CN106838468A - Support of pipelines and its method to set up - Google Patents

Support of pipelines and its method to set up Download PDF

Info

Publication number
CN106838468A
CN106838468A CN201611001531.8A CN201611001531A CN106838468A CN 106838468 A CN106838468 A CN 106838468A CN 201611001531 A CN201611001531 A CN 201611001531A CN 106838468 A CN106838468 A CN 106838468A
Authority
CN
China
Prior art keywords
unit support
support
nut
combined
adjusting bracket
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201611001531.8A
Other languages
Chinese (zh)
Other versions
CN106838468B (en
Inventor
黄圣奎
李旻耿
张成旭
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Korea Agru Kk
Original Assignee
Korea Agru Kk
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Korea Agru Kk filed Critical Korea Agru Kk
Publication of CN106838468A publication Critical patent/CN106838468A/en
Application granted granted Critical
Publication of CN106838468B publication Critical patent/CN106838468B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F16ENGINEERING ELEMENTS AND UNITS; GENERAL MEASURES FOR PRODUCING AND MAINTAINING EFFECTIVE FUNCTIONING OF MACHINES OR INSTALLATIONS; THERMAL INSULATION IN GENERAL
    • F16LPIPES; JOINTS OR FITTINGS FOR PIPES; SUPPORTS FOR PIPES, CABLES OR PROTECTIVE TUBING; MEANS FOR THERMAL INSULATION IN GENERAL
    • F16L3/00Supports for pipes, cables or protective tubing, e.g. hangers, holders, clamps, cleats, clips, brackets
    • F16L3/08Supports for pipes, cables or protective tubing, e.g. hangers, holders, clamps, cleats, clips, brackets substantially surrounding the pipe, cable or protective tubing

Landscapes

  • Engineering & Computer Science (AREA)
  • General Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • Supports For Pipes And Cables (AREA)
  • Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)

Abstract

The present invention relates to a kind of support of pipelines, it includes:Adjusting bracket;And unit support, it is single or multiple from basal surface lamination, so as to be combined with the adjusting bracket, and with the height for having set, and the adjusting bracket is located at lamination between the unit support and pipeline of the superiors, so as to can make to remain height set in advance from datum level to the height of the pipeline center.

Description

Support of pipelines and its method to set up
Technical field
The present invention relates to a kind of pipeline (pipe) support and its method to set up.
Background technology
The piping material of plastic material according to peripheral temperature, operation temperature, fluid weight and hydraulic pressure etc. scene various Part, volume produces change to longitudinal direction and transverse direction.Existing pipe arrangement support member (support) is in situation about being made up of Steel material Under, it is different from the expansion or shrinkage rate of plastics pipe arrangement and turn into cause pipe arrangement breakage due to.
For the setting of pipe arrangement, have a problem in that, first, the fluid for flowing into pipe arrangement beginning is raw to multiple Product equipment is separated and while flow into, pipe arrangement is subdivided, and while pipe arrangement is subdivided, the diameter of pipe arrangement diminishes, from bottom surface to The height at the center of pipe arrangement gradually step-down, so that pipe arrangement buckles downwards or so that hydraulic pressure changes.
The content of the invention
It is of the invention to be proposed to solve problem as described above, it is therefore intended that a kind of bulk (block) form is provided Support of pipelines and its method to set up, even if the support of pipelines of the block-shape morphology is straight while being subdivided with pipeline In the case that footpath changes, also cause to keep certain from datum level to the height of pipe arrangement pipeline center.
Realize that technical task of the invention is not intended to be limited to above-mentioned technical task, and NM or others Technical task is can clearly from following record for the personnel with general knowledge in the technical field belonging to the present invention Understand.
In order to reach described purpose, support of pipelines of the invention includes the present invention:Adjusting bracket;And, unit Support, it is single or multiple from basal surface lamination and is combined with the adjusting bracket, and with the height for having set, it is described Adjusting bracket is located between the unit support and pipeline of the superiors' lamination, may be such that from datum level to the pipeline center Height be maintained at prespecified height.
Support of pipelines of the invention includes the pipeline support part combined with the pipeline, and the adjusting bracket can be wrapped Include:First installs groove portion, and its top for being located at the adjusting bracket is simultaneously combined with the pipeline support part;First center Bolt hole portion, the middle body of the first installation groove portion described in its insertion;Second installs groove portion, and it is located under the adjusting bracket Portion is simultaneously combined with the unit support;And, multiple grooves, its bottom for being located at the adjusting bracket.
The first central bolt hole portion may include:First upper hole, it is located at top;First nut of nut shape Groove, its bottom for being located at first upper hole;And, the first plectane groove of plectane form, it is located at first nut groove Bottom, and with the big diameter of the diameter than first upper hole.
The adjusting bracket also includes the first nut part combined with the first central bolt hole portion, first spiral shell Auxiliary assembly includes:First nut portions, it is inserted in the form of corresponding to first nut groove;First plectane portion, it is from described First nut portions extend, and including hollow bulb, and inserted in the form of corresponding to the first plectane groove.
The adjusting bracket also includes two the first side spiral shells of the first installation groove portion described in insertion and the second installation groove portion Bolt joint portion, the first side bolt joint portion is set centered on the first central bolt hole portion in symmetrical form, And can be the pore morphology of strip.
Support of pipelines of the invention includes the pipeline support part being combined with the pipeline, the unit support May include:Protrusion joint portion, it is set in the form of the top for protruding from the unit support, and with the adjusting bracket Bottom is combined;Second central bolt hole portion, the middle body of unit support described in its insertion;3rd installs groove portion, its position It is combined in the bottom of the unit support and with the protrusion joint portion of the unit support positioned at downside;With And, multiple grooves, its bottom for being located at the unit support.
The second central bolt hole portion may include:Second upper hole, it is located at top;Second nut of nut shape Groove, its bottom for being located at second upper hole;And, the second plectane groove of plectane form, it is located at second nut groove Bottom, and with the big diameter of the diameter than second upper hole.
The unit support also includes the second nut part combined with the second central bolt hole portion, second spiral shell Auxiliary assembly may include:Second nut portions, it is inserted in the form of corresponding to second nut groove;Second plectane portion, it is from institute The extension of the second nut portions is stated, and including hollow bulb, and inserted in the form of corresponding to the second plectane groove.
The unit support also includes two the second side bolts of protrusion joint portion described in insertion and the 3rd installation groove portion Joint portion, the second side bolt joint portion is set centered on the second central bolt hole portion in symmetrical form, and And can be the pore morphology of strip.
The hollow bulb of the unit support including strip, and may also include and be inserted into second side bolt and combine First insertion (insert) part in portion.
The second side bolt joint portion may include:3rd upper hole of strip, it is located at top;And, first Insertion part insertion groove, its bottom for being located at the 3rd upper hole.
The hollow bulb of the unit support including strip, and may also include and be combined with the described 3rd installation groove portion The second insertion part.
The method to set up of support of pipelines of the invention includes:A steps, in order to support pipeline, and will be with the pipeline With reference to pipeline support part and adjusting bracket first installation groove portion be combined;B step, the first nut part is incorporated into First central bolt hole portion of the adjusting bracket, and the first insertion part is being incorporated into the second side spiral shell of unit support Bolt joint portion and the second nut part is incorporated into after the second central bolt hole portion of the unit support, lamination multiple institutes State unit support;Step c, groove portion, institute are installed with reference to the protrusion joint portion of the unit support with the second of the adjusting bracket Adjusting bracket is stated positioned at the pipeline support part and between the unit support of the superiors' lamination, will be from datum level to institute The height for stating pipeline center remains prespecified height, the unit support from basal surface lamination it is single or multiple and with institute State adjusting bracket to be combined, and there can be the height for having set.
The method to set up of support of pipelines of the invention may also include after the step c:Step d, from as The first unit support in the unit support of lamination removes second nut part, and central bolt is inserted To the second central bolt hole portion of the second unit support being combined with the first unit support, and combine described first Unit support and the second unit support;Step e, from lamination in the 3rd unit support of the downside of the second unit support Remove first insertion part and second nut part, and insertion to the side hole of the pipeline support part, First side bolt joint portion of the adjusting bracket and the second side bolt joint portion of the unit support carry out insertion Side bolt after, nut is combined with the side bolt, described in it will be combined with the side bolt Nut is inserted in after the first insertion part insertion groove of the 3rd unit support, and the side bolt and the nut are entered Row screw is combined;F steps, screw combination central bolt and fixture, the central bolt from the second unit support Two central bolt hole portion insertions to the undermost described unit support for obtaining lamination, the fixture is located at the basal part.
The method to set up of support of pipelines of the invention may also include after the step c:G steps, insert to institute In stating the second of the medium pore of pipeline support part, the first central bolt hole portion of the adjusting bracket and the unit support Centre bolt hole portion carries out the central bolt of insertion, and the central bolt is carried out into screw knot with the fixture for being located at the basal surface Close.
The method to set up of support of pipelines of the invention may also include after the step c:Step d, from as The first unit support in the unit support of lamination removes second nut part, and central bolt is inserted To the second central bolt hole portion of the second unit support being combined with the first unit support, and combine described first Unit support and the second unit support;Step e, from lamination in the 3rd unit support of the downside of the second unit support Remove first insertion part and second nut part, and insertion to the side hole of the pipeline support part, First side bolt joint portion of the adjusting bracket and the second side bolt joint portion of the unit support carry out insertion Side bolt after, nut is combined with the side bolt, described in it will be combined with the side bolt Nut is inserted in after the first insertion part insertion groove of the 3rd unit support, and the side bolt and the nut are entered Row screw is combined;H steps, will be located at the undermost 5th unit support of the unit support for obtaining lamination from described the After the 4th unit support that five unit supports are combined is separated, the second insertion part is inserted in the 4th unit support The 3rd installation groove portion, the 5th unit support is overturn, by the 3rd installation groove portion of the 5th unit support and described the Two insertion parts are combined, or overturn the 5th unit support, and the second insertion part is inserted in into the 5th unit 3rd installation groove portion of support, and combine the 3rd installation groove portion of second insertion part and the 4th unit support;I is walked Suddenly, the protrusion joint portion of the 5th unit support is tied with the fixture including groove shape positioned at the basal surface Close;J steps, carry out central bolt and the fixture screw and are combined with the screw of bar form, the central bolt insertion institute State the second central bolt hole portion of the second unit support and the 5th unit support.
The method to set up of support of pipelines of the invention may also include after the step c:H steps, will positioned at To lamination the unit support undermost 5th unit support from the 4th unit combined with the 5th unit support After support is separated, the second insertion part is inserted in the 3rd installation groove portion of the 4th unit support, upset is described 5th unit support, the 3rd installation groove portion of the 5th unit support is combined with second insertion part, or The 5th unit support is overturn, the second insertion part is inserted in the 3rd installation groove portion of the 5th unit support, and tie Close second insertion part and groove portion is installed with the 3rd of the 4th unit support the;I steps, by the 5th unit support Protrusion joint portion is combined with the fixture including groove shape positioned at the basal surface;K steps, insert to the pipeline branch Second central bolt hole of the medium pore of support part part, the first central bolt hole portion of the adjusting bracket and the unit support Portion carries out the central bolt of insertion, and the central bolt and the fixture are carried out into screw with the screw of bar form is combined.
The method to set up of support of pipelines of the invention may also include after the step c:H steps, will positioned at To lamination the unit support undermost 5th unit support from the 4th unit combined with the 5th unit support After support is separated, the second insertion part is inserted in the 3rd installation groove portion of the 4th unit support, upset is described 5th unit support, the 3rd installation groove portion of the 5th unit support is combined with second insertion part, or The 5th unit support is overturn, the second insertion part is inserted in the 3rd installation groove portion of the 5th unit support, and tie Close second insertion part and groove portion is installed with the 3rd of the 4th unit support the;I steps, by the 5th unit support Protrusion joint portion is combined with the fixture including groove shape positioned at the basal surface;M steps, insert to the pipeline branch The side hole of support part part, the first side bolt joint portion of the adjusting bracket and the second side bolt of the unit support Joint portion carries out the side bolt of insertion, and the side bolt and the fixture are carried out into screw knot with the screw of bar form Close.
The method to set up of support of pipelines of the invention may also include after the step c:N steps, insert to institute State the second of the side hole of pipeline support part, the first side bolt joint portion of the adjusting bracket and the unit support Side bolt joint portion carries out the side bolt of insertion, and the side bolt is carried out with the fixture positioned at the basal surface Screw is combined.
Support of pipelines of the invention uses regulation in order to the distance from datum level to pipeline center is kept into certain Support makes up the difference in height from datum level to pipeline support part with unit support.
Unit support includes the block-shape morphology with certain altitude, can be easily remedied from basal surface by lamination unit support To various difference in height of pipeline support part.
Adjusting bracket using the support with various height can make up from lamination in the superiors unit frame upper to pipe Various differences in height of road support member.
Although adjusting bracket can have various height to make up various differences in height, unit support is for operation Swiftness economy with production etc., and the standardized support of certain altitude can be used.
Additionally, the adhesion in order to strengthen adjusting bracket and unit support, and bolts and nuts can be used, and can be used First insertion part, the second insertion part, the first nut part, the second nut part strengthen the adhesion and rigidity of support.
The method to set up of support of pipelines of the invention can according to lamination height of the diameter of pipeline or unit support etc. Rapidly and readily adjusting bracket is combined with unit support and bracket support members by various methods.Using center Bolt and side bolt, screw of bar form etc. combine support by various methods, can with exactly will from datum level to The form that the height of pipeline center keeps certain sets support of pipelines.
Brief description of the drawings
Fig. 1 is the use state figure of the outline of support of pipelines according to an embodiment of the invention.
Fig. 2 is the stereogram of the adjusting bracket of the support of pipelines of different embodiment of the invention from Fig. 3.
Fig. 4 is according to Fig. 2 and the skeleton diagram of the adjusting bracket of the embodiment of Fig. 3 from downside observation.
Fig. 5 is the stereogram of the adjusting bracket of the support of pipelines of still another embodiment of the invention.
Fig. 6 is the skeleton diagram according to the adjusting bracket of the embodiment of Fig. 5 from downside observation.
Fig. 7 is the stereogram of the unit support of support of pipelines according to an embodiment of the invention.
Fig. 8 is the skeleton diagram according to the unit support of the embodiment of Fig. 7 from downside observation.
Fig. 9 is the stereogram of the unit support of support of pipelines according to another embodiment of the invention.
Figure 10 is the skeleton diagram according to the unit support of the embodiment of Fig. 9 from downside observation.
Figure 11 is the first nut part of support of pipelines according to an embodiment of the invention or the solid of the second nut part Figure.
Figure 12 is the stereogram of first insertion (insert) part of support of pipelines according to an embodiment of the invention.
Figure 13 is the stereogram of second insertion (insert) part of support of pipelines according to an embodiment of the invention.
Figure 14 to Figure 19 is method to set up of the first embodiment of the invention to the support of pipelines of sixth embodiment Skeleton diagram.
Specific embodiment
Hereinafter, the figure by illustrating is described in detail to a part of embodiment of the invention.Just reference numeral is added For the inscape of each figure, although can be represented on different figures for identical inscape, also need to stay Meaning has identical label as much as possible.Additionally, just for embodiments of the invention are illustrated, for relevant public affairs Know composition or function specific description be judged as hinder for embodiments of the invention understanding in the case of, omit its detailed Explanation.
Additionally, just for the inscape of embodiments of the invention is illustrated, can be used first, second, A, B, The term of (a), (b) etc..The term is only used for the term that its inscape is distinguished with other inscapes, The essence or order or order etc. of corresponding inscape are not limited by its term.It is being recited as some inscapes " even Connect ", " with reference to " or " engagement " be in the case of other inscapes, it is thus understood that although its inscape can be directly connected Or be engaged in its other inscape, but " can also be connected " between each inscape, " with reference to " or " engagement " have and Another inscape.
Hereinafter, referring to the drawings, the support of pipeline 10 according to an embodiment of the invention is described in detail.
Fig. 1 is the use state figure of the outline of the support of pipeline 10 according to an embodiment of the invention, and Fig. 2 and Fig. 3 is basis The stereogram of the adjusting bracket 100 of the support of pipeline 10 of different embodiment of the invention, Fig. 4 is according to Fig. 2 from downside observation With the skeleton diagram of the adjusting bracket 100 of the embodiment of Fig. 3, Fig. 5 is 10, the pipeline of still another embodiment of the invention The stereogram of the adjusting bracket 100 of frame, Fig. 6 is the skeleton diagram according to the adjusting bracket 100 of the embodiment of Fig. 5 from downside observation.
The support of pipeline 10 of an example of the invention may include adjusting bracket 100, unit support 200, the first spiral shell Auxiliary assembly 300, the second nut part 600, the first insertion part 400, the second insertion part 500.
The support of pipeline 10 includes:Adjusting bracket 100;And, unit support 200, it is single or multiple from basal surface lamination And be combined with the adjusting bracket 100, and with the height for having set, the adjusting bracket 100 is located in the superiors' layer Between the long-pending unit support 200 and pipeline 10, may be such that from datum level to the height at the center of the pipeline 10 and be maintained at pre- The height for first specifying.Including the pipeline support part 20 being combined with the pipeline 10, the adjusting bracket 100 may include: First installs groove portion 120, and its top for being located at the adjusting bracket 100 is simultaneously combined with the pipeline support part 20;The One central bolt hole portion 110, the middle body of the first installation groove portion 120 described in its insertion;Second installs groove portion 130, and it is located at The bottom of the adjusting bracket 100 is simultaneously combined with the unit support 200;And, multiple grooves 150, it is located at the tune Save the bottom of support 100.
The first central bolt hole portion 110 may include:First upper hole 111, it is located at top;The first of nut shape Nut groove 112, its bottom for being located at first upper hole 111;And, the first plectane groove 113 of plectane form, it is located at institute The bottom of the first nut groove 112 is stated, and with the big diameter of the diameter than first upper hole 111.The adjusting bracket 100 also include the first nut part 300 being combined with the first central bolt hole portion 110, first nut part 300 may include:First nut portions 310, it is inserted in the form of corresponding to first nut groove 112;First plectane portion 320, It extends and including hollow bulb from first nut portions 310, and is inserted in the form of corresponding to the first plectane groove 113 Enter.The adjusting bracket 100 also includes that the first installation groove portion 120 and second described in insertion installs two the first sides of groove portion 130 Square bolt joint portion 140, the first side bolt joint portion 140 is centered on the first central bolt hole portion 110 with right The form of title is set, and may include the pore morphology of strip.
Pipeline support part 20 is carried out directly in conjunction with playing a part of support with pipeline 10 as with pipeline 10 Part, it may include adjusting bracket joint portion 21, medium pore 22 and side hole 23.Adjusting bracket joint portion 21 is located at pipeline support portion The bottom of part 20, can play a part of to be combined with adjusting bracket described later 100.Medium pore 22 is located at adjusting bracket joint portion 21 center, can be inserted by central bolt described later 30.As shown in the illustration of Figure 15 or Figure 18, side hole 23 is located at adjusting bracket Joint portion 21, and have two so that symmetrical form is settable centered on the medium pore 22 of pipeline support part 20, and can be rear The side bolt 40 stated is inserted.
Adjusting bracket 100 is located between unit support 200 and pipeline support part 20, and the unit support 200 is located at To the superiors of the unit support 200 described later of lamination, it may include first the 110, first installation of central bolt hole portion groove portion 120, Second installs groove portion 130 and the groove 150 positioned at bottom.Adjusting bracket 100 can play a part of, will from datum level to The distance at the center of pipeline 10 remains certain height.Datum level can be turned into the height from specific face to the center of pipeline 10 The virtual plane of the benchmark that degree is measured.Adjusting bracket 100 support with various height can be used make up from lamination in The top of unit support 200 of the superiors to pipeline support part 20 various differences in height.
First install groove portion 120 be located at adjusting bracket 100 top, the top of adjusting bracket 100 formed segment difference, and with it is preceding The adjusting bracket joint portion 21 of the pipeline support part 20 stated is combined, and thus can play with reference to adjusting bracket 100 and pipeline The effect of support member 20.As shown in the illustration of Fig. 2, Fig. 3 or Fig. 5, the first installation groove portion 120 may include variform.
First central bolt hole portion 110 is disposed through the middle body of the first installation groove portion 120, and may include first Upper hole 111, the first nut groove 112, the first plectane groove 113.First central bolt hole portion 110 can be played by central spiral shell described later The effect of the insertion of bolt 30.
As shown in the illustration of Fig. 4 or Fig. 6, the first upper hole 111 is located at the top of the first central bolt hole portion 110, and May include cylinder form.
First nut groove 112 is located at the bottom of the first upper hole 111, for example, it may include the nut shape of hexagon prism, can be with It is the form bigger than the diameter of the first upper hole 111.
First plectane groove 113 is located at the bottom of the first nut groove 112, for example, it may include with than the first upper hole 111 The plectane form of the big diameter of diameter.
For example, as shown in the illustration of Fig. 4, it is the hole of cylinder form that the first central bolt hole portion 110 can also be merely compriseed.
Second installs the bottom that groove portion 130 is located at adjusting bracket 100, in the bottom of adjusting bracket 100 formation segment difference, and with The protrusion joint portion 220 of unit support 200 described later is combined, and thus can play with reference to adjusting bracket 100 and unit support 200 effect.For example, as shown in the illustration of Fig. 4 or Fig. 6, second installs groove portion 130 includes two, and can be mutually right The form of title.
The bottom of adjusting bracket 100 may include multiple grooves 150.For example, as shown in the illustration of Fig. 4 or Fig. 6, adjusting bracket The groove 150 of 100 bottoms can be formed on the basis of the length direction of adjusting bracket 100 with symmetrical formal rule.Regulation branch The groove 150 of the bottom of frame 100 have material-saving effect, and with prevent manufacture adjusting bracket 100 when due to material The effect bent caused by contraction.
First nut part 300 is incorporated into the first central bolt hole portion 110, can play a part of be, to adjusting bracket 100 are supported with the central bolt 30 for being incorporated into the first central bolt hole portion 110.First nut part 300 may include first The plectane portion 320 of nut portions 310 and first.
As shown in the illustration of Figure 11, the first nut portions 310 can be with the foregoing corresponding form of the first nut groove 112 Hexagon prism form including hollow bulb.
First plectane portion 320 extends from the side of the first nut portions 310, and can be and the first foregoing plectane groove 113 corresponding forms include the plectane form of hollow bulb.For example, the first nut portions 310 form as one with the first plectane portion 320 And the first nut groove 112 and the first plectane groove 113 are inserted into, central bolt described later 30 can the nut part of insertion first 300 hollow bulb.
For example, the first nut part 300 is according to the size and pattern of the first central bolt hole portion 110, and its form can be become Shape.Reference picture 11, for example, the height of the first nut part 300 can be 7.5 ㎜, the diameter in the first plectane portion 320 can be 20 ㎜。
First side bolt joint portion 140 is to install groove portion 130 with the first foregoing installation groove portion 120 and second of insertion The pore morphology that form is formed, two can be formed centered on the first central bolt hole portion 110 in symmetrical form.First side spiral shell Bolt joint portion 140 can play a part of so that the side bolt 40 for being inserted in the side hole 23 of pipeline support part 20 is passed through It is logical.
As shown in the illustration of Fig. 5, the first side bolt joint portion 140 can be to the length direction of adjusting bracket 100 with more long Form be formed as strip, the first side bolt joint portion 140 of bar form can play a part of to be that may be such that pipeline branch Support part part 20 carries out position adjustments and is combined to the length direction of adjusting bracket 100.For example, the first side bolt joint portion 140 two ends can be semicircle form, and the width of the first side bolt joint portion 140 length than side described later The diameter of bolt 40 is bigger, may be such that produced when the bolt with Circles is combined space-minimized, and can strengthen tune Save the adhesion of the security of the structure of support 100, reinforcing side bolt 40 and adjusting bracket 100.
For example, as shown in the illustration of Fig. 2 or Fig. 3, adjusting bracket 100 may not include the first side bolt joint portion 140.
For example, size of the adjusting bracket 100 according to the pipeline 10 being supported can with height its size apart from basal surface Deformed.Reference picture 2 or Fig. 5, for example, the lateral length of adjusting bracket 100 can be 87 ㎜, longitudinal length can be 40 ㎜, highly can be 9 ㎜, or lateral length can be 167 ㎜, and longitudinal length can be 70 ㎜, highly can be 16.5 ㎜.
Fig. 7 is the stereogram of the unit support 200 of the support of pipeline 10 according to an embodiment of the invention, and Fig. 8 is from downside According to the skeleton diagram of the unit support 200 of the embodiment of Fig. 7, Fig. 9 is pipeline according to another embodiment of the invention for observation The stereogram of the unit support 200 of 10 supports, Figure 10 is according to the general of the unit support 200 of the embodiment of Fig. 9 from downside observation Sketch map, Figure 11 is first nut part 300 or the second nut part 600 of the support of pipeline 10 according to an embodiment of the invention Stereogram.
The support of pipeline 10 includes the pipeline support part 20 being combined with the pipeline 10, and the unit support 200 can Including:Protrusion joint portion 220, it is set in the form of the top for protruding from the unit support 200 and adjusts branch with described The bottom of frame 100 is combined;Second central bolt hole portion 210, the middle body of unit support 200 described in its insertion;3rd Install groove portion 230, its bottom for being located at the unit support 200 and with described in the unit support 200 positioned at downside Protrusion joint portion 220 is combined;And, multiple grooves 250, its bottom for being located at the unit support 200.Second center Bolt hole portion 210 may include:Second upper hole 211, it is located at top;Second nut groove 212 of nut shape, it is located at described The bottom of the second upper hole 211;And, the second plectane groove 213 of plectane form, it is located under second nut groove 212 Portion, and with the big diameter of the diameter than second upper hole 211.
The unit support 200 also includes the second nut part 600 combined with the second central bolt hole portion 210, Second nut part 600 may include:Second nut portions 610, it is inserted in the form of corresponding to second nut groove 212 Enter;Second plectane portion 620, it extends from second nut portions 610, and including hollow bulb, and with corresponding to the described second circle The form insertion of board slot 213.The unit support 200 also includes that groove portion 230 is installed in protrusion joint portion 220 and the 3rd described in insertion Two the second side bolt joint portions 240, the second side bolt joint portion 240 is with the second central bolt hole portion Set in symmetrical form centered on 210, and can be the pore morphology of strip.The second side bolt joint portion 240 May include:3rd upper hole 241 of strip, it is located at top;And, the first insertion part insertion groove 242, it is located at described The bottom of the 3rd upper hole 241.
Unit support 200 is multiple from basal surface lamination, and installs groove portion 130 with the second of foregoing adjusting bracket 100 It is combined, and may include that the second central bolt hole portion 210, protrusion joint portion the 220, the 3rd are installed groove portion 230 and be located at The groove 250 of bottom.Basal surface is provided with the local bottom surface portions of pipeline 10, or exists and 10, pipeline in bottom surface portions Can be the portion of the fixture 60,70 contacted with the support of pipeline 10 in the case of the fixture 60,70 that frame is combined Point.
Unit support 200 have certain height, can play a part of be, for from basal surface to adjusting bracket 100 Space lamination multiple unit supports 200, so as to support pipeline 10.For example, from basal surface to the distance of adjusting bracket 100 compared with It is small, there may be do not need unit support 200 situation or there may be needs one situation of unit support 200.For example, unit The certain height for having set of support 200 can be 10 ㎜.
Protrusion joint portion 220 is located at the top of unit support 200, including with can be with the of foregoing adjusting bracket 100 The part of the form protrusion that two installation groove portions 130 are combined, so that can bonding unit support 200 and adjusting bracket 100.This Outward, protrusion joint portion 220 play a part of be, the 3rd peace described later with the bottom for being present in another unit support 200 Tankage portion 230 is combined so as to lamination unit support 200.For example, as shown in the illustration of Fig. 7 or Fig. 9, protruding joint portion 220 Centered on the second central bolt hole portion 210 described later two can be formed with symmetrical form.
Second central bolt hole portion 210 is disposed through the middle body of unit support 200, and may include the second top Hole 211, the second nut groove 212, the second plectane groove 213.For example, the second central bolt hole portion 210 may include identical size Hole can play what is inserted by central bolt described later 30 to be connected with the first foregoing central bolt hole portion 110 Effect.
As shown in the illustration of Figure 10, the second upper hole 211 is located at the top of the second central bolt hole portion 210, and can wrap Include cylinder form.
Second nut groove 212 is located at the bottom of the second upper hole 211, for example, it may include the nut shape of hexagon prism, can be with It is the form bigger than the diameter of the second upper hole 211.
Second plectane groove 213 is located at the bottom of the second nut groove 212, for example, it may include with than the second upper hole 211 The plectane form of the big diameter of diameter.
For example, as shown in the illustration of Fig. 8, it is the hole of cylinder form that the second central bolt hole portion 210 can also be merely compriseed.
3rd installs the bottom that groove portion 230 is located at unit support 200, in the bottom of unit support 200 formation segment difference, and with The protrusion joint portion 220 of the unit support 200 of lower floor is combined, and thus can play and is combined with unit support 200 and layer Long-pending effect.For example, as shown in the illustration of Fig. 8 or Figure 10, the 3rd installs groove portion 230 includes two, and may be configured as with the Symmetrical form centered on two central bolt hole portions 210.
The bottom of unit support 200 may include multiple grooves 250.For example, as shown in the illustration of Fig. 8 or Figure 10, unit support The groove 250 of 200 bottoms can be formed on the basis of the length direction of unit support 200 with symmetrical formal rule.Unit branch The groove 250 of the bottom of frame 200 has the effect of material-saving, and with preventing in manufacturer's support 200 due to material The effect bent caused by contraction.
Second nut part 600 is incorporated into the second central bolt hole portion 210, can play a part of be, to unit support 200 are supported with the central bolt 30 for being incorporated into the second central bolt hole portion 210.Second nut part 600 may include second The plectane portion 620 of nut portions 610 and second.For example, the second nut part 600 can be with the homomorphosis of the first nut part 300.
As shown in the illustration of Figure 11, the second nut portions 610 can be and the foregoing corresponding form bag of the second nut groove 212 Include the hexagon prism form with hollow bulb.
Second plectane portion 620 extends from the side of the second nut portions 610, and can be and the second foregoing plectane groove 213 corresponding forms include the plectane form with hollow bulb.For example, the second nut portions 610 are formed as with the second plectane portion 620 One and be inserted into the second nut groove 212 and the second plectane groove 213, central bolt described later 30 can the nut portions of insertion second The hollow bulb of part 600.
For example, the second nut part 600 is according to the size and pattern of the second central bolt hole portion 210, and its form can be become Shape.Reference picture 11, for example, the height of the second nut part 600 can be 7.5 ㎜, the diameter in the second plectane portion 620 can be 20 ㎜。
Second side bolt joint portion 240 is formed in the form of insertion protrusion joint portion 220 with the 3rd installation groove portion 230 Pore morphology, and may include the 3rd upper hole 241, the first insertion part insertion groove 242.Second side bolt joint portion 240 Centered on the second central bolt hole portion 210 two can be formed in symmetrical form.Second side bolt joint portion 240 can play Effect be so that be inserted in the insertion of side bolt 40 in the side hole 23 of pipeline support part 20.For example, the second side spiral shell Bolt joint portion 240 may include the hole of same size, to be connected with the first side bolt joint portion 140.
As shown in the illustration of Figure 10, the 3rd upper hole 241 is located at the top of the second side bolt joint portion 240, and can Including cylindroid form.
First insertion part insertion groove 242 is located at the bottom of the 3rd upper hole 241, can play so that the first insertion described later The effect that part 400 is inserted and installed.For example, the first insertion part insertion groove 242 can be than the size of the 3rd upper hole 241 The hexagonal post shapes of bigger form.
As shown in the illustration of Fig. 9, the second side bolt joint portion 240 can along the length direction of unit support 200 with compared with Form long is formed as strip, and the second side bolt joint portion 240 of bar form can play a part of to be that may be such that pipeline Support member 20 carries out position adjustments and is combined to the length direction of unit support 200.For example, the 3rd upper hole 241 Two ends can be semicircle form, and the width of the 3rd upper hole 241 diameter of the length than side bolt 40 described later It is bigger, produced when the bolt with Circles is combined space-minimized is may be such that, and the knot of unit support 200 can be strengthened The adhesion of the security of structure, reinforcing side bolt 40 and unit support 200.
For example, as shown in the illustration of Fig. 7, unit support 200 may not include the second side bolt joint portion 240.
For example, size of the unit support 200 according to the pipeline 10 being supported can with height its size apart from basal surface Deformed.Reference picture 7 or Fig. 9, for example, the lateral length of unit support 200 can be 81 ㎜, longitudinal length can be 40 ㎜, highly can be 10 ㎜, or lateral length can be 120 ㎜, and longitudinal length can be 70 ㎜, highly can be 10 ㎜.
Figure 12 is the stereogram of the first insertion part 400 of the support of pipeline 10 according to an embodiment of the invention, Tu13Shi The stereogram of the second insertion part 500 of the support of pipeline 10 according to an embodiment of the invention.
The unit support 200 includes the hollow bulb 410 of strip, may also include and is inserted into the second side bolt knot First insertion part 400 in conjunction portion 240.The hollow bulb 510 of the unit support 200 including strip, may also include with it is described The second insertion part 500 that 3rd installation groove portion 230 is combined.
First insertion part 400 forms the first insertion part for being inserted in the second side bolt joint portion 240 with corresponding Insertion groove 242, and may include hexagon prism form.As shown in the illustration of Figure 12, the first insertion part 400 may include there is such as the The hollow bulb 410 of the size of three upper holes 241 and the strip of pattern so that produced when the bolt with Circles is combined It is space-minimized, and the security of the structure of unit support 200 can be strengthened, reinforcing side bolt 40 and unit support 200 Adhesion.First insertion part 400 plays a part of, to unit support 200 be incorporated into the second side bolt joint portion 240 side bolt 40 is supported.
Second insertion part 500 is combined with the 3rd installation groove portion 230, and may include the hollow bulb 510 of strip. As shown in the illustration of Figure 13, the second insertion part 500 is inserted in the 3rd installation and groove portion 230 and combines, its one end with it is non-bulging in The form of the longitudinal component of unit support 200 turns into linear, and other ends may include Circles.Second insertion part 500 is combined Groove portion 230 is installed in the 3rd existed in the bottom of unit support 200 and plays similar to foregoing protrusion joint portion 220 Function.As shown in the illustration of Figure 16, with the unit that the lower floor of the unit support 200 for being combined with the second insertion part 500 is combined 3rd installation groove portion 230 of support 200 can also be combined with the second insertion part 500, so as in the bonding unit branch of fixture 70 Second insertion part 500 can be used during frame 200, and the fixture 70 includes groove described later.For example, the second insertion part 500 the second mounting grooves that also can be combined in adjusting bracket 100.
Second insertion part 500 may include hollow bulb 510, the hollow bulb of the insertion part 400 of the hollow bulb 510 and first 410 and the correspondence of the 3rd upper hole 241.Second insertion part 500 can play a part of, to unit support 200 and combination Side bolt 40 in the second side bolt joint portion 240 is supported.For example, the second insertion part 500 can be right with two The combination of shape and state of title installs groove portion 230 in the 3rd, so as to be incorporated into two the 3rd installation groove portions 230.
For example, the size of the first insertion part 400 and the second insertion part 500 according to the second side bolt joint portion 240 Can be deformed.Reference picture 12, for example, the lateral length of the first insertion part 400 can be 26.5 ㎜, longitudinal length can be 10 ㎜, highly can be 5 ㎜.For example, referring to Figure 13, the lateral length of the second insertion part 500 can be 31 ㎜, longitudinal length Can be 13 ㎜, highly can be 4 ㎜.
Hereinafter, the method for setting the support of pipeline 10 is described in detail referring to the drawings.
Figure 14 is the skeleton diagram of the method to set up of the support of pipeline 10 of first embodiment of the invention.
The method to set up of the support of pipeline 10 includes:S1 steps, in order to support pipeline 10, and will be combined with the pipeline 10 First installation groove portion 120 of pipeline support part 20 and adjusting bracket 100 is combined;S2 steps, by the first nut part 300 The first central bolt hole portion 110 of the adjusting bracket 100 is incorporated into, and the first insertion part 400 is being incorporated into unit Second side bolt joint portion 240 of support 200 and the second nut part 600 is incorporated into the of the unit support 200 After two central bolt hole portions 210, the multiple unit supports 200 of lamination;S3 steps, with reference to the convex of the unit support 200 Go out joint portion 220 and groove portion 130 is installed with the second of the adjusting bracket 200, the adjusting bracket 100 is located at the pipeline support Part 20 and between the unit support 200 of the superiors' lamination, will protect from datum level to the height at the center of the pipeline 10 It is prespecified height to hold, and the unit support 200 is single or multiple from basal surface lamination and enters with the adjusting bracket 100 Row is combined, and can have the height for having set.
Be may also include after the S3 steps:S4 steps, from first of in the unit support 200 as lamination Unit support 700 removes second nut part 600, and central bolt 30 is inserted and the knot of the first unit support 700 Second central bolt hole portion 210 of the second unit support 800 for closing, then to the first unit support 700 and described second Unit support 800 is combined;S5 steps, from lamination in the 3rd unit support 900 of the downside of the second unit support 800 Remove first insertion part 400 and second nut part 600, side hole of the insertion to the pipeline support part 20 23rd, the second side bolt knot of the first side bolt joint portion 140 of the adjusting bracket 100 and the unit support 200 After conjunction portion 240 carries out the side bolt 40 of insertion, combine nut and the side bolt 40, will be with the knot of side bolt 40 After the nut for closing inserts the first insertion part insertion groove 242 of the 3rd unit support 900, screw combines the side Bolt 40 and the nut;S6 steps, screw combination central bolt 30 and fixture 60, the central bolt 30 is from described second The insertion of second central bolt hole portion 210 of unit support 800 to lamination undermost described unit support 200, the fixation Thing 60 is located at the basal surface.
The step of S1 steps to pipeline support part 20 and adjusting bracket 100 as being combined, may also include pipeline The step of support joint portion 21 of support member 20 is incorporated into the first installation groove portion 120 of adjusting bracket 100.
S1 steps also can be in central bolt described later 30 or the medium pore 22 of the insertion pipeline of side bolt 40 support member 20 Or implement after the arbitrary steps before side hole 23.
S2 steps may also include the steps of:First nut part 300 is incorporated into the first central spiral shell of adjusting bracket 100 Female hole portion 100, the second nut part 600 is incorporated into the second central bolt hole portion 210 of unit support 200, and first is inserted Enter after part 400 is incorporated into the second side bolt joint portion 240 of unit support 200, to the protrusion knot of bottom unit support 200 3rd installation groove portion 230 of conjunction portion 220 and upper floor unit support 200 is combined, so that lamination unit support 200.
S3 steps may include the step of being combined to unit support 200 and adjusting bracket 100.Unit support 200 and tune The unit support 200 of the combination for the lamination in S2 steps of support 100 is saved, can be to the convex of the unit support 200 of the superiors The the second installation groove portion 130 for going out joint portion 220 and adjusting bracket 100 is combined.Only, to adjusting bracket 100 and unit The unit support 200 of lamination can be incorporated into the unit support 200 combined with adjusting bracket 100 after being combined for support 200.
Next S4 steps are observed, the first unit support 700 is as any one in the unit support 200 of lamination The unit support 200 of the second nut part 600 that removal is combined in S2 steps.Second unit support 800 is in the first unit The unit support that the lower floor of support 700 is directly combined with the first unit support 700.S4 steps may include following steps:From first The second nut part 600 is removed in unit support 700, and central bolt 30 is inserted the second center of the second unit support 800 After bolt hole portion 210, the first unit support 700 and the second unit support 800 are combined.Central bolt 30 is insertion pipeline Second center of the medium pore 22 of support member 20, the first central bolt hole portion 110 of adjusting bracket 100 and unit support 200 The bolt of bolt hole portion 210.
Observation S5 steps, the 3rd unit support 900 as compared to the lamination of the second unit support 800 in following unit support 200, it is the unit support 200 for removing the first insertion part 400 and the second nut part 600 combined in S2 steps.S5 is walked Suddenly following steps be may include:The first insertion part 400 and the second nut part 600 are removed from the 3rd unit support 900, it is right to insert The side hole 23 of pipeline support part 20, the first side bolt joint portion 140 of adjusting bracket 100 and unit support 200 Second side bolt joint portion 240 carries out the side bolt 40 of insertion.
Side bolt 40 is side hole 23, the first side bolt knot of adjusting bracket 100 of insertion pipeline support member 20 The bolt of the second side bolt joint portion 240 of conjunction portion 140 and unit support 200.For example, side bolt 40 can use than The small bolt of the diameter of central bolt 30.
Next, nut and side bolt 40 are combined, and the nut insertion first that will be combined with side bolt 40 is inserted Unit insert groove 242, to be installed on the first insertion part insertion groove 242 of the 3rd unit support 900, afterwards can screw combination Side bolt 40 and nut.If S5 steps are carried out, propped up from pipeline support part 20 and adjusting bracket 100 and with regulation The unit support 900 of unit support 200 to the 3rd that frame 100 is combined is realized combining by side bolt 40 with screw combination.
S6 steps may include following steps:Screw combination central bolt 30 and fixture 60, the central bolt 30 is from The insertion of second central bolt hole portion 210 of two unit supports 800 to lamination undermost unit support 200, the fixture 60 are located at basal surface.For example, fixture can be I-steel (H beam).
For example, as shown in the illustration of Figure 14, including the second unit support 800 and the 3rd unit support 900 and it is located at second Unit support 200 between the unit support 900 of unit support 800 and the 3rd can be central bolt 30 and side bolt 40 simultaneously The interval of insertion.Overlap (overlap) interval of central bolt 30 and the equal insertion of side bolt 40 can play more strongly The support of pipeline 10 is combined, so that the effect being more stably supported to the pipe arrangement of pipeline 10.
Figure 15 is the skeleton diagram of the method to set up of the support of pipeline 10 according to the second embodiment of the present invention.
The method to set up of the support of pipeline 10 may also include S7 steps after the S3 steps, in the S7 steps, insertion The first central bolt hole portion 110 and the list of medium pore 22, the adjusting bracket 100 to the pipeline support part 20 After second central bolt hole portion 210 of position support 200 carries out the central bolt 30 of insertion, make the central bolt 30 and positioned at institute The fixture 60 for stating basal surface carries out screw combination.
S7 steps may also include the steps of:Insert the to the medium pore 22 of pipeline support part 20, adjusting bracket 100 After second central bolt hole portion 210 of one central bolt hole portion 110 and unit support 200 carries out the central bolt 30 of insertion, Central bolt 30 and the fixture 60 positioned at basal surface is set to carry out screw combination.For example, as shown in the illustration of Figure 15, fixture can Being I-steel.
Second embodiment implements S7 after S3 steps compared with first embodiment without S4 steps are implemented to S6 steps Step, in the case of little from datum level to the distance at the center of pipeline 10, relatively simple and promptly can set and use.
Figure 16 is the skeleton diagram of the method to set up of the support of pipeline 10 according to the third embodiment of the present invention.
The method to set up of the support of pipeline 10 may also include after the S3 steps:S4 steps, from the list as lamination The first unit support 700 of one in the support 200 of position removes second nut part 600, and central bolt 30 is inserted Second central bolt hole portion 210 of the second unit support 800 combined with the first unit support 700, then to described One unit support 700 and the second unit support 800 are combined;S5 steps, from lamination in the second unit support 800 The 3rd unit support 900 of downside remove first insertion part 400 and second nut part 600, insert to institute State the side hole 23 of pipeline support part 20, the first side bolt joint portion 140 of the adjusting bracket 100 and the unit After second side bolt joint portion 240 of support 200 carries out the side bolt 40 of insertion, make nut and the knot of side bolt 40 Close, the nut that will be combined with the side bolt 40 inserts the first insertion part insertion of the 3rd unit support 900 After groove 242, screw combines the side bolt 40 and the nut;S8 steps, will be located at the unit support 200 of lamination After undermost 5th unit support 1100 is separated from the 4th unit support 1000 combined with the 5th unit support 1100, Second insertion part 500 is inserted the 3rd installation groove portion 230 of the 4th unit support 1000, the 5th unit branch is overturn Frame 1100 so that the 5th unit support 1100 the 3rd installation groove portion 230 combined with second insertion part 500, or Person, overturns the 5th unit support 1100 so that the second insertion part 500 inserts the of the 5th unit support 1100 Three install groove portion 230, and make the 3rd installation groove portion 230 of second insertion part 500 and the 4th unit support 1000 With reference to;S9 steps, make the protrusion joint portion 220 of the 5th unit support 1100 and positioned at the basal surface including groove shape Fixture 70 combine;S10 steps, screw knot is carried out by central bolt 30 and the fixture 70 with the screw 50 of bar form Close, the second central bolt of the second unit support 800 and the 5th unit support 1100 described in the insertion of the central bolt 30 Hole portion 210.
S4 steps, S5 steps are as previously described.
Next S8 steps are observed, the 5th unit support 1100 be located at lamination unit support 200 most under Layer unit support 200, the 4th unit support 1000 be located at the 5th unit support 1100 upper strata and with the 5th unit support 1100 directly in conjunction with unit support 200.
S8 steps are the steps of:5th unit support 1100 of lamination is separated from the 4th unit support 1000, and will After second insertion part 500 inserts the 3rd installation groove portion 230 of the 4th unit support 1000 or the 5th unit support 1100, upset 5th unit support 1100 is so that the 4th unit support 1000 and the 5th unit support 1100 are combined.In other words, such as Figure 16 Illustration shown in, in the case that the second insertion part 500 is inserted into the 4th unit support 1000, make the 5th unit support 1100 The 3rd installation insertion part 500 of groove portion 230 and second is combined, and the second insertion part 500 is inserted into the 5th unit support 1100 In the case of, make the 3rd of the 4th unit support 1000 insertion part 500 of groove portion 230 and second is installed and combine, so as to the 4th can be made Unit support 1000 and upturned 5th unit support 1100 are combined.
S9 steps may include following steps:Make the protrusion joint portion 220 of the 5th unit support 1100 and be located at basal surface Fixture 70 including groove shape is combined.For example, as shown in the illustration of Figure 16, including the fixture 70 of groove shape may include have Pallet (tray) form of the part on hollow bulb and top into opening.For example, the protrusion of the 5th unit support 1100 is combined The insertion of portion 220 includes the groove 71 of the fixture 70 of groove shape, so as to the 5th unit support 1100 and consolidating including groove shape can be made Earnest 70 is combined.
S10 steps may include following steps:Central bolt 30 and fixture 70 are carried out into spiral shell using the screw 50 of bar form Silk combination, the second central bolt hole portion 210 of 30 pairs of the second unit supports 800 of the central bolt and the 5th unit branch of lamination Second central bolt hole portion 210 of frame 1100 carries out insertion, and the fixture 70 includes groove shape.
For example, as shown in the illustration of Figure 16, for the screw 50 of bar form, the length of the length direction of screw can be longer than The length of the width of the groove 71 of the fixture 70 including groove shape, or the transverse direction of the fixture 70 including groove shape can be longer than The length in direction.For example, after the insertion central bolt 30 of screw 50 of the bar form combined with central bolt 30, insertion includes groove Behind the inside of groove 71 of the fixture 70 of shape, make central bolt 30 to the width of the groove 71 of the fixture 70 including groove shape The inner side of the fixture 70 including groove shape is rotated and is stuck in, so as to central bolt 30 and the fixation including groove shape can be made The screw of thing 70 is combined.
Figure 17 is the skeleton diagram of the method to set up of the support of pipeline 10 according to the fourth embodiment of the invention.
The method to set up of the support of pipeline 10 may also include after the S3 steps:S8 steps, will be located at the list of lamination The undermost 5th unit support 1100 of position support 200 is from the 4th unit support combined with the 5th unit support 1100 After 1000 separate, the second insertion part 500 is inserted the 3rd installation groove portion 230 of the 4th unit support 1000, overturn institute The 5th unit support 1100 is stated so that the 3rd installation groove portion 230 and second insertion section of the 5th unit support 1100 Part 500 is combined, or, the 5th unit support 1100 is overturn so that the second insertion part 500 inserts the 5th unit 3rd installation groove portion 230 of support 1100, and make the 3rd of second insertion part 500 and the 4th unit support 1000 the Groove portion 230 is installed to combine;S9 steps, make the protrusion joint portion 220 of the 5th unit support 1100 and are located at the basal surface The fixture 70 including groove shape combine;S11 steps, insert medium pore 22, the tune to the pipeline support part 20 Second central bolt hole portion 210 of the first central bolt hole portion 110 and the unit support 200 that save support 100 is passed through After logical central bolt 30, the central bolt 30 and the fixture 70 are carried out into screw with the screw 50 of bar form and is combined.
S8 steps, S9 steps are as previously described.
S11 steps may include following steps:Insert the to the medium pore 22 of pipeline support part 20, adjusting bracket 100 After second central bolt hole portion 210 of one central bolt hole portion 110 and unit support 200 carries out the central bolt 30 of insertion, Central bolt 30 and fixture 70 including groove shape are carried out into screw with the screw 50 of bar form to be combined.
For example, as shown in the illustration of Figure 17, for the screw 50 of bar form, the length of the length direction of screw can be longer than The length of the width of the groove 71 of the fixture 70 including groove shape, or the transverse direction of the fixture 70 including groove shape can be longer than The length in direction.For example, after the insertion central bolt 30 of screw 50 of the bar form combined with central bolt 30, insertion includes groove After the groove 71 of the fixture 70 of shape is inner, central bolt 30 is set to be revolved to the width of the groove 71 of the fixture 70 including groove shape Turn and be stuck in the inner side of the fixture 70 including groove shape, so as to can combine central bolt 30 and fixture screw.
Fourth embodiment compared with 3rd embodiment, due to without implementing S4 steps and S5 steps, thus from datum level To the center of pipeline 10 distance it is little in the case of, relatively simple and promptly can set and use.
Figure 18 is the skeleton diagram of the method to set up of the support of pipeline 10 according to the fifth embodiment of the invention.
The method to set up of the support of pipeline 10 may also include after the S3 steps:S8 steps, will be located at the list of lamination The undermost 5th unit support 1100 of position support 200 is from the 4th unit support combined with the 5th unit support 1100 After 1000 separate, the second insertion part 500 is inserted the 3rd installation groove portion 230 of the 4th unit support 1000, overturn institute The 5th unit support 1100 is stated so that the 3rd installation groove portion 230 and second insertion section of the 5th unit support 1100 Part 500 is combined, or, the 5th unit support 1100 is overturn so that the second insertion part 500 inserts the 5th unit 3rd installation groove portion 230 of support 1100, and make the 3rd of second insertion part 500 and the 4th unit support 1000 the Groove portion 230 is installed to combine;S9 steps, make the protrusion joint portion 220 of the 5th unit support 1100 and are located at the basal surface The fixture 70 including groove shape combine;S12 steps, insert side hole 23, the tune to the pipeline support part 20 Second side bolt joint portion 240 of the first side bolt joint portion 140 and the unit support 200 of saving support 100 is entered After the side bolt 40 of row insertion, the side bolt 40 and the fixture 70 are carried out into screw knot with the screw 50 of bar form Close.
S8 steps, S9 steps are as previously described.
S12 steps may include following steps:Insert the to the side hole 23 of pipeline support part 20, adjusting bracket 100 Second side bolt joint portion 240 of side square bolt joint portion 140 and unit support 200 carries out the side bolt of insertion 40, side bolt 40 and fixture 70 including groove shape are carried out into screw with the screw 50 of bar form and is combined.
For example, as shown in the illustration of Figure 18, for the screw 50 of bar form, the length of the length direction of screw can be longer than The length of the width of the groove 71 of the fixture 70 including groove shape, or the transverse direction of the fixture 70 including groove shape can be longer than The length in direction.For example, after the insertion side square bolt 40 of screw 50 of the bar form combined with side bolt 40, insertion includes groove After the groove 71 of the fixture 70 of shape is inner, side bolt 40 is set to be revolved to the width of the groove 71 of the fixture 70 including groove shape Turn and be stuck in the inner side of the fixture 70 including groove shape, so as to side bolt 40 and the fixture including groove shape can be made 70 screws are combined.
5th embodiment central bolt 30 instead in fourth embodiment and use the situation of side bolt 40, the 5th Embodiment implements S4 steps and S5 steps compared with 3rd embodiment due to no, thus from datum level to the center of pipeline 10 Distance it is little in the case of, relatively simple and promptly can set and use.
Figure 19 is the skeleton diagram of the method to set up of the support of pipeline 10 according to the sixth embodiment of the invention.
The method to set up of the support of pipeline 10 may also include after the S3 steps:S13 steps, insert to the pipeline support The side hole 23 of part 20, the first side bolt joint portion 140 of the adjusting bracket 100 and the unit support 200 After second side bolt joint portion 240 carries out the side bolt 40 of insertion, by the side bolt 40 and positioned at the basal surface Fixture 60 carry out screw combination.
S13 steps may include following steps:Insert the to the side hole 23 of pipeline support part 20, adjusting bracket 100 Second side bolt joint portion 240 of side square bolt joint portion 140 and unit support 200 carries out the side bolt of insertion 40, carry out screw combination by side bolt 40 and positioned at the fixture 60 of basal surface.For example, as shown in the illustration of Figure 19, it is fixed Thing can be I-steel.
Sixth embodiment central bolt 30 instead in second embodiment and use the situation of side bolt 40, with the One embodiment is compared, and S4 steps and S5 steps are implemented due to no, thus little to the distance at the center of pipeline 10 from datum level In the case of, relatively simple and promptly can set and use.
More than, although embodiment is distinguish between being illustrated for convenience of description, but, the embodiment can be one Realized together in body, and can realized to be only made up of combined form a part for each embodiment.
More than, although all inscapes to constituting embodiments of the invention are combined into one or combine and operate It is illustrated, but the present invention is not necessarily defined in the embodiment.In other words, as long as in purpose of the present invention scope Interior, its all of the foundation elements also can selectively be combined into more than one and be operated.In addition, " the bag recorded above Include ", the term such as " composition " or " having ", it should be construed to, as long as without especially opposite record, it is meant that can include corresponding Inscape, thus and non-excluded other inscapes, but also include other inscapes.Including technical or science All terms of property term, as long as no differently being defined, just with possessing typically with the technical field belonging to the present invention The identical meaning that the technical staff of knowledge is conventionally understood.Term as defined in dictionary, the term for generally using Should be construed to it is identical with the contextual meaning of correlation technique, as long as and do not explicitly define in the present invention, be not interpreted as Preferably or excessively formal meaning.
Explanation above is only the explanation that citing is carried out to technological thought of the invention, if in the skill belonging to the present invention Art field possesses the technical staff of general knowledge, is not departing from the range of intrinsic propesties of the invention, can carry out various modifications And deformation.Therefore, disclosed embodiment of this invention is not intended to be defined technological thought of the invention, but for right It is illustrated, and the scope of technological thought of the invention is not limited by the embodiment.Protection scope of the present invention should Explained by the claims below, and should be construed to, therewith all technological thought bags in the range of identical It is contained in interest field of the invention.
Label declaration
10:Pipeline 20:Pipeline support part
21:The adjusting bracket joint portion 22 of pipeline support part:The medium pore of pipeline support part
23:The side hole 30 of pipeline support part:Central bolt
40:Side bolt 50:The screw of bar form
60:Fixture 70:Fixture including groove shape
100:Adjusting bracket 110:First central bolt hole portion
111:First upper hole 112:First nut groove
113:First plectane groove 120:First installs groove portion
130:Second installs groove portion 140:First side bolt joint portion
150:Adjusting bracket lower channel 200:Unit support
210:Second central bolt hole portion 211:Second upper hole
212:Second nut groove 213:Second plectane groove
220:Protrusion joint portion 230:3rd installs groove portion
240:Second side bolt joint portion 241:3rd upper hole
242:First insertion part insertion groove 250:Unit support lower channel
300:First nut part 310:First nut portions
320:First plectane portion 400:First insertion part
410:First insertion part hollow bulb 500:Second insertion part
510:Second insertion part hollow bulb 600:Second nut part
610:Second nut portions 620:Second plectane portion
700:First unit support 800:Second unit support
900:3rd unit support 1000:4th unit support
1100:5th unit support

Claims (18)

1. a kind of support of pipelines, it is characterised in that including:
Adjusting bracket;And
Unit support, it is single or multiple from basal surface lamination, so that combined with the adjusting bracket, and with the height for having set Degree;
The adjusting bracket is located at lamination between the unit support and pipeline of the superiors, so that from datum level to described The height of pipeline center remains height set in advance;
The unit support includes:
Protrusion joint portion, its protrusion is arranged at the top of the unit support and is combined with the bottom of the adjusting bracket;
Second central bolt hole portion, the middle body of unit support described in its insertion;
3rd installs groove portion, its bottom for being located at the unit support and and the unit support positioned at downside the protrusion Joint portion combines;And
Multiple grooves, its bottom for being arranged at the unit support.
2. support of pipelines according to claim 1, it is characterised in that including:
Pipeline support part, itself and the pipeline are combined;
The adjusting bracket includes:
First install groove portion, its top for being located at the adjusting bracket and with the pipeline support part combine;
First central bolt hole portion, the middle body of the first installation groove portion described in its insertion;
Second install groove portion, its bottom for being located at the adjusting bracket and with the unit support combine;And
Multiple grooves, its bottom for being arranged at the adjusting bracket.
3. support of pipelines according to claim 2, it is characterised in that the first central bolt hole portion includes:
First upper hole, it is located at top;
First nut groove, its bottom for being located at first upper hole is nut shape;And
First plectane groove, its bottom for being located at first nut groove and be plectane form, the plectane form has than described The big diameter of the diameter of the first upper hole.
4. support of pipelines according to claim 3, it is characterised in that
The adjusting bracket also includes the first nut part, first nut part and the first central bolt hole portion knot Close;
First nut part includes:
First nut portions, it is inserted in the form of corresponding to first nut groove;
First plectane portion, it extends and including hollow bulb from first nut portions, and with corresponding to the first plectane groove Form is inserted.
5. support of pipelines according to claim 2, it is characterised in that
The adjusting bracket also includes two the first side bolt joint portions, the described in the first side bolt joint portion insertion One installs groove portion and second installs groove portion;
The first side bolt joint portion is symmetrical arranged and the hole as strip centered on the first central bolt hole portion Form.
6. support of pipelines according to claim 1, it is characterised in that the second central bolt hole portion includes:
Second upper hole, it is located at top;
Second nut groove, its bottom for being located at second upper hole is nut shape;And
Second plectane groove, its bottom for being located at second nut groove and be plectane form, the plectane form has than described The big diameter of the diameter of the second upper hole.
7. support of pipelines according to claim 6, it is characterised in that
The unit support also includes the second nut part, second nut part and the second central bolt hole portion knot Close;
Second nut part includes:
Second nut portions, it is inserted in the form of corresponding to second nut groove;
Second plectane portion, it extends and including hollow bulb from second nut portions, and with corresponding to the second plectane groove Form is inserted.
8. support of pipelines according to claim 1, it is characterised in that
The unit support also includes two the second side bolt joint portions, convex described in the second side bolt joint portion insertion Go out joint portion and the 3rd installation groove portion;
The second side bolt joint portion is symmetrical arranged and the hole as strip centered on the second central bolt hole portion Form.
9. support of pipelines according to claim 8, it is characterised in that
The unit support includes the hollow bulb of strip and also includes that the first of insertion the second side bolt joint portion inserts Enter part.
10. support of pipelines according to claim 8, it is characterised in that the second side bolt joint portion includes:
3rd upper hole, it is located at top and is strip;And
First insertion part insertion groove, its bottom for being located at the 3rd upper hole.
11. supports of pipelines according to claim 1, it is characterised in that
The unit support includes the second insertion part, the hollow bulb of second insertion part including strip, and with it is described 3rd installs groove portion combines.
12. a kind of methods to set up of support of pipelines, it is characterised in that comprise the following steps:
A () to pipeline in order to be supported, and the first peace of pair pipeline support part combined with the pipeline and adjusting bracket Tankage portion is combined;
B () the first nut part is incorporated into the first central nut hole portion of the adjusting bracket, and by the first insertion part knot The second side bolt joint portion together in unit support and the second nut part is incorporated into the second of the unit support After the bolt hole portion of centre, the multiple unit supports of lamination;
C () is combined to the protrusion joint portion of the unit support and the second installation groove portion of the adjusting bracket;
The adjusting bracket is located at the pipeline support part and lamination between the unit support of the superiors, so that from Datum level to the height of the pipeline center remains height set in advance;
The unit support is single or multiple so as to be combined with the adjusting bracket from basal surface lamination, and with the height for having set Degree.
The method to set up of 13. supports of pipelines according to claim 12, it is characterised in that after (c) step also Comprise the following steps:
D () removes second nut part from the first unit support of in the unit support as lamination, and Second central bolt hole portion of the second unit support that central bolt insertion is combined with the first unit support, then to institute State the first unit support and the second unit support is combined;
E the 3rd unit support of () from lamination in the downside of the second unit support removes first insertion part and described Second nut part, insertion is to the side hole of the pipeline support part, the first side bolt joint portion of the adjusting bracket And after the second side bolt joint portion of the unit support carries out the side bolt of insertion, make nut and the side bolt With reference to the nut that will be combined with the side bolt inserts the first insertion part insertion groove of the 3rd unit support Afterwards, screw combines the side bolt and the nut;
(f) screw combination central bolt and fixture, second central bolt of the central bolt from the second unit support Hole portion insertion to lamination undermost described unit support, the fixture be located at the basal surface.
The method to set up of 14. supports of pipelines according to claim 12, it is characterised in that after (c) step also Comprise the following steps:
G () insertion is to the medium pore of the pipeline support part, the first central bolt hole portion of the adjusting bracket and described After second central bolt hole portion of unit support carries out the central bolt of insertion, make the central bolt and positioned at the basal surface Fixture carry out screw combination.
The method to set up of 15. supports of pipelines according to claim 12, it is characterised in that after (c) step also Comprise the following steps:
D () removes second nut part from the first unit support of in the unit support as lamination, and Second central bolt hole portion of the second unit support that central bolt insertion is combined with the first unit support, then to institute State the first unit support and the second unit support is combined;
E the 3rd unit support of () from lamination in the downside of the second unit support removes first insertion part and described Second nut part, insertion is to the side hole of the pipeline support part, the first side bolt joint portion of the adjusting bracket And after the second side bolt joint portion of the unit support carries out the side bolt of insertion, make nut and the side bolt With reference to the nut that will be combined with the side bolt inserts the first insertion part insertion groove of the 3rd unit support Afterwards, screw combines the side bolt and the nut;
H () is combined the undermost 5th unit support for being located at the unit support of lamination from the 5th unit support The 4th unit support separate after, the second insertion part is inserted the 3rd installation groove portion of the 4th unit support, overturn institute State the 5th unit support so that the 5th unit support the 3rd installation groove portion combined with second insertion part, or Person, overturns the 5th unit support so that the second insertion part inserts the 3rd installation groove portion of the 5th unit support, And combine second insertion part and the 3rd installation groove portion of the 4th unit support;
I () makes the protrusion joint portion of the 5th unit support and the fixture knot including groove shape for being located at the basal surface Close;
J central bolt and the fixture are carried out screw and are combined by () with the screw of bar form, described in the central bolt insertion Second central bolt hole portion of the second unit support and the 5th unit support.
The method to set up of 16. supports of pipelines according to claim 12, it is characterised in that after (c) step also Comprise the following steps:
H () is combined the undermost 5th unit support for being located at the unit support of lamination from the 5th unit support The 4th unit support separate after, the second insertion part is inserted the 3rd installation groove portion of the 4th unit support, overturn institute State the 5th unit support so that the 5th unit support the 3rd installation groove portion combined with second insertion part, or Person, overturns the 5th unit support so that the second insertion part inserts the 3rd installation groove portion of the 5th unit support, And combine second insertion part and the 3rd installation groove portion of the 4th unit support;
I () makes the protrusion joint portion of the 5th unit support and the fixture knot including groove shape for being located at the basal surface Close;
K () insertion is to the medium pore of the pipeline support part, the first central bolt hole portion of the adjusting bracket and described After second central bolt hole portion of unit support carries out the central bolt of insertion, by the central bolt and the fixture and bar The screw of form carries out screw combination.
The method to set up of 17. supports of pipelines according to claim 12, it is characterised in that after (c) step also Comprise the following steps:
H () is combined the undermost 5th unit support for being located at the unit support of lamination from the 5th unit support The 4th unit support separate after, the second insertion part is inserted the 3rd installation groove portion of the 4th unit support, overturn institute State the 5th unit support so that the 5th unit support the 3rd installation groove portion combined with second insertion part, or Person, overturns the 5th unit support so that the second insertion part inserts the 3rd installation groove portion of the 5th unit support, And combine second insertion part and the 3rd installation groove portion of the 4th unit support;
I () makes the protrusion joint portion of the 5th unit support and the fixture knot including groove shape for being located at the basal surface Close;
M () is inserted to the side hole of the pipeline support part, the first side bolt joint portion of the adjusting bracket and institute After stating the second side bolt joint portion of unit support and carrying out the side bolt of insertion, by the side bolt and the fixture Screw is carried out with the screw of bar form to be combined.
The method to set up of 18. supports of pipelines according to claim 12, it is characterised in that after (c) step also Comprise the following steps:
N () is inserted to the side hole of the pipeline support part, the first side bolt joint portion of the adjusting bracket and institute After stating the second side bolt joint portion of unit support and carrying out the side bolt of insertion, by the side bolt and positioned at the base The fixture of bottom surface carries out screw combination.
CN201611001531.8A 2015-11-10 2016-11-10 Support of pipelines and its setting method Active CN106838468B (en)

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
KR1020150157250A KR101638082B1 (en) 2015-11-10 2015-11-10 Pipe supports and installation methods thereof
KR10-2015-0157250 2015-11-10

Publications (2)

Publication Number Publication Date
CN106838468A true CN106838468A (en) 2017-06-13
CN106838468B CN106838468B (en) 2018-11-27

Family

ID=56504682

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201611001531.8A Active CN106838468B (en) 2015-11-10 2016-11-10 Support of pipelines and its setting method

Country Status (2)

Country Link
KR (1) KR101638082B1 (en)
CN (1) CN106838468B (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR102240956B1 (en) * 2020-10-10 2021-04-15 주식회사 한솔세미텍 Band type pipe fixing apparatus installed in clean room

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
FR2553493A1 (en) * 1983-10-17 1985-04-19 Philippe Chastaing Adjustable and modular device for the supports of a tubular network
CN1190634A (en) * 1997-02-15 1998-08-19 螺纹管保护技术有限公司 Apparatus for supporting pipes
JP2002295730A (en) * 2001-03-29 2002-10-09 Mym Corp Pipe support
WO2009082087A1 (en) * 2007-12-21 2009-07-02 Ki-Yong Song Large diameter pillar construction method by layer-built and frame construction method adapting the same
CN202302309U (en) * 2011-11-04 2012-07-04 中国石油天然气集团公司 Adjustable fixed base

Family Cites Families (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR910005119Y1 (en) * 1989-04-07 1991-07-20 이창열 Refractory Brick Structure for Furnace
KR101004747B1 (en) * 2007-12-21 2011-01-04 송기용 Pillar construction method by layer-built and frame construction method adapting the same
CN203395384U (en) * 2013-03-14 2014-01-15 王浩 Adjustable modular pipe clamp

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
FR2553493A1 (en) * 1983-10-17 1985-04-19 Philippe Chastaing Adjustable and modular device for the supports of a tubular network
CN1190634A (en) * 1997-02-15 1998-08-19 螺纹管保护技术有限公司 Apparatus for supporting pipes
JP2002295730A (en) * 2001-03-29 2002-10-09 Mym Corp Pipe support
WO2009082087A1 (en) * 2007-12-21 2009-07-02 Ki-Yong Song Large diameter pillar construction method by layer-built and frame construction method adapting the same
CN202302309U (en) * 2011-11-04 2012-07-04 中国石油天然气集团公司 Adjustable fixed base

Also Published As

Publication number Publication date
KR101638082B1 (en) 2016-07-08
CN106838468B (en) 2018-11-27

Similar Documents

Publication Publication Date Title
CN1171022C (en) Metal-plastic staple for fixing vehicle roofs and accessories to the body of vehicle
SA515360444B1 (en) Actuated arm for use with a shaker
CN106838468A (en) Support of pipelines and its method to set up
NO20020162L (en) Process for reducing the build-up of solids in hydrocarbon streams produced from wells
WO2007137305A3 (en) A towel rail
WO2002055916A3 (en) Fitting and method for joining structural tubular elements
US20160053855A1 (en) Chain Link and Method for Forming Chain Link
CN202717178U (en) Inflatable medicinal material box for field operations
WO2008060221A3 (en) Self-supporting suspension device and method for assembling thereof
CN105794518B (en) A kind of plant walls implant system
CN207230769U (en) Refrigerating plant
JP5114584B2 (en) Guardrail foundation block installation structure
US418829A (en) Stand for bicycles
US337404A (en) Circle-iron for wagons
CN202262515U (en) Zipper head
EP2762399A2 (en) Floating platform
CN103727361A (en) High-density polyethylene enhanced support of prefabricated direct-burial thermal insulation pipe and assembling method of high-density polyethylene enhanced support
CN207355066U (en) A kind of mushroom cultivates greenhouse bracket structure
CN204653957U (en) The vertical spacing syndeton of inner sole and outer peripheral edge, the footwear large end
ATE326672T1 (en) COLUMN SYSTEM AND METHOD FOR PRODUCING IT
CN101217906A (en) Removable device for ballasting a shower curtain without perforating same
KR100890567B1 (en) Device for mounting reserve seedling rack of rice-planting machine
CN207809607U (en) A kind of motorcycle trunk easy to use
SE529565C2 (en) Locking device for fixing trays and lids
CN206456701U (en) A kind of fruit case

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant