CN106996095A - A kind of preparation method of rubble clay core wall material - Google Patents

A kind of preparation method of rubble clay core wall material Download PDF

Info

Publication number
CN106996095A
CN106996095A CN201710233404.9A CN201710233404A CN106996095A CN 106996095 A CN106996095 A CN 106996095A CN 201710233404 A CN201710233404 A CN 201710233404A CN 106996095 A CN106996095 A CN 106996095A
Authority
CN
China
Prior art keywords
blending
clay
stone
rubble
metaling
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201710233404.9A
Other languages
Chinese (zh)
Other versions
CN106996095B (en
Inventor
谢祥明
陈伟平
陈再
余青山
孟庆红
谢小明
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guangdong Ysd Surveying & Designing Co Ltd
Guangdong No 2 Hydropower Engineering Co Ltd
Original Assignee
Guangdong Ysd Surveying & Designing Co Ltd
Guangdong No 2 Hydropower Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guangdong Ysd Surveying & Designing Co Ltd, Guangdong No 2 Hydropower Engineering Co Ltd filed Critical Guangdong Ysd Surveying & Designing Co Ltd
Priority to CN201710233404.9A priority Critical patent/CN106996095B/en
Publication of CN106996095A publication Critical patent/CN106996095A/en
Application granted granted Critical
Publication of CN106996095B publication Critical patent/CN106996095B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B7/00Barrages or weirs; Layout, construction, methods of, or devices for, making same
    • E02B7/02Fixed barrages
    • E02B7/04Dams across valleys
    • E02B7/06Earth-fill dams; Rock-fill dams
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B3/00Engineering works in connection with control or use of streams, rivers, coasts, or other marine sites; Sealings or joints for engineering works in general
    • E02B3/16Sealings or joints

Landscapes

  • Engineering & Computer Science (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Environmental & Geological Engineering (AREA)
  • Ocean & Marine Engineering (AREA)
  • Revetment (AREA)

Abstract

The invention discloses a kind of preparation method of rubble clay core wall material, comprise the following steps:1)Set and excavate upper dam blending field and get the raw materials ready with blending field;2)Size grading and the moisture content of metaling and clay material are determined, then calculates the mass ratio for determining metaling and clay material;3)Determine that the individual layer thickness that paves, the mutual number of plies and the stockpile design heap of metaling and clay material are high;4)Carry out small-scale Blending Experiments;5)Paved parameter according to small-scale Blending Experiments modified result, then carry out extensive stone and blending;6)Leftover pieces formation exploitation facade is cut out after the completion of stone with backacter;7)Facade exploitation, repeatedly mix are carried out with backacter, rubble clay core wall material is obtained.The present invention is using layering alternately tiling clay and rubble, the blending method of backacter facade exploitation, and civilwork engineering quantity is smaller, blending technique, simple, economy, quality are good, and rubble clay core wall material yield is high.

Description

A kind of preparation method of rubble clay core wall material
Technical field
The present invention relates to a kind of preparation method of rubble clay core wall material.
Background technology
Core-wall be earth and rockfill dam, rock-fill dams frequently with leakage preventing structure, mainly entered by clay, gravel clay, rubble clay Row is filled.In the various dam types of earth and rockfill dam, rubble Clay Core Wall Rockfill Dam has been increasingly becoming the main flow dam of world's high dam construction One of type.The blending of domestic and international broken (gravel) stone clay core wall material is broadly divided into following several method:1) continous way mix is forced;2) Sealing-tape machine transport is first mixed stores up afterwards;3) sealing-tape machine transport layering stone;4) stacker cloth layering stone.Above-mentioned several conventional sides One or more in the following defect of method generally existing:Complex process, civilwork engineering quantity are big, admixture uniformity is poor, construction Cost is high.
Therefore, it is necessary to develop that a kind of civilwork engineering quantity is smaller, it is simple to blend technique, economy, quality are good, that yield is high is broken Stone clay core wall material preparation method.
The content of the invention
It is an object of the invention to provide a kind of preparation method of rubble clay core wall material.
The technical solution used in the present invention is:
A kind of preparation method of rubble clay core wall material, comprises the following steps:
1) the upper dam of excavation is set to blend according to earth material, filter material and metaling system of processing and the arrangement of upper dam road And get the raw materials ready with blend field, cleaning, smooth blending field;
2) size grading of metaling and clay material is determined according to design objective, design core-wall material envelope and grain composition And moisture content, then calculate the mass ratio for determining metaling and clay material;
3) according to design parameter, blend place shape and construction machinery determine metaling and clay material the individual layer thickness that paves, The mutual number of plies and stockpile design heap are high;
4) small-scale Blending Experiments are carried out, blending replaces stone using level;
5) paved parameter according to small-scale Blending Experiments modified result, then carry out extensive stone and blending;
6) leftover pieces formation exploitation facade is cut out after the completion of stone with backacter;
7) facade exploitation, repeatedly mix are carried out with backacter, obtains rubble clay core wall material.
Step 1) described in get the raw materials ready with blend field be 1~3.
Step 4) thickness of the stone is controlled by spirit level or total powerstation.
Step 5) carry out stone when aspect the gradient be 1%~2%.
Step 7) described in facade exploitation thickness be 30~50cm.
The beneficial effects of the invention are as follows:The present invention is opened using layering alternating tiling clay and rubble, backacter facade The blending method adopted, civilwork engineering quantity is smaller, blending technique, simple, economy, quality are good, and rubble clay core wall material yield is high.
Brief description of the drawings
Fig. 1 is rubble clay core wall material Making programme figure.
Fig. 2 is that facade exploitation backhoe mixes artwork.
Embodiment
A kind of preparation method of rubble clay core wall material, comprises the following steps:
1) the upper dam of excavation is set to blend according to earth material, filter material and metaling system of processing and the arrangement of upper dam road And get the raw materials ready with blend field, cleaning, smooth blending field;
2) size grading of metaling and clay material is determined according to design objective, design core-wall material envelope and grain composition And moisture content, then calculate the mass ratio for determining metaling and clay material;
3) according to design parameter, blend place shape and construction machinery determine metaling and clay material the individual layer thickness that paves, The mutual number of plies and stockpile design heap are high;
4) small-scale Blending Experiments are carried out, blending replaces stone using level;
5) paved parameter according to small-scale Blending Experiments modified result, then carry out extensive stone and blending;
6) leftover pieces formation exploitation facade is cut out after the completion of stone with backacter;
7) facade exploitation, repeatedly mix are carried out with backacter, obtains rubble clay core wall material.
It is preferred that, step 1) described in get the raw materials ready with blend field be 1~3.
It is preferred that, step 4) thickness of the stone is controlled by spirit level or total powerstation.
It is preferred that, step 5) carry out stone when aspect the gradient be 1%~2%.
It is preferred that, step 7) described in facade exploitation thickness be 30~50cm.
The present invention is made further explanation and description with reference to specific embodiment.
Embodiment 1:
The rubble clay core wall material of mixing stone contents 25%:
Rubble clay core wall material Making programme figure as shown in figure 1, facade exploitation backhoe to mix artwork as shown in Figure 2.
Blend field specification:8m×15m;
Clay material paves individual layer thickness for 75cm, and metaling paves individual layer thickness for 25cm, and alternating horizontal making is spread first Clay material, totally 6 layers;
Exploited and dug with backacter 40cm thickness facade after the completion of stone, backacter mix 4 times;
Quality testing is using the method for determining admixture medium stone mass content and its uniformity, compound stone contents control Make within ± the 5% of design content, sampling is representative, each testing site samples 100kg, from different position samples 7, stone contents therein are detected, the uniformity of rubble clay core wall material manufactured in the present embodiment is as shown in table 1.
Embodiment 2:
The rubble clay core wall material of mixing stone contents 30%:
Rubble clay core wall material Making programme figure as shown in figure 1, facade exploitation backhoe to mix artwork as shown in Figure 2.
Blend field specification:8m×15m;
Clay material paves individual layer thickness for 70cm, and metaling paves individual layer thickness for 30cm, and alternating horizontal making is spread first Clay material, totally 6 layers;
Exploited and dug with backacter 40cm thickness facade after the completion of stone, backacter mix 4 times;
Quality testing is using the method for determining admixture medium stone mass content and its uniformity, compound stone contents control Make within ± the 5% of design content, sampling is representative, each testing site samples 100kg, from different position samples 7, stone contents therein are detected, the uniformity of rubble clay core wall material manufactured in the present embodiment is as shown in table 1.
Embodiment 3:
The rubble clay core wall material of mixing stone contents 35%:
Rubble clay core wall material Making programme figure as shown in figure 1, facade exploitation backhoe to mix artwork as shown in Figure 2.
Blend field specification:8m×15m;
Clay material paves individual layer thickness for 65cm, and metaling paves individual layer thickness for 35cm, and alternating horizontal making is spread first Clay material, totally 6 layers;
Exploited and dug with backacter 50cm thickness facade after the completion of stone, backacter mix 3 times;
Quality testing is using the method for determining admixture medium stone mass content and its uniformity, compound stone contents control Make within ± the 5% of design content, sampling is representative, each testing site samples 100kg, from different position samples 7, stone contents therein are detected, the uniformity of rubble clay core wall material manufactured in the present embodiment is as shown in table 1.
Test case:
The uniformity such as following table of rubble clay core wall material prepared by embodiment 1~3:
The uniformity test result of the rubble clay core wall material of the embodiment 1~3 of table 1
Above-described embodiment is preferably embodiment, but embodiments of the present invention are not by above-described embodiment of the invention Limitation, other any Spirit Essences without departing from the present invention and the change made under principle, modification, replacement, combine, simplification, Equivalent substitute mode is should be, is included within protection scope of the present invention.

Claims (5)

1. a kind of preparation method of rubble clay core wall material, it is characterised in that:Comprise the following steps:
1)According to earth material, filter material and metaling system of processing and the arrangement of upper dam road set the upper dam of excavation with blend field and Get the raw materials ready with blending field, cleaning, smooth blending field;
2)The size grading of metaling and clay material is determined according to design objective, design core-wall material envelope and grain composition and contained Water rate, then calculate the mass ratio for determining metaling and clay material;
3)Pave individual layer thickness, the alternating layers of metaling and clay material are determined according to design parameter, blending place shape and construction machinery Number and stockpile design heap are high;
4)Small-scale Blending Experiments are carried out, blending replaces stone using level;
5)Paved parameter according to small-scale Blending Experiments modified result, then carry out extensive stone and blending;
6)Leftover pieces formation exploitation facade is cut out after the completion of stone with backacter;
7)Facade exploitation, repeatedly mix are carried out with backacter, rubble clay core wall material is obtained.
2. preparation method according to claim 1, it is characterised in that:Step 1)Described getting the raw materials ready with field is blended is 1~3 It is individual.
3. preparation method according to claim 1, it is characterised in that:Step 4)The thickness of the stone by spirit level or Total powerstation is controlled.
4. preparation method according to claim 1, it is characterised in that:Step 5)Carry out the gradient of aspect during stone for 1%~ 2%。
5. preparation method according to claim 1, it is characterised in that:Step 7)The thickness of described facade exploitation for 30~ 50cm。
CN201710233404.9A 2017-04-11 2017-04-11 A kind of production method of rubble clay core wall material Active CN106996095B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710233404.9A CN106996095B (en) 2017-04-11 2017-04-11 A kind of production method of rubble clay core wall material

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710233404.9A CN106996095B (en) 2017-04-11 2017-04-11 A kind of production method of rubble clay core wall material

Publications (2)

Publication Number Publication Date
CN106996095A true CN106996095A (en) 2017-08-01
CN106996095B CN106996095B (en) 2019-01-04

Family

ID=59434422

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710233404.9A Active CN106996095B (en) 2017-04-11 2017-04-11 A kind of production method of rubble clay core wall material

Country Status (1)

Country Link
CN (1) CN106996095B (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109987894A (en) * 2019-05-06 2019-07-09 土上(北京)建筑设计咨询有限公司 Cob earth material and the method for evaluating cob earth material
CN112536914A (en) * 2020-11-27 2021-03-23 中国电建集团成都勘测设计研究院有限公司 Gravel doping method for core wall soil material of core wall dam

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2014162563A (en) * 2013-02-21 2014-09-08 Kajima Corp Volumetric feeder and method for application of compacting soil using volumetric feeder
CN104264698A (en) * 2014-09-05 2015-01-07 中国葛洲坝集团国际工程有限公司 Construction method of clay core earth rock cofferdam
CN205604186U (en) * 2015-12-03 2016-09-28 云南润晶水利电力工程技术股份有限公司 Clay core morals and manners material dam
CN106368176A (en) * 2016-11-08 2017-02-01 中国电建集团成都勘测设计研究院有限公司 High dam structure built on deep overburden of soil material shortage area

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2014162563A (en) * 2013-02-21 2014-09-08 Kajima Corp Volumetric feeder and method for application of compacting soil using volumetric feeder
CN104264698A (en) * 2014-09-05 2015-01-07 中国葛洲坝集团国际工程有限公司 Construction method of clay core earth rock cofferdam
CN205604186U (en) * 2015-12-03 2016-09-28 云南润晶水利电力工程技术股份有限公司 Clay core morals and manners material dam
CN106368176A (en) * 2016-11-08 2017-02-01 中国电建集团成都勘测设计研究院有限公司 High dam structure built on deep overburden of soil material shortage area

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109987894A (en) * 2019-05-06 2019-07-09 土上(北京)建筑设计咨询有限公司 Cob earth material and the method for evaluating cob earth material
CN112536914A (en) * 2020-11-27 2021-03-23 中国电建集团成都勘测设计研究院有限公司 Gravel doping method for core wall soil material of core wall dam
CN112536914B (en) * 2020-11-27 2022-04-08 中国电建集团成都勘测设计研究院有限公司 Gravel doping method for core wall soil material of core wall dam

Also Published As

Publication number Publication date
CN106996095B (en) 2019-01-04

Similar Documents

Publication Publication Date Title
Peila et al. Using the slump test to assess the behavior of conditioned soil for EPB tunneling
Yates et al. A review of the geotechnical characteristics of loess and loess-derived soils from Canterbury, South Island, New Zealand
Daniel Predicting hydraulic conductivity of clay liners
CN104153380B (en) A kind of antiseepage cofferdam structure and construction technology
Gierlowski-Kordesch Carbonate deposition in an ephemeral siliciclastic alluvial system: Jurassic Shuttle Meadow Formation, Newark Supergroup, Hartford basin, USA
Maziar Excavations at Köhné Pāsgāh Tepesi, the Araxes Valley, Northwest Iran: First Preliminary Report
CN106996095B (en) A kind of production method of rubble clay core wall material
JP4574386B2 (en) Mixing method of solidifying material in improved soil and mixing method of solidifying material and auxiliary in improved soil
KR101380354B1 (en) Composition for improvement of soft ground and bio-grout method using the same
CN112206753A (en) Hydrophilic polymer modified bentonite composite material and preparation method and application thereof
CN106759399A (en) A kind of side slope vegetation ecological recovery system and method
CN108708350A (en) A kind of ecological slope protection structure and its construction method
CN102943423A (en) Construction technology for clay roadbed with high liquid limit
CN106223346B (en) A kind of packing method for scrapping motor-pumped well
CN106734126B (en) A kind of infiltration type reaction wall and its construction method for the processing of phreatic water polluted by nitrogen
Djelal et al. Recommendation for concrete mix design to prevent bleed channels on diaphragm walls
CN109914174A (en) A kind of pond backfill packing sedimentation by throwing stones construction method
CN106812118A (en) One kind is for mixing gravel earth material Gradation Control method
Liu et al. Suppressing Drought-Induced Soil Desiccation Cracking Using MICP: Field Demonstration and Insights
CN108396706A (en) The ecology of solidification riverbed soil, which subtracts infiltration method, solidified earth and ecology and subtracts, oozes structure
CN112536914B (en) Gravel doping method for core wall soil material of core wall dam
CN105714634A (en) Construction method of soil-rock geological roadbed
Olszewski et al. A fourth season at Yutil al-Hasa (WHS 784): renewed Early Epipaleolithic excavations
CN107313422A (en) A kind of method that road/place basis is prepared under muddy soft soil environment
CN114438969A (en) Construction method suitable for mining, blending and filling of high earth-rock dam gravel soil materials

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant