CN106801365A - Existing railway line Tunnel Base sluicing anchor bolt grouting restorative procedure - Google Patents

Existing railway line Tunnel Base sluicing anchor bolt grouting restorative procedure Download PDF

Info

Publication number
CN106801365A
CN106801365A CN201710038755.4A CN201710038755A CN106801365A CN 106801365 A CN106801365 A CN 106801365A CN 201710038755 A CN201710038755 A CN 201710038755A CN 106801365 A CN106801365 A CN 106801365A
Authority
CN
China
Prior art keywords
hole
grouting
anchor
renovated
section
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201710038755.4A
Other languages
Chinese (zh)
Other versions
CN106801365B (en
Inventor
彭峰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Beijing Ruiwei Century Railway Engineering Co ltd
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201710038755.4A priority Critical patent/CN106801365B/en
Publication of CN106801365A publication Critical patent/CN106801365A/en
Application granted granted Critical
Publication of CN106801365B publication Critical patent/CN106801365B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01BPERMANENT WAY; PERMANENT-WAY TOOLS; MACHINES FOR MAKING RAILWAYS OF ALL KINDS
    • E01B2/00General structure of permanent way
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D15/00Handling building or like materials for hydraulic engineering or foundations
    • E02D15/02Handling of bulk concrete specially for foundation or hydraulic engineering purposes
    • E02D15/04Placing concrete in mould-pipes, pile tubes, bore-holes or narrow shafts
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D3/00Improving or preserving soil or rock, e.g. preserving permafrost soil
    • E02D3/02Improving by compacting
    • E02D3/10Improving by compacting by watering, draining, de-aerating or blasting, e.g. by installing sand or wick drains
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D3/00Improving or preserving soil or rock, e.g. preserving permafrost soil
    • E02D3/12Consolidating by placing solidifying or pore-filling substances in the soil
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/74Means for anchoring structural elements or bulkheads
    • E02D5/80Ground anchors
    • E02D5/808Ground anchors anchored by using exclusively a bonding material
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01BPERMANENT WAY; PERMANENT-WAY TOOLS; MACHINES FOR MAKING RAILWAYS OF ALL KINDS
    • E01B2204/00Characteristics of the track and its foundations
    • E01B2204/08Deep or vertical foundation
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2250/00Production methods
    • E02D2250/003Injection of material
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2300/00Materials
    • E02D2300/0004Synthetics
    • E02D2300/0018Cement used as binder
    • E02D2300/0023Slurry

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Engineering & Computer Science (AREA)
  • Civil Engineering (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • Mining & Mineral Resources (AREA)
  • Agronomy & Crop Science (AREA)
  • Environmental & Geological Engineering (AREA)
  • Soil Sciences (AREA)
  • Architecture (AREA)
  • Lining And Supports For Tunnels (AREA)

Abstract

The present invention discloses a kind of existing railway line Tunnel Base sluicing anchor bolt grouting restorative procedure, including:Along longitudinally disposed one first side formed including bottom surface and by plane where two side walls and the section to be renovated of second side in tunnel;In first side and second side, equi-spaced apart applies some spilled water holes at two lining surfaces;In bottom surface, some bonding holes and some anchor holes are applied along the longitudinal direction interval of section to be renovated, often row bonds hole includes at least four bonding holes arranged along the horizontal direction of section to be renovated, and often arranging anchor hole includes being respectively arranged in two the four of track both sides anchor holes along the horizontal direction of section to be renovated;Successively to each bonding hole in slip casting is carried out with 0.01~0.03 MPa of grouting pressure;Successively to anchor pole and slip casting core pipe is inserted in each anchor hole to bottom hole, after carrying out injection hole sealing with 0.01~0.03 MPa of grouting pressure, backing plate and nut are installed to be anchored on the top of anchor pole.

Description

Existing railway line Tunnel Base sluicing anchor bolt grouting restorative procedure
Technical field
The present invention relates to a kind of restorative procedure, more particularly to a kind of restorative procedure for Existing Railway Line substrate.
Background technology
During the freight volume and the speed of service of rail track are improved constantly, the road bed board positioned at Tunnel Base is long-term In the presence of the factors such as the dynamic load repeatedly by the temperature difference, underground water and train, road bed board and some rich waters of tunnel bottom are soft Easily there are the diseases such as road bed board cracking, the sedimentation of tunnel bottom in weak-strong test, in addition, when there is Rainfall Disaster, often there is tunnel Level of ground water in road rises, and the hydraulic pressure of increase causes the situation of road bed board lifting, had a strong impact on the operation security of train.Cause This, in this case it is necessary to be repaired to tunnel both wired substrate.
Currently for tunnel both wired substrate reclamation activities mainly have stifled thin underground water, grouting and reinforcing base plate fracture area, The methods such as disease railway roadbed are overhauled, the method for the above treatment disease is served preferably in the different phase that railway roadbed disease develops Effect, but these methods there is also certain deficiency, such as overhaul disease railway roadbed easily increase engineering input, influence existing Railway operation;Single grouting and reinforcing can play a part of preferably to improve base plate, but tend not to control the dynamic of track plates completely State is settled, and the opening and closing gap between road bed board and base plate is difficult control.
A kind of subgrade of metro reinforcing construction process is disclosed such as Chinese patent application 201210100652.3, it include with Lower step:The first step:Drilling:Using small-sized rig, drill through the hole of Φ 20-60mm on railway roadbed, hole depth enter two linings or Just prop up;Drilling can in two rows arrange that pitch-row is 1.0m-3.4m, and array pitch is 0.3m-3.0m;Second step:Under enter anchor pole:According to existing Field actual borehole depth, grouting joint and hollow rock-bolt length are connected with coil of strip ruler measurement, and rock-bolt length should be than actual hole depth Many 5cm, can be cut with angle grinder, then will be connected with grouting joint and hollow anchor pole is lowered into hole;3rd step:Machinery Break adrift:The pretension body of rod, makes anchor head top be close to locking with bottom hole portion, then installs stop grouting plug, backing plate, nut, using normal after connection Rule tensioning apparatus, implements prestressed stretch-draw, break adrift;4th step:Grouting:Grouting material is prepared, and is poured into slip casting machine;Open Dynamic slip casting machine, is in the milk, after 0.2~1.5MPa pressure is reached, be in the milk into slurry amount it is little when, grouting can be terminated, remove note Slurry joint, cleaning equipment.But, the invention still has the following disadvantages or not enough:(1), tunnel bottom underground water is drawn without open Technique;(2), need to use and be connected with grouting joint and hollow anchor pole, improve construction cost.
And for example Chinese patent application 201310531472.5 discloses a kind of railway roadbed and tunnel bottom Disease Treatment construction method And anchor, drainage channel is built using fast gel material in its gutter first in the middle of solid concrete roabed and ditch, by damaged water Flowing water in ditch passes through channel drainage, it is ensured that in anhydrous in disease region;Then, road bed board and base plate opening and closing region every 5~10cm inserts stainless steel plate, and steel plate length is divided into 0.6m~1.2m, width is 0.1m, and thickness has 6mm~12mm;Then, Bore bolthole in gutter between road bed board and both sides ditch respectively, and the road bed board between two boltholes interposition Put and be drilled with again a bolthole so that three boltholes on the same line, anchor pole are inserted perpendicular to road bed board axial direction Enter bolthole, three anchor poles are fixed together with road bed board by anchor, two anchor poles in the gutter of both sides are passed through Anchor is fixed together, and the anchor pole in road bed board centre position is fixed together along road bed board axial direction;Finally, on side Ditch internal drilling slip casting, using the broken region of the anti-current stall material reinforced base plate of solidifying high strength grouting, grouting pressure is no more than 0.2Mpa, blocks base plate and rupture section ditch water outlet, while reinforcing tunnel base concrete and country rock by slip casting.But, the invention Still have the following disadvantages or not enough:(1), the flowing water in damaged ditch is only passed through channel drainage by it so that in disease region In anhydrous, without by the potential safety hazard for carrying out drainage and step-down, still there is road bed board lifting inside tunnel surrounding;(2)、 Steel plate length between insertion road bed board and base plate opening and closing region is difficult to the strong bonded between road bed board and base plate;(3)、 Bored grouting is carried out at position in gutter, slurries are difficult to tamp in the gap between tunnel floor and country rock, easily formed Subsurface flow passage;(4), first carry out single anchoring carries out the operation that slip casting is tamped again, easily causes tunnel bottom to deform.
Therefore it provides a kind of method that can fully repair tunnel both wired substrate turns into urgent problem in the industry.
The content of the invention
It is an object of the invention to provide a kind of short construction period and the method that can effectively repair tunnel both wired substrate, its By the way of the space between spilled water hole draining pressure release, slip casting filling base plate and country rock and anchor bolt grouting reinforce road bed board, Deformation to tunnel both wired substrate is repaired, it is ensured that the safety of driving.
To achieve these goals, the invention provides a kind of existing railway line Tunnel Base sluicing anchor bolt grouting reparation side Method, it includes:(1) a section to be renovated, is set to along every 10~30 meters of the longitudinal direction in tunnel, each section to be renovated is included by treating Renovate top surface, the road bed board place bottom surface that is formed of plane by section renovate that plane where the vault of section formed and The first side and second side formed by plane where the side wall of section to be renovated two;(2), in the of each section to be renovated One side and second side, equi-spaced apart applies some spilled water holes at two lining surfaces;(3), in the bottom of each section to be renovated Face, applies at least four rows and bonds hole along the longitudinal direction interval of section to be renovated, and often row bonds hole and includes along section to be renovated At least four bonding holes of horizontal direction arrangement, each depth-set for bonding hole is 6~7 meters;(4), in each area to be renovated Section bottom surface, along section renovate longitudinal direction interval apply at least three row's anchor holes, often arrange anchor hole include edge wait to renovate The horizontal direction of section is respectively arranged in two the four of track both sides anchor holes, and the depth-set of each anchor hole is 6~7 Rice;(5) after, bonding the water in hole to insertion water-bag type stop grouting plug discharge in each bonding hole successively, water-bag type stop grouting plug is carried To 1.5~2 meters of depth, water filling pressurising carries out sealing of hole, and slip casting is carried out with 0.01~0.03 MPa of grouting pressure;And (6), Successively to anchor pole and slip casting core pipe is inserted in each anchor hole to bottom hole, slip casting is carried out with 0.01~0.03 MPa of grouting pressure After sealing of hole, backing plate and nut are installed to be anchored on the top of anchor pole.
Selectively, in step (5) and step (6), when grouting pressure is 0~0.01 MPa, injection speed is 15 ~20 liters/min;When grouting pressure is 0.01~0.02 MPa, injection speed is 10~15 liters/min;When grouting pressure is 0.02 At~0.03 MPa, injection speed is 5~10 liters/min;When grouting pressure is 0.03 MPa, injection speed is 0 liter/min.
Selectively, in step (5) and step (6), the slurry material of slip casting is carried out for sulphate aluminium cement single slurry, The ratio of mud of sulphate aluminium cement single slurry is (0.6~0.8):1.
Selectively, in step (5) and step (6), grouting process is set as jumping hole slip casting and jumps pitch-row from gradually increasing Greatly.
Preferably, in step (5), each grouting amount bonded in hole is
Q=π × r2 × H × n × α × (1+ β),
Wherein, Q is the grouting amount (cubic meter) in single bonding hole, and r is grout spreading range (rice), and H adds for loose media Gu height (rice), n is formation void rate, α is formation void pack completeness, and β is slurries loss late.
Selectively, some spilled water holes can include at least ten spilled water holes.The method also includes that monitoring at least ten is let out The effluent quality in water hole, when the effluent quality of at least ten spilled water holes occurs turbid phenomenon, stops being in operation in step (5) In bonding hole grouting operation.
Selectively, the distance between anchor hole and adjacent orbit are set as 0.3~0.5 meter.
Selectively, bond hole and the diameter of anchor hole is set as 75~85 millimeters.
Selectively, the diameter of water-bag type stop grouting plug is set as 65~75 millimeters.
Selectively, the diameter of anchor pole is set as 30~35 millimeters, and the diameter of slip casting core pipe is set as 15~25 millimeters.
Preferably, anchor pole is made up of PSB930 finish rolling deformed bars.
Selectively, also include in step (5):Track displacement is monitored to ensure track during slip casting Lifting elevation is less than 8 millimeters.
The beneficial effects of the invention are as follows:(1) spilled water hole, is applied first, so as to ensure that being smoothed out for draining pressure release, is Follow-up mortar depositing construction provides necessary precondition;(2), carry out slip casting to bonding hole, can effectively by road bed board and country rock it Between space or empty quarrel filling consolidated compacting, do not re-form water stream channel, it is to avoid road bed board lifting again;(3), anchor hole is entered Row anchor bolt grouting, further can couple as an entirety road bed board with country rock, suppress the harm that road bed board deforms; (4), using ultralow pressure micrometeor slip casting, effectively reduce slip casting process influences for the elevation of road bed board, it is ensured that the peace of driving Quan Xing;(5), the plane where road bed board carries out slip casting and anchoring, more efficiently ensures the slurries between road bed board and country rock Filling effect and anchoring effect.
Brief description of the drawings
Fig. 1 is the flow chart of existing railway line Tunnel Base sluicing anchor bolt grouting restorative procedure of the invention.
Fig. 2 is the distribution schematic diagram of bonding hole of the invention and anchor hole.
Specific embodiment
Existing railway line Tunnel Base sluicing anchor bolt grouting restorative procedure of the invention is specifically described referring next to accompanying drawing (XMZ methods).
First, Fig. 1-2 is refer to, in step sl, every 20 meters are set to a section Q to be renovated along the longitudinal direction in tunnel, often Individual section Q to be renovated include by section renovate vault place plane formed top surface (not shown), by section to be renovated Bottom surface (non-label) that plane where road bed board is formed and formed by section renovate two side wall W1 and W2 place plane First side 100 and second side 200.
Then, in step s 2, in the first side 100 and second side 200 of each section to be renovated, surface is served as a contrast two Place's equi-spaced apart applies ten spilled water hole A, and the setting of spilled water hole A can not only ensure that being smoothed out for draining pressure release, after being Continuous mortar depositing construction provides necessary precondition, when the effluent quality generation for during slip casting, finding spilled water hole A is muddy existing As when, then stop grouting operation immediately.
Then, in step S3,25 a diameter of 80 millimeters viscous is applied using down-the-hole drill in the bottom surface of section Q to be renovated Knot hole B, reinforcing bar is cut when reinforcing bar is run into using geological drilling rig.25 longitudinal directions for being placed along section Q to be renovated of bonding hole B Direction interval applies five rows and bonds hole, and often row bonds hole includes the five bonding holes arranged along the horizontal direction of section to be renovated, Each depth for bonding hole B is 6.5 meters.
In step s 4,16 equally a diameter of 80 millimeters are applied using down-the-hole drill in the bottom surface of section Q to be renovated Anchor hole C, reinforcing bar is cut when reinforcing bar is run into using geological drilling rig.16 anchor hole C's is placed along the vertical of section Q to be renovated Four row's anchor holes are applied to direction interval, often arranging anchor hole includes four anchor holes, respectively positioned at track T1 and a left side of track T2 At 0.4 meter of right both sides, the depth of each anchor hole C is similarly 6.5 meters.
Applied after finishing hole B and anchor hole C is bonded, in step s 5, successively to insertion diameter 70 in each bonding hole B The water-bag type stop grouting plug of millimeter, after bonding the water discharge in the B of hole, then water-bag type stop grouting plug is carried to 1.5~2 meters of depth, Water filling pressurising carries out sealing of hole, lifting situation occurs in order to prevent road bed board during slip casting, with 0.01 MPa, 0.02 MPa and 0.03 million The different small grouting pressure of handkerchief three carries out slip casting.Thus, can effectively by tunnel by carrying out slip casting in hole is bonded Space or empty quarrel filling consolidated compacting between road base plate and country rock, do not re-form water stream channel, it is to avoid the lifting again of tunnel bottom.
Finally, in step s 6, make to 32 millimeters of PSB930 finish rolling deformed bars of insertion diameter in each anchor hole C successively It is anchor pole, the slip casting core pipe of 20 millimeters of diameter is inserted into afterwards to bottom hole, equally with 0.01 MPa, 0.02 MPa and 0.03 MPa After three different small grouting pressures carry out injection hole sealing, backing plate and supporting double nut are installed on the top of anchor pole, meet Anchor is reinforced after intensity tight, if anchor pole should carry out cutting reparation when stretching out long, headroom of driving a vehicle must not be influenceed.Thus, by anchoring The operation of slip casting couples as an entirety tunnel floor with country rock, suppresses the deformation of tunnel bottom.
As a kind of alternative implementation method, in step S5 and step S6, when grouting pressure is 0~0.01 MPa When, injection speed is controlled to 15~20 liters/min;When grouting pressure rises to 0.01~0.02 MPa, injection speed is controlled to 10~15 liters/min;When grouting pressure rises to 0.02~0.03 MPa, injection speed is controlled to 5~10 liters/min;And when note Slurry pressure then stops slip casting when rising to 0.03 MPa, grout leaking occurs overflows the phenomenon of slurry so as to efficiently avoid, while also keeping away The potential safety hazard that road bed board occurs uplift deformation is exempted from.
In the non-limiting embodiment, it is irrigated using sulphate aluminium cement single slurry in slip casting, sulphur aluminic acid The ratio of mud of salt cement single slurry is 0.6~0.8:1, so as to the diffusion of slurries is controlled in limited scope.
Used as another alternative implementation method, it is Q=π × r2 × H × n × α × (1+ to bond the grouting amount in hole β), wherein, Q is the grouting amount (cubic meter) in single bonding hole, and r is grout spreading range (rice), and H is that loose media reinforces height (rice), n is formation void rate, and α is formation void pack completeness, and β is slurries loss late, according to the property of tunnel surrounding, slurries Species, may be selected different coefficients, in the present invention, r values 1.5, H values 0.2, α values 60~80%, β values 10%.
In the non-limiting embodiment, there is lifting to prevent road bed board, in whole slip casting and anchoring procedure, Track displacement is monitored, it is ensured that the lifting elevation of track is less than 8 millimeters, prevents security incident.
Application of the construction method of the invention in engineering is introduced below in conjunction with example.
Required according to Specific construction, can selected using down-the-hole drill as main construction equipment, it is both wired in order to adapt to Reparation, there is provided 15 down-the-hole drills, for drilling provides place facilitate.
Surveying setting-out.Survey crew is demarcated at abutment wall and road bed board using the hole position that fine measuring instrument will be designed.
Point position repetition measurement, rig is in place.The point position that survey crew will demarcate carries out repetition measurement, and rig is marched into the arena after debugging.
Apply spilled water hole.Performed at the side wall of tunnel two, per plate two, lining performs six holes.
Apply bonding hole and anchor hole.80 millimeters of diameter, the bonding hole of 6.5 meters of depth and anchoring are drilled with using down-the-hole drill Hole.Reinforcing bar is cut using geological drilling rig when reinforcing bar is run into.
In this way, hole position is constructed one by one, circulation is completed until all design hole position constructions.
Perfusion bonds hole.First insertion diameter 70mm water-bag types stop grouting plug discharges water in hole, then filler block is carried to depth 1.5~2m, water filling pressurising carries out sealing of hole, starts to irrigate sulphate aluminium cement single slurry with 0.01 MPa of pressure, until pressure 0.03 MPa is reached, then stops slip casting.
To 32 millimeters of PSB930 finish rolling deformed bars of diameter are inserted in anchor hole, the slip casting of 20 millimeters of diameter is inserted into afterwards Core pipe starts to irrigate sulphate aluminium cement single slurry to bottom hole with 0.01 MPa of pressure, until pressure reaches 0.03 MPa, stops Only after slip casting, backing plate and supporting double nut are installed on the top of anchor pole, anchor are reinforced tightly after meeting intensity, if anchor pole stretches out long Cutting reparation should be carried out, to avoid influence driving headroom.
During slip casting is carried out, using infrared ray gradienter, Sopwith staff, the equipment such as mobile monitor foot stool is entered to slip casting region Row whole process supervision, provides Monitoring Data in time, instructs mortar depositing construction.
Railway monitoring:Before mortar depositing construction, elevation identical level at is set every 5 meters at the side wall of slip casting region two Datum mark.A monitoring point is set every 5 meters in both sides track midline, each monitoring is measured using infrared ray gradienter and Sopwith staff Put the discrepancy in elevation and accurate recording with horizontal reference point.
Grouting monitoring:During mortar depositing construction, before each bonding hole starts slip casting, mobile monitor foot stool is placed on note At slurry and mobile monitor foot stool centre distance bond hole be not more than 50 centimetres.Infrared ray gradienter is placed at abutment wall, will Scale 30 (graduated scale is put upside down) place of mobile monitor foot stool is directed at the infrared ray of infrared ray gradienter, takes overall process uninterruptedly to supervise The mode of control is monitored.
Although having described the preferred embodiment of the present invention in detail herein, it is to be understood that the invention is not limited in this In describe in detail and the concrete structure that shows and step, without departing from the spirit and scope of the present invention can be by this area Technical staff realize other modifications and variant.

Claims (10)

1. a kind of existing railway line Tunnel Base sluicing anchor bolt grouting restorative procedure, it is characterised in that including:
(1) a section to be renovated is set to along every 10~30 meters of the longitudinal direction in tunnel, each described section to be renovated is included by described The bottom that the top surface of plane formation, the plane where the road bed board of the section to be renovated where the vault of section to be renovated are formed Face and the first side and second side that are formed by plane where the side wall of section to be renovated two;
(2) in the first side and second side of each section to be renovated, equi-spaced apart applies some at two lining surfaces Spilled water hole;
(3) in the bottom surface of each section to be renovated, at least four rows are applied along the longitudinal direction interval of the section to be renovated Hole is bonded, often row bonds hole includes at least four bonding holes arranged along the horizontal direction of the section to be renovated, each bonding The depth-set in hole is 6~7 meters;
(4) in the bottom surface of each section to be renovated, at least three rows are applied along the longitudinal direction interval of the section to be renovated Anchor hole, often arranging anchor hole includes being respectively arranged in two the four of track both sides anchors along the horizontal direction of the section to be renovated Solid hole, the depth-set of each anchor hole is 6~7 meters;
(5) after discharging the water in the bonding hole to insertion water-bag type stop grouting plug in each bonding hole successively, by the water-bag type Stop grouting plug is carried to 1.5~2 meters of depth, and water filling pressurising carries out sealing of hole, and slip casting is carried out with 0.01~0.03 MPa of grouting pressure; And
(6) successively to anchor pole and slip casting core pipe is inserted in each anchor hole to bottom hole, with 0.01~0.03 MPa of grouting pressure After carrying out injection hole sealing, backing plate and nut are installed to be anchored on the top of the anchor pole.
2. existing railway line Tunnel Base sluicing anchor bolt grouting restorative procedure as claimed in claim 1, it is characterised in that in step Suddenly in (5) and step (6), when grouting pressure is 0~0.01 MPa, injection speed is 15~20 liters/min;When grouting pressure is At 0.01~0.02 MPa, injection speed is 10~15 liters/min;When grouting pressure is 0.02~0.03 MPa, injection speed It is 5~10 liters/min;When grouting pressure is 0.03 MPa, injection speed is 0 liter/min.
3. existing railway line Tunnel Base sluicing anchor bolt grouting restorative procedure as claimed in claim 2, it is characterised in that in step Suddenly in (5) and step (6), the slurry material of slip casting is carried out for sulphate aluminium cement single slurry, the sulphate aluminium cement list liquid The ratio of mud of slurry is 0.6~0.8:1.
4. existing railway line Tunnel Base sluicing anchor bolt grouting restorative procedure as claimed in claim 3, it is characterised in that in step Suddenly in (5) and step (6), grouting process is set as jumping hole slip casting and jumps pitch-row from gradually increasing.
5. existing railway line Tunnel Base sluicing anchor bolt grouting restorative procedure as claimed in claim 3, it is characterised in that also wrap The effluent quality for monitoring some spilled water holes is included, when the effluent quality of some spilled water holes occurs turbid phenomenon, is stopped The grouting operation in the bonding hole in step (5) in operation.
6. existing railway line Tunnel Base sluicing anchor bolt grouting restorative procedure as claimed in claim 3, it is characterised in that described The distance between anchor hole and adjacent orbit are set as 0.3~0.5 meter.
7. existing railway line Tunnel Base sluicing anchor bolt grouting restorative procedure as claimed in claim 3, it is characterised in that described The diameter for bonding hole and the anchor hole is set as 75~85 millimeters.
8. existing railway line Tunnel Base sluicing anchor bolt grouting restorative procedure as claimed in claim 7, it is characterised in that described The diameter of water-bag type stop grouting plug is set as 65~75 millimeters.
9. existing railway line Tunnel Base sluicing anchor bolt grouting restorative procedure as claimed in claim 7, it is characterised in that described The diameter of anchor pole is set as 30~35 millimeters, and the diameter of the slip casting core pipe is set as 15~25 millimeters.
10. the existing railway line Tunnel Base sluicing anchor bolt grouting restorative procedure as described in claim 1~9 is any, its feature It is also to include in step (5):Track displacement is monitored to ensure the lifting elevation of the track during slip casting Less than 8 millimeters.
CN201710038755.4A 2017-01-18 2017-01-18 Draining anchoring grouting repair method for existing railway line tunnel base Active CN106801365B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710038755.4A CN106801365B (en) 2017-01-18 2017-01-18 Draining anchoring grouting repair method for existing railway line tunnel base

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710038755.4A CN106801365B (en) 2017-01-18 2017-01-18 Draining anchoring grouting repair method for existing railway line tunnel base

Publications (2)

Publication Number Publication Date
CN106801365A true CN106801365A (en) 2017-06-06
CN106801365B CN106801365B (en) 2021-07-30

Family

ID=58986817

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710038755.4A Active CN106801365B (en) 2017-01-18 2017-01-18 Draining anchoring grouting repair method for existing railway line tunnel base

Country Status (1)

Country Link
CN (1) CN106801365B (en)

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102787846A (en) * 2012-07-31 2012-11-21 中铁隧道集团有限公司 Upper-blocking and lower-draining construction method for undersea tunnel fault fracture zone
KR101254975B1 (en) * 2011-02-16 2013-04-17 재단법인 포항산업과학연구원 Railroad for tube transporting system
CN203114299U (en) * 2013-01-31 2013-08-07 中铁十四局集团有限公司 Long-distance horizontal reinforced construction structure capable of spraying vortically and plugging water
CN103321230A (en) * 2013-07-12 2013-09-25 上海隧道工程股份有限公司 Excavation method for deep and big foundation pit in long-distance crossing field for shallow-buried subway
CN105041325A (en) * 2015-07-13 2015-11-11 长沙理工大学 Construction method of high-tension water-rich extra-large-section weak breccia tunnel
CN105840207A (en) * 2016-03-24 2016-08-10 杭州江润科技有限公司 Cross shallow buried bias pressure loose accumulation body large-span tunnel comprehensive entrance structure construction method
CN106050266A (en) * 2016-07-22 2016-10-26 中铁建大桥工程局集团第五工程有限公司 Construction method for undermining connected channel between shield sections in water-rich sand cobble stratum tunnel

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101254975B1 (en) * 2011-02-16 2013-04-17 재단법인 포항산업과학연구원 Railroad for tube transporting system
CN102787846A (en) * 2012-07-31 2012-11-21 中铁隧道集团有限公司 Upper-blocking and lower-draining construction method for undersea tunnel fault fracture zone
CN203114299U (en) * 2013-01-31 2013-08-07 中铁十四局集团有限公司 Long-distance horizontal reinforced construction structure capable of spraying vortically and plugging water
CN103321230A (en) * 2013-07-12 2013-09-25 上海隧道工程股份有限公司 Excavation method for deep and big foundation pit in long-distance crossing field for shallow-buried subway
CN105041325A (en) * 2015-07-13 2015-11-11 长沙理工大学 Construction method of high-tension water-rich extra-large-section weak breccia tunnel
CN105840207A (en) * 2016-03-24 2016-08-10 杭州江润科技有限公司 Cross shallow buried bias pressure loose accumulation body large-span tunnel comprehensive entrance structure construction method
CN106050266A (en) * 2016-07-22 2016-10-26 中铁建大桥工程局集团第五工程有限公司 Construction method for undermining connected channel between shield sections in water-rich sand cobble stratum tunnel

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
张民庆等: ""铁路隧道不良地质突水突泥治理技术与工程应用"", 《铁道工程学报》 *

Also Published As

Publication number Publication date
CN106801365B (en) 2021-07-30

Similar Documents

Publication Publication Date Title
CN106437726B (en) Shallow-depth-excavation tunnel crosses ground fissure crushed zone construction method
CN105696427B (en) The construction method and its road structure of a kind of consolidation process newly built railway karst foundation
CN104746517B (en) A kind of suspension roof support system of total length below artesian head
CN106968690A (en) The method for tunnel construction for soil property of caving in
CN110230499A (en) Rich water soft clay area shield closely wears operation tunnel and actively protects structure and construction method
CN107059496B (en) A kind of track road-bridge transition section slip casting correction lifting method
CN107130475A (en) Ballastless track roadbed Deformation control is worn under a kind of aqueduct with repairing structure and method
CN105350988B (en) Tunnel Base reinforcement means
CN111119128B (en) Danger-removing, reinforcing and seepage-proofing method for natural rock-fill dam of barrier lake
CN114233385B (en) Treatment method for mud-bursting water of inclined shaft
CN110439590A (en) Method for tunnel construction
CN111350104A (en) Construction method of high-speed railway excavation roadbed in deep artificial spoil area
CN107191206B (en) A kind of six step construction method of Shallow-buried Large-span Tunnel Unit two
CN109281239B (en) Rib type abutment taper slope cutting method in road operation state
CN108708290B (en) Box bridge frame hollow structure of small-radius railway curve unit and cast-in-place construction method
CA3039971A1 (en) System and method for subgrade stabilization of railroad bed
CN103615012B (en) Steel construction self-drilling hollow anchor bars reinforces the most wired gear safeguard structure
CN108005681B (en) Compaction grouting method
CN111075455A (en) Freezing method channel construction process
CN106801365A (en) Existing railway line Tunnel Base sluicing anchor bolt grouting restorative procedure
CN110565452A (en) Railway roadbed body steel flower tube grouting reinforcement method and railway roadbed
CN214992966U (en) Concrete road surface fracture subsidence section punishment structure
CN108505547A (en) A kind of structural system and method for the antiseismic liquefaction uplifting in subway station
CN211689677U (en) Railway roadbed
CN208981352U (en) A kind of fence net composite structure with prevention and treatment and early warning karst collapse

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
TA01 Transfer of patent application right
TA01 Transfer of patent application right

Effective date of registration: 20210708

Address after: 101499 room 409, 4th floor, South, 113 Kaifang Road, Huairou District, Beijing

Applicant after: BEIJING RUIWEI CENTURY RAILWAY ENGINEERING Co.,Ltd.

Address before: 100086 room 103, building 9, West District, 56 Zhichun Road, Haidian District, Beijing

Applicant before: Peng Feng

GR01 Patent grant