CN107060800A - A kind of shield-tunneling construction huge stone handling construction method - Google Patents

A kind of shield-tunneling construction huge stone handling construction method Download PDF

Info

Publication number
CN107060800A
CN107060800A CN201710138502.4A CN201710138502A CN107060800A CN 107060800 A CN107060800 A CN 107060800A CN 201710138502 A CN201710138502 A CN 201710138502A CN 107060800 A CN107060800 A CN 107060800A
Authority
CN
China
Prior art keywords
boulder
obstacle
construction
hole
place
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201710138502.4A
Other languages
Chinese (zh)
Inventor
丁仕辉
汪永剑
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guangdong No 2 Hydropower Engineering Co Ltd
Original Assignee
Guangdong No 2 Hydropower Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guangdong No 2 Hydropower Engineering Co Ltd filed Critical Guangdong No 2 Hydropower Engineering Co Ltd
Priority to CN201710138502.4A priority Critical patent/CN107060800A/en
Publication of CN107060800A publication Critical patent/CN107060800A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/12Devices for removing or hauling away excavated material or spoil; Working or loading platforms
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D5/00Lining shafts; Linings therefor
    • E21D5/06Lining shafts; Linings therefor with iron or steel
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/06Making by using a driving shield, i.e. advanced by pushing means bearing against the already placed lining

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Environmental & Geological Engineering (AREA)
  • Mechanical Engineering (AREA)
  • Excavating Of Shafts Or Tunnels (AREA)

Abstract

The invention discloses a kind of shield-tunneling construction huge stone handling construction method, comprise the following steps:The orientation of Construction of Silo is determined according to obstacle boulder;Carry out Construction of Silo and lay steel pile casting;Laterally construction forms the hole in place being located at below obstacle boulder in vertical shaft, formed by the high pressure jer cutting soil body and discharge cutting dregs through vertical shaft, the work completion until place hole is spreaded manuer in holes, obstacle boulder is dropped down onto in hole in place, the hole in place that space is slightly larger than obstacle boulder volume is excavated below obstacle boulder by construction shaft, obstacle boulder is guided to be moved in the hole in place outside tunnel cross-section by the gravity of shield machine or obstacle boulder in itself, shield machine is set to be passed through on original design tunnel axis, abandoning tradition is abolished mode by force to obstacle boulder, obstacle huge stone handling is simple and quick, cost is low, short construction period.

Description

A kind of shield-tunneling construction huge stone handling construction method
Technical field
The present invention relates to tunneling shield technical field of construction, more particularly to a kind of shield-tunneling construction huge stone handling construction method.
Background technology
At present, the construction of the engineerings such as urban subway tunnel, road and rail tunnel, water conservancy water-conveyance tunnel is carried out using shield machine Deng more and more universal, it has the advantages that automaticity is high, speed of application is fast, quality is good, safe.Wherein, soil pressure is put down Weighing apparatus formula shield machine is wider to the adaptability on stratum, is to apply a kind of more type, its operation principle is the knife using shield machine Disk cuts the soil body or rock mass, with the propulsion of shield machine, and the soil that knife cutting gets off enters in the native storehouse of shield machine, passes through spiral transferring The control of the casting such as machine and its casting valve mechanism is sent, matching for soil discharge quantity and shield driving amount is realized, shield driving is formed Keep excavating the stable dynamic equilibrium of face simultaneously, Shield Construction Method Used is smooth.
However, when granitic formation carries out constructing tunnel using shield machine, being frequently encountered " boulder ", (granite is spherical Waste) cause shield machine driving difficult, it is impossible to normal construction.Granite onion weathering thing is a kind of common weathering phenomenon, It is in residual soil and weathered rock formation, because being influenceed the weathering to be formed is uneven to remain by the arrangement of mineral anisotropy and fractured zones Body, due to weathering ball surrounding rock mass, with onion weathering rock mass there is larger gap in intensity itself, often there is soft or hard uneven ground Matter phenomenon, this just easily causes tool damage, results even in cutterhead deformation, causes whole shield machine to be paralysed.
At present, in granitic formation tunneling shield tunneling process, the method for disposal of boulder is run into substantially:Verifying shield In front of structure after " boulder " distributing position and size, according to live periphery human settlement, geology and geomorphology, underground utilities move towards situation, The methods such as surface drilling explosion, punching are broken, manually digging hole is abolished are taken to abolish boulder.
The content of the invention
The technical problems to be solved by the invention are to provide the shield-tunneling construction huge stone handling that a kind of efficiency of construction is high, cost is low Construction method.
To solve the technical scheme that above-mentioned technical problem is used:A kind of shield-tunneling construction huge stone handling construction method, including Following steps:
S1, basis verify size, the position of the residing underground space of obstacle boulder, determine the orientation of Construction of Silo;
S2, progress Construction of Silo reach predetermined well depth, and the steel pile casting that diameter is less than vertical shaft aperture is laid in vertical shaft;
Former slurry coat method in S3, pump drainage steel pile casting, meanwhile, to injection paste mud between steel pile casting and vertical shaft inwall;
S4, the size according to obstacle boulder, the position of the residing underground space, laterally construction is formed positioned at obstacle boulder in vertical shaft The hole in place of lower section, hole in place is formed by the high pressure jer cutting soil body and discharges cutting dregs through vertical shaft, until Place hole is spreaded manuer in holes work completion, and obstacle boulder dropped down onto in hole in place;
S5, to slip casting at original obstacle boulder position and vertical shaft is filled, the steel pile casting in removal shaft.
Beneficial effect:In this shield-tunneling construction huge stone handling construction method, abandoning tradition is abolished by force to obstacle boulder Mode, excavates the hole in place that space is slightly larger than obstacle boulder volume below obstacle boulder by construction shaft, passes through shield The gravity guiding obstacle boulder of machine or obstacle boulder in itself is moved in the hole in place outside tunnel cross-section, shield machine is set in original Passed through on meter tunnel axis, obstacle huge stone handling is simple and quick, cost is low, short construction period.
Brief description of the drawings
The present invention is described further with reference to the accompanying drawings and examples;
Fig. 1 is the structural representation of the embodiment of the present invention.
Embodiment
A kind of reference picture 1, shield-tunneling construction huge stone handling construction method of the invention, comprises the following steps:
S1, size, the position of the residing underground space for verifying using drilling machine obstacle boulder 1, to determine to excavate the lonely stone of obstacle The position and the space of required excavation in hole 2 in place, it is ensured that do not hinder the normal pick of follow-up shield machine after obstacle boulder dropping place Enter;
S2, using Big Diameter Hole Drills earth's surface through designed appropriate location drilling carry out vertical shaft 3 construct, boring procedure uses mud Starch retaining wall pore-forming;
S3, the construction of vertical shaft 3 are reached after design well depth, insert the steel pile casting 4 for being slightly less than the inwall aperture of vertical shaft 3 with well depth equal length, The cat ladder 5 that vertical shaft 3 is passed in and out for staff is welded with steel pile casting 4;
S4, using former slurry coat method in slush pump pump drainage steel pile casting 4, meanwhile, inject cream between steel pile casting 4 and the inwall of vertical shaft 3 Shape mud 6;
After mud is cleaned out in S5, steel pile casting 4, workmen enter vertical shaft 3, by obstacle boulder 1 hole in place 2 it is relevant Parameter, sets up an operation platform below the elevation location in the horizontal hole 7 of processing boulder, carries out the processing horizontal hole 7 of boulder and in place The construction in hole 2;
S6, hole in place 2 carry out cutting excavation using high-pressure water jet, and the high process control in the bottom of hole 2 in place and the horizontal bottom of hole 7 of boulder are high Cheng Xiangtong, the dregs that high pressure jer cutting is excavated is flowed into vertical shaft 3 by the horizontal hole 7 of boulder, and uses slush pump by cutting Outside dregs discharge vertical shaft 3, excavated by the lasting cutting of high-pressure water jet, dregs is constantly discharged outside vertical shaft, until hole is applied Work is completed, obstacle boulder dropping place;
S7, when determining that obstacle boulder 1 is had moved into outside shield tunnel section, to original obstacle boulder position at slip casting and fill Steel pile casting 4 in vertical shaft 3, removal shaft 3, recovers original place looks.
The hole in place 2 that space is slightly larger than obstacle boulder volume is excavated below obstacle boulder 1 by construction shaft, passed through The gravity guiding obstacle boulder 1 of shield machine or obstacle boulder 1 itself is moved in the hole in place 2 outside tunnel cross-section, makes shield Machine is passed through on original design tunnel axis, obstacle boulder 1 is not abolished, to save substantial amounts of human and material resources, wealth Power and the duration for shortening processing boulder.
Embodiments of the present invention are explained in detail above in conjunction with accompanying drawing, but the invention is not restricted to above-mentioned embodiment party Formula, can also be before present inventive concept not be departed from the knowledge that the technical field those of ordinary skill possesses Put that various changes can be made.

Claims (1)

1. a kind of shield-tunneling construction huge stone handling construction method, it is characterised in that comprise the following steps:
S1, basis verify size, the position of the residing underground space of obstacle boulder, determine the orientation of Construction of Silo;
S2, progress Construction of Silo reach predetermined well depth, and the steel pile casting that diameter is less than vertical shaft aperture is laid in vertical shaft;
Former slurry coat method in S3, pump drainage steel pile casting, meanwhile, to injection paste mud between steel pile casting and vertical shaft inwall;
S4, the size according to obstacle boulder, the position of the residing underground space, laterally construction is formed positioned at obstacle boulder in vertical shaft The hole in place of lower section, hole in place is formed by the high pressure jer cutting soil body and discharges cutting dregs through vertical shaft, until Place hole is spreaded manuer in holes work completion, and obstacle boulder dropped down onto in hole in place;
S5, to slip casting at original obstacle boulder position and vertical shaft is filled, the steel pile casting in removal shaft.
CN201710138502.4A 2017-03-09 2017-03-09 A kind of shield-tunneling construction huge stone handling construction method Pending CN107060800A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710138502.4A CN107060800A (en) 2017-03-09 2017-03-09 A kind of shield-tunneling construction huge stone handling construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710138502.4A CN107060800A (en) 2017-03-09 2017-03-09 A kind of shield-tunneling construction huge stone handling construction method

Publications (1)

Publication Number Publication Date
CN107060800A true CN107060800A (en) 2017-08-18

Family

ID=59622517

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710138502.4A Pending CN107060800A (en) 2017-03-09 2017-03-09 A kind of shield-tunneling construction huge stone handling construction method

Country Status (1)

Country Link
CN (1) CN107060800A (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109026039A (en) * 2018-10-19 2018-12-18 深圳市工勘岩土集团有限公司 Subway tunnel shield tunnels boulder deep hole blasting and pre-processes construction method
CN109372526A (en) * 2018-11-12 2019-02-22 中铁工程装备集团有限公司 The novel balancing earth-pressure shielding machine of foreign matter obstacle can be passed through
CN109441454A (en) * 2018-09-11 2019-03-08 广东水电二局股份有限公司 A kind of construction method of underground lonestone reception room
CN109505614A (en) * 2019-01-09 2019-03-22 海南大学 A kind of shield machine directly promotes the construction method by boulder
CN110578524A (en) * 2019-08-27 2019-12-17 中交第二航务工程局有限公司 Boulder treatment construction method for dense drilling and crushing in shield region
CN114837681A (en) * 2022-06-07 2022-08-02 江苏旭睿重工科技有限公司 Quick stone removing device for soil bin of shield machine and construction method thereof

Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH08254094A (en) * 1995-03-15 1996-10-01 Fujita Corp Boulder removing method for jacking method
CN201933510U (en) * 2011-03-14 2011-08-17 中国水电顾问集团成都勘测设计研究院 Outlet shaft structure of underground factories in hydroelectric engineering
CN102518442A (en) * 2011-12-14 2012-06-27 中铁十二局集团第二工程有限公司 Method for processing isolated stone groups in shield excavation karren section
CN103032071A (en) * 2012-12-09 2013-04-10 中铁十二局集团有限公司 Shield receiving forward-shift construction method of boulder group open excavation and embedment mutation space
CN103075161A (en) * 2013-01-16 2013-05-01 中铁隧道集团有限公司 Quick underground obstacle clearing method for slurry shield construction
CN103790594A (en) * 2014-02-26 2014-05-14 中铁一局集团有限公司 Method for exploring and processing interior of boulder hole in front for shield method construction
CN103924980A (en) * 2014-04-24 2014-07-16 上海隧道工程股份有限公司 Obstacle removing construction method
JP2015074957A (en) * 2013-10-11 2015-04-20 鹿島建設株式会社 Tunnel excavation method and sediment removal method
CN105604553A (en) * 2015-12-21 2016-05-25 上海市基础工程集团有限公司 Construction method for exploration and treatment of shield driving complex formation boulders

Patent Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH08254094A (en) * 1995-03-15 1996-10-01 Fujita Corp Boulder removing method for jacking method
CN201933510U (en) * 2011-03-14 2011-08-17 中国水电顾问集团成都勘测设计研究院 Outlet shaft structure of underground factories in hydroelectric engineering
CN102518442A (en) * 2011-12-14 2012-06-27 中铁十二局集团第二工程有限公司 Method for processing isolated stone groups in shield excavation karren section
CN103032071A (en) * 2012-12-09 2013-04-10 中铁十二局集团有限公司 Shield receiving forward-shift construction method of boulder group open excavation and embedment mutation space
CN103075161A (en) * 2013-01-16 2013-05-01 中铁隧道集团有限公司 Quick underground obstacle clearing method for slurry shield construction
JP2015074957A (en) * 2013-10-11 2015-04-20 鹿島建設株式会社 Tunnel excavation method and sediment removal method
CN103790594A (en) * 2014-02-26 2014-05-14 中铁一局集团有限公司 Method for exploring and processing interior of boulder hole in front for shield method construction
CN103924980A (en) * 2014-04-24 2014-07-16 上海隧道工程股份有限公司 Obstacle removing construction method
CN105604553A (en) * 2015-12-21 2016-05-25 上海市基础工程集团有限公司 Construction method for exploration and treatment of shield driving complex formation boulders

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109441454A (en) * 2018-09-11 2019-03-08 广东水电二局股份有限公司 A kind of construction method of underground lonestone reception room
CN109026039A (en) * 2018-10-19 2018-12-18 深圳市工勘岩土集团有限公司 Subway tunnel shield tunnels boulder deep hole blasting and pre-processes construction method
CN109372526A (en) * 2018-11-12 2019-02-22 中铁工程装备集团有限公司 The novel balancing earth-pressure shielding machine of foreign matter obstacle can be passed through
CN109505614A (en) * 2019-01-09 2019-03-22 海南大学 A kind of shield machine directly promotes the construction method by boulder
CN110578524A (en) * 2019-08-27 2019-12-17 中交第二航务工程局有限公司 Boulder treatment construction method for dense drilling and crushing in shield region
CN114837681A (en) * 2022-06-07 2022-08-02 江苏旭睿重工科技有限公司 Quick stone removing device for soil bin of shield machine and construction method thereof

Similar Documents

Publication Publication Date Title
AU2020101047A4 (en) Method for filling underground cavity in bedrock by grouting and hydraulic filling device
CN107060800A (en) A kind of shield-tunneling construction huge stone handling construction method
CN205172598U (en) Pipe curtain spouts a supporting construction soon
CN108560541B (en) Rotary drilling full-casing follow-up rock face drilling construction method
CN102943466B (en) Construction method for miniature steel pipe concrete pile to penetrate through roadbed layer for reinforcing soft foundation construction
CN110656947B (en) Method for tunneling raised section of seabed bedrock
CN108678130A (en) A kind of non-digging drag pipe construction method
CN104153352A (en) Karst geology rotary-drilling bored concrete pile hole forming process
CN106088099B (en) A kind of subway foundation pit anchor cable processing method
CN106149679A (en) The construction technology of diaphram wall built by slotter
CN110952528A (en) Construction method of cement-soil underground continuous wall under complex geological conditions
CN108842764B (en) Rotary stirring type anchor pipe construction method
CN107339122B (en) Construction method for treating goaf by steel pipe column
CN109667276A (en) A kind of karst cave treatment and tracking grouting construction method
CN101158269B (en) Method for drilling roadbed small-caliber horizontal jacking pipe and drill bit
CN203821414U (en) Structure of protecting wall of hole-digging pile
CN105649010A (en) Grouting pile construction technology
CN108071110A (en) Rotary drilling rig Pile method under complex geological condition
CN110130909A (en) The construction method of building up station is worn under a kind of shield in powder land floor
CN114059527A (en) Large-diameter mixing pile construction method suitable for high-groundwater-level hard soil layer
CN112196494B (en) Construction process and construction equipment for geological pipeline jointed between rock and soil layer
CN103850261A (en) In-rock deep foundation pit rock-socketed water-stop curtain construction method
CN104631479B (en) Construction method of soil-changing and stirring waterproof curtain
CN103161469A (en) Method for excavating vertical shaft to underground repair pipe-jacking tool pipe
CN205296194U (en) Rich irrigated land layer undercut tunnel interlock pipe curtain

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20170818