CN106761742B - A kind of deep island working face gob side entry driving surrounding rock stability control method - Google Patents

A kind of deep island working face gob side entry driving surrounding rock stability control method Download PDF

Info

Publication number
CN106761742B
CN106761742B CN201611034588.8A CN201611034588A CN106761742B CN 106761742 B CN106761742 B CN 106761742B CN 201611034588 A CN201611034588 A CN 201611034588A CN 106761742 B CN106761742 B CN 106761742B
Authority
CN
China
Prior art keywords
working face
entry driving
adjacent
island
side entry
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201611034588.8A
Other languages
Chinese (zh)
Other versions
CN106761742A (en
Inventor
李树刚
双海清
丁洋
魏宗勇
严敏
陈高峰
赵鹏翔
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Xian University of Science and Technology
Original Assignee
Xian University of Science and Technology
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Xian University of Science and Technology filed Critical Xian University of Science and Technology
Priority to CN201611034588.8A priority Critical patent/CN106761742B/en
Publication of CN106761742A publication Critical patent/CN106761742A/en
Application granted granted Critical
Publication of CN106761742B publication Critical patent/CN106761742B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21CMINING OR QUARRYING
    • E21C41/00Methods of underground or surface mining; Layouts therefor
    • E21C41/16Methods of underground mining; Layouts therefor
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D20/00Setting anchoring-bolts

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Remote Sensing (AREA)
  • Lining And Supports For Tunnels (AREA)

Abstract

The invention discloses a kind of deep island working face gob side entry driving surrounding rock control methods, include the following steps: to carry out the disconnected top of presplitting before adjacent two working face extraction of island working face, make it that can not form articulated structure in face end, the hinged rock beam of key stratum is avoided to transmit Adjacent Working Face overlying strata mining induced stress to this working face;Constant resistance and large deformation anchor rod is selected in gob side entry driving support system, while increasing entity coal wall side and top plate side anchor rope length, enables anchor pole by deforming come release, anchor cable can shift country rock concentrated stress to farther entity coal wall side;Destressing borehole is arranged obliquely to the inclination of entity coal wall in the advanced 3-4 periodic weighting step pitch of island working face;Whitewashing processing is carried out in thin coal pillar side.The present invention effectively reduces deep working face stress concentration degree, reaches and reduces bracket, pillar and Support Resistance, improves the rate of extraction of coal resources, while improving the safe and efficient back production efficiency of working face, has great technology and economic benefit.

Description

A kind of deep island working face gob side entry driving surrounding rock stability control method
Technical field
The present invention relates to deep island working face gob side entry driving country rock fields, and in particular to a kind of deep island working face edge The lane Kong Jue surrounding rock stability control method.
Background technique
Pit mining occupies important ratio in China's coal-mine, when working face single-blade strip-type arrangement, for the ease of Excavation replacement and the reasons such as centralized production are avoided, it is general to be adopted using jumping, to form numerous island working faces.Due to isolated island work It is big relative to common working face stress concentration degree to make face, causes that force piece resistance is big, roadway support is difficult.Traditional area Section coal pillar width is 30-50m, and tunnel rock deformation is big in exploitation process, directly dangerous the safe and efficient back production of working face.Mesh Preceding edge air gallery technology reaches its maturity, which, which passes through to stay, sets the rate of extraction that thin coal pillar improves coal resources, while will dig along sky Lane, which is arranged in surrouding rock stress, reduces region, can effectively control deformation of the surrounding rock in tunnel.But with the day of superficial part coal resources It is beneficial exhausted, all enter the exploitation of deep resource successively both at home and abroad, pit mining reaches certain depth, and pressure rack often occurs in working face The problems such as, roadway surrounding rock shows high-ground stress, large deformation (serious bottom distension etc.), zonal fracturing, bump, coal and gas When the nonlinear physics phenomenon such as prominent, even if roadway surrounding rock is also difficult to control effectively, serious using gob side entry driving technology Obstruct the safe and efficient back production of working face.
Summary of the invention
To solve the above problems, the present invention provides a kind of deep island working face gob side entry driving surrounding rock stability controlling parties Method.Main technical measures are started with from " large and small " structure of the surrounding rock stability of gob side entry driving carries out comprehensively control, wherein big knot Structure refers to carries out the disconnected top of presplitting before adjacent two working face extraction of island working face, and small structure refers to the support system after gob side entry driving Middle selection constant resistance and large deformation anchor rod lengthens anchor cable, rolls tiltedly in the advanced 3-4 periodic weighting step pitch of island working face to entity coal wall Arrangement destressing borehole downwards, finally carries out whitewashing processing to thin coal pillar side.
To achieve the above object, the technical scheme adopted by the invention is as follows:
A kind of deep island working face gob side entry driving surrounding rock control method, includes the following steps:
When first stage, back production Adjacent Working Face, close to the 3-4 period of first advance in the tunnel of island working face side It it is tilted towards base object model at distance makes a call to a row and intensively drill, pre- brisement top is carried out using advanced concentrated stress, on Adjacent Working Face Rock stratum carries out gob side entry driving after stablizing, identical method is used in Adjacent Working Face;
Second stage, in back production island working face, entity coal wall side can by it is appropriate deformation reach release purpose, Require that the anchor pole in the collateral protecting system of entity coal wall is constant resistance and large deformation anchor rod at this time, entity coal wall side and top plate side anchor rope Length increases.
Phase III: before island working face back production advanced 3-4 periodic weighting step pitch to entity coal wall direction side sideling to Lower arrangement destressing borehole, the span length that drilling depth is 3-4 times, diameter are generally 53-75mm, are apart from roadway floor side 1m, spacing distance 2m.
Fourth stage: to prevent, adjacent goaf pernicious gas from being gushed out by thin coal pillar or gob side entry driving air enters Adjacent goaf causes the safety problems such as spontaneous combustion of remaining coal, carries out whitewashing processing in thin coal pillar side.
The invention has the following advantages:
(1) it is answered since the 3-4 period of Adjacent Working Face first advance weakens advanced support by drilling pre- brisement top The influence of power reduces support resistance, the Support Resistance of Adjacent Working Face, has reached the safe and efficient back production of Adjacent Working Face.
(2) island working face stress concentration degree can be effectively reduced, reduce force piece resistance in exploitation process, Advanced support hydraulic prop intensity and supporting intensity, alleviate the amount of labour of staff, ensured bracket, pillar and The safety of anchor pole (rope).
(3) gob side entry surrouding rock deformation can effectively be reduced, since base object model can not form articulated structure, roadway surrounding rock is answered Power intensity reduces, and constant resistance and large deformation anchor rod can achieve the effect that release by deforming, and increasing anchor cable being capable of general Country rock concentrated stress is shifted to entity coal wall side deeper inside, while first advance further ensures release to coal seam drilling Effect reduces the supporting intensity in tunnel on the whole, has achieved the purpose that reduce supporting expense, it is safe and efficient to increase working face Back production.
(4) thin coal pillar gob side entry driving is set due to using to stay, can significantly improves coal resources compared to traditional coal column The rate of extraction, while being quickly smoothly connected convenient for working face.
It in summary it can be seen, this deep island working face gob side entry driving surrounding rock stability control method can reach " two High two benefits that subtract two ".Effectively reduce deep working face stress concentration degree, reaches reduction bracket, pillar and supporting resistance Power improves the rate of extraction of coal resources, improves the safe and efficient back production efficiency of working face, with certain technology and economic effect Benefit.
Detailed description of the invention
Fig. 1 is deep island working face gob side entry driving surrounding rock stability control arrangement diagrammatic cross-section
In figure: 1- Adjacent Working Face 1;2- Adjacent Working Face 2;3- island working face;4- is close to island working face side tunnel; 5- base object model;6- intensively drills;7- thin coal pillar;8- gob side entry driving;9- gob side entry driving entity coal wall side;10- gob side entry driving bottom plate Side;11- gob side entry driving top plate side;12- destressing borehole;13- gob side entry driving thin coal pillar side.
Specific embodiment
In order to which objects and advantages of the present invention are more clearly understood, the present invention is carried out with reference to embodiments further It is described in detail.It should be appreciated that the specific embodiments described herein are merely illustrative of the present invention, it is not used to limit this hair It is bright.
The embodiment of the invention provides a kind of deep island working face gob side entry driving surrounding rock stability control methods, including such as Lower step:
When first stage, back production Adjacent Working Face 1, close to 3-4 week of first advance in island working face side tunnel 4 It it is tilted towards base object model 5 at phase distance makes a call to a row and intensively drill 6, pre- brisement top is carried out using advanced concentrated stress, to operated adjacent Gob side entry driving 8 is carried out after the stability of overlying rock strata of face.Identical method is used in Adjacent Working Face 2.
Second stage, in back production island working face 3, entity coal wall side 9 can by it is appropriate deformation reach release mesh , require that the anchor pole in 9 support system of entity coal wall side is constant resistance and large deformation anchor rod, entity coal wall side 9 and top plate side at this time The length of 11 anchor cables increases.
Phase III: before 3 back production of island working face advanced 3-4 periodic weighting step pitch to 9 direction side of entity coal wall sideling Arrangement destressing borehole 12 downwards, the span length that drilling depth is 3-4 times, diameter is generally 53-75mm, apart from roadway floor side 10 be 1m, spacing distance 2m.
Fourth stage: for prevent adjacent 1,2 goaf pernicious gases from gushing out by thin coal pillar or 8 air of gob side entry driving into Enter to adjacent 1,2 goafs and cause the safety problems such as spontaneous combustion of remaining coal, carries out whitewashing processing in thin coal pillar side 13.
Specifically, including the following steps:
S1, in order to reduce Adjacent Working Face 1,2 overburden stress are transmitted to island working face 3, in back production operated adjacent When face 1,2, only illustrates that working face (1) takes measures because the measure that island working face two sides are taken is the same, in the application, work as work Working face 2 takes identical measure after making 1 back production of face.Close to first advance 3-4 in island working face side tunnel 4 A row is made a call to base object model 5 at periodic distance and intensively drills 6, and with the advance of the face, advanced stress will make the base object model 5 of reduction It is caving in advance, reduces 1 support resistance of working face, while making can not shape in 3 overlying rock of working face 1 and island working face At articulated structure, hinged rock beam is avoided to transmit 1 overlying strata mining induced stress of Adjacent Working Face to island working face 3, to operated adjacent 1 overlying rock activity of face, which stay after stablizing, sets 7 gob side entry driving 8 of thin coal pillar.
S2, surrouding rock stress reduction area is arranged in due to gob side entry driving 8,7 stress of coal column close to goaf is relative to entity 9 surrouding rock stress of coal wall side is smaller, and is influenced by island working face 3, and 9 stress concentration degrees of tunnel entity coal wall side are larger, During 3 back production of island working face, 8 surrouding rock stress intensity of gob side entry driving tunnel will significantly increase in the advanced range of stress Add, causes 9 deflections of entity coal wall side larger, while also increasing the deflection of roadway floor side 10.Entity coal wall side 9 can be with Reach release purpose by deformation appropriate, requires the anchor pole in support system to have constant resistance at this time and have certain stretch Long property, i.e. the constant resistance and large deformation anchor rod patent No. 201010196197.2, it is ensured that beyond the entirety for not influencing its supporting after deflection Intensity.Suitably increase in entity coal wall side 9 and 11 anchor cable of top plate side, it thus can be by country rock concentrated stress to entity coal The farther distance transfer of wall side 9, while can also effectively guarantee top plate side overlying strata combination beam mode and synchronous migration, reduce lane Road top plate 11, entity coal wall side 9, bottom plate side deflection 10.
S3, in order to reduce the stress concentration phenomenon in the advanced range of stress of island working face 3, while before working face extraction Advanced 3-4 periodic weighting step pitch rolls sideling arrangement destressing borehole 12 downwards, the lane that drilling depth is 3-4 times to entity coal wall 9 Road width, diameter are generally 53-75mm, are 1m, spacing distance 2m apart from roadway floor side 10, and drilling can incite somebody to action to a certain extent Working face 3 adopts front support pressure and carries out release, and 9 concentrated stress of entity coal wall side is avoided to transmit to gob side entry bottom plate side 10, protects Confirm body coal wall side 9,10 deflection of bottom plate side in allowed limits.
Although S4,13 deformation ranges of gob side entry driving thin coal pillar side are small, thin coal pillar is before gob side entry driving arrangement in real Body coal wall plastic zone, thin coal pillar is sunk to squeezing by the rotation of key block B after digging lane, causes have crack in 7 coal body of thin coal pillar Generate, for prevent adjacent goaf 1,2 pernicious gases from gushing out by thin coal pillar or 8 air of gob side entry driving enter it is adjacent mined out Area 1,2 causes the safety problems such as spontaneous combustion of remaining coal, need to carry out whitewashing processing in thin coal pillar side 13.
The above is only a preferred embodiment of the present invention, it is noted that for the ordinary skill people of the art For member, without departing from the principle of the present invention, it can also make several improvements and retouch, these improvements and modifications are also answered It is considered as protection scope of the present invention.

Claims (1)

1. a kind of deep island working face gob side entry driving surrounding rock control method, which comprises the steps of:
When first stage, back production Adjacent Working Face (1), close to 3-4 week of the interior first advance in island working face side tunnel (4) It it is tilted towards base object model (5) at phase distance makes a call to a row and intensively drill (6), pre- brisement top is carried out using advanced concentrated stress, to adjacent Gob side entry driving (8) are carried out after working face stability of overlying rock strata, identical method is used in Adjacent Working Face (2);
Second stage, in back production island working face (3), entity coal wall side (9) can by it is appropriate deformation reach release mesh , require that the anchor pole in entity coal wall side (9) support system is constant resistance and large deformation anchor rod, entity coal wall side (9) and top at this time The length of plate side (11) anchor cable increases;
Phase III: before island working face (3) back production advanced 3-4 periodic weighting step pitch to entity coal wall (9) direction side sideling Arrangement destressing borehole (12) downwards, the span length that drilling depth is 3-4 times, diameter 53-75mm, apart from roadway floor side It (10) is 1m, spacing distance 2m;
Fourth stage: goaf pernicious gas is gushed out by thin coal pillar to prevent adjacent (1,2) or gob side entry driving (8) air into Enter to adjacent (1,2) goaf and cause spontaneous combustion of remaining coal safety problem, carries out whitewashing processing in thin coal pillar side (13).
CN201611034588.8A 2016-11-23 2016-11-23 A kind of deep island working face gob side entry driving surrounding rock stability control method Expired - Fee Related CN106761742B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201611034588.8A CN106761742B (en) 2016-11-23 2016-11-23 A kind of deep island working face gob side entry driving surrounding rock stability control method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201611034588.8A CN106761742B (en) 2016-11-23 2016-11-23 A kind of deep island working face gob side entry driving surrounding rock stability control method

Publications (2)

Publication Number Publication Date
CN106761742A CN106761742A (en) 2017-05-31
CN106761742B true CN106761742B (en) 2019-04-16

Family

ID=58971159

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201611034588.8A Expired - Fee Related CN106761742B (en) 2016-11-23 2016-11-23 A kind of deep island working face gob side entry driving surrounding rock stability control method

Country Status (1)

Country Link
CN (1) CN106761742B (en)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112727461B (en) * 2021-01-04 2023-04-18 天地科技股份有限公司 Gob-side roadway mining stress superposition control method
CN114086957B (en) * 2021-11-23 2023-05-05 陕西正通煤业有限责任公司 Colliery strong impact dangerous island working face roadway outside staggered arrangement anti-impact method

Family Cites Families (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE19631520C2 (en) * 1996-08-03 2001-10-18 Kavernen Bau Und Betr S Gmbh Process and plant for the sol-technical extraction of evaporites and preparation of salt solutions
CN101725368B (en) * 2009-11-28 2011-08-17 山东科技大学 Thick seam large mining height working face gob-side entry retaining method
CN103321642B (en) * 2013-05-06 2015-03-11 中国矿业大学 Gob-side entry retaining surrounding rock stabilizing method based on lateral rock stratum pre-splitting control
CN104131834B (en) * 2014-07-11 2016-05-11 华北科技学院 A kind of stope drift active workings gob-side entry retaining method that is applicable to thin and medium seam
CN104533482B (en) * 2014-10-28 2016-08-31 淮浙煤电有限责任公司顾北煤矿分公司 A kind of reinforcement means improving gob side entry driving fender stability

Also Published As

Publication number Publication date
CN106761742A (en) 2017-05-31

Similar Documents

Publication Publication Date Title
WO2020192055A1 (en) Two-step grouting modified water-protective coal mining method for roof aquifers
CN108894787B (en) Leave the pressure break release method of ore pillar stress concentration in Overburden gob area
CN104863629B (en) A kind of method taking out absciss layer gas and draining slip casting under overlying strata using combined drilling and counterboring
CN103161480B (en) Initiatively support the method for roadside packing gob side entry retaining
WO2017096674A1 (en) An above ground and underground cooperative control method of far and near field roofs of extra-large stoping space
CN103306683B (en) A kind of construction method of comprehensive precipitation in hole when excavating deep tunnel
AU2015345830B2 (en) Coal mining method with digging, mining and filling parallel operations under control of cover rock cracks and surface subsidence
CN105370299B (en) The buried empty roadway protection processing in high seam thin coal pillar edge of km
CN105134269A (en) Control technology for roadway surrounding rock achieving cooperative load bearing by enabling anchor cables to penetrate through sheds
CN108868833A (en) A method of it carries out cutting gob side entry retaining in the relieving roadway of top in U-shaped steel supported laneway
CN103306713A (en) Networked reinforcement method for cross-layer drilling of outburst coal seam
CN102678092A (en) Method for commonly extracting coal and coal bed gas by up-hole and down-hole joint construction
CN110529151A (en) A kind of fully mechanized workface Grading And Zoning integrative consolidation passing sunk pillars on full method
CN104234749A (en) Surrounding rock control method for large-section dismantling tunnel of fully-mechanized mining face
CN109026024A (en) A kind of great horizontal stress effect back deformation control method
CN109630168A (en) Comprehensive extracting and caving face tunnel is arranged along floor strata and support pattern
CN106761742B (en) A kind of deep island working face gob side entry driving surrounding rock stability control method
CN103775095A (en) Ridge soft-foundation tunnel advance double guide tunnel and construction method thereof
CN105863639A (en) Coal-mining method of loose coal seam
CN209457957U (en) A kind of New Anchor Cable anchorage
CN109899105A (en) A kind of multistage crossing-hole gas extraction method of low level for coal petrography alternating layers coal seam
CN104265294A (en) Coal pillar-free mining technology for blasting mining face of steeply dipping seam
CN103939115A (en) Semi-subsurface excavation method construction shed tunnel method and structure
CN102852532A (en) Grouting method for preventing rib walk caving
CN210919066U (en) Fully mechanized caving face coal top down integrated tunneling device

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20190416

Termination date: 20191123

CF01 Termination of patent right due to non-payment of annual fee