CN106759364B - Deep basal pit bottom plate step-by-step construction method - Google Patents

Deep basal pit bottom plate step-by-step construction method Download PDF

Info

Publication number
CN106759364B
CN106759364B CN201611063939.8A CN201611063939A CN106759364B CN 106759364 B CN106759364 B CN 106759364B CN 201611063939 A CN201611063939 A CN 201611063939A CN 106759364 B CN106759364 B CN 106759364B
Authority
CN
China
Prior art keywords
deep basal
basal pit
catchment area
interim
processing unit
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201611063939.8A
Other languages
Chinese (zh)
Other versions
CN106759364A (en
Inventor
李焱熠
黄捷
彭光仲
谭明偲
徐礼全
谢光勇
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Metallurgical Construction Engineering Group Co Ltd
Original Assignee
China Metallurgical Construction Engineering Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Metallurgical Construction Engineering Group Co Ltd filed Critical China Metallurgical Construction Engineering Group Co Ltd
Priority to CN201611063939.8A priority Critical patent/CN106759364B/en
Publication of CN106759364A publication Critical patent/CN106759364A/en
Application granted granted Critical
Publication of CN106759364B publication Critical patent/CN106759364B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/02Foundation pits
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D19/00Keeping dry foundation sites or other areas in the ground
    • E02D19/06Restraining of underground water
    • E02D19/10Restraining of underground water by lowering level of ground water
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D31/00Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution
    • E02D31/02Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution against ground humidity or ground water

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Hydrology & Water Resources (AREA)
  • Environmental & Geological Engineering (AREA)
  • Sewage (AREA)

Abstract

The invention discloses a kind of deep basal pit bottom plate step-by-step construction methods, and deep basal pit bottom is divided into catchment area and non-catchment area, is included the following steps:S1, the first interim processing unit that catchments is set in catchment area;S2, the construction of non-catchment area bottom cushion collect the water flowed into from waterproof of man breakthrough and catchmenting collection outside discharge deep basal pit in the non-catchment area bottom cushion work progress using the first interim processing unit that catchments;S3, the interim processing unit that catchments of setting second on the non-catchment area bottom cushion that construction is completed, and catchment area bottom cushion construction is carried out, the height of the bottom cushion of the catchment area is less than the bottom cushion of the non-catchment area;S4, deep basal pit construction of bottom plates, and corresponding position reserves third and catchments temporarily the water collecting part of processing unit and processing unit upper end of catchmenting temporarily positioned at third on the bottom cushion of catchment area;S5, water collecting part lower end third are catchmented processing unit closure construction temporarily.

Description

Deep basal pit bottom plate step-by-step construction method
Technical field
The present invention relates to a kind of construction method of deep foundation ditch, more particularly to a kind of deep basal pit bottom plate step-by-step construction method.
Background technology
Deep-foundation pit engineering refers to that cutting depth is more than 5m(Containing 5m)Foundation pit(Slot)Earth excavation, supporting, dewatering project, Though cutting depth is less than 5m, geological conditions, ambient enviroment and underground utilities complexity, or influence adjacent building(It constructs) The foundation pit of object safety(Slot)Earth excavation, supporting, dewatering project.
In the work progress of deep basal pit, deep basal pit waterproof of man leakage is frequently problem in construction, traditional Method is first to carry out waterproof of man leak stopping to carry out subsequent construction again, due to factors such as geology, operation, leakage cause complexity, often Time-consuming for plugging operation, and repeatedly, foundation pit is immersed in water for a long time, causes base plate of foundation pit that cannot construct, and the time of delay is longer for construction, Uncontrollable factor is more, and security risk is bigger, gently then influences the duration, or even can cause foundation pit collapse, causes serious safety accident.
Specific to refer to Fig. 1, after the completion of deep basal pit Guan Liang, in further digging process, it is existing that leakage occurs in waterproof of man As, the suitable bored concrete pile that seeps water flows into hole bottom, forms hole bottom water, and flowing water constantly causes hole bottom that can not carry out deep basal pit construction of bottom plates, If carrying out leak stopping to waterproof of man not in time, causes the water that waterproof of man is leaked or leaked to flow into deep basal pit bottom, cause in this way It catchments more, construction can not carry out continuing bottom construction, it is necessary to first to first waterproof of man leak stopping, then carry out bottom again Plate is constructed, and then time-consuming for plugging operation, seriously affects duration and construction efficiency.
Invention content
In view of the above shortcomings of the prior art, the technical problem to be solved by the present invention is to:One kind is provided to intercept water in foundation pit The deep basal pit bottom plate step-by-step construction method constructed to deep basal pit bottom plate in the case of curtain seepage, do not rest, being not to wait for.
In order to solve the above technical problems, one aspect of the present invention is:A kind of deep basal pit bottom plate substep is provided Deep basal pit bottom is divided into catchment area and non-catchment area, included the following steps by construction method:
S1, the first interim processing unit that catchments is set in catchment area;
S2, the construction of non-catchment area bottom cushion, in the non-catchment area bottom cushion work progress, face using first Shi Jishui processing units collect the water flowed into from waterproof of man breakthrough and catchmenting collection outside discharge deep basal pit;
S3, the interim processing unit that catchments of setting second on the non-catchment area bottom cushion that construction is completed, and catchment Region bottom cushion construction, the height of the bottom cushion of the catchment area are less than the bottom cushion of the non-catchment area;
S4, deep basal pit construction of bottom plates, and corresponding position reserves third and catchments temporarily processing on the bottom cushion of catchment area The water collecting part in portion and processing unit upper end of catchmenting temporarily positioned at third;
S5, the interim processing unit that catchments of setting the 4th on the non-catchment area deep basal pit bottom plate that construction is completed, then carry out Water collecting part lower end third is catchmented processing unit closure construction temporarily.
Further, the described first interim processing unit that catchments includes the first interim water collecting part, set on the described first interim collection The first suction pump, several first aqueducts in water portion and the first drainpipe, the diversion end of several first aqueducts with The breakthrough of waterproof of man is connected to, and water outlet is set in the first interim water collecting part, the first end and first of first drainpipe Suction pump connects, and water outlet will be for that will catchment outside discharge deep basal pit.
Further, the described second interim processing unit that catchments includes the be placed on the bottom cushion of the non-catchment area Two interim water collecting parts and first suction pump either the second suction pump, several first aqueducts or several second Aqueduct and first drainpipe or the second drainpipe.
Further, the third processing unit that catchments temporarily includes set on the catch pit lower end and the third that communicates therewith Interim water collecting part, first suction pump either third suction pump, several first aqueducts or several third aqueducts And first drainpipe or third drainpipe.
Further, the inner wall of the interim water collecting part of the third is located in the inner wall of the water collecting part, so that described An absolute altitude platform is formed between the top of the inner wall of the interim water collecting part of third and the bottom end of the inner wall of water collecting part.
Further, S4 steps specifically include:In catchment area, bottom cushion construction is completed and intensity satisfaction continues to apply After work requires, continue reinforcing bar binding and the template construction of bottom plate, the reserved space conduct on the bottom cushion of catchment area Third is catchmented temporarily processing unit and catchments processing unit upper end reserved space as water collecting part temporarily in third, then carries out deep base Hole underplate concrete pours.
Further, it catchments temporarily in third and is horizontally arranged with a ring seal plate in the middle part of processing unit, the annular is stopped The outer edge of water plate catchments embedded in the third on processing unit inner wall temporarily, and inward flange protrudes from the third and catchments temporarily processing Portion's inner wall.
Further, the section of the ring seal plate is turned under curved in both ends.
Further, the frame shape sealing to match with base plate configuration is provided in the upper surface of the deep basal pit bottom edge The lower end of plate, the frame shape seal plate is inserted on the bottom plate, and upper end protrudes from the upper surface of the bottom plate.
Further, the section of the frame shape seal plate is curved in both ends bent outward
The deep basal pit backplane construction method of the present invention is directed to the problem of background technology, in order to not influence construction Progress prevents foundation pit to be immersed in water for a long time, reduces security risk, we change traditional first waterproof of man leak stopping, rear bottom The method of plate construction, has invented deep basal pit bottom plate step-by-step construction method.First deep basal pit construction of bottom plates, then reprocesses waterproof of man Leakage, has reached the target for the duration that ensures safety, protects.The deep basal pit backplane construction method of the present invention is intercepted water curtain in deep basal pit In the case of curtain leakage, infiltration is effectively collected in the measures such as sump, aqueduct, dust-collecting bucket of scientific utilization deep basal pit, simultaneously Steel plate for sealing water is set, and fast and fractional carries out deep basal pit construction of bottom plates.Safety, economic, effective, reduction construction hidden danger, it is ensured that construction Duration.The deep basal pit backplane construction method of the present invention is according to deep basal pit design feature, using the catch pit of deep basal pit bottom, The measures such as dust-collecting bucket, aqueduct are set simultaneously and collect infiltration and draining, substep carries out construction of bottom plates, adds steel plate for sealing water guarantee Construction of bottom plates quality, base plate of foundation pit is impermeable after construction, meet design and operational requirement.
Description of the drawings
Fig. 1 is deep basal pit bottom water schematic diagram after waterproof of man leakage.
Fig. 2 is the plan view of deep basal pit.
Fig. 3 is the schematic diagram after deep basal pit bottom cushion construction of the present invention.
Fig. 4 is the schematic diagram after deep basal pit bottom plate catch pit cushion construction of the present invention.
Fig. 5 is the schematic diagram after deep basal pit construction of bottom plates of the present invention.
Fig. 6 is the schematic diagram after the completion of deep basal pit construction of bottom plates of the present invention.
Fig. 7 is that infiltration flows to schematic diagram in Fig. 6.
Specific implementation mode
Following will be combined with the drawings in the embodiments of the present invention, and technical solution in the embodiment of the present invention carries out clear, complete Site preparation describes, it is clear that described embodiments are only a part of the embodiments of the present invention, instead of all the embodiments.It is based on Embodiment in the present invention, it is obtained by those of ordinary skill in the art without making creative efforts every other Embodiment shall fall within the protection scope of the present invention.
Refer to Fig. 2 to Fig. 7, in specific example of the present invention, deep basal pit bottom plate bottom surface absolute altitude is -9.90m, plate top surface mark A height of -8.8m, deep basal pit inner wall size are 14m × 12m, and crater wall thickness is 500mm.Deep foundation pit supporting structure takes inner ring 44 The cast-in-situ bored pile of φ 900mm × 22m, outer ring are intercepted water curtain using 316 double deep cement-mixed piles of φ 500mm × 11m Curtain.Guan Liang is set in -4.5m in digging process, bottom plate sets water collecting part, water collecting part(Catch pit)Size is 1m × 1m, water collecting part bottom mark A height of -9.87m.
In deep basal pit bottom plate step-by-step construction method of the present invention, need deep basal pit bottom being divided into catchment area and non-collection Water area, the deep basal pit bottom plate step-by-step construction method include the following steps:
S1, the first interim processing unit that catchments is set in catchment area;
Deep pit digging first collects in the catchment area of deep basal pit bottom setting first temporarily to after meeting construction of bottom plates requirement Water-handling portion would, for collecting the water flowed into from waterproof of man breakthrough and catchmenting collection outside discharge deep basal pit.The present embodiment In, the described first interim processing unit that catchments includes the first interim water collecting part 101, in the described first interim water collecting part 101 First suction pump 102,103 and first drainpipe 104 of several first aqueducts, the diversion of several first aqueducts 103 End is connected to the breakthrough of waterproof of man, and water outlet is in the first interim water collecting part 101, and the of first drainpipe 104 One end is connect with the first suction pump 102, and water outlet will be for that will catchment outside discharge deep basal pit.
In the specific example, the first interim water collecting part 101 is first dug downwards by the deep basal pit bottom Interim catch pit, top end opening area are more than hole floor space, and hole bottom to top end opening forms slope.It is intelligible, it is described It can be in various embodiments any one that first interim water collecting part 101, which is not limited to the first interim catch pit, The container that kind can be filled with water.
S2, the construction of non-catchment area bottom cushion 11 utilize the in non-11 work progress of catchment area bottom cushion The one interim processing unit that catchments collects the water flowed into from waterproof of man breakthrough and catchmenting collection outside discharge deep basal pit;
In specific practice, the first interim catch pit is set in catchment area, it is corresponding to leak points connection according to waterproof of man Infiltration is led to the first interim catch pit by the first aqueduct 103 of quantity, and infiltration is collected, and the first suction pump 102 is used in combination to take out Water will be catchmented outside the discharge deep basal pit by the first drainpipe 104, and can lead to construction area drainage pipeline networks, make deep basal pit Non- 11 construction area of catchment area bottom cushion, can be to carry out the non-catchment area bottom of deep basal pit without immersion when catchment processing Plate bed course 11 is constructed, and in this example, non-11 absolute altitude of catchment area bottom cushion is -9.9m(Rice).
S3, the interim processing unit that catchments of setting second on the non-catchment area bottom cushion 11 that construction is completed, and collected Water area bottom cushion 12 is constructed, and the height of the catchment area bottom cushion 12 is less than the bottom cushion of the non-catchment area 11;
The described second interim processing unit that catchments include be placed on the bottom cushion 11 of the non-catchment area it is second interim Water collecting part 111 and first suction pump 102 either the second suction pump, several first aqueducts 103 or several 104 or second drainpipe of two aqueducts and first drainpipe.
In the present embodiment, the described second interim processing unit that catchments draws water including the second interim water collecting part 111, described first Pump 102, several first aqueducts 103 and first drainpipe 104 may not necessarily replace aqueduct, draining in this way Pipe and suction pump, it is only necessary to replace the second interim water collecting part 111 and its position, greatly save the construction time, improve Construction efficiency reduces cost.
In this specific embodiment, the described second interim water collecting part 111 is the steel dust-collecting bucket of an a diameter of 1.3m, directly Be placed on having constructed completion non-catchment area bottom cushion 11 on.
The non-catchment area bottom cushion of deep basal pit 11 has been constructed, intensity meets continue construction requirement after, it is non-what is constructed The steel dust-collecting bucket 1 that 1m3 is placed on catchment area bottom cushion 11, the water outlet of each first aqueduct 103 is put In dust-collecting bucket, the first suction pump 102 is put also in dust-collecting bucket, water is discharged outside foundation pit by the first drainpipe 104, is led to Construction area drainage pipeline networks makes bottom cushion 12 construction area in deep basal pit catchment area without immersion, carries out deep basal pit catchment area Bottom cushion 12 construct, in this example, bottom cushion 12 absolute altitude in catchment area is -10.7m.
S4, deep basal pit bottom plate 15 are constructed, and the reserved third in corresponding position is catchmented temporarily on catchment area bottom cushion 12 The water collecting part 13 of processing unit and processing unit upper end of catchmenting temporarily positioned at third;
The third processing unit that catchments temporarily includes catchmenting temporarily set on the catch pit lower end and the third that communicates therewith Portion 121, first suction pump 102 either third suction pump, several first aqueducts 103 or several third aqueducts And first drainpipe 104 or third drainpipe.
When for third suction pump, third aqueduct and third drainpipe, which can be by above-mentioned second Suction pump arranges aqueduct as the third suction pump, the second aqueduct as third, and the second drainpipe is as third drainpipe. New suction pump, aqueduct and drainpipe may be used as third suction pump, third aqueduct and/or third drainpipe.
The third of the present embodiment catchment temporarily processing unit include the interim water collecting part 121 of third, it is the first suction pump 102, several First aqueduct 103 and the first drainpipe 104.
In this specific embodiment, the interim water collecting part 121 of the third be reserve in catchment area bottom cushion 12 it On the second interim catch pit, the water collecting part 13 is catch pit on the described second interim catch pit.
In the present embodiment, after catchment area bottom cushion 12 constructs completion and intensity satisfaction continuation construction requirement, after The continuous reinforcing bar binding for carrying out bottom plate 15 and template construction, reserved space is interim as third on catchment area bottom cushion 12 It catchments and processing unit and catchments processing unit upper end reserved space temporarily as water collecting part 13 in third, then carry out deep basal pit bottom plate 15 concretings.Specific construction way is as follows:
It waits for that deep basal pit catchment area bottom cushion 12 has been constructed, after intensity meets continuation construction requirement, starts to carry out successively The reinforcing bar of bottom plate 15 is bound and template construction, reserves 600mm × 600mm below -9.87m absolute altitudes at position at the catchment area Depth is to the space of catchment area bottom cushion 12, as the second interim catch pit, by the first aqueduct 103, the first suction pump 102, interim catch pit continues to collect infiltration and draining the first drainpipe 104 concentration herein.And it is located at the second interim catch pit top Space to be preserved more than end -9.87m absolute altitudes is water collecting part 13(Catch pit), 13 size of water collecting part is 1000mm*1000mm.
In this step, the second interim catch pit is designed as size and is less than 13 size of water collecting part, its object is to:Described The inner wall of three interim water collecting parts 121 is located in the inner wall of the water collecting part 13, so that the interim water collecting part of the third 121 An absolute altitude platform 14 is formed between the top of inner wall and the bottom end of the inner wall of water collecting part 13.The second interim catch pit is blocked to be continuous When, provide an absolute altitude, it is not necessary to determine repeatedly and block height, improve working efficiency.It in other examples, can also be direct By the interim water collecting part of third 121 be designed and sized to it is identical as the size of water collecting part 13.
In this step, in order to ensure being well connected water-tight with follow-up concreting, in deep basal pit bottom plate 15 with after Seal plate is arranged in the middle part of interim catch pit below deep basal pit bottom surface in continuous foundation pit walls faying face setting seal plate, then carries out deep 15 concreting of base plate of foundation pit.Specific design method is as follows:
It catchments temporarily in third and is horizontally arranged with a ring seal plate 161, the ring seal plate 161 in the middle part of processing unit Outer edge catchment temporarily on processing unit inner wall embedded in the third, inward flange protrudes from the third and catchments in processing unit temporarily Wall.The section of the ring seal plate 161 is turned under curved in both ends, and specially both ends are downwardly and outwardly bent.
The frame shape seal plate to match with 15 shape of bottom plate is provided in the upper surface at 15 edge of deep basal pit bottom plate 162, the lower end of the frame shape seal plate 162 is inserted on the bottom plate 15, and upper end protrudes from the upper surface of the bottom plate 15, described The section of frame shape seal plate 162 is curved in both ends bent outward, and specially both ends are outside and are bent in the opposite direction.
S5, the interim processing unit that catchments of setting the 4th on the non-catchment area deep basal pit bottom plate that construction is completed, then carry out 13 lower end third of water collecting part is catchmented processing unit closure construction temporarily.
That is, being closed below 13 bottom surface of water collecting part.It has constructed in deep basal pit bottom plate 15, intensity, which meets, continues construction requirement Afterwards, 1.3 meters of steel dust-collecting bucket is placed on deep basal pit bottom plate 15 again, by the first aqueduct 103, the first suction pump 102, First drainpipe 104, which is concentrated, to be continued to collect infiltration and draining in this steel dust-collecting bucket, to form the 4th interim processing unit that catchments. Then it toward the 15 following casting concretes of catch pit bottom surface -9.87m of deep basal pit bottom plate, completes entire deep basal pit bottom plate 15 and constructs.
After the completion of deep basal pit bottom plate 15 is constructed, entire deep basal pit enters comparatively safe, stable state.Then curtain is carried out again Seepage treatment and the construction of deep basal pit subsequent content.
The invention solves the problems, such as that in the case of deep basal pit waterproof of man leakage deep basal pit construction of bottom plates can not be carried out, pushes away Into construction speed, safe construction ensure that, obtain good economic and social benefit benefit, there have to similar situation to be very good Popularization and reference value.The present invention utilizes the catch pit of deep basal pit bottom and the interim collection of setting according to deep basal pit design feature Bucket Fraction collection seeps water, and carries out construction of bottom plates by region substep, while adding steel plate for sealing water in concrete seam and ensureing Construction quality, it is ensured that after construction base plate of foundation pit is impermeable.
It these are only embodiments of the present invention, be not intended to limit the scope of the invention, it is every to utilize the present invention Equivalent structure or equivalent flow shift made by specification and accompanying drawing content is applied directly or indirectly in other relevant technologies Field is included within the scope of the present invention.

Claims (10)

1. deep basal pit bottom is divided into catchment area and non-catchment area by a kind of deep basal pit bottom plate step-by-step construction method, packet Include following steps:
S1, the first interim processing unit that catchments is set in catchment area;
S2, the construction of non-catchment area bottom cushion utilize the first interim collection in the non-catchment area bottom cushion work progress Water-handling portion would collects the water flowed into from waterproof of man breakthrough and catchmenting collection outside discharge deep basal pit;
S3, the interim processing unit that catchments of setting second on the non-catchment area bottom cushion that construction is completed, and carry out catchment area Bottom cushion is constructed, and the height of the bottom cushion of the catchment area is less than the bottom cushion of the non-catchment area;
S4, deep basal pit construction of bottom plates, and on the bottom cushion of catchment area corresponding position reserve third catchment temporarily processing unit with And the water collecting part for processing unit upper end of catchmenting temporarily positioned at third;
S5, the interim processing unit that catchments of setting the 4th on the non-catchment area deep basal pit bottom plate that construction is completed, then catchment Subordinate end third is catchmented processing unit closure construction temporarily.
2. deep basal pit bottom plate step-by-step construction method as described in claim 1, it is characterised in that:Described first interim processing of catchmenting Portion include the first interim water collecting part, the first suction pump in the described first interim water collecting part, several first aqueducts and The diversion end of first drainpipe, several first aqueducts is connected to the breakthrough of waterproof of man, and water outlet is faced set on first When water collecting part in, the first end of first drainpipe is connect with the first suction pump, water outlet for will catchment discharge deep basal pit Outside.
3. deep basal pit bottom plate step-by-step construction method as claimed in claim 2, it is characterised in that:Described second interim processing of catchmenting Portion includes the second interim water collecting part being placed on the bottom cushion of the non-catchment area and first suction pump or Either several second aqueducts and first drainpipe or the second draining of two suction pumps, several first aqueducts Pipe.
4. deep basal pit bottom plate step-by-step construction method as claimed in claim 2, it is characterised in that:The third is catchmented processing temporarily Portion includes drawing water set on the catch pit lower end and the interim water collecting part of third, first suction pump or the third that communicate therewith Pump, several first aqueducts either several third aqueducts and first drainpipe or third drainpipe.
5. deep basal pit bottom plate step-by-step construction method as claimed in claim 4, it is characterised in that:The interim water collecting part of third Inner wall is located in the inner wall of the water collecting part, so that the top of the inner wall of the interim water collecting part of the third and water collecting part is interior An absolute altitude platform is formed between the bottom end of wall.
6. deep basal pit bottom plate step-by-step construction method as described in claim 1, which is characterized in that S4 steps specifically include:Collecting The construction of water area bottom cushion is completed and after intensity satisfaction continuation construction requirement, and reinforcing bar binding and the mould of bottom plate are continued Plate is constructed, and reserved space catchments processing unit and in the interim catchment of third temporarily as third on the bottom cushion of catchment area Then reason portion upper end reserved space carries out deep basal pit underplate concrete and pours as water collecting part.
7. the deep basal pit bottom plate step-by-step construction method as described in any one of claim 1 to 6 claim, it is characterised in that: It catchments temporarily in third and is horizontally arranged with a ring seal plate in the middle part of processing unit, the outer edge of the ring seal plate is embedded in institute It states third to catchment temporarily on processing unit inner wall, inward flange protrudes from the third and catchments temporarily processing unit inner wall.
8. deep basal pit bottom plate step-by-step construction method as claimed in claim 7, it is characterised in that:The ring seal plate section Both ends are respectively bent downward.
9. deep basal pit bottom plate step-by-step construction method as claimed in claim 7, it is characterised in that:In the deep basal pit bottom edge Upper surface be provided with the frame shape seal plate to match with base plate configuration, the bottom plate is inserted into the lower end of the frame shape seal plate On, upper end protrudes from the upper surface of the bottom plate.
10. deep basal pit bottom plate step-by-step construction method as claimed in claim 9, it is characterised in that:The frame shape seal plate breaks Face is curved in both ends bent outward.
CN201611063939.8A 2016-11-28 2016-11-28 Deep basal pit bottom plate step-by-step construction method Active CN106759364B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201611063939.8A CN106759364B (en) 2016-11-28 2016-11-28 Deep basal pit bottom plate step-by-step construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201611063939.8A CN106759364B (en) 2016-11-28 2016-11-28 Deep basal pit bottom plate step-by-step construction method

Publications (2)

Publication Number Publication Date
CN106759364A CN106759364A (en) 2017-05-31
CN106759364B true CN106759364B (en) 2018-09-04

Family

ID=58901886

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201611063939.8A Active CN106759364B (en) 2016-11-28 2016-11-28 Deep basal pit bottom plate step-by-step construction method

Country Status (1)

Country Link
CN (1) CN106759364B (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112412472B (en) * 2020-11-09 2022-11-18 安徽省新路建设工程集团有限责任公司 Pipe-jacking working well wall reverse-acting system in soft soil area and construction method and application thereof

Family Cites Families (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100655384B1 (en) * 2004-07-13 2006-12-08 엄기형 Method of drain construction for basement
CN101705691B (en) * 2009-10-30 2011-07-20 南通建工集团股份有限公司 Construction method of dewatering well under foundation slab in foundation pit
CN102418347B (en) * 2011-09-27 2013-10-23 天津住宅集团建设工程总承包有限公司 Drainage construction method for blind drain and sump wells in deep foundation pit
CN204080839U (en) * 2014-11-05 2015-01-07 江苏省华建建设股份有限公司 A kind of Yield rainfall relation device
CN204370462U (en) * 2014-12-22 2015-06-03 中铁十九局集团轨道交通工程有限公司 Open-cut station water drainage of deep foundation pit system
CN104711994A (en) * 2015-01-27 2015-06-17 江苏省华建建设股份有限公司 Foundation pit deep well rainfall and plugging construction method
CN205205842U (en) * 2015-10-08 2016-05-04 中国建筑第八工程局有限公司 Local precipitation structure of deep basal pit

Also Published As

Publication number Publication date
CN106759364A (en) 2017-05-31

Similar Documents

Publication Publication Date Title
CN104131575B (en) A kind of karst height grows the leak stopping water discharge method of the stratum dam foundation
CN207314368U (en) Steel cofferdam waterproof/drainage structure
CN203947484U (en) Foundation pit drainage and circulating water utilization system
CN106320353B (en) A kind of construction method of basement construction Yield rainfall relation device
CN105002913A (en) Strongly-permeable stratum deep foundation pit bottom sealing water stopping structure and construction method thereof
CN105544576B (en) A kind of foundation pit Yield rainfall relation excavation method
CN109736340B (en) Dewatering device and method for guaranteeing integrity of cushion layer by reserving dewatering well on foundation slab
CN106013265B (en) Basement is met an urgent need the construction method of float Structure
CN108385627A (en) Power station diversion tunnel plugging construction method based on karst landform
CN110397057A (en) A kind of soft soil area Self-sinking type steel open caisson support system and method
CN114108649A (en) Foundation pit reinforcing construction method for mucky soil layer
CN104234089B (en) The construction method that a kind of basement guarded drainage combines
CN110130982A (en) A kind of traffic tunnel building safety construction method
CN106759364B (en) Deep basal pit bottom plate step-by-step construction method
CN110670613B (en) Foundation pit elevator shaft water seepage prevention structure and construction method thereof
CN109723071A (en) The construction method of the double-deck steel drum Yield rainfall relation system built in basement bottom plate rear pouring tape
CN106223351B (en) Self priming pump reduces local groundwater level construction method
CN107642101A (en) A kind of rocky bed steel cofferdam back cover leak stopping and guarded drainage construction method
CN109736337B (en) Precipitation device and method for guaranteeing integrity of cushion layer through sediment flowing treatment of foundation elevator shaft sump
CN203320576U (en) Waterproof and drainage system for basement external wall of super high-rise buildings
CN110258660A (en) The manufacture craft and shut-in well technique of the decompression drainage sump of basement anti-floating
CN206571490U (en) The drainage bucket of water burst is administered in a kind of vertical shaft for mine construction
CN210946854U (en) Anti-seepage structure of foundation pit elevator shaft
CN206359989U (en) Substrate local dewatering drainage arrangement
CN204825916U (en) Highly permeable stratum deep basal pit back cover stagnant water structure

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant