CN106896749A - construction management client based on BIM technology - Google Patents

construction management client based on BIM technology Download PDF

Info

Publication number
CN106896749A
CN106896749A CN201710142817.6A CN201710142817A CN106896749A CN 106896749 A CN106896749 A CN 106896749A CN 201710142817 A CN201710142817 A CN 201710142817A CN 106896749 A CN106896749 A CN 106896749A
Authority
CN
China
Prior art keywords
server end
module
construction
task
processing module
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201710142817.6A
Other languages
Chinese (zh)
Inventor
伍军
汪清河
陈平
刘文兵
杨铭
黄景新
胡伟
孙中梁
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Tiesiju Civil Engineering Group Co Ltd CTCE Group
Fourth Engineering Co Ltd of CTCE Group
Original Assignee
China Tiesiju Civil Engineering Group Co Ltd CTCE Group
Fourth Engineering Co Ltd of CTCE Group
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Tiesiju Civil Engineering Group Co Ltd CTCE Group, Fourth Engineering Co Ltd of CTCE Group filed Critical China Tiesiju Civil Engineering Group Co Ltd CTCE Group
Priority to CN201710142817.6A priority Critical patent/CN106896749A/en
Publication of CN106896749A publication Critical patent/CN106896749A/en
Pending legal-status Critical Current

Links

Classifications

    • GPHYSICS
    • G05CONTROLLING; REGULATING
    • G05BCONTROL OR REGULATING SYSTEMS IN GENERAL; FUNCTIONAL ELEMENTS OF SUCH SYSTEMS; MONITORING OR TESTING ARRANGEMENTS FOR SUCH SYSTEMS OR ELEMENTS
    • G05B19/00Programme-control systems
    • G05B19/02Programme-control systems electric
    • G05B19/04Programme control other than numerical control, i.e. in sequence controllers or logic controllers
    • HELECTRICITY
    • H04ELECTRIC COMMUNICATION TECHNIQUE
    • H04LTRANSMISSION OF DIGITAL INFORMATION, e.g. TELEGRAPHIC COMMUNICATION
    • H04L67/00Network arrangements or protocols for supporting network services or applications
    • H04L67/50Network services
    • H04L67/55Push-based network services

Landscapes

  • Engineering & Computer Science (AREA)
  • Physics & Mathematics (AREA)
  • General Physics & Mathematics (AREA)
  • Automation & Control Theory (AREA)
  • Computer Networks & Wireless Communication (AREA)
  • Signal Processing (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The invention discloses a construction management client based on a BIM technology, which belongs to the technical field of railway beam yards and comprises the following steps: the system comprises a task processing module and a preview module; the task processing module is connected with the server end to carry out bidirectional communication, and the task processing module executes initiating or closing operation on the process task sent by the server end; the task processing module sends the initiating or closing operation information to the server so that the process task of the server executes the initiating or closing operation information and hangs the information on the BIM model of the box girder with the corresponding number according to the corresponding number principle; the preview module is connected with the server end to preview the beam yard construction information stored by the server end. By utilizing the informatization technology, the defects of large information transmission error and inaccuracy in the construction production process are well overcome. The accuracy and the efficiency of information transmission are greatly improved, and the construction progress is accelerated.

Description

Construction management client based on BIM technology
Technical field
The present invention relates to railway beam field technology field, more particularly to a kind of construction management client based on BIM technology.
Background technology
At present, production management is carried out to railway prefabricated Liang Chang to be mainly by the extensive pattern of traditional people pipe people, is passed through The mode such as phone, oral is exchanged the normality turned into whole construction and production management.This traditional way to manage is present Some defects be:One is, the source of information is not clear and transmission efficiency is low, inaccurate, when going wrong, not clear and definite phase Close person liable.Two are, can cause low construction efficiency, and resource utilization is low, it is impossible to meet scientific rationalization construction production will Ask.Especially in the case where current construction production task weight, duration are compact, how fast and accurately transmission information, raising is applied Work speed is the most important thing.
The content of the invention
It is existing railway prefabricated to solve it is an object of the invention to provide a kind of construction client based on BIM technology Liang Chang in construction and production management, the problem that message can not be transmitted accurately and timely.
To realize object above, the technical solution adopted by the present invention is:A kind of construction management visitor based on BIM technology is provided Family end, including:Task processing module and previewing module;
Task processing module is connected with server end carries out two-way communication, and the operation that task processing module sends to server end is appointed Business is performed to be initiated or closed procedure;
Task processing module will be initiated or closed procedure information is sent to server end so that server end operation tasks carrying is sent out Rise or closed procedure information and the information is articulated on the BIM models of reference numeral box beam according to the numbering principle of correspondence;
Previewing module is connected with server end carries out preview with the beam construction information stored to server end.
Compared with prior art, there is following technique effect in the present invention:The present invention utilizes the reception server end of client The operation task of transmission, and the operation tasks carrying initiation for receiving is acted by client, when operation task is completed, visitor Family end is closed to the operation task and is sent to server end closure information.Closure information is articulated in correspondence by service end On the BIM models of operation task.By using BIM(Building Information Modeling, BIM)With And informationization technology, solve well construction production process in information transmission error it is big, it is inaccurate the drawbacks of.Greatly improve The accuracy rate and efficiency of information transmission, accelerates construction speed.
Brief description of the drawings
Fig. 1 is a kind of structural representation of the construction management client based on BIM technology in one embodiment of the invention;
Fig. 2 is the structural representation of another construction management client based on BIM technology in one embodiment of the invention.
Specific embodiment
With reference to shown in Fig. 1 to Fig. 2, the present invention is described in further detail.
As shown in figure 1, present embodiment discloses a kind of construction management client based on BIM technology, including:
Task processing module 10 and previewing module 20;
Task processing module 10 is connected with server end carries out two-way communication, the work that task processing module 10 sends to server end Sequence task is performed initiates or closed procedure;
Task processing module 10 will be initiated or closed procedure information is sent to server end so that server end operation tasks carrying Be articulated in the information on the BIM models of reference numeral box beam according to the numbering principle of correspondence simultaneously by the information of initiation or closed procedure;
Previewing module 20 is connected with server end carries out preview with the beam construction information stored to server end.
It should be noted that previewing module 20 can enter the overall production status preview of cross girders:Box beam life has been completed as current 175 Pin are produced, plans 200 Pin, remaining 320 Pin, completion rate:35%, overall progress:It is delayed.
Enter cross girders production material preview:Such as current stock's rubble:50 tons, cement:100 tons, water coal ash:20 tons, reinforcing bar 100 tons etc..
Carry out job instruction preview:Such as speed per hour 350km/h Line for Passenger Transportation post-tensioned precast box girder prestressed stretch-draw operations Guiding book.Here job instruction includes two-dimentional guiding book and 3D guiding books.
Carry out preview of confiding a technological secret:Tell somebody what one's real intentions are such as speed per hour 350km/h Line for Passenger Transportation post-tensioned precast box girder Reinforcement binding techniques, Speed per hour 350km/h Line for Passenger Transportation post-tensioned precast box girder concretings are confided a technological secret.
Carry out depositing beam-like condition when front-axle beam:Tooling device seizure condition preview.Such as:Maximum deposits beam 48 Pin, existing 26 Pin, 3- No. 3 pedestal free time, 3-4-2 is idle, and 5# beam making bench is idle, and 2#65 ton gantry crane leaves unused etc..
Carry out product, tooling device current state preview.Such as:The pre- tensioning of 166# box beam current states, 5# beam making bench: 167# box girder webs concrete terminates.4# steel bar binding clamping fixtures:169# case beam steel bar colligations.
Carry out personal information current state preview.Such as:As front-axle beam administrative staff:18, construction teams:5, reinforcing bar is tied up The mutual aid system devised for poor peasants:18 people, concreting work:12 people etc..
Specifically, the detailed process of the work of task processing module 10 in the present embodiment includes:
Beam production task is performed and is initiated or closed procedure:Such as, the reinforcing bar for receiving server end transmission in client is tied up During mutual aid system devised for poor peasants sequence task, perform and initiate operation, after related personnel receives information, carry out operation and prepare to start construction.Tied up in reinforcing bar At the end of bundle, client closes the task by scanning Quick Response Code corresponding with reinforcing bar colligation task.And wait service to be received Next operation assignment instructions that device end is assigned.
Tooling device is performed and enables operation:Opened when such as by Liang Chang beam making bench ×× year ×× month ×× day ×× The beginning ×× # information of prefabricated box -beam is sent to related personnel, after related personnel receives information, proceeds by the standard before operation It is standby.
The notice of the change of plan that the reception server end sends simultaneously is automatically fed to server end after reading.
Personnel, equipment adjustment notice that the reception server end sends.
Specifically, related personnel can be carried out by the previewing module 20 of client to the beam construction information in server Preview, the condition of construction actual accurately to learn Liang Chang in detail.
Further, the client in the present embodiment also includes:The warning module 30 being connected with server end;
Warning module 30 carries out corresponding early warning operation according to the alarm command that server end is pushed, and wherein early warning operation includes storehouse Deposit early warning, maintenance of equipment and inspection early warning and construction times after the early warning of material deficiency, the delayed early warning of speed of application, working procedure Business early warning.
Specifically, the need for beam materials in storage is unsatisfactory for current construction production, server can push prompt message extremely Client, client carries out materials in storage deficiency early warning.
When the practice of construction progress of Liang Chang is compared to the construction plan schedule delay set with server end, server end is pushed away Sending prompt message to client, client carries out early warning after construction speed.
After construction task is pushed to client by server end, if be not received by client within the time of regulation returned The task closure information returned, then judge that workmen does not complete the construction task within the time of regulation, and server push is carried Show information to client, client carries out the delayed early warning of operation.Meanwhile, client receive the prompt message after, by relevant people The reason for member passes through to take pictures or writing record is delayed, such as:Steel flxer sequence can be completed for 8 hours, and the actual operation is held The continuous time is 24 hours, then related personnel can have the reason for remarks:Raw material deficiency etc..After the completion of remarks by client send to Server end.
When server end judges that the access times of equipment will exceed stipulated number, server end pushes prompt message extremely Client, client carries out maintenance of equipment, inspection early warning.
Server, when that can carry out for 8 hours in future, pushes prompt message to client in certain operation task, and client is carried out Task early warning.
Further, the construction management client in the present embodiment also includes:Two-dimensional code generation module 40;
Task processing module 10 is connected to be scanned the Quick Response Code for generating to hold with the transmitting terminal of two-dimensional code generation module 40 The initiation of row operation task or closed procedure.
It should be noted that client is when the operation task that service end sends is received, by two-dimensional code generation module 40 The procedure is initiated or closed to generation Quick Response Code corresponding with the procedure, client by scanning Quick Response Code.
Further, client also includes the database mould for being connected with previewing module 20, two-dimensional code generation module 40 respectively Block 50;
Previewing module 20 carries out preview to the data stored in DBM 50;
Wherein, DBM 50 includes master database, Quick Response Code repository, beam production schedule storehouse, task instruction stack room;
The structural data of the quality guarantee data needed for master data library storage Liang Chang construction productions, the BIM models of caching, construction work Sequence model and production material;
Quick Response Code repository is stored to the Quick Response Code that two-dimensional code generation module is generated;
The beam production schedule library storage beam production schedule, manufacturing program of a year, the season production schedule and manufacturing program of a month;
Job instruction library storage Liang Chang job instruction and Disclosure of invention that all construction is produced.
It should be noted that the construction information by storing Liang Chang in the local DBM 50 of client, so as to In related personnel's quickly and easily preview beam condition of construction.Meanwhile, other clients can be remotely accessed and be cached with Liang Chang The client of construction data, preview is carried out to beam condition of construction.
Further, as shown in Fig. 2 client also includes the change of plan module 60 being connected with server end;
Change of plan module 60 is used to change Liang Chang into product plan according to timing node, and will be carried out the reason for change standby Note the end that uploads onto the server.
Specifically, related personnel initiates the change of construction plan according to the concrete condition that Liang Chang constructs, and is intended to add Fast or delayed the reason for, uploads onto the server end in client remarks.
It should be noted that client also includes the interface that is connected with other systems, such as automatic Tensioning process interface is used to The data in other systems are read, related quality guarantee data is filled in.
The foregoing is only presently preferred embodiments of the present invention, be not intended to limit the invention, it is all it is of the invention spirit and Within principle, any modification, equivalent substitution and improvements made etc. should be included within the scope of the present invention.

Claims (5)

1. a kind of construction management client based on BIM technology, it is characterised in that including:Task processing module(10)And preview Module(20);
Task processing module(10)Being connected with server end carries out two-way communication, task processing module(10)Server end is sent Operation tasks carrying initiate or closed procedure;
Task processing module(10)To initiate or closed procedure information is sent to server end so that server end operation task is held Row initiate or closed procedure information and the information is articulated in the BIM models of reference numeral box beam according to the numbering principle of correspondence On;
Previewing module(20)Be connected with server end carries out preview with the beam construction information stored to server end.
2. client as claimed in claim 1, it is characterised in that also include:The warning module being connected with server end(30);
Warning module(30)The alarm command pushed according to server end carries out corresponding early warning operation, and wherein early warning operation includes Early warning, maintenance of equipment and inspection early warning and construction after the early warning of materials in storage deficiency, the delayed early warning of speed of application, working procedure Task early warning.
3. client as claimed in claim 1 or 2, it is characterised in that also include:Two-dimensional code generation module(40);
Task processing module(10)With two-dimensional code generation module(40)Transmitting terminal connection with to generate Quick Response Code be scanned To perform initiation or the closed procedure of operation task.
4. client as claimed in claim 3, it is characterised in that also include:Respectively and previewing module(20), Quick Response Code generation Module(40)The DBM of connection(50);
Previewing module(20)To DBM(50)The data of middle storage carry out preview;
Wherein, DBM(50)Including master database, Quick Response Code repository, beam production schedule storehouse, job instruction Storehouse;
The structural data of the quality guarantee data needed for master data library storage Liang Chang construction productions, the BIM models of caching, construction work Sequence model and production material;
Quick Response Code repository is stored to the Quick Response Code that two-dimensional code generation module is generated;
The beam production schedule library storage beam production schedule, manufacturing program of a year, the season production schedule and manufacturing program of a month;
Job instruction library storage Liang Chang job instruction and Disclosure of invention that all construction is produced.
5. it is as claimed in claim 4, it is characterised in that the also change of plan module including being connected with server end(60);
Change of plan module(60)For being changed into product plan to Liang Chang according to timing node, and will be carried out the reason for change Remarks upload onto the server end.
CN201710142817.6A 2017-03-10 2017-03-10 construction management client based on BIM technology Pending CN106896749A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710142817.6A CN106896749A (en) 2017-03-10 2017-03-10 construction management client based on BIM technology

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710142817.6A CN106896749A (en) 2017-03-10 2017-03-10 construction management client based on BIM technology

Publications (1)

Publication Number Publication Date
CN106896749A true CN106896749A (en) 2017-06-27

Family

ID=59192549

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710142817.6A Pending CN106896749A (en) 2017-03-10 2017-03-10 construction management client based on BIM technology

Country Status (1)

Country Link
CN (1) CN106896749A (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108427381A (en) * 2017-08-12 2018-08-21 中民筑友科技投资有限公司 A kind of component production process management method and system based on BIM
CN109165869A (en) * 2018-09-14 2019-01-08 广东电网有限责任公司 Construction management and control system and management and control method
CN110363852A (en) * 2019-07-15 2019-10-22 中铁四局集团有限公司 Three-dimensional digital beam field, construction method, computer equipment and storage medium
CN113793000A (en) * 2021-08-31 2021-12-14 广东瀚阳轨道信息科技有限公司 Beam field information processing system, beam field information processing method, computer device, and storage medium

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103679401A (en) * 2013-12-31 2014-03-26 浙江中控研究院有限公司 Flow control method, server, client side and system
CN104537459A (en) * 2014-12-03 2015-04-22 上海同筑信息科技有限公司 BIM-based micro field system and method
CN105184519A (en) * 2015-10-23 2015-12-23 国家电网公司 Standardized safety operation tracing management system
CN105930973A (en) * 2016-04-22 2016-09-07 广州硕品物联网科技有限公司 BIM-based construction site griddization management system and control method thereof
CN106095989A (en) * 2016-06-21 2016-11-09 上海市建筑科学研究院(集团)有限公司 A kind of architectural engineering information switching method based on BIM
JP2017021580A (en) * 2015-07-10 2017-01-26 東芝エレベータ株式会社 BIM system and method

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103679401A (en) * 2013-12-31 2014-03-26 浙江中控研究院有限公司 Flow control method, server, client side and system
CN104537459A (en) * 2014-12-03 2015-04-22 上海同筑信息科技有限公司 BIM-based micro field system and method
JP2017021580A (en) * 2015-07-10 2017-01-26 東芝エレベータ株式会社 BIM system and method
CN105184519A (en) * 2015-10-23 2015-12-23 国家电网公司 Standardized safety operation tracing management system
CN105930973A (en) * 2016-04-22 2016-09-07 广州硕品物联网科技有限公司 BIM-based construction site griddization management system and control method thereof
CN106095989A (en) * 2016-06-21 2016-11-09 上海市建筑科学研究院(集团)有限公司 A kind of architectural engineering information switching method based on BIM

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
孙中梁,等: "基于BIM可视化技术的施工进度管理", 《铁路技术创新》 *

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108427381A (en) * 2017-08-12 2018-08-21 中民筑友科技投资有限公司 A kind of component production process management method and system based on BIM
CN109165869A (en) * 2018-09-14 2019-01-08 广东电网有限责任公司 Construction management and control system and management and control method
CN110363852A (en) * 2019-07-15 2019-10-22 中铁四局集团有限公司 Three-dimensional digital beam field, construction method, computer equipment and storage medium
CN110363852B (en) * 2019-07-15 2023-08-29 中铁四局集团有限公司 Three-dimensional digital beam field, construction method, computer equipment and storage medium
CN113793000A (en) * 2021-08-31 2021-12-14 广东瀚阳轨道信息科技有限公司 Beam field information processing system, beam field information processing method, computer device, and storage medium

Similar Documents

Publication Publication Date Title
CN106896749A (en) construction management client based on BIM technology
CN111210199B (en) Bridge prefab BIM information management system
CN104484524B (en) A kind of method and system interacted based on BIM simulation models with site operation
CN107423865A (en) BIM-based high-speed railway informatization management system
CN110363852B (en) Three-dimensional digital beam field, construction method, computer equipment and storage medium
CN106997511A (en) Railway beam yard management system and railway beam yard management method based on BIM technology
CN111091304A (en) Digital work ticket management and control system and method for power industry
CN107748951A (en) Building engineering construction inspection of quality method and system based on BIM
CN110216789B (en) Intelligent control system of bridge segment prefabrication field
CN106991214A (en) BIM-based informatization management method for high-speed railway precast beam yard
CN102436556B (en) Track traffic accident inversion system
CN105931029A (en) Production management system for girder fabrication yard based on BIM
CN108154308A (en) Power construction process management optimization method and system
WO2019183945A1 (en) Steel bar prefabrication method
CN109034404A (en) A kind of thermal power plant's multi-person synergy examination and repair system based on AR glasses, method and a kind of AR glasses
CN110216788A (en) A kind of Intelligentized control method of bridge subsection precasting yard
CN106127398A (en) A kind of construction costs being applicable to project of transmitting and converting electricity calculates system
Carbonari et al. How Facility Management can use Building Information Modelling (BIM) to improve the decision making process
CN111611292A (en) Supply chain management and control method for assembly type building component
CN107025516A (en) BIM-based information management system for high-speed railway precast beam yard
CN114677117A (en) Building engineering management system and device
Menegon et al. The impact of industry 4.0 concepts and technologies on different phases of construction project lifecycle: a literature review
CN108428110A (en) A kind of acquisition methods of construction-engineering project management information
CN108241816A (en) Assembled architecture quality control system
CN106779490A (en) A kind of Expressway Road maintenance failure management method, apparatus and system

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20170627