CN107060039A - A kind of drainage arrangement preparation method of indoor and roof construction ground - Google Patents

A kind of drainage arrangement preparation method of indoor and roof construction ground Download PDF

Info

Publication number
CN107060039A
CN107060039A CN201710118219.5A CN201710118219A CN107060039A CN 107060039 A CN107060039 A CN 107060039A CN 201710118219 A CN201710118219 A CN 201710118219A CN 107060039 A CN107060039 A CN 107060039A
Authority
CN
China
Prior art keywords
ground
floor
tubing
water
horizon
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201710118219.5A
Other languages
Chinese (zh)
Inventor
高贯友
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201710118219.5A priority Critical patent/CN107060039A/en
Publication of CN107060039A publication Critical patent/CN107060039A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E03WATER SUPPLY; SEWERAGE
    • E03FSEWERS; CESSPOOLS
    • E03F3/00Sewer pipe-line systems
    • E03F3/02Arrangement of sewer pipe-lines or pipe-line systems
    • EFIXED CONSTRUCTIONS
    • E03WATER SUPPLY; SEWERAGE
    • E03FSEWERS; CESSPOOLS
    • E03F3/00Sewer pipe-line systems
    • E03F3/04Pipes or fittings specially adapted to sewers
    • EFIXED CONSTRUCTIONS
    • E03WATER SUPPLY; SEWERAGE
    • E03FSEWERS; CESSPOOLS
    • E03F3/00Sewer pipe-line systems
    • E03F3/04Pipes or fittings specially adapted to sewers
    • E03F3/046Open sewage channels
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04FFINISHING WORK ON BUILDINGS, e.g. STAIRS, FLOORS
    • E04F15/00Flooring
    • E04F15/18Separately-laid insulating layers; Other additional insulating measures; Floating floors
    • E04F15/182Underlayers coated with adhesive or mortar to receive the flooring
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04FFINISHING WORK ON BUILDINGS, e.g. STAIRS, FLOORS
    • E04F2290/00Specially adapted covering, lining or flooring elements not otherwise provided for
    • E04F2290/04Specially adapted covering, lining or flooring elements not otherwise provided for for insulation or surface protection, e.g. against noise, impact or fire

Landscapes

  • Engineering & Computer Science (AREA)
  • Health & Medical Sciences (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Hydrology & Water Resources (AREA)
  • Public Health (AREA)
  • Water Supply & Treatment (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Floor Finish (AREA)

Abstract

A kind of drainage arrangement preparation method of indoor and roof construction ground, it is characterised in that:First before the installation floor of decorating house ground, two layers of water-repellent paint is uniformly brushed comprehensively on ground, after after water-repellent paint solidification, on provided with coating ground, lay two centimetres of tubing of diameter, about 30 square metres of rooms need lay 67 drainage pipes, put for 50 to 60 centimetres and put one, one of final tubing will connect with main sewer connecting tube.Tubing needs to get out countless arrangement apertures lack of standardization, and the size diameter in hole seeps water the rough slurry in laying floor tile by this device and discharged, reduces mildew bacterium and grow in 2MM or so apertures.

Description

A kind of drainage arrangement preparation method of indoor and roof construction ground
The present invention relates to building technical field of drainage, especially a kind of indoor and roof construction ground drainage arrangement makes Technology.
Background technology
The present inventor is to be engaged in building trade for many years and family to fit up family in the past, passes therethrough and observes many times, is found current each Each family indoor floor of family and roof finishing all have the hidden danger of very serious ground water, it has been found that now with many buildings Floor infiltration is extremely serious, finds the cement mortar used in the indoor Horizon of construction, interior decoration Horizon note patch floor tile, is all a kind of Very rough sandstone water mixing mud, cement proportion is seldom, or even proportioning percentage 90 is all based on sand, if having used water Mud is matched somebody with somebody in the big cement mortar of specific strength, the time limit afterwards, and cement mortar can play one kind and chemically react, and floor can be caused to extrude Craze and transfiguration, if without using the big cement mortar of intensity, certain kind of berries germ, humidity, building in Horizon water under floor, generating chamber can be caused Plate leak, if along with indoor door and window is stuffy, just can more produce harmful germ, affect the healthy of people, sends out A person of good sense simultaneously, sets up a kind of construction drainage device by floor construction indoors, once there is the situation of infiltration on ground roof floor, The row of infiltration can just be discharged to sewer pipe by this drainage arrangement, ensure that people's is healthy.
The content of the invention
A kind of drainage arrangement preparation method of indoor and roof construction ground, it is characterised in that.
First before the installation floor of decorating house ground, two layers of water-repellent paint is uniformly brushed comprehensively on ground.
After after water-repellent paint solidification, on provided with coating ground, two centimetres of tubing of diameter, about 30 square metres of rooms are laid 6-7 root drainage pipes need be laid, puts for 50 to 60 centimetres and puts one, one of final tubing will be with main sewer connecting tube Connection.
Tubing needs to get out countless arrangement apertures lack of standardization, and the size diameter in hole is in 2MM or so apertures, and tubing has been to do Filter sand stone mud, plays discharge room plate infiltration effect.
Then conventional decoration construction floor board method is recycled, then is pacified being covered with the ground of aperture drainage arrangement tubing The objects such as installed floor, the effect of the method is that it is all that the not high cement of cement proportion is rough to have used in order to prevent from fitting up floor Slurry, cause infiltration, if cement grade is too high, will in the service life of floor chemically reactive, will result in floor can hold Split or heave, this method is to play to make provision against emergencies, or ground after finishing, plate stitch infiltration, will result in the following water in floor A large amount of waters at the rough slurry of mud, a century is relied mainly on prevention greatly in season, is reduced because indoor water humidity produces the germs such as long-term mould, once Pipe leakage and ground plate stitch infiltration, will discharge water by the method device, reduce mildew bacterium and grow under roofing.
The main downcomer on the preceding ground of interior decoration, level land Ping Chu, surrounding gets out aperture, plays landing ground infiltration, draining Effect, the observation through inventor many times is constructed, the rough house before Horizon is not done, it is found that main sewer pipe is all reserved and be higher by ground Flat, after isanomal floor is carried out, pipeline just cuts according to needed for construction and put down in ground, if do not bored in the preceding level land Ping Chu of construction Several draining apertures, once Horizon floor tile is made on ground, and is mounted with toilet device, this pipeline just it is permanent under floor, such as Fruit is not subject to make drainage reconstruction drilling in main drainpipe in advance, and this sewer pipe will be into check dam, coming to roofing Infiltration is stored under floor.
In addition while Horizon floor tile is laid, the synchronous several centimeters of cement mortars construction, the flat place in level land is made with cleaver 2x2 centimetres high wide groove, one layer of sandstone for not containing the thicker shape of cement granules is laid in groove and is placed in groove, groove A straight-through sewage device, if room is in 30 square meters, it is proposed that Horizon make 5-6 transformation drainage arrangement ditch Groove.
Roof water-proof drainage, and indoor water-proof drainage, can discharge infiltration leak by this several water discharge method.
Brief description of the drawings:
Fig. 1 is schematic structural view of the invention.
1 is drainpipe infiltration aperture in figure, and 2 be ground level before finishing, and 3 be drainpipe, and 4 be drain header road, and 5 be signal room Face roof surrounding wall side.
The method does not influence normal construction making cement Horizon, and the construction of laying floor tile normal operating, once have infiltration Existing picture, water will be arranged by the method device to main sewer pipe discharge, will not be because being produced caused by infiltration below Horizon floor Raw water, the fungal effects people's that would not be produced by indoor moisture is healthy, reduces because indoor floor water is made Into the infiltration of floor, neighbours' dispute and the property loss caused by infiltration are reduced.

Claims (1)

1. a kind of drainage arrangement preparation method of indoor and roof construction ground, it is characterised in that:
First before the installation floor of decorating house ground, two layers of water-repellent paint is uniformly brushed comprehensively on ground;
After after water-repellent paint solidification, on provided with coating ground, two centimetres of tubing of diameter are laid, about 30 square metres of rooms need 6-7 root drainage pipes are laid, puts for 50 to 60 centimetres and puts one, one of final tubing will connect with main sewer connecting tube Connect;
Tubing needs to get out countless arrangement apertures lack of standardization, and the size diameter in hole is in 2MM or so apertures, and tubing has been to do filter sand Stone mud, plays discharge room plate infiltration effect;
Then conventional decoration construction floor board method is recycled, then installs ground being covered with the ground of aperture drainage arrangement tubing The objects such as plate, the effect of the method is that it is all the rough slurry of the not high cement of cement proportion to have used, and is made in order to prevent from fitting up floor Into infiltration, if cement grade is too high, will in the service life of floor chemically reactive, will result in floor can ftracture or drum Rise, this method is to play to make provision against emergencies, or ground after finishing, plate stitch infiltration, will result in the rough slurry of the following cement in floor Locate a large amount of waters, a century is relied mainly on prevention greatly in season, reduce because indoor water humidity produces the germs such as long-term mould, once under roofing Pipe leakage and ground plate stitch infiltration, will discharge water by the method device, reduce mildew bacterium and grow;
The main downcomer on the preceding ground of interior decoration, level land Ping Chu, surrounding gets out aperture, plays landing ground and seeps water, the effect of draining, Observation construction through inventor many times, the rough house before Horizon is not done, the main sewer pipe of discovery, which is all reserved, is higher by Horizon, etc. After Horizon floor is carried out, pipeline just cuts according to needed for construction and put down in ground, if not boring several in the preceding level land Ping Chu of construction Draining aperture, once Horizon floor tile is made on ground, and is mounted with toilet device, this pipeline just it is permanent under floor, if thing It is not subject to first to make drainage reconstruction drilling in main drainpipe, this sewer pipe will be into check dam, coming to the infiltration of roofing It is stored under floor;
In addition while Horizon floor tile is laid, the synchronous several centimeters of cement mortars construction, the flat place in level land makes 2x2 lis with cleaver Meter Gao Kuan groove, one layer of sandstone for not containing the thicker shape of cement granules is laid in groove and is placed in groove, and the one of groove Straight-through sewage device, if room is in 30 square meters, it is proposed that Horizon makes the drainage arrangement groove of 5-6 transformation.
CN201710118219.5A 2017-03-01 2017-03-01 A kind of drainage arrangement preparation method of indoor and roof construction ground Pending CN107060039A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710118219.5A CN107060039A (en) 2017-03-01 2017-03-01 A kind of drainage arrangement preparation method of indoor and roof construction ground

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710118219.5A CN107060039A (en) 2017-03-01 2017-03-01 A kind of drainage arrangement preparation method of indoor and roof construction ground

Publications (1)

Publication Number Publication Date
CN107060039A true CN107060039A (en) 2017-08-18

Family

ID=59622343

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710118219.5A Pending CN107060039A (en) 2017-03-01 2017-03-01 A kind of drainage arrangement preparation method of indoor and roof construction ground

Country Status (1)

Country Link
CN (1) CN107060039A (en)

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
FR1364277A (en) * 1963-06-13 1964-06-19 Process for drying the walls of a building
US5501044A (en) * 1994-08-31 1996-03-26 Janesky; Lawrence M. Sub-floor drain conduit for water-control systems
JPH09228576A (en) * 1996-02-20 1997-09-02 Hidekazu Kiyono Roof floor structure of wooden house
CN1858368A (en) * 2006-03-31 2006-11-08 涂少泉 Leaked water collector and its mounting construction method
CN103835376A (en) * 2014-02-12 2014-06-04 苏州金螳螂建筑装饰股份有限公司 Stone ground bonding layer construction excrescent water drainage pressure-reduction whiskering-preventing structure
CN104047356A (en) * 2014-05-26 2014-09-17 深圳市洪涛装饰股份有限公司 Anti-seeping bath room and anti-seeping method thereof

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
FR1364277A (en) * 1963-06-13 1964-06-19 Process for drying the walls of a building
US5501044A (en) * 1994-08-31 1996-03-26 Janesky; Lawrence M. Sub-floor drain conduit for water-control systems
JPH09228576A (en) * 1996-02-20 1997-09-02 Hidekazu Kiyono Roof floor structure of wooden house
CN1858368A (en) * 2006-03-31 2006-11-08 涂少泉 Leaked water collector and its mounting construction method
CN103835376A (en) * 2014-02-12 2014-06-04 苏州金螳螂建筑装饰股份有限公司 Stone ground bonding layer construction excrescent water drainage pressure-reduction whiskering-preventing structure
CN104047356A (en) * 2014-05-26 2014-09-17 深圳市洪涛装饰股份有限公司 Anti-seeping bath room and anti-seeping method thereof

Similar Documents

Publication Publication Date Title
CN104358305B (en) A kind of cyclone, water drainage riser connecting piece of caisson type washroom
CN202745335U (en) Sunken type toilet water-resistant deodorization settling basin structure
CN104234089B (en) The construction method that a kind of basement guarded drainage combines
CN101691840B (en) Water level observation well and construction method thereof
CN103938679A (en) Drainage riser connector of caisson-type toilet
CN207376723U (en) A kind of subsided rest room
CN201212156Y (en) Interception and drainage system of basement engineering
CN108179766A (en) The shed deckhead waterproof construction of sponge urban design
CN107060039A (en) A kind of drainage arrangement preparation method of indoor and roof construction ground
Reich et al. A Preliminary Report on the" Miqwaʾot" of Migdal
CN104863218B (en) Toilet-entering mounting method for water supply pipe in toilet
CN111088830A (en) Caisson type toilet secondary drainage pipeline
CN109930780A (en) A kind of construction technology of subsided rest room
CN203821521U (en) Soil stack connection piece for caisson type toilet
CN211973796U (en) Novel rainwater underground disconnection system
CN104060677B (en) A kind of skyscraper has construction method and the composite floor drain used of floor drain between boiled water room
TW451019B (en) Water-proof and damp-proof method for basement side wall
CN103556841B (en) A kind of hollow type residence toilet substructure
CN209924297U (en) Breather pipe leak protection subassembly and breather pipe joint
CN1664257A (en) Technical proposal for toilet drainage
Sear Cisterns, drainage and lavatories in Pompeian houses, Casa dei Capitelli Colorati (VII. 4.51), Casa della Caccia Antica (VII. 4.48) and Casa dei Capitelli Figurati (VII. 4.57)
CN206015921U (en) Drain pipe waterproof construction
CN204282499U (en) A kind of cyclone, water drainage riser connecting piece of caisson type washroom
CN204876482U (en) Building drainage pipe well
CN205857310U (en) A kind of reserved type Matheson and Dresser joint

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20170818

WD01 Invention patent application deemed withdrawn after publication