CN106978885A - It is a kind of to ensure the method for the firm connection of reinforced bar sleeve - Google Patents

It is a kind of to ensure the method for the firm connection of reinforced bar sleeve Download PDF

Info

Publication number
CN106978885A
CN106978885A CN201710343047.1A CN201710343047A CN106978885A CN 106978885 A CN106978885 A CN 106978885A CN 201710343047 A CN201710343047 A CN 201710343047A CN 106978885 A CN106978885 A CN 106978885A
Authority
CN
China
Prior art keywords
reinforcing bar
section
sleeve
screw thread
bar
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201710343047.1A
Other languages
Chinese (zh)
Inventor
刘传敏
谢兰敏
金玲玲
王帅
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China MCC17 Group Co Ltd
Original Assignee
China MCC17 Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China MCC17 Group Co Ltd filed Critical China MCC17 Group Co Ltd
Priority to CN201710343047.1A priority Critical patent/CN106978885A/en
Publication of CN106978885A publication Critical patent/CN106978885A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04CSTRUCTURAL ELEMENTS; BUILDING MATERIALS
    • E04C5/00Reinforcing elements, e.g. for concrete; Auxiliary elements therefor
    • E04C5/16Auxiliary parts for reinforcements, e.g. connectors, spacers, stirrups
    • E04C5/162Connectors or means for connecting parts for reinforcements
    • E04C5/163Connectors or means for connecting parts for reinforcements the reinforcements running in one single direction
    • E04C5/165Coaxial connection by means of sleeves
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04CSTRUCTURAL ELEMENTS; BUILDING MATERIALS
    • E04C5/00Reinforcing elements, e.g. for concrete; Auxiliary elements therefor
    • E04C5/16Auxiliary parts for reinforcements, e.g. connectors, spacers, stirrups
    • E04C5/18Spacers of metal or substantially of metal

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Piles And Underground Anchors (AREA)

Abstract

The present invention be it is a kind of ensure the method for the firm connection of reinforced bar sleeve, belong to the householder method of Bridge Pile Foundation Construction, it is characterized in that:When processing the reinforcing bar I 1 described in (i.e. turning), the right-hand thread section on reinforcing bar II 3, left-hand thread section, each length by thread segment increases the ㎜ of 20 ㎜~25 than design length, meanwhile, during turning left-hand thread section is together with screw thread lengthening section, the depth in turning screw thread bottom footpath is:From left to right by most deep gradually to most shallow, during turning right-hand thread section is together with screw thread lengthening section, the depth in turning screw thread bottom footpath is:From right-to-left by most deep gradually to most shallow, the most deep depth in bottom footpath is 3mm, most shallow depth is 2mm, when reinforcing bar I 1, the correspondence of reinforcing bar II 3 are angled into reinforced bar sleeve 2, make to support between reinforcing bar I 1 and reinforcing bar II 3 and close, being completely embedded between reinforcing bar I 1, reinforcing bar II 3 and reinforced bar sleeve 2 is ensure that, construction quality is improved.

Description

It is a kind of to ensure the method for the firm connection of reinforced bar sleeve
Technical field
The invention belongs to the householder method of Bridge Pile Foundation Construction, more particularly, to a kind of connection method of reinforcing bar.
Background technology
Nearly ten years, China achieves in terms of the MACHINERY JOINT of reinforcing bar and developed on a large scale very much, wherein extruding connection conduct A kind of mechanical bar connecting measure, with traditional bar splicing, welding compare have joint performance reliably, steady quality Not the influence of climate and welder technology level, connection speed fast and safety, the flames of anger, be not required to large power supply, it is solderable With the advantages of weldable steel muscle can be reliably connected;But during Bridge Pile Foundation Construction, or reinforcing bar often occur deforms, partially The quality problems such as position, prove, the reason for such phenomenon occur is by Site Detection and experiment:Due to reinforcing bar and reinforced bar sleeve Junction there is a problem, when reinforcing bar is with straight screw sleeve connection, sometimes workmen by reinforcing bar along being threaded into reinforcing bar set When in cylinder, often due to the cause for quality of reinforced bar sleeve causes the thread segment of reinforcing bar smoothly to screw in, it is impossible to as defined in reaching Screw-in length, after reinforcing bar screws in certain length in reinforced bar sleeve, can allow workmen to take for having reached because resistance is increased To the screw-in length of standard, and cause two reinforcing bars not abut together, the centre of reinforced bar sleeve also has space, influence The stretching resistance that reinforcing bar is produced to concrete, causes reinforcing bar during concrete construction the quality problems such as deformation, off normal occur.
The content of the invention
The purpose of the present invention is the above-mentioned technical problem for existing, and proposition is a kind of to ensure the side of the firm connection of reinforced bar sleeve Method, not only easy to operate, effective, cost is relatively low, and applicability is extensive, and the quality of solution reinforcing bar and straight screw sleeve connection is asked Topic, improves construction quality.
The object of the present invention is achieved like this:It is a kind of to ensure the method for the firm connection of reinforced bar sleeve, including reinforcing bar I 1, Reinforcing bar II 3 and reinforced bar sleeve 2, right-hand thread section is provided with described reinforcing bar I 1, and left spiral shell is provided with described reinforcing bar II 3 Line section, described right-hand thread section, the diameter of thread (i.e. bottom footpath, overall diameter and the pitch of screw thread) of left-hand thread section, length according to Depending on design, left section in described reinforced bar sleeve 2 carries internal thread segment I, and right section in described reinforced bar sleeve 2 carries interior spiral shell Line section II, internal thread segment I on described reinforced bar sleeve 2 is corresponding with the right-hand thread section on reinforcing bar I 1 to be screwed, described reinforcing bar Internal thread segment II on sleeve 2 is corresponding with the left-hand thread section on reinforcing bar II 3 to be screwed, it is characterized in that:It is described in processing (i.e. turning) Reinforcing bar I 1 on right-hand thread section and reinforcing bar II 3 on left-hand thread section when, respectively by the length of thread segment than design length increase by 20 The ㎜ of ㎜~25 (i.e. the length of screw thread lengthening section is 20~25 ㎜), and the length of this screw thread lengthening section is preferred with 20 ㎜, meanwhile, During left-hand thread section on turning reinforcing bar II 3 is together with screw thread lengthening section, the diameter in turning screw thread bottom footpath is:From left to right By the standard value less than bottom footpath, gradually to the standard value equal to or more than bottom footpath, (i.e. the depth in turning screw thread bottom footpath is from left to right By most deep gradually to most shallow), during right-hand thread section on turning reinforcing bar I 1 is together with screw thread lengthening section, turning screw thread bottom footpath Diameter be:From right-to-left by the standard value less than bottom footpath gradually to standard value (the i.e. turning screw thread equal to or more than bottom footpath The depth in bottom footpath is:From right-to-left by most deep gradually to most shallow), it is 3mm, this screw thread bottom that the depth in this screw thread bottom footpath is most deep It is 2mm that the depth in footpath is most shallow, when reinforcing bar I 1, the correspondence of reinforcing bar II 3 are angled into reinforced bar sleeve 2, when running into reinforced bar sleeve 2 The reinforcing bar I 1 of one end or the screw-in length of reinforcing bar II 3 are below standard punctual, or because resistance can not continue to screw in greatly very much when, reinforced bar sleeve 2 other end of reinforcing bars II 3 or reinforcing bar I 1 just can increase the length of its screw-in, make to support between reinforcing bar I 1 and reinforcing bar II 3 and close, make steel Combination is completely embedded between muscle I 1, reinforcing bar II 3 and reinforced bar sleeve 2.
In use, when reinforcing bar I 1, the correspondence of reinforcing bar II 3 are angled into reinforced bar sleeve 2, if one end of reinforced bar sleeve 2 There are quality problems, reinforcing bar I 1 or reinforcing bar II 3 can not be screwed into place, and the reinforcing bar II 3 or reinforcing bar I 1 of the other end of reinforced bar sleeve 2 also can Continue to screw in, until reinforcing bar I 1, the perfect inner space for contacting and filling full reinforced bar sleeve 2 of the energy of reinforcing bar II 3, reach closely sealed effect Really, so, the active force between reinforcing bar I 1, reinforcing bar II 3 and reinforced bar sleeve 2 is also bigger, strengthens reinforcing bar I 1, reinforcing bar II 3 and steel Connection between muscle sleeve 2, solves the quality problems of reinforcing bar and straight screw sleeve connection, improves construction quality.
A kind of method for ensuring the firm connection of reinforced bar sleeve proposed presently in connection with drawings and examples to invention make into One step explanation.
Brief description of the drawings
Fig. 1 is schematic diagram when a kind of method for ensuring the firm connection of reinforced bar sleeve proposed by the invention is used.
In Fig. 1:1st, reinforcing bar I 2, reinforced bar sleeve 3, reinforcing bar II
Embodiment (embodiment)
In the construction of certain bridge pile foundation, employ that invention proposed a kind of ensures the side of the firm connection of reinforced bar sleeve Method, the length of reinforcing bar I 1 is that 9000 ㎜, diameter are 22 ㎜, and the length of reinforcing bar II 3 is that 9000 ㎜, diameter are 22 ㎜, reinforced bar sleeve 2 Length be that 60 ㎜, overall diameter are that 33 ㎜, interior diameter are 22.2mm, be provided with described reinforcing bar I 1 length be 50 ㎜, it is straight Footpath is 22 ㎜ right-hand thread section, be provided with described reinforcing bar II 3 length be 50 ㎜, diameter be 22 ㎜ left-hand thread section, institute Left section of the reinforced bar sleeve 2 stated carries internal thread segment I, and right section of described reinforced bar sleeve 2 carries internal thread segment II, described steel Internal thread segment I on muscle sleeve 2 is corresponding with the right-hand thread section on reinforcing bar I 1 to be screwed, the internal thread on described reinforced bar sleeve 2 Section II is corresponding with the left-hand thread section on reinforcing bar II 3 to be screwed, it is characterized in that:In the right-hand thread section described in processing (i.e. turning), left spiral shell During line section, the length of thread segment is respectively increased into 20 ㎜ (i.e. the length of screw thread lengthening section is 20 ㎜) than design length, meanwhile, in car During the left-hand thread section on reinforcing bar II 3 is cut together with screw thread lengthening section, the depth in turning screw thread bottom footpath is:From left to right by It is most deep gradually to arrive most shallow, during the right-hand thread section on turning reinforcing bar I 1 is together with screw thread lengthening section, turning screw thread bottom footpath Depth is:From right-to-left by most deep gradually to most shallow, the innermost depth in screw thread bottom footpath is 3mm, the most shallow place in screw thread bottom footpath Depth is 2mm;When reinforcing bar I 1, the correspondence of reinforcing bar II 3 are angled into reinforced bar sleeve 2, it is ensured that tight between reinforcing bar I 1 and reinforcing bar II 3 Close support is closed, and is strengthened the connection between reinforcing bar I 1, reinforcing bar II 3 and reinforced bar sleeve 2, is solved what reinforcing bar was connected with reinforced bar sleeve 2 Quality problems, strengthen the connection between reinforcing bar I 1, reinforcing bar II 3 and reinforced bar sleeve 2.
This method is applied in Bridge Pile Foundation Construction, is solved the quality problems of reinforcing bar and straight screw sleeve connection, is improved Efficiency of construction and construction quality, it is ensured that construction period, are worthy of popularization.

