CN106884625B - A method of it administers on oil-water well oil layer casing and alters - Google Patents

A method of it administers on oil-water well oil layer casing and alters Download PDF

Info

Publication number
CN106884625B
CN106884625B CN201510934282.7A CN201510934282A CN106884625B CN 106884625 B CN106884625 B CN 106884625B CN 201510934282 A CN201510934282 A CN 201510934282A CN 106884625 B CN106884625 B CN 106884625B
Authority
CN
China
Prior art keywords
oil
production string
pipe
string
casing
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201510934282.7A
Other languages
Chinese (zh)
Other versions
CN106884625A (en
Inventor
刘承炜
马永忠
尤冬青
靳利
江凌飞
强海萍
赵广恒
杨瑞起
李思琪
姚俊成
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Petroleum and Natural Gas Co Ltd
Original Assignee
China Petroleum and Natural Gas Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Petroleum and Natural Gas Co Ltd filed Critical China Petroleum and Natural Gas Co Ltd
Priority to CN201510934282.7A priority Critical patent/CN106884625B/en
Publication of CN106884625A publication Critical patent/CN106884625A/en
Application granted granted Critical
Publication of CN106884625B publication Critical patent/CN106884625B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21BEARTH OR ROCK DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
    • E21B41/00Equipment or details not covered by groups E21B15/00 - E21B40/00
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21BEARTH OR ROCK DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
    • E21B29/00Cutting or destroying pipes, packers, plugs or wire lines, located in boreholes or wells, e.g. cutting of damaged pipes, of windows; Deforming of pipes in boreholes or wells; Reconditioning of well casings while in the ground

Landscapes

  • Life Sciences & Earth Sciences (AREA)
  • Engineering & Computer Science (AREA)
  • Geology (AREA)
  • Mining & Mineral Resources (AREA)
  • Physics & Mathematics (AREA)
  • Environmental & Geological Engineering (AREA)
  • Fluid Mechanics (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Earth Drilling (AREA)

Abstract

The invention discloses a kind of methods altered on improvement oil-water well oil layer casing, belong to oil-water well oil recovery field.This method comprises: acting the flow string in oil-water well, scraping process is carried out to production string, construction section in production string is insulated with setting of casing with the sealing tubing string with packer.Height will be altered on oil-water well well head production string and is denoted as X meters, and the vehicle button bit that the position at X meters of production string top is reset to production string is set;The height of casing-pipe cutting machine is denoted as Y meters, using casing-pipe cutting machine-cut except vehicle button bit sets the surface pipe in following Y meters of range, then excision vehicle button bit set more than production string, re-work casing threads, then seal the annular space between production string and surface pipe and production string.Deblocking packer retightens the production string of well head, records the resection length of surface pipe and production string, acts sealing tubing string.This method is good to the regulation effect altered on oil-water well oil layer casing, and validity period is long.

Description

A method of it administers on oil-water well oil layer casing and alters
Technical field
The present invention relates to oil-water well oil recovery fields, in particular to a kind of to administer the method altered on oil-water well oil layer casing.
Background technique
With deepening continuously for oil field development, part oil-water well is influenced by ground settlement, and production string shows difference It alters in degree, highly centimeter is differed from several centimeters to tens, serious person causes pumping unit of well polished rod eye to collide with well head packing Box;It breaks or drawing crack well head surface pipe and production procedure;It pumps for a long time with pumping unit, be easy to cause oil reservoir Casing fatigue fracture;Sucker rod partial wear breaks de- etc. near well head, and the serious exploitation for affecting oil field of problem is altered on casing, and It is normally produced to subsequent oil-water well and has buried serious security risk.It is altered on a kind of improvement oil-water well oil layer casing so providing Method be necessary.
The method altered on the improvement oil-water well oil layer casing that the prior art provides such as directly welds or what angle iron welded consolidates Determine method, altered on production string and be encased inside the method that multilayer loop shape steel plate is welded and fixed in space, thus righting and reinforcing oil reservoir Casing prevents well head from pumping and causes production string fatigue fracture, eliminates well head and shakes bring job execution process The risks such as security risk, restore the normal production of oil-water well.
Inventor has found that the prior art at least has following technical problem:
The prior art provide to the method altered on oil-water well oil layer casing is administered, may be only available for altering on production string away from The case where from 20cm is less than, and well head production string can only be reinforced.But because surface subsidence reversely apply to production string it is huge , there is the problem of reinforcement tools and production string Rewelding in the effect of upper top power, and such method prevents to alter on production string Validity period it is shorter, and Rewelding is also also easy to produce damage to production string ontology, time-consuming and laborious.
Summary of the invention
Technical problem to be solved by the present invention lies in, provide it is a kind of it is anti-on alter the improvement that effect is good and validity period is long The method altered on oil-water well oil layer casing, specific technical solution are as follows:
The embodiment of the invention provides a kind of methods altered on improvement oil-water well oil layer casing, this method comprises: rising fuel-displaced Flow string in well, pre-processes production string, carries out pre-treatment to oil-water well, then cuts surface pipe and oil Layer casing, finally post-processes oil-water well.
It is described to production string carry out pretreatment include: with casing scraper to 10m range below the oil-water well well head The interior production string inner wall carries out scraping, to remove the dirt of the production string inner wall.
It is described to oil-water well carry out pre-treatment include: into the production string after pretreatment tripping in have packer Sealing tubing string, so that the packer is stuck in predetermined position, and carry out setting.Then to positioned at described in the packer top It is filled the water in annular space between production string and the production string and surface pipe.It is finally flammable to the oil-water well well head Gas is detected, and after detection is qualified, is dug out working pit around the oil-water well well head, is completed the preceding place of the oil-water well Reason.The predetermined position is in production string, apart from any position below production string top 3m.
The cutting surface pipe and production string include: that will alter height on oil-water well well head production string to be denoted as X meters, The vehicle button bit that position at described production string top X meters is reset to the production string is set;By casing-pipe cutting The height of machine is denoted as Y meters, cuts off the vehicle button bit using described sleeve pipe cutting machine and sets the surface layer set sentenced in lower Y meters of range Pipe, then cuts off the vehicle button bit and sets above production string.
It is described that carry out post-processing to oil-water well include: to set upper processing set in the vehicle button bit of the production string of reset Pipe screw thread is sealed the annular space between the production string and the surface pipe and the production string, then solves The packer is sealed, then the production string of the well head is retightened.Finally record the surface pipe and the oil reservoir set The resection length of pipe restores the oil-water well well head landforms, acts the sealing tubing string.
Specifically, preferably, described sleeve pipe scraper also passes through oil pipe variable buckle connector connect with the first tubing round thread, and First oil pipe, the oil pipe variable buckle connector, described sleeve pipe scraper are sequentially arranged from top to bottom, pass through first oil pipe Described sleeve pipe scraper is driven to move up and down in the production string.
Specifically, preferably, the sealing tubing string further include: the second oil pipe, plug valve, third oil pipe, horn mouth.Institute The second oil pipe, the plug valve, the packer, the third oil pipe, the horn mouth is stated to be sequentially connected from top to bottom, it is described Third tubing length is 310-480m, and the plug valve is in close state.The packer be stuck in the predetermined position it Before, the sealing tubing string is recorded in the tubing string suspending weight in the predetermined position.
Specifically, preferably, it is described it is setting include: above to mention the sealing tubing string 1.2-1.6m, then slowly put down, Apply the pressure of 30-80KN on the sealing tubing string, completion is described setting, and second oil pipe is buckled to and is taken out.
Specifically, preferably, the working pit is centered on the surface pipe, excavating radius 1-1.5m, depth For from the downward 0.7-1.5m of oil-water well well head doughnut-shaped steel plate.
Specifically, preferably, by the way that the adjustable lifter of casing is mounted on the surface pipe and the oil reservoir set At annular space between pipe, and make the production string after cutting from bottom to top successively with casing coupling, increase pipe nipple and well head Production tree is threadedly coupled, to be sealed to the annular space between the production string and the surface pipe and production string.
Specifically, preferably, unsealing the packer includes: the second oil pipe described in tripping in, make second oil pipe with The plug valve be connected, the sealing tubing string is above mentioned by second oil pipe, until it is described sealing tubing string suspending weight with it is setting Preceding equal, the removing seal for packer finishes.
Specifically, preferably, it includes: that casing lifting pipe nipple is made to pass through method that the production string of the well head, which is retightened, Orchid is connected with big four, and the lifting load for controlling the production string is 80-150kN, after the promotion for completing the production string, Make the lifting load on of the production string on the adjustable lifter of described sleeve pipe, completing the again solid of the production string It is fixed.
Technical solution provided in an embodiment of the present invention has the benefit that
It is provided in an embodiment of the present invention to administer the method altered on oil-water well oil layer casing, by acting the production in oil-water well Tubing string, and scraping process is carried out to production string, the dirt of production string inner wall is removed, subsequent job is convenient for.By using envelope Every device to insulating below production string construction section, and by filling the water into construction section production string, keep construction section below The production string of production string and construction section separates, and the gas permeation of oil-water well underground is avoided to cause danger, to make oil-water well The governance process altered on production string is safer.According to the height for altering height and casing-pipe cutting machine on production string, table is set The cutting position of layer casing and production string, by casing-pipe cutting machine-cut except the surface pipe and production string for above altering part, and By re-working screw thread on production string after dicing, connect the extracting device of oil such as production string and wellhead oil tree again It connects, has been inherently eliminated the raising of wellhead assembly caused by altering on production string or deflection, has eliminated the safety of oil-water well well head Hidden danger guarantees the normal production of oil-water well.It is recorded by the resection length to surface pipe and production string, guarantees grease Well basic data it is complete, convenient for later to the production of oil-water well and exploitation.As it can be seen that improvement grease provided in an embodiment of the present invention The method altered on well production string, regulation effect is good, and validity period is long, and safe operation, is convenient for large-scale promotion application.
Specific embodiment
To make the object, technical solutions and advantages of the present invention clearer, embodiment of the present invention will be made into one below Step ground detailed description.
The embodiment of the invention provides a kind of methods altered on improvement oil-water well oil layer casing, and this method includes following step It is rapid: to act the flow string in oil-water well, production string is pre-processed, pre-treatment is carried out to oil-water well, then cuts table Layer casing and production string, finally post-process oil-water well.
Carrying out pretreatment to production string includes: with casing scraper to the oil reservoir within the scope of 10m below oil-water well well head Internal surface of sleeve pipe carries out scraping, to remove the dirt of production string inner wall.
Carrying out pre-treatment to oil-water well includes: the seal pipe that tripping in has packer into production string after pretreatment Column makes packer be stuck in predetermined position, and carries out setting.Then to the production string and oil reservoir set for being located at packer top It is filled the water in annular space between pipe and surface pipe.Finally oil-water well well head fuel gas is detected, after detection is qualified, in oil Working pit is dug out around well well head, completes the pre-treatment of oil-water well.Predetermined position is in production string, apart from production string top Hold any position below 3m.
Cutting surface pipe and production string include: that will alter height on oil-water well well head production string to be denoted as X meters, will be away from The vehicle button bit that position at X meters from production string top is reset to production string is set;The height of casing-pipe cutting machine is denoted as Y Rice, using casing-pipe cutting machine-cut except vehicle button bit sets the surface pipe sentenced in lower Y meters of range, then excision vehicle button bit is set above Production string.
Carrying out post-processing to oil-water well includes: to set upper processing casing threads in the vehicle button bit of the production string of reset, Annular space between production string and production string and surface pipe is sealed, then deblocking packer, then by the oil of well head Layer casing retightens.The resection length for finally recording surface pipe and production string, restores oil-water well well head landforms, rises close out Sealing pipe column.
It is provided in an embodiment of the present invention to administer the method altered on oil-water well oil layer casing, by acting the production in oil-water well Tubing string, and scraping process is carried out to production string, the dirt of production string inner wall is removed, subsequent job is convenient for.By using envelope Every device to insulating below production string construction section, and by filling the water into production string, make construction section oil reservoir set below It manages and is separated with the production string of construction section, avoid the gas permeation of oil-water well underground from causing danger, to make oil-water well oil layer set The governance process altered on pipe is safer.According to the height for altering height and casing-pipe cutting machine on production string, surface pipe is set With the cutting position of production string, by casing-pipe cutting machine-cut except the surface pipe and production string for above altering part, and by Screw thread is re-worked on production string after cutting, reconnects the extracting device of oil such as production string and wellhead oil tree, from root The raising of wellhead assembly caused by altering on production string or deflection are eliminated on this, eliminates the security risk of oil-water well well head, are protected Demonstrate,prove the normal production of oil-water well.It is recorded by the resection length to surface pipe and production string, guarantees oil-water well basis Data it is complete, convenient for later to the production of oil-water well and exploitation.As it can be seen that improvement oil-water well oil layer provided in an embodiment of the present invention The method altered on casing, regulation effect is good, and validity period is long, and safe operation, is convenient for large-scale promotion application.
Wherein, flow string includes oil pipe, sucker rod and oil well pump, by flow string from oil-water well out after again to oil Layer casing is cut, in order to avoid flow string impacts work progress, while facilitating the cutting construction of production string.
A time scraping carried out to the production string inner wall within the scope of 10m below oil-water well well head with casing scraper, and Set position up and down within the scope of 5m, be convenient for removing the dirt, wax and other obturators of production string inner wall by scraping 3 times repeatedly Packer it is setting.Wherein, casing scraper can choose GX-T140 type.Casing scraper also pass through oil pipe variable buckle connector with The connection of first tubing round thread, and the first oil pipe, oil pipe variable buckle connector, casing scraper are sequentially arranged from top to bottom, forming sleeves Scraping tubing string.Casing scraper is driven to move up and down in production string by the first oil pipe, to realize to the clear of production string It is clean.After scraping, act scraping tubing string.
Specifically, tubing string is sealed further include: the second oil pipe, plug valve, third oil pipe, horn mouth.Second oil pipe, cock Valve, packer, third oil pipe, horn mouth are sequentially connected from top to bottom, wherein Y211-114 type, the second oil may be selected in packer Pipe and third oil pipe are the external upset tubing that diameter is 73mm, and third tubing length is 310-480m.The effect of second oil pipe It is that will seal tubing string to be sent into production string, the packer set in tubing string to be sealed finishes, and the second oil pipe can be buckled to and be taken out, To facilitate subsequent job.The effect of third oil pipe is to generate lower pulling force to packer, is conducive to packer set, improves packing The sealing effect of device oil-separating layer casing, reaches safe construction.Plug valve is constantly in closed state, so that plug valve is below Seal pipe column sealing.Before packer is stuck in predetermined position, record sealing tubing string predetermined position tubing string suspending weight, in order to The pressure applied on sealing tubing string when controlling setting.The physical location of packer should be within the scope of ± the 1m of predetermined position, and answers The box cupling of adjacent production string is avoided, so that packer is accurate, closely setting.Packer and plug valve collective effect, sealing Entire production string prevents construction section oil gas leakage below, guarantees site operation safety.
Specifically, setting procedure includes: that sealing tubing string 1.2-1.6m is above mentioned by the second oil pipe, then slowly puts down, leads to It crosses and the suspending weight of sealing tubing string is measured, when the suspending weight of sealing tubing string hangs light 30-80KN than the tubing string measured in predetermined position When, illustrate to seal the pressure for having applied 30-80KN on tubing string, at this point, setting completion, and the second oil pipe is buckled to and is taken out.
In order to further ensure that the stringent sealing of construction section production string below, clear water is poured into from well head big four, clearly Water level should not be greater than vehicle button bit and set, in order to avoid there is water spilling in cutting process, clear water pours into speed control in 2-5m3/h.So Afterwards, clear water is poured into the annular space between surface pipe and production string, clear water liquid level also should not be greater than vehicle button bit and set, clear water Speed control is poured into 10-30m3/ h, so as not to pour water it is too fast lead to clear water spillage oil well mouth, influence to construct.After pouring into clear water, Clear water liquid level is not decreased obviously in 30min in production string, illustrates that packer set is tight, while by clear water to construction Section or less be sealed in production string.
After completing setting and water-pouring process, the production string of grease well head, surface layer are covered with combustible gas monitoring alarm The fuel gas in annular space between pipe and production string is detected, and is examined with petrochemical enterprise fuel gas and toxic gas Alert design specification is observed and predicted as examination criteria, specific execution standard GB 50493-2009.After detection is qualified, it can carry out next Step construction, if detection is unqualified, should re-start setting.
Then, working pit is dug out around oil-water well well head.First remove wellhead oil tree, casing increases pipe nipple and first Casing coupling, then centered on surface pipe, digging out radius is 1-1.5m, and depth is downward from oil-water well well head doughnut-shaped steel plate The cylindrical work of 0.7-1.5m is cheated, convenient working.
Specifically, using casing-pipe cutting machine-cut except vehicle button bit sets the surface pipe sentenced in lower Y meters of range, to facilitate in oil Installation set tube cutting machine on layer casing, and production string is cut.The height of casing-pipe cutting machine is generally 0.7m, so, The Cutting Length of surface pipe is not less than 0.7m.After cutting to surface pipe and production string, specific cutting length need to be write down Degree, to guarantee that oil-water well basic data is completed.Then, according to casing threads standard, i.e. GB/T 9253.2-1999, using casing Thread generator (vertical) re-works screw thread to production string, so that the production string after cutting can be connect with wellhead installation.
Then, by the way that the adjustable lifter of casing to be mounted on production string, to seal surface pipe and oil reservoir set Annular space between pipe, and make the production string after cutting from bottom to top successively with casing coupling, increase pipe nipple and wellhead oil tree It is threadedly coupled, to be sealed to the annular space between production string and production string and surface pipe.Wherein, adjustable lifter Effect be to be sealed to the annular space section between production string and surface pipe, had by Renqiu City Ke Feng oil field science service What limit company provided, the patent No.: ZL201120447665.9.
Specifically, deblocking packer includes: the wellhead oil tree for removing big four or more, and the second oil pipe of tripping in makes second Oil pipe is connected with plug valve make-up, and the second oil pipe above mentions sealing tubing string 0.2-0.6m, records tubing string suspending weight, continues above to propose seal pipe Column, until the suspending weight of sealing tubing string is restored to setting preceding suspending weight, removing seal for packer is finished.Meanwhile sealing tubing string and tubing hanger It is connected, and seat holds out against well head jackscrew in well head big four,
Specifically, the production string of well head is retightened includes: to lift pipe nipple in big four upper joint sleeve pipe, makes casing Lifting pipe nipple is connected by flange with big four, and production string is promoted;The lifting load for controlling production string is 80-150kN (empty Under wellbore conditions), after the promotion for completing production string, make the lifting load on of production string in the adjustable lifter of casing On, complete retightening for well head production string.
Finally, adjusting the production string in oil-water well basic data according to the resection length of surface pipe and production string Length, surface pipe length are connected to and repairing data, and achieve preservation.It acts sealing tubing string, completes on oil-water well oil layer casing The governance process altered.
It will be described in detail below by specific embodiment:
Embodiment 1
It present embodiments provides in a kind of pair of Z61-6X well and alters the method administered on production string, specific steps are such as Under:
Step 1: the pretreatment of production string
The flow string in producing well is played, sets in the predetermined position for sealing packer in tubing string to away from production string top At 5m, the tripping in scraping tubing string in down-hole casing, in scraping tubing string, the first oil pipe, oil pipe variable buckle connector, GX-T140 casing are scraped Device is cut sequentially to be threadedly coupled from top to bottom.Casing scraper is driven to move up and down in production string by the first oil pipe, to well Mouthful or less 10m well section internal surface of sleeve pipe carry out a scraping, to scraping 3 times repeatedly of 5m above and below setting well section, remove in down-hole casing Dirt, wax and the other internal surface of sleeve pipe obturators of wall.After scraping, act scraping tubing string.
Step 2: oil-water well pre-treatment
Into production string after pretreatment, (the well surface pipe outer diameter is D339.73mm, internal diameter d320.4mm; Production string outer diameter is D139.7mm, internal diameter d124.3mm) sealing tubing string of the tripping in packer, it seals in tubing string, the Two oil pipes, plug valve, Y211-114 packer, third oil pipe, horn mouth are sequentially threadedly coupled from top to bottom, the length of third oil pipe 525m is spent, plug valve is in close state.It seals and records tubing string suspending weight in tubing string after packer to production string depth location 5m 50KN, and packer stuck point is adjusted here, it is ready for setting.
Sealing tubing string is above mentioned into 1.3m, then slowly decentralization, to sealing tubing string pressurization 50KN;It is fallen after packer set is qualified Take off out the second oil pipe.
Clear water is pumped into until filling the above production string of packer from well head big four, and the speed for pouring into clear water is 2m3/ h.Liquid level 30min in production string is observed, liquid level is unchanged, and packer sealing is tight.To between surface pipe and production string Annular space be pumped into clear water, until filling;The speed for being pumped into clear water is 25m3/h。
With combustible gas monitoring alarm to the annular space between the production string, surface pipe and production string of grease well head In fuel gas detected, using petrochemical enterprise fuel gas and toxic gas detection alarm design specification as detection Standard is specific to execute standard GB 50493-2009, testing result zero, detection qualification.
Remove wellhead oil tree, casing increases pipe nipple and first production string box cupling.Centered on well head surface pipe, The cylindrical work of excavating radius 1m, depth 0.7m below well head doughnut-shaped steel plate are cheated.
Step 3: cutting surface pipe and production string
Altering height on measurement well head is 50cm, and the position at the 50cm of production string top is reset to oil reservoir set The vehicle button bit of pipe is set;On the basis of this position, the casing-pipe cutting machine of D339.73mm is installed, cuts off this position or less 0.7m depth Interior surface pipe, the length of the surface pipe of excision are 0.7m.
The casing-pipe cutting machine that D139.7mm is installed on production string cuts off the vehicle button bit reset on production string and sets Above production string, the production string length of excision are 0.5m.
Step 4: oil-water well post-processing
Casing threads processing machine (vertical) is installed on D139.7mm production string, executes standard GB/T according to casing threads 9253.2-1999 re-works casing threads.
Installation is by Renqiu City section peak between table set (internal diameter d320.4mm) and oil jacket (outer diameter D139.7mm) annular space The adjustable lifter of casing (patent No.: ZL201120447665.9) that oil field science service Co., Ltd provides, to oil reservoir Annular space between casing and surface pipe is sealed;And make cutting after production string from bottom to top successively with casing coupling, It increases pipe nipple and wellhead oil tree is threadedly coupled, to be sealed to production string.
Tear the wellhead oil tree of big four or more open, the second oil pipe of tripping in makes the second oil pipe be connected with plug valve make-up, together When, sealing tubing string is connected with tubing hanger, and seat holds out against well head jackscrew in well head big four, above proposes sealing by the second oil pipe Tubing string upper lifting pipe post 0.3m records tubing string suspending weight 60KN;Continue upper lifting pipe post, tubing string suspending weight is restored to 50KN, removing seal for packer.
After sealing tubing string deblocking, pipe nipple is lifted in big four upper joint sleeve pipe, casing lifting pipe nipple is made to pass through flange and big Four-way is connected, and promotes production string;The lifting load for controlling production string is the 200KN (weight including well oil pipe tubing string After 50KN), the adjustment adjustable lifter of casing to closely production string box cupling lower end surface lays down production string lifting load, oil Layer casing coupling seat is in the adjustable lifter upper surface of casing, and the production string load on of lifting is in the adjustable lifter of casing On, the fixation of well head production string finishes;
After production string is fixed, well head working pit is backfilled, restores well head landforms;It is long to appraise and decide the removed surface pipe of well head The length 0.5m for spending 0.7m and production string adjusts Z61-6X well base according to the length of the surface pipe of excision and production string In plinth data table set length, be connected to and oil mend away from data, and achieve preservations (drop cover before table cover length 147.56m, be connected to 4.92m, oil are mended away from 4.35m;Table covers length 146.86m after drop set, is connected to 5.42m, and oil is mended away from 4.85m).
Tubing string is sealed in oil-water well finally, rising, and completes the improvement to altering on Z61-6X well production string.
After above-mentioned improvement, eliminates pumping unit hanging rope caused by altering on Z61-6X well production string and collide with well head packing The problems such as box, job execution production wellhead shakes, restore the normal production of the well.By the end of current validity period be greater than 200 days and Regulation effect continuous and effective.
Embodiment 2
It present embodiments provides in a kind of pair of J45-210 well and alters the method administered on production string, specific steps are such as Under:
Step 1: the pretreatment of production string
The flow string in producing well is played, sets in sealing tubing string packer predetermined position to away from production string top 5m Locate, the tripping in scraping tubing string in down-hole casing, in scraping tubing string, the first oil pipe, oil pipe variable buckle connector, GX-T140 casing scraping Device is sequentially threadedly coupled from top to bottom.Casing scraper is driven to move up and down in production string by the first oil pipe, to well head Following 10m well section internal surface of sleeve pipe carries out a scraping, to scraping 3 times repeatedly of 5m above and below setting well section, removes down-hole casing inner wall Dirt, wax and other internal surface of sleeve pipe obturators.After scraping, act scraping tubing string.
Step 2: oil-water well pre-treatment
Into production string after pretreatment, (the well surface pipe outer diameter is D339.73mm, internal diameter d305mm;Oil Layer sleeve outer is D139.7mm, internal diameter d124.3mm) sealing tubing string of the tripping in packer, it seals in tubing string, second Oil pipe, plug valve, Y211-114 packer, third oil pipe, horn mouth are sequentially threadedly coupled from top to bottom, the length of third oil pipe 522m, plug valve are in close state.It seals and records tubing string suspending weight in tubing string after packer to production string depth location 5m 50KN, and packer stuck point is adjusted here, it is ready for setting.
Sealing tubing string is above mentioned into 1.3m, then slowly decentralization, to sealing tubing string pressurization 50KN;It is fallen after packer set is qualified Take off out the second oil pipe.
Clear water is pumped into until filling the above production string of packer from well head big four, and the speed for pouring into clear water is 1.5m3/h.Liquid level 30min in production string is observed, liquid level is unchanged, and packer sealing is tight.To surface pipe and oil reservoir set Annular space between pipe is pumped into clear water, until filling;The speed for being pumped into clear water is 28m3/h。
With combustible gas monitoring alarm to the annular space between the production string, surface pipe and production string of grease well head In fuel gas detected, using petrochemical enterprise fuel gas and toxic gas detection alarm design specification as detection Standard is specific to execute standard GB 50493-2009, testing result zero, detection qualification.
Remove wellhead oil tree, casing increases pipe nipple and first production string box cupling.Centered on well head surface pipe, The cylindrical work of excavating radius 1.3m, depth 1.2m below well head doughnut-shaped steel plate are cheated.
Step 3: cutting surface pipe and production string
Altering height on measurement well head is 35cm, and the position at the 35cm of production string top is reset to oil reservoir set The vehicle button bit of pipe is set;On the basis of this position, the casing-pipe cutting machine of D339.73mm is installed, cuts off this position or less 0.7m depth Interior surface pipe, the length of the surface pipe of excision are 0.7m.
The casing-pipe cutting machine that D139.7mm is installed on production string cuts off the vehicle button bit reset on production string and sets Above production string, the production string length of excision are 0.35m.
Step 4: oil-water well post-processing
Casing threads processing machine (vertical) is installed on D139.7mm production string, executes standard GB/T according to casing threads 9253.2-1999 re-works casing threads.
Installation is by Renqiu City section peak oil between table set (internal diameter d305mm) and oil jacket (outer diameter D139.7mm) annular space The adjustable lifter of casing (patent No.: ZL201120447665.9) that field science service Co., Ltd provides, to oil reservoir set Annular space between pipe and surface pipe is sealed;And make cutting after production string from bottom to top successively with casing coupling, rise High pipe nipple and wellhead oil tree are threadedly coupled, to be sealed to production string.
Tear the wellhead oil tree of big four or more open, the second oil pipe of tripping in makes the second oil pipe be connected with plug valve make-up, together When, sealing tubing string is connected with tubing hanger, and seat holds out against well head jackscrew in well head big four, above proposes sealing by the second oil pipe Tubing string upper lifting pipe post 0.3m records tubing string suspending weight 65KN;Continue upper lifting pipe post, tubing string suspending weight is restored to 50KN, removing seal for packer.
After sealing tubing string deblocking, pipe nipple is lifted in big four upper joint sleeve pipe, casing lifting pipe nipple is made to pass through flange and big Four-way is connected, and promotes production string;The lifting load for controlling production string is the 160KN (weight including well oil pipe tubing string After 50KN), the adjustment adjustable lifter of casing to closely production string box cupling lower end surface lays down production string lifting load, oil Layer casing coupling seat is in the adjustable lifter upper surface of casing, and the production string load on of lifting is in the adjustable lifter of casing On, the fixation of well head production string finishes;
After production string is fixed, well head working pit is backfilled, restores well head landforms;It is long to appraise and decide the removed surface pipe of well head The length 0.35m for spending 0.7m and production string adjusts J45-210 well according to the length of the surface pipe of excision and production string In basic data table set length, be connected to and oil mend away from data, and achieve preservations (drop cover before table cover length 117.69m, be connected to 3.48m, oil are mended away from 2.76m;Table covers length 118.39m after drop set, is connected to 3.83m, and oil is mended away from 3.31m).
Tubing string is sealed in oil-water well finally, rising, and completes the improvement to altering on J45-210 well production string.
After above-mentioned improvement, eliminates in 200 meters of well sections of well head caused by being altered on J45-210 well production string or less and take out The problems such as beam hanger eccentric wear, job execution production wellhead shake, and wellhead casing pipe Rewelding fixes damage casing, is restoring the well just Often production.It is greater than 480 days and regulation effect continuous and effective by the end of current validity period.
The foregoing is merely presently preferred embodiments of the present invention, the protection scope being not intended to limit the invention, all in this hair Within bright spirit and principle, any modification, equivalent replacement, improvement and so on should be included in protection scope of the present invention Within.

Claims (5)

1. a kind of administer the method altered on oil-water well oil layer casing, comprising: act the flow string in oil-water well, to production string It is pre-processed, pre-treatment is carried out to oil-water well, then cuts surface pipe and production string, after finally being carried out to oil-water well Reason;
It is described to production string carry out pretreatment include: with casing scraper within the scope of 10m below the oil-water well well head The production string inner wall carries out scraping, to remove the dirt of the production string inner wall;
It is described to oil-water well carry out pre-treatment include: into the production string after pretreatment tripping in it is close with packer Sealing pipe column, the sealing tubing string include: the second oil pipe, plug valve, third oil pipe, horn mouth;Second oil pipe, the cock Valve, the packer, the third oil pipe, the horn mouth are sequentially connected from top to bottom, and the third tubing length is 310- 480m, the plug valve are in close state;The sealing tubing string is recorded in the tubing string suspending weight in predetermined position, makes the packer Be stuck in the predetermined position, and carry out it is setting, then to be located at the packer top the production string and the oil It is filled the water in annular space between layer casing and surface pipe, by the way that the adjustable lifter of casing is mounted on the surface pipe and institute It states at the annular space between production string, and keeps the production string after cutting successively short with casing coupling, raising from bottom to top Section and wellhead oil tree are threadedly coupled, to the ring between the production string and the production string and the surface pipe Sky is sealed;Finally the oil-water well well head fuel gas is detected, after detection is qualified, in the oil-water well well head week It encloses and digs out working pit, complete the pre-treatment of the oil-water well;The predetermined position is in production string, apart from the production string Any position below top 3m;
The cutting surface pipe and production string include: that will alter height on oil-water well well head production string to be denoted as X meters, will be away from The vehicle button bit for being reset to the production string from the position at described production string top X meters is set;By casing-pipe cutting machine Height is denoted as Y meters, cuts off the vehicle button bit using described sleeve pipe cutting machine and sets the surface pipe sentenced in lower Y meters of range, It then cuts off the vehicle button bit and sets above production string;
The ring between the production string and the production string and surface pipe that are located at the packer top Aerial water filling, comprising:
With 2-5m3The speed of/h is filled the water into the production string, and the liquid level of water is set not higher than the vehicle button bit;
With 10-30m3The speed of/h is filled the water into the annular space between the production string and surface pipe, and the liquid level of water is not high It is set in the vehicle button bit;
It is described to oil-water well carry out post-processing include: to set upper processing casing spiral shell in the vehicle button bit of the production string of reset Line, is sealed the annular space between the production string and the production string and the surface pipe, then passes through institute It states the second oil pipe and above mentions the sealing tubing string, until the suspending weight for sealing tubing string and setting preceding equal, the removing seal for packer It finishes, then the production string of the well head is retightened, finally record the excision of the surface pipe and the production string Length restores the oil-water well well head landforms, acts the sealing tubing string.
2. according to claim 1 administer the method altered on oil-water well oil layer casing, which is characterized in that described sleeve pipe scraping Device also passes through oil pipe variable buckle connector and connect with the first tubing round thread, and first oil pipe, the oil pipe variable buckle connector, the set Pipe scraper is sequentially arranged from top to bottom, by first oil pipe drive described sleeve pipe scraper in the production string on Lower movement.
3. according to claim 1 administer the method altered on oil-water well oil layer casing, which is characterized in that the setting packet It includes: above mentioning the sealing tubing string 1.2-1.6m, then slowly put down, apply the pressure of 3-8t on the sealing tubing string, complete It is described setting, and second oil pipe is buckled to and is taken out.
4. according to claim 1 administer the method altered on oil-water well oil layer casing, which is characterized in that the working pit with Centered on the surface pipe, excavating radius 1-1.5m, depth is from the downward 0.7- of oil-water well well head doughnut-shaped steel plate 1.5m。
5. according to claim 1 administer the method altered on oil-water well oil layer casing, which is characterized in that by the well head It includes: that casing lifting pipe nipple is made to be connected by flange with big four that production string, which retightens, controls mentioning for the production string Pulling load is 80-150kN, after the promotion for completing the production string, makes the lifting load on of the production string in described On the adjustable lifter of casing, retightening for the production string is completed.
CN201510934282.7A 2015-12-15 2015-12-15 A method of it administers on oil-water well oil layer casing and alters Active CN106884625B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510934282.7A CN106884625B (en) 2015-12-15 2015-12-15 A method of it administers on oil-water well oil layer casing and alters

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510934282.7A CN106884625B (en) 2015-12-15 2015-12-15 A method of it administers on oil-water well oil layer casing and alters

Publications (2)

Publication Number Publication Date
CN106884625A CN106884625A (en) 2017-06-23
CN106884625B true CN106884625B (en) 2019-04-09

Family

ID=59174472

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510934282.7A Active CN106884625B (en) 2015-12-15 2015-12-15 A method of it administers on oil-water well oil layer casing and alters

Country Status (1)

Country Link
CN (1) CN106884625B (en)

Families Citing this family (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109322634B (en) * 2017-07-31 2021-01-01 中国石油天然气股份有限公司 Oil well wellhead fixing device
CN108691515B (en) * 2018-05-04 2020-07-10 中国石油天然气股份有限公司 Device and method for treating oil-water well oil layer casing pipe channeling
CN109538148A (en) * 2018-09-30 2019-03-29 山西晋城无烟煤矿业集团有限责任公司 A kind of soft metal expandable casing patching coal bed gas well suck-back layer method
CN110725658B (en) * 2019-10-14 2022-05-03 中国石油化工股份有限公司 Radial anchoring inverted-buckling casing taking and replacing device and method
CN112681996B (en) * 2019-10-18 2022-11-04 中国石油天然气股份有限公司 Casing leakage repairing method

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US7021381B1 (en) * 2003-09-29 2006-04-04 Hudson Services, Inc. Method and apparatus for removing casing
CN201517387U (en) * 2009-07-20 2010-06-30 中国石油集团渤海钻探工程有限公司 Flexible device for preventing upward movement of sleeve tube
CN202325332U (en) * 2011-11-14 2012-07-11 代烈 Anchoring and reinforcing disposal device capable of preventing production casing from jumping up
CN203383769U (en) * 2013-06-06 2014-01-08 中国石油集团西部钻探工程有限公司 Casing anti-creeping device for casing heads
CN204827309U (en) * 2015-08-04 2015-12-02 代烈 Fall set well restoration and hang a seat ware

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US7021381B1 (en) * 2003-09-29 2006-04-04 Hudson Services, Inc. Method and apparatus for removing casing
CN201517387U (en) * 2009-07-20 2010-06-30 中国石油集团渤海钻探工程有限公司 Flexible device for preventing upward movement of sleeve tube
CN202325332U (en) * 2011-11-14 2012-07-11 代烈 Anchoring and reinforcing disposal device capable of preventing production casing from jumping up
CN203383769U (en) * 2013-06-06 2014-01-08 中国石油集团西部钻探工程有限公司 Casing anti-creeping device for casing heads
CN204827309U (en) * 2015-08-04 2015-12-02 代烈 Fall set well restoration and hang a seat ware

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
套管窜出综合治理技术研究与应用;张洋洋07;《百度文库https://wenku.***.com/view/5357e47f1711cc7931b7164d.html?sxts=1532328732727》;20120710;第19-24,30页

Also Published As

Publication number Publication date
CN106884625A (en) 2017-06-23

Similar Documents

Publication Publication Date Title
CN106884625B (en) A method of it administers on oil-water well oil layer casing and alters
CN107448169B (en) Three-body type hydraulic fracture stress measurement push-pull valve
CN105986776B (en) A kind of restorative procedure of Casing Failure breakage
CN103982154B (en) A kind of well casing recovery method
NO334625B1 (en) Method and apparatus for extracting pipes from a well
NO793839L (en) APPARATUS AND PROCEDURE FOR THE PROTECTION OF UNDERWATER CONSTRUCTIONS.
CN101775977B (en) Dual-tube injection well safety production string
CN104047590A (en) Well control project monitoring system
CN105971588A (en) Casing overflow monitoring device
CN104929558B (en) Fixed point takes set process
RU2709921C1 (en) Method of delivering a solvent in a well
CN205823208U (en) A kind of novel returning of oilfield oil well mediates stifled system
RU2732167C1 (en) Method of repairing casing string in non-cemented part (embodiments)
CN105781458A (en) Wellhead pressure relief method during deflagration fracturing of offshore platform
CN104847323A (en) Thickened oil injection and recovery integrated complete device comprising all metal screw pump
CN205449698U (en) Anti outer crowded intensity experimental apparatus of sand control pipe under evaluation high temperature environment
CN208885204U (en) A kind of scalable compensator of production string
CN204098872U (en) Electric immersible pump well tubing string and electric immersible pump well
RU2649205C1 (en) Method and device for sealing mouth of directional well
CN104632130A (en) Workover well completion process
CN205714137U (en) Compensation separate injection tubing string
CN105134124B (en) Crude oil pipeline coagulates pipe paraffin blockage emergency repairing technology
CN107288620A (en) A kind of oil drilling well head anti-overflow pipe drilling liquid level intelligent detection device
US20130259572A1 (en) Device and methods for capturing, separating, and transferring petroleum fluids from underwater leak sites
CN209179731U (en) A kind of failure oil well oil conduit inside crude oil fishing device

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant