CN106759445A CN201710100004.0A CN201710100004A CN106759445A CN 106759445 A CN106759445 A CN 106759445A CN 201710100004 A CN201710100004 A CN 201710100004A CN 106759445 A CN106759445 A CN 106759445A
Authority
CN
China
Prior art keywords
steel
skirtboard
combined type
bucket foundation
cylindrical structure
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201710100004.0A
Other languages
Chinese (zh)
Inventor
郭耀华
张浦阳
丁红岩
练继建
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Tianjin University
Original Assignee
Tianjin University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Tianjin University filed Critical Tianjin University
Priority to CN201710100004.0A priority Critical patent/CN106759445A/en
Publication of CN106759445A publication Critical patent/CN106759445A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/32Foundations for special purposes
    • E02D27/42Foundations for poles, masts or chimneys
    • E02D27/425Foundations for poles, masts or chimneys specially adapted for wind motors masts
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/10Deep foundations
    • E02D27/18Foundations formed by making use of caissons

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Foundations (AREA)
  • Wind Motors (AREA)

Abstract

The invention belongs to offshore wind power foundation field, a kind of combined type bucket foundation with skirtboard and its construction method, including steel cylindrical structure, reinforced concrete canopy, armored concrete changeover portion are disclosed;The top cover outer rim of steel cylindrical structure is expanded in steel cylindrical structure and is welded with steel skirtboard;Reinforced concrete canopy bottom is connected with steel cylindrical structure using WELDING STUDS, and top pours with armored concrete changeover portion and is connected;Deadweight is passed sequentially through during construction to sink to sink up to steel skirtboard bottom enters sea bed with negative pressure, then is drawn water by the drinking-water pipe on the inside of steel skirtboard, increase the down force of combined type bucket foundation.Simple structure of the present invention, easy construction, low cost, can self-floating towing and negative pressure sinking, the increase of skirtboard can increase the antidumping and erosion resistibility when basis normally uses, and effectively improve the down force on basis, while reduce steel cartridge type basic internal soil and fill in developing.

Description

A kind of combined type bucket foundation with skirtboard and its construction method
Technical field
It is to be related to a kind of combined type tubular base of offshore wind farm specifically the invention belongs to offshore wind power foundation field Plinth and its construction method.
Background technology
At present, at sea in New Equipment Engineering such as offshore wind farm engineering, foundation structure is generally included:Single pile, tripod, conduit Posture basis, gravity foundation, negative pressure cylinder base and floating platform structure etc. are several.These bases generally need the large-scale equipment to carry out Transport and installation, cause costly when marine site is constructed, and the limited in one's ability of seafloor scour is resisted on above-mentioned basis.
Coastal waters foundation structure is usually faced with the souring of reciprocal ocean current, and wash away has necessarily to foundation structure bearing capacity The influence of degree.Therefore, conventional compound cylinder-shaped foundation structure how is improved, stronger antiscour and antidumping energy is made it have Power, is sea so as to farthest play the bearing capacity of foundation structure, it is ensured that safety and stability of the foundation structure during running An important step in foreign basic constructional design.
The content of the invention
Requirement in terms of anti-seafloor scour ability based on offshore wind power foundation structure, the invention provides a kind of band skirtboard Combined type bucket foundation and its construction method, the foundation construction is convenient, low cost, can self-floating towing and negative pressure sinking, skirtboard Antidumping and erosion resistibility of the increase when can increase basic normal use, and effectively improve the down force on basis, The soil plug development of steel cartridge type basic internal is reduced simultaneously.
In order to solve the above-mentioned technical problem, the present invention is achieved by following technical scheme:
A kind of combined type bucket foundation with skirtboard, including steel cylindrical structure, reinforced concrete canopy, armored concrete Changeover portion;
The top cover outer rim of the steel cylindrical structure is expanded in the steel cylindrical structure, the top of the steel cylindrical structure Lid outer rim is welded with the steel skirtboard extended downwardly by top cover;The steel cartridge type inside configuration is disposed with multiple subdivision plates, with Make the steel cylindrical structure that the sealing subdivision of multiple bottom openings is constituted with the subdivision plate;
The reinforced concrete canopy bottom is connected with the steel cylindrical structure using WELDING STUDS;The armored concrete Top cover arrangement has multiple drinking-water pipes, including drinking-water pipe corresponding to each sealing subdivision and corresponding to the steel skirtboard with it is described The uniform drinking-water pipe of annular section between steel cartridge type structure side wall;
The armored concrete changeover portion is poured and is connected to the reinforced concrete canopy top.
Preferably, a diameter of 10~50m of the steel cylindrical structure, wall thickness is 10~100mm.
Preferably, the cap diameter of the steel cylindrical structure is 1.2~2 times of base circle barrel diameter.
Preferably, the height of the steel skirtboard is the Sidewall Height of 0.1~0.5 times of the steel cylindrical structure.
Preferably, the sealing subdivision that the steel cylindrical structure is constituted with the subdivision plate is cellular subdivision structure, bag The six identical side subdivisions for including a regular hexagon subdivision at center and being uniformly arranged on around it;Regular hexagon subdivision and side The length of side of subdivision is impartial, is 0.25 times of the steel cartridge type diameter of movement.
Preferably, the height of the subdivision plate is identical with bucket foundation side wall, thickness and bucket foundation side wall It is identical.
Preferably, the diameter of the reinforced concrete canopy is identical with the cap diameter of steel cylindrical structure, be 10~ 50m;Thickness is 0.2~0.6m.
Preferably, the height of the armored concrete changeover portion is 5~10 meters, and thickness is 0.1~2m, and top surface diameter is less than Equal to basal diameter, and wall is arc concave shape curved surface, and the curvature of curved surface is 1/60~1/10.
Preferably, the armored concrete changeover portion is prestressed reinforced concrete construction, and deformed bar is disposed with inside it, The ratio of reinforcement is not less than 0.3%, and the tension stress of its deformed bar is not less than 0.75 times of reinforcement yielding stress.
The construction method of the above-mentioned combined type bucket foundation with skirtboard, is carried out in accordance with the following steps:
(1) will assemble in the combined type bucket foundation immigration water of tower and blower fan, its entirety is swum on the water surface;
(2) combined type bucket foundation transportation by driving support is navigated to specified job location, the sea bed to job location is tentatively put down It is whole;
(3) all drinking-water pipes on the reinforced concrete canopy are opened, combined type bucket foundation is passed through sinking of conducting oneself with dignity To sea bed;
(4) by the drinking-water pipe corresponding to the steel cylindrical structure to the steel cylindrical structure after deadweight sinks to stopping Inside is drawn water, and combined type bucket foundation is sunk by negative pressure and is continued to sink;
(5) when negative pressure sinks down into the steel skirtboard bottom into sea bed, then by corresponding to the steel skirtboard and institute State the auxiliary of the drinking-water pipe between steel cartridge type structure side wall to be drawn water, increase the down force of combined type bucket foundation;
(6) after combined type barrel-shaped foundation sinking is in place, total construction is finished.
The beneficial effects of the invention are as follows:
Combined type bucket foundation with skirtboard of the invention and its construction method, the simple compact, construction of the foundation structure is just Prompt quick, the increase of edge of foundation steel skirtboard effectively increases the heavy penetration force on basis, reduces basic internal soil plug height Development, at the same can also effectively improve basis resistance to capsizing and erosion resistibility, its installation process can self-floating towing and sinking, Sinking process does not need large scale equipment, with low cost, efficiency of construction is high the features such as.
Brief description of the drawings
Fig. 1 is the front view of the combined type bucket foundation with skirtboard provided by the present invention;
Fig. 2 is the upward view of the combined type bucket foundation with skirtboard provided by the present invention;
Fig. 3 is the front view of steel cylindrical structure;
Fig. 4 is the front view after the completion of the combined type bucket foundation construction with skirtboard provided by the present invention.
In figure:1st, armored concrete changeover portion;2nd, reinforced concrete canopy;3rd, steel skirtboard;4th, steel cylindrical structure;5、 Drinking-water pipe;6th, subdivision plate;7th, bucket foundation side wall.
Specific embodiment
For the content of the invention of the invention, feature and effect can be further appreciated that, following examples are hereby enumerated, and coordinate accompanying drawing Describe in detail as follows:
As shown in Figure 1 to Figure 3, a kind of combined type bucket foundation with skirtboard is present embodiments provided, is mainly mixed by reinforcing bar Solidifying soil changeover portion 1, reinforced concrete canopy 2, the part of steel cylindrical structure 4 three composition,
A diameter of 10~50m of steel cylindrical structure 4, wall thickness is 10~100mm.The top cover outer rim of steel cylindrical structure 4 Expand in bucket foundation side wall 7, the cap diameter of steel cylindrical structure 4 is 1.2~2 times of base circle barrel diameter.Steel The top cover outer rim of cylindrical structure 4 is welded with the steel skirtboard 3 extended downwardly by top cover, and the height of steel skirtboard 3 is 0.1~0.5 times The height of bucket foundation side wall 7, wall thickness is identical with bucket foundation side wall 7.
For the ease of foundation immersion leveling, multiple subdivision plates 6 are disposed with inside steel cylindrical structure 4, so that steel cartridge type Structure 4 constitutes the sealing subdivision of multiple bottom openings with subdivision plate 6.Preferably, steel cylindrical structure 4 constitutes honeybee with subdivision plate 6 Nest shape subdivision structure, including center a regular hexagon subdivision and six identical side subdivisions being uniformly arranged on around it. The length of side of regular hexagon subdivision and side subdivision is impartial, is 0.25 times of the diameter of steel cylindrical structure 4, as shown in Figure 2.Subdivision structure In seven subdivisions it is sealed against one another intact in addition to bottom opening, it is ensured that do not go here and there cabin each other, and each subdivision top is respectively The reserved pipeline for being provided with switch, for applying negative pressure in cabin respectively.The top of subdivision plate 6 and the weldering of the inner roof wall of steel cylindrical structure 4 Fixation is connect, the height of subdivision plate 6 is identical with bucket foundation side wall 7, and thickness is identical with bucket foundation side wall 7.
A diameter of 10~50m of reinforced concrete canopy 2, its diameter is identical with the cap diameter of steel cylindrical structure 4.Steel The thickness range of choice of reinforced concrete top cover 2 is in 0.2~0.6m.The one-time-concreting of reinforced concrete canopy 2 is molded, and overall arrangement of reinforcement Rate is not less than 0.3%.
The top of reinforced concrete canopy 2 is poured with armored concrete changeover portion 1 and is connected, and bottom is adopted with steel cylindrical structure 4 Connected with WELDING STUDS.13 drinking-water pipes 5 are disposed with reinforced concrete canopy 2, wherein corresponding to the seven of steel cylindrical structure 4 Individual subdivision is respectively arranged with one, and six are evenly equipped with corresponding to the annular section between bucket foundation side wall 7 and steel skirtboard 3. A diameter of 20~200mm of drinking-water pipe 5, its top is piercing in reinforced concrete canopy 2, bottom and extends to steel cylindrical structure 4 It is internal.
The concrete structure of armored concrete changeover portion 1 is not limited, it is preferred to use the armored concrete changeover portion of curved face type 1, it is highly 5~10 meters, and thickness is 0.1~2m, and top surface diameter is less than or equal to basal diameter, and wall is bent arc concave shape Face, the curvature of curved surface is 1/60~1/10.Armored concrete changeover portion 1 is prestressed reinforced concrete construction, is disposed with inside it pre- Stress reinforcing bar, the ratio of reinforcement is not less than 0.3%, and the tension stress of its deformed bar is not less than 0.75 times of reinforcement yielding stress.
Present invention also offers the construction method of the above-mentioned combined type bucket foundation with skirtboard, carry out in accordance with the following steps:
A. land fabrication steel cylindrical structure 4, in the interior welds subdivision plate 6 of steel cylindrical structure 4, in steel cylindrical structure 4 top cover outer rim welding steel skirtboard 3;
B. on the top of steel cylindrical structure 4 by the use of thin-walled profiled sheet is as the template of reinforced concrete canopy 2 and arranges Reinforcing bar, pouring reinforcement concrete top cover 2, and in the reserved connection steel with armored concrete changeover portion 1 of reinforced concrete canopy 2 Muscle;
C. reinforced concrete canopy 2 is connected with steel cylindrical structure 4 with WELDING STUDS, while in reinforced concrete canopy 2 Upper installation drinking-water pipe 5, and air-tight test is carried out with the combining structure of steel cylindrical structure 4 to reinforced concrete canopy 2;
D. after air-tightness meets the requirements, the template simultaneously assembling reinforcement of arrangement armored concrete changeover portion 1 carries out reinforcing bar and mixes The concreting of solidifying soil changeover portion 1;
E. after the construction of armored concrete changeover portion 1 is completed and reaches design strength requirement, then tower and blower fan are assembled;
F. the combined type bucket foundation that tower and blower fan will be assembled using crane is moved into water, by combined type bucket foundation Self-buoyancy makes its entirety swim on the water surface;
G. combined type bucket foundation is dragged to specified job location using towboat, while being carried out just to the sea bed of job location Step is smooth;
H. all drinking-water pipes 5 on reinforced concrete canopy 2 are opened, combined type bucket foundation is sunk down into sea by deadweight Bed;Deadweight extracts water unnecessary in steel cylindrical structure 4 out after sinking to stopping by the drinking-water pipe 5 corresponding to steel cylindrical structure 4, Realize producing negative pressure i.e. negative pressure sinking watching in steel cylindrical structure 4 by the extraction of water body;
Reinforced concrete canopy 2 and sea bed plane holding level should be made in sinking watching, if combined type bucket foundation occurs During inclination, pressure carries out leveling in the cabins different to the applying of each subdivision by presenting control system;
I. when negative pressure sinks down into the bottom of steel skirtboard 3 into sea bed, it is further added by by corresponding to bucket foundation side wall 7 and steel Drinking-water pipe 5 between matter skirtboard 3 is drawn water, and increases the down force of combined type bucket foundation;
J. after combined type barrel-shaped foundation sinking is in place, total construction is finished, as shown in Figure 4.
Although being described to the preferred embodiments of the present invention above in conjunction with accompanying drawing, the invention is not limited in upper The specific embodiment stated, above-mentioned specific embodiment is only schematical, be not it is restricted, this area it is common Technical staff in the case of present inventive concept and scope of the claimed protection is not departed from, may be used also under enlightenment of the invention To make the specific conversion of many forms, these are belonged within protection scope of the present invention.

Claims (10)

1. a kind of combined type bucket foundation with skirtboard, it is characterised in that including steel cylindrical structure, reinforced concrete canopy, Armored concrete changeover portion;
The top cover outer rim of the steel cylindrical structure is expanded in outside the steel cylindrical structure, the top cover of the steel cylindrical structure Edge is welded with the steel skirtboard extended downwardly by top cover;The steel cartridge type inside configuration is disposed with multiple subdivision plates, so that institute State the sealing subdivision that steel cylindrical structure constitutes multiple bottom openings with the subdivision plate;
The reinforced concrete canopy bottom is connected with the steel cylindrical structure using WELDING STUDS;The reinforced concrete canopy Multiple drinking-water pipes are disposed with, including the drinking-water pipe of subdivision is sealed and corresponding to the steel skirtboard and the steel corresponding to each The uniform drinking-water pipe of annular section between the wall of cylindrical structure side;
The armored concrete changeover portion is poured and is connected to the reinforced concrete canopy top.
2. a kind of combined type bucket foundation with skirtboard according to claim 1, it is characterised in that the steel cartridge type knot A diameter of 10~50m of structure, wall thickness is 10~100mm.
3. a kind of combined type bucket foundation with skirtboard according to claim 1, it is characterised in that the steel cartridge type knot The cap diameter of structure is 1.2~2 times of base circle barrel diameter.
4. a kind of combined type bucket foundation with skirtboard according to claim 1, it is characterised in that the steel skirtboard Highly it is the Sidewall Height of 0.1~0.5 times of the steel cylindrical structure.
5. a kind of combined type bucket foundation with skirtboard according to claim 1, it is characterised in that the steel cartridge type knot The sealing subdivision that structure and the subdivision plate are constituted is cellular subdivision structure, including the regular hexagon subdivision at center and uniform It is arranged at six identical side subdivisions around it;The length of side of regular hexagon subdivision and side subdivision is impartial, is the steel cartridge type 0.25 times of diameter of movement.
6. a kind of combined type bucket foundation with skirtboard according to claim 1, it is characterised in that the height of the subdivision plate Degree is identical with bucket foundation side wall, and thickness is identical with bucket foundation side wall.
7. a kind of combined type bucket foundation with skirtboard according to claim 1, it is characterised in that the armored concrete The diameter of top cover is identical with the cap diameter of steel cylindrical structure, is 10~50m;Thickness is 0.2~0.6m.
8. a kind of combined type bucket foundation with skirtboard according to claim 1, it is characterised in that the armored concrete The height of changeover portion is 5~10 meters, and thickness is 0.1~2m, and top surface diameter is less than or equal to basal diameter, and wall is in arc Concave curved surface, the curvature of curved surface is 1/60~1/10.
9. a kind of combined type bucket foundation with skirtboard according to claim 1, it is characterised in that the armored concrete Changeover portion is prestressed reinforced concrete construction, and deformed bar is disposed with inside it, and the ratio of reinforcement is not less than 0.3%, its prestress steel The tension stress of muscle is not less than 0.75 times of reinforcement yielding stress.
10. a kind of construction method of combined type bucket foundation as any one of claim 1-9 with skirtboard, its feature exists In carrying out in accordance with the following steps:
(1) will assemble in the combined type bucket foundation immigration water of tower and blower fan, its entirety is swum on the water surface;
(2) combined type bucket foundation transportation by driving support is navigated to specified job location, the sea bed of job location is carried out preliminary smooth;
(3) all drinking-water pipes on the reinforced concrete canopy are opened, combined type bucket foundation is sunk down into sea by deadweight Bed;
(4) by the drinking-water pipe corresponding to the steel cylindrical structure to the steel cartridge type inside configuration after deadweight sinks to stopping Draw water, combined type bucket foundation is sunk by negative pressure and continue to sink;
(5) when negative pressure sinks down into the steel skirtboard bottom into sea bed, then by corresponding to the steel skirtboard and the steel Drinking-water pipe auxiliary between the wall of cylindrical structure side processed is drawn water, and increases the down force of combined type bucket foundation;
(6) after combined type barrel-shaped foundation sinking is in place, total construction is finished.
CN201710100004.0A 2017-02-23 2017-02-23 A kind of combined type bucket foundation with skirtboard and its construction method Pending CN106759445A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710100004.0A CN106759445A (en) 2017-02-23 2017-02-23 A kind of combined type bucket foundation with skirtboard and its construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710100004.0A CN106759445A (en) 2017-02-23 2017-02-23 A kind of combined type bucket foundation with skirtboard and its construction method

Publications (1)

Publication Number Publication Date
CN106759445A true CN106759445A (en) 2017-05-31

Family

ID=58960074

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710100004.0A Pending CN106759445A (en) 2017-02-23 2017-02-23 A kind of combined type bucket foundation with skirtboard and its construction method

Country Status (1)

Country Link
CN (1) CN106759445A (en)

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107740436A (en) * 2017-09-28 2018-02-27 天津大学 A kind of three floating drum buoyancy tank combined type foundation structures of sea and its construction method
CN109356797A (en) * 2018-12-28 2019-02-19 北京天杉高科风电科技有限责任公司 Tower structure, offshore wind turbine and its installation method
CN109537621A (en) * 2018-12-19 2019-03-29 天津大学 A kind of combined type sea windward electricity bucket foundation
CN109930621A (en) * 2019-04-19 2019-06-25 中交第一航务工程勘察设计院有限公司 For the cylinder-shaped foundation structure with water pocket in geological prospecting platform
CN110004968A (en) * 2019-03-28 2019-07-12 天津大学 A kind of offshore wind farm cylindrical foundation reinforcing method
CN110158640A (en) * 2019-06-12 2019-08-23 长江勘测规划设计研究有限责任公司 Constructing structure and construction method are built in offshore wind farm bucket foundation water
CN110331734A (en) * 2019-07-05 2019-10-15 天津大学前沿技术研究院 A kind of cylinder-shaped foundation structure excavates offshore construction method in advance
CN114809063A (en) * 2022-02-28 2022-07-29 上海勘测设计研究院有限公司 Multi-compartment composite cylindrical foundation and construction method thereof
CN115045323A (en) * 2022-07-11 2022-09-13 天津大学 Geopolymer air film concrete suction bucket foundation and construction method thereof

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH11209996A (en) * 1998-01-27 1999-08-03 Ohbayashi Corp Footing structure of cylindrical towery structure
EP2236676A1 (en) * 2009-03-25 2010-10-06 Tiefbau-GmbH "Unterweser" Foundation for a wind turbine
EP2366767A2 (en) * 2010-03-19 2011-09-21 Merck Patent GmbH Electrically conductive floor polish
CN102877484A (en) * 2012-09-11 2013-01-16 天津大学 Steel-concrete composite cylinder-type foundation structure and construction method thereof
CN103938650A (en) * 2014-04-10 2014-07-23 天津大学 Foundation of cellular subdivision structures
CN103981891A (en) * 2014-05-29 2014-08-13 成都城电电力工程设计有限公司 Excavation foundation and construction method for same
CN104594377A (en) * 2015-01-19 2015-05-06 天津港航工程有限公司 Steel cylinder type foundation structure of offshore wind turbine
CN105401577A (en) * 2014-09-10 2016-03-16 天津市海王星海上工程技术股份有限公司 Suction type pile shoe suitable for self-lifting platform and mounting method

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH11209996A (en) * 1998-01-27 1999-08-03 Ohbayashi Corp Footing structure of cylindrical towery structure
EP2236676A1 (en) * 2009-03-25 2010-10-06 Tiefbau-GmbH "Unterweser" Foundation for a wind turbine
EP2366767A2 (en) * 2010-03-19 2011-09-21 Merck Patent GmbH Electrically conductive floor polish
CN102877484A (en) * 2012-09-11 2013-01-16 天津大学 Steel-concrete composite cylinder-type foundation structure and construction method thereof
CN103938650A (en) * 2014-04-10 2014-07-23 天津大学 Foundation of cellular subdivision structures
CN103981891A (en) * 2014-05-29 2014-08-13 成都城电电力工程设计有限公司 Excavation foundation and construction method for same
CN105401577A (en) * 2014-09-10 2016-03-16 天津市海王星海上工程技术股份有限公司 Suction type pile shoe suitable for self-lifting platform and mounting method
CN104594377A (en) * 2015-01-19 2015-05-06 天津港航工程有限公司 Steel cylinder type foundation structure of offshore wind turbine

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
BIENEN B, GAUDIN C, CASSIDY M J, ET AL: "Numerical modelling of a hydrid skirted foundation under combined loading", 《COMPUTER AND GEOTECHNICS》 *
丁红岩等: "海上风电大尺度筒型基础分舱优化设计", 《航海工程》 *

Cited By (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107740436A (en) * 2017-09-28 2018-02-27 天津大学 A kind of three floating drum buoyancy tank combined type foundation structures of sea and its construction method
CN109537621A (en) * 2018-12-19 2019-03-29 天津大学 A kind of combined type sea windward electricity bucket foundation
CN109356797A (en) * 2018-12-28 2019-02-19 北京天杉高科风电科技有限责任公司 Tower structure, offshore wind turbine and its installation method
CN110004968A (en) * 2019-03-28 2019-07-12 天津大学 A kind of offshore wind farm cylindrical foundation reinforcing method
CN109930621A (en) * 2019-04-19 2019-06-25 中交第一航务工程勘察设计院有限公司 For the cylinder-shaped foundation structure with water pocket in geological prospecting platform
CN110158640A (en) * 2019-06-12 2019-08-23 长江勘测规划设计研究有限责任公司 Constructing structure and construction method are built in offshore wind farm bucket foundation water
CN110331734A (en) * 2019-07-05 2019-10-15 天津大学前沿技术研究院 A kind of cylinder-shaped foundation structure excavates offshore construction method in advance
CN110331734B (en) * 2019-07-05 2021-01-12 天津大学前沿技术研究院 Cylindrical foundation structure pre-excavation offshore construction method
CN114809063A (en) * 2022-02-28 2022-07-29 上海勘测设计研究院有限公司 Multi-compartment composite cylindrical foundation and construction method thereof
CN115045323A (en) * 2022-07-11 2022-09-13 天津大学 Geopolymer air film concrete suction bucket foundation and construction method thereof

Similar Documents

Publication Publication Date Title
CN106906839A (en) A kind of combined type bucket foundation with skirtboard and its construction method
CN106759445A (en) A kind of combined type bucket foundation with skirtboard and its construction method
CN106836265A (en) A kind of gravity type bucket foundation with skirtboard and its construction method
CN103205980A (en) Large-diameter mono-pile foundation of offshore wind turbine and construction method of large-diameter mono-pile foundation
CN106759430B (en) A kind of wind-powered electricity generation complete machine construction method of three bucket foundations and concrete support structure
CN110397069A (en) A kind of more cabin combination foundation structures of the monotubular with support construction and its construction method
CN110158638A (en) Offshore wind farm composite tube foundation construction structure and construction method
CN106638662A (en) Three-bucket-foundation combined foundation structure system of concrete supporting structure
CN106522263B (en) A kind of wind-powered electricity generation complete machine construction method of four bucket foundations and concrete support structure
CN102322074A (en) A kind of jacket foundation structure and job practices
CN110155264B (en) Marine fan composite cylinder foundation towing structure and towing method
CN110453715A (en) Can gas-liquid displacement combined type cartridge type jacket frame foundation structure and its construction method
CN102286986B (en) Five-horse foundation structure and construction method thereof
CN104594343B (en) A kind of assembled stake and its construction method
CN207987950U (en) Four floating drum buoyancy tank foundation structures on a kind of combined type sea
CN106638661A (en) Four-cylindrical-foundation combined foundation structure system of concrete support structure
CN214116682U (en) Offshore wind power suction barrel-single pile combined foundation
CN215594101U (en) Truss combined type steel-concrete cylindrical wind power foundation
CN216185899U (en) Pontoon connection structure for offshore wind turbine generator system
CN212715142U (en) Movable water inlet with head positioned by upright post and float bowl
CN209686386U (en) A kind of intectate waters steel-pipe pile can pull out anchor structure
CN213038418U (en) Novel all-steel cylindrical foundation structure for offshore wind power
CN210827534U (en) Integral installation offshore wind power multi-pile foundation structure system
CN211547794U (en) Multi-cylinder jacket foundation connected by grouting
CN210766850U (en) Ring cylinder reinforced concrete combined foundation structure

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20170531

RJ01 Rejection of invention patent application after publication