CN106892064A - A kind of PVD over-water constructions special purpose ship - Google Patents

A kind of PVD over-water constructions special purpose ship Download PDF

Info

Publication number
CN106892064A
CN106892064A CN201710108174.3A CN201710108174A CN106892064A CN 106892064 A CN106892064 A CN 106892064A CN 201710108174 A CN201710108174 A CN 201710108174A CN 106892064 A CN106892064 A CN 106892064A
Authority
CN
China
Prior art keywords
hull
vehicle frame
plate
special purpose
bar
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201710108174.3A
Other languages
Chinese (zh)
Inventor
梁永根
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
GUANGZHOU SHENGZHOU FOUNDATION ENGINEERING Co Ltd
Original Assignee
GUANGZHOU SHENGZHOU FOUNDATION ENGINEERING Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by GUANGZHOU SHENGZHOU FOUNDATION ENGINEERING Co Ltd filed Critical GUANGZHOU SHENGZHOU FOUNDATION ENGINEERING Co Ltd
Priority to CN201710108174.3A priority Critical patent/CN106892064A/en
Publication of CN106892064A publication Critical patent/CN106892064A/en
Pending legal-status Critical Current

Links

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B63SHIPS OR OTHER WATERBORNE VESSELS; RELATED EQUIPMENT
    • B63BSHIPS OR OTHER WATERBORNE VESSELS; EQUIPMENT FOR SHIPPING 
    • B63B35/00Vessels or similar floating structures specially adapted for specific purposes and not otherwise provided for
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B63SHIPS OR OTHER WATERBORNE VESSELS; RELATED EQUIPMENT
    • B63BSHIPS OR OTHER WATERBORNE VESSELS; EQUIPMENT FOR SHIPPING 
    • B63B21/00Tying-up; Shifting, towing, or pushing equipment; Anchoring
    • B63B21/50Anchoring arrangements or methods for special vessels, e.g. for floating drilling platforms or dredgers
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D7/00Methods or apparatus for placing sheet pile bulkheads, piles, mouldpipes, or other moulds
    • E02D7/02Placing by driving

Landscapes

  • Engineering & Computer Science (AREA)
  • Chemical & Material Sciences (AREA)
  • Ocean & Marine Engineering (AREA)
  • Mechanical Engineering (AREA)
  • Combustion & Propulsion (AREA)
  • Mining & Mineral Resources (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Civil Engineering (AREA)
  • Paleontology (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Investigation Of Foundation Soil And Reinforcement Of Foundation Soil By Compacting Or Drainage (AREA)

Abstract

The invention discloses a kind of PVD over-water constructions special purpose ship, four lifting poles of right-angle position including hull and on hull, four right-angle positions on hull positioned at hull are also respectively provided with two anchor poles and anchor pole winch, some movements are additionally provided with hull to re-pack vehicle frame, each movement to re-pack and be provided with frame rail below vehicle frame, the mobile vehicle frame that re-packs includes vehicle frame base and plate truss, and the side of plate truss is additionally provided with the plate bar that can be lifted along plate truss, and the bottom of the mobile vehicle frame that re-packs be provided with board plug device.This PVD over-water constructions special purpose ship is when beach cofferdam construction is carried out, marine site can be thrown into by by each anchor pole on hull, operate to move hull to required construction location by anchor pole winch, and the plate truss and plate bar by being set on hull quickly raise to realize the installation of drain bar, plate bar can be transferred after installation, and plate truss is lain against on hull meet construction equipment limit for height requirement, this is invented for operation on the sea apparatus field.

Description

A kind of PVD over-water constructions special purpose ship
Technical field
The present invention relates to operation on the sea apparatus field, more particularly to a kind of PVD over-water constructions special purpose ship.
Background technology
When the marine site of near airports carries out cofferdam construction by the sea, have sternly to construction site, construction equipment and engineering time Lattice are limited, daily engineering time only certain between night and morning, the time beyond the engineering time, setting in construction site Standby no more than certain altitude.
And carry out cofferdam construction need insertion drain bar carry out draining, this engineering operation need by higher level auxiliary Building could be completed, and with reference to the site environment that beach is constructed, the auxiliary construction equipment of lifting can quickly be realized within a certain period of time The great accelerating construction progress of energy, and construction cost can be saved.
The content of the invention
It is an object of the invention to provide it is a kind of can fast lifting and can meet beach construction environment PVD over-water constructions it is special Use ship.
The technical solution used in the present invention is:
A kind of PVD over-water constructions special purpose ship, including hull and four lifting poles of right-angle position on hull, lifting pole can be along ship Body oscilaltion, four right-angle positions on hull positioned at hull are also respectively provided with two anchor poles and the anchor pole of each anchor pole of folding and unfolding is twisted respectively Car, is additionally provided with some movements and re-packs vehicle frame on hull, each movement to re-pack and be provided with the vehicle frame for being fixed on hull surface below vehicle frame Guide rail, movement re-packs vehicle frame including that vertically arranged along the vehicle frame base of frame rail movement and above vehicle frame base can insert Plate girder, the side of plate truss is additionally provided with the plate bar that can be lifted along plate truss, and the bottom of the mobile vehicle frame that re-packs is provided with slotting Panel assembly.
The improvement of technical solution of the present invention is further used as, hull is provided with operable lifting pole and carries out rising for lifting action Stake winch, the position of each lifting pole is provided with the piling bar chassis being enclosed within outside lifting pole, the steel that can be pivoted is provided with piling bar chassis Pile protection cylinder, being provided with piling bar sleeve can be to the positioner of lifting pole positioning.
The improvement of technical solution of the present invention is further used as, the bottom of lifting pole is provided with the stake set perpendicular to lifting pole Target.
The improvement of technical solution of the present invention is further used as, the bottom of each plate truss is hinged in vehicle frame base, hull Being provided with some can respectively drive each plate truss that the turntable to rise is rotated around jointed shaft.
The improvement of technical solution of the present invention is further used as, the top of plate bar is provided with fixed pulley, and hull is provided with lifting Turntable, is additionally provided with hoisting gear rope, and one end of hoisting gear rope is fixed on the top of plate bar, the other end of hoisting gear rope It is fixed on hoisting gear frame.
The improvement of technical solution of the present invention is further used as, two anchor poles of a right-angle position pass through anchor respectively on hull Rope is connected on anchor pole winch, and some lead columns are additionally provided with hull, and anchor line bypasses lead column and delivered, and two anchor poles are thrown respectively It is placed on side and the diagonal positions of hull.
The improvement of technical solution of the present invention is further used as, board plug device includes being vertically installed at inserting for plate truss bottom Plate case and some groups of friction pulley pedestals that both sides are symmetrically installed in plugboard box, each friction pulley pedestal include two friction pulleys and with two Friction pulley engagement to drive and pass through chain gear transmission between the driving wheel that two friction pulleys rotate in same direction, two driving wheels being oppositely arranged.
The improvement of technical solution of the present invention is further used as, driving driving wheel is provided with friction pulley pedestal and is leaned on to two friction pulleys Tight compression spring.
The improvement of technical solution of the present invention is further used as, at least three pairs frictions being arranged symmetrically in relation to each other are provided with plugboard box The gap for placing drain bar is left between wheel pedestal, the two friction pulley pedestals being oppositely arranged, positioned at the axis of each friction pulley of homonymy In a vertical lines.
Beneficial effects of the present invention:This PVD over-water constructions special purpose ship, can be by by hull when beach cofferdam construction is carried out Upper each anchor pole is thrown into marine site, operates to move hull to required construction location by anchor pole winch, and by setting on hull Plate truss and plate bar quickly raise to realize the installation of drain bar, can transfer plate bar after installation, and by plate purlin Frame lies against on hull to meet the requirement of construction equipment limit for height.
Brief description of the drawings
The invention will be further described below in conjunction with the accompanying drawings:
Fig. 1 is embodiment of the present invention overall structure front view;
Fig. 2 is embodiment of the present invention overall structure top view;
Fig. 3 is embodiment of the present invention polycrystalline substance schematic diagram;
Fig. 4 is that lifting pole is fixed on view on sea bed in the embodiment of the present invention.
Specific embodiment
1~Fig. 4 of reference picture, the present invention is a kind of PVD over-water constructions special purpose ship, including hull 1 and four on hull 1 The lifting pole 2 of right-angle position, lifting pole 2 can also be respectively provided with along the oscilaltion of hull 1, four right-angle positions on hull 1 positioned at hull 1 Two anchor poles 3 and respectively the anchor pole winch 31 of each anchor pole 3 of folding and unfolding, are additionally provided with some movements and re-pack vehicle frame 4, each movement on hull 1 The re-pack lower section of vehicle frame 4 is provided with the frame rail 41 for being fixed on the surface of hull 1, and movement re-packs that vehicle frame 4 includes can be along frame rail The vehicle frame base and vertically arranged plate truss 42 above vehicle frame base of 41 movements, the side of plate truss 42 is additionally provided with The plate bar 43 that can be lifted along plate truss 42, the bottom of the mobile vehicle frame 4 that re-packs is provided with board plug device.
This PVD over-water constructions special purpose ship can be thrown into sea when beach cofferdam construction is carried out by by each anchor pole 3 on hull 1 Domain, operates to move hull 1 to required construction location, and the plate truss 42 by being set on hull 1 by anchor pole winch 31 Quickly raise to realize the installation of drain bar with plate bar 43, can transfer plate bar 43 after installation, and by plate truss 42 Lie against on hull 1 to meet the requirement of construction equipment limit for height.
Entirely construction includes two operations of installation of the movement of hull 1 and drain bar to the ship that re-packs of this operation on the sea.
Hull 1 is moved through the combination action of anchor pole 3 and anchor pole winch 31 realizing.Workaday constructed at one Cheng Zhong, the number of times moved needed for the ship that re-packs is few, it is necessary to when mobile, the anchor pole 3 on hull 1 be thrown into hull 1 to be moved Direction, restarts the folding and unfolding anchor line of anchor pole winch 31, until the station needed for hull 1 is moved into construction.Then decentralization lifting pole 2 will Hull 1 is consolidated.
Used as the preferred embodiment of the present invention, hull 1 is provided with operable lifting pole 2 and carries out a stake strand of lifting action Car, the position of each lifting pole 2 is provided with the piling bar chassis being enclosed within outside lifting pole 2, and the piling bar that can be pivoted is provided with piling bar chassis Sleeve, being provided with piling bar sleeve can be to the positioner of the positioning of lifting pole 2.
Used as the preferred embodiment of the present invention, the bottom of lifting pole 2 is provided with the stake target 21 set perpendicular to lifting pole 2.
The bottom of lifting pole 2 is provided with a target 21, can be contacted with sea bed to forming construction by hull 1 is firm position by the sea Platform.
Lifting pole 2 is arranged in piling bar sleeve, can be rotated around piling bar chassis with piling bar sleeve, or in piling bar sleeve in fact Now lift, and after liter is down to required position, the positioning between lifting pole 2 and piling bar sleeve is realized by positioner.
Used as the preferred embodiment of the present invention, the bottom of each plate truss 42 is hinged in vehicle frame base, is set on hull 1 Having some can respectively drive each plate truss 42 that the turntable to rise is rotated around jointed shaft.
Used as the preferred embodiment of the present invention, the top of plate bar 43 is provided with fixed pulley, and hull 1 is provided with hoisting gear Frame, is additionally provided with hoisting gear rope, and one end of hoisting gear rope is fixed on the top of plate bar 43, and the other end of hoisting gear rope is consolidated It is scheduled on hoisting gear frame.
Vehicle frame base can be moved in frame rail 41, after required position is moved to, vehicle frame base be positioned, with Plate truss 42 is risen afterwards, and the plate bar 43 on plate truss 42 is risen to by top, just drain bar edge by hoisting gear rope Plate truss 42 and plate bar 43 arranged, plate operation is carried out by board plug device.
Used as the preferred embodiment of the present invention, two anchor poles 3 of a right-angle position are connected by anchor line respectively on hull 1 It is connected on anchor pole winch 31, some lead columns is additionally provided with hull 1, anchor line bypasses lead column and delivered, two anchor poles 3 is thrown respectively It is placed on side and the diagonal positions of hull 1.
Used as the preferred embodiment of the present invention, board plug device includes being vertically installed at the plugboard box of the bottom of plate truss 42 Some groups of friction pulley pedestals being symmetrically installed with the both sides in plugboard box, each friction pulley pedestal includes two friction pulleys and is rubbed with two Wheel engagement to drive and pass through chain gear transmission between the driving wheel that two friction pulleys rotate in same direction, two driving wheels being oppositely arranged.
As the preferred embodiment of the present invention, the pressure for driving driving wheel to be close to two friction pulleys is provided with friction pulley pedestal Power spring.
As the preferred embodiment of the present invention, at least three pairs friction wheel seats being arranged symmetrically in relation to each other are provided with plugboard box The gap for placing drain bar is left between body, the two friction pulley pedestals being oppositely arranged, the axis positioned at each friction pulley of homonymy is located at In one vertical lines.
This board plug device rotates at the same speed in the same direction by the friction pulley in three pairs of friction pulley pedestals being arranged symmetrically in relation to each other Row incremental drain bar inserts installation.
Two friction pulleys in same friction pulley pedestal are driven by same driving wheel, two symmetrical masters By chain gear transmission between driving wheel, chain gear transmission has more preferable transmitting accuracy, can preferably ensure in three pairs of friction pulley pedestals Multiple friction pulleys rotate to install drain bar under conditions of in the same direction at the same speed.So as to ensure that injury will not be produced to drain bar.
Certainly, the invention is not limited to above-mentioned implementation method, and those of ordinary skill in the art are without prejudice to originally Equivalent variations or replacement can be also made on the premise of spirit, these equivalent modifications or replacement are all contained in the application right It is required that in limited range.

Claims (9)

1. a kind of PVD over-water constructions special purpose ship, it is characterised in that:Including hull and four liters of right-angle position on the hull Drop stake, the lifting pole can also be respectively provided with two anchors along hull oscilaltion, four right-angle positions on the hull positioned at hull Bar and respectively the anchor pole winch of each anchor pole of folding and unfolding, are additionally provided with some movements and re-pack vehicle frame on the hull, each movement re-packs It is provided with the frame rail for being fixed on hull surface below vehicle frame, the movement vehicle frame that re-packs includes what can be moved along frame rail Vehicle frame base and vertically arranged plate truss above vehicle frame base, the side of the plate truss is additionally provided with can be along plate The plate bar of truss lifting, the re-pack bottom of vehicle frame of the movement is provided with board plug device.
2. PVD over-water constructions special purpose ship according to claim 1, it is characterised in that:The hull is provided with operable liter Drop stake carries out a stake winch of lifting action, and the position of each lifting pole is provided with the piling bar chassis being enclosed within outside lifting pole, described The piling bar sleeve that can be pivoted is provided with piling bar chassis, being provided with the piling bar sleeve can be to the positioning dress of lifting pole positioning Put.
3. PVD over-water constructions special purpose ship according to claim 2, it is characterised in that:The bottom of the lifting pole is provided with vertical The straight stake target set in lifting pole.
4. PVD over-water constructions special purpose ship according to claim 1, it is characterised in that:The bottom hinge of each plate truss It is connected in vehicle frame base, the hull is provided with and some can respectively drive each plate truss that the winch to rise is rotated around jointed shaft Frame.
5. PVD over-water constructions special purpose ship according to claim 4, it is characterised in that:The top of the plate bar is provided with fixed Pulley, the hull is provided with hoisting gear frame, is additionally provided with hoisting gear rope, and one end of the hoisting gear rope is fixed on plate The top of bar, the other end of the hoisting gear rope is fixed on hoisting gear frame.
6. PVD over-water constructions special purpose ship according to claim 1, it is characterised in that:A right-angle position on the hull Two anchor poles be connected on anchor pole winch by anchor line respectively, be additionally provided with some lead columns on the hull, the anchor line around Cross lead column to be delivered, anchor pole described in two is delivered in the side of hull and diagonal positions respectively.
7. PVD over-water constructions special purpose ship according to claim 1, it is characterised in that:The board plug device includes peace vertically It is each described mounted in the plugboard box of plate truss bottom and both sides are symmetrically installed in the plugboard box some groups of friction pulley pedestals Friction pulley pedestal includes two friction pulleys and the driving wheel for driving two friction pulleys to rotate in same direction is engaged with friction pulley described in two, and two is relative Pass through chain gear transmission between the driving wheel for setting.
8. PVD over-water constructions special purpose ship according to claim 7, it is characterised in that:Drive is provided with the friction pulley pedestal The compression spring that dynamic driving wheel is close to two friction pulleys.
9. PVD over-water constructions special purpose ship according to claim 7, it is characterised in that:At least three are provided with the plugboard box To the friction pulley pedestal being arranged symmetrically in relation to each other, the gap for placing drain bar is left between the two friction pulley pedestals being oppositely arranged, be located at The axis of each friction pulley of homonymy is located in a vertical lines.
CN201710108174.3A 2017-02-27 2017-02-27 A kind of PVD over-water constructions special purpose ship Pending CN106892064A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710108174.3A CN106892064A (en) 2017-02-27 2017-02-27 A kind of PVD over-water constructions special purpose ship

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710108174.3A CN106892064A (en) 2017-02-27 2017-02-27 A kind of PVD over-water constructions special purpose ship

Publications (1)

Publication Number Publication Date
CN106892064A true CN106892064A (en) 2017-06-27

Family

ID=59185308

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710108174.3A Pending CN106892064A (en) 2017-02-27 2017-02-27 A kind of PVD over-water constructions special purpose ship

Country Status (1)

Country Link
CN (1) CN106892064A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112500034A (en) * 2020-11-09 2021-03-16 河海大学 Operating ship for building island by using self-compacting cement soil and construction method
CN114872829A (en) * 2022-04-21 2022-08-09 中交第四航务工程勘察设计院有限公司 Anchoring construction method and system for operation ship and steel pile driving ship
CN116001983A (en) * 2023-03-27 2023-04-25 烟台鲁东勘察测绘有限公司 Pile foot butt joint device for geological survey ship

Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH1076989A (en) * 1996-09-04 1998-03-24 I H I Amutetsuku:Kk Work barge for drain construction
CN1184188A (en) * 1997-07-29 1998-06-10 浙江省围海工程公司 Soft foundation reinforcing method and equipment utilizing underwater plastic drain board
CN2716342Y (en) * 2004-07-27 2005-08-10 徐州鹏达基桩工程机械研究所 Water plate-inserting machine
KR20050115835A (en) * 2005-11-02 2005-12-08 김용기 Vertical drainage apparatus and method for improvement of the sea ground and dredged soil area
CN2811400Y (en) * 2005-02-04 2006-08-30 徐州鹏达基桩工程机械研究所 Steel rail type pile engine
KR100652205B1 (en) * 2005-11-08 2006-11-29 (주)지티이건설 Pbd execution equipment at sea and pbd execution method for operating he same
CN201362340Y (en) * 2008-04-24 2009-12-16 中国神华能源股份有限公司 Lift type drain bar striking boat
CN102094412A (en) * 2010-12-22 2011-06-15 天津天大滨海船舶与海洋工程研究院有限公司 Mud-water amphibious plate-inserting device for soft foundation
CN104594332A (en) * 2015-01-09 2015-05-06 张巧文 Flashboard machines and machine frames thereof
CN106245618A (en) * 2016-08-18 2016-12-21 武汉船用机械有限责任公司 A kind of multistage spud leg jacking system

Patent Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH1076989A (en) * 1996-09-04 1998-03-24 I H I Amutetsuku:Kk Work barge for drain construction
CN1184188A (en) * 1997-07-29 1998-06-10 浙江省围海工程公司 Soft foundation reinforcing method and equipment utilizing underwater plastic drain board
CN2716342Y (en) * 2004-07-27 2005-08-10 徐州鹏达基桩工程机械研究所 Water plate-inserting machine
CN2811400Y (en) * 2005-02-04 2006-08-30 徐州鹏达基桩工程机械研究所 Steel rail type pile engine
KR20050115835A (en) * 2005-11-02 2005-12-08 김용기 Vertical drainage apparatus and method for improvement of the sea ground and dredged soil area
KR100652205B1 (en) * 2005-11-08 2006-11-29 (주)지티이건설 Pbd execution equipment at sea and pbd execution method for operating he same
CN201362340Y (en) * 2008-04-24 2009-12-16 中国神华能源股份有限公司 Lift type drain bar striking boat
CN102094412A (en) * 2010-12-22 2011-06-15 天津天大滨海船舶与海洋工程研究院有限公司 Mud-water amphibious plate-inserting device for soft foundation
CN104594332A (en) * 2015-01-09 2015-05-06 张巧文 Flashboard machines and machine frames thereof
CN106245618A (en) * 2016-08-18 2016-12-21 武汉船用机械有限责任公司 A kind of multistage spud leg jacking system

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112500034A (en) * 2020-11-09 2021-03-16 河海大学 Operating ship for building island by using self-compacting cement soil and construction method
CN114872829A (en) * 2022-04-21 2022-08-09 中交第四航务工程勘察设计院有限公司 Anchoring construction method and system for operation ship and steel pile driving ship
CN116001983A (en) * 2023-03-27 2023-04-25 烟台鲁东勘察测绘有限公司 Pile foot butt joint device for geological survey ship
CN116001983B (en) * 2023-03-27 2023-06-06 烟台鲁东勘察测绘有限公司 Pile foot butt joint device for geological survey ship

Similar Documents

Publication Publication Date Title
CN106892064A (en) A kind of PVD over-water constructions special purpose ship
US3001592A (en) Well drilling and servicing barge including bridge and rig structure and methods
AU2016204008A1 (en) Hopper Handling Kit and Apparatus
CN106697189A (en) Installation method for float-dragging method offshore type ocean booster station
CN105714829B (en) The constructing device and use its construction method that deep pit digging is built with underground station
US20090188204A1 (en) Method for the construction of a civil engineering structure and associated system
CN216664296U (en) Housing construction deep foundation pit structure convenient to prevent long-pending soil in foundation ditch edge
CN102433868B (en) Insert plate device capable of walking on blown-filled mud soil
CN207000757U (en) A kind of PVD over-water constructions special purpose ship
CN105858540B (en) Underground work well capping device based on hydraulic jack and pulley mechanism
CN110700624B (en) Building displacement system and method
CN211946187U (en) Device is laid with well lid of being convenient for remove to road facilities construction
CN110700299B (en) Deep foundation pit structural beam reinforcement framework modularization rapid construction method
CN105735223B (en) A kind of technique for turning to sliding pile extension for pile legs of self-elevating drilling platform
CN107487724B (en) Non-crane-assisted large floating crane arm support mounting device and mounting method
CN108396721A (en) A kind of Liftable type ice resistant device suitable for truss leg self-elevating ocean platform
KR101803373B1 (en) Offshore structure
CN204224987U (en) A kind of continuous girder bridge multiple pipeline installation structure
CN203938342U (en) Civil engineering elevator
CN108677749B (en) PLC frequency conversion control system for bridge swivel construction
KR100525710B1 (en) Caisson launching spot and the caisson launching method using the same
CN105780828B (en) The model test apparatus and operating method that open-cut foundation ditch influences on adjacent building basis
CN207017622U (en) A kind of elevator safe construction operating platform
CN102839669A (en) Mounting method for foundation ring of marine wind turbine
CN204826821U (en) A carry a sweep and prevent shaking device for lifting and horizontal moving stereo garage

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20170627

RJ01 Rejection of invention patent application after publication