive power support is persistently provided to AC;
(3) when dc bus goes free process to terminate and (recover dielectric level), to the direct current interruption on dc bus Device sends reclosing signal;
(4) whether the surge current stress of Judging fault pole dc bus is excessive;It is to show that temporary fault is not clear Remove, sent to the dc circuit breaker and back off signal, isolated fault point;Go to step (5);Otherwise temporary fault is shown It is eliminated, sends progressively recovery power transmission signal to failure pole MMC, it is transferred to stable state control model;Turn to terminate;
(5) judge whether the dc circuit breaker is more than presetting excessively stream number of times by the number of times of electric current overrate; It is MMC is kept STATCOM operational modes, direct-current short circuit device no longer carries out reclosing trial, turns to terminate;Otherwise go to step (1);Presetting excessively stream number of times takes 2~3 times.
As a kind of prioritization scheme, the step (2) includes following sub-step:
(2-1) is pressed according to converter power transformer capacity, MMC bridge arms through-current capability, half-bridge submodule, submodule capacitor voltage Fluctuation and DC line overload capacity constraints, try to achieve the active power for perfecting pole MMC and reactive power operation region; In the active power and reactive power operation region, adjustment perfects pole MMC stable operations operating point, it is run on mistake in short-term Carry, with transmitting active power as much as possible, so as to make up the power notch of monopolar grounding fault;
(2-2) transmits twice of rated reactive power signal during being emitted in failure to the failure pole MMC, make described strong The rated reactive power of full pole MMC required transmission in the steady state is undertaken by failure pole MMC.
As a kind of prioritization scheme, the restrictive condition of converter power transformer capacity is described in the step (2-1):
The transmission capacity S of active-power P, reactive power Q and converter power transformer that transverter is transmittedmaxMeet:
P2+Q2< Smax 2
Wherein, active-power P, reactive power Q are respectively from points of common connection PCC (Point of Common Coupling MMC active and reactive power, S) are flowed tomaxFor the maximum transfer capacity of converter power transformer.
As a kind of prioritization scheme, the restrictive condition of MMC bridge arm through-current capabilities is described in the step (2-1):
Each bridge arm current is met:
Wherein, IlimFor the maximum current capacity of each IGBT in submodule, UdcFor single MMC DC bus-bar voltage, Usm For ac bus voltage magnitude;Rectification direction is positive direction.(// note:Here power represents direction, and rectification direction is retouched for positive direction It is more accurate to state, so write it will be realized that.//)
As a kind of prioritization scheme, the restrictive condition that each half-bridge submodule is pressed in the step (2-1) is:
The DC component of each bridge arm current is necessarily less than AC compounent;I.e. active-power P and reactive power Q are met:
As a kind of prioritization scheme, the restrictive condition of voltage fluctuation of capacitor is in each submodule:
During MMC steady-state operations, capacitance voltage ripple rate no more than the permitted maximum range of submodule, i.e.,:
Wherein, N is submodule quantity, and C is submodule capacitance, UcFor submodule rated voltage, k modulates for built-in potential Than submodule capacitor voltage fluctuation percentageIts maximum is εmax.Transverter institute The reactive power Q of transmissioncBy the difference of Q and AC equivalent inductance the L reactive power consumedI.e.XLFor the induction reactance X of AC equivalent inductanceL=ω L, ω are angular frequency.
As a kind of prioritization scheme, DC line overload capacity described in the step (2-1) is met:
The short-time overload capacity limit of DC current no more than DC line, i.e.,
Wherein, idcFor DC bus current, idc_maxFor the DC line short-time overload capacity limit.
As a kind of prioritization scheme, after the step (2-1), step (2-2), following steps are also performed:
(2-3) is superimposed auxiliary voltage on the upper and lower bridge arm reference voltages of MMCMake the upper and lower bridges of MMC Arm voltage is:The superposition auxiliary voltage reduces the rising of surge current Rate, the risk brought with the current surge stress for avoiding transverter excessive caused by unsuccessful reclosing to system safety operation;
Wherein, δ is PCC point built-in potentials evRelative to ac bus voltage usPhase difference, idcFor failure dc bus electricity Stream (rectification direction is positive direction),For DC current reference value, R (R>0) it is damped coefficient, up_upFor bridge arm voltage on MMC, up_downFor bridge arm voltage under MMC;If dc circuit breaker reclosing success, due to the presence of the flat ripple reactance of direct current, idcIt will not go out Existing surge current, therefore cut-off stream current reference valueIf dc circuit breaker unsuccessful reclosing, surge current idcOn rapid Rise.
The traversing method and recovery policy for the symmetrical bipolar MMC monopolar grounding faults that the present invention is provided are by MMC and straight Flow what breaker cooperation was realized.During failure, MMC lockings cut-off dc circuit breaker to protect the peace of failure pole transverter Row for the national games.In the case where considering the limitation of multi-constraint condition, coordinate to match somebody with somebody by perfecting the active power and reactive power of pole and failure pole Close, overload is run on when making to perfect extremely short, reduce power shortage of the system during failure.Meanwhile, run failure pole In STATCOM states persistently to provide reactive power support to AC and reduce impact to AC system.By to MMC transverters The active control of upper and lower bridge arm reference voltage common mode component, the surge that effectively reduction is produced by dc circuit breaker unsuccessful reclosing Current-rising-rate.
To make those skilled in the art more fully understand the present invention, with reference to symmetric double of the specific embodiment to the present invention Pole semi-bridge type MMC monopolar grounding faults are passed through to be described in detail with recovery policy.
This example uses the data of Zhangbei County's flexible DC power transmission engineering, and sub-modular structure uses the knot of semi-bridge type submodule Structure, systematic parameter is:Dc bus rated voltage is 500kV, and rated power is 1500MW, and bridge arm inductance is 80mH, Mei Geqiao Arm includes 218 submodule numbers, and submodule electric capacity is 15mF, and submodule rated voltage is 2.294kV.Transformer uses Y0/ △ Bind mode, net side/valve side no-load voltage ratio (l-l, rms) is 525/260kV, and rated impedance perunit value is 15%, rated capacity 1700MVA.It is assumed that each pole transverter provides 450MVar reactive power, i.e., the stable state of each pole to AC during stable state Acceptable operating point is P (1500MW, -450MVar).The present invention is so that failure occurs at positive direct-current bus as an example, such as Fig. 2.
Analyze MMC active power and reactive power operation regional extent:Converter power transformer capacity, bridge arm through-current capability, half Bridge submodule is pressed, submodule capacitor voltage is fluctuated, DC line overload capacity is determined by following formula respectively:P2+Q2< Smax 2
The symmetrical bipolar MMC DC power transmission lines of both-end are used as using overhead line.After monopolar grounding fault is detected, failure Pole MMC transverters are switched to fault traversing control model:The locking immediately of failure pole transverter, and turn on the bypass of half-bridge submodule IGCT, while dc circuit breaker, which is immediately performed, cut-offs operation.After direct fault current decays to zero, failure pole transverter Unblock, is transferred to STATCOM operational mode.
During failure, perfect pole short-time overload under conditions of many limiting factors are considered, failure pole transmission current conversion station Whole rated reactive powers.Meanwhile, during failure, auxiliary voltage u is superimposed on upper and lower bridge arm reference voltagez,Upper and lower bridge arm voltage is:
When DC power transmission line goes free process to terminate, due to using open-wire transmission line, DC side monopolar grounding fault is more For non-permanent failure, therefore this example has carried out voltage twice recovers to attempt.If there is huge surge current stress, direct current breaks Road device is backed off, isolated fault point;If there is not huge surge current stress, failure pole MMC progressively recovers power biography It is defeated, finally it is transferred to stable state control model.Meanwhile, judge whether DC bus current exceedes DC bus current rated value number of times big In presetting excessively stream number of times, if so, then MMC keeps current state, direct-current short circuit device no longer carries out reclosing trial;Otherwise direct current Breaker is backed off, and repeats above step.
Pressed by converter power transformer capacity, bridge arm through-current capability, half-bridge submodule, submodule capacitor voltage is fluctuated, direct current The constraints of circuit overload ability can obtain the operation area of active power and reactive power, as shown in Figure 5.As a result show:MMC Active power and reactive power can range of operation and bridge arm through-current capability, submodule capacitor voltage fluctuation maximum and AC line Loading capability is passed by into positive correlation.The parameter for taking multiple limiting factors during failure is:MMC bridge arms are through-flow, and maximum current capacity is 1.1pu, the maximum allowable stability bandwidth of submodule capacitor voltage is 1.1pu, and DC line overload capacity is 1.2pu, then can obtain such as Active power and reactive power shown in Fig. 6 can operation area scope (shadow region for can operation area), as a result show:Direct current During failure, perfect pole and can run on operating point P2 (1700MW, 0MVar), failure pole can run on operating point P1 (0MW ,- 900MVar).MMC can provide 1700MW active power and 900MVar reactive power during failure.The fault traversing phase Between, by perfecting the active power and the cooperation of reactive power of pole and failure pole, it can not only continue to provide to AC Nominal reactive is supported, and can overcome the disadvantages that the power shortage of failure pole 11.76%.
Assuming that ground short circuit failure, the fault clearance after 450ms occur in 1s for positive direct-current bus.Fig. 7 is based on symmetrical The semi-bridge type MMC simulation results of bipolar main electrical scheme, (A) represents failure pole, and (B) represents to perfect pole.Failure pole DC bus current As shown in Fig. 7 (A2), as a result show:Dc circuit breaker is cut-off after DC Line Fault, and fault current decays to zero.Perfect pole and failure The active power of pole is with shown in reactive power such as Fig. 7 (A3) and Fig. 7 (B3), as a result showing:Transverter can be carried during failure The reactive power of active power and 900MVar for 1700MW.By perfecting pole and failure pole during demonstrating fault traversing Active and reactive power, which coordinates, can continue to provide nominal reactive support to AC, and can overcome the disadvantages that failure pole 11.76% The conclusion of power shortage.Perfect pole upper and lower bridge arm submodule capacitor voltage and six bridge arm currents such as Fig. 7 (B5) and Fig. 7 (B6) institute Show, as a result show:When perfecting pole transverter and running on short-time overload state, submodule capacitor voltage fluctuation percentage is specified 1.11 times of value, MMC bridge arms maximum current is 1.104 times of rated value, is coincide substantially with theory analysis.Perfect pole and failure pole Ac-side current such as Fig. 7 (A4) and Fig. 7 (B4) shown in, as a result show:Whole fault traversing and recovery control, smoothly, quickly, Without impact.
After dc circuit breaker isolated DC failure, go to dissociate through the 300ms times, then carry out reclosing.Due to now, directly Stream failure is not yet eliminated, therefore can produce huge surge current stress.As a result as shown in Fig. 7 (A).As a result show:If System failure unsuccessful reclosing, if being added without surge current Optimal Control Strategy, voltage step and current surge current stress are big; Meanwhile, power and the bridge arm voltage fluctuation of system are also very big, and the safe operation to system brings risk.
Introduce after surge current optimal control, for different damped coefficient R, the surge current stress of system is carried out Contrast simulation.Simulation result is as shown in Figure 8.As a result show:With damped coefficient R increase, dc circuit breaker loses in reclosing Surge current stress caused by after losing is gradually reduced, and this fully demonstrates the validity of proposed optimisation strategy.However, entering one Step is it can be found that with damped coefficient R increase, the inhibition to surge current is gradually reduced.This is due to semi-bridge type MMC Bridge arm voltage output area be:0≤uarm≤Udc.With damped coefficient R increase, auxiliary voltage uzGradually increase so that The reference voltage of upper and lower bridge arm reaches the limit of fan-out capability, so that the inhibition to surge current is reduced.
Dc circuit breaker detects after surge current isolated DC failure again.Again pass by 300ms goes the free time Afterwards, second of trial of dc circuit breaker carries out reclosing, and final system is successfully recovered.
As it will be easily appreciated by one skilled in the art that the foregoing is merely illustrative of the preferred embodiments of the present invention, it is not used to The limitation present invention, any modifications, equivalent substitutions and improvements made within the spirit and principles of the invention etc., it all should include Within protection scope of the present invention.

Claims (8)

1. a kind of symmetrical bipolar MMC DC sides monopolar grounding fault is passed through and restoration methods, it is characterised in that including following step Suddenly:
(1) differentiate whether MMC DC sides occur monopolar grounding fault:
It is then to perform following act:Failure pole MMC block signals are sent, make IGBT in all half-bridge submodules of failure pole MMC complete Portion is turned off, to block the discharge path of the half-bridge submodule electric capacity;The bypass turn on thyristors signal of half-bridge submodule is sent, Antiparallel diode in the half-bridge submodule is bypassed, to protect anti-paralleled diode;To the dc circuit breaker hair of failure pole Go out open command, block the short circuit path of AC network;Act above in no particular order;The MMC refers to the modular multilevel change of current One pole of DC side earth fault extremely occurs for device, the failure;Go to step (2);
Otherwise system keeps stable state control model, goes to step (6);
(2) after bus direct fault current decays to zero, failure pole MMC unlocking signals are sent, failure pole MMC is transferred to nothing Work(compensates STATCOM (Static Synchronous Compensator) operational mode, and idle branch is persistently provided to AC Support;
(3) when failure pole dc bus goes free process to terminate, that is, when recovering dielectric level, to the direct current interruption on dc bus Device sends reclosing signal;
(4) whether the surge current stress on the dc bus of Judging fault pole is excessive;
It is to show that failure is not eliminated, is sent to the dc circuit breaker on the dc bus of the failure pole and back off signal, Isolated fault point;Go to step (5);
Otherwise show that temporary fault has been eliminated, send progressively recovery power transmission signal to failure pole MMC, it is transferred to surely State control model, goes to step (6);
(5) judge whether the dc circuit breaker is more than default excessively stream number of times by the number of times of electric current overrate;It is to make MMC keeps STATCOM operational modes, and direct-current short circuit device no longer carries out reclosing trial, gone to step (6);Otherwise go to step (1); The presetting excessively stream number of times takes 2~3 times;
(6) terminate.
2. fault traversing according to claim 1 and restoration methods, it is characterised in that the step (2) includes following son Step:
(2-1) is pressed according to converter power transformer capacity, MMC bridge arms through-current capability, half-bridge submodule, submodule capacitor voltage fluctuation With DC line overload capacity constraints, the active power for perfecting pole MMC and reactive power operation region are determined;At this In active power and reactive power operation region, adjustment perfects pole MMC stable operations operating point, it is run on short-time overload, With transmitting active power as much as possible, so as to make up power shortage caused by monopolar grounding fault;
Twice of rated reactive power signal of transmission during (2-2) is emitted in failure to the failure pole MMC, makes described to perfect pole The rated reactive power of MMC required transmission in the steady state is undertaken by failure pole MMC.
3. fault traversing according to claim 2 and restoration methods, it is characterised in that changed described in the step (2-1) The restrictive condition of convertor transformer capacity is:
The transmission capacity S of active-power P, reactive power Q and converter power transformer that transverter is transmittedmaxMeet:P2+Q2< Smax 2
Wherein, active-power P, reactive power Q are respectively from points of common connection PCC (Point of Common Coupling) streams To MMC active and reactive power, SmaxFor the maximum transfer capacity of converter power transformer.
4. fault traversing according to claim 2 and restoration methods, it is characterised in that MMC described in the step (2-1) The restrictive condition of bridge arm through-current capability is:
Each bridge arm current is met:
Wherein, IlimFor the maximum current capacity of each IGBT in submodule, UdcFor single MMC DC bus-bar voltage, UsmFor exchange Busbar voltage amplitude;Rectification direction is positive direction.
5. fault traversing according to claim 2 and restoration methods, it is characterised in that each half-bridge in the step (2-1) The restrictive condition that submodule is pressed is:
The DC component of each bridge arm current is necessarily less than AC compounent;I.e. active-power P and reactive power Q are met:
6. fault traversing according to claim 2 and restoration methods, it is characterised in that voltage fluctuation of capacitor in each submodule Restrictive condition be:
During MMC steady-state operations, voltage fluctuation of capacitor no more than the permitted maximum range of submodule, i.e.,:
<mrow> <mfrac> <msqrt> <mrow> <msup> <mi>P</mi> <mn>2</mn> </msup> <mo>+</mo> <msup> <mrow> <mo>(</mo> <mi>Q</mi> <mo>+</mo> <mfrac> <mrow> <mn>2</mn> <mrow> <mo>(</mo> <msup> <mi>P</mi> <mn>2</mn> </msup> <mo>+</mo> <msup> <mi>Q</mi> <mn>2</mn> </msup> <mo>)</mo> </mrow> </mrow> <mrow> <mn>9</mn> <msubsup> <mi>U</mi> <mrow> <mi>s</mi> <mi>m</mi> </mrow> <mn>2</mn> </msubsup> </mrow> </mfrac> <msub> <mi>X</mi> <mi>L</mi> </msub> <mo>)</mo> </mrow> <mn>2</mn> </msup> </mrow> </msqrt> <mrow> <mn>3</mn> <msubsup> <mi>kNC&amp;omega;U</mi> <mi>c</mi> <mn>2</mn> </msubsup> </mrow> </mfrac> <msup> <mrow> <mo>&amp;lsqb;</mo> <mn>1</mn> <mo>-</mo> <mfrac> <mrow> <msup> <mi>k</mi> <mn>2</mn> </msup> <msup> <mi>P</mi> <mn>2</mn> </msup> </mrow> <mrow> <mn>4</mn> <mrow> <mo>(</mo> <msup> <mi>P</mi> <mn>2</mn> </msup> <mo>+</mo> <msup> <mrow> <mo>(</mo> <mrow> <mi>Q</mi> <mo>+</mo> <mfrac> <mrow> <mn>2</mn> <mrow> <mo>(</mo> <msup> <mi>P</mi> <mn>2</mn> </msup> <mo>+</mo> <msup> <mi>Q</mi> <mn>2</mn> </msup> <mo>)</mo> </mrow> </mrow> <mrow> <mn>9</mn> <msubsup> <mi>U</mi> <mrow> <mi>s</mi> <mi>m</mi> </mrow> <mn>2</mn> </msubsup> </mrow> </mfrac> <msub> <mi>X</mi> <mi>L</mi> </msub> </mrow> <mo>)</mo> </mrow> <mn>2</mn> </msup> <mo>)</mo> </mrow> </mrow> </mfrac> <mo>&amp;rsqb;</mo> </mrow> <mfrac> <mn>3</mn> <mn>2</mn> </mfrac> </msup> <mo>&amp;le;</mo> <msub> <mi>&amp;epsiv;</mi> <mrow> <mi>m</mi> <mi>a</mi> <mi>x</mi> </mrow> </msub> <mo>;</mo> </mrow>
Wherein, N is submodule quantity, and C is submodule capacitance, UcFor submodule rated voltage, k is built-in potential modulation ratio, submodule Block voltage fluctuation of capacitor percentageIts maximum is εmax.What transverter was transmitted Reactive power QcBy the difference of Q and AC equivalent inductance the L reactive power consumedI.e.XLFor the induction reactance X of AC equivalent inductanceL=ω L, ω are angular frequency.
7. fault traversing according to claim 2 and restoration methods, it is characterised in that straight described in the step (2-1) Flow Line overload capacity is met:
The short-time overload capacity limit of DC current no more than DC line, i.e.,
Wherein, idcFor DC bus current, idc_maxFor the DC line short-time overload capacity limit.
8. fault traversing according to claim 2 and restoration methods, it is characterised in that the step (2-1), step (2- 2) after, following steps are also performed:
(2-3) is superimposed auxiliary voltage on the upper and lower bridge arm reference voltages of MMCMake the upper and lower bridge arm voltages of MMC For:The superposition auxiliary voltage reduces the climbing of surge current, with The risk that the current surge stress for avoiding transverter excessive caused by unsuccessful reclosing is brought to system safety operation;
Wherein, δ is PCC point built-in potentials evRelative to ac bus voltage usPhase difference, idcIt is (whole for failure DC bus current Stream direction is positive direction),For DC current reference value, R (R>0) it is damped coefficient, up_upFor bridge arm voltage on MMC, up_down For bridge arm voltage under MMC;If dc circuit breaker reclosing success, due to the presence of the flat ripple reactance of direct current, idcIt is not in wave Gush electric current, therefore cut-off stream current reference valueIf dc circuit breaker unsuccessful reclosing, surge current idcIt is rapid to rise.
CN201710199650.7A 2017-03-30 2017-03-30 A kind of symmetrical bipolar MMC DC side monopolar grounding fault passes through and restoration methods Active CN107069679B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710199650.7A CN107069679B (en) 2017-03-30 2017-03-30 A kind of symmetrical bipolar MMC DC side monopolar grounding fault passes through and restoration methods

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710199650.7A CN107069679B (en) 2017-03-30 2017-03-30 A kind of symmetrical bipolar MMC DC side monopolar grounding fault passes through and restoration methods

Publications (2)

Publication Number Publication Date
CN107069679A true CN107069679A (en) 2017-08-18
CN107069679B CN107069679B (en) 2018-12-28

Family

ID=59620902

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710199650.7A Active CN107069679B (en) 2017-03-30 2017-03-30 A kind of symmetrical bipolar MMC DC side monopolar grounding fault passes through and restoration methods

Country Status (1)

Country Link
CN (1) CN107069679B (en)

Cited By (26)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107706894A (en) * 2017-11-15 2018-02-16 国家电网公司 A kind of monopole fault isolation system of true bipolar flexible DC transmission engineering
CN108226728A (en) * 2018-01-30 2018-06-29 深圳供电局有限公司 Device and method for monitoring insulation level of current converter and direct-current bus on line
CN108306341A (en) * 2017-12-21 2018-07-20 中国电力科学研究院有限公司 A kind of flexible direct current power grid wind transmitting system fault ride-through method and system
CN108400575A (en) * 2018-03-19 2018-08-14 西安交通大学 The DC line fault guard method of characteristic signal is injected based on transverter
CN108539796A (en) * 2018-05-31 2018-09-14 华中科技大学 Fault ride-through and energy dissipation control method for wind power bipolar flexible direct-current power grid
CN108551161A (en) * 2018-03-20 2018-09-18 西安交通大学 Utilize the transverter DC line fault guard method that actively injection and traveling wave couple
CN108649539A (en) * 2018-04-23 2018-10-12 天津大学 AC/DC interconnected system failure sorted cutting method based on VSC
CN108711876A (en) * 2018-06-07 2018-10-26 重庆大学 A kind of enhancing direct-current short circuit fault traversing control method suitable for modularization multi-level converter
CN108899880A (en) * 2018-05-31 2018-11-27 全球能源互联网研究院有限公司 A kind of power distribution network partition protecting configuration system based on flexible multimode switch
CN109347134A (en) * 2018-11-09 2019-02-15 国家电网有限公司 Bipolar flexible direct-current power grid polar line electric main wiring system and online maintenance method
CN109546679A (en) * 2018-11-29 2019-03-29 东南大学 Straightening stream collects system and the bipolar short trouble traversing method of medium voltage side in photovoltaic
CN109861192A (en) * 2018-12-17 2019-06-07 华中科技大学 A kind of flexible direct current inverter direct fault current suppressing method and its application
CN110470947A (en) * 2019-08-15 2019-11-19 天津大学 A kind of ground electrode circuit fault distance-finding method suitable for MMC direct current system
CN110797903A (en) * 2019-12-05 2020-02-14 国网江苏省电力有限公司扬州供电分公司 Rapid fault recovery method for flexible direct-current power distribution network of energy storage built-in converter
CN110850237A (en) * 2019-12-03 2020-02-28 西安交通大学 Direct current single-end-quantity fault positioning system and method based on active detection
CN110994674A (en) * 2019-11-27 2020-04-10 湖南大学 Power electronic transformer fault ride-through method based on photovoltaic power supply support
CN111507004A (en) * 2020-04-20 2020-08-07 云南电网有限责任公司 Method for evaluating maximum transmission capability of direct current tie line
CN112838578A (en) * 2019-11-25 2021-05-25 南京南瑞继保电气有限公司 Rapid recovery system for DC fault of half-bridge flexible DC converter and control method
CN112952890A (en) * 2021-03-15 2021-06-11 南方电网科学研究院有限责任公司 Short-circuit protection method and device for bridge arm reactor of flexible direct-current power transmission system
CN112952777A (en) * 2021-03-19 2021-06-11 四川大学 Mixed cascade type direct current fault ride-through system based on fault current limiter and control method
CN113078619A (en) * 2021-04-12 2021-07-06 中国矿业大学 Rapid protection method for flexible direct-current power grid
CN114221384A (en) * 2021-12-17 2022-03-22 华中科技大学 Fault-tolerant operation networking control method and device of offshore wind power system
CN114336551A (en) * 2022-01-14 2022-04-12 贵州大学 Flexible direct current transmission system fault protection system based on MMC
CN114498576A (en) * 2021-12-21 2022-05-13 西南交通大学 MMC-based run-through flexible traction substation and protection configuration method thereof
CN115825539A (en) * 2022-10-17 2023-03-21 盛东如东海上风力发电有限责任公司 Voltage and current determination method and system for wind power grid-connected two-phase ground fault
CN117559567A (en) * 2024-01-11 2024-02-13 西安西电电力***有限公司 Control method and device of multiport energy router

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102611096A (en) * 2012-03-13 2012-07-25 浙江大学 Bipolar direct current power transmission system with direct current failure self-elimination capacity
WO2013185825A1 (en) * 2012-06-14 2013-12-19 Abb Technology Ltd Multiline hvdc station with mmc and csc inputs
CN103701145A (en) * 2014-01-02 2014-04-02 浙江大学 Mixed MMC-based mixed direct current power transmission system
CN104300569A (en) * 2014-09-29 2015-01-21 华中科技大学 Short-circuit fault ride-through and recovery method for direct current side of HVDC on basis of mixed type MMC
CN105048488A (en) * 2015-09-01 2015-11-11 华中科技大学 Flexible DC network DC short-circuit fault ride through method

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102611096A (en) * 2012-03-13 2012-07-25 浙江大学 Bipolar direct current power transmission system with direct current failure self-elimination capacity
WO2013185825A1 (en) * 2012-06-14 2013-12-19 Abb Technology Ltd Multiline hvdc station with mmc and csc inputs
CN103701145A (en) * 2014-01-02 2014-04-02 浙江大学 Mixed MMC-based mixed direct current power transmission system
CN104300569A (en) * 2014-09-29 2015-01-21 华中科技大学 Short-circuit fault ride-through and recovery method for direct current side of HVDC on basis of mixed type MMC
CN105048488A (en) * 2015-09-01 2015-11-11 华中科技大学 Flexible DC network DC short-circuit fault ride through method

Cited By (41)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107706894A (en) * 2017-11-15 2018-02-16 国家电网公司 A kind of monopole fault isolation system of true bipolar flexible DC transmission engineering
CN107706894B (en) * 2017-11-15 2023-08-15 国家电网公司 Monopole fault isolation system of true bipolar flexible direct current transmission project
CN108306341A (en) * 2017-12-21 2018-07-20 中国电力科学研究院有限公司 A kind of flexible direct current power grid wind transmitting system fault ride-through method and system
CN108226728A (en) * 2018-01-30 2018-06-29 深圳供电局有限公司 Device and method for monitoring insulation level of current converter and direct-current bus on line
CN108400575A (en) * 2018-03-19 2018-08-14 西安交通大学 The DC line fault guard method of characteristic signal is injected based on transverter
CN108551161A (en) * 2018-03-20 2018-09-18 西安交通大学 Utilize the transverter DC line fault guard method that actively injection and traveling wave couple
CN108649539B (en) * 2018-04-23 2019-07-30 天津大学 AC/DC interconnected system failure sorted cutting method based on VSC
CN108649539A (en) * 2018-04-23 2018-10-12 天津大学 AC/DC interconnected system failure sorted cutting method based on VSC
CN108539796B (en) * 2018-05-31 2023-08-25 华中科技大学 Fault ride-through and energy dissipation control method for wind power bipolar flexible direct current power grid
CN108899880A (en) * 2018-05-31 2018-11-27 全球能源互联网研究院有限公司 A kind of power distribution network partition protecting configuration system based on flexible multimode switch
CN108539796A (en) * 2018-05-31 2018-09-14 华中科技大学 Fault ride-through and energy dissipation control method for wind power bipolar flexible direct-current power grid
CN108711876A (en) * 2018-06-07 2018-10-26 重庆大学 A kind of enhancing direct-current short circuit fault traversing control method suitable for modularization multi-level converter
CN108711876B (en) * 2018-06-07 2020-06-23 重庆大学 Direct-current short-circuit fault ride-through control method of modular multilevel converter
CN109347134B (en) * 2018-11-09 2021-10-22 国家电网有限公司 Bipolar flexible direct-current power grid polar line electric main wiring system and online maintenance method
CN109347134A (en) * 2018-11-09 2019-02-15 国家电网有限公司 Bipolar flexible direct-current power grid polar line electric main wiring system and online maintenance method
CN109546679A (en) * 2018-11-29 2019-03-29 东南大学 Straightening stream collects system and the bipolar short trouble traversing method of medium voltage side in photovoltaic
CN109546679B (en) * 2018-11-29 2023-11-03 东南大学 Photovoltaic medium-voltage direct current collection system and medium-voltage side bipolar short-circuit fault ride-through method
CN109861192A (en) * 2018-12-17 2019-06-07 华中科技大学 A kind of flexible direct current inverter direct fault current suppressing method and its application
CN110470947B (en) * 2019-08-15 2021-08-31 天津大学 Grounding electrode line fault distance measurement method suitable for MMC direct current system
CN110470947A (en) * 2019-08-15 2019-11-19 天津大学 A kind of ground electrode circuit fault distance-finding method suitable for MMC direct current system
CN112838578B (en) * 2019-11-25 2022-07-22 南京南瑞继保电气有限公司 Rapid recovery system for DC fault of half-bridge flexible DC converter and control method
CN112838578A (en) * 2019-11-25 2021-05-25 南京南瑞继保电气有限公司 Rapid recovery system for DC fault of half-bridge flexible DC converter and control method
CN110994674B (en) * 2019-11-27 2021-03-23 湖南大学 Power electronic transformer fault ride-through method based on photovoltaic power supply support
CN110994674A (en) * 2019-11-27 2020-04-10 湖南大学 Power electronic transformer fault ride-through method based on photovoltaic power supply support
CN110850237B (en) * 2019-12-03 2020-10-27 西安交通大学 Direct current single-end-quantity fault positioning system and method based on active detection
CN110850237A (en) * 2019-12-03 2020-02-28 西安交通大学 Direct current single-end-quantity fault positioning system and method based on active detection
CN110797903B (en) * 2019-12-05 2021-09-24 国网江苏省电力有限公司扬州供电分公司 Rapid fault recovery method for flexible direct-current power distribution network of energy storage built-in converter
CN110797903A (en) * 2019-12-05 2020-02-14 国网江苏省电力有限公司扬州供电分公司 Rapid fault recovery method for flexible direct-current power distribution network of energy storage built-in converter
CN111507004A (en) * 2020-04-20 2020-08-07 云南电网有限责任公司 Method for evaluating maximum transmission capability of direct current tie line
CN111507004B (en) * 2020-04-20 2023-08-08 云南电网有限责任公司 Evaluation method for maximum transmission capacity of direct-current tie line
CN112952890A (en) * 2021-03-15 2021-06-11 南方电网科学研究院有限责任公司 Short-circuit protection method and device for bridge arm reactor of flexible direct-current power transmission system
CN112952777B (en) * 2021-03-19 2021-09-21 四川大学 Mixed cascade type direct current fault ride-through system based on fault current limiter and control method
CN112952777A (en) * 2021-03-19 2021-06-11 四川大学 Mixed cascade type direct current fault ride-through system based on fault current limiter and control method
CN113078619A (en) * 2021-04-12 2021-07-06 中国矿业大学 Rapid protection method for flexible direct-current power grid
CN114221384B (en) * 2021-12-17 2023-08-25 华中科技大学 Fault-tolerant operation networking control method and device for offshore wind power system
CN114221384A (en) * 2021-12-17 2022-03-22 华中科技大学 Fault-tolerant operation networking control method and device of offshore wind power system
CN114498576A (en) * 2021-12-21 2022-05-13 西南交通大学 MMC-based run-through flexible traction substation and protection configuration method thereof
CN114336551A (en) * 2022-01-14 2022-04-12 贵州大学 Flexible direct current transmission system fault protection system based on MMC
CN115825539A (en) * 2022-10-17 2023-03-21 盛东如东海上风力发电有限责任公司 Voltage and current determination method and system for wind power grid-connected two-phase ground fault
CN117559567A (en) * 2024-01-11 2024-02-13 西安西电电力***有限公司 Control method and device of multiport energy router
CN117559567B (en) * 2024-01-11 2024-04-26 西安西电电力***有限公司 Control method and device of multiport energy router

Also Published As

Publication number Publication date
CN107069679B (en) 2018-12-28

Similar Documents

Publication Publication Date Title
CN107069679B (en) A kind of symmetrical bipolar MMC DC side monopolar grounding fault passes through and restoration methods
Rao et al. Key technologies of ultra-high voltage hybrid LCC-VSC MTDC systems
CN105162155B (en) A kind of series hybrid bipolar direct current transmission system with DC Line Fault ride-through capability
CN109038658B (en) Open sea wind power flexible direct current sending-out system and onshore alternating current single-phase earth fault ride-through method
Rao et al. Design aspects of hybrid HVDC system
CN103219738B (en) Direct current transmission system based on three-pole type structure
CN106655237B (en) The fault ride-through method of multiterminal flexible high pressure DC transmission system DC monopole ground connection
CN111525826B (en) Modular capacitor phase-change current converter and method
CN109950916B (en) UPFC fault transition method based on mixed impedance
Xu et al. Modular multilevel converter with embedded energy storage for bidirectional fault isolation
CN111769530A (en) Flexible direct-current transmission fault current cooperative inhibition method for large-scale wind power access
WO2021196563A1 (en) Resistor-type sub-module mixed-type mmc and direct-current fault processing policy therefor
WO2023134225A1 (en) Low-frequency power transmission system and control mode therefor
CN108400701A (en) A kind of flexible direct current power transmission system
CN111276995A (en) Power balancing device for offshore wind power flexible direct-delivery system and control method
CN208063039U (en) A kind of flexible direct current power transmission system
CN108242896A (en) Transverter, DC side ground connection tertiary structure flexible direct current system and control method
Li et al. Study on main circuit configuration and control modes for a new LCC-MMC hybrid HVDC system
CN113422369A (en) Optimized operation and control method of fault flexible arc extinction and power quality regulation and control composite system
Han et al. A three-terminal hybrid HVDC system based on LCC and hybrid MMC with DC fault clearance capability
Han et al. Research on grounding mode of AC-AC converter system
Zhu et al. New VSC-HVDC Solution with Overhead Transmission Line for BC-SIN Project
CN211744055U (en) Power balancing device suitable for offshore wind power flexible direct current sending-out system
Liu et al. Research on Fault Transient Characteristics and Arrester Arrangement of Multi-terminal Ring-shaped MVDC Distribution Network
CN117154665B (en) Deep overvoltage suppression method for symmetrical monopole flexible-direct system

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant