CN106760593B - A kind of barnacle wall reinforcement method - Google Patents

A kind of barnacle wall reinforcement method Download PDF

Info

Publication number
CN106760593B
CN106760593B CN201611037733.8A CN201611037733A CN106760593B CN 106760593 B CN106760593 B CN 106760593B CN 201611037733 A CN201611037733 A CN 201611037733A CN 106760593 B CN106760593 B CN 106760593B
Authority
CN
China
Prior art keywords
wall
zinc
collar tie
tie beam
wire mesh
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201611037733.8A
Other languages
Chinese (zh)
Other versions
CN106760593A (en
Inventor
褚云朋
刘潇
贾彬
王汝恒
甘璐
古松
张春涛
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Southwest University of Science and Technology
Original Assignee
Southwest University of Science and Technology
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Southwest University of Science and Technology filed Critical Southwest University of Science and Technology
Priority to CN201611037733.8A priority Critical patent/CN106760593B/en
Publication of CN106760593A publication Critical patent/CN106760593A/en
Application granted granted Critical
Publication of CN106760593B publication Critical patent/CN106760593B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G23/00Working measures on existing buildings
    • E04G23/02Repairing, e.g. filling cracks; Restoring; Altering; Enlarging
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G23/00Working measures on existing buildings
    • E04G23/02Repairing, e.g. filling cracks; Restoring; Altering; Enlarging
    • E04G23/0218Increasing or restoring the load-bearing capacity of building construction elements

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Chemical & Material Sciences (AREA)
  • Chemical Kinetics & Catalysis (AREA)
  • Electrochemistry (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Foundations (AREA)
  • Revetment (AREA)

Abstract

The present invention provides a kind of barnacle wall reinforcement method, comprising: builds stone cement strip footing;Build each layer bearing wall in house;Floor beam can be placed on stone cement collar tie beam top after construction intensity by reaching after stone cement collar tie beam;For exterior wall lateral surface, tightened after the preformed hole appeared on zinc-coated wire mesh sheet standard component by embedded bar in stone cement strip footing;The plant that creeps is planted on exterior wall side, beautifies metope, forms green screen;The present invention uses the constraint of barnacle strip footing and each layer collar tie beam as wall entirety, then is aided with to constrain the mode that zinc-coated wire mesh sheet standard component applies pretightning force and conjugate outside block plane, and then improve the globality of wall;Steel fibre is mixed in mud, improves ability to resist splash erosion, reduces the damage to wall, while improving wall durability.

Description

A kind of barnacle wall reinforcement method
Technical field
The present invention relates to construction engineering technical fields more particularly to a kind of barnacle wall to reinforce method.
Background technique
Stone compression strength itself is high, durability is good, is since ancient times exactly a kind of traditional building materials, and according to locality Construction material characteristics form traditional brick-building art.The house built by stone material, it is cool in summer and warm in winter that there is preferable comfortable for living Property, but the local applicable construction material of institute is limited to for most of residential houses and is limited, the landform such as mountainous region, remote limitation, it is difficult to will The big material of the weight such as cement sandstone transports to construction site, therefore fortune fortune few as far as possible, material can use local material as far as possible less.The people It is placed in the middle many added water and stirred using clay after mud be used as building materials, be packed between irregular stone and be built into bearing wall, And the building method adopts so far.Bulk shape size is different, belongs to discrete material, due to the gluing power between block and clay Difference, with long-time rain drop erosion, filleting soil can fall off, and constraint dies down between block, and wall shear resistant is deteriorated, when meeting with big shake It being easy to happen and collapses, the destruction of all previous earthquake middle peasant room such as Wenchuan and the earthquake of Yaan Lushan County is serious, therefore improvement brick-building art, Enhancing wall anti-seismic performance is disposed by construction, and then improves whole collapse resistant capacity of the house under severe earthquake action.
For irregular stone masonry construction house, it is main to limit in wall block the outer changing of the relative positions of plane occurs induced Total collapse only moves in wall plane, though will cause cracking of the wall between gap, when earthquake can be split without falling, and Energy-dissipating and shock-absorbing, it is advantageous instead to antidetonation.Number of patent application 201320630817.8, it is entitled " additional using framework of steel reinforcement through walls The patent of steel plate mesh sheet reinforcing stone structure ", such method is relatively suitable for the smaller situation of wall stress, because after steel plate mesh sheet stress Moderate finite deformation can be generated, and finger stone and soil can be skidded off along fenestral porosity, for most of residential house of such as Tibet region, Since barnacle wall is using mode is piled up, stock material hardness is big, and thickness of wall body is also thicker, carries out pore-forming using electric drill on wall When, enforcement difficulty is big, should reduce drilling hole amount as far as possible, and such method can destroy block integrality.What applicant once applied Number of patent application 201410718582.7, entitled " barnacle wall reinforcement method " are related to a kind of blue using the outer connection of screw rod through walls The method that disk reinforces stone-made house wall by zinc-coated wire junction steel plate mesh sheet, but be not directed to and create irregular stone using mud It starches the wall assembled and proposes improving technology, to improve seismic performance of building.
Summary of the invention
The wall that the purpose of the present invention is assemble out for irregular stone assembles out without neat regular gap Back wall surface irregularity, is built using folk art, carries out filling out block using steel fibre mud between gap, designs one kind in building At layer height be arranged reinforcing bar barnacle cement collar tie beam, wall two sides by the way of galvanized prestressed steel silk netting to barnacle wall into Row construction is reinforced, and band steel confining part is arranged in steel fabric sheet edge, produces to form standard component in factory process, be tightened by tensioning Embedded bar applies pretightning force to steel fabric sheet standard component, and being close to metope ensures that the plane for effectively limiting stone conjugates outside, technique It is simple and easy, the integrality of original wall body stone block is not destroyed, and can effectively improve the shatter-proof ability of stone-made house, and disassembling, assembling and replacing It is convenient, former house construction duration is not influenced.
A kind of barnacle wall reinforcement method, comprising:
Step 1: stone cement strip footing is built, width is 200mm wider than wall, deep 300-500mm;
Step 2: building each layer bearing wall in house, and short steel fibre is mixed in mud used, forms steel fibre mud, After every layer of building wall, it is close to build stone cement collar tie beam on the downside of floor beam, the embedded bar inside collar tie beam, between reinforcing bar Away from 150mm, stone diameter is less than 100mm;For the wall outer side of exterior wall, all reinforcing bars are both passed through, and for inner side of outer wall, partly It skims the upper floor in collar tie beam on number reinforcing bar to go out to appear in floor, half level goes out to appear;And for interior wall, half steel in collar tie beam Muscle is upper in collar tie beam to be skimmed to upper floor to go out to appear, half reinforcing bar in collar tie beam level in lower layer's flooring exposure head, length of appearing 150mm;
Step 3: floor beam, building can be placed on stone cement collar tie beam top after construction intensity by reaching after stone cement collar tie beam Layer beam gos deep into no less than 200mm in wall;
Step 4: it for exterior wall alien invasion, is appeared by embedded bar in stone cement strip footing across galvanized steel It tightens after preformed hole on silk netting standard component, even level embedded bar is appeared across zinc-coated wire mesh sheet using same method Standard component tense and tighten reinforcing bar appear into it is hook-shaped after it is fixed, then by two layers of basal layer zinc-coated wire mesh sheet, structure zinc-coated wire Mesh sheet standard component is tightened at one layer of collar tie beam of structure, and reinforcing bar is passed through junction to the reserved of zinc-coated wire mesh sheet standard component together Reinforcing bar is tightened behind hole to appear and bend to hook-shaped locking, completes one layer of structure, two layers of reinforcement;Again according to this method successively complete it is other The reinforcement of each structure sheaf is constructed;
Step 5: for inner side of outer wall face and interior wall, then directly completing zinc-coated wire mesh sheet standard component in This floor, Be taped against at floor stone cement collar tie beam thereon, under be taped against at floor upper surface;The reinforcing bar in lower layer house is appeared across close The zinc-coated wire mesh sheet standard component of floor upper surface bottom row preformed hole after tighten, the reinforcing bar at stone cement collar tie beam appear across It is tightened after the top row preformed hole of zinc-coated wire mesh sheet standard component, that is, completes the assembly of interior wall zinc-coated wire mesh sheet standard component;
Step 6: plastering outside stone cement collar tie beam, in the external placing concrete of stone cement strip footing, covers Reinforcing bar is appeared, and cover to reinforcement is formed;Exterior wall inner surface and interior wall stone cement collar tie beam processing mode with exterior wall be it is identical, But for the reinforcing bar above interior wall floor beam be bent into it is hook-shaped after, need to by reinforcing bar be close to alien invasion socket, using coat of plaster conduct Stretch out the protective layer of the reinforcing bar of metope.
Step 7: the plant that creeps is planted on exterior wall side, beautifies metope, forms green screen.
Further, method as described above, the stone cement collar tie beam intensity poured are not less than C20, the diameter of reinforcing bar For 12mm, stone diameter is preferably less than 100mm.
Further, method as described above, the production method of zinc-coated wire mesh sheet standard component are as follows: in zinc-coated wire mesh sheet Inside and outside two layers of band steel band is placed at edge, is subsequently filled rubber sheet gasket, then pass through bolt hole and galvanized steel wire netting by high-strength bolt The mesh of piece is tightened the nut of high-strength bolt and is made, inside be provided with window reserved opening.
Further, method as described above, tensioning need to adjust window hole periphery when assembling zinc-coated wire mesh sheet standard component Dimension line adds band steel band, band steel plate tape thickness 10mm, in band steel band intersection along 45 degree of angles on the reserved opening periphery opened up Four frame of periphery is formed after welding using butt weld;Adjustment zinc-coated wire mesh sheet avoids blocking window hole, wherein galvanized steel wire netting On piece opens up reserved opening, and size is slightly larger than window hole, and flat on zinc-coated wire mesh sheet standard component using expansion bolt It is fixed after the reserving hole of steel band with periphery wall, wherein expansion bolt arranged for interval;Door opening schoolmate reserved opening processing side Formula is identical.
Further, method as described above, the band steel band with a thickness of 8mm.
Further, method as described above, the amount of mixing of short steel fibre is according to volume volume in the steel fibre mud 1% carries out.
The utility model has the advantages that
Constraint of the present invention using the collar tie beam of barnacle strip footing and each layer as wall entirety, then be aided with to zinc-coated wire The mode that mesh sheet standard component applies pretightning force is constrained and is conjugated outside block plane, and then improves the globality of wall, to reach earthquake The purpose split when generation without falling;Steel fibre is mixed in mud, improves ability to resist splash erosion, reduces the damage to wall, Wall durability is improved simultaneously.In turn:
This wall construction technology is primarily adapted for use in irregular block, and the wall built using mud, and construction technology is simple, Original barnacle bulk is not destroyed, substantially reduces construction workload;Steel fibre is mixed in mud, and it is de- to significantly improve preventing rain wash The ability fallen improves mortar joint layer anti-cracking ability.
Wall strengthening process is simple, low to skilled worker's dependence, and common laborer can carry out the construction of strengthening process, institute With material from heavy and light, it is easily portable, it is adaptable, and using spanner by tightening reinforcing bar into crotch, quality is readily available Guarantee, the steel fabric sheet of tensioning is close to surface of wall, can effectively inhibit the outer changing of the relative positions of block plane, improve wall under external force Stability.
Floor collar tie beam central axis places reinforcing bar taut wire mesh sheet standard component, and the upper and lower level pulling force that pretightning force generates is to circle Beam is self equilibrium systems, and additional pulling force effect will not be generated to collar tie beam, and collar tie beam is still non-bearing component, only plays construction and reinforces Effect reduces the mechanical property requirements to collar tie beam.
Zinc-coated wire mesh sheet standard component is processed by door and window modulus, and matching is strong, and the factorial production, cost low-quality Measure readily available guarantee;Light-weight, not needing hanging device can be completed installation, and when placement can be made into coiled material, be easily portable and Storage, the zinc-plated corrosion resistance of steel wire surface are strong.
Grass seeds is placed in it when constructing wall mud gap, or plants the plant that creeps on wall side, metope, shape can be beautified At green screen, steel fabric sheet is that plant seeks connections with growth raising support;By the strong feature of soil water-retaining property in mortar joint, it is easy to plant It survives, and summer room temperature, energy conservation and environmental protection can be adjusted.
Detailed description of the invention
Fig. 1 is the irregular barnacle wall plane schematic diagram that reinforced mesh is reinforced;
Fig. 2 is the A-A sectional schematic diagram of barnacle wall described in Fig. 1;
Fig. 3 is wall B-B section connection schematic diagram;
Fig. 4 is Edge Enhancement window hole connection schematic diagram;
C1 partial enlargement diagram in Fig. 5 Fig. 2;
Fig. 6 is exterior wall steel fabric sheet standard component connection signal;
Fig. 7 is interior wall steel fabric sheet standard component connection signal;
Fig. 8 is C2 partial enlargement diagram in Fig. 4.
In attached drawing: 1, barnacle wall;2, zinc-coated wire mesh sheet standard component;3, stone cement strip footing;4, stone cement Collar tie beam;5, steel fibre mud;6, band steel band;7, reinforcing bar;8, rubber sheet gasket;9, reserved opening;10, high-strength bolt;11, expanding screw Bolt;12, floor beam.
Specific embodiment
To make the object, technical solutions and advantages of the present invention clearer, the technical solution below in the present invention carries out clear Chu is fully described by, it is clear that described embodiments are some of the embodiments of the present invention, instead of all the embodiments.It is based on Embodiment in the present invention, it is obtained by those of ordinary skill in the art without making creative efforts every other Embodiment shall fall within the protection scope of the present invention.
The present invention is to improve the ability that it resists eaerthquake damage comprising: by designing, preparation high-strength bolt, nut, light are round Reinforcing bar, rubber sheet gasket, band steel band, zinc-coated wire mesh sheet, cast-in-place barnacle collar tie beam and steel fibre etc., in which:
Reinforcing bar is placed in the barnacle collar tie beam central axis at floor, crosses wall and passes through from the gap between block, is not required to Vertical with metope, being easily propagated through with construction is advisable, and on the outside of wall face, all reinforcing bars are both passed through, and in inner side of outer wall, half It skims the upper floor in collar tie beam on reinforcing bar to go out to appear to floor, half level goes out to appear;And for interior wall, half steel in collar tie beam Muscle is upper in collar tie beam to be skimmed to upper floor to go out to appear, and level is in lower layer's flooring exposure head in collar tie beam for half reinforcing bar, and both ends are revealed Head goes out collar tie beam at least 150mm.Mortar in collar tie beam uses cement mixing, and barnacle collar tie beam side indent is lower than inside and outside metope about 30mm;
Four side of zinc-coated wire mesh sheet passes through the standard component that Edge Enhancement band steel band is formed, wherein the rubber sheet gasket in standard component Thickness 2mm, steel fabric sheet is fixed in factory, it is connected afterwards using frictional high-strength bolts every hole, nut is tightened;Steel wire The steel wire of mesh sheet is the zinc-coated wire of non-mopping, and 20 × 20mm of size of mesh opening is in prismatic, and zinc-coated wire diameter 4.5mm, market has It sells;
Basis uses barnacle cement strip footing, and by reinforcing bar buried foundation, reinforcing bar tenses zinc-coated wire mesh sheet standard component Preformed hole after tense, after bend to hook-shaped locking, placing concrete covers reinforcing bar, formed cover to reinforcement, avoid reinforcing bar Corrosion.
Reinforcing bar of appearing is tightened after embedded bar is passed through steel fabric sheet standard component reserving hole when construction, using same method Fixed even level steel fabric sheet standard component, is pulled to one layer of structure for basic steel fabric sheet, even level steel fabric sheet standard component, passes through Reinforcing bar appears after reserving hole, and it is hook-shaped to tighten into, successively fixes steel fabric sheet standard component, and touch ash at collar tie beam surface, ash Thickness, which is subject to, plasters to surface of wall, forms cover to reinforcement.
Short steel fibre, length of steel fiber 30mm are mixed in mud, the amount of mixing is carried out according to volume volume 1%, stirred with soil It mixes uniformly, the ability to fall off to improve preventing rain wash, and mortar joint layer anti-cracking ability can be improved.
Then it successively follows these steps to carry out:
Step 1: pouring stone strip footing, and width is 200mm wider than wall, and depth of section 300-500mm, intensity is not C20 should be lower than.The spiral of pre-buried 12mm in collar tie beam, bar spacing 150mm, on the outside of wall face, all reinforcing bars are worn It crosses, and skims the upper floor in collar tie beam in inner side of outer wall, half reinforcing bar and go out to appear in floor, half level goes out to appear;And it is right In half reinforcing bar in interior wall, collar tie beam, upper skim to upper floor is appeared out in collar tie beam, and half reinforcing bar keeps level simultaneously in collar tie beam Go out to appear in flooring, length of appearing 150mm.
Step 2: masonry panel mixes short steel fibre in mud used, and the amount of mixing is carried out according to volume volume 1%, to every After layer building wall, stone cement collar tie beam is built by detailing requiments at floor structure height.
Step 3: it after the concrete strength of collar tie beam reaches age, is appeared by reinforcing bar across zinc-coated wire mesh sheet standard After preformed hole on part, stretching wire mesh sheet standard component and the reinforcing bar that will appear are tightened into hook-shaped, pay attention to building by wall outer side When stone, vegetable seeds is placed in crust mud ash seam, the high 300mm of collar tie beam, places floor wooden frame on collar tie beam top, wooden frame is deep Enter no less than 200mm in wall;
Step 4: pay attention to adjusting window hole peripheral size line when tensioning assembly steel fabric sheet standard component, avoid steel fabric sheet Window hole is blocked, wherein opening holes size is slightly larger than window hole on steel fabric sheet, uses expansion bolt by steel fabric sheet mark afterwards Quasi- part is fixed, and adds band steel plate band, strip thickness 8mm, in strip intersection along 45 degree on the steel fabric sheet hole periphery opened up Angle constitutes indeformable rigid region under external force repeated action using four frame of periphery is formed after butt weld welding.
Step 5: after zinc-coated wire mesh sheet fixes, the Turf Culture or plantation is creeped plant on wall side between wall crack, Beautify metope, forms green screen;And because being that soil water-retaining property is strong in mortar joint, it is easy to plant survival, can adjusts in summer room Temperature, energy conservation and environmental protection.
In the present invention, the interior collar tie beam being arranged of wall wears collar tie beam embedded bar, zinc-coated wire mesh sheet standard component and steel fibre mud Slurry constitutes one for irregular stone-made house wall entirety and the new process of local strengthening.
Embodiment:
As shown in Fig. 1-Fig. 7, barnacle wall provided by the invention reinforces method, comprising:
By stone, soil and the short steel fibre, zinc-coated wire mesh sheet standard component 2, masonry stone for designing preparation barnacle wall 1 It is the raw material of cement strip footing 3, the raw material of steel fibre mud 5, steel band 6, reinforcing bar 7, rubber sheet gasket 8, high-strength bolt 10, swollen Swollen bolt 11, floor beam 12.Wherein:
The production method of zinc-coated wire mesh sheet standard component 2 are as follows: place inside and outside two layers of band steel band at zinc-coated wire mesh sheet edge 6, it is subsequently filled rubber sheet gasket 8, then pass through the mesh of bolt hole and zinc-coated wire mesh sheet by high-strength bolt 10, tightens high-strength spiral shell The nut of bolt 10 and be made, zinc-coated wire mesh sheet standard component 2 factory process produce, inside be provided with window reserved opening 9.
The reinforcement processing mode of window reserved opening 9 on steel fabric sheet are as follows: reserved opening 9 is slightly larger than window hole thereon, 9 periphery of steel fabric sheet reserved opening adds steel plate band steel band 6, and steel plate tape thickness 10mm is adopted in band steel band intersection along 45 degree of angles Four frame of periphery is formed after being welded with butt weld;Adjustment is consolidated after not blocking window using expansion bolt 11 and hole periphery wall It is fixed.
Then it successively follows these steps to carry out:
Step 1: stone cement strip footing 3 is built, width is 200mm wider than wall, deep 300-500mm, the stone poured Block cement ground beam intensity is not lower than C20, when masonry pre-buried diameter be 12mm reinforcing bar 7.
Step 2: building each layer wall in house, and short steel fibre is mixed in mud used, steel fibre mud 5 is formed, to every After layer building wall, stone cement collar tie beam 4 is built at floor structure absolute altitude degree, strength grade used is not lower than C20. In 4 inside embedded bar 7 of collar tie beam, bar spacing 150mm, for the wall outer side of exterior wall, the equal level of all reinforcing bars 7 is pierced by, and It skims the upper floor in collar tie beam for inner side of outer wall, on half reinforcing bar 7 to go out to appear in floor, half level goes out to appear;And for Interior wall, half reinforcing bar 7 is upper in collar tie beam in collar tie beam skims to upper floor to go out to appear, and half reinforcing bar 7 keeps level simultaneously in collar tie beam Go out to appear in flooring, length of appearing 150mm;
Step 3: floor beam 12, floor beam can be placed on collar tie beam top after construction intensity by reaching after stone cement collar tie beam 4 12 go deep into no less than 200mm in wall;
Step 4: it for exterior wall lateral surface, is appeared by embedded bar 7 in stone cement strip footing 3 across zinc-plated It tightens after preformed hole on steel fabric sheet standard component 2, even level embedded bar 7 is appeared across zinc-coated wire using same method Mesh sheet standard component 2, which tenses and tightens reinforcing bar 7, appears into hook-shaped fixation afterwards, then basal layer zinc-coated wire mesh sheet 2, two layers of structure are plated Zinc steel fabric sheet standard component 2 is tightened at one layer of cement collar tie beam 4 of structure, and reinforcing bar 7 is passed through junction to galvanized steel wire netting together Reinforcing bar is tightened after the preformed hole of piece standard component 2 to appear and bend to hook-shaped locking, completes one layer of structure, two layers of reinforcement;Again according to This method successively completes the reinforcement construction of other each structure sheafs.
Step 5: for inner side of outer wall face and interior wall, then directly zinc-coated wire mesh sheet standard component 2 is spread in This floor It is good, be taped against at floor collar tie beam 4 thereon, under be taped against at floor upper surface.The reinforcing bar 7 in lower layer house is appeared across close to floor It is tightened after bottom row's preformed hole of the zinc-coated wire mesh sheet standard component 2 of upper surface, the reinforcing bar 7 at collar tie beam 4 is appeared across zinc-coated wire It is tightened after the top row preformed hole of mesh sheet standard component 2, that is, completes the assembly of interior wall zinc-coated wire mesh sheet standard component 2.
Step 6: pay attention to adjusting window hole peripheral size line when tensioning assembly zinc-coated wire mesh sheet standard component 2, what is opened up 9 periphery of reserved opening adds band steel band 6, band steel band 6 with a thickness of 8mm, use butt weld along 45 degree of angles in strip intersection Four frame of periphery is formed after welding;Adjustment zinc-coated wire mesh sheet avoids blocking window hole, and wherein galvanized steel wire netting on piece opens up reserved Hole 9, size is slightly larger than window hole, and passes through the pre- of the band steel band 6 on zinc-coated wire mesh sheet standard component 2 using expansion bolt 11 It boxes out and is fixed with periphery wall behind hole, wherein 11 arranged for interval of expansion bolt, door opening reserved opening processing mode of studying in the same school is identical.
Step 7: plastering outside stone cement collar tie beam 4, in the external placing concrete of stone cement strip footing 3, lid Firmly reinforcing bar 7 is appeared, and forms cover to reinforcement;Exterior wall inner surface and 4 processing mode of interior wall collar tie beam are identical, but right with exterior wall Reinforcing bar 7 above interior wall floor beam 12 be bent into it is hook-shaped after, the abutting metope of reinforcing bar 7 is socketed, using coat of plaster as stretching The protective layer of the reinforcing bar 7 of metope out.The plant that creeps is planted on exterior wall side, beautifies metope, forms green screen;And because mortar joint is Soil water-retaining property is strong, is easy to plant survival, can adjust summer room temperature, energy conservation and environmental protection.
Present invention is particularly suitable for the agriculture room exterior walls that the irregular stone built using mud is built.
Finally, it should be noted that the above embodiments are merely illustrative of the technical solutions of the present invention, rather than its limitations;Although Present invention has been described in detail with reference to the aforementioned embodiments, those skilled in the art should understand that: it still may be used To modify the technical solutions described in the foregoing embodiments or equivalent replacement of some of the technical features; And these are modified or replaceed, technical solution of various embodiments of the present invention that it does not separate the essence of the corresponding technical solution spirit and Range.

Claims (5)

1. a kind of barnacle wall reinforces method characterized by comprising
Step 1: it builds stone cement strip footing (3), width is 200mm wider than wall, deep 300-500mm;
Step 2: building each layer bearing wall in house, and short steel fibre is mixed in mud used, is formed steel fibre mud (5), to After every layer of building wall, it is close to build stone cement collar tie beam (4) on the downside of floor beam (12), in stone cement collar tie beam (4) Portion's embedded bar (7), reinforcing bar (7) spacing 150mm;For the wall outer side of exterior wall, all reinforcing bars (7) are both passed through, and for outer Side within the walls skims the upper floor in collar tie beam on half reinforcing bar (7) and goes out to appear in floor, and half level goes out to appear;And for interior wall, Half reinforcing bar (7) is upper in collar tie beam in collar tie beam skims to upper floor to go out to appear, half reinforcing bar in collar tie beam level in lower layer's flooring It appears out, length of appearing 150mm;
Step 3: floor beam can be placed on stone cement collar tie beam (4) top after construction intensity by reaching after stone cement collar tie beam (4) (12), floor beam (12) gos deep into no less than 200mm in wall;
Step 4: for exterior wall alien invasion, embedded bar (7) appears across zinc-plated in stone cement strip footing (3) It tightens after preformed hole on steel fabric sheet standard component (2), even level embedded bar (7) is appeared across zinc-plated using same method Steel fabric sheet standard component (2) tense and tighten reinforcing bar (7) appear into it is hook-shaped after it is fixed, then by basal layer zinc-coated wire mesh sheet standard Two layers of part (2), structure zinc-coated wire mesh sheet standard component (2) are tightened at one layer of stone cement collar tie beam (4) of structure, by reinforcing bar (7) Reinforcing bar is tightened after preformed hole of the junction to zinc-coated wire mesh sheet standard component (2) together to appear and bend to hook-shaped locking, Complete one layer of structure, two layers of reinforcement;The reinforcement that method successively completes other each structure sheafs according to this again is constructed;
Step 5: for inner side of outer wall face and interior wall, then directly completing zinc-coated wire mesh sheet standard component (2) in This floor, Be taped against at floor stone cement collar tie beam (4) thereon, under be taped against at floor upper surface;The reinforcing bar (7) in lower layer house is appeared and is worn It is tightened after crossing bottom row's preformed hole of the zinc-coated wire mesh sheet standard component (2) close to floor upper surface, at stone cement collar tie beam (4) Reinforcing bar (7) is appeared to be tightened after the top row preformed hole of zinc-coated wire mesh sheet standard component (2), i.e. completion interior wall zinc-coated wire mesh sheet The assembly of standard component (2);
Step 6: plastering outside stone cement collar tie beam (4), in the external placing concrete of stone cement strip footing (3), lid Firmly reinforcing bar (7) appear, and form cover to reinforcement;Exterior wall inner surface and interior wall stone cement collar tie beam (4) processing mode and exterior wall Identical, but for the reinforcing bar (7) of interior wall floor beam (12) above be bent into it is hook-shaped after, need to by reinforcing bar (7) be close to metope draw It connects, the protective layer using coat of plaster as the reinforcing bar (7) for stretching out metope.
Step 7: the plant that creeps is planted on exterior wall side, beautifies metope, forms green screen.
2. the method according to claim 1, wherein the stone cement collar tie beam intensity poured is not less than C20, steel The diameter of muscle (7) is 12mm, and stone diameter is preferably less than 100mm.
3. the method according to claim 1, wherein the production method of zinc-coated wire mesh sheet standard component (2) are as follows: Inside and outside two layers of band steel band (6) is placed at zinc-coated wire mesh sheet edge, is subsequently filled rubber sheet gasket (8), then passes through high-strength bolt (10) Across bolt hole and the mesh of zinc-coated wire mesh sheet, tighten the nut of high-strength bolt (10) and be made, inside to be provided with window reserved Hole (9).
4. according to the method described in claim 3, it is characterized in that, tensioning needs to adjust when assembling zinc-coated wire mesh sheet standard component (2) Whole window hole peripheral size line adds band steel band (6), band steel band (6) thickness 10mm on reserved opening (9) periphery opened up, Band steel band (6) intersection is along 45 degree of angles using formation four frame of periphery after butt weld welding;Adjustment zinc-coated wire mesh sheet avoids hiding Window hole is kept off, wherein galvanized steel wire netting on piece opens up reserved opening (9), and size is slightly larger than window hole, and uses expansion bolt (11) it is fixed after passing through the reserving hole of the band steel band (6) on zinc-coated wire mesh sheet standard component (2) with periphery wall, wherein expanding Bolt (11) arranged for interval;Door opening schoolmate's reserved opening processing mode is identical.
5. the method according to claim 1, wherein in the steel fibre mud (5) short steel fibre the amount of mixing It is carried out according to volume volume 1%.
CN201611037733.8A 2016-11-23 2016-11-23 A kind of barnacle wall reinforcement method Expired - Fee Related CN106760593B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201611037733.8A CN106760593B (en) 2016-11-23 2016-11-23 A kind of barnacle wall reinforcement method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201611037733.8A CN106760593B (en) 2016-11-23 2016-11-23 A kind of barnacle wall reinforcement method

Publications (2)

Publication Number Publication Date
CN106760593A CN106760593A (en) 2017-05-31
CN106760593B true CN106760593B (en) 2019-01-29

Family

ID=58974762

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201611037733.8A Expired - Fee Related CN106760593B (en) 2016-11-23 2016-11-23 A kind of barnacle wall reinforcement method

Country Status (1)

Country Link
CN (1) CN106760593B (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114059791A (en) * 2021-11-12 2022-02-18 中国电建集团华东勘测设计研究院有限公司 Method for reinforcing and heightening circular structure pool by prestressed concrete technology

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2003155827A (en) * 2002-09-30 2003-05-30 Asahi Kasei Corp Future-extension residence
CN202081575U (en) * 2011-05-12 2011-12-21 河北农业大学 Ring beam made of dense mesh steel wire mesh
CN202689240U (en) * 2012-07-05 2013-01-23 西安建筑科技大学 Stone wall body
CN103046665A (en) * 2012-12-14 2013-04-17 北京工业大学 Insulating mortar strengthening layer rowlock wall with steel wire mesh for setting hose tooth constructional column and manufacturing method thereof

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2003155827A (en) * 2002-09-30 2003-05-30 Asahi Kasei Corp Future-extension residence
CN202081575U (en) * 2011-05-12 2011-12-21 河北农业大学 Ring beam made of dense mesh steel wire mesh
CN202689240U (en) * 2012-07-05 2013-01-23 西安建筑科技大学 Stone wall body
CN103046665A (en) * 2012-12-14 2013-04-17 北京工业大学 Insulating mortar strengthening layer rowlock wall with steel wire mesh for setting hose tooth constructional column and manufacturing method thereof
CN103046665B (en) * 2012-12-14 2015-06-17 北京工业大学 Insulating mortar strengthening layer rowlock wall with steel wire mesh for setting hose tooth constructional column and manufacturing method thereof

Also Published As

Publication number Publication date
CN106760593A (en) 2017-05-31

Similar Documents

Publication Publication Date Title
CN104405139B (en) Strengthening method for stone wall body
CN109811776B (en) Assembled lattice frame roof beam
KR100793985B1 (en) Method and structure of slope reinforce
KR100788934B1 (en) Greening segmental retaining wall
CN106760593B (en) A kind of barnacle wall reinforcement method
KR101078989B1 (en) Artificial rock wall for blasted slope and constructing method thereof
CN207706804U (en) Prefabricated assembled plant walls
CN207079605U (en) The prefabricated concrete gridiron of highway slope protection
CN113833293B (en) Method for reinforcing rubble wall by flat steel-reinforcing steel mesh
CN112359850B (en) Masonry protection structure of road engineering and construction method thereof
KR101229757B1 (en) Ecological waterway
CN211773858U (en) Landscape gabion retaining wall
KR101035411B1 (en) Retaining wall structure and method thereof
KR100476122B1 (en) Method vegetation afforesting soundproofed wall using of vegetation planter
RU2672889C1 (en) Fence
KR101048499B1 (en) Four season vegetation loess sound proof wall and construction method using the same
KR20090033581A (en) Retaining wall of tree-planting soil and vegetated nailing method
CN204919575U (en) Road bed side slope protection U type net skeleton
CN206350368U (en) A kind of protected fruit trees energy-saving heliogreenhouse
KR101307403B1 (en) The slope reinforcement method using a blocks of natural stone texture
KR102548639B1 (en) Construction method of upper net binding type stone protection structure
KR101364260B1 (en) Wire-mesh retaining wall structure for natural planting
CN219352491U (en) Pavement tree pool structure capable of being constructed rapidly
KR20140016684A (en) Dome-shaped vinyl house
JP4012403B2 (en) Wall greening method

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20190129

Termination date: 20191123

CF01 Termination of patent right due to non-payment of annual fee