CN107062234A - A kind of excellent garbage disposal furnace of pre-heat effect - Google Patents

A kind of excellent garbage disposal furnace of pre-heat effect Download PDF

Info

Publication number
CN107062234A
CN107062234A CN201710023081.0A CN201710023081A CN107062234A CN 107062234 A CN107062234 A CN 107062234A CN 201710023081 A CN201710023081 A CN 201710023081A CN 107062234 A CN107062234 A CN 107062234A
Authority
CN
China
Prior art keywords
chamber
furnace
furnace chamber
auxiliary
pipe
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201710023081.0A
Other languages
Chinese (zh)
Inventor
曹文波
张文锐
魏凌敏
舒志强
唐武才
李启仁
李文龙
郎志中
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Anhui Weiming Dinghe Environmental Protection Co Ltd
Original Assignee
Anhui Weiming Dinghe Environmental Protection Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Anhui Weiming Dinghe Environmental Protection Co Ltd filed Critical Anhui Weiming Dinghe Environmental Protection Co Ltd
Priority to CN201710023081.0A priority Critical patent/CN107062234A/en
Publication of CN107062234A publication Critical patent/CN107062234A/en
Pending legal-status Critical Current

Links

Classifications

    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F23COMBUSTION APPARATUS; COMBUSTION PROCESSES
    • F23GCREMATION FURNACES; CONSUMING WASTE PRODUCTS BY COMBUSTION
    • F23G5/00Incineration of waste; Incinerator constructions; Details, accessories or control therefor
    • F23G5/02Incineration of waste; Incinerator constructions; Details, accessories or control therefor with pretreatment
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F23COMBUSTION APPARATUS; COMBUSTION PROCESSES
    • F23GCREMATION FURNACES; CONSUMING WASTE PRODUCTS BY COMBUSTION
    • F23G5/00Incineration of waste; Incinerator constructions; Details, accessories or control therefor
    • F23G5/44Details; Accessories
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F23COMBUSTION APPARATUS; COMBUSTION PROCESSES
    • F23GCREMATION FURNACES; CONSUMING WASTE PRODUCTS BY COMBUSTION
    • F23G2203/00Furnace arrangements
    • F23G2203/80Furnaces with other means for moving the waste through the combustion zone
    • F23G2203/801Furnaces with other means for moving the waste through the combustion zone using conveyors
    • F23G2203/8013Screw conveyors

Landscapes

  • Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Processing Of Solid Wastes (AREA)

Abstract

The present invention proposes a kind of excellent garbage disposal furnace of pre-heat effect, including main furnace body, secondary body of heater, the first auxiliary body and the second auxiliary body;Provided with big furnace chamber, circulating air adapter cavity, the first tail gas caching chamber and the second tail gas caching chamber in main furnace body, main stove feeding gate, air entraining pipe, the first slag-draining device and downtake pipe are installed on main furnace body;Provided with the small furnace chamber being sequentially communicated, auxiliary furnace chamber and the 3rd tail gas caching chamber in secondary body of heater, secondary body of heater feeding gate, interior circulation airway tube and the second slag-draining device are installed on secondary body of heater;First auxiliary body include material pusher, second exhaust pipe, the first oxygen supplying tube, the second oxygen supplying tube, the 3rd oxygen supplying tube, communicating pipe, except wet tank and multiple preheating servicing units;Preheating servicing unit includes heat conducting pipe, isolating bar and catch.The present invention is easy to use, effectively make use of garbage pre-heating excellent effect in the energy of garbage disposal, and big furnace chamber.

Description

A kind of excellent garbage disposal furnace of pre-heat effect
Technical field
The present invention relates to field of Environment Protection, and in particular to a kind of excellent garbage disposal furnace of pre-heat effect.
Background technology
Using landfill more than the method for current China's processing rubbish, because China's house refuse has calorific value low, aqueous many etc. Feature, handles rubbish by the way of landfill, and in addition to producing niff during landfill, the percolate of generation is The problem of garbage loading embeading technology, the generation severe contamination underground water of percolate endangers human survival.The product of heat treatment mode holds It is disposable, do not easily cause in environmental pollution, but actual mechanical process, because garbage treatment quantity is larger, rubbish species is more, therefore Garbage disposal effect is poor, the serious situation of energy dissipation.
The content of the invention
The technical problem existed based on background technology, the present invention proposes a kind of excellent garbage disposal furnace of pre-heat effect.
A kind of excellent garbage disposal furnace of pre-heat effect proposed by the present invention, including main furnace body, secondary body of heater, the first auxiliary machine Structure and the second auxiliary body;
Provided with big furnace chamber, circulating air adapter cavity, the first tail gas caching chamber and the second tail gas caching chamber, main furnace body in main furnace body It is provided with big furnace chamber top and the big furnace chamber top of connection and circulating air adapter cavity is installed in main stove feeding gate, main furnace body Air entraining pipe, main furnace body is provided with the first slag-draining device, main furnace body positioned at big furnace chamber bottom is provided with connection the second tail gas caching The downtake pipe of chamber;
Provided with the small furnace chamber being sequentially communicated, auxiliary furnace chamber and the 3rd tail gas caching chamber, small furnace chamber bottom connection in secondary body of heater Furnace chamber top is aided in, secondary body of heater, which is located to be provided with secondary body of heater feeding gate, secondary body of heater at small furnace chamber top, is provided with connection port Chamber top and the interior circulation airway tube of bottom;Secondary body of heater, which is located at the portion of auxiliary furnace bottom of chamber, is provided with the second slag-draining device;
First auxiliary body includes material pusher, second exhaust pipe, the first oxygen supplying tube, the second oxygen supplying tube, the 3rd confession Oxygen pipe, communicating pipe, except wet tank and multiple preheating servicing units, material pusher is arranged on port bottom of chamber portion, the second deslagging dress Put installed in auxiliary furnace bottom of chamber portion, second exhaust pipe first end is connected with the 3rd tail gas caching chamber, the end of second exhaust pipe second and First tail gas caching chamber connection, the first oxygen supplying tube first end is connected with big furnace chamber bottom, and the second oxygen supplying tube first end and the 3rd is supplied Oxygen pipe first end is respectively communicated with small furnace chamber bottom and auxiliary furnace chamber bottom;Communicating pipe is connected under circulating air adapter cavity and small furnace chamber Portion, except air inlet pipe and escape pipe is provided with wet tank, air inlet pipe and escape pipe are respectively communicated with circulating air adapter cavity and big furnace chamber;
Preheating servicing unit includes heat conducting pipe, isolating bar and catch, and isolating bar is axially arranged along heat conducting pipe, and isolating bar will be led Inside heat pipe through hole is separated to form the first flow-guiding channel and the second flow-guiding channel, and the second flow-guiding channel inwall scribbles thermal insulation layer, gear Piece is rotatably arranged on isolating bar, and catch, which is rotated, can be such that the first flow-guiding channel changes at catch with the extraneous area that leads in succession Become, catch, which is rotated, can be such that the second flow-guiding channel changes at catch with the extraneous area that leads in succession.
Preferably, the first flow-guiding channel and the second flow-guiding channel section are semicircle, and catch is semicircle, the catch center of circle On heat conducting pipe axis.
Preferably, preheating servicing unit is from top to bottom set gradually, and heat conducting pipe axis is parallel to each other.
Preferably, material pusher includes auxiliary frame and the first helical blade, and auxiliary frame is located at port with auxiliary furnace chamber The relative both sides of chamber, the first helical blade first end is rotatably connected auxiliary frame, and first the second end of helical blade is by port bottom of chamber Portion is passed through, and extends to auxiliary furnace intracavitary.
Preferably, the second slag-draining device includes storing up miscellaneous frame, rotary shaft and at least one second helical blade, stores up and is set in miscellaneous frame There is the miscellaneous chamber of storage, store up miscellaneous chamber and connected with auxiliary furnace chamber, rotary shaft may be rotatably mounted at the miscellaneous intracavitary of storage, the second helical blade, which is arranged on, to be turned On moving axis, store up miscellaneous chamber and be located at the second helical blade provided with the impurity discharging port of at least one.
Preferably, the second helical blade is provided with two, two second helical blade hands of spiral on the contrary, and installed in rotation The relative both sides of axle, impurity discharging port is provided with two, and two impurity discharging ports are located at rotary shaft opposite sides.
Rubbish is added to big furnace chamber and port intracavitary by main stove feeding gate and secondary body of heater feeding gate respectively when the present invention is used Rubbish, makes small furnace chamber handle a small amount of rubbish, and the gas that big furnace chamber garbage disposal is produced enters circulating air adapter cavity by air entraining pipe, followed The portion gas of ring gas adapter cavity except wet tank by completing to dehumidify, and another part enters small furnace chamber, at small furnace chamber rubbish Reason amount is few, rubbish easily-controlled reaction conditions, is conducive to improving the effect of rubbish disposed of in its entirety, and the tail gas of secondary body of heater processing can enter Servicing unit is preheated, changes the throughput of the first flow-guiding channel and the second flow-guiding channel by adjusting catch, thus it is possible to vary preheating Servicing unit is the effect of garbage pre-heating.The present invention is easy to use, effectively make use of in the energy of garbage disposal, and big furnace chamber Garbage pre-heating excellent effect.
Brief description of the drawings
Fig. 1 is a kind of excellent garbage disposal furnace main view direction main furnace body perspective view of pre-heat effect proposed by the present invention;
Fig. 2 is a kind of excellent garbage disposal furnace side-looking direction sectional view of pre-heat effect proposed by the present invention;
Fig. 3 is preheating servicing unit sectional view.
Embodiment
Shown in reference picture 1, Fig. 2 and Fig. 3, a kind of excellent garbage disposal furnace of pre-heat effect proposed by the present invention, including master Body of heater 1, secondary body of heater 2, the first auxiliary body and the second auxiliary body;
Provided with big furnace chamber 11, circulating air adapter cavity 12, the first tail gas caching chamber 13 and second tail gas caching chamber in main furnace body 1 14, main furnace body 1, which is located at the big top of furnace chamber 11 to be provided with main stove feeding gate 15, main furnace body 1, to be provided with the big furnace chamber 11 of connection Portion and the air entraining pipe 16 of circulating air adapter cavity 12, main furnace body 1 are provided with the first slag-draining device 17, main stove positioned at the big bottom of furnace chamber 11 The downtake pipe 18 that the second tail gas of connection caches chamber 14 is installed on body 1;
Provided with the small furnace chamber 21, auxiliary furnace chamber 22 and the 3rd tail gas caching chamber 23, small furnace chamber 21 being sequentially communicated in secondary body of heater 2 Bottom connection auxiliary furnace chamber 22 top, secondary body of heater 2, which is located at the small top of furnace chamber 21, is provided with secondary body of heater feeding gate 24, secondary body of heater 2 The interior circulation airway tube 25 for connecting the small top of furnace chamber 21 and bottom is inside installed;Secondary body of heater 2, which is located at auxiliary furnace chamber 22 bottom, pacifies Equipped with the second slag-draining device;
First auxiliary body include material pusher, second exhaust pipe 32, the first oxygen supplying tube 33, the second oxygen supplying tube 34, 3rd oxygen supplying tube 35, communicating pipe 36, except wet tank 37 and multiple preheating servicing units, material pusher is arranged on the small bottom of furnace chamber 21 Portion, the second slag-draining device is arranged on auxiliary furnace chamber 22 bottom, and the first end of second exhaust pipe 32 is connected with the 3rd tail gas caching chamber 23, The end of second exhaust pipe 32 second is connected with the first tail gas caching chamber 13, and the first end of the first oxygen supplying tube 33 connects with the big bottom of furnace chamber 11 Logical, the first end of the second oxygen supplying tube 34 and the first end of the 3rd oxygen supplying tube 35 are respectively communicated with the small bottom of furnace chamber 21 and auxiliary furnace chamber 22 Portion;The connection of communicating pipe 36 circulating air adapter cavity 12 and the small bottom of furnace chamber 21, except being provided with air inlet pipe 371 and escape pipe on wet tank 37 372, air inlet pipe 371 and escape pipe 372 are respectively communicated with circulating air adapter cavity 12 and big furnace chamber 11;
Preheating servicing unit includes heat conducting pipe 381, isolating bar 382 and catch 383, and isolating bar 382 is axial along heat conducting pipe 381 Set, the interior bone of heat conducting pipe 381 is separated to form the first flow-guiding channel and the second flow-guiding channel, the second water conservancy diversion by isolating bar 382 Vias inner walls scribble thermal insulation layer, and catch 383 is rotatably arranged on isolating bar 382, and catch 383, which is rotated, can lead to the first water conservancy diversion Road is located at catch 383 to be changed with the extraneous area that leads in succession, and catch 383, which is rotated, can be such that the second flow-guiding channel is located at catch 383 Change with the extraneous area that leads in succession.
Respectively by main stove feeding gate 15 and secondary body of heater feeding gate 24 to big furnace chamber 11 and small furnace chamber 21 when the present invention is used Interior addition rubbish, makes small furnace chamber 21 handle a small amount of rubbish, and the gas that the big garbage disposal of furnace chamber 11 is produced is entered by air entraining pipe 16 Circulating air adapter cavity 12, the portion gas of circulating air adapter cavity 12 except wet tank 37 by completing to dehumidify, and another part enters small Furnace chamber 21, because the small garbage treatment quantity of furnace chamber 21 is few, rubbish easily-controlled reaction conditions are conducive to improving the effect of rubbish disposed of in its entirety Really, the tail gas that secondary body of heater 2 is handled can enter preheating servicing unit, and the first flow-guiding channel and second is changed by adjusting catch 383 The throughput of flow-guiding channel, thus it is possible to vary preheating servicing unit is the effect of garbage pre-heating.
In present embodiment, the first flow-guiding channel and the second flow-guiding channel section are semicircle, and catch 383 is semicircle Shape, the center of circle of catch 383 is located on the axis of heat conducting pipe 381, simple and convenient to realize the first flow-guiding channel and the ventilation of the second flow-guiding channel The adjustment of effect, preheating servicing unit is from top to bottom set gradually, and the axis of heat conducting pipe 381 is parallel to each other, and is easy to preheating auxiliary dress Garbage pre-heating at different height is set to, is easy to rubbish to carry out oxidation reaction.
In present embodiment, material pusher include the helical blade 312 of auxiliary frame 311 and first, auxiliary frame 311 with it is auxiliary Furnace chamber 22 is helped to be located at the relative both sides of small furnace chamber 21, the first end of the first helical blade 312 is rotatably connected auxiliary frame 311, first The end of helical blade 312 second is passed through by the small bottom of furnace chamber 21, and is extended in auxiliary furnace chamber 22, the feeding of the first helical blade 312 It is stable, and be difficult to block rubbish.
In present embodiment, the second slag-draining device includes storing up miscellaneous frame 261, rotary shaft 262 and at least one second helical-blade Piece 263, is stored up in miscellaneous frame 261 provided with miscellaneous chamber is stored up, and is stored up miscellaneous chamber and is connected with auxiliary furnace chamber 22, it is miscellaneous that rotary shaft 262 may be rotatably mounted at storage Intracavitary, the second helical blade 263 is arranged in rotary shaft 262, is stored up miscellaneous chamber and is located at the second helical blade 263 provided with least one Impurity discharging port, be easy to clinker to be conducive to waste steady to discharge while insulation.
In present embodiment, the second helical blade 263 be provided with two, two hands of spiral of the second helical blade 263 on the contrary, And installed in the relative both sides of rotary shaft 262, impurity discharging port is provided with two, and two impurity discharging ports are located at the opposite sides of rotary shaft 262, can To effectively improve clinker expulsion efficiency.
The foregoing is only a preferred embodiment of the present invention, but protection scope of the present invention be not limited thereto, Any one skilled in the art the invention discloses technical scope in, technique according to the invention scheme and its Inventive concept is subject to equivalent substitution or change, should all be included within the scope of the present invention.

Claims (6)

1. a kind of excellent garbage disposal furnace of pre-heat effect, it is characterised in that:Including main furnace body (1), secondary body of heater (2), first auxiliary Help mechanism and the second auxiliary body;
It is slow provided with big furnace chamber (11), circulating air adapter cavity (12), the first tail gas caching chamber (13) and the second tail gas in main furnace body (1) Chamber (14) is deposited, main furnace body (1), which is located at big furnace chamber (11) top, is provided with main stove feeding gate (15), is provided with main furnace body (1) The air entraining pipe (16) on big furnace chamber (11) top and circulating air adapter cavity (12) is connected, main furnace body (1) is located at big furnace chamber (11) bottom The downtake pipe that connection the second tail gas caching chamber (14) is provided with first slag-draining device (17), main furnace body (1) is installed (18);
Provided with the small furnace chamber (21), auxiliary furnace chamber (22) and the 3rd tail gas caching chamber (23) being sequentially communicated, port in secondary body of heater (2) Chamber (21) bottom connection auxiliary furnace chamber (22) top, secondary body of heater (2), which is located at small furnace chamber (21) top, is provided with secondary body of heater charging The interior circulation airway tube (25) for connecting small furnace chamber (21) top and bottom is installed in door (24), secondary body of heater (2);Secondary body of heater (2) The second slag-draining device is installed at auxiliary furnace chamber (22) bottom;
First auxiliary body includes material pusher, second exhaust pipe (32), the first oxygen supplying tube (33), the second oxygen supplying tube (34), the 3rd oxygen supplying tube (35), communicating pipe (36), except wet tank (37) and multiple preheating servicing units, material pusher is installed In small furnace chamber (21) bottom, the second slag-draining device is arranged on auxiliary furnace chamber (22) bottom, second exhaust pipe (32) first end and the Three tail gas caching chamber (23) connection, the end of second exhaust pipe (32) second is connected with the first tail gas caching chamber (13), the first oxygen supplying tube (33) first end is connected with big furnace chamber (11) bottom, the second oxygen supplying tube (34) first end and the 3rd oxygen supplying tube (35) first end difference Connect small furnace chamber (21) bottom and auxiliary furnace chamber (22) bottom;Communicating pipe (36) connection circulating air adapter cavity (12) and small furnace chamber (21) bottom, except being provided with air inlet pipe (371) and escape pipe (372), air inlet pipe (371) and escape pipe (372) on wet tank (37) It is respectively communicated with circulating air adapter cavity (12) and big furnace chamber (11);
Preheating servicing unit includes heat conducting pipe (381), isolating bar (382) and catch (383), and isolating bar (382) is along heat conducting pipe (381) axially arranged, heat conducting pipe (381) interior bone is separated to form the first flow-guiding channel and the second water conservancy diversion by isolating bar (382) Passage, the second flow-guiding channel inwall scribbles thermal insulation layer, and catch (383) is rotatably arranged on isolating bar (382), catch (383) rotating can be such that the first flow-guiding channel changes positioned at catch (383) place with the extraneous area that leads in succession, and catch (383) rotation can Make the second flow-guiding channel be located at catch (383) place with the extraneous area that in succession leads to change.
2. the excellent garbage disposal furnace of pre-heat effect according to claim 1, it is characterised in that:First flow-guiding channel and Two flow-guiding channel sections are semicircle, and catch (383) is semicircle, and catch (383) center of circle is located at heat conducting pipe (381) axis On.
3. the excellent garbage disposal furnace of pre-heat effect according to claim 1, it is characterised in that:Servicing unit is preheated by upper Set gradually under, heat conducting pipe (381) axis is parallel to each other.
4. the excellent garbage disposal furnace of pre-heat effect according to claim 1, it is characterised in that:Material pusher includes Auxiliary frame (311) and the first helical blade (312), it is relative that auxiliary frame (311) is located at small furnace chamber (21) with auxiliary furnace chamber (22) Both sides, the first helical blade (312) first end is rotatably connected auxiliary frame (311), and the end of the first helical blade (312) second is by small Furnace chamber (21) bottom is passed through, and is extended in auxiliary furnace chamber (22).
5. the excellent garbage disposal furnace of pre-heat effect according to claim 1, it is characterised in that:Second slag-draining device includes Miscellaneous frame (261), rotary shaft (262) and at least one second helical blade (263) are stored up, stores up in miscellaneous frame (261) provided with miscellaneous chamber is stored up, stores up Miscellaneous chamber is connected with auxiliary furnace chamber (22), and rotary shaft (262) may be rotatably mounted at the miscellaneous intracavitary of storage, and the second helical blade (263) is installed In rotary shaft (262), store up miscellaneous chamber and be located at the second helical blade (263) place provided with the impurity discharging port of at least one.
6. the excellent garbage disposal furnace of pre-heat effect according to claim 5, it is characterised in that:Second helical blade (263) be provided with two, two the second helical blade (263) hands of spiral on the contrary, and installed in rotary shaft (262) it is relative two Side, impurity discharging port is provided with two, and two impurity discharging ports are located at rotary shaft (262) opposite sides.
CN201710023081.0A 2017-01-13 2017-01-13 A kind of excellent garbage disposal furnace of pre-heat effect Pending CN107062234A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710023081.0A CN107062234A (en) 2017-01-13 2017-01-13 A kind of excellent garbage disposal furnace of pre-heat effect

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710023081.0A CN107062234A (en) 2017-01-13 2017-01-13 A kind of excellent garbage disposal furnace of pre-heat effect

Publications (1)

Publication Number Publication Date
CN107062234A true CN107062234A (en) 2017-08-18

Family

ID=59598287

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710023081.0A Pending CN107062234A (en) 2017-01-13 2017-01-13 A kind of excellent garbage disposal furnace of pre-heat effect

Country Status (1)

Country Link
CN (1) CN107062234A (en)

Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1286748A (en) * 1998-09-25 2001-03-07 森口桂 Ascending kiln type drying apparatus and furnace equipment with same
CN201262526Y (en) * 2008-06-28 2009-06-24 青岛德固特机械制造有限公司 Diameter-variable tube bundle air preheater
CN101813326A (en) * 2010-04-24 2010-08-25 四川同心门业有限公司 Tunable energy-saving firewood stove
CN103954143A (en) * 2014-05-05 2014-07-30 山东省能源与环境研究院 Bootstrap system for rotary cement kiln
CN204346191U (en) * 2014-12-19 2015-05-20 中冶东方工程技术有限公司 A kind of heating furnace fume extractor
JP2015163833A (en) * 2014-01-28 2015-09-10 株式会社五常 Low-temperature pyrolysis treatment furnace, low-temperature pyrolysis treatment system, and low-temperature pyrolysis treatment method
US20160169509A1 (en) * 2014-12-12 2016-06-16 Infinitus Renewable Energy, LLC Pyrolytic gas processor and tire conversion system therefrom
CN105698192A (en) * 2016-03-21 2016-06-22 安徽未名生物环保有限公司 An inlet control device of garbage incinerator
CN105757677A (en) * 2016-03-21 2016-07-13 安徽未名生物环保有限公司 Intelligent garbage treatment system with multiple gas circulation function
CN205619317U (en) * 2016-03-21 2016-10-05 安徽未名生物环保有限公司 A device for rubbish burning

Patent Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1286748A (en) * 1998-09-25 2001-03-07 森口桂 Ascending kiln type drying apparatus and furnace equipment with same
CN201262526Y (en) * 2008-06-28 2009-06-24 青岛德固特机械制造有限公司 Diameter-variable tube bundle air preheater
CN101813326A (en) * 2010-04-24 2010-08-25 四川同心门业有限公司 Tunable energy-saving firewood stove
JP2015163833A (en) * 2014-01-28 2015-09-10 株式会社五常 Low-temperature pyrolysis treatment furnace, low-temperature pyrolysis treatment system, and low-temperature pyrolysis treatment method
CN103954143A (en) * 2014-05-05 2014-07-30 山东省能源与环境研究院 Bootstrap system for rotary cement kiln
US20160169509A1 (en) * 2014-12-12 2016-06-16 Infinitus Renewable Energy, LLC Pyrolytic gas processor and tire conversion system therefrom
CN204346191U (en) * 2014-12-19 2015-05-20 中冶东方工程技术有限公司 A kind of heating furnace fume extractor
CN105698192A (en) * 2016-03-21 2016-06-22 安徽未名生物环保有限公司 An inlet control device of garbage incinerator
CN105757677A (en) * 2016-03-21 2016-07-13 安徽未名生物环保有限公司 Intelligent garbage treatment system with multiple gas circulation function
CN205619317U (en) * 2016-03-21 2016-10-05 安徽未名生物环保有限公司 A device for rubbish burning

Similar Documents

Publication Publication Date Title
CN103624060B (en) Handle the continuous high temperature oxygen barrier carbonizing plant of application of city life garbage
CN205606589U (en) Mud distillation pyrolysis incinerator
CN106642146A (en) Garbage air drying treatment system and method
CN105805765B (en) A kind of pyrolyzing sludge incinerator
CN205619288U (en) Multi -functional household garbage treating device
CN107062234A (en) A kind of excellent garbage disposal furnace of pre-heat effect
CN112076497B (en) Non-stop production decoloring system based on continuous production of steroid medicament
CN206018654U (en) A kind of thoroughly Disposal System of Mud Burning that burns
CN205046046U (en) Rubbish low treatment temperature device
CN205619344U (en) Energy -efficient household garbage treating device
CN205560779U (en) Pyrolysis incineration equipment
CN205909308U (en) Arrange sediment type sludge incineration system
CN214141594U (en) Microwave catalytic carbonization furnace for waste organic matters
CN105823063B (en) A kind of pyrolysis incineration apparatus
CN211170582U (en) Double-layer roller carbonizing device
CN208841619U (en) A kind of rubber Plasticator with exhaust-gas treatment function
CN206430159U (en) A kind of sufficient garbage disposal furnace of garbage disposal
CN206430117U (en) A kind of practical garbage disposal furnace that function is preheated with oxygen
CN207741114U (en) Vehicular rubbish processing unit
CN206279134U (en) A kind of solid slag recovery type electronic waste pyrolysis installation
CN206783597U (en) A kind of multi-functional successively biaxial fluidized bed cracking stove for being used to handle urban waste
CN206396123U (en) A kind of carbonization device of low temperature preparation charcoal
CN206430146U (en) It is a kind of can oxygen preheating garbage disposal furnace
CN106765124B (en) A kind of garbage disposal furnace
CN205909290U (en) Energy -efficient processing apparatus of mud

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20170818