CN106965909B CN201710236215.7A CN201710236215A CN106965909B CN 106965909 B CN106965909 B CN 106965909B CN 201710236215 A CN201710236215 A CN 201710236215A CN 106965909 B CN106965909 B CN 106965909B
Authority
CN
China
Prior art keywords
ship
semi
submarines
submarine
submerged
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201710236215.7A
Other languages
Chinese (zh)
Other versions
CN106965909A (en
Inventor
池洪鹏
郭明明
于海东
田庆园
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Dalian Liaonan Shipyard
Original Assignee
Dalian Liaonan Shipyard
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Dalian Liaonan Shipyard filed Critical Dalian Liaonan Shipyard
Priority to CN201710236215.7A priority Critical patent/CN106965909B/en
Publication of CN106965909A publication Critical patent/CN106965909A/en
Application granted granted Critical
Publication of CN106965909B publication Critical patent/CN106965909B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B63SHIPS OR OTHER WATERBORNE VESSELS; RELATED EQUIPMENT
    • B63BSHIPS OR OTHER WATERBORNE VESSELS; EQUIPMENT FOR SHIPPING 
    • B63B35/00Vessels or similar floating structures specially adapted for specific purposes and not otherwise provided for
    • B63B35/40Vessels or similar floating structures specially adapted for specific purposes and not otherwise provided for for transporting marine vessels
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B63SHIPS OR OTHER WATERBORNE VESSELS; RELATED EQUIPMENT
    • B63BSHIPS OR OTHER WATERBORNE VESSELS; EQUIPMENT FOR SHIPPING 
    • B63B35/00Vessels or similar floating structures specially adapted for specific purposes and not otherwise provided for
    • B63B35/40Vessels or similar floating structures specially adapted for specific purposes and not otherwise provided for for transporting marine vessels
    • B63B2035/405Vessels or similar floating structures specially adapted for specific purposes and not otherwise provided for for transporting marine vessels for carrying submarines

Landscapes

  • Engineering & Computer Science (AREA)
  • Transportation (AREA)
  • Chemical & Material Sciences (AREA)
  • Combustion & Propulsion (AREA)
  • Mechanical Engineering (AREA)
  • Ocean & Marine Engineering (AREA)
  • Jib Cranes (AREA)
  • Placing Or Removing Of Piles Or Sheet Piles, Or Accessories Thereof (AREA)
  • Revetment (AREA)

Abstract

The invention discloses a kind of double ship submarines to haul shipment localization method waterborne, comprising the following steps: A, the acquisition practical offset of submarine, and calculate the deviation of practical offset Yu design size value;B, submarine ballast scheme is determined;C, the position submarine Bai Dun is determined;D, positioning column manufacturing specification and installation site are determined;E, steel instrument reflection target manufacturing specification and reflector plate paste position, direction are determined;F, the stickup height of reflector plate above positioning column is determined;G, add offset between hull and positioning column;H, semi-submerged ship direction is determined;I, two submarines are drawn close to semi-submerged ship simultaneously, and when reaching away from semi-submerged ship cross according to 50m, semi-submerged ship is by bow, stern rope rope band to submarine, while semi-submerged ship starts to float;J, space multistory coordinate basis point is formed.The present invention solves the problems, such as that sea construction without positioning datum point, carries out double ship submarines by the cross-application of measuring instrument function again later and loads positioning measurement work onto ship by establishing space multistory three-dimensional coordinate.

Description

Double ship submarines haul shipment localization method waterborne
Technical field
The present invention relates to a kind of double ship submarines to haul shipment localization method waterborne.
Background technique
In the prior art, the long-distance transport work of submarine be usually by semi-submerged ship haul in the way of complete, submarine Loading and unloading carries out under floating on water state, due to constructing in the water surface without positioning datum point, so during shipment contraposition Locating measurement method complex, only there was a tentative application in the country in terms of single ship haul at present, while haul two The shipment location technology of submarine is still in blank application state at home, and no mature experience can be used for reference.
Summary of the invention
The object of the present invention is to provide a kind of double ship submarines to haul shipment localization method waterborne.
Present invention technical solution used for the above purpose is: a kind of double ship submarines hauls shipment positioning side waterborne Method, comprising the following steps:
A, the practical offset of submarine is acquired, and calculates the deviation of practical offset Yu design size value;
B, submarine ballast scheme is determined;
C, Strength Calculation is carried out to semi-submerged ship, determines the position submarine Bai Dun;
D, force analysis is carried out to submarine, determines positioning column manufacturing specification and installation site;
E, operating environment is analyzed, determines steel instrument reflection target manufacturing specification and reflector plate paste position, direction;
F, according to semi-submerged ship draft, the stickup height of reflector plate above positioning column is determined;
G, according to the practical longitudinal and transverse observation of inclining of submarine, between hull and positioning column plus offset;
H, according to loading onto ship, the wind-force on the same day, wave is high, gushes high, seawater velocity determines semi-submerged ship direction;
I, two submarines are drawn close to semi-submerged ship simultaneously, and when reaching away from semi-submerged ship cross according to 50m, semi-submerged ship is by bow, stern rope rope band Onto submarine, while semi-submerged ship starts to float;
J, using the reflector plate on two total station difference measurement and positioning columns, space multistory coordinate basis point is formed;
K, operator start on ship target carry out continuous precision measurement, and in time notice behaviour ship personnel adjust ship state and Ship state;
L, when semi-submerged ship is floated up to hull distance from bottom in 200mm, semi-submerged ship stops floating, and confirms every measurement number According to after location data is less than 10mm, semi-submerged ship continues to float moment for two submarines while holding up.
In the step G, longitudinal and transverse observation of inclining is no more than 0.5 °, and offset is between 2~6mm.
The step H, wind-force are less than 0.5m less than 15 sections, wave height, gush high 0.3m, the seawater velocity of being less than less than 1 section.
A kind of double ship submarines of the present invention haul shipment localization method waterborne, by establishing space multistory three-dimensional coordinate, solve Sea is constructed without positioning datum point problem, carries out double ship submarine shipment positioning by the cross-application of measuring instrument function again later Measure work.
Specific embodiment
Double ship submarines haul shipment localization method waterborne, specifically include following steps, comprising the following steps: A, acquisition submarine Practical offset, and calculate the deviation of practical offset Yu design size value;B, submarine ballast scheme is determined;C, to semi-submerged ship into Row Strength Calculation determines the position submarine Bai Dun;D, force analysis is carried out to submarine, determines positioning column manufacturing specification and installation Position;E, operating environment is analyzed, determines steel instrument reflection target manufacturing specification and reflector plate paste position, direction;F, root According to semi-submerged ship draft, the stickup height of reflector plate above positioning column is determined;G, according to the practical longitudinal and transverse observation of inclining of submarine, Between hull and positioning column plus offset, longitudinal and transverse observation of inclining are not more than 0.5 °, and offset is between 2~6mm;H, basis The wind-force on the shipment same day, wave is high, gush height, seawater velocity determines semi-submerged ship direction, and wind-force is less than 0.5m less than 15 sections, wave height, gushes Height is less than 0.3m, seawater velocity less than 1 section;I, two submarines are drawn close to semi-submerged ship simultaneously, when reaching away from semi-submerged ship cross according to 50m, Semi-submerged ship is by bow, stern rope rope band to submarine, while semi-submerged ship starts to float;J, measurement and positioning column is distinguished using two total stations On reflector plate, formed space multistory coordinate basis point;K, operator starts to carry out target on ship continuous precision measurement, and Notice behaviour ship personnel adjust ship state and ship state in time;L, when semi-submerged ship is floated up to hull distance from bottom in 200mm, semi-submerged ship Stopping is floated, and confirms every measurement data, and after location data is less than 10mm, semi-submerged ship continues floating moment, and two submarines are same When hold up, the double ship submarines of the present invention haul shipment localization method waterborne, by establishing space multistory three-dimensional coordinate, solve sea and apply Work carries out double ship submarines by the cross-application of measuring instrument function again later and loads positioning measurement work onto ship without positioning datum point problem Make.

Claims (3)

1. a kind of double ship submarines haul shipment localization method waterborne, which comprises the following steps:
A, the practical offset of submarine is acquired, and calculates the deviation of practical offset Yu design size value;
B, submarine ballast scheme is determined;
C, Strength Calculation is carried out to semi-submerged ship, determines the position submarine Bai Dun;
D, force analysis is carried out to submarine, determines positioning column manufacturing specification and installation site;
E, operating environment is analyzed, determines steel instrument reflection target manufacturing specification and reflector plate paste position, direction;
F, according to semi-submerged ship draft, the stickup height of reflector plate above positioning column is determined;
G, according to the practical longitudinal and transverse observation of inclining of submarine, between hull and positioning column plus offset;
H, according to loading onto ship, the wind-force on the same day, wave is high, gushes high, seawater velocity determines semi-submerged ship direction;
I, two submarines are drawn close to semi-submerged ship simultaneously, and when reaching away from semi-submerged ship transfer 50m, semi-submerged ship is by bow, stern rope rope band to diving On ship, while semi-submerged ship starts to float;
J, using the reflector plate on two total station difference measurement and positioning columns, space multistory coordinate basis point is formed;
K, operator starts to carry out continuous precision measurement to target on ship, and notice behaviour ship personnel adjust ship state and ship in time State;
L, when semi-submerged ship is floated up to hull distance from bottom in 200mm, semi-submerged ship stops floating, and confirms every measurement data, After location data is less than 10mm, semi-submerged ship continues to float moment for two submarines while holding up.
2. a kind of double ship submarines according to claim 1 haul shipment localization method waterborne, it is characterised in that: the step In G, longitudinal and transverse observation of inclining is no more than 0.5 °, and offset is between 2~6mm.
3. a kind of double ship submarines according to claim 1 haul shipment localization method waterborne, it is characterised in that: the step H, wind-force are less than 0.5m less than 15 sections, wave height, gush high 0.3m, the seawater velocity of being less than less than 1 section.
CN201710236215.7A 2017-04-12 2017-04-12 Double ship submarines haul shipment localization method waterborne Active CN106965909B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710236215.7A CN106965909B (en) 2017-04-12 2017-04-12 Double ship submarines haul shipment localization method waterborne

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710236215.7A CN106965909B (en) 2017-04-12 2017-04-12 Double ship submarines haul shipment localization method waterborne

Publications (2)

Publication Number Publication Date
CN106965909A CN106965909A (en) 2017-07-21
CN106965909B true CN106965909B (en) 2019-01-29

Family

ID=59332285

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710236215.7A Active CN106965909B (en) 2017-04-12 2017-04-12 Double ship submarines haul shipment localization method waterborne

Country Status (1)

Country Link
CN (1) CN106965909B (en)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109425329B (en) * 2017-08-30 2021-08-17 宝山钢铁股份有限公司 Method for detecting deviation offset of plate blank in heating furnace
CN112504151B (en) * 2020-11-26 2022-04-15 大连辽南船厂 Three-dimensional measurement process method for propeller pitch

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB478253A (en) * 1936-07-14 1938-01-14 George Henry Kreasel Williams Improvements in or relating to ships for carrying other craft
US3807335A (en) * 1972-12-07 1974-04-30 Us Navy Submersible underwater docking concept
GB2007598B (en) * 1977-10-17 1982-05-26 Selmar A S Ing F Hoyer Ellefse Protection of seabed installations
CN202138515U (en) * 2011-05-13 2012-02-08 大连理工大学 Semi-submerged ship formed by configuring transport ship

Family Cites Families (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS59179491A (en) * 1983-03-28 1984-10-12 Mitsui Eng & Shipbuild Co Ltd Outboard lifting device
US8881665B2 (en) * 2011-09-30 2014-11-11 Cggveritas Services Sa Deployment and recovery vessel for autonomous underwater vehicle for seismic survey
FR2989816B1 (en) * 2012-04-19 2014-06-13 Dcns UNDERWATER ELECTRIC POWER GENERATION MODULE WITH MEANS OF PIETEMENT

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB478253A (en) * 1936-07-14 1938-01-14 George Henry Kreasel Williams Improvements in or relating to ships for carrying other craft
US3807335A (en) * 1972-12-07 1974-04-30 Us Navy Submersible underwater docking concept
GB2007598B (en) * 1977-10-17 1982-05-26 Selmar A S Ing F Hoyer Ellefse Protection of seabed installations
CN202138515U (en) * 2011-05-13 2012-02-08 大连理工大学 Semi-submerged ship formed by configuring transport ship

Also Published As

Publication number Publication date
CN106965909A (en) 2017-07-21

Similar Documents

Publication Publication Date Title
CN102167140B (en) Method for measuring continuously-variable load precision of large-scale floating dock in floating state
CN106965909B (en) Double ship submarines haul shipment localization method waterborne
CN106167077B (en) Can autonomous navigation ultra-large type offshore steel structure floating body and its manufacture method
CN102358413A (en) Installation method of full-revolving rudder propeller device with special angle
CN106184609A (en) Semi-spade rudder installation method under half ship floating state
CN101508327A (en) Ro-ro passenger ship incline test method
CN101362557A (en) Slippage shipment method for large scale structure object
CN107226182A (en) A kind of method and system that shift building berth under water of large ship
CN104229099A (en) Offshore engineering vessel loading and launching system and method
CN107621259A (en) A kind of floading condition calibration system and method for immersed tube tunnel final joint
CN102897298B (en) Method for floating, forward shifting, positioning and sitting three bow-stern semi ships in dock
CN110615064B (en) Equipment installation point positioning method of saturated diving system
CN101670882B (en) Method for positioning water floating fall pier of super-huge type segmental dock
CN108382528A (en) A kind of method of ro-ro passenger ship incline test
CN104149932B (en) Ton bulk goods deadwood pre-installs closure workmanship
CN2920818Y (en) Car type electric propelling device and berth mounting structure
KR20110136395A (en) Ship construction method using wooden support allowance
WO2013127042A1 (en) Loading apparatus floating-state control device for land and sea connection and transport, and working method thereof
CN211285747U (en) Underwater foundation bed leveling machine
CN105625484A (en) Deep-water measurement and control system and method for large-size objects
CN107284608B (en) Method for removing field obstacle in transverse repair area
KR101654608B1 (en) Semi-submergible rig and inclining test method thereof
CN202491911U (en) Loading equipment floating state control device for land-sea connection transportation
CN113022808A (en) Ship water gauge measuring method
CN203005705U (en) Water-permeable framework dropping ship provided with multiple steel wire protection ropes in attached mode

Legal Events

Date Code Title Description
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant