CN106906908A - Colored steel room construction method of installation - Google Patents

Colored steel room construction method of installation Download PDF

Info

Publication number
CN106906908A
CN106906908A CN201710192609.7A CN201710192609A CN106906908A CN 106906908 A CN106906908 A CN 106906908A CN 201710192609 A CN201710192609 A CN 201710192609A CN 106906908 A CN106906908 A CN 106906908A
Authority
CN
China
Prior art keywords
plate
steel
installation
metope
scaffold
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201710192609.7A
Other languages
Chinese (zh)
Inventor
王建武
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Four Seasons Sunshine Container Technology Co Ltd
Original Assignee
Shanghai Four Seasons Sunshine Container Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Four Seasons Sunshine Container Technology Co Ltd filed Critical Shanghai Four Seasons Sunshine Container Technology Co Ltd
Priority to CN201710192609.7A priority Critical patent/CN106906908A/en
Publication of CN106906908A publication Critical patent/CN106906908A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/343Structures characterised by movable, separable, or collapsible parts, e.g. for transport
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Physics & Mathematics (AREA)
  • Electromagnetism (AREA)
  • Mechanical Engineering (AREA)
  • Working Measures On Existing Buildindgs (AREA)

Abstract

The invention discloses a kind of colored steel room construction method of installation, mainly including vertical rod, it is desirable to tamp smooth, the erection of shelf, laying of scaffold board etc. in the basis of scaffold upright rod.The colored steel room construction method of installation that the present invention is provided, with total quality is light, combination flexibly, convenient and quick construction, without secondary decoration, dismounting the resettlement series of advantages such as easily.It is relatively broad storeyed house to be built using color steel, because urban land is nervous, many entity and individual are intended to can be on the premise of larger load not be constituted to original building, add in top room and build 1 layer of house, so put into little situation, both usable floor area is expanded, the heat-insulated and waterproof problem of former roofing is solved again, and every advantage in color steel combination room just meets the demand of user comprehensively.

Description

Colored steel room construction method of installation
Technical field
The present invention relates to a kind of construction method, more particularly, to a kind of colored steel room construction method of installation.
Background technology
Colored steel room is a kind of with light steel as skeleton, with battenboard as cladding, spatial group is carried out with standard module series Close, component is connected by screw bolts, the environmental protection and economy type movable dwellings of novel concept.Assembly and disassembly can be conveniently and efficiently carried out, The universal standardization of temporary building is realized, the facade lighting of environmental protection and energy saving, quickness and high efficiency is set up, one off houses is entered One seriation exploitation, integrated production, supporting supply, can stock and the approved product field that can repeatedly be used in turn.This Invention is related to a kind of colored steel room construction method of installation.
The content of the invention
It is an object of the invention to provide a kind of colored steel room construction method of installation, specially:
1) vertical rod:The basis compacting of the fundamental importance scaffold upright rod of vertical rod is smooth, all the upper thickness 5cm of pad, width The plank of 20cm;
2) the erection requirement of shelf:
Double-pole scaffold vertical rod spacing is 1.5 meters, and joint should mutually stagger, and the spacing of double frame leger is 1.0m, institute There is joint to be docked using clamp is connect, joint location should mutually stagger;Vertical equity bar is arranged on vertical rod inner side, and its length is not less than 3 across vertical equity bar spreading connects the structural specificationses of transverse horizontal bar using sleeve couple, and a horizontal water is set at main contact Flat bar, in double-pole scaffold, the extension by wall one end is not more than 500mm. scaffolds and must be provided with laterally sweeping the floor bar, indulges To sweeping the floor, bar should be fixed in the vertical rod of the lower section of longitudinal bar of sweeping the floor using right-angle coupler;Vertical rod must use wall-connecting piece and building Thing is reliably connected, wall-connecting piece arrangement spacing:Vertical spacing≤4.5m, level interval≤4.5m, rod end is preferably higher by cornice Skin 1.5m, the arrangement of wall-connecting piece is preferably close to node setting, and the distance for deviateing main contact not should be greater than 300mm, should be from bottom first Started setting up at step vertical equity bar;Double-pole scaffold sets bridging with horizontal diagonal brace, and per pass bridging crosses over 4 vertical rods, Per pass bridging width is no less than 4 across and not less than 6m, the inclination angle on brace and ground is between 45-60 degree;
Double-pole scaffold must respectively set one bridging at the two ends of side elevation, and be set by bottom to top is continuous, middle Clear distance is less than 15m between each road bridging, and bridging brace rotary buckle is fixed on stretching for intersecting therewith transverse horizontal bar Go out in end or vertical rod, rotary buckle, center line to main contact, distance no more than 150mm, horizontal diagonal brace should in same internode, by Bottom to top continuously arranges that diagonal brace is not more than 150mm using rotary buckle center line to the distance of main contact in zig-zag type;
3) laying of scaffold board:
Scaffold board uses hardwood plate first, during laying scaffold board, it is necessary to the end socket of two sides, 20cm is cannot be greater than from wall, full paving Plate of taking the lead can not occur, personal mustn't remove scaffold board, work layer scaffold board Ying Manpu, paving are steady, leave metope 120-150mm;
4) external scaffolding peace tears technical safety measures open:
The material that external scaffolding is used:Steel pipe, fastener, prohibit the use of the material of corrosion, deformation, bending, crackle, prick, When tearing scaffold open, enclosing or caution notice should be around set, and sets special messenger and kept an eye on, no admittance for non-workmen, steel pipe scaffold Vertical rod be vertically surely placed on the chock of metab, each tie point must be connected firmly with fastener, ban the use of iron wire colligation, be applied Work operating personnel forbid tossing downwards when material is transmitted, and use rope handling.Upper and lower same working face forbids operation simultaneously, Construction tool will be with good, in case something lost falls to hurting sb.'s feelings;
5) scaffold is removed:
Remove operation carried out by the opposite program for setting up operation, it then follows from top to bottom, first take and tear open afterwards, after take the original first torn open Then, i.e., railing, scaffold board, bridging are first torn open, after tear small cross bar, leger, vertical rod etc. open, enter successively according to the clear principle of a step one OK, forbid up and down while carrying out dismounting operation;When tearing vertical rod open, should first embrace vertical rod and take most latter two button apart again, tear leger open, cut When knife is supportted, middle button should be first torn open, then hold centre, then solve termination button;Wall connecting rod rod member dismounting at an upper portion thereof finishes rear Can remove;Unclamp fastener flat rod member should remove at any time, must not pine hang on frame, remove long pole when answer two people's work compounds, In order to avoid occurring mishap during separate operaton, the rod member pulled down should be hoisted to ground, must not throwing downwards;The bar accessory for being transported to ground should Appointed place, with tearing open with fortune, classification is piled up, and it is clear that the same day tears the same day open;
6) lifeline is set up:
Lifeline maximum outreach 12M, need to increase a vertical rod and fix lifeline during more than 12M;Lifeline gaily decorated basket Luo Xuan Button is tensed, and the vertical arc of maximum is not more than 100MM;Lifeline should soften pad with the part of girder steel sharp edge contact, and lifeline is drawn to be located at and faced Empty face column inner side, must not draw and be located at outside, and lifeline is all not less than 10 millimeters of galvanized steel wire rope, lifeline using diameter Elastic regulation, gaily decorated basket sieve spinner should be lossless;
The height of lifeline is to be higher by landing ground 1.2M;Rice above work high above the ground, it is necessary to wear safety belt, uses peace every time During full band, label and the quality certification should be checked, check that nylon tape has flawless, whether firm at suture, metalwork whether there is is lacked, split Line and corrosion situation, safety rope should hang in connection ring and use;Safety belt high should hang low use, and prevent from swinging, collide, and avoid point Sharp thing matter, it is impossible to contact naked light, the hook of safety belt, ring should be hung over be tethered on a little securely during operation, be made in low temperature environment When using safety belt, it should be noted that prevent safety belt to be hardened and isolate, visual examination should be often done using frequently safety rope, occurred abnormal When should more renew rope in time, and note plus rope sling problem, it is impossible to safety belt is knotted and is used, safety rope when to avoid impact Disconnected from knotting, safety hook should be hung in connection ring, it is impossible to directly hang on safety rope, to avoid safety when falling Rope is cut off, and safety belt should buy situation and be inspected by random samples using after 2 years by batch, and enclosing belt makees static load experimental safe rope and does Impact test, crack-free can be continuing with, and defective work is refused to be continuing with, and the safety rope to sampling must re-replace peace Could be used after full rope.
7) safe fence and safety net are set:
Security isolation region is set below storage bin ceiling hangs prevents non-working person to be strayed into the personnel's injury for causing; Safety net is hung up properly in the next layer of ceiling, prevents personnel's falling accident from occurring.
8) roofing construction of bottom plates method:
Roofing base plate using combined mobile steel pipe frame as operation platform, according to the slope of roof adjust by the height of scaffold Whole, roofing base plate is upper, middle and lower section Q900 templates, and transition joint is received side plate connection, first determines angle brace in purlin during construction using color To beam back gauge, then angle brace is pulled down, base plate self-tapping screw is fixed on purlin, according to the size for measuring on base plate Perforate, then angle brace is installed successively, the half-section base plate in the case where that could be installed after installing receipts side plate is carried out successively.
9) heat-preservation cotton and roofing upper strata board construction method:
The horizontal flatness of plate is should be noted that when roof boarding is installed, first measuring girder steel with steel tape in first block of plate of laying arrives One parallel size on parapet side, and positioned, the width of ridge and cornice should be measured when 3-5 piece roof boardings are laid It is whether consistent, to ensure the parallel of roofing, and ensure 20mm of the maximum slope no more than code requirement.
10) metope flashing plate, ridge cover plate and deformation joint cover plate construction method:
After roof boarding installation, the water-proofing treatment of dripping eaves flashing edge is first done to ridge and cornice, then carry out ridge The installation of cap;
The installation of metope flashing plate, metope flashing plate vertically overlaps 100mm, and without sealing, horizontal direction is overlapped without envelope naturally Glue;
Work and must carry out below inspection in installation process and after finishing:Check whether fixed screw is firm, checks nail Whether position used by sub is consistent, and whether waterstop pad is complete, must not have and come off, damaged and loosening phenomenon;Receipts side at window upper and lower opening The levelness of plate;When pair colored steel larger with physical length deviation carries out on-site cutting, edge can not be jagged, should keep whole Together;Inner panel should avoid especially outside that the abrasion for producing plate surface is contacted with steel construction or purlin surface in hoisting process;If Colored steel coating surface is scratched, and will should be cleaned out at scuffing, is allowed to drying, then with paint coating;After installing, reply is color Plate surface carries out cleaning work, particularly forbids to deposit any metal object on steel plate, in case corrosion steel plate, influences to use the longevity Life;After roofing installation, waterproof detection should be carried out using the method for water drenching experiment, the building node position to closing.
11) when ridge cap is installed, overlap length is not less than 100mm, and is attached with rivet, then installs Deformation joint cover plate, two flangings of deformation joint cover plate are attached fixation with the fixed support rivet on movement joint both sides respectively, After the completion of ridge cover plate and deformation joint cover plate, fluid sealant is completely beaten to all rivets that expose, metope flashing plate work progress is being installed In, output the flashing groove of 10mm × 15mm along the slope of roof apart from the height of side wave peak heights 250mm in metope first, secondly will Flashing plate flanging is connected with groove junction using M6 expansion bolts, is sealed with fluid sealant to exposing expansion bolt part Treatment;Be fixed on roof board support with roof boarding junction tapping screw, and using elongated backwater adhesive tape to flashing plate with Roof boarding seam crossing carries out water-proofing treatment.
12) construction method of gutter:
Stainless steel gutter carries out butt welding using argon arc welding, thermal deformation occurs to avoid weld, at butt joint between elder generation Disconnected formula spot welding, until joint dock completely it is smooth after again by its full weld, gutter seat and beam end, inserted using cutting seam with wall Enter to break marine glue, plant nail and fix, installed successively;
If gutter plate color steel, its lap of splice is 200mm, and imposes twice sealing, and position is respectively away from mutually overlap joint Two boards edge 15mm, and with the fixed position of waterproof rivet, waterproof rivet twice, single central row is staggered away from being 80mm Distribution, rivet should be beaten on glue sealing line, and the size that the place of gutter end ought to indicate according to drawing is installed, at gutter drain gully, Fixed with a circle waterproof rivet, rivet pitch 40mm is connected with gutter plate, and imposes twice sealing.
Width should rest in 6mm or so when sealing is extruded, and after lap-joint's sealing extruding, thickness is about 3mm, and width is in 10mm More than, it is long that often pipe sealing 300ml about beats 12m, sealing centre-to-centre spacing edges of boards 15mm or so, and colored steel protection plastics are must be driven off before gluing Film, and surface wipes are clean.
The receipts side plate and the flashing plate lap of splice of roof boarding are 150mm, are both needed to apply sealing together.
13) installation of metope colored steel:
Metope color steel is using the compound mounting means in scene:
The installation of wall system color steel, should check mounted metope purlin first, including purlin away from whether and Drawing is consistent, and whether on the same plane, whether purlin anticorrosive coat intact for perpendicularity and levelness, door and window position whether with drawing one Cause, such as find not being inconsistent with drawing, adjust in time or change, it is noted that whether have the purlin of variable cross-section in same facade, such as ask the visitor in Note the joint structure between different cross section;
The installation of wall system color steel:
The laying of colored steel is it is noted that erection sequence, generally bottom-up installation, while avoid left and right two from installing simultaneously, Should be carried out from one end of building to the other end, rib of slab overlap joint should be opposite with local wind direction throughout the year, it is noted that installs first piece The importance of plate;Metope color steel lateral connection only overlaps a rib, and without sealing, it is grafting that colored steel is longitudinally connected, downstream stream side To grafting gap must be tight.
Correct transverse lap mode:
Vertically connection needs 120mm to metope lamina rara externa color steel, without sealing;Vertically overlap joint is 50mm to metope inner panel, without sealing; The fixation of metope outside plate, should be vertical with steel plate and purlin by fixing screws, and is directed at purlin center, per one, rib, apart from crest Lower edge 10mm, answers hanging wire before nailing, screw is beaten point-blank;The fixation of metope inner panel is identical with outside plate, fixed spiral shell Nail is per one, rib;Having at wall coil road hole, wallboard inner side should do reinforcement solutions;5--6 block steel plates are often installed, that is, need to check The flatness at plate two ends, to ensure plate parallel laid;Building negative and positive angle, door, at window hole, the receipts that should be indicated according to drawing Side plate position, size are installed, when installing receipts side plate, it is noted that receive the flatness of side plate.
Dribbing:Punch treatment, inevitably shingle nail or roof boarding is cut in construction, punch place Reason, must be labeled, setting-out before cutting on sheet material;Burr, crimping that the cutting part of plate is produced after dicing etc. should enter Row grinding process.
The present invention has the advantages that relative to prior art:
With total quality is light, combination flexibly, convenient and quick construction, without secondary decoration, dismounting resettlement easily etc. one be Row advantage.Storeyed house is built using color steel relatively broad, because urban land is nervous, many entity and individual are intended to energy On the premise of larger load is not constituted to original building, add in top room and build 1 layer of house, so put into little situation, both Usable floor area is expanded, the heat-insulated and waterproof problem of former roofing is solved again, and every advantage in color steel combination room is just complete Face meets the demand of user.The characteristics of color steel combination room can be moved repeatedly also makes it be widely used in temporary building.Separately Outward, color steel is also widely applied to make the assembled house of multiple use inside industrial premises.
Brief description of the drawings
Fig. 1 is the structural representation in colored steel room.
Specific embodiment
Before construction, first by security official to install and dismounting personnel to carry out detailed rear of confiding a technological secret operable, and Operating personnel should take appointment with certificate.All operating personnels in three step frame level above wear Safety Belt.All instruments are hung over rope With.When setting up shelf, if more than six grades of strong wind and thunderstorm, it is necessary to stop operation.
1) vertical rod:The basis compacting of the fundamental importance scaffold upright rod of vertical rod is smooth, all the upper thickness 5cm of pad, width The plank of 20cm;
2) the erection requirement of shelf:
Double-pole scaffold vertical rod spacing is 1.5 meters, and joint should mutually stagger, and the spacing of double frame leger is 1.0m, institute There is joint to be docked using clamp is connect, joint location should mutually stagger;Vertical equity bar is arranged on vertical rod inner side, and its length is not less than 3 across vertical equity bar spreading connects the structural specificationses of transverse horizontal bar using sleeve couple, and a horizontal water is set at main contact Flat bar, in double-pole scaffold, the extension by wall one end is not more than 500mm. scaffolds and must be provided with laterally sweeping the floor bar, indulges To sweeping the floor, bar should be fixed in the vertical rod of the lower section of longitudinal bar of sweeping the floor using right-angle coupler;Vertical rod must use wall-connecting piece and building Thing is reliably connected, wall-connecting piece arrangement spacing:Vertical spacing≤4.5m, level interval≤4.5m, rod end is preferably higher by cornice Skin 1.5m, the arrangement of wall-connecting piece is preferably close to node setting, and the distance for deviateing main contact not should be greater than 300mm, should be from bottom first Started setting up at step vertical equity bar;Double-pole scaffold sets bridging with horizontal diagonal brace, and per pass bridging crosses over 4 vertical rods, Per pass bridging width is no less than 4 across and not less than 6m, the inclination angle on brace and ground is between 45-60 degree;
Double-pole scaffold must respectively set one bridging at the two ends of side elevation, and be set by bottom to top is continuous, middle Clear distance is less than 15m between each road bridging, and bridging brace rotary buckle is fixed on stretching for intersecting therewith transverse horizontal bar Go out in end or vertical rod, rotary buckle, center line to main contact, distance no more than 150mm, horizontal diagonal brace should in same internode, by Bottom to top continuously arranges that diagonal brace is not more than 150mm using rotary buckle center line to the distance of main contact in zig-zag type;
3) laying of scaffold board:
Scaffold board uses hardwood plate first, during laying scaffold board, it is necessary to the end socket of two sides, 20cm is cannot be greater than from wall, full paving Plate of taking the lead can not occur, personal mustn't remove scaffold board, work layer scaffold board Ying Manpu, paving are steady, leave metope 120-150mm;
4) external scaffolding peace tears technical safety measures open:
The material that external scaffolding is used:Steel pipe, fastener, prohibit the use of the material of corrosion, deformation, bending, crackle, prick, When tearing scaffold open, enclosing or caution notice should be around set, and sets special messenger and kept an eye on, no admittance for non-workmen, steel pipe scaffold Vertical rod be vertically surely placed on the chock of metab, each tie point must be connected firmly with fastener, ban the use of iron wire colligation, be applied Work operating personnel forbid tossing downwards when material is transmitted, and use rope handling.Upper and lower same working face forbids operation simultaneously, Construction tool will be with good, in case something lost falls to hurting sb.'s feelings;
5) scaffold is removed:
Remove operation carried out by the opposite program for setting up operation, it then follows from top to bottom, first take and tear open afterwards, after take the original first torn open Then, i.e., railing, scaffold board, bridging are first torn open, after tear small cross bar, leger, vertical rod etc. open, enter successively according to the clear principle of a step one OK, forbid up and down while carrying out dismounting operation;When tearing vertical rod open, should first embrace vertical rod and take most latter two button apart again, tear leger open, cut When knife is supportted, middle button should be first torn open, then hold centre, then solve termination button;Wall connecting rod rod member dismounting at an upper portion thereof finishes rear Can remove;Unclamp fastener flat rod member should remove at any time, must not pine hang on frame, remove long pole when answer two people's work compounds, In order to avoid occurring mishap during separate operaton, the rod member pulled down should be hoisted to ground, must not throwing downwards;The bar accessory for being transported to ground should Appointed place, with tearing open with fortune, classification is piled up, and it is clear that the same day tears the same day open;
6) lifeline is set up:
Lifeline maximum outreach 12M, need to increase a vertical rod and fix lifeline during more than 12M;Lifeline gaily decorated basket Luo Xuan Button is tensed, and the vertical arc of maximum is not more than 100MM;Lifeline should soften pad with the part of girder steel sharp edge contact, and lifeline is drawn to be located at and faced Empty face column inner side, must not draw and be located at outside, and lifeline is all not less than 10 millimeters of galvanized steel wire rope, lifeline using diameter Elastic regulation, gaily decorated basket sieve spinner should be lossless;
The height of lifeline is to be higher by landing ground 1.2M;Rice above work high above the ground, it is necessary to wear safety belt, uses peace every time During full band, label and the quality certification should be checked, check that nylon tape has flawless, whether firm at suture, metalwork whether there is is lacked, split Line and corrosion situation, safety rope should hang in connection ring and use;Safety belt high should hang low use, and prevent from swinging, collide, and avoid point Sharp thing matter, it is impossible to contact naked light, the hook of safety belt, ring should be hung over be tethered on a little securely during operation, be made in low temperature environment When using safety belt, it should be noted that prevent safety belt to be hardened and isolate, visual examination should be often done using frequently safety rope, occurred abnormal When should more renew rope in time, and note plus rope sling problem, it is impossible to safety belt is knotted and is used, safety rope when to avoid impact Disconnected from knotting, safety hook should be hung in connection ring, it is impossible to directly hang on safety rope, to avoid safety when falling Rope is cut off, and safety belt should buy situation and be inspected by random samples using after 2 years by batch, and enclosing belt makees static load experimental safe rope and does Impact test, crack-free can be continuing with, and defective work is refused to be continuing with, and the safety rope to sampling must re-replace peace Could be used after full rope.
7) safe fence and safety net are set:
Security isolation region is set below storage bin ceiling hangs prevents non-working person to be strayed into the personnel's injury for causing; Safety net is hung up properly in the next layer of ceiling, prevents personnel's falling accident from occurring.
8) roofing construction of bottom plates method:
Roofing base plate using combined mobile steel pipe frame as operation platform, according to the slope of roof adjust by the height of scaffold Whole, roofing base plate is upper, middle and lower section Q900 templates, and transition joint is received side plate connection, first determines angle brace in purlin during construction using color To beam back gauge, then angle brace is pulled down, base plate self-tapping screw is fixed on purlin, according to the size for measuring on base plate Perforate, then angle brace is installed successively, the half-section base plate in the case where that could be installed after installing receipts side plate is carried out successively.
9) heat-preservation cotton and roofing upper strata board construction method:
The horizontal flatness of plate is should be noted that when roof boarding is installed, first measuring girder steel with steel tape in first block of plate of laying arrives One parallel size on parapet side, and positioned, the width of ridge and cornice should be measured when 3-5 piece roof boardings are laid It is whether consistent, to ensure the parallel of roofing, and ensure 20mm of the maximum slope no more than code requirement.
10) metope flashing plate, ridge cover plate and deformation joint cover plate construction method:
After roof boarding installation, the water-proofing treatment of dripping eaves flashing edge is first done to ridge and cornice, then carry out ridge The installation of cap;
The installation of metope flashing plate, metope flashing plate vertically overlaps 100mm, and without sealing, horizontal direction is overlapped without envelope naturally Glue;
Work and must carry out below inspection in installation process and after finishing:Check whether fixed screw is firm, checks nail Whether position used by sub is consistent, and whether waterstop pad is complete, must not have and come off, damaged and loosening phenomenon;Receipts side at window upper and lower opening The levelness of plate;When pair colored steel larger with physical length deviation carries out on-site cutting, edge can not be jagged, should keep whole Together;Inner panel should avoid especially outside that the abrasion for producing plate surface is contacted with steel construction or purlin surface in hoisting process;If Colored steel coating surface is scratched, and will should be cleaned out at scuffing, is allowed to drying, then with paint coating;After installing, reply is color Plate surface carries out cleaning work, particularly forbids to deposit any metal object on steel plate, in case corrosion steel plate, influences to use the longevity Life;After roofing installation, waterproof detection should be carried out using the method for water drenching experiment, the building node position to closing.
11) when ridge cap is installed, overlap length is not less than 100mm, and is attached with rivet, then installs Deformation joint cover plate, two flangings of deformation joint cover plate are attached fixation with the fixed support rivet on movement joint both sides respectively, After the completion of ridge cover plate and deformation joint cover plate, fluid sealant is completely beaten to all rivets that expose, metope flashing plate work progress is being installed In, output the flashing groove of 10mm × 15mm along the slope of roof apart from the height of side wave peak heights 250mm in metope first, secondly will Flashing plate flanging is connected with groove junction using M6 expansion bolts, is sealed with fluid sealant to exposing expansion bolt part Treatment;Be fixed on roof board support with roof boarding junction tapping screw, and using elongated backwater adhesive tape to flashing plate with Roof boarding seam crossing carries out water-proofing treatment.
12) construction method of gutter:
Stainless steel gutter carries out butt welding using argon arc welding, thermal deformation occurs to avoid weld, at butt joint between elder generation Disconnected formula spot welding, until joint dock completely it is smooth after again by its full weld, gutter seat and beam end, inserted using cutting seam with wall Enter to break marine glue, plant nail and fix, installed successively;
If gutter plate color steel, its lap of splice is 200mm, and imposes twice sealing, and position is respectively away from mutually overlap joint Two boards edge 15mm, and with the fixed position of waterproof rivet, waterproof rivet twice, single central row is staggered away from being 80mm Distribution, rivet should be beaten on glue sealing line, and the size that the place of gutter end ought to indicate according to drawing is installed, at gutter drain gully, Fixed with a circle waterproof rivet, rivet pitch 40mm is connected with gutter plate, and imposes twice sealing.
Width should rest in 6mm or so when sealing is extruded, and after lap-joint's sealing extruding, thickness is about 3mm, and width is in 10mm More than, it is long that often pipe sealing 300ml about beats 12m, sealing centre-to-centre spacing edges of boards 15mm or so, and colored steel protection plastics are must be driven off before gluing Film, and surface wipes are clean.
The receipts side plate and the flashing plate lap of splice of roof boarding are 150mm, are both needed to apply sealing together.
13) installation of metope colored steel:
Metope color steel is using the compound mounting means in scene:
The installation of wall system color steel, should check mounted metope purlin first, including purlin away from whether and Drawing is consistent, and whether on the same plane, whether purlin anticorrosive coat intact for perpendicularity and levelness, door and window position whether with drawing one Cause, such as find not being inconsistent with drawing, adjust in time or change, it is noted that whether have the purlin of variable cross-section in same facade, such as ask the visitor in Note the joint structure between different cross section;
The installation of wall system color steel:
The laying of colored steel is it is noted that erection sequence, generally bottom-up installation, while avoid left and right two from installing simultaneously, Should be carried out from one end of building to the other end, rib of slab overlap joint should be opposite with local wind direction throughout the year, it is noted that installs first piece The importance of plate;Metope color steel lateral connection only overlaps a rib, and without sealing, it is grafting that colored steel is longitudinally connected, downstream stream side To grafting gap must be tight.
Correct transverse lap mode:
Vertically connection needs 120mm to metope lamina rara externa color steel, without sealing;Vertically overlap joint is 50mm to metope inner panel, without sealing; The fixation of metope outside plate, should be vertical with steel plate and purlin by fixing screws, and is directed at purlin center, per one, rib, apart from crest Lower edge 10mm, answers hanging wire before nailing, screw is beaten point-blank;The fixation of metope inner panel is identical with outside plate, fixed spiral shell Nail is per one, rib;Having at wall coil road hole, wallboard inner side should do reinforcement solutions;5--6 block steel plates are often installed, that is, need to check The flatness at plate two ends, to ensure plate parallel laid;Building negative and positive angle, door, at window hole, the receipts that should be indicated according to drawing Side plate position, size are installed, when installing receipts side plate, it is noted that receive the flatness of side plate.
Dribbing:Punch treatment, inevitably shingle nail or roof boarding is cut in construction, punch place Reason, must be labeled, setting-out before cutting on sheet material;Burr, crimping that the cutting part of plate is produced after dicing etc. should enter Row grinding process.
Final acceptance of construction:
To collect through supervision & assessment raw material data such as data, arrangement and method for construction of applying for checking and examination, the installation money that installation process is formed Material makes the data report supervision & assessment that applies for checking and examination, while application carries out inspection of quality to our company's working range.
Although the present invention is disclosed as above with preferred embodiment, so it is not limited to the present invention, any this area skill Art personnel, without departing from the spirit and scope of the present invention, when a little modification and perfect, therefore protection model of the invention can be made Enclose when by being defined that claims are defined.

Claims (8)

1. a kind of colored steel room construction method of installation, it is characterised in that:
1) vertical rod:The basis compacting of the fundamental importance scaffold upright rod of vertical rod is smooth, all the upper thickness 5cm of pad, width 20cm's Plank;
2) the erection requirement of shelf:
Double-pole scaffold vertical rod spacing is 1.5 meters, and joint should mutually stagger, and the spacing of double frame leger is 1.0m, Suo Youjie Head is docked using clamp is connect, and joint location should mutually stagger;Vertical equity bar be arranged on vertical rod inner side, its length not less than 3 across, Vertical equity bar spreading connects the structural specificationses of transverse horizontal bar using sleeve couple, and a transverse horizontal is set at main contact Bar, in double-pole scaffold, the extension by wall one end is not more than 500mm. scaffolds and must be provided with laterally sweeping the floor bar, longitudinal direction Bar of sweeping the floor should be fixed in the vertical rod of the lower section of longitudinal bar of sweeping the floor using right-angle coupler;Vertical rod must use wall-connecting piece and building It is reliably connected, wall-connecting piece arrangement spacing:Vertical spacing≤4.5m, level interval≤4.5m, rod end is preferably higher by cornice epithelium 1.5m, the arrangement of wall-connecting piece is preferably close to node setting, and the distance for deviateing main contact not should be greater than 300mm, should be from the bottom first step Started setting up at vertical equity bar;Double-pole scaffold sets bridging with horizontal diagonal brace, and per pass bridging crosses over 4 vertical rods, often Road bridging width is no less than 4 across and not less than 6m, the inclination angle on brace and ground is between 45-60 degree;
Double-pole scaffold must respectively set one bridging at the two ends of side elevation, and be set by bottom to top is continuous, middle each road Clear distance is less than 15m between bridging, and bridging brace rotary buckle is fixed on the external part of intersecting therewith transverse horizontal bar Or in vertical rod, rotary buckle, center line to main contact, distance no more than 150mm, horizontal diagonal brace should be in same internode, the bottom of by extremely Top continuously arranges that diagonal brace is not more than 150mm using rotary buckle center line to the distance of main contact in zig-zag type;
3) laying of scaffold board:
Scaffold board uses hardwood plate first, during laying scaffold board, it is necessary to the end socket of two sides, 20cm is cannot be greater than from wall, and full paving can not There is plate of taking the lead, personal mustn't remove scaffold board, work layer scaffold board Ying Manpu, paving are steady, leave metope 120-150mm;
4) external scaffolding peace tears technical safety measures open:
The material that external scaffolding is used:Steel pipe, fastener, prohibit the use of the material of corrosion, deformation, bending, crackle, prick, tear pin open During hand cradle, should around set enclosing or caution notice, and set special messenger and keep an eye on, no admittance for non-workmen, steel pipe scaffold it is vertical Bar is vertically surely placed on the chock of metab, and each tie point must be connected firmly with fastener, bans the use of iron wire colligation, construction behaviour Make personnel when material is transmitted, forbid tossing downwards, use rope handling.Upper and lower same working face forbids operation simultaneously, construction Instrument will be with good, in case something lost falls to hurting sb.'s feelings;
5) scaffold is removed:
Remove operation carried out by the opposite program for setting up operation, it then follows from top to bottom, first take and tear open afterwards, after take the principle first torn open, i.e., First tear railing, scaffold board, bridging open, after tear small cross bar, leger, vertical rod etc. open, carried out successively according to the clear principle of a step one, sternly Prohibit carries out dismounting operation simultaneously up and down;When tearing vertical rod open, should first embrace vertical rod and take most latter two button apart again, tear leger, bridging open When, should first tear middle button open, centre is then held, then solve termination button;Wall connecting rod rod member dismounting at an upper portion thereof can tear open after finishing Remove;Unclamp fastener flat rod member should remove at any time, must not pine hang on frame, remove long pole when answer two people's work compounds, in order to avoid Occur mishap during separate operaton, the rod member pulled down should be hoisted to ground, must not throwing downwards;The bar accessory for being transported to ground should be specified Place, with tearing open with fortune, classification is piled up, and it is clear that the same day tears the same day open;
6) lifeline is set up:
Lifeline maximum outreach 12M, need to increase a vertical rod and fix lifeline during more than 12M;Lifeline is drawn with gaily decorated basket sieve spinner Tightly, maximum vertical arc is not more than 100MM;Lifeline should soften pad with the part of girder steel sharp edge contact, and lifeline is drawn and is located at free face Column inner side, must not draw and be located at outside, and lifeline is all not less than 10 millimeters of galvanized steel wire rope using diameter, and lifeline is elastic Regulation, gaily decorated basket sieve spinner should be lossless;
The height of lifeline is to be higher by landing ground 1.2M;Rice above work high above the ground, it is necessary to wear safety belt, use of seat belts every time When, should check label and the quality certification, check that nylon tape has flawless, it is whether firm at suture, metalwork whether there is to be lacked, crackle and Corrosion situation, safety rope should hang in connection ring and use;Safety belt high should hang low use, and prevent from swinging, collide, and avoid sharp object Matter, it is impossible to contact naked light, the hook of safety belt, ring should be hung over be tethered on a little securely during operation, and peace is used in low temperature environment During full band, it should be noted that prevent safety belt to be hardened and isolate, visual examination should be often done using frequently safety rope, should when occurring abnormal More renew rope in time, and note plus rope sling problem, it is impossible to safety belt knotting is used, safety rope is from beating when to avoid impact Disconnected at knot, safety hook should be hung in connection ring, it is impossible to directly hang on safety rope, to avoid safety rope quilt when falling Cut off, safety belt should buy situation and be inspected by random samples using after 2 years by batch, and enclosing belt makees static load experimental safe rope and does and impacts Experiment, crack-free can be continuing with, and defective work is refused to be continuing with, and the safety rope to sampling must re-replace safety rope After could use.
7) safe fence and safety net are set:
Security isolation region is set below storage bin ceiling hangs prevents non-working person to be strayed into the personnel's injury for causing;In canopy Push up next layer and hang up properly safety net, prevent personnel's falling accident from occurring.
2. colored steel room as claimed in claim 1 construction method of installation, it is characterised in that:
Roofing construction of bottom plates method:
Using combined mobile steel pipe frame as operation platform, the height of scaffold is adjusted roofing base plate according to the slope of roof, room Face base plate is upper, middle and lower section Q900 templates, and transition joint is received side plate connection, first determines angle brace in purlin to beam during construction using color Back gauge, then pulls down angle brace, and base plate self-tapping screw is fixed on purlin, is opened on base plate according to the size for measuring Hole, then angle brace is installed successively, the half-section base plate in the case where that could be installed after installing receipts side plate is carried out successively.
3. colored steel room as claimed in claim 2 construction method of installation, it is characterised in that:
Heat-preservation cotton and roofing upper strata board construction method:
The horizontal flatness of plate is should be noted that when roof boarding is installed, first girder steel to daughter is measured with steel tape first block of plate is laid One parallel size on wall side, and being positioned, should be measured when 3-5 piece roof boardings are laid ridge and cornice width whether Unanimously, to ensure the parallel of roofing, and 20mm of the maximum slope no more than code requirement is ensured.
4. colored steel room as claimed in claim 3 construction method of installation, it is characterised in that:
Metope flashing plate, ridge cover plate and deformation joint cover plate construction method:
1) after roof boarding installation, the water-proofing treatment of dripping eaves flashing edge is first done to ridge and cornice, then carry out ridge cap The installation of lid;
2) installation of metope flashing plate, metope flashing plate vertically overlaps 100mm, and without sealing, horizontal direction is overlapped without sealing naturally;
3) work and must carry out below the inspection in installation process and after finishing:Check whether fixed screw is firm, checks nail Whether position used is consistent, and whether waterstop pad is complete, must not have and come off, damaged and loosening phenomenon;Receipts side plate at window upper and lower opening Levelness;When pair colored steel larger with physical length deviation carries out on-site cutting, edge can not be jagged, should keep whole Together;Inner panel should avoid especially outside that the abrasion for producing plate surface is contacted with steel construction or purlin surface in hoisting process;If Colored steel coating surface is scratched, and will should be cleaned out at scuffing, is allowed to drying, then with paint coating;After installing, reply is color Plate surface carries out cleaning work, particularly forbids to deposit any metal object on steel plate, in case corrosion steel plate, influences to use the longevity Life;After roofing installation, waterproof detection should be carried out using the method for water drenching experiment, the building node position to closing.
5. colored steel room as claimed in claim 4 construction method of installation, it is characterised in that:
When ridge cap is installed, overlap length is not less than 100mm, and is attached with rivet, then installs movement joint Cover plate, two flangings of deformation joint cover plate are attached fixation with the fixed support rivet on movement joint both sides respectively, in ridge cap After the completion of plate and deformation joint cover plate, fluid sealant is completely beaten to all rivets that expose, in metope flashing plate work progress is installed, first The flashing groove of 10mm × 15mm is outputed along the slope of roof apart from the height of side wave peak heights 250mm in metope, secondly by flashing plate Flanging is connected with groove junction using M6 expansion bolts, and encapsulation process is carried out with fluid sealant to exposing expansion bolt part; It is fixed on roof board support with roof boarding junction tapping screw, and using elongated backwater adhesive tape to flashing plate and roof boarding Seam crossing carries out water-proofing treatment.
6. colored steel room as claimed in claim 5 construction method of installation, it is characterised in that:
The construction method of gutter:
1) stainless steel gutter carries out butt welding using argon arc welding, thermal deformation occurs to avoid weld, is first interrupted at butt joint Formula spot welding, until joint dock completely it is smooth after again by its full weld, gutter seat and beam end, with wall using cutting seam insertion Marine glue is broken, nail is planted and is fixed, installed successively;
If 2) gutter plate color steel, its lap of splice is 200mm, and imposes twice sealing, and position is respectively away from mutual overlap joint Two boards edge 15mm, and with the fixed position of waterproof rivet, waterproof rivet twice, single central row is staggered point away from being 80mm Cloth, rivet should be beaten on glue sealing line, and the size that the place of gutter end ought to indicate according to drawing is installed, at gutter drain gully, with One circle waterproof rivet is fixed, and rivet pitch 40mm is connected with gutter plate, and imposes twice sealing.
3) width should rest in 6mm or so when sealing is extruded, and after lap-joint's sealing extruding, thickness is about 3mm, width 10mm with On, it is long that often pipe sealing 300ml about beats 12m, sealing centre-to-centre spacing edges of boards 15mm or so, colored steel protection plastics is must be driven off before gluing thin Film, and surface wipes are clean.
4) the receipts side plate and the flashing plate lap of splice of roof boarding are 150mm, are both needed to apply sealing together.
7. colored steel room as claimed in claim 6 construction method of installation, it is characterised in that:
The installation of metope colored steel
1) metope color steel is using the compound mounting means in scene:
The installation of wall system color steel, should check mounted metope purlin first, including purlin away from whether and drawing Unanimously, whether on the same plane, whether purlin anticorrosive coat is intact for perpendicularity and levelness, and whether door and window position is consistent with drawing, As found not to be inconsistent with drawing, adjustment in time or change, it is noted that whether have the purlin of variable cross-section in same facade, if any please noting Joint structure between different cross section;
2) installation of wall system color steel:
The laying of colored steel is it is noted that erection sequence, generally bottom-up installation, while avoid left and right two from installing simultaneously, Ying Cong One end of building is carried out to the other end, and rib of slab overlap joint should be opposite with local wind direction throughout the year, it is noted that first block of plate of installation Importance;Metope color steel lateral connection only overlaps a rib, and without sealing, it is grafting that colored steel is longitudinally connected, and Parallel to the flow direction is inserted Connecing gap must be tight.
3) correct transverse lap mode:
Vertically connection needs 120mm to metope lamina rara externa color steel, without sealing;Vertically overlap joint is 50mm to metope inner panel, without sealing;Metope The fixation of outside plate, should be vertical with steel plate and purlin by fixing screws, and is directed at purlin center, following apart from crest per one, rib Edge 10mm, answers hanging wire before nailing, screw is beaten point-blank;The fixation of metope inner panel is identical with outside plate, and fixing screws are every One, rib;Having at wall coil road hole, wallboard inner side should do reinforcement solutions;5--6 block steel plates are often installed, i.e., need to check plate two The flatness at end, to ensure plate parallel laid;Building negative and positive angle, door, at window hole, the receipts side plate that should be indicated according to drawing Position, size are installed, when installing receipts side plate, it is noted that receive the flatness of side plate.
8. colored steel room as claimed in claim 7 construction method of installation, it is characterised in that:
Dribbing:Punch treatment, inevitably shingle nail or roof boarding is cut in construction, punch treatment, cuts Must be labeled on sheet material before cutting, setting-out;Burr, crimping that the cutting part of plate is produced after dicing etc. should be polished Treatment.
CN201710192609.7A 2017-03-28 2017-03-28 Colored steel room construction method of installation Pending CN106906908A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710192609.7A CN106906908A (en) 2017-03-28 2017-03-28 Colored steel room construction method of installation

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710192609.7A CN106906908A (en) 2017-03-28 2017-03-28 Colored steel room construction method of installation

Publications (1)

Publication Number Publication Date
CN106906908A true CN106906908A (en) 2017-06-30

Family

ID=59195849

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710192609.7A Pending CN106906908A (en) 2017-03-28 2017-03-28 Colored steel room construction method of installation

Country Status (1)

Country Link
CN (1) CN106906908A (en)

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108457431A (en) * 2018-02-11 2018-08-28 中国二十冶集团有限公司 The color steel installation method and mounting device of the double-deck colorful plate roof
CN109322489A (en) * 2018-10-17 2019-02-12 广西建工集团第安装有限公司 360 ° of standing-seam profiled sheet construction technologies of one kind and its device
CN111173310A (en) * 2018-11-13 2020-05-19 浙江瑞邦建设工程检测有限公司 Non-stop large steel structure roof reinforcing construction method
CN111809843A (en) * 2020-03-25 2020-10-23 东莞市通成彩钢板有限公司 High resistant various steel sheet that insulates against heat that waits
CN112609911A (en) * 2020-12-04 2021-04-06 刘礼艾 Method for laying and installing color steel plates on roof of steel structure building
CN114837473A (en) * 2022-05-23 2022-08-02 柳州市易泰活动板房有限公司 Two-layer five-ridge four-slope K-shaped movable plank house
CN109322489B (en) * 2018-10-17 2024-07-09 广西建工集团第一安装工程有限公司 Construction process and device for 360-degree vertical overlock profiled steel sheet

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN202635164U (en) * 2012-06-27 2013-01-02 盐城市爱菲尔钢结构有限公司 Roof glass liner insulation structure of edible mushroom room
CN203834823U (en) * 2014-04-30 2014-09-17 湖北福鑫重型钢结构工程股份有限公司 Novel steel plate gutter
CN105133841A (en) * 2015-07-29 2015-12-09 五洋建设集团股份有限公司 Spatial curved surface steel structure pipe truss roof installation construction method
CN205259423U (en) * 2015-12-22 2016-05-25 士兴(福建)钢结构有限公司 Steel construction gable nodal connection structure

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN202635164U (en) * 2012-06-27 2013-01-02 盐城市爱菲尔钢结构有限公司 Roof glass liner insulation structure of edible mushroom room
CN203834823U (en) * 2014-04-30 2014-09-17 湖北福鑫重型钢结构工程股份有限公司 Novel steel plate gutter
CN105133841A (en) * 2015-07-29 2015-12-09 五洋建设集团股份有限公司 Spatial curved surface steel structure pipe truss roof installation construction method
CN205259423U (en) * 2015-12-22 2016-05-25 士兴(福建)钢结构有限公司 Steel construction gable nodal connection structure

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
FF5965738: ""彩板房安装施工设计方案"", 《HTTP://JZ.DOCIN.COM/P-1577297700.HTML》 *

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108457431A (en) * 2018-02-11 2018-08-28 中国二十冶集团有限公司 The color steel installation method and mounting device of the double-deck colorful plate roof
CN109322489A (en) * 2018-10-17 2019-02-12 广西建工集团第安装有限公司 360 ° of standing-seam profiled sheet construction technologies of one kind and its device
CN109322489B (en) * 2018-10-17 2024-07-09 广西建工集团第一安装工程有限公司 Construction process and device for 360-degree vertical overlock profiled steel sheet
CN111173310A (en) * 2018-11-13 2020-05-19 浙江瑞邦建设工程检测有限公司 Non-stop large steel structure roof reinforcing construction method
CN111809843A (en) * 2020-03-25 2020-10-23 东莞市通成彩钢板有限公司 High resistant various steel sheet that insulates against heat that waits
CN112609911A (en) * 2020-12-04 2021-04-06 刘礼艾 Method for laying and installing color steel plates on roof of steel structure building
CN114837473A (en) * 2022-05-23 2022-08-02 柳州市易泰活动板房有限公司 Two-layer five-ridge four-slope K-shaped movable plank house

Similar Documents

Publication Publication Date Title
CN106906908A (en) Colored steel room construction method of installation
CN110259090B (en) Construction method of novel pull-up type overhanging scaffold
CN210236926U (en) Folding type tower crane pedestrian safety passage
CN106284857A (en) A kind of construction technology of aluminium sheet roofing standing-seam system
CN107905536A (en) Glass curtain wall construction method
CN104763109A (en) Quick construction method for pressed bottom tile of large-span steel structure factory building roof
CN107165281A (en) A kind of high-altitude long-span overhung steel platform mould bases construction
CN106703407A (en) Construction method of double-layered shape steel supporting rack of cantilever beam plate
CN205443895U (en) Modular shelter bridge
CN210482770U (en) Roof panel system suitable for installing photovoltaic solar power station
CN110616902A (en) Installation and construction method for metal cored color steel plate of thermal power plant
CN202370263U (en) Roof plate carrier vehicle
CN115306137B (en) Operation platform structure for installing suspended ceiling at bottom of high-altitude corridor and construction method thereof
CN102839803A (en) Construction method for installing decorating and modeling concrete slab
CN110700573A (en) Construction method, device and application of formwork support system adopting steel beam
CN111236603A (en) Comprehensive construction method for steel plate mesh overhanging scaffold
CN106193621A (en) Fabricated construction superimposed sheet string hangs construction method
CN115030518A (en) Sectional integral hoisting method for steel structure coal conveying trestle
CN111608377B (en) Comprehensive construction method for building overhanging scaffold
CN210105398U (en) Portable processing canopy in job site
CN106906909A (en) Template activity board house arrangement and method for construction
Zhenglin et al. Research on Construction Technology for Prefabricated Stone Curtain Wall Base Keel
CN207672441U (en) A kind of integrated steel trusses bolt applies stubborn workbench
CN111608376A (en) Comprehensive construction method for shaping component
CN211850986U (en) Safety rope suspension device for laying profiled metal sheet

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20170630