CN106764052A - A kind of water applies method pipeline laying facility - Google Patents

A kind of water applies method pipeline laying facility Download PDF

Info

Publication number
CN106764052A
CN106764052A CN201611226220.1A CN201611226220A CN106764052A CN 106764052 A CN106764052 A CN 106764052A CN 201611226220 A CN201611226220 A CN 201611226220A CN 106764052 A CN106764052 A CN 106764052A
Authority
CN
China
Prior art keywords
pipeline
sleeve pipe
waterwall
laying
pipeline laying
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201611226220.1A
Other languages
Chinese (zh)
Inventor
牛存良
翟佳
李明
许博
刘永
杨磊
冯建勇
苏斌
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Co Ltd Of Bjrb Ruitong Maintenance Center
BEIJING MUNICIPAL BRIDGE MANAGEMENT MAINTENANCE GROUP Co Ltd
Original Assignee
Co Ltd Of Bjrb Ruitong Maintenance Center
BEIJING MUNICIPAL BRIDGE MANAGEMENT MAINTENANCE GROUP Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Co Ltd Of Bjrb Ruitong Maintenance Center, BEIJING MUNICIPAL BRIDGE MANAGEMENT MAINTENANCE GROUP Co Ltd filed Critical Co Ltd Of Bjrb Ruitong Maintenance Center
Priority to CN201611226220.1A priority Critical patent/CN106764052A/en
Publication of CN106764052A publication Critical patent/CN106764052A/en
Pending legal-status Critical Current

Links

Classifications

    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F16ENGINEERING ELEMENTS AND UNITS; GENERAL MEASURES FOR PRODUCING AND MAINTAINING EFFECTIVE FUNCTIONING OF MACHINES OR INSTALLATIONS; THERMAL INSULATION IN GENERAL
    • F16LPIPES; JOINTS OR FITTINGS FOR PIPES; SUPPORTS FOR PIPES, CABLES OR PROTECTIVE TUBING; MEANS FOR THERMAL INSULATION IN GENERAL
    • F16L1/00Laying or reclaiming pipes; Repairing or joining pipes on or under water
    • F16L1/024Laying or reclaiming pipes on land, e.g. above the ground
    • F16L1/028Laying or reclaiming pipes on land, e.g. above the ground in the ground
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F16ENGINEERING ELEMENTS AND UNITS; GENERAL MEASURES FOR PRODUCING AND MAINTAINING EFFECTIVE FUNCTIONING OF MACHINES OR INSTALLATIONS; THERMAL INSULATION IN GENERAL
    • F16LPIPES; JOINTS OR FITTINGS FOR PIPES; SUPPORTS FOR PIPES, CABLES OR PROTECTIVE TUBING; MEANS FOR THERMAL INSULATION IN GENERAL
    • F16L5/00Devices for use where pipes, cables or protective tubing pass through walls or partitions
    • F16L5/02Sealing

Landscapes

  • Engineering & Computer Science (AREA)
  • General Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • Pipeline Systems (AREA)

Abstract

The present invention relates to pipeline laying technical field, there is provided a kind of water applies method pipeline laying facility.The water applies method pipeline laying facility, including installed in the first waterwall of the entrance point port of described sleeve pipe;The poling hole for penetrating pipeline is provided with first waterwall.When the water being applied into method pipeline laying facility being used for pipeline laying, after the poling hole on the first waterwall is penetrated wait the pipe end for laying, can be to injecting liquid in liquid containing chamber.Now, the pipeline entered into sleeve pipe is subject to buoyancy straight up, so that the active force needed during pipeline laying reduces, to reduce requirement and the complex operation degree to laying apparatus, the security and laying speed of construction are improved, and ensures pipeline laying in place.Further, since support member drives pipeline sleeve pipe again after installing in advance, therefore can prevent support member from damaging deformation;Meanwhile, the frictional resistance that pipeline is subject under buoyancy reduces, such that it is able to the outer anti-corrosion of effective protective conduit.

Description

A kind of water applies method pipeline laying facility
Technical field
The present invention relates to pipeline laying technical field, there is provided a kind of water applies method pipeline laying facility.
Background technology
The municipal supporting pipelines engineering-regeneration Hydraulic Projects in Green Lake East Road, Haidian District (the close flume north side road-Green Lake South Road in capital) Construction in, recycled water Pipeline Crossing Program Beiqing Road, Planning Landscape river course and planning Da Zhai canal section.Wherein, correspondence Beiqing Road, planning Regeneration waterpipe 133.5m, 97.5m and 65.5m long respectively of Landscape River and planning Da Zhai canal section.Because job site does not have Propose first to be installed in place sleeve pipe using pipe jacking method for bright fluting condition, therefore prior art, laid in sleeve pipe afterwards Regeneration waterpipe.
Fig. 1 is referred to, sleeve pipe uses the reinforced concrete sleeve of a diameter of 3000mm.Lay a diameter of in the sleeve pipe domestic demand The regeneration waterpipe of the twice steel of 1200mm and a diameter of 400mm.And it will be noted from fig. 1 that it is cast with sleeve pipe The mounting platform of track, track is embedded on the mounting platform, and is provided with for pipeline to be fixed in sleeve pipe in orbit Steel bracket.
Wherein, the laid processes of regeneration waterpipe are comprised the following steps:C20 concretings and track are completed in sleeve pipe It is pre-buried --- steel bracket --- regeneration waterpipe is placed on the platform of steel bracket sustained height --- to be installed in orbit to adopt Laid waterpipe is regenerated to receiving terminal from the entrance point of sleeve pipe with top pick jacking construction so that pipeline is seated on steel bracket.
By taking the regeneration waterpipe of a diameter of 1200mm as an example, its factory calibration length 12m, together with internal and external anti-corrosive, it is single from Weight 8T.Because its gravity is larger, therefore lay for convenience in the prior art, brushed using between steel bracket, pre-buried track The method of butter reduces frictional resistance, but it is only capable of alleviating the partial pressure for laying, still exist in specific laying work with Lower problem:
Firstth, the top power needed when self weight of pipeline is larger is larger, so as to require laying apparatus higher, cumbersome and peace Full property is poor;
Secondth, laying speed is slow;
3rd, the breakage of the outer anticorrosion structure of pipeline is easily caused, and causes the steel bracket deformation for supporting pipeline;
4th, the increase with lay length, frictional resistance constantly increases, or even top power deficiency occurs, lays not in place Situation.
Also, it is not only regeneration waterpipe, above mentioned problem is equally existed in the laid processes of other pipelines.
The content of the invention
(1) technical problem to be solved
The purpose of the present invention is:A kind of water is provided and applies method pipeline laying facility, solve present in prior art to laying Equipment requirement is higher, cumbersome, security is poor, laying speed is slow, the problems such as damage structure and lay not in place.
(2) technical scheme
In order to realize the purpose, method pipeline laying facility is applied the invention provides a kind of water, in working pit, including Sleeve pipe and it is fixed in described sleeve pipe and is used for the supporting member of fixed -piping, also including installed in the entrance point port of described sleeve pipe The first waterwall, and form liquid containing chamber between first waterwall and described sleeve pipe;First waterwall On be provided with poling hole for penetrating pipeline.
Preferably, the receiving terminal port of described sleeve pipe is provided with the second waterwall so that second waterwall, sleeve pipe and The liquid containing chamber is formed between first waterwall.
Preferably, the spout hole for adjusting liquid level in described sleeve pipe is opened up on first waterwall so that pipeline section enters Enter holding suspended state or floating state after described sleeve pipe;
Or,
When the receiving terminal port of described sleeve pipe is provided with the second waterwall, opened up for adjusting on second waterwall State the spout hole of liquid level in sleeve pipe so that pipeline section keeps suspended state or floating state after entering described sleeve pipe.
Preferably, mounting platform is provided with described sleeve pipe, the supporting member is fixed on the mounting platform.
Preferably, the supporting member is steel bracket, and the track coaxial with described sleeve pipe is provided with the mounting platform, many The individual steel bracket is spaced apart along the length direction of the track.
Preferably, first waterwall is arranged on the mounting platform.
Preferably, the collar is installed at the poling hole.
Preferably, sealing collar is installed in the collar.
Preferably, the collar collar extension is circumferentially provided with multiple locating parts so that penetrate pipeline in the poling hole with The collar and sealing collar are concentric.
Preferably, the locating part is the fast pulley being fixed on first waterwall.
(3) beneficial effect
Water of the invention applies method pipeline laying facility, in working pit, including sleeve pipe and is fixed in described sleeve pipe And for the supporting member of fixed -piping, also including the first waterwall installed in the entrance point port of described sleeve pipe, and described Liquid containing chamber is formed between first waterwall and described sleeve pipe;It is provided with for penetrating pipeline on first waterwall Poling hole.When the water is applied into method pipeline laying facility for pipeline laying, when pipe end to be laid penetrates the first waterwall On poling hole after, can be to injecting liquid in liquid containing chamber.After injection liquid, the pipeline entered into sleeve pipe is subject to perpendicular Straight upward buoyancy so that the active force needed during pipeline laying reduces, with reduce requirement to laying apparatus and Complex operation degree, improves the security and laying speed of construction, and ensures pipeline laying in place.Further, since support member is pre- Pipeline sleeve pipe is driven after first installing again, therefore can prevent support member from damaging deformation;Meanwhile, in buoyancy down tube The frictional resistance that road is subject to reduces, such that it is able to the outer anti-corrosion of effective protective conduit.
Brief description of the drawings
In order to illustrate more clearly about the embodiment of the present invention or technical scheme of the prior art, below will be to embodiment or existing The accompanying drawing to be used needed for having technology description is briefly described, it should be apparent that, drawings in the following description are only this Some embodiments of invention, for those of ordinary skill in the art, on the premise of not paying creative work, can be with Other accompanying drawings are obtained according to these accompanying drawings.
Fig. 1 is the structural representation of the deposited method pipeline laying facility of water of embodiment;
Fig. 2 is recycled water pipeline laying structural representation in place;
Fig. 3 is the use state schematic diagram of pipeline work platform in embodiment;
In figure:1st, sleeve pipe;2nd, waterpipe is regenerated;3rd, steel bracket;4th, mounting platform;5th, waterwall;6th, the collar;7th, sealing Circle;8th, fast pulley;9th, spout hole;10th, pipeline work platform;11st, working pit;12nd, fixed pulley;13rd, hoist engine.
Specific embodiment
It is below in conjunction with the accompanying drawings and specific real in order to be more clearly understood that the above objects, features and advantages of the present invention Mode is applied to be further described in detail the present invention.It should be noted that in the case where not conflicting, the implementation of the application Feature in example and embodiment can be mutually combined.
In the description of the invention, it is necessary to explanation, term " " center ", " longitudinal direction ", " transverse direction ", " on ", D score, The orientation or position relationship of the instruction such as "front", "rear", "left", "right", " vertical ", " level ", " top ", " bottom ", " interior ", " outward " are Based on orientation shown in the drawings or position relationship, it is for only for ease of and describes the present invention and simplify to describe, rather than instruction or dark Showing the device or element of meaning must have specific orientation, with specific azimuth configuration and operation therefore it is not intended that right Limitation of the invention.Additionally, term " first ", " second ", " the 3rd " are only used for describing purpose, and it is not intended that indicating or dark Show relative importance.
In the description of the invention, it is necessary to illustrate, unless otherwise clearly defined and limited, term " connected ", " company Connect " should be interpreted broadly, for example, it may be being fixedly connected, or being detachably connected, or it is integrally connected;It can be machine Tool is connected, or electrically connected;Can be joined directly together, it is also possible to be indirectly connected to by intermediary.For this area For those of ordinary skill, above-mentioned term concrete meaning in the present invention can be understood with concrete condition.
Refer to Fig. 1, the deposited method pipeline laying facility of water of the present embodiment, including sleeve pipe 1 and be fixed in described sleeve pipe 1 simultaneously For the supporting member of fixed -piping, also including the first waterwall 5 installed in the entrance point port of described sleeve pipe 1, and described Liquid containing chamber is formed between first waterwall 5 and described sleeve pipe 1;It is provided with for penetrating pipe on first waterwall 5 The poling hole in road.
When the water is applied into method pipeline laying facility for pipeline laying, when pipe end to be laid penetrates the first waterwall Behind poling hole on 5, can be to injecting liquid in liquid containing chamber.After injection liquid, the pipeline entered into sleeve pipe 1 is subject to Buoyancy straight up, so that the active force needed during pipeline laying reduces, to reduce the requirement to laying apparatus With complex operation degree, the security and laying speed of construction are improved, and ensure pipeline laying in place.Further, since support member Pipeline sleeve pipe 1 is driven after installing in advance again, therefore can prevent support member from damaging deformation;Meanwhile, in buoyancy The frictional resistance that lower pipeline is subject to reduces, such that it is able to the outer anti-corrosion of effective protective conduit.
It should be noted that the present embodiment middle sleeve 1 and pipeline are two independent concepts, pipeline is including sleeve pipe 1 Only refer only to the pipe fitting being laid in sleeve pipe 1.
It is noted that the second waterwall 5 can also be set in the receiving terminal port of sleeve pipe 1 so that the second gear The liquid containing chamber is formed between waterwall 5, the waterwall 5 of sleeve pipe 1 and first.This kind of situation can prevent receiving terminal correspondence work Make 11 internal water accumulations of hole, cause to need to inject more liquid when liquid level reaches setting height in sleeve pipe 1.Certainly, even if sleeve pipe 1 connects Receiving end port is not provided with the second waterwall 5, then can also form the liquid between working pit 11, the first waterwall 5 and sleeve pipe 1 Body accommodating chamber, so as to nor affect on laying for the present embodiment pipeline.
It should be noted that because the second waterwall 5 is provided in the receiving terminal port of sleeve pipe 1, it does not have with the installation of pipeline There is direct relation, therefore poling hole need not be set on second waterwall 5.
In order to be adjusted to the liquid level in liquid containing chamber, liquid containing chamber after pipeline sleeve pipe 1 is prevented Interior liquid level more and more higher, preferably opens up the spout hole 9 for adjusting liquid level in described sleeve pipe 1 on first waterwall 5, So that pipeline section keeps suspended state or floating state after entering described sleeve pipe 1.
Obviously, when after pipeline sleeve pipe 1 in floating or suspended state, namely liquid is applied to pipeline in sleeve pipe 1 Plus buoyancy not less than the interior conduit of sleeve pipe 1 gravity, now due to almost not rubbed between pipeline and support member, therefore The outer anti-corrosion of pipeline can obtain optimal protection.
In order that obtain after pipeline section enters described sleeve pipe 1 keeping suspended state or floating state, then liquid containing chamber Indoor liquid level is needed by presetting.Wherein, injection liquid is different, and its setting liquid level is also different.
It is preferred that being water to the liquid injected in sleeve pipe 1.Pipeline is now caused to suspend or float, then what pipeline was subject to Gravity of the buoyancy not less than the pipeline in sleeve pipe 1, it is assumed that the buoyancy that pipeline is subject to is equal to the weight of the pipeline in sleeve pipe 1 Power, according to Archimedes's formula ρWatergVRow=mg, can obtain VRow.Wherein, ρWaterIt is the density of water, VRowOne meter is often pushed for pipeline Corresponding displacement of volume, mg is one meter of weight of above-mentioned regeneration waterpipe 2, and waterpipe 2 is regenerated with the steel of a diameter of 1200mm As a example by, its every meter weight is 0.667T.Further, according to VRowCan be obtaining setting level value.
Even if certainly it should be noted that the liquid being passed through in sleeve pipe 1, it is less than sleeve pipe to the buoyancy that pipeline applies The gravity of the pipeline in 1, but as long as certain buoyancy can be applied to pipeline, then its effect is equivalent to reduction pipeline and is subject to Frictional resistance, such that it is able to facilitate laying for pipeline.
When liquid is less than the gravity of the interior conduit of sleeve pipe 1 to the buoyancy that pipeline applies in sleeve pipe 1, in order to prevent pipeline External anti-corrosion layer and support member are scraped damage when contacting, and can be selected after pipeline is installed in place in sleeve pipe 1, then give pipeline appearance Face coats outer anti-corrosion.Certainly, in the prior art, the outer anti-corrosion of pipeline is typically all just to have been completed before pipeline laying.
Wherein, the catch pit that the water for being overflowed from spout hole 9 can be entered first in working pit 11, then it is evacuated to working pit through water pump Outside 11.
It should be noted that in order to keep liquid level, in addition to spout hole 9 is set on the first waterwall 5, it is also an option that Spout hole 9 is set on the second waterwall 5 or sleeve pipe 1, or directly auxiliary is drawn water with suction pump, or use with top The combination of method.
In the present embodiment, in order to be supported the installation of part, mounting platform 4 is preferably set in sleeve pipe 1, and track is consolidated It is scheduled on the mounting platform 4.Wherein, the concrete platform that mounting platform 4 can be formed using C20 concretings, and Track can be embedded in concrete platform.On this basis, support member is spaced apart along the length direction of track.Branch Support member is preferably necessarily still more typical steel bracket 3, so as to conveniently draw materials.Wherein, the size of steel bracket 3 again wait to apply by basis If depending on the size of pipeline so that the bearing-surface that steel bracket 3 is formed just matches with pipeline external surface.
Certainly, the mounting means and concrete structure of support member are not enumerated by the present embodiment and limited, as long as it can be supported And the stabilization interior conduit of sleeve pipe 1.
Additionally, the waterwall 5 of above-mentioned first waterwall 5 and second can up be installed since the upper surface of mounting platform 4, Fig. 1 is referred to, wherein the first waterwall 5 is located at the top of mounting platform 4.Or, the first waterwall 5 and the second waterwall 5 May be mounted at the outside of mounting platform 4 and installed since the inner surface of sleeve pipe 1.Wherein, the height of the first waterwall 5 is referred to Fig. 1, the port of sleeve pipe 1 is completely enclosed due to it, therefore to be installed and can also pass in and out sleeve pipe 1 after the first waterwall 5 and enter Capable some basic constructions.
Additionally, the poling hole on the first waterwall 5 of entrance point port, its position determines according to the position of laying of pipeline, To ensure that pipeline, through after poling hole sleeve pipe 1, is nearly seated at the surface of support member.Also, in order to prevent pipe Collide interference after road sleeve pipe 1 with support member, and the height in preferred pair poling hole is designed, to cause to pass through poling hole The pipeline of sleeve pipe 1, its bottom surface is higher by certain position than the bearing-surface of support member.
To prevent leak between pipeline and poling hole, the collar 6 is preferably installed at poling hole, and in the collar 6 Sealing collar 7 is installed.Wherein, the collar 6 is preferably necessarily still steel collar 6 and consolidates in advance in the installation process of the first waterwall 5 It is scheduled in the first waterwall 5.Sealing collar 7 is fixedly mounted along the inner surface of the collar 6.
On this basis, in order to prevent pipeline uneven to the power that sealing collar 7 applies, preferably along the collar extension of the collar 6 week To multiple locating parts are distributed with, the locating part can ensure that the collar 6, sealing collar 7 and pipeline are concentric all the time, so as to prevent pipeline inclined , there are the phenomenons such as damage, leak to avoid sealing collar 7 in the unbalance stress of sealing collar 7 caused by heart play.For example, when pipeline is subject to During the upward play of buoyancy, if the not locating part, then the active force that the top of sealing collar 7 is subject to is larger, now may There are the phenomenons such as damage, leak on the top of sealing collar 7.Wherein, the quantity of locating part is unrestricted, and preferably but necessarily edge The collar 6 circumferentially to be uniformly distributed.
In the present embodiment, locating part is preferably the fast pulley 8 being fixed on first waterwall 5.In the case of this kind, when It is rolling friction due to what is produced between pipeline and fast pulley 8 during pipe extrusion fast pulley 8, the frictional force is very small, so that can To avoid pipeline from being scraped off.
Further, in order to prevent pipeline for scratch, slurries generally are lubricated in pipeline outer wall brushing, to reduce sealing collar 7 With the frictional resistance of pipeline lateral wall, and the outer anti-corrosion of pipeline is protected by.Additionally, lubrication slurries also have Packed effect, can Effectively to prevent water in sleeve pipe 1 from outflowing.
Wherein it is possible to apply method pipeline laying facility by the water that following construction procedure obtains the present embodiment:
Sleeve pipe 1 is arranged in working pit 11;
Support member is installed in sleeve pipe 1;
First waterwall 5 is installed in the entrance point port of described sleeve pipe 1, and in the first waterwall of the entrance point port The poling hole of pipeline is set on 5.
It is noted that support member can be installed before the first waterwall 5 is installed, it is also possible to installing the first dash Support member is installed after wall 5, or even support member can also be installed in laid processes.
When carrying out pipeline laying using the deposited method pipeline laying facility of the water, including:
S1, pipeline end install pipe plug after, the end of the pipeline is penetrated into described sleeve pipe 1 by the poling hole It is interior, to block the poling hole;
S2, in described sleeve pipe 1 inject liquid with to enter described sleeve pipe 1 in pipeline apply buoyancy;
S3, the pipeline is pushed or pulled into described sleeve pipe 1;
S4, the liquid emitted in described sleeve pipe 1 so that pipeline falls on the support member and fixed.
In S1, by blocking pipe end, it is ensured that during pipeline is advanced to receiving terminal, liquid will not be through pipeline Outflow, and liquid provides certain buoyancy to pipeline in sleeve pipe 1, so that for pipeline laying provides a drying, the work of safety Space.As for the pipe plug installed in the end of pipeline, its form is unrestricted, as long as closure can be realized to prevent water excessive .It is for instance possible to use blind plate is used as the pipe plug, and the blind plate can be embedded in pipeline inside simultaneously and table in the pipeline Face interference fit.Additionally, pipe plug can take out after last pipeline laying completion from the receiving terminal of sleeve pipe 1.
In S3, during pipeline is pushed or pulled into sleeve pipe 1, it can use technology hand disclosed in any prior art Section.Equally, the end of pipeline is passed through in poling hole threading 1 also based on same technological means in S1.
Wherein, when the pipeline in sleeve pipe to be laid in 1, when it is divided into many pipeline sections, will be close to the pipeline section of the receiving terminal First gradually it is moved in described sleeve pipe 1, until the pipeline section only has afterbody and stays in outside described sleeve pipe 1, now by the pipeline section and another Pipeline section is end to end.Wherein, for the pipeline section of steel, the connection between pipeline section can be carried out by the way of welding, and butt welding Mouth position carries out preservative treatment.
In S4, after the equal sleeve pipe 1 of pipeline, in order to ensure that pipeline is finally accurately arranged on support member, can be with While liquid in exclusion sleeve 1, human assistance is adjusted to the position of pipeline.Obviously, under buoyancy, it is only necessary to Manually can just realize being accurately positioned for pipeline on a small quantity.Certainly, in an ideal case, after liquid is discharged from sleeve pipe 1, pipeline meeting Automatic accurate falls in support member, without manually adjusting.Wherein it is possible to emitted the water in sleeve pipe 1 using pump, when Can also so cause that the water in sleeve pipe 1 flows out naturally by way of opening.
After S4, can select to disassemble the first waterwall 5, obtain regenerating waterpipe 2 and lay structure in place such as Shown in Fig. 2.
The steel that the above method is applied to a diameter of 1200mm is regenerated into when laying of waterpipe 2:First of all for being easy to apply Work, can cut into every 6m by the pipeline section of factory calibration length 12m;Secondly, for above-mentioned recycled water pipeline section, by support member It is set to 2.5m;Thirdly, in pipeline section laid processes, when the recycled water pipeline section of the 6m has a quarter sleeve pipe 1, Now start the water filling toward in sleeve pipe 1;Also, when recycled water pipeline section only 1m stay in sleeve pipe 1 it is outer when, by follow-up recycled water pipeline section Welded with current recycled water pipeline section.
In order to further facilitate pipeline laying, the present embodiment provides a kind of pipeline work platform 10, refers to Fig. 3.From Fig. 3 In it can be seen that, the pipeline work platform 10 be arranged on the entrance point port of sleeve pipe 1 outside, so as to facilitate laying for subsequent pipeline.
On the basis of the above, applying method pipeline laying facility according to above-mentioned pipeline work platform 10 and water carries out pipeline laying When, comprise the following steps:
Pipeline work platform 10 is arranged on the entrance point port outside of sleeve pipe 1;
To treat that roughing-in is positioned over the directive wheel to upper;
Pipeline is drawn using power set so that pipeline is moved and entered on the directive wheel along the setting track In sleeve pipe 1.
Wherein, when the power set are hoist engine 13, " drawing pipeline using power set " includes:
The hoist engine 13 is arranged on the first end top of pipeline to be laid, in the top at the second end of the pipeline Fixed pulley 12 is set;
The hawser of hoist engine 13 is bypassed into the first end that the fixed pulley 12 is connected to the pipeline afterwards;
Start hoist engine 13 to be wound, with pipeline described in horizontally tracting towards motion in described sleeve pipe 1.
Fig. 3 is referred to, wherein hoist engine 13 is arranged on the upper right side of pipeline;Fixed pulley 12 is fixed on the upper left side of pipeline, Specifically it is fixed on the entrance point port of sleeve pipe 1 top.In the case of this kind, the winding hawser of hoist engine 13, to cause pipeline in hoist engine Level is moved towards described sleeve pipe 1 is interior under 13 draws.It is of course also possible to hoist engine 13 is arranged on the upper left side of pipeline, and Fixed pulley 12 is fixed on the upper right side of pipeline, as above-mentioned, here is omitted for specific operation principle.
Embodiment of above is merely to illustrate the present invention, rather than limitation of the present invention.Although with reference to embodiment to this hair It is bright to be described in detail, it will be understood by those within the art that, technical scheme is carried out various combinations, Modification or equivalent, without departure from the spirit and scope of technical solution of the present invention, all should cover will in right of the invention Ask in the middle of scope.

Claims (10)

1. a kind of water applies method pipeline laying facility, including sleeve pipe and is fixed in described sleeve pipe and is used for the supporting of fixed -piping Part, it is characterised in that also including the first waterwall installed in the entrance point port of described sleeve pipe, and in first waterwall Liquid containing chamber is formed and described sleeve pipe between;The poling hole for penetrating pipeline is provided with first waterwall.
2. water according to claim 1 applies method pipeline laying facility, it is characterised in that the receiving terminal port of described sleeve pipe sets It is equipped with the second waterwall so that second waterwall, the liquid containing chamber is formed between sleeve pipe and the first waterwall.
3. water according to claim 1 and 2 applies method pipeline laying facility, it is characterised in that opened on first waterwall If the spout hole for adjusting liquid level in described sleeve pipe so that pipeline section keeps suspended state or floating after entering described sleeve pipe State;
Or,
When the receiving terminal port of described sleeve pipe is provided with the second waterwall, opened up for adjusting the set on second waterwall The spout hole of intraluminal fluid position so that pipeline section keeps suspended state or floating state after entering described sleeve pipe.
4. water according to claim 1 applies method pipeline laying facility, it is characterised in that installation is provided with described sleeve pipe flat Platform, the supporting member is fixed on the mounting platform.
5. water according to claim 4 applies method pipeline laying facility, it is characterised in that the supporting member is steel bracket, institute State and the track coaxial with described sleeve pipe is provided with mounting platform, between length direction of multiple steel brackets along the track Every distribution.
6. water according to claim 4 applies method pipeline laying facility, it is characterised in that first waterwall is arranged on institute State on mounting platform.
7. water according to claim 1 applies method pipeline laying facility, it is characterised in that be provided with set at the poling hole Ring.
8. water according to claim 7 applies method pipeline laying facility, it is characterised in that be provided with sealing in the collar Circle.
9. water according to claim 8 applies method pipeline laying facility, it is characterised in that the collar collar extension is circumferentially provided with Multiple locating parts so that the pipeline penetrated in the poling hole is concentric with the collar and sealing collar.
10. water according to claim 9 applies method pipeline laying facility, it is characterised in that the locating part is to be fixed on State the fast pulley on the first waterwall.
CN201611226220.1A 2016-12-27 2016-12-27 A kind of water applies method pipeline laying facility Pending CN106764052A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201611226220.1A CN106764052A (en) 2016-12-27 2016-12-27 A kind of water applies method pipeline laying facility

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201611226220.1A CN106764052A (en) 2016-12-27 2016-12-27 A kind of water applies method pipeline laying facility

Publications (1)

Publication Number Publication Date
CN106764052A true CN106764052A (en) 2017-05-31

Family

ID=58922095

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201611226220.1A Pending CN106764052A (en) 2016-12-27 2016-12-27 A kind of water applies method pipeline laying facility

Country Status (1)

Country Link
CN (1) CN106764052A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108194137A (en) * 2017-11-22 2018-06-22 中国市政工程中南设计研究总院有限公司 A kind of penstock installation method in the straight tunnel of light section
CN111119217A (en) * 2020-01-21 2020-05-08 天津市管道工程集团有限公司 Pipeline interface welding space device that blocks water
CN112762240A (en) * 2021-01-25 2021-05-07 浙江大亚节能科技有限公司 Detachable wall-penetrating heat insulation sleeve and mounting method thereof

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4616955A (en) * 1984-10-18 1986-10-14 Bechtel International Corporation Method and apparatus for encasing pipeline or cable
CA2479961A1 (en) * 2002-03-29 2003-10-09 Fiberspar Corporation Systems and methods for pipeline rehabilitation
CN102261519A (en) * 2011-04-15 2011-11-30 胜利油田胜利石油化工建设有限责任公司 Method for assisting sliding, floating and down-ditching of pipeline by air bags
CN103016840A (en) * 2013-01-10 2013-04-03 李荣海 Pipe distributing method by pipe threading in draining
CN105927792A (en) * 2016-04-07 2016-09-07 广东省水利水电第三工程局有限公司 Water floating transportation method for prestressed concrete cylinder pipes
CN206347201U (en) * 2016-12-27 2017-07-21 北京市政路桥管理养护集团有限公司 A kind of water applies method pipeline laying facility

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4616955A (en) * 1984-10-18 1986-10-14 Bechtel International Corporation Method and apparatus for encasing pipeline or cable
CA2479961A1 (en) * 2002-03-29 2003-10-09 Fiberspar Corporation Systems and methods for pipeline rehabilitation
CN102261519A (en) * 2011-04-15 2011-11-30 胜利油田胜利石油化工建设有限责任公司 Method for assisting sliding, floating and down-ditching of pipeline by air bags
CN103016840A (en) * 2013-01-10 2013-04-03 李荣海 Pipe distributing method by pipe threading in draining
CN105927792A (en) * 2016-04-07 2016-09-07 广东省水利水电第三工程局有限公司 Water floating transportation method for prestressed concrete cylinder pipes
CN206347201U (en) * 2016-12-27 2017-07-21 北京市政路桥管理养护集团有限公司 A kind of water applies method pipeline laying facility

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
SABERQIURUI: "套管内管道敷设施工工艺-漂管", 《HTTP://V.YOUKU.COM/V_SHOW/ID_XMTCWNTY0NDK4NA==.HTML?SPM=A2H0K.8191407.0.0&FROM=S1.8-1-1.2》 *

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108194137A (en) * 2017-11-22 2018-06-22 中国市政工程中南设计研究总院有限公司 A kind of penstock installation method in the straight tunnel of light section
CN111119217A (en) * 2020-01-21 2020-05-08 天津市管道工程集团有限公司 Pipeline interface welding space device that blocks water
CN112762240A (en) * 2021-01-25 2021-05-07 浙江大亚节能科技有限公司 Detachable wall-penetrating heat insulation sleeve and mounting method thereof
CN112762240B (en) * 2021-01-25 2022-09-06 浙江大亚节能科技有限公司 Detachable wall-penetrating heat insulation sleeve and mounting method thereof

Similar Documents

Publication Publication Date Title
CN106594388A (en) Pipe working platform and method for laying pipes by applying pipe working platform
CN106838459A (en) A kind of method of roughing-in in sleeve pipe
CN106764052A (en) A kind of water applies method pipeline laying facility
CN206347201U (en) A kind of water applies method pipeline laying facility
CN206346209U (en) A kind of quick solution dewatering well piping plugging structure
CN104805842A (en) Steel flower pipe segmented grouting system and construction method thereof
CN104776268B (en) Mechanical construction method for mounting large-caliber reinforced concrete drainage pipe
CN108412017A (en) A kind of drainage pipeline inner wall Mortar spraying machine and its application method
CN206347202U (en) Pipeline work platform
CN206495234U (en) The existing pipe excavation protection constructing device of underground pipe gallery
CN208563315U (en) A kind of pile foundation grouting behind shaft or drift lining constructing device
CN209369832U (en) Steel pipe behind fill concrete structure in a kind of tunnel
CN204080839U (en) A kind of Yield rainfall relation device
CN110172995B (en) Grouting construction system and method for large-diameter single-pile steel pipe pile interpolation transition section
CN209724371U (en) A kind of water-conveyance tunnel narrow space lined steel pipe mounting structure
JPH10238655A (en) Method for piping pipe body making use of buoyancy
CN207621485U (en) A kind of prestressed concrete pipe mounting device
CN207277486U (en) A kind of mill tailings storehouse is met an urgent need self-draining arrangement
CN105486461A (en) Exterior wall water spray test system and test method thereof
CN213297251U (en) Grouting and trowelling equipment for repairing obstacle points in communication pipeline
CN205329515U (en) Manual portable highway marking device
CN210341975U (en) Major diameter single pile steel-pipe pile interpolation changeover portion grouting construction system
CN204626409U (en) A kind of steel floral tube segmenting slip casting system
JP3987369B2 (en) Laying method and equipment for rehabilitating existing pipes
CN209568460U (en) A kind of pipeline arrangement being suitable for different height lubricant injected hole after open caisson wall

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20170531