CN106845782A - Distribution big data intelligent analysis method - Google Patents

Distribution big data intelligent analysis method Download PDF

Info

Publication number
CN106845782A
CN106845782A CN201611207372.7A CN201611207372A CN106845782A CN 106845782 A CN106845782 A CN 106845782A CN 201611207372 A CN201611207372 A CN 201611207372A CN 106845782 A CN106845782 A CN 106845782A
Authority
CN
China
Prior art keywords
power transmission
transmission information
actual
stop
actually
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201611207372.7A
Other languages
Chinese (zh)
Inventor
陈敏志
付小平
孔维怡
陈云彪
袁楚楚
应国德
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
State Grid Corp of China SGCC
Taizhou Power Supply Co of State Grid Zhejiang Electric Power Co Ltd
Original Assignee
State Grid Corp of China SGCC
Taizhou Power Supply Co of State Grid Zhejiang Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by State Grid Corp of China SGCC, Taizhou Power Supply Co of State Grid Zhejiang Electric Power Co Ltd filed Critical State Grid Corp of China SGCC
Priority to CN201611207372.7A priority Critical patent/CN106845782A/en
Publication of CN106845782A publication Critical patent/CN106845782A/en
Pending legal-status Critical Current

Links

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0631Resource planning, allocation, distributing or scheduling for enterprises or organisations
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
    • G06Q50/06Energy or water supply
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y04INFORMATION OR COMMUNICATION TECHNOLOGIES HAVING AN IMPACT ON OTHER TECHNOLOGY AREAS
    • Y04SSYSTEMS INTEGRATING TECHNOLOGIES RELATED TO POWER NETWORK OPERATION, COMMUNICATION OR INFORMATION TECHNOLOGIES FOR IMPROVING THE ELECTRICAL POWER GENERATION, TRANSMISSION, DISTRIBUTION, MANAGEMENT OR USAGE, i.e. SMART GRIDS
    • Y04S10/00Systems supporting electrical power generation, transmission or distribution
    • Y04S10/50Systems or methods supporting the power network operation or management, involving a certain degree of interaction with the load-side end user applications

Landscapes

  • Business, Economics & Management (AREA)
  • Human Resources & Organizations (AREA)
  • Engineering & Computer Science (AREA)
  • Economics (AREA)
  • Strategic Management (AREA)
  • Theoretical Computer Science (AREA)
  • Entrepreneurship & Innovation (AREA)
  • Health & Medical Sciences (AREA)
  • Marketing (AREA)
  • General Physics & Mathematics (AREA)
  • General Business, Economics & Management (AREA)
  • Tourism & Hospitality (AREA)
  • Physics & Mathematics (AREA)
  • Public Health (AREA)
  • Primary Health Care (AREA)
  • Water Supply & Treatment (AREA)
  • Development Economics (AREA)
  • Educational Administration (AREA)
  • General Health & Medical Sciences (AREA)
  • Game Theory and Decision Science (AREA)
  • Operations Research (AREA)
  • Quality & Reliability (AREA)
  • Remote Monitoring And Control Of Power-Distribution Networks (AREA)

Abstract

The invention discloses a kind of distribution big data intelligent analysis method, first, read the coverage in 95598 outage informations, line name, scheduled outage time and plan electric power feeding time;Secondly, line name public, that specially change actually stops in power transmission information, actual power off time and actual electric power feeding time are read;Finally, with " main line line name & dates " for Matching Elements, public affairs are become, is specially become and is actually stopped power transmission information and plan stops power transmission information and carries out intelligent Matching, counted every and plan to stop that power transmission information is corresponding actually to stop power transmission information.The method that the present invention is analyzed by big data, public affairs is become, is specially become and is actually stopped power transmission information and plan stops power transmission information and carries out intelligent Matching, is counted every and is planned to stop that power transmission information is corresponding actually to stop power transmission information.

Description

Distribution big data intelligent analysis method
Technical field
The present invention relates to electric network data Intellectual Analysis Technology.
Background technology
State Grid Corporation of China by 95598 system release plan outage informations, but it is public, specially become actually stop power transmission information with The scheduled outage information of 95598 systems issue often has deviation.How actual are become with public, special to 95598 scheduled outage information Stopping power transmission information carries out intelligent Matching, stops that power transmission information is corresponding actually to stop power transmission information to count every plan, with weight The meaning wanted.
The content of the invention
The technical problems to be solved by the invention are just to provide a kind of distribution big data intelligent analysis method, by 95598 meters Draw outage information with it is public, specially become and actually stop power transmission information and carry out intelligent Matching, stop power transmission information correspondence to count every plan Actually stop power transmission information.
In order to solve the above technical problems, the present invention is adopted the following technical scheme that:Distribution big data intelligent analysis method, it is first First, the coverage in 95598 outage informations, line name, scheduled outage time are read and plans electric power feeding time;Secondly, read Take public affairs, specially become line name, actual power off time and the actual electric power feeding time actually stopped in power transmission information;Finally, with " main line line The road title & dates " are Matching Elements, and by public affairs change, specially change actually stops power transmission information and plan stops power transmission information and carries out intelligent Matching, Count every plan and stop that power transmission information is corresponding actually to stop power transmission information.
Preferably, 95598 scheduled outage information early stages treatment, for the same working day multiple operating point of same circuit Situation, causes same circuit to have multiple different periods power failure plan informations to reject with working day.
Preferably, when 95598 scheduled outage information early stages are processed, by the information comprising 0.38kV in 95598 outage informations Reject.
Preferably, the actual power transmission information of stopping of single public, special terminal is rejected according to following rule to initial stage unreasonable data:
A, single public, special transformer terminals are actual stops imperfect described in power transmission information;
B, single public, special transformer terminals are actual stop power transmission information in actual electric power feeding time be ahead of actual power off time;
C, single public, special transformer terminals are actual stop power transmission information in the actual delayed actual power off time of electric power feeding time it is small more than 24 When.
Preferably, using normal distribution principle, plan is stopped by electric power feeding time and is actually stopped electric power feeding time and is matched.
Further, public, special change a plurality of to same scheduled outage information correspondence actually stops power transmission information, using normal distribution Mathematical logic, select closest to the outage information of electric power feeding time is actually stopped, if the electric power feeding time that actually stops chosen stops with plan Electric power feeding time deviation exceedes setting threshold values, rejects unreasonable data and chooses data again according to normal distribution, until finding most Reasonably stop close to reality and actually electric power feeding time.
Of the invention to pass through the method that big data is analyzed, by public affairs change, specially change actually stops power transmission information and plan stops power transmission information Intelligent Matching is carried out, every plan is counted and is stopped that power transmission information is corresponding actually to stop power transmission information.
Specific embodiment
Distribution big data intelligent analysis method:
First, by 95598 scheduled outage information:Coverage, line name, scheduled outage time and plan power transmission Time, this several column was processed in reading Excel file automatically.
Secondly, by it is public, specially become and actually stop power transmission information:Line name, actual power off time and actual electric power feeding time This several column is processed in reading access database files automatically.
Finally, two class data more than being read from Excel file, database file, with " main line line name & dates " It is Matching Elements, by public affairs change, specially change actually stops power transmission information and plan stops power transmission information and carries out intelligent Matching, counts every meter Draw and stop that power transmission information is corresponding actually to stop power transmission information.
In addition, 95598 scheduled outage information, public affairs, specially becoming and actually stopping power transmission information and need to carry out early stage treatment, and reject part Data.
First, 95598 scheduled outage information early stages treatment.
1st, for the same working day multiple operating point situation of same circuit, same circuit is caused to have multiple with working day Different periods power failure plan information.Public affairs change, special transformer terminals cannot be distinguished by the geographic area inside 95598 scheduled outage information, match somebody with somebody Network data intellectual analysis treatment software will be rejected in data processing early stage.Such as the first and second A001 of identical working day line, the first and second A001 lines # Public change of 1 branch line, the first and second A001 line #5 branch lines, the first and second A001 lines #1 etc., will all be removed.
2nd, divided according to the whole province's distribution scheduling compass of competency, the equipment of 0.38kV (380V) is not belonging to dispatching management scope, So distribution data intellectual analysis process software by data processing early stage by including inside 95598 scheduled outage information 0.38kV (380V) is intelligently rejected.Such as the first and second A001 line #1 branch lines (0.38kV), the first and second A001 lines #1 are public to become (0.38kV), all Will be removed.
Causing outage information bar after the rejecting of 95598 scheduled outage information intelligents can reduce 10 to 3 percent Ten.
Suggestion effectively stops power transmission bar number (i.e. denominator)=95598 scheduled outage information bar number-stop comprising 0.38kV (380V) Power information bar number.
2nd, single public, special terminal is actual stops power transmission information processing rules.
A, single public, special transformer terminals are actual stops imperfect described in power transmission information.During comprising line name, actual power failure Between, the key element such as time electric power feeding time be vacant or for the judgement of single character this information is unreasonable, software will be in intelligence Deleted before matching.(bar number is few under normal circumstances, and it is more bar number occur when with extraction system upgrading or equipment fault)
B, single public, special transformer terminals are actual to stop the judgement that actual electric power feeding time in power transmission information is ahead of actual power off time This information is unreasonable, and software will be deleted before intelligent Matching.(situations such as data are wrong, bar number is few)
C, single public, special transformer terminals are actual stop power transmission information in the actual delayed actual power off time of electric power feeding time it is small more than 24 When judgement this information it is unreasonable, the overwhelming majority 95598 scheduled outage informational program used times not over 24 hours, software To be deleted before intelligent Matching.(bar number is few under normal circumstances, and it is more bar number occur when marketing system changes battery, device)
Because monthly single public, special terminal data is more than 100,000, though initial stage unreasonable data screening deletes single public, specially Terminal data bar number is more, but greatly improves subsequent data analysis result accuracy.
Finally, using normal distribution principle, electric power feeding time is stopped to plan and actually stops matching for electric power feeding time.
Because distribution power failure is planned in practical implementation, the public of diverse location becomes and specially change in same power supply area Actually stop electric power feeding time to differ (general each public affairs become or specially become just a time data).Therefore normal distribution model is used The corresponding a plurality of electric power feeding time information of actually stopping of every power failure plan is screened.
It is as follows, it is denoted as N (μ, σ ^2):
Wherein, μ is the location parameter of normal distribution, describes the central tendency position of normal distribution.Probabilistic law is to take and μ The probability of neighbouring value is big, and take from μ more away from value probability it is smaller.Normal distribution is symmetrical with X=μ as symmetry axis.
σ is the form parameter of normal distribution, and the dispersion degree of description normal distribution data distribution, σ is bigger, data point Cloth gets over dispersion, and σ is smaller, and data distribution gets over concentration.
Daily substantial amounts of power off time that is public, specially becoming is in normal distribution in the ideal case, and electric power feeding time point is stopped from plan It is nearer, it is corresponding to stop that power transmission information content is more, so according to " normal distribution " selection closest to location parameter actually stop give The electric time carries out subsequent data analysis, and accuracy is higher.
Normal distribution chooses public, special change and actually stops power transmission information.
Because there is error (typically within 3 points) the different terminals time of electricity consumption acquisition system record, same plan is stopped Power information often corresponds to a plurality of public, special change and actually stops power transmission information, and software is selected closest using the mathematical logic of normal distribution Actually stop the outage information of electric power feeding time.If the electric power feeding time that actually stops chosen stops electric power feeding time deviation more than setting valve with plan Value (is temporarily set to 180 minutes), and system will reject unreasonable data and choose data again according to normal distribution, most be connect until finding It is near actual and reasonably actually stop electric power feeding time.
" intelligence is rejected and calculated again " function can at utmost avoid the timing error because of acquisition terminal system and failure In the case of error in data matching, make subsequent data analysis result more accurately and reliably, going out crucial management and control target to programming count carries For correct data source.
Stop that power transmission information is corresponding actually to stop power transmission information according to count every plan, can further be divided Analysis, will " actual have a power failure advanced scheduled outage ", " actual have a power failure delayed plan 30 minutes and more than " and " the actual delayed plan of power transmission Electric power feeding time " as " five zero time differences " key management and control target analysis emphasis.Reduce as far as possible because acquisition system and trouble light are former Not statistical uncertainty situation is upgraded because caused by, and statistics is included into crucial management and control mesh calibration method is adjusted:
A, because there is an error public, the special transformer terminals time, 5 minutes nargin is set, can avoid because public, the special transformer terminals time The error statistics that error causes.By " the actual advanced scheduled outage that has a power failure " and " the actual delayed plan of power transmission in Classifying Sum result The Intelligent statistical that electric power feeding time " is all higher than 5 minutes goes out crucial management and control target.(note:Set 5 minutes nargin be consider personnel time, Each link time such as public, special transformer terminals and operation is inconsistent)
B, the normal conditions lower deviation difference of time (plan with) it is excessive be usually because scheduled overhaul and breakdown repair Superposition and cause terminal time entanglement with extraction system system upgrade, for as far as possible avoid because breakdown repair and with extraction system upgrade draw The error statistics for rising, by " the actual advanced scheduled outage that has a power failure " in Classifying Sum result and " the actual delayed plan power transmission of power transmission The intelligence rejecting of big 200 minutes of time " numerical bias, statistics is not included.
C, actual used time accounting plan used time percentage can be substantially reaction this scheduled outage information accuracy, lead to Cross substantial amounts of data feedback accounting and think that data are unreasonable below 10% and to more than 200%, should reject.When this accounting exists It is probably that scheduling is stopping the adjustment of the labour method of operation or dual power supply user in power operation below percent 10%, it is impossible to receive Enter crucial management and control object statistics.When this accounting is probably because scheduled overhaul and breakdown repair more than percent 200% Superposition, it is impossible to include crucial management and control object statistics.

Claims (6)

1. distribution big data intelligent analysis method, it is characterised in that:First, coverage, the line in 95598 outage informations are read Road title, scheduled outage time and plan electric power feeding time;Secondly, read it is public, specially become actually stop in power transmission information line name, Actual power off time and actual electric power feeding time;Finally, with " main line line name & dates " for Matching Elements, public affairs are become, specially becomes real Border stops power transmission information and plan and stops power transmission information to carry out intelligent Matching, counts every plan and stops that power transmission information is corresponding actually to stop Power transmission information.
2. distribution big data intelligent analysis method according to claim 1, it is characterised in that:95598 scheduled outage information Early stage treatment, for the same working day multiple operating point situation of same circuit, causes same circuit to have multiple with working day Different periods power failure plan information is rejected.
3. distribution big data intelligent analysis method according to claim 2, it is characterised in that:95598 scheduled outage information During early stage treatment, the information comprising 0.38kV in 95598 outage informations is rejected.
4. distribution big data intelligent analysis method according to claim 1, it is characterised in that:Single public, special terminal reality Stop power transmission information to reject initial stage unreasonable data according to following rule:
A, single public, special transformer terminals are actual stops imperfect described in power transmission information;
B, single public, special transformer terminals are actual stop power transmission information in actual electric power feeding time be ahead of actual power off time;
C, single public, special transformer terminals are actual stop power transmission information in the actual delayed actual power off time of electric power feeding time more than 24 hours.
5. distribution big data intelligent analysis method according to claim 1, it is characterised in that:Using normal distribution principle, Plan is stopped by electric power feeding time and actually stopped electric power feeding time and is matched.
6. distribution big data intelligent analysis method according to claim 5, it is characterised in that:To same scheduled outage information Correspondence it is a plurality of it is public, specially become and actually stop power transmission information, using the mathematical logic of normal distribution, select closest to actually stopping electric power feeding time Outage information, if actually stop electric power feeding time and the plan chosen stop electric power feeding time deviation and exceed setting threshold values, reject unreasonable Data simultaneously choose data again according to normal distribution, until finding closest to reality and reasonably actually stopping electric power feeding time.
CN201611207372.7A 2016-12-23 2016-12-23 Distribution big data intelligent analysis method Pending CN106845782A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201611207372.7A CN106845782A (en) 2016-12-23 2016-12-23 Distribution big data intelligent analysis method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201611207372.7A CN106845782A (en) 2016-12-23 2016-12-23 Distribution big data intelligent analysis method

Publications (1)

Publication Number Publication Date
CN106845782A true CN106845782A (en) 2017-06-13

Family

ID=59135294

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201611207372.7A Pending CN106845782A (en) 2016-12-23 2016-12-23 Distribution big data intelligent analysis method

Country Status (1)

Country Link
CN (1) CN106845782A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107833151A (en) * 2017-11-10 2018-03-23 国网浙江省电力公司温州供电公司 Distribution plan stops power transmission zero time difference data processing method and equipment
CN109871961A (en) * 2018-12-29 2019-06-11 深圳供电局有限公司 Method and system for analyzing medium-voltage power failure event
CN110942223A (en) * 2019-09-12 2020-03-31 国网浙江平湖市供电有限公司 Method for real-time control of five zero time differences of distribution network power failure plan

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103489062A (en) * 2013-09-04 2014-01-01 广东电网公司佛山供电局 Scheduled outage method and device based on CIM model
CN104156790A (en) * 2014-08-22 2014-11-19 国家电网公司 Method for optimizing and balancing power-cut schemes
CN104536565A (en) * 2014-12-18 2015-04-22 深圳市酷商时代科技有限公司 Application program control method and device
CN104881729A (en) * 2015-04-23 2015-09-02 中国南方电网有限责任公司 Electric power marketing system power failure information processing method, and electric power marketing system power failure information processing system
CN106095856A (en) * 2016-06-01 2016-11-09 广东电网有限责任公司 A kind of analysis method and device of client's outage information

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103489062A (en) * 2013-09-04 2014-01-01 广东电网公司佛山供电局 Scheduled outage method and device based on CIM model
CN104156790A (en) * 2014-08-22 2014-11-19 国家电网公司 Method for optimizing and balancing power-cut schemes
CN104536565A (en) * 2014-12-18 2015-04-22 深圳市酷商时代科技有限公司 Application program control method and device
CN104881729A (en) * 2015-04-23 2015-09-02 中国南方电网有限责任公司 Electric power marketing system power failure information processing method, and electric power marketing system power failure information processing system
CN106095856A (en) * 2016-06-01 2016-11-09 广东电网有限责任公司 A kind of analysis method and device of client's outage information

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107833151A (en) * 2017-11-10 2018-03-23 国网浙江省电力公司温州供电公司 Distribution plan stops power transmission zero time difference data processing method and equipment
CN109871961A (en) * 2018-12-29 2019-06-11 深圳供电局有限公司 Method and system for analyzing medium-voltage power failure event
CN110942223A (en) * 2019-09-12 2020-03-31 国网浙江平湖市供电有限公司 Method for real-time control of five zero time differences of distribution network power failure plan

Similar Documents

Publication Publication Date Title
CN106845782A (en) Distribution big data intelligent analysis method
CN104600840A (en) Intelligent dispatching and mis-operation preventing management system and method
CN102663537A (en) Maintenance system of power equipment based on risk assessment
CN103050931A (en) Power system hierarchical data matching and relay protection setting merging method
CN110688389B (en) Cloud management system for defects of secondary equipment of transformer substation
CN103679373A (en) Full chain budget data processing system and method for production infrastructure standard cost system
CN110336375A (en) A kind of processing method and system of power system monitor warning information
CN104850934A (en) Meteorological device maintenance and repair management system
CN111934274A (en) Intelligent substation protection constant value intelligent downloading method
CN113743892B (en) Tracking processing method and device for power grid infrastructure problems, computer equipment and medium
CN109615233B (en) Intelligent water affair management platform based on basic data acquisition
CN107766570A (en) A kind of homologous check method of archives
CN107844320A (en) State's net software version information management system and implementation method
CN104616111A (en) Budget fund management method and system
CN106651653A (en) Intelligent power distribution network project auxiliary management system
CN105589000A (en) Power consumption data graphical management and control system
CN105574666A (en) Method and device for evaluating credit level of enterprise based on key data modeling
CN105741084A (en) Service authority management system and method
CN108966631A (en) Producing line technical solution applied to surface mounting technology
CN105761008A (en) Intelligent production management method for signal equipment maintenance
CN111580462A (en) Cutter consumption management system and method
CN108879661A (en) The method and apparatus of grid switching operation is checked by association history ticket
CN115293734A (en) Real-time cost accounting method and system based on manufacturing process
CN107315395A (en) One kind production automatic error-correcting program system and method
WO2023093031A1 (en) Pod adjustment and control method and apparatus, and electronic device

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20170613

RJ01 Rejection of invention patent application after publication