CN106948266A - A kind of multistage bridge placing installation and its construction method - Google Patents

A kind of multistage bridge placing installation and its construction method Download PDF

Info

Publication number
CN106948266A
CN106948266A CN201710231774.9A CN201710231774A CN106948266A CN 106948266 A CN106948266 A CN 106948266A CN 201710231774 A CN201710231774 A CN 201710231774A CN 106948266 A CN106948266 A CN 106948266A
Authority
CN
China
Prior art keywords
module
bridge
guide rail
hydraulic cylinder
built
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201710231774.9A
Other languages
Chinese (zh)
Other versions
CN106948266B (en
Inventor
钟爱华
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guangdong Huang Ye Construction Engineering Corp Ltds
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201710231774.9A priority Critical patent/CN106948266B/en
Publication of CN106948266A publication Critical patent/CN106948266A/en
Application granted granted Critical
Publication of CN106948266B publication Critical patent/CN106948266B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

The invention discloses a kind of multistage bridge placing installation and its construction method, including module one, module two, bridge is mounted with the module one, module two and pours built module, set up module device, upper bridge and pour built module.When pouring bridge, built module is poured using upper bridge, and one section of bridge is first poured on bridge pier, module one, module two are sequentially connected by setting up module device, movable bridge pours built module to the required bridge section poured and poured, until being docked with the bridge poured on bridge pier;Beneficial effects of the present invention:The equipment sets up convenient, speed of application soon, greatlys save manpower and materials, improves construction period and efficiency.

Description

A kind of multistage bridge placing installation and its construction method
Technical field
The present invention relates to a kind of multistage bridge placing installation and its construction method, belong to technical field of bridge engineering.
Background technology
Bridge construction is accent in the construction such as mountain area, highway, high-speed railway and overhead road of city, when bridge is poured Need to use support supporting bridge mould, traditional support is generally beam-column type bracket, and beam-column type bracket is mainly reassembling type, its by Foundation, fall rack device, column, crossbeam and longeron composition.It pours completion after-poppet and can not moved, and often pours after one section, Need completely to dismantle support, be transported to it is other need casting position, dismounting, transport and the assembling of support waste substantial amounts of manpower Material resources, have a strong impact on construction period and efficiency.
And for example Patent publication No CN201386251 discloses a kind of traverse displacement unit of beam-column type bracket, including a plurality of installation Flute profile slideway on the basis of transverse direction, each flute profile slideway is equally parallel to each other, the same neighbouring bridge casting position of each section of insertion, beam The bottom of each column of pillar support is pressed with dolly, is inserted in flute profile slideway, can be slided along slideway by dolly, each horizontal On the basis of be mounted on hydraulic cylinder, one end connection dolly of hydraulic cylinder, the other end is fixed on the basis of slideway or transverse direction.Due to Support, by pulling hydraulic cylinder, can be moved to by the casting position of the neighbouring bridge of each section of flute profile slideway insertion along along flute profile slideway The casting position of each neighbouring bridge, completes pouring for each bridge.It can complete pouring for each bridge in the case of not removal bracket Build, the work that the bridge erection in the section that many turnout sections, parallel section etc. are made up of multiple sections of adjacent bridges is poured is greatly reduced Measure and the time, significantly shorten the construction period of many neighbouring bridges, reduce construction cost and improve efficiency of construction.
And for example Patent publication No CN201521115U discloses a kind of beam-column type bracket, and its column is laterally connected firmly with row, together Row longitudinal direction is connected firmly, and forms the entirety of a stable connection, by it is liftable fall rack device support post foundation it is horizontal Extend through laterally adjacent to each bridge casting position.It has been poured after one section of bridge, and falling rack device can drive under support Drop, departs from bridge, then by replacing rack device in the foundation extended laterally, is prolonged by drive devices such as hydraulic cylinders Laterally pulling dolly can move integrally support the casting position of next bridge section to slideway, in the case that it can not be dismantled Entirety moves laterally to neighbouring bridge casting position, shortens the pouring construction cycle of bridge, improves efficiency of construction.
Nowadays, bridge placing installation is mostly bulky, and a large amount of manpowers are needed when pouring or go to build by plant equipment Equipment, is not easy to implement in mountain area, wastes a large amount of manpower and materials, inefficiency.
The content of the invention
The problem of existing instant invention overcomes prior art, it is proposed that a kind of multistage bridge placing installation and its side of pouring Method, the equipment sets up convenient, speed of application soon in mountain area, greatlys save manpower and materials, improves construction period and efficiency.
The concrete technical scheme of the present invention is as follows:
Bridge is mounted with a kind of multistage bridge placing installation, including module one, module two, the module one, module two Pour built module, set up module device, bridge pours built module on bridge pier;
The module one includes panel one, and the bottom even of panel one is provided with hydraulic cylinder one, the both sides of panel one Guide rail two is laid with from top to bottom, set up module guide rail one, module groove column, guide rail one;The erection module guide rail one is with leading Clasp one is installed between rail one;It is provided with the clasp one in attachment means one, the attachment means one and spring is installed One;
The module two includes panel two, and the bottom even of panel two is provided with hydraulic cylinder two, the both sides of panel two Guide rail three is laid with from top to bottom, module guide rail two, module projection column, guide rail four is set up, and the erection module guide rail two is with leading Clasp two is installed between rail four;The clasp two is buckled into attachment means one, makes the connection of both module one and module two;
The bridge, which pours built module, includes bridge concrete template, and the bridge concrete template both sides are separately installed with outstanding Connecting rod, guide rail five, base are hung, the hanging connecting rod is provided with above and below hydraulic cylinder three, the hanging connecting rod by hinge one and installed There are directive wheel group one, directive wheel group two;
The erection module device includes connecting rod set, and butt end is installed between connecting rod set top, the butt end and installed There is hydraulic cylinder six, dolly plate is connected by hinge two with connecting rod set, and the dolly plate side is provided with directive wheel one;The bridge pier Upper bridge, which pours built module, includes concrete blinding on bridge pier, is connected by hinge three with concrete blinding on bridge pier, the hydraulic pressure The other end of cylinder seven connection directive wheel group five;
Preferably, it is laid with concreting hole in the module one and module two.
Preferably, the bridge, which is poured, is provided with plug-in type vibrating device on the base of built module both sides, described plug-in type is shaken Dynamic device includes motor one, and the motor one connects telescopic vibrating head by support;
Preferably, the bridge, which is poured, is mounted with bridge surface vibration apparatus for leveling on the guide rail five of built module;The bridge face Vibration leveling apparatus includes being provided with motor two in vibration plate face, the vibration plate face, and the vibration plate face passes through hydraulic cylinder four It is connected with directive wheel two;
Preferably, the attachment means one open the spring one for separating module one and module two provided with energy itself;
Present invention also offers a kind of multistage bridge placing installation construction method, comprise the following steps:
1) reinforcing bar is laid between adjacent two bridge pier, and on bridge pier installs bridge and pour built module and pour one section of bridge Beam, forms one section of bridge floor one;
2) after after bridge finally solidification, laying hydraulic cylinder is in the lump in the mould placed over of hydraulic cylinder one laid on bridge floor Block one;
3) hydraulic cylinder two is uniformly laid in the front side of module one and module two is laid on hydraulic cylinder two, by module projection column Module groove column is inserted, attachment means one is inserted in the clasp one of module one and the clasp two of module two, makes module one and mould Block two is connected;
4) bridge is poured into built module to be laid in below the bridge floor one poured, is directed to wheel group one and is caught in guide rail two, will lead Guide rail one is caught in wheel group two, bridge is poured built module and can freely be slided in module one and module two;
5) module device will be set up to be arranged in module one, and will be directed to wheel one and is stuck in erection module guide rail one, make erection Module device can be slided freely in module one and module two;
6) bridge is laid on adjacent bridge pier and pours built module, opening attachment means one makes two points of module one and module From;
7) module device will be set up first to fix, then will set up butt end the stretching by hydraulic cylinder six of module device In the clasp two of contracting insertion module two, module two is pushed to the upper bridge laid on adjacent bridge pier by the elongation covered by controls connecting rod Beam is poured at built module, directive wheel group five is entered in guide rail three;
8) adjusting module two flushes it with the position that upper bridge pours built module, is blocked simultaneously before and after upper bridge is poured into built module Pour bridge floor two;
9) after the completion of pouring, bridge is poured into the gap that built module is moved between bridge floor one and bridge floor two, bridge floor is carried out Pour, concrete is squeezed into bridge concrete template, mutually tied with bridge surface vibration apparatus for leveling using plug-in type vibrating device The mode of conjunction is vibrated to the bridge poured and leveling forms bridge floor three, and the bridge between bridge pier and bridge pier pours completion.
Brief description of the drawings
Fig. 1 is a kind of structural scheme of mechanism of multistage bridge placing installation of the invention
Fig. 2 is the structural representation of module one;
Fig. 3 is the structural representation of module two;
Fig. 4 pours the structural representation of built module for bridge;
Fig. 5 is the structural representation for setting up module device;
Fig. 6 is the structural representation that bridge pours built module on bridge pier;
Fig. 7 is the schematic diagram of bridge pouring construction of the present invention.
Embodiment
With reference to specific embodiment, the present invention is described in detail.Following examples will be helpful to the technology of this area Personnel further understand the present invention, but the invention is not limited in any way.It should be pointed out that to the ordinary skill of this area For personnel, without departing from the inventive concept of the premise, various modifications and improvements can be made.These belong to the present invention Protection domain.
Embodiment one:
As illustrated, a kind of multistage bridge placing installation, including module 1, module 22, pacify in module 1, module 22 Bridge is equipped with to pour built module 3, set up module device 5, upper bridge and pour built module 6.
Module 1 includes panel 1, and the bottom even of panel 1 is provided with hydraulic cylinder 1, the panel 1 Both sides are laid with guide rail 2 18, set up module guide rail 1, module groove column 15, guide rail 1 from top to bottom;The erection mould Clasp 1 is installed between block guide rail 1 and guide rail 1;Attachment means 1 are installed on the clasp 1;It is described Attachment means 1 open the spring 1 for separating module 1 and module 22 provided with energy itself.
The module 22 includes panel 2 29, and the bottom even of panel 2 29 is provided with hydraulic cylinder 2 21, the panel 2 29 both sides are laid with guide rail 3 22, set up module guide rail 2 26, module projection column 28, guide rail 4 25, the frame from top to bottom If being provided with clasp 2 27 between module guide rail 2 26 and guide rail 4 25;The clasp 2 27 is buckled into attachment means 1, is made The connection of both module 1 and module 22;The module 1 and module 22 are Steel material;The module 1 and module 22 On be laid with concreting hole.The bridge, which pours built module 3, includes bridge concrete template 36, the bridge concrete mould The both sides of plate 36 are separately installed with hanging connecting rod 31, guide rail 5 37, base 38, and the hanging connecting rod 31 is provided with by hinge 1 Hydraulic cylinder 3 35, the hanging connecting rod is provided with directive wheel group 1, directive wheel group 2 33, the base 38 about 31 and installed There is plug-in type vibrating device 7, described plug-in type vibrating device 7 includes motor 1, and the motor 1 is controlled by support 72 Telescopic vibrating head 73 is made to stretch and vibrate.Bridge surface vibration apparatus for leveling 4, bridge surface vibration are installed on the guide rail 5 37 Apparatus for leveling 4, which includes being provided with described in motor 2 44 in vibration plate face 43, the vibration plate face 43, vibrates plate face 43 by hydraulic pressure Cylinder 4 41 is connected with directive wheel 2 42.
The erection module device 5 includes connecting rod set 51, and butt end 55 is installed on connecting rod and covers 51 tops, the butt end 55 Between hydraulic cylinder 6 56 is installed, dolly plate 58 is connected by hinge 2 53 and connecting rod set 51, the side of dolly plate 58 installation There is directive wheel 1.
The upper bridge, which pours built module 6, includes concrete blinding 61 on bridge pier, passes through hinge 3 63 and the phase of hydraulic cylinder 7 62 Connect, the other end of the hydraulic cylinder 7 62 connection directive wheel group 5 64.
In addition present invention also offers a kind of multistage bridge placing installation construction method, including the step of following orders:
1) reinforcing bar is laid between adjacent two bridge pier, and on bridge pier installs bridge and pour built module 6 and pour one section of bridge Beam, forms one section of bridge floor 1;
2) after after bridge finally solidification, hydraulic cylinder 1 and the peace on the hydraulic cylinder 1 laid are laid on bridge floor Put module 1;
3) hydraulic cylinder 2 21 is uniformly laid in the front side of module one and module 22 is laid on hydraulic cylinder 2 21, by module The insertion module groove column of projection column 28 15, attachment means 1 is inserted the clasp 1 of module 1 and the clasp two of module 22 In 27, module 1 is set to be connected with module 22;
4) bridge is poured into built module 3 to be laid in below the bridge floor 1 poured, is directed to wheel group 1 and is caught in guide rail two 18, it is directed to wheel group 2 33 and is caught in guide rail 1, bridge is poured built module 3 and can freely be slided in module 1 and module 22 It is dynamic;
5) module device 5 will be set up to be arranged in module 1, and will be directed to wheel 1 and is stuck in erection module guide rail 1, Erection module device 5 is set freely to be slided in module 1 and module 22;
6) bridge is laid on adjacent bridge pier and pours built module 6, opening attachment means 1 makes module 1 and module two 2 separation;
7) module device 5 will be set up first to fix, the butt end 55 for setting up module device 5 is then passed through into hydraulic cylinder six In the clasp 2 27 of 56 flexible insertion module 22, module 22 is pushed to by adjacent bridge pier by the elongation of controls connecting rod set 51 The upper bridge of upper laying is poured at built module 6, directive wheel group 5 64 is entered in guide rail 3 22;
8) adjusting module 22 flushes it with the position that upper bridge pours built module 6, is blocked up before and after upper bridge is poured into built module 6 Firmly and pour bridge floor 2 200;
9) after the completion of pouring, bridge is poured into the gap that built module 3 is moved between bridge floor 1 and bridge floor 2 200, entered Row bridge floor is poured, and concrete is squeezed into bridge concrete template 36, and concrete is carried out first by plug-in type vibrating device 7 Vibration, controls telescopic vibrating head 73 to insert and is vibrated in concrete by motor 1, when not producing bubble on concrete Also after not sinking, vibrated and flattened using 4 pairs of bridges poured of bridge surface vibration apparatus for leveling, by controlling hydraulic pressure Cylinder 41 makes the vibration plate face 43 be fitted with bridge floor, and controlled motor 2 44 makes the vibration plate face produce vibration, controls directive wheel 2 42 Vibration plate face 43 is moved back and forth on guide rail 5 39 makes bridge floor vibration leveling, and the bridge poured is vibrated and shape is flattened Into bridge floor 3 300, the bridge between bridge pier and bridge pier pours completion.
Embodiment two:
As illustrated, a kind of multistage bridge placing installation, including module 1, module 22, pacify in module 1, module 22 Bridge is equipped with to pour built module 3, set up module device 5, upper bridge and pour built module 6.
Module 1 includes panel 1, and the bottom even of panel 1 is provided with hydraulic cylinder 1, the panel 1 Both sides are laid with guide rail 2 18, set up module guide rail 1, module groove column 15, guide rail 1 from top to bottom;The erection mould Clasp 1 is installed between block guide rail 1 and guide rail 1;Attachment means 1 are installed on the clasp 1;It is described Attachment means 1 open the spring 1 for separating module 1 and module 22 provided with energy itself.
The module 22 includes panel 2 29, and the bottom even of panel 2 29 is provided with hydraulic cylinder 2 21, the panel 2 29 both sides are laid with guide rail 3 22, set up module guide rail 2 26, module projection column 28, guide rail 4 25, the frame from top to bottom If being provided with clasp 2 27 between module guide rail 2 26 and guide rail 4 25;The clasp 2 27 is buckled into attachment means 1, is made The connection of both module 1 and module 22;The module 1 and module 22 are Steel material, the module 1 and module 22 On be laid with concreting hole.The hydraulic cylinder 1 under hydraulic cylinder 2 21 with being equipped with rubber blanket 8.
The bridge, which pours built module 3, includes bridge concrete template 36, and the both sides of bridge concrete template 36 are pacified respectively Equipped with hanging connecting rod 31, guide rail 5 37, base 38, the hanging connecting rod 31 is provided with hydraulic cylinder 3 35, institute by hinge 1 State hanging connecting rod and be provided with about 31 on directive wheel group 1, directive wheel group 2 33, the base 38 and plug-in type vibrating is installed Device 7, described plug-in type vibrating device 7 includes motor 1, and the motor 1 controls telescopic vibration by support 72 Rod 73 is flexible and vibrates.Bridge surface vibration apparatus for leveling 4 is installed, bridge surface vibration apparatus for leveling 4 is wrapped on the guide rail 5 37 Include to be provided with described in motor 2 44 in vibration plate face 43, the vibration plate face 43 and vibrate plate face 43 by hydraulic cylinder 4 41 with being oriented to 2 42 are taken turns to be connected.
The erection module device 5 includes connecting rod set 51, and butt end 55 is installed on connecting rod and covers 51 tops, the butt end 55 Between hydraulic cylinder 6 56 is installed, dolly plate 58 is connected by hinge 2 53 and connecting rod set 51, the side of dolly plate 58 installation There is directive wheel 1, erection module device 5 bottom is provided between base 57, base 57 and the connecting rod set 51 and is provided with Hydraulic cylinder 54.
The upper bridge, which pours built module 6, includes concrete blinding 61 on bridge pier, passes through hinge 3 63 and the phase of hydraulic cylinder 7 62 Connect, the other end of the hydraulic cylinder 7 62 connection directive wheel group 5 64.
In addition present invention also offers a kind of multistage bridge placing installation construction method, including the step of following orders:
1) reinforcing bar is laid between adjacent two bridge pier, and on bridge pier installs bridge and pour built module 6 and pour one section of bridge Beam, forms one section of bridge floor 1;
2) after after bridge finally solidification, hydraulic cylinder 1 is laid on bridge floor, the bottom of hydraulic cylinder 1 is equipped with rubber blanket 8, and in the module 1 placed over of hydraulic cylinder 1 laid;
3) hydraulic cylinder 2 21 is uniformly laid in the front side of module one, the bottom of hydraulic cylinder 2 21 is also equipped with rubber blanket 8, and Module 22 is laid on hydraulic cylinder 2 21, module projection column 28 is inserted into module groove column 15, attachment means 1 are inserted into module In one 1 clasp 1 and the clasp 2 27 of module 22, module 1 is set to be connected with module 22;
4) bridge is poured into built module 3 to be laid in below the bridge floor 1 poured, is directed to wheel group 1 and is caught in guide rail two 18, it is directed to wheel group 2 33 and is caught in guide rail 1, bridge is poured built module 3 and can freely be slided in module 1 and module 22 It is dynamic;
5) module device 5 will be set up to be arranged in module 1, and will be directed to wheel 1 and is stuck in erection module guide rail 1, Erection module device 5 is set freely to be slided in module 1 and module 22;
6) bridge is laid on adjacent bridge pier and pours built module 6, opening attachment means 1 makes module 1 and module two 2 separation;
7) module device 5 will be set up first to fix, the butt end 55 for setting up module device 5 is then passed through into hydraulic cylinder six In the clasp 2 27 of 56 flexible insertion module 22, module 22 is pushed to by adjacent bridge pier by the elongation of controls connecting rod set 51 The upper bridge of upper laying is poured at built module 6, by lifting the hydraulic cylinder 54 set up on module device 5, enters directive wheel group 5 64 Enter in guide rail 3 22;
8) adjusting module 22 flushes it with the position that upper bridge pours built module 6, is blocked up before and after upper bridge is poured into built module 6 Firmly and pour bridge floor 2 200;
9) after the completion of pouring, bridge is poured into the gap that built module 3 is moved between bridge floor 1 and bridge floor 2 200, entered Row bridge floor is poured, and concrete is squeezed into bridge concrete template 36, and concrete is carried out first by plug-in type vibrating device 7 Vibration, controls telescopic vibrating head 73 to insert and is vibrated in concrete by motor 1, when not producing bubble on concrete Also after not sinking, vibrated and flattened using 4 pairs of bridges poured of bridge surface vibration apparatus for leveling, by controlling hydraulic pressure Cylinder 41 makes the vibration plate face 43 be fitted with bridge floor, and controlled motor 2 44 makes the vibration plate face produce vibration, controls directive wheel 2 42 Vibration plate face 43 is moved back and forth on guide rail 5 39 makes bridge floor vibration leveling, and the bridge poured is vibrated and shape is flattened Into bridge floor 3 300, the bridge between bridge pier and bridge pier pours completion.
Embodiment three:
As illustrated, a kind of multistage bridge placing installation, including module 1, module 22, pacify in module 1, module 22 Bridge is equipped with to pour built module 3, set up module device 5, upper bridge and pour built module 6.
Module 1 includes panel 1, and the bottom even of panel 1 is provided with hydraulic cylinder 1, the panel 1 Both sides are laid with guide rail 2 18, set up module guide rail 1, module groove column 15, guide rail 1 from top to bottom;The erection mould Clasp 1 is installed between block guide rail 1 and guide rail 1;Attachment means 1 are installed on the clasp 1;It is described Attachment means 1 open the spring 1 for separating module 1 and module 22, the module groove column 15 provided with energy itself It is provided with hasp hole 151.
The module 22 includes panel 2 29, and the bottom even of panel 2 29 is provided with hydraulic cylinder 2 21, the panel 2 29 both sides are laid with guide rail 3 22, set up module guide rail 2 26, module projection column 28, guide rail 4 25, the frame from top to bottom If being provided with clasp 2 27 between module guide rail 2 26 and guide rail 4 25;The clasp 2 27 is buckled into attachment means 1, is made The connection of both module 1 and module 22;The module 1 and module 22 are Steel material, the module 1 and module 22 On be laid with concreting hole, the module projection column 28 is provided with hasp 281.
The hydraulic cylinder 1 under hydraulic cylinder 2 21 with being equipped with rubber blanket 8.
The bridge, which pours built module 3, includes bridge concrete template 36, and the both sides of bridge concrete template 36 are pacified respectively Equipped with hanging connecting rod 31, guide rail 5 37, base 38, the hanging connecting rod 31 is provided with hydraulic cylinder 3 35, institute by hinge 1 State hanging connecting rod and be provided with about 31 on directive wheel group 1, directive wheel group 2 33, the base 38 and plug-in type vibrating is installed Device 7, described plug-in type vibrating device 7 includes motor 1, and the motor 1 controls telescopic vibration by support 72 Rod 73 is flexible and vibrates.Bridge surface vibration apparatus for leveling 4 is installed, bridge surface vibration apparatus for leveling 4 is wrapped on the guide rail 5 37 Include to be provided with described in motor 2 44 in vibration plate face 43, the vibration plate face 43 and vibrate plate face 43 by hydraulic cylinder 4 41 with being oriented to Take turns 2 42 to be connected, the bridge to pour and be provided with searchlight on built module 3.
The erection module device 5 includes connecting rod set 51, and butt end 55 is installed on connecting rod and covers 51 tops, the butt end 55 Between hydraulic cylinder 6 56 is installed, dolly plate 58 is connected by hinge 2 53 and connecting rod set 51, the side of dolly plate 58 installation There is directive wheel 1, erection module device 5 bottom is provided between base 57, base 57 and the connecting rod set 51 and is provided with Hydraulic cylinder 54.
The upper bridge, which pours built module 6, includes concrete blinding 61 on bridge pier, passes through hinge 3 63 and the phase of hydraulic cylinder 7 62 Connect, the other end of the hydraulic cylinder 7 62 connection directive wheel group 5 64.
In addition present invention also offers a kind of multistage bridge placing installation construction method, including the step of following orders:
1) reinforcing bar is laid between adjacent two bridge pier, and on bridge pier installs bridge and pour built module 6 and pour one section of bridge Beam, forms one section of bridge floor 1;
2) after after bridge solidification, hydraulic cylinder 1 is laid on bridge floor, the bottom of hydraulic cylinder 1 is equipped with rubber blanket 8, and In the module 1 placed over of hydraulic cylinder 1 laid;
3) hydraulic cylinder 2 21 is uniformly laid in the front side of module one, the bottom of hydraulic cylinder 2 21 is also equipped with rubber blanket 8, and Module 22 is laid on hydraulic cylinder 2 21, module projection column 28 is inserted into module groove column 15, makes hasp hole 151 and the phase of hasp 281 Even, attachment means 1 are inserted in the clasp 1 of module 1 and the clasp 2 27 of module 22, makes module 1 and module two 2 connections;
4) bridge is poured into built module 3 to be laid in below the bridge floor 1 poured, is directed to wheel group 1 and is caught in guide rail two 18, it is directed to wheel group 2 33 and is caught in guide rail 1, bridge is poured built module 3 and can freely be slided in module 1 and module 22 It is dynamic;
5) module device 5 will be set up to be arranged in module 1, and will be directed to wheel 1 and is stuck in erection module guide rail 1, Erection module device 5 is set freely to be slided in module 1 and module 22;
6) bridge is laid on adjacent bridge pier and pours built module 6, opening attachment means 1 makes module 1 and module two 2 separation;
7) module device 5 will be set up first to fix, the butt end 55 for setting up module device 5 is then passed through into hydraulic cylinder six In the clasp 2 27 of 56 flexible insertion module 22, module 22 is pushed to by adjacent bridge pier by the elongation of controls connecting rod set 51 The upper bridge of upper laying is poured at built module 6, by adjusting the hydraulic cylinder 54 set up on module device 5, enters directive wheel group 5 64 Enter in guide rail 3 22;
8) adjusting module 22 flushes it with the position that upper bridge pours built module 6, is blocked up before and after upper bridge is poured into built module 6 Firmly and pour bridge floor 2 200;
9) after the completion of pouring, bridge is poured into the gap that built module 3 is moved between bridge floor 1 and bridge floor 2 200, entered Row bridge floor is poured, and concrete is squeezed into bridge concrete template 36, and concrete is carried out first by plug-in type vibrating device 7 Vibration, controls telescopic vibrating head 73 to insert and is vibrated in concrete by motor 1, when not producing bubble on concrete Also after not sinking, vibrated and flattened using 4 pairs of bridges poured of bridge surface vibration apparatus for leveling, by controlling hydraulic pressure Cylinder 41 makes the vibration plate face 43 be fitted with bridge floor, and controlled motor 2 44 makes the vibration plate face produce vibration, controls directive wheel 2 42 Vibration plate face 43 is moved back and forth on guide rail 5 39 makes bridge floor vibration leveling, and the bridge poured is vibrated and shape is flattened Into bridge floor 3 300, the bridge between bridge pier and bridge pier pours completion, at night, can open bridge and pour spy on built module 3 Illuminator, convenient construction.
In addition to the implementation, the present invention can also have other embodiment.All use equivalent or equivalent transformation shape Into technical scheme, all fall within the protection domain of application claims.

Claims (6)

1. a kind of multistage bridge placing installation, it is characterised in that:Including module one (1), module two (2), it is characterised in that:It is described Be mounted with module one (1), module two (2) bridge pour built module (3), set up module device (5), upper bridge pour built module (6);
The module one (1) includes panel one (19), and described (19) bottom even of panel one is provided with hydraulic cylinder one (13), described Panel one (19) both sides are laid with guide rail two (18), set up module guide rail one (16), module groove column (15), guide rail from top to bottom One (12);Clasp one (17) is installed between the erection module guide rail one (16) and guide rail one (12);The clasp one (17) On attachment means one (14) are installed, the module groove column (15) is provided with hasp hole (151);
The module two (2) includes panel two (29), and described (29) bottom even of panel two is provided with hydraulic cylinder two (21), described Panel two (29) both sides are laid with guide rail three (22), set up module guide rail two (26), module projection column (28), guide rail from top to bottom Four (25), clasp two (27) is provided between the erection module guide rail two (26) and guide rail four (25);The clasp two (27) Buckle into attachment means one (14), connect both module one (1) and module two (2), the module projection column (28) is provided with Hasp (281);
The module one (1) and module two (2) are Steel material;
The hydraulic cylinder one (13) under hydraulic cylinder two (21) with being equipped with rubber blanket (8);
The bridge, which pours built module (3), includes bridge concrete template (36), bridge concrete template (36) the both sides difference Hanging connecting rod (31), guide rail five (37), base (38) are installed, the hanging connecting rod (31) is provided with liquid by hinge one (34) Cylinder pressure three (35), the hanging connecting rod (31) is provided with directive wheel group one (32), directive wheel group two (33) up and down, and the bridge is poured Built module is provided with searchlight on (3);
The erection module device (5) includes connecting rod set (51), and butt end (55) are installed on connecting rod set (51) top, the docking Hydraulic cylinder six (56) is installed between end (55), dolly plate (58) is connected by hinge two (53) with connecting rod set (51), described small Sweep (58) side is provided with directive wheel one (52), and described erection module device (5) bottom is provided with base (57), the base (57) hydraulic cylinder (54) is installed between connecting rod set (51);
The upper bridge, which pours built module (6), includes concrete blinding (61) on bridge pier, passes through hinge three (63) and hydraulic cylinder seven (62) connect, (62) other end of hydraulic cylinder seven connection directive wheel group five (64).
2. a kind of multistage bridge placing installation according to claim 1, it is characterised in that the module one (1) and module Concreting hole is laid with two (2).
3. a kind of multistage bridge placing installation according to claim 1, it is characterised in that:The bridge pours built module (3) Plug-in type vibrating device (7) is installed, described plug-in type vibrating device (7) includes motor one (71) on two wing bases (38), The motor one (71) connects telescopic vibrating head (73) by support (72).
4. a kind of multistage bridge placing installation according to claim 1 or 2, it is characterised in that:The bridge pours built module (3) bridge surface vibration apparatus for leveling (4) is mounted with guide rail five (39), the bridge surface vibration apparatus for leveling (4) includes shaking Motor two (44) is installed, the vibration plate face (43) passes through hydraulic cylinder four on dynamic plate face (43), the vibration plate face (43) (41) it is connected with directive wheel two (42).
5. a kind of multistage bridge placing installation according to claim 1, it is characterised in that:On the attachment means one (14) Make the spring one (11) of module one (1) and module two (2) separation provided with that itself can open.
6. a kind of multistage bridge placing installation construction method, it is characterised in that comprise the following steps:
1) reinforcing bar is laid between adjacent two bridge pier, and on bridge pier installs bridge and pour built module (6) and pour one section of bridge, Form one section of bridge floor one (100);
2) after bridge finally solidifies, hydraulic cylinder one (13) is laid on bridge floor and in the hydraulic cylinder one (13) laid, hydraulic pressure Cylinder one (13) bottom is equipped with rubber blanket (8), module one (1) placed over;
3) hydraulic cylinder two (21) is uniformly laid in the front side of module one and module two (2), hydraulic pressure are laid on hydraulic cylinder two (21) Cylinder two (21) bottom is also equipped with rubber blanket (8), and module projection column (28) is inserted into module groove column (15), makes hasp hole (151) it is connected with hasp (281), attachment means one (14) is inserted into the clasp one (17) of module one (1) and buckleing for module two (2) In ring two (27), module one (1) is set to be connected with module two (2);
4) bridge is poured into built module (3) to be laid in below the bridge floor one (100) poured, is directed to wheel group one (32) and is caught in guide rail Two (18), are directed to wheel group two (33) and are caught in guide rail one (12), and bridge is poured built module (3) can be in module one (1) and module two (2) can freely it be slided on;
5) module device (5) will be set up to be arranged in module one (1), and will be directed to wheel one (52) and is stuck in erection module guide rail one (16) It is interior, erection module device (5) is freely slided in module one (1) and module two (2) interior energy;
6) bridge is laid on adjacent bridge pier and pours built module (6), opening attachment means one (14) makes module one (1) and module Two (2) are separated;
7) module device (5) will be set up first to fix, the butt end (55) that then will set up module device (5) passes through hydraulic cylinder In the clasp two (27) of the flexible insertion module two (2) of six (56), module two (2) is pushed away by the elongation of controls connecting rod set (51) Move the upper bridge laid on adjacent bridge pier and pour built module (6) place, by lifting the hydraulic cylinder set up on module device (5) (54) directive wheel group five (64), is made to enter in guide rail three (22);
8) adjusting module two (2) flushes it with the position that upper bridge pours built module (6), and it is front and rear that upper bridge is poured into built module (6) Block and pour bridge floor two (200);
9) after the completion of pouring, bridge is poured into the gap that built module (3) is moved between bridge floor one (100) and bridge floor two (200), The casting concrete in bridge concrete template (36), uses plug-in type vibrating device (7) and bridge surface vibration apparatus for leveling (4) The mode being combined is vibrated to the bridge poured and leveling forms bridge floor three (300), the bridge between bridge pier and bridge pier Completion is poured, at night, bridge can be opened and pour searchlight on built module 3, convenient construction.
CN201710231774.9A 2016-04-29 2016-04-29 A kind of multistage bridge placing installation and its construction method Expired - Fee Related CN106948266B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710231774.9A CN106948266B (en) 2016-04-29 2016-04-29 A kind of multistage bridge placing installation and its construction method

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
CN201710231774.9A CN106948266B (en) 2016-04-29 2016-04-29 A kind of multistage bridge placing installation and its construction method
CN201610278146.1A CN105862600B (en) 2016-04-29 2016-04-29 A kind of multistage bridge placing installation and its construction method

Related Parent Applications (1)

Application Number Title Priority Date Filing Date
CN201610278146.1A Division CN105862600B (en) 2016-04-29 2016-04-29 A kind of multistage bridge placing installation and its construction method

Publications (2)

Publication Number Publication Date
CN106948266A true CN106948266A (en) 2017-07-14
CN106948266B CN106948266B (en) 2018-10-12

Family

ID=56629731

Family Applications (2)

Application Number Title Priority Date Filing Date
CN201710231774.9A Expired - Fee Related CN106948266B (en) 2016-04-29 2016-04-29 A kind of multistage bridge placing installation and its construction method
CN201610278146.1A Expired - Fee Related CN105862600B (en) 2016-04-29 2016-04-29 A kind of multistage bridge placing installation and its construction method

Family Applications After (1)

Application Number Title Priority Date Filing Date
CN201610278146.1A Expired - Fee Related CN105862600B (en) 2016-04-29 2016-04-29 A kind of multistage bridge placing installation and its construction method

Country Status (1)

Country Link
CN (2) CN106948266B (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109537430B (en) * 2019-01-18 2023-11-21 中交四公局第十工程有限公司 Guide device for box girder concrete pouring and box girder concrete pouring method

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2008274586A (en) * 2007-04-26 2008-11-13 Kajima Corp Pillar head construction method
JP2009191458A (en) * 2008-02-12 2009-08-27 Jfe Engineering Corp Construction apparatus for bridge, construction method for floor slab, and construction method for bridge
CN102877416A (en) * 2012-10-26 2013-01-16 上海市城市建设设计研究总院 Herring-bone wall body construction method of large-span concrete herring-bone continuous girder bridge and structure thereof
CN203795311U (en) * 2013-11-22 2014-08-27 中铁三局集团有限公司 Multi-leg high pier and slip form construction device
CN104695337A (en) * 2015-01-26 2015-06-10 中交一公局厦门工程有限公司 Self-lifting sliding and turnover construction system and construction method

Family Cites Families (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN100351484C (en) * 2005-11-07 2007-11-28 中建一局建设发展公司 Liftable hydraulic climbing template and construction method thereof
JP4777922B2 (en) * 2007-03-02 2011-09-21 三井住友建設株式会社 Mobile suspension support
CN201521115U (en) * 2009-04-15 2010-07-07 中铁二十二局哈尔滨铁路建设集团有限责任公司 Beam-column type bracket
CN201386251Y (en) * 2009-04-15 2010-01-20 中铁二十二局哈尔滨铁路建设集团有限责任公司 Transverse unit of beam column bracket
CN102900022B (en) * 2012-10-22 2015-09-30 中铁十局集团有限公司 Cable stayed bridge leaning tower hydraulic climbing mould construction method
CN104695335B (en) * 2015-01-15 2016-09-14 中铁四局集团第二工程有限公司 Upstroke movable framework steel bar overall binding lifting construction engineering method and constructing device

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2008274586A (en) * 2007-04-26 2008-11-13 Kajima Corp Pillar head construction method
JP2009191458A (en) * 2008-02-12 2009-08-27 Jfe Engineering Corp Construction apparatus for bridge, construction method for floor slab, and construction method for bridge
CN102877416A (en) * 2012-10-26 2013-01-16 上海市城市建设设计研究总院 Herring-bone wall body construction method of large-span concrete herring-bone continuous girder bridge and structure thereof
CN203795311U (en) * 2013-11-22 2014-08-27 中铁三局集团有限公司 Multi-leg high pier and slip form construction device
CN104695337A (en) * 2015-01-26 2015-06-10 中交一公局厦门工程有限公司 Self-lifting sliding and turnover construction system and construction method

Also Published As

Publication number Publication date
CN105862600A (en) 2016-08-17
CN106948266B (en) 2018-10-12
CN105862600B (en) 2017-06-13

Similar Documents

Publication Publication Date Title
CN106089253B (en) A kind of all-hydraulic template system poured for culvert
CN104594918B (en) Split integrated underground passage steel mold plate trolley and construction method thereof
CN107338727A (en) A kind of overall demolition, installation anticollision wall form and its walking track crane move system
CN104120877B (en) A kind of hydraulic climbing die block system and climbing form method
CN113235472A (en) Concrete placement platform truck is contained to apron
CN108442255A (en) Movable formwork bridge fabrication machine and construction method for cast-in-place bridge fabrication
CN104564104A (en) Trolley system used for tunnel lining
CN109594479A (en) A kind of parallel overpass center anticollision barrier of double width while construct mould bases and method
CN107630709B (en) A kind of construction method of the mobile trolley of bored tunnel construction
CN110629793A (en) Rapid supporting die frame for pipe gallery and construction method thereof
CN107201719B (en) Viaduct anti-collision wall template hoisting transfer machine and anti-collision wall construction method
CN110777674A (en) Hydraulic self-propelled anti-collision wall formwork trolley
CN207633229U (en) Highway prestress concrete box girder mobile formwork
CN108086170B (en) The hole construction method excessively of mobile formwork and mobile formwork
CN104453951B (en) Combined type subway station lining template trolley for baffle
CN206512605U (en) A kind of overall demolition, installation anticollision wall form and its walking track crane move system
CN102268858B (en) Cradle for suspension pouring of arch-type bridge
CN214993219U (en) Concrete placement platform truck is contained to apron
CN205936645U (en) A full liquid die plate system for culvert is pour
CN104929660B (en) Formation and construction set for continuous open-cut tunnel
CN105862600B (en) A kind of multistage bridge placing installation and its construction method
CN206784172U (en) Overpass anti-collision wall formwork hoisting conveyance
CN212026337U (en) Pipe gallery wallboard running construction supporting and dismantling walking system
CN211547804U (en) Cantilever type retaining wall rapid construction device
CN107829374A (en) Highway prestress concrete box girder mobile formwork and construction method of encorbelmenting

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
TA01 Transfer of patent application right

Effective date of registration: 20180903

Address after: 523000 Dongcheng Street, Dongsha Road, Dongsha Road, Dongling Road, Dongling Road, Dongsha Road, Dongguan, Guangdong, 401-402

Applicant after: Guangdong Huang Ye construction engineering corporation, Ltds

Address before: 215600 Jinsha Road, Yang She Town, Zhangjiagang City, Suzhou, Jiangsu

Applicant before: Zhong Aihua

TA01 Transfer of patent application right
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20181012

CF01 Termination of patent right due to non-payment of annual fee