CN106712300A - Intelligent master station and sub-station multi-level anti-misoperation locking system - Google Patents

Intelligent master station and sub-station multi-level anti-misoperation locking system Download PDF

Info

Publication number
CN106712300A
CN106712300A CN201710068771.8A CN201710068771A CN106712300A CN 106712300 A CN106712300 A CN 106712300A CN 201710068771 A CN201710068771 A CN 201710068771A CN 106712300 A CN106712300 A CN 106712300A
Authority
CN
China
Prior art keywords
main frame
station
supervisory control
substation
primary equipment
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201710068771.8A
Other languages
Chinese (zh)
Other versions
CN106712300B (en
Inventor
黎强
韩茂林
徐奕信
王水
徐成斌
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
CYG Sunri Co Ltd
Original Assignee
CYG Sunri Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CYG Sunri Co Ltd filed Critical CYG Sunri Co Ltd
Priority to CN201710068771.8A priority Critical patent/CN106712300B/en
Publication of CN106712300A publication Critical patent/CN106712300A/en
Application granted granted Critical
Publication of CN106712300B publication Critical patent/CN106712300B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • H02J13/0013
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E60/00Enabling technologies; Technologies with a potential or indirect contribution to GHG emissions mitigation
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y04INFORMATION OR COMMUNICATION TECHNOLOGIES HAVING AN IMPACT ON OTHER TECHNOLOGY AREAS
    • Y04SSYSTEMS INTEGRATING TECHNOLOGIES RELATED TO POWER NETWORK OPERATION, COMMUNICATION OR INFORMATION TECHNOLOGIES FOR IMPROVING THE ELECTRICAL POWER GENERATION, TRANSMISSION, DISTRIBUTION, MANAGEMENT OR USAGE, i.e. SMART GRIDS
    • Y04S10/00Systems supporting electrical power generation, transmission or distribution
    • Y04S10/16Electric power substations

Landscapes

  • Remote Monitoring And Control Of Power-Distribution Networks (AREA)
  • Supply And Distribution Of Alternating Current (AREA)

Abstract

The invention discloses an intelligent master station and sub-station multi-level anti-misoperation locking system. The invention aims to realize effective cooperation between a master station and sub-stations. The intelligent master station and sub-station multi-level anti-misoperation locking system of the invention is provided with a monitoring and control device, a transformer station monitoring host and a scheduling master station; the monitoring and control device is in communication connection with a communication gateway machine and the transformer station monitoring host; and the scheduling master station is in communication connection with the communication gateway machine and the transformer station monitoring host. The transformer station monitoring host performs configuration generation, maintenance and check for the five-prevention rules of the monitoring and control device and the scheduling master station; the transformer station monitoring host has unique management authority over the management of the operation of primary equipment; the five-prevention modules of the scheduling master station and the transformer station monitoring host share five-prevention locking logic with each other; and the scheduling master station and the transformer station monitoring host realize multi-level anti-misoperation locking and achieve effective coordination operation, and therefore, the debugging workload of the five-prevention rules of the scheduling master station and the transformer station monitoring host can be greatly decreased.

Description

The multistage anti-error locking system in intelligent substation boss station
Technical field
The present invention relates to a kind of automated system of intelligent substation, the anti-misoperation locking system of particularly a kind of intelligent substation System.
Background technology
Intelligent substation anti-misoperation locking (anti-error) refers to that five prevent:1st, prevent on-load from dividing by mistake, close disconnecting switch by mistake;2nd, prevent from missing Point, falsely close circuit breaker;3rd, anti-stop-band ground wire or earthing switch blade close breaker;4th, prevent live connection of ground wire or close earthing switch blade; 5th, mistakenly entering charged chamber is prevented.Setting the principle of error-proof device is:All high voltage electric equipments for being possible to cause maloperation, all should Installing error-proof device and corresponding anti-error electric blocking loop.The issue in 2000 of former State Power Corporation《Prevent power generation 25 important requirements of major accident》The 2.5th article of clear stipulaties of chapter 2 " preventing electric fault-operation accident ":Using meter When calculating machine monitoring system, a distant place, local operation all should possess anti mis-closedown function.
The conventional anti-misoperation locking mode for occurring at home mainly has four kinds:Mechanical latching, procedure lock, electric interlock and electromagnetism Lock.Since the nineties in last century, electrical anti-error lock-in control system starts using microcomputer control, domestic Electrical utility firms phase After being proposed computer anti-misoperation and lockout device.By the development of more than 10 years, computer anti-misoperation and lockout device was gradually ripe, in electric power By wide popularization and application in system.Computer-lock Device For Preventing Incorrect Operation Used is returned the substantial amounts of secondary locking in intelligent substation scene by anti-error system Road is converted to the five-defence block rule base in computer, realizes the digitlization of anti-misoperation locking, it is possible to which realization can not be realized in the past Or anti-error function difficult to realize, such as:To mistakenly entering charged chamber, the mounting of ground wire, dismounting etc..
In the five-preventing system of prior art, power system regulation and control central master station (scheduling station, main website) five-preventing systems at different levels Cannot realize that latching logic is shared with intelligent substation substation five-preventing system, so that effective cooperating cannot be realized, specially: 1st, main website of control centre five-preventing system and intelligent substation substation five-preventing system each have five-defence block logic, exist inconsistent Situation, cause operation order in the case where the verification of main website five prevention logic passes through, may not passed through by the verification of substation five prevention logic, Maloperation may be caused;2nd, when main website five-preventing system accesses different substation five-preventing systems, it is required to carry out main website-substation locking to patrol Contrast debugging is collected, debugging work load is very big;3rd, during main website or substation carry out five-prevention operation, lack to operating unique power Management, it is impossible to accomplish main website with the automatic mutually locking of substation five-preventing system.
The content of the invention
It is an object of the invention to provide a kind of multistage anti-error locking system in intelligent substation boss station and method, to be solved Technical problem is to realize main website and the effective cooperating in substation.
The present invention uses following technical scheme:The multistage anti-error locking system in intelligent substation boss station, be provided with measure and control device, Supervisory control of substation main frame and scheduling station, the measure and control device are connected logical with communication network shutdown and supervisory control of substation main frame respectively Letter, scheduling station respectively with communication gate and supervisory control of substation main frame connection communication;
The supervisory control of substation main frame carries out configuration generation to the proofing rules of measure and control device and scheduling station, safeguards and school Test, the operation of management supervisory control of substation main frame and scheduling station to primary equipment is uniquely weighed, to the remote control corresponding to straighforward operation The proofing rules of passage are verified, and operation is remotely controlled to primary equipment;
The remote signalling information and telemetry intelligence (TELINT) of the measure and control device Real-time Collection primary equipment, through delivering to tune in communication network shutdown Spend main website and above deliver to supervisory control of substation main frame, real-time judge currently gathers the state of information, calculates each remote-control channel Proofing rules check results, proofing rules check results are supervised through delivering to scheduling station in communication network shutdown and above delivering to transformer station Control main frame, receives the straighforward operation order that supervisory control of substation main frame or scheduling station are sent through communication network shutdown, to straighforward operation Remote-control channel carry out proofing rules verification pass through after, straighforward operation order is just issued to the operation circuit of primary equipment, realization Straighforward operation control to primary equipment;
Before the scheduling station is remotely controlled operation to primary equipment, five are carried out to the remote-control channel corresponding to the operation Anti- rule verification, by verification, sends the order of the request unique power of the operation to the primary equipment to supervisory control of substation main frame, adjusts After degree main website obtains the unique power of operation from supervisory control of substation main frame, send to the straighforward operation order of primary equipment through communication gate To measure and control device, scheduling station receives remote measurement, the remote signalling information that communication network shutdown is sent to machine, refreshes the reality of scheduling station real-time database When state of value, produce correspondence transformer station alarm record.
Measure and control device of the invention is logical using station level network connection with communication network shutdown and supervisory control of substation main frame respectively Letter, scheduling station uses dispatch data net connection communication with communication gate and supervisory control of substation main frame respectively.
Management operation to primary equipment of supervisory control of substation main frame and scheduling station of the invention is uniquely weighed, scheduling station or Supervisory control of substation main frame will be obtained to the unique power of operation of certain primary equipment, it is necessary to prevent five of corresponding remote-control channel after operation Rule is verified, and then supervisory control of substation main frame is filed an application, and supervisory control of substation main frame carries out proofing rules verification, verification By rear, check measure and control device it is real-time on the five anti-check results sent, then to be responsible for batch operation by supervisory control of substation main frame unique Power, supervisory control of substation main frame or scheduling station are obtaining the operation of certain primary equipment uniquely after power, supervisory control of substation main frame locking Operation of the miscellaneous equipment to the primary equipment.
Supervisory control of substation main frame of the invention and scheduling station are obtained uniquely to be weighed to the operation of transforming plant primary equipment, is used Whose first to file, whose principle for first obtaining.
After supervisory control of substation main frame of the invention or scheduling station obtain the unique power of operation of certain primary equipment, in regulation The straighforward operation to the primary equipment is completed in time, after operation execution terminates, this behaviour to the primary equipment is actively discharged Make unique power.
Supervisory control of substation main frame of the invention or scheduling station are exercised after uniquely being weighed to the operation of primary equipment, are not released actively The unique power of operation is put, the unique power of operation is reclaimed by supervisory control of substation main frame or discharged.
Measure and control device of the invention receives supervisory control of substation main frame or scheduling station and is grasped through the remote control that communication network shutdown is sent Order, carrying out corresponding proofing rules verification to the remote-control channel of straighforward operation does not pass through, measure and control device locking remote control behaviour Order, reply remote control failure message to supervisory control of substation main frame or scheduling station.
Before scheduling station of the invention is remotely controlled operation to primary equipment, the remote-control channel corresponding to the operation is entered Row proofing rules are verified, not validated to stop operation.
Measure and control device of the invention is entered with communication network shutdown and supervisory control of substation main-machine communication by the agreements of IEC 61850 respectively OK, the communication network shutdown communicates with scheduling station and is carried out by by the stipulations of IEC 104, described to be pressed with supervisory control of substation main-machine communication Carried out by the stipulations of IEC 104.
Management operation to primary equipment of supervisory control of substation main frame and scheduling station of the invention is uniquely weighed, scheduling station or Supervisory control of substation main frame will be obtained to the unique power of operation of certain primary equipment, it is necessary to prevent five of corresponding remote-control channel after operation Rule is verified, and then supervisory control of substation main frame is filed an application, and is responsible for batch operation by supervisory control of substation main frame and is uniquely weighed, Supervisory control of substation main frame carries out proofing rules verification, after verification passes through, check measure and control device it is real-time on the five anti-check results sent, Supervisory control of substation main frame or scheduling station obtaining the operation of certain primary equipment uniquely after power, the locking of supervisory control of substation main frame other Operation of the equipment to the primary equipment.
Compared with prior art, measure and control device shuts down and supervisory control of substation main frame connection communication the present invention with communication network, adjusts Degree main website with and supervisory control of substation main frame connection communication, supervisory control of substation main frame is to measure and control device and the proofing rules of scheduling station Configuration generation is carried out, is safeguarded and is verified, the management that supervisory control of substation main frame possesses management operation primary equipment is uniquely weighed, scheduling master Stand and the shared five-defence block logic of the anti-module of supervisory control of substation main frame five, scheduling station is anti-error with supervisory control of substation machine multi-stage to be closed Lock, realizes effective cooperating, significantly reduces the debugging work load of scheduling station and supervisory control of substation main frame proofing rules.