Claims (4)

1. a kind of ensure the method for the firm connection of reinforced bar sleeve, including reinforcing bar I (1), reinforcing bar II (3) and reinforced bar sleeve (2), in institute Right-hand thread section is provided with the reinforcing bar I (1) stated, left-hand thread section, described right-hand thread are provided with described reinforcing bar II (3) Section, the length of left-hand thread section and diameter be screw thread bottom footpath, overall diameter and pitch according to design depending on, in described reinforcing bar Left section of sleeve (2) carries internal thread segment I, and right section in described reinforced bar sleeve (2) carries internal thread segment II, described reinforcing bar Internal thread segment I on sleeve (2) is corresponding with the right-hand thread section on reinforcing bar I (1) to be screwed, interior on described reinforced bar sleeve (2) Thread segment II is corresponding with the left-hand thread section on reinforcing bar II (3) to be screwed, it is characterized in that:It is on the reinforcing bar I (1) described in turning in processing Right-hand thread section and reinforcing bar II (3) on left-hand thread section when, the length of thread segment is respectively increased into the ㎜ of 20 ㎜~25 than design length, I.e. the length of screw thread lengthening section is 20~25 ㎜, meanwhile, the left-hand thread section on turning reinforcing bar II (3) is together with screw thread lengthening section During, the diameter in turning screw thread bottom footpath is:From left to right by the standard value less than bottom footpath gradually to equal to or more than bottom footpath Standard value, i.e., the depth in turning screw thread bottom footpath is from left to right by most deep gradually to most shallow, the right side on turning reinforcing bar I (1) During thread segment is together with screw thread lengthening section, the diameter in turning screw thread bottom footpath is:From right-to-left by the standard less than bottom footpath Value gradually arrives the standard value equal to or more than bottom footpath, i.e. the depth in turning screw thread bottom footpath is:From right-to-left by most it is deep gradually to It is most shallow, when reinforcing bar I (1), reinforcing bar II (3) correspondence are angled into reinforced bar sleeve (2), run into the steel of reinforced bar sleeve (2) one end The screw-in length of muscle I (1) or reinforcing bar II (3) is below standard punctual, or because resistance can not continue to screw in greatly very much when, reinforced bar sleeve (2) The reinforcing bar II (3) or reinforcing bar I (1) of the other end make to support between reinforcing bar I (1) and reinforcing bar II (3) with regard to that can increase the length of its screw-in Close, make to be completely embedded combination between reinforcing bar I (1), reinforcing bar II (3) and reinforced bar sleeve (2).
A kind of ensure the method for the firm connection of reinforced bar sleeve 2. according to claim 1, it is characterised in that this screw thread is lengthened The length of section is 20 ㎜.
A kind of ensure the method for the firm connection of reinforced bar sleeve 3. according to claim 1, it is characterised in that this screw thread bottom footpath Depth most depth be 3mm.
A kind of ensure the method for the firm connection of reinforced bar sleeve 4. according to claim 1, it is characterised in that this screw thread bottom footpath Depth most it is shallow be 2mm.
CN201710343047.1A 2017-05-16 2017-05-16 It is a kind of to ensure the method for the firm connection of reinforced bar sleeve Pending CN106978885A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710343047.1A CN106978885A (en) 2017-05-16 2017-05-16 It is a kind of to ensure the method for the firm connection of reinforced bar sleeve

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710343047.1A CN106978885A (en) 2017-05-16 2017-05-16 It is a kind of to ensure the method for the firm connection of reinforced bar sleeve

Publications (1)

Publication Number Publication Date
CN106978885A true CN106978885A (en) 2017-07-25

Family

ID=59342178

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710343047.1A Pending CN106978885A (en) 2017-05-16 2017-05-16 It is a kind of to ensure the method for the firm connection of reinforced bar sleeve

Country Status (1)

Country Link
CN (1) CN106978885A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110130585A (en) * 2019-05-21 2019-08-16 上海森信建设集团有限公司 A kind of Large-size rebar free end docking facilities and its application method

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101575844A (en) * 2009-06-05 2009-11-11 中国葛洲坝集团股份有限公司 Accurate contraposition connection method of horizontally embedded reinforcing steel bars
KR101223407B1 (en) * 2012-09-11 2013-01-16 고석화 Reinforced seismic coupling structure
JP2013221365A (en) * 2012-04-19 2013-10-28 Tokai Corp Screw type reinforcement joint for deformed bar, and deformed bar with screw
CN205476079U (en) * 2016-01-08 2016-08-17 建研科技股份有限公司 Major diameter reinforcing bar net piece

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101575844A (en) * 2009-06-05 2009-11-11 中国葛洲坝集团股份有限公司 Accurate contraposition connection method of horizontally embedded reinforcing steel bars
JP2013221365A (en) * 2012-04-19 2013-10-28 Tokai Corp Screw type reinforcement joint for deformed bar, and deformed bar with screw
KR101223407B1 (en) * 2012-09-11 2013-01-16 고석화 Reinforced seismic coupling structure
CN205476079U (en) * 2016-01-08 2016-08-17 建研科技股份有限公司 Major diameter reinforcing bar net piece

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110130585A (en) * 2019-05-21 2019-08-16 上海森信建设集团有限公司 A kind of Large-size rebar free end docking facilities and its application method

Similar Documents

Publication Publication Date Title
AU2011250703B2 (en) Anchor module, in particular for mining and tunneling
CN204059345U (en) Preformed pile casing method syndeton
CN204608757U (en) A kind of steel pipe pile pile splicing structure
CN105756190A (en) Fabricated circular steel tube truss tubular joint and machining and manufacturing method thereof
CN105464290A (en) Novel steel bar connection sleeve
CN205348589U (en) One end extrusion anchored half grout sleeve steel bar connection connect
CN108868008A (en) Replaceable screw shell ductility reinforcing steel bar connecting device and installation and replacement method
RU88729U1 (en) BORING PIP JOINT
CN205935417U (en) Take half grout sleeve of threaded connection spare
CN203729498U (en) Vertical reinforcement-steel sleeve but joint connection structure of assembled wall
CN106978885A (en) It is a kind of to ensure the method for the firm connection of reinforced bar sleeve
CN204715628U (en) Bitubular reinforcing steel bar connecting device
CN204311444U (en) For the cottor pin linkage that prestressed concrete pipe pile connects fast
CN203613533U (en) Reinforced prestressed pipe pile
CN105350530A (en) Pipe pile connecting method
CN201706091U (en) Pipe connection component
CN204081278U (en) Split type steel bar sleeve is partly in the milk joint
CN106639165A (en) Butt muff
CN103382727A (en) Sounding pipe for foundation pile detection
CN106592865B (en) Prefabricated concrete lintel
CN204098358U (en) Grout sleeve bar connecting assembly
CN205047167U (en) Big latus rectum spiral drill rod
CN201933614U (en) Welded steel bar threaded joint
CN203066883U (en) Air pipe suspension type gas lift reverse circulation drilling rod
CN204551903U (en) Universal building complete thread reinforcing steel bar and special connector thereof

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
WD01 Invention patent application deemed withdrawn after publication
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20170725