CN106744391A - One kind balance arm brace installs auxiliary body - Google Patents
One kind balance arm brace installs auxiliary body Download PDFInfo
- Publication number
- CN106744391A CN106744391A CN201710118588.4A CN201710118588A CN106744391A CN 106744391 A CN106744391 A CN 106744391A CN 201710118588 A CN201710118588 A CN 201710118588A CN 106744391 A CN106744391 A CN 106744391A
- Authority
- CN
- China
- Prior art keywords
- pull bar
- shaft hole
- pin shaft
- arm joint
- type groove
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B66—HOISTING; LIFTING; HAULING
- B66C—CRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
- B66C23/00—Cranes comprising essentially a beam, boom, or triangular structure acting as a cantilever and mounted for translatory of swinging movements in vertical or horizontal planes or a combination of such movements, e.g. jib-cranes, derricks, tower cranes
- B66C23/62—Constructional features or details
- B66C23/72—Counterweights or supports for balancing lifting couples
Landscapes
- Engineering & Computer Science (AREA)
- Mechanical Engineering (AREA)
- Jib Cranes (AREA)
Abstract
Auxiliary body is installed the invention discloses one kind balance arm brace, installation for aiding in balance arm of tower-type crane, including hydraulic jacking device and U-type groove, the lower end of hydraulic jacking device is secured by bolts in rear arm joint, and U-type groove is located at the top of hydraulic jacking device;Pull bar is provided with pull bar pin shaft hole near one end of preceding arm joint, and bearing pin sequentially fixes pull bar with top boom with top boom pin shaft hole through the pull bar pin shaft hole, and the other end of pull bar is fixed by pin joint with rear arm joint;During normal mounting, pull bar is positioned in U-type groove.In installation process, without the use of external equipment raising rod, mounting cost is reduced;Balance arm brace is positioned in U-type groove, pull bar swing can be prevented effectively from, prevent pull bar from causing to damage with miscellaneous part collision;By the effect of lifting of hydraulic jacking device, the speed that pull bar pin shaft hole and top boom pin shaft hole are aligned can be greatly improved with the height of adjusting yoke pin shaft hole, improve the installation effectiveness of bearing pin.
Description
Technical field
The invention belongs to engineering machinery field, and in particular to a kind of balance arm brace suitable for derrick crane is installed auxiliary
Help mechanism.
Background technology
With the development of engineering machinery technology, derrick crane develops toward large-scale, ultra-large type direction.Generally,
Counter-balance Boom for Big Tower Crane is generally multi-arm nodule structure, is generally attached by pull bar between arm joint.Counter-balance Boom for Big Tower Crane is general
Including counter-jib arm joint and counter-jib periproct, the wherein lower boom of counter-jib arm joint is connected with counter-jib periproct, counter-jib
Be connected by pull bar between the top boom of arm joint and counter-jib periproct, pull bar when the top boom with counter-jib arm joint is connected,
Need first to raise the end of pull bar by hanger by external equipment (such as truck crane), then slowly putting down makes the bearing pin of pull bar
Hole aligns with the pin shaft hole of top boom, could install connection bearing pin, pull bar is connected with the top boom of counter-jib arm joint.
General to align pin shaft hole using two ways when installing connection bearing pin, one is using external equipment (such as truck crane)
Hanger (referring to the mark 8 in Fig. 1) on pulling pull bar lifts tie rod end pin shaft hole and top boom pin shaft hole is aligned, and two are
Pull bar is lifted using the artificial mode of lifting.During using first method, the cost of use of external equipment (such as truck crane) is higher, meeting
Increase cost, during using second method, personnel are easily tired, can cause security incident.And, both the above method all can not
Ensure the stabilization in pull bar installation process, cause pull bar easily to touch counter-jib other structures and cause to damage, simultaneously for large-scale
Derrick crane for, pull bar weight is bigger, and aligning for pin shaft hole is also more difficult.
The content of the invention
It is an object of the invention to provide one kind can solve to balance in the prior art installation difficulty when arm brace row is installed it is big,
High cost, the balance arm brace of bearing pin installation difficulty install auxiliary body.
To achieve the above object, the present invention provides a kind of balance arm brace and installs auxiliary body, for aiding in tower lifting
The installation of machine counter-jib, the counter-jib includes preceding arm joint, rear arm joint and pull bar, lower boom and the rear arm joint of the preceding arm joint
Front end is connected, and the top boom of the preceding arm joint is connected so as to realize and rear arm joint through top boom pin shaft hole by bearing pin with pull bar
The connection of rear end;The auxiliary body includes hydraulic jacking device and U-type groove, and the lower end of the hydraulic jacking device is solid by bolt
Due in the rear arm joint, the U-type groove is located at the top of the hydraulic jacking device;The pull bar is near one end of preceding arm joint
Pull bar pin shaft hole is provided with, bearing pin sequentially passes through the pull bar pin shaft hole and top boom pin shaft hole by the pull bar and the top boom
Fixed, the other end of the pull bar is fixed by pin joint with the rear arm joint;And during normal mounting, the pull bar is positioned over institute
State in U-type groove.
During installation, first pull bar is positioned in U-type groove, pull bar is adjusted around pin joint by adjusting hydraulic jacking device
Rotate, and then adjust the relative position of pull bar pin shaft hole and top boom pin shaft hole, until pull bar pin shaft hole and top boom pin shaft hole
Align;After pull bar pin shaft hole and top boom pin shaft hole are aligned, in the presence of hydraulic jacking device, supported by U-type groove
Firmly pull bar, bearing pin is sequentially fixed pull bar with top boom with top boom pin shaft hole through pull bar pin shaft hole.
Compared with prior art, the invention has the advantages that:
1st, in installation process, will balance arm brace be positioned in U-type groove, can be prevented effectively from pull bar swing, prevent pull bar with
Miscellaneous part collision causes to damage, and extends the service life of derrick crane and pull bar;
2nd, in installation process, by the effect of lifting of hydraulic jacking device, can be with the height of adjusting yoke pin shaft hole, greatly
Improve the speed that pull bar pin shaft hole and top boom pin shaft hole are aligned, improve the installation effectiveness of bearing pin;
3rd, this patent is without the use of external equipment (such as truck crane) raising rod, reduces mounting cost;It is not required to artificial support
Lift pull bar, it is to avoid the generation of personal security accident;
4th, using ripe hydraulic technique, safety simple to operate, reliability is high, and maintenance is convenient.
Brief description of the drawings
Fig. 1 is structural representation of the invention, wherein:
1- bearing pins, 2- pull bar pin shaft holes, 3-U type grooves, 4- top boom pin shaft holes, 5- hydraulic jacking devices, arm joint after 6-, 7-
Preceding arm joint, 71- lower booms, 72- top booms, 8- hangers, 9- pull bars, 10- pin joints.
Specific embodiment
Below in conjunction with the accompanying drawing in the embodiment of the present invention, the technical scheme in the embodiment of the present invention is carried out clear, complete
Site preparation is described, it is clear that described embodiment is only a part of embodiment of the invention, rather than whole embodiments.It is based on
Embodiment in the present invention, it is every other that those of ordinary skill in the art are obtained under the premise of creative work is not made
Embodiment, belongs to the scope of protection of the invention.
1 is referred to, the present embodiment provides a kind of balance arm brace and installs auxiliary body, for aiding in tower crane balance
The installation of arm, the counter-jib includes preceding arm joint 7, rear arm joint 6 and pull bar 9, lower boom 71 and the rear arm joint 6 of the preceding arm joint 7
Front end connection, the top boom 72 of the preceding arm joint 7 is connected so as to realize through top boom pin shaft hole 4 by bearing pin 1 with pull bar 9
With the connection of the rear end of rear arm joint 6.
The auxiliary body includes hydraulic jacking device 5 and U-type groove 3, and the lower end of the hydraulic jacking device 5 is solid by bolt
Due in the rear arm joint 6, the U-type groove 3 is located at the top of the hydraulic jacking device 5;The pull bar 9 is near preceding arm joint 7
One end be provided with pull bar pin shaft hole 2, bearing pin 1 is sequentially through the pull bar pin shaft hole 2 and top boom pin shaft hole 4 by the pull bar 9
Fixed with the top boom 72, the other end of the pull bar 9 is fixed by pin joint 10 with the rear arm joint 6;And normal mounting
When, the pull bar 9 is positioned in the U-type groove 3.
During installation, first pull bar 9 is positioned in U-type groove 3, pull bar 9 is adjusted around hinge by adjusting hydraulic jacking device 5
Contact 10 is rotated, and then adjusts the relative position of pull bar pin shaft hole 2 and top boom pin shaft hole 4, until pull bar pin shaft hole 2 with wind up
Lever pin axis hole 4 is aligned;After pull bar pin shaft hole 2 and top boom pin shaft hole 4 are aligned, in the presence of hydraulic jacking device 5, lead to
Cross U-type groove 3 and support pull bar 9, bearing pin 1 is sequentially passed through pull bar pin shaft hole 2 and top boom pin shaft hole 4 by pull bar 9 and top boom
72 fix.
To sum up, be positioned over balance arm brace 9 in U-type groove 3 in installation process by the present embodiment, can be prevented effectively from pull bar
Swing, prevent pull bar from causing to damage with miscellaneous part collision, extend the service life of derrick crane and pull bar;By hydraulic pressure
The effect of lifting of jacking apparatus 5, can be greatly improved pull bar pin shaft hole 2 and top boom with the height of adjusting yoke pin shaft hole 2
The speed that pin shaft hole 4 is aligned, improves the installation effectiveness of bearing pin 1;Without the use of external equipment (such as truck crane) raising rod 9,
Reduce mounting cost;It is not required to manually lift pull bar 9, it is to avoid the generation of personal security accident;Using ripe hydraulic technique,
Safety simple to operate, reliability is high, and maintenance is convenient.
The hanger 8 used in prior art installation process is still remained in counter-jib involved by the present embodiment, can be
The situation that oneself uses must not be out of order in auxiliary body carries out the installation of bearing pin using original technology.
Although an embodiment of the present invention has been shown and described, for the ordinary skill in the art, can be with
Understanding can carry out various changes, modification, replacement to these embodiments without departing from the principles and spirit of the present invention
And modification, the scope of the present invention be defined by the appended.
Claims (1)
1. a kind of balance arm brace installs auxiliary body, the installation for aiding in balance arm of tower-type crane, the counter-jib bag
Preceding arm joint (7), rear arm joint (6) and pull bar (9) are included, the lower boom (71) of the preceding arm joint (7) connects with the front end of rear arm joint (6)
Connect, the top boom (72) of the preceding arm joint (7) is connected so as to real through top boom pin shaft hole (4) by bearing pin (1) with pull bar (9)
Now with the connection of rear arm joint (6) rear end, it is characterised in that the auxiliary body includes hydraulic jacking device (5) and U-type groove (3), institute
The lower end for stating hydraulic jacking device (5) is secured by bolts on the rear arm joint (6), and the U-type groove (3) is located at the hydraulic pressure
The top of jacking apparatus (5);The pull bar (9) is provided with pull bar pin shaft hole (2) near one end of preceding arm joint (7), and bearing pin (1) is sequentially
It is through the pull bar pin shaft hole (2) and top boom pin shaft hole (4) that the pull bar (9) is fixed with the top boom (72), it is described
The other end of pull bar (9) is fixed with the rear arm joint (6) by pin joint (10);And during normal mounting, the pull bar (9) is placed
In the U-type groove (3).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710118588.4A CN106744391A (en) | 2017-03-01 | 2017-03-01 | One kind balance arm brace installs auxiliary body |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710118588.4A CN106744391A (en) | 2017-03-01 | 2017-03-01 | One kind balance arm brace installs auxiliary body |
Publications (1)
Publication Number | Publication Date |
---|---|
CN106744391A true CN106744391A (en) | 2017-05-31 |
Family
ID=58959204
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201710118588.4A Pending CN106744391A (en) | 2017-03-01 | 2017-03-01 | One kind balance arm brace installs auxiliary body |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN106744391A (en) |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
EP2639196A1 (en) * | 2010-10-14 | 2013-09-18 | Changsha Zoomlion Heavy Industry Science & Technology Development Co., Ltd. | Tower crane and balance arm tension rod structure thereof and mounting method for the structure |
CN103539023A (en) * | 2013-10-29 | 2014-01-29 | 中联重科股份有限公司 | Structure and method for mounting balance arm and pull rod with tower head as well as tower crane |
CN203541966U (en) * | 2013-10-10 | 2014-04-16 | 中联重科股份有限公司 | Auxiliary installation system for pull rod of tower crane |
CN204342307U (en) * | 2014-12-11 | 2015-05-20 | 徐州建机工程机械有限公司 | Balance arm of tower-type crane pull bar auxiliary installation device |
CN205132989U (en) * | 2015-09-30 | 2016-04-06 | 徐州建机工程机械有限公司 | Tower machine balance arm pull rod carrier structure |
-
2017
- 2017-03-01 CN CN201710118588.4A patent/CN106744391A/en active Pending
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
EP2639196A1 (en) * | 2010-10-14 | 2013-09-18 | Changsha Zoomlion Heavy Industry Science & Technology Development Co., Ltd. | Tower crane and balance arm tension rod structure thereof and mounting method for the structure |
CN203541966U (en) * | 2013-10-10 | 2014-04-16 | 中联重科股份有限公司 | Auxiliary installation system for pull rod of tower crane |
CN103539023A (en) * | 2013-10-29 | 2014-01-29 | 中联重科股份有限公司 | Structure and method for mounting balance arm and pull rod with tower head as well as tower crane |
CN204342307U (en) * | 2014-12-11 | 2015-05-20 | 徐州建机工程机械有限公司 | Balance arm of tower-type crane pull bar auxiliary installation device |
CN205132989U (en) * | 2015-09-30 | 2016-04-06 | 徐州建机工程机械有限公司 | Tower machine balance arm pull rod carrier structure |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
US10865077B2 (en) | System for assembling/disassembling windmills | |
CN202451081U (en) | Automatic discharge device of racking platform drill pipe | |
CN101284628B (en) | Hoisting method for framework of large tonnage pressing machine | |
CN201783769U (en) | Wind power generation tower shell section turning device | |
DK180818B1 (en) | Wind turbine tower with crane connecting elements and a crane with tower flange connecting elements | |
CN109441361B (en) | Pile frame and mast erecting method thereof | |
CN106760903A (en) | A kind of electric power pylon differential settlement adjusting means | |
US20210155460A1 (en) | Cranes and Methods for Erecting a Tower | |
CN106229889B (en) | A kind of transmission line of electricity lifting device for aerial wires | |
CN111762699A (en) | Safety tower crane and implementation method thereof | |
WO2023221302A1 (en) | Boom system for independently mounting wind turbine and large-scale construction apparatus | |
CN114873497A (en) | Vertical lifting installation device and method for variable-diameter unbalanced load equipment | |
CN104989111A (en) | Construction method for steel structure high-rise hoisting | |
CN206553111U (en) | One kind balance arm brace installs auxiliary body | |
CN204625045U (en) | A kind of steel structure hoisting door shaped stent formula hanging apparatus | |
CN201334770Y (en) | Wall-attached supporting seat | |
CN102303821A (en) | Luffing tower crane with balanced type suspension arm based on traction luffing of steel rope | |
CN206590793U (en) | Connect arm assembly and the movable arm tower crane comprising the device in the air | |
CN111891944A (en) | Integral self-lifting device for upper equipment of tower crane | |
CN202323771U (en) | Installation and maintenance system for highway bridge | |
CN110562850B (en) | Main tower integral hoisting system and method | |
WO2017166905A1 (en) | Tower type derrick and mounting method therefor | |
CN106744391A (en) | One kind balance arm brace installs auxiliary body | |
CN209742887U (en) | Crushing device and arch center mounting crushing arm | |
CN103539020B (en) | Novel hoisting construction method and special hanging device |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
WD01 | Invention patent application deemed withdrawn after publication |
Application publication date: 20170531 |
|
WD01 | Invention patent application deemed withdrawn after publication |