Brief description of the drawings
Fig. 1 is system construction drawing of the invention.
Fig. 2 is system network topology figure of the invention.
Fig. 3 is the flow chart that scheduling station of the invention initiates straighforward operation.
Fig. 4 is the flow chart that supervisory control of substation main frame of the invention initiates straighforward operation.
Specific embodiment
The present invention is described in further detail with reference to the accompanying drawings and examples.As shown in figure 1, intelligence of the invention becomes The multistage anti-error locking system in power station (transformer station) boss station, by measure and control device, supervisory control of substation main frame, communication network shutdown, scheduling Four parts of main website constitute.Measure and control device passes through Substation Station control layer network with communication network shutdown and supervisory control of substation main frame respectively Connection, communication network shutdown is connected with the scheduled data network of scheduling station, and supervisory control of substation main frame is with scheduling station via scheduling Data network is connected.The anti-module in substation five is provided with supervisory control of substation main frame, the anti-module of main website five is provided with scheduling station.
As shown in Fig. 2 measure and control device uses station level network connection with communication network shutdown and supervisory control of substation main frame respectively Communication, scheduling station uses dispatch data net connection communication with communication network shutdown, and scheduling station is used with supervisory control of substation main frame Dispatch data net connection communication.
Measure and control device measurement collection transformer station's terminal device (electric power primary equipment, transforming plant primary equipment, primary equipment) Information, component, data handling component, five anti-verification components, mailing address are outputed by digital quantity and analog acquisition component, remote control Reason component and man-machine display component composition.Five it is anti-verification components proofing rules by supervisory control of substation main frame the anti-module in substation five Configuration generation, maintenance and verification, are sent to measure and control device by supervisory control of substation main frame by the agreements of IEC 61850.Measure and control device has Body completes following work:
1. the digital data acquisition component of measure and control device presses the remote signalling information of 1ms sampling period Real-time Collection primary equipments:Become The location status (remote signalling) of power station primary equipment, the analog acquisition component of measure and control device presses the frequency Real-time Collection of 4000 points/s Telemetry intelligence (TELINT):The secondary current of current transformer and the secondary voltage (remote measurement) of voltage transformer.Digital quantity and analog acquisition Remote signalling that component is collected and telemetry intelligence (TELINT) are via the communication process component of measure and control device by delivering to communication in the agreements of IEC 61850 Gateway machine and supervisory control of substation main frame.Transforming plant primary equipment is disconnecting switch (switch), breaker (disconnecting link) and earthing switch blade (knife).
2. the five of measure and control device anti-verification component real-time judges currently gather the state of remote signalling information and telemetry intelligence (TELINT), calculate Go out the proofing rules check results to each remote-control channel, proofing rules check results are pressed into IEC via communication process component Communication network shutdown and supervisory control of substation main frame are delivered in 61850 agreements.The proofing rules of five anti-verification components, by supervisory control of substation Main frame unification carries out configuration generation, safeguards and verify.Remote-control channel is the quantity of measure and control device remote control object, by receiving The remote control divide-shut brake order of remote monitor device, realizes the breaking-closing operating to primary equipment, and different remote-control channels pass through IEC61850 citations reference carries out unique mark.It is every that five anti-verification components are connected to measure and control device with intelligent substation One remote-control channel carries out proofing rules verification.
3. the communication process component of measure and control device receives the straighforward operation order of supervisory control of substation main frame, in five anti-verification groups Part is carried out after the verification of corresponding proofing rules passes through to the remote-control channel, and straighforward operation order could be outputed under component via remote control The operation circuit of primary equipment is sent to, the straighforward operation control to primary equipment is realized.If the proofing rules school of the remote-control channel Test and do not pass through, data handling component then locking straighforward operation order of measure and control device is replied remote control and lost through communication process component Lose message to supervisory control of substation main frame.
4. the communication process component of measure and control device gathers digital quantity and analog acquisition component remote signalling and telemetry intelligence (TELINT) On give supervisory control of substation main frame and communication network shutdown, by proofing rules check results by delivering to communication in the agreements of IEC 61850 Gateway machine and supervisory control of substation main frame.
5. the communication process component of measure and control device receives the straighforward operation order that scheduling station shuts down through communication network, anti-five Verification component is carried out after the verification of corresponding proofing rules passes through to the remote-control channel, and straighforward operation order could be via measure and control device Remote control output the operation circuit that component is issued to primary equipment, realize the remote operation control to primary equipment.If the remote control The proofing rules verification of passage does not pass through, data handling component then locking straighforward operation order of measure and control device, through mailing address Reason component replys remote control failure message through communication network shutdown to scheduling station.Between the proofing rules verifying function of measure and control device is Interlayer anti mis-closedown function.
6. man-machine display component can show to all processing procedures of measure and control device.
Proofing rules are verified as:Before being operated to primary equipment and after operation, by measure and control device, supervisory control of substation master Machine and scheduling station check all primary equipments point position of intelligent substation, close position according to the proofing rules being pre-configured with Location status amount, the combination more than or less than limit value of Current Voltage, if meet the operating condition of proofing rules.If five prevent The result of rule verification is to pass through, that is, represent that the primary equipment allows to be operated, and otherwise represents that the primary equipment does not allow to be grasped Make.
Communication network is shut down for the communication connection for setting up measure and control device and scheduling station, specially:
1. measure and control device is received to prevent by the remote measurement, remote signals sent in the agreements of IEC 61850, to the five of each remote-control channel Regular check results, are sent to scheduling station by correspondence, enter by the stipulations of IEC 104 between communication network shutdown and scheduling station Row communication.
2. the straighforward operation order that the stipulations of IEC 104 receive scheduling station is pressed in communication network shutdown, is turned by the agreements of IEC 61850 It is sent to measure and control device.
Supervisory control of substation main frame is data acquisition and the monitoring control SCADA system of transformer substation end, is provided with the anti-mould in substation five Block (five anti-components), five anti-components are responsible for carrying out the proofing rules of measure and control device and scheduling station configuration generation, are safeguarded and school Test, i.e., the proofing rules inside measure and control device and scheduling station by supervisory control of substation main frame five anti-components generations, safeguard and Verification so that measure and control device and scheduling station are completely the same with the proofing rules of supervisory control of substation main frame.Supervisory control of substation main frame Complete following work:
1. supervisory control of substation main frame is received remote measurement, the remote signals sent on measure and control device by the agreements of IEC 61850, is refreshed and is become The real-time state of value of monitoring power station main frame real-time database, produces corresponding event sequence recording system SOE alarms record, on man-machine boundary The running status of face real-time exhibition transformer station, the running state information of primary equipment, facilitate transformer station's operation maintenance personnel quickly to recognize The operating condition of intelligent substation.The proofing rules that supervisory control of substation main frame is pressed in IEC61850 agreements reception measure and control device are real-time Check results, are shown in man-machine interface, to facilitate operation maintenance personnel quickly to grasp the anti-execution state of current five, it is ensured that operation Absolute safety.
2. operating personnel are remotely controlled operation to primary equipment in supervisory control of substation main frame man-machine interface, the primary equipment Operation is not blocked, and five anti-modules of supervisory control of substation main frame carry out school to the proofing rules of corresponding remote-control channel after operation Test, proofing rules verification passes through, check measure and control device it is real-time on the five anti-check results sent, then sent by supervisory control of substation main frame Straighforward operation order is to measure and control device, operation of the locking other equipment to the primary equipment;If verification does not pass through, guidance command At once forbidden sending.Proofing rules verification herein, also for station level anti-misoperation locking is verified.
3. supervisory control of substation main frame possesses the unique power of management, and scheduling station enters through communication network shutdown to transforming plant primary equipment , it is necessary to press IEC104 stipulations before row straighforward operation, the order for sending the unique power of request operation to supervisory control of substation main frame (is calculated Machine order), unique power that request is operated to the primary equipment.Supervisory control of substation main frame receives the unique power of scheduling station operation After request command, the state after being operated according to residing for the primary equipment carries out proofing rules verification, and proofing rules verification is logical Later, supervisory control of substation main frame checks whether the primary equipment is in and is grasped by other scheduling stations or supervisory control of substation main frame The state of work, if the primary equipment is not in by the state of other scheduling stations or supervisory control of substation host service function, should Uniquely power distributes to the scheduling station for the operation of primary equipment, sends to obtain to operate to scheduling station and uniquely weighs successful message; Otherwise, reply and obtain the unique message for weighing failure of operation to scheduling station.
Uniquely power is for operation:The primary equipment a certain moment only allows to be operated by an equipment, supervisory control of substation main frame With the side in scheduling station after the unique power of certain primary equipment operation is obtained, the opposing party is not allowed to grasp the primary equipment Make.The operation of the operation primary equipment is uniquely weighed, and is authorized by the supervisory control of substation main frame with the unique power of management.
Uniquely power is for management:The operation of management supervisory control of substation main frame and scheduling station to certain primary equipment is uniquely weighed, this Unique power is managed in invention to be responsible for and exercised by supervisory control of substation main frame.Scheduling station or supervisory control of substation main frame need to obtain in itself , it is necessary to be filed an application to supervisory control of substation main frame before taking the unique power of operation to certain primary equipment, by supervisory control of substation main frame Responsible batch operation is uniquely weighed.Supervisory control of substation main frame and scheduling station are obtained uniquely to be weighed to the operation of transforming plant primary equipment, Using the principle of " whose first to file, who first obtain ".Supervisory control of substation main frame or scheduling station are obtaining the operation of certain primary equipment After unique power, operation of the supervisory control of substation main frame locking miscellaneous equipment to the primary equipment;Supervisory control of substation main frame or scheduling master After the unique power of operation for obtaining certain primary equipment of standing, for example it is defaulted as 120 seconds domestic demands in the stipulated time and completes to the primary equipment Straighforward operation, after operation execution terminates, or do not complete straighforward operation to the primary equipment at the appointed time, transformer station's prison Control main frame or scheduling station need to actively discharge this operation to the primary equipment and uniquely weigh, so as to ensure the primary equipment at this Non-operating state, i.e. idle condition are in after the completion of secondary operation, supervisory control of substation main frame or scheduling station are operated to it next time When, normally can be obtained by the application process application of the unique power of operation again.Supervisory control of substation main frame or scheduling station exercise a certain After the operation of secondary device is uniquely weighed, or the straighforward operation to the primary equipment is not completed at the appointed time, at the appointed time Actively release operation is not unique weighs, then be responsible for reclaiming or discharging the unique power of operation by supervisory control of substation main frame.
Scheduling station, refers to that the power-management centre in province, city or area is used to realize the Department of Automation of dispatching of power netwoks monitoring System, it passes through to access the communication network shutdown in transformer station to gather the service data of the power network in transformer station, primary equipment, connects Receive the proofing rules check results of each remote-control channel;Shut down by the communication network of transformer station, assign the remote control life of scheduling station Primary equipment is controlled in order to transformer station.Scheduling station is provided with the anti-module of main website five, and the proofing rules of the anti-module of main website five are by son Stand five anti-modules configuration generations, safeguard and verify, by supervisory control of substation main frame by delivering to scheduling station in IEC104 stipulations.Scheduling Main website specifically completes following work:
1. scheduling station transforming plant primary equipment is remotely controlled operation before, to the remote-control channel corresponding to the operation Proofing rules verification after being operated, it is not validated to stop operation;By verification, then request is sent by IEC104 stipulations right To supervisory control of substation main frame, request supervisory control of substation main frame gives scheduling station should for the order of the unique power of operation of the primary equipment The operation of primary equipment is uniquely weighed.The proofing rules verifying function, as scheduling station anti mis-closedown function.
2. after scheduling station obtains the unique power of operation from supervisory control of substation main frame, sent to primary equipment by IEC104 stipulations Straighforward operation order to communication network shut down, communication network shutdown the straighforward operation order is forwarded to measure and control device.
3. scheduling station receives remote measurement, the remote signalling information that communication network shutdown is sent, and refreshes the real-time of scheduling station real-time database State of value, produces the SOE alarm records of correspondence transformer station, the fortune of running status, equipment in man-machine interface real-time exhibition power network Row status information, facilitates scheduling station operation maintenance personnel quickly to recognize the operating condition of transformer station.
Supervisory control of substation main frame by straighforward operation, can control the location status of primary equipment with scheduling station, come Change the method for operation of intelligent substation.Supervisory control of substation main frame possesses the unique power of management, behaviour of the unified management to primary equipment Make unique power.Supervisory control of substation main frame and scheduling station are obtained to primary equipment by the way of " whose first to file, who first obtain " Operation uniquely weigh.After performing straighforward operation, the actively unique power of release operation, the time-out actively unique power of release operation, then by The unification of supervisory control of substation main frame be managed with recovery, carry out time-out and be automatically releasable the unique power of operation operation, and advised by IEC104 About notify scheduling station.
Complete anti-misoperation locking flow is illustrated by taking a certain primary equipment in scheduling station straighforward operation transformer station as an example.Adjust Before degree main website is to primary equipment straighforward operation, the proofing rules verification after being operated sends request behaviour by IEC104 stipulations Make unique power order to supervisory control of substation main frame.After supervisory control of substation main frame receives the unique power order of request operation, first, it is determined that The unique power of operation, checks whether the primary equipment of this operation is grasped by supervisory control of substation main frame or other scheduling stations Make, on the premise of the primary equipment is not operated by supervisory control of substation main frame or other scheduling stations, by the unique power distribution of operation Operate to the scheduling station, locking supervisory control of substation main frame and other scheduling stations to the primary equipment, such as this once sets For in being operated by supervisory control of substation main frame or other scheduling stations, then the locking scheduling station is to the primary equipment Operation.Secondly, in confirmation, the primary equipment is in not operation after state supervisory control of substation main frame, and the five of supervisory control of substation main frame Anti- module carries out the verification of station level (supervisory control of substation main frame) proofing rules, after passing through to the verification of station level proofing rules, becomes The five anti-check results sent on the anti-module check measure and control device in monitoring power station main frame substation five is real-time, in station level proofing rules school Real-time with measure and control device five anti-check results are tested, i.e., multistage anti-misoperation locking logic is verified under conditions of passing through, supervisory control of substation Host response scheduling station obtains the unique power success command of operation.Can also batch operation uniquely weigh it is successful after inspection point The proofing rules of control layer and wall.Scheduling station receive acquisition operation uniquely weigh successful commands in return after, send remote control behaviour Order to the communication network for making primary equipment is shut down, and measure and control device, five anti-verification groups of measure and control device are forwarded to by communication network shutdown Part is carried out after the verification of corresponding proofing rules passes through to remote-control channel, and straighforward operation order outputs group via the remote control of measure and control device Part is issued to the operation circuit of primary equipment, realizes the remote operation control to primary equipment, reaches change substation operation side The purpose of formula.Finally, after measure and control device is through the communication network shutdown successful result of return operation to scheduling station, scheduling station is actively Discharge and the operation of the primary equipment is uniquely weighed, if actively release does not operate unique power to time-out, by supervisory control of substation main frame Recovery operation is uniquely weighed.
The multistage anti-error locking system in intelligent substation boss station of the invention, five anti-verification component and