CN106812146A - A kind of construction method of steel sheet-pile cofferdam concrete sealing bottom - Google Patents

A kind of construction method of steel sheet-pile cofferdam concrete sealing bottom Download PDF

Info

Publication number
CN106812146A
CN106812146A CN201710147175.9A CN201710147175A CN106812146A CN 106812146 A CN106812146 A CN 106812146A CN 201710147175 A CN201710147175 A CN 201710147175A CN 106812146 A CN106812146 A CN 106812146A
Authority
CN
China
Prior art keywords
concrete
construction method
back cover
substrate
absolute altitude
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201710147175.9A
Other languages
Chinese (zh)
Inventor
潘国安
王春堂
许广利
李红金
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
First Engineering Co Ltd of China Railway 23rd Bureau Group Co Ltd
Original Assignee
First Engineering Co Ltd of China Railway 23rd Bureau Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by First Engineering Co Ltd of China Railway 23rd Bureau Group Co Ltd filed Critical First Engineering Co Ltd of China Railway 23rd Bureau Group Co Ltd
Priority to CN201710147175.9A priority Critical patent/CN106812146A/en
Publication of CN106812146A publication Critical patent/CN106812146A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D19/00Keeping dry foundation sites or other areas in the ground
    • E02D19/02Restraining of open water
    • E02D19/04Restraining of open water by coffer-dams, e.g. made of sheet piles

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Bulkheads Adapted To Foundation Construction (AREA)

Abstract

The invention discloses a kind of construction method of steel sheet-pile cofferdam concrete sealing bottom, including(1)Substrate is constructed:Subregion is carried out according to steel sheet-pile cofferdam area, and each region is excavated respectively and absolute altitude detection, stopped after meeting design substrate absolute altitude, form substrate;(2)Cushion construction:Blotter is laid in the substrate;(3)Back cover is constructed:Back cover conduit is respectively arranged according to subregion, and concreting is carried out by back cover conduit, while carrying out absolute altitude detection, stopped after meeting design back cover absolute altitude;The construction method is by increasing cushion construction and adjustment pouring order of concrete, it is to avoid silt is mingled with concrete, so as to improve the intensity of bottom concrete, it is ensured that construction quality.

Description

A kind of construction method of steel sheet-pile cofferdam concrete sealing bottom
Technical field
The present invention relates to Bridge Construction technical field, more particularly to a kind of construction of steel sheet-pile cofferdam concrete sealing bottom Method.
Background technology
At present, due to fast with speed, workload is small, low cost, adapts to for the construction method of steel sheet-pile cofferdam back cover under water The strong advantage of property and be widely used in science of bridge building technology, be that the rapid construction and construction of road and bridge bring many benefits Place.However, being found in work progress, the construction method of steel sheet-pile cofferdam back cover under water there is also some problems and risk, especially It is when carrying out application and construction in sandy riverbed or river, may to cause to be easy to be mingled with silt during filling concrete, is caused The hidden danger of quality and engineering accident of bottom concrete.
Therefore, it is to avoid steel sheet-pile cofferdam sedimentation or to be mixed in concrete inside and outside and influence in back cover work progress under water Bottom concrete construction quality, is to improve science of bridge building quality problem in urgent need to solve.
The content of the invention
It is an object of the invention to overcome the above-mentioned deficiency in the presence of prior art, there is provided a kind of steel sheet-pile cofferdam coagulation The construction method at grave bottom;The construction method pours order by increasing cushion construction and changing mixed mud, makes the silt of river bed Will not be mixed in mixed mud, the quick sand in water is not deposited on concrete, so as to improve concrete strength, it is ensured that work Cheng Zhiliang.
In order to realize foregoing invention purpose, the invention provides a kind of construction method of steel sheet-pile cofferdam concrete sealing bottom, Comprise the following steps:
(1)Substrate is constructed:Subregion is carried out according to steel sheet-pile cofferdam area, and each region is excavated respectively and absolute altitude inspection Survey, stop after meeting design substrate absolute altitude, form substrate;
(2)Cushion construction:Blotter is laid in the substrate;
(3)Back cover is constructed:Back cover conduit is respectively arranged according to subregion, and concreting is carried out by back cover conduit, while entering Rower high detection, stops after meeting design back cover absolute altitude.
In a kind of construction method of above-mentioned steel sheet-pile cofferdam concrete sealing bottom, the subregion in step 1 to cofferdam is pressed per area Area is 10-30m2Divided;It is divided into smaller area and is excavated and detected absolute altitude, can be prevented effectively from due in digging process The back cover thickness that the funnel-form that is likely to result in and measurement density are not enough caused do not reach the requirement of design thickness, hidden danger of quality, The problems such as security incident.
Wherein, it is preferred that described digging mode include mud pumping mud, digging machine excavate in one or two;Excavate Mode carries out Reasonable adjustment and selection according to construction environment and requirement, can effectively improve efficiency of construction and construction quality, it is ensured that base Bottom meets design requirement.
Wherein, it is preferred that described absolute altitude detection includes the one or two more than water surface in measurement, submarine inspection;Inspection Survey mode carries out Reasonable adjustment and selection according to construction environment and requirement, can effectively improve efficiency of construction and construction quality, it is ensured that Substrate reaches design thickness requirement.
In a kind of construction method of above-mentioned steel sheet-pile cofferdam concrete sealing bottom, the blotter thickness control described in step 2 In 10-50cm, bed course can be effectively isolated the free sand of substrate, contact of the soil with concrete to system, prevent bottom concrete to be mingled with silt, So as to influence bottom concrete intensity;Preferably, the preferred slabstone of described blotter, slabstone can prevent drift sand to be deposited on rubble Surface with concrete so as to be mingled with.
In a kind of construction method of above-mentioned steel sheet-pile cofferdam concrete sealing bottom, back cover conduit laying time control guidance in step 3 The mouth of pipe is 10cm~15cm apart from substrate level.
Wherein, the pouring order of concrete is:Poured since the region at cofferdam edge, gradually to cofferdam central area Advanced, finally terminate to pour with cofferdam central area;Pouring order using this can push away the debris such as the free silt of substrate The region that edge concrete has been the beginning of coagulation is moved to, reduction silt is mingled with concrete, so that it is guaranteed that the quality of bottom concrete.
Wherein, it is preferred that in the concreting process, in addition to first pours a little, subsequent sections pour a position and need elder generation Insert the catheter into concrete, and the perfusion of concrete can be just carried out after draining conduit internal water accumulation with water pump;Can be had using the method Effect solves concrete and returns water problems, improves the intensity of bottom concrete.
Wherein, it is preferred that the method that can be simultaneously poured using multiple spot in the concreting process is poured, and can be increased Plus speed of perfusion, it is to avoid there is construction joint in concrete, improves the construction quality of bottom concrete and speeds up the work.
Wherein, it is preferred that the concrete is that the slump is the concrete of 180mm-240mm;Feud can be effectively controlled to mix The flatness on solidifying soil surface, improves back cover quality;Most preferably, the concrete is that the slump is the coagulation of 200mm-220mm Soil.
A kind of construction method of steel sheet-pile cofferdam concrete sealing bottom, first passes through laying bed course, is acted on using the cut-off of bed course, Avoid concrete from being contacted with the silt of substrate, so as to avoid silt from being mixed in concrete, improve the intensity of bottom concrete; Again by adjusting the pouring order of concrete of different zones in cofferdam, the debris such as free silt are made to elapse to edge concrete The region of initial set, so that being mingled with for silt and concrete is reduced, to ensure the quality of bottom concrete;The construction method can not only Improve the intensity of bottom concrete, it is ensured that construction quality, moreover it is possible to speed up the work, and simply, reliably, it is adaptable to various waters Road and bridge back cover construction.
Compared with prior art, beneficial effects of the present invention:
1st, construction method of the present invention pours order by increasing cushion construction and adjustment mixed mud, it is to avoid silt and concrete It is mingled with, so as to improve the intensity of bottom concrete, it is ensured that construction quality.
2nd, construction method of the present invention can using multiple spot simultaneously excavate substrate and concreting, so as to accelerate construct into Degree, reduces the construction period.
3rd, construction method of the present invention is simple, reliable, it is adaptable to the road and bridge back cover construction in various waters.
Brief description of the drawings:
Fig. 1 is the subregion of the embodiment of the present invention 1 and excavates point position division schematic diagram;
Fig. 2 is that the back cover conduit of the embodiment of the present invention 1 is laid and filling concrete point distribution schematic diagram;
Fig. 3 is the pouring order of concrete schematic diagram of the embodiment of the present invention 1;
Reference:1- steel sheet-pile cofferdams, 2- bracing members, 3- back cover conduits, 4- perfusion points, 5- cofferdam subregion.
Specific embodiment
With reference to test example and specific embodiment, the present invention is described in further detail.But this should not be understood For the scope of above-mentioned theme of the invention is only limitted to following embodiment, all technologies realized based on present invention belong to this The scope of invention.
Embodiment 1
The construction method of certain Huanghe River Highway Bridge 115# pier concrete sealing bottoms:
(1)Substrate is constructed:4.8*5.28m points is substantially pressed for 20 areas according to steel sheet-pile cofferdam area(As shown in Figure 1), excavate point Position is arranged on each regional center (RC) position, based on mud pumping mud, each region is entered supplemented by long-armed digging machine underwater excavation Row foundation ditch underwater excavation, and use more than the water surface based on measurement, the method for being aided with submarine inspection carries out absolute altitude detection, meets design Stop after substrate absolute altitude, form substrate;
(2)Cushion construction:Laying depth is about the blotter of 20cm in the substrate;
(3)Back cover is constructed:Back cover conduit is respectively arranged according to subregion(As shown in Figure 2), poured using two groups of symmetrical concrete of conduit Construction is built, is elapsed to long side direction using after short side direction casting complete, when pouring three rows, pour point moves to the 5th and discharges into Row cast(Order is poured as shown in figure 3, A, B represent two groups while carrying out pouring construction, digitized representation pours order), while entering Rower high detection, stops after meeting design back cover absolute altitude.
Embodiment 2
The construction method of certain Huanghe River Highway Bridge 109# pier concrete sealing bottoms:
(1)Substrate is constructed:4.8*5.28m points is substantially pressed for 20 areas according to steel sheet-pile cofferdam area, excavates site setting every Individual regional center (RC) position, based on mud pumping mud, foundation ditch is carried out under water supplemented by long-armed digging machine underwater excavation to each region Excavate, and use more than the water surface based on measurement, the method for being aided with submarine inspection carries out absolute altitude detection, after meeting design substrate absolute altitude Stop, forming substrate;
(2)Cushion construction:Laying depth is about the blotter of 15cm in the substrate;
(3)Back cover is constructed:Back cover conduit is respectively arranged according to subregion, using single group tremie concrete pouring construction, using short side Elapsed to long side direction after the casting complete of direction, when pouring three rows, pour point moves to the 5th and discharges into capable cast, while carrying out Absolute altitude is detected, stopped after meeting design back cover absolute altitude.
Comparative example 1
The construction method of certain Huanghe River Highway Bridge 114# pier concrete sealing bottoms:
(1)Substrate is constructed:4.8*5.28m points is substantially pressed for 20 areas according to steel sheet-pile cofferdam area, excavates site setting every Individual regional center (RC) position, based on mud pumping mud, foundation ditch is carried out under water supplemented by long-armed digging machine underwater excavation to each region Excavate, and use more than the water surface based on measurement, the method for being aided with submarine inspection carries out absolute altitude detection, after meeting design substrate absolute altitude Stop, forming substrate;
(2)Cushion construction:Laying depth is about the blotter of 20cm in the substrate;
(3)Back cover is constructed:Back cover conduit is respectively arranged according to subregion, using two groups of symmetrical concrete pouring constructions of conduit, is used Elapsed to long side direction after short side direction casting complete, directly pour completion in order successively, while absolute altitude detection is carried out, until Stop after meeting design back cover absolute altitude.
Comparative example 2
The construction method of certain Huanghe River Highway Bridge 112# pier concrete sealing bottoms:
(1)Substrate is constructed:4.8*5.28m points is substantially pressed for 20 areas according to steel sheet-pile cofferdam area, excavates site setting every Individual regional center (RC) position, based on mud pumping mud, foundation ditch is carried out under water supplemented by long-armed digging machine underwater excavation to each region Excavate, and use more than the water surface based on measurement, the method for being aided with submarine inspection carries out absolute altitude detection, after meeting design substrate absolute altitude Stop, forming substrate;
(2)Back cover is constructed:Back cover conduit is respectively arranged according to subregion, using two groups of symmetrical concrete pouring constructions of conduit, is used Elapsed to long side direction after short side direction casting complete, when pouring three rows, pour point moves to the 5th and discharges into capable cast, while Absolute altitude detection is carried out, is stopped after meeting design back cover absolute altitude.
To above-described embodiment 1(115#), embodiment 2(109#)Comparative example 1(114#)With comparative example 2(112#)Construction method The concrete sealing bottom for obtaining is detected and counted, as a result as follows:
Sequence number Design thickness (m) Actual measurement thickness (m) Back cover quality
Embodiment 1 2 2.3 100 1034 It is good
Embodiment 2 2 2.3 75 1058 It is good
Comparative example 1 2 2.3 100 1043 Typically
Comparative example 2 2 2.3 0 1138 Typically
Knowable to above-mentioned detection and statistics, underwater concrete back cover is carried out using construction method of the present invention, can significantly improved Back cover quality, reduces concrete amount.

Claims (10)

1. a kind of construction method of steel sheet-pile cofferdam concrete sealing bottom, it is characterised in that comprise the following steps:
(1)Substrate is constructed:Subregion is carried out according to steel sheet-pile cofferdam area, and each region is excavated respectively and absolute altitude inspection Survey, stop after meeting design substrate absolute altitude, form substrate;
(2)Cushion construction:Blotter is laid in the substrate;
(3)Back cover is constructed:Back cover conduit is respectively arranged according to subregion, and concreting is carried out by back cover conduit, while entering Rower high detection, stops after meeting design back cover absolute altitude;
The pouring order of concrete is:Poured since the region at cofferdam edge, gradually advanced to cofferdam central area, Finally terminate to pour with cofferdam central area.
2. construction method according to claim 1, it is characterised in that the area per area is pressed to the subregion in cofferdam in step 1 It is 10-30m2Divided.
3. construction method according to claim 1, it is characterised in that digging mode includes mud pumping mud, digs in step 1 Machine excavate in one or two.
4. construction method according to claim 1, it is characterised in that in step 1 detection mode of absolute altitude include the water surface with One or two in upper measurement, submarine inspection.
5. construction method according to claim 1, it is characterised in that the blotter thickness control described in step 2 exists 10-50cm。
6. construction method according to claim 1, it is characterised in that the blotter described in step 2 is slabstone bed course.
7. construction method according to claim 1, it is characterised in that back cover conduit laying time control conduit mouth in step 3 It is 10cm~15cm apart from substrate level.
8. construction method according to claim 1, it is characterised in that in step 3 in concreting process, pours except first Build a little outer, subsequent sections pour a position and need to first insert the catheter into concrete, and can just carry out after draining conduit internal water accumulation with water pump The perfusion of concrete.
9. construction method according to claim 1, it is characterised in that use multiple spot in step 3 in concreting process The method for pouring simultaneously is poured.
10. construction method according to claim 1, it is characterised in that concrete is that the slump is 180mm- in step 3 The concrete of 240mm.
CN201710147175.9A 2017-03-13 2017-03-13 A kind of construction method of steel sheet-pile cofferdam concrete sealing bottom Pending CN106812146A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710147175.9A CN106812146A (en) 2017-03-13 2017-03-13 A kind of construction method of steel sheet-pile cofferdam concrete sealing bottom

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710147175.9A CN106812146A (en) 2017-03-13 2017-03-13 A kind of construction method of steel sheet-pile cofferdam concrete sealing bottom

Publications (1)

Publication Number Publication Date
CN106812146A true CN106812146A (en) 2017-06-09

Family

ID=59115157

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710147175.9A Pending CN106812146A (en) 2017-03-13 2017-03-13 A kind of construction method of steel sheet-pile cofferdam concrete sealing bottom

Country Status (1)

Country Link
CN (1) CN106812146A (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110158625A (en) * 2019-06-24 2019-08-23 中铁四局集团第二工程有限公司 Steel sheet pile cofferdam layered bottom sealing structure and method under silt geological condition
CN110965556A (en) * 2019-11-20 2020-04-07 中建桥梁有限公司 Large-area underwater concrete pouring method
CN113026781A (en) * 2021-03-18 2021-06-25 中铁四局集团有限公司 Bearing platform fore shaft steel pipe pile cofferdam back cover structure and construction method thereof
CN114645549A (en) * 2020-12-21 2022-06-21 中交第二公路工程局有限公司 Construction method of steel sheet pile cofferdam

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101235648A (en) * 2008-01-04 2008-08-06 贵州省桥梁工程总公司 Underwater bridge foundation construction method
US20120224920A1 (en) * 2011-03-04 2012-09-06 Weekly Bros. Inc. Cofferdam modules
CN104294835A (en) * 2014-10-14 2015-01-21 中国水利水电第四工程局有限公司 Steel sheet pile cofferdam constructing method
CN105544569A (en) * 2015-12-11 2016-05-04 中铁大桥局集团第二工程有限公司 Block-by-block bottom sealing method for steel sheet pile cofferdam

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101235648A (en) * 2008-01-04 2008-08-06 贵州省桥梁工程总公司 Underwater bridge foundation construction method
US20120224920A1 (en) * 2011-03-04 2012-09-06 Weekly Bros. Inc. Cofferdam modules
CN104294835A (en) * 2014-10-14 2015-01-21 中国水利水电第四工程局有限公司 Steel sheet pile cofferdam constructing method
CN105544569A (en) * 2015-12-11 2016-05-04 中铁大桥局集团第二工程有限公司 Block-by-block bottom sealing method for steel sheet pile cofferdam

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110158625A (en) * 2019-06-24 2019-08-23 中铁四局集团第二工程有限公司 Steel sheet pile cofferdam layered bottom sealing structure and method under silt geological condition
CN110158625B (en) * 2019-06-24 2024-05-14 中铁四局集团有限公司 Layered bottom sealing structure and method for steel sheet pile cofferdam under geological condition of muddy silt
CN110965556A (en) * 2019-11-20 2020-04-07 中建桥梁有限公司 Large-area underwater concrete pouring method
CN114645549A (en) * 2020-12-21 2022-06-21 中交第二公路工程局有限公司 Construction method of steel sheet pile cofferdam
CN113026781A (en) * 2021-03-18 2021-06-25 中铁四局集团有限公司 Bearing platform fore shaft steel pipe pile cofferdam back cover structure and construction method thereof
CN113026781B (en) * 2021-03-18 2023-03-10 中铁四局集团有限公司 Bearing platform fore shaft steel pipe pile cofferdam back cover structure and construction method thereof

Similar Documents

Publication Publication Date Title
CN104196034B (en) A kind of utilize steel sheet pile as the foundation ditch construction method in supporting cofferdam
CN106812146A (en) A kind of construction method of steel sheet-pile cofferdam concrete sealing bottom
CN105040595A (en) Bridge main pier bearing platform foundation pit supporting structure on gentle slope riverbed bedrock and construction method thereof
CN108797618A (en) One kind being used for Urban Underground pipe gallery drainage of foundation pit structure and its construction method
CN113006108B (en) Construction method of film bag sand cofferdam
CN108457289A (en) A kind of open caisson construction method of complex condition
CN108316283A (en) The devices and methods therefor of influence of foundation excavation is controlled using hole rising pouring slurry ground-connecting-wall
CN105332382B (en) Adjacent river foundation ditch builds island cofferdam clay water stop construction method
CN107606305A (en) A kind of underground water abundance of water area gas pipeline erection method
CN113006144B (en) Permeable structure tunnel structure
CN109610429A (en) Sedimentation treatment method under a kind of Collapsible Loess District prevention gas collection station ground and terrace
CN218148458U (en) Deep water deep foundation pit drainage system of fissure development rock stratum
CN110206062A (en) The dark construction method of underground river shallow embedding is worn under a kind of Urban Underground pipe gallery
CN108316237B (en) Revetment retaining wall
CN102021912A (en) Method for constructing special shaped deepwater cofferdams on steep rocky riverbeds
CN109183964A (en) A kind of storage pond construction method
CN104846837A (en) Construction method for ultra-deep well pit in surface drainage foundation pit
CN105064373A (en) Foundation pit supporting structure of bridge main pier bearing platform on river channel steep slope bedrock and construction method thereof
CN115614542A (en) Pipe jacking construction method taking existing foundation pit in water as starting point
CN204875807U (en) Bridge main pier cushion cap foundation pit supporting structure on river channel abrupt slope basement rock
CN209837067U (en) Plugging structure of base exploration hole piping in foundation pit
CN202577341U (en) Pipe section foundation of large-scale immersed pipe tunnel
CN105220696A (en) Rotating-milling formula deep-layer stirring construction method of enclosure structure
CN101608457B (en) Method for processing wharf foundation by geotextile granular material pile
CN108611941A (en) Method for processing saturated high-fill roadbed

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20170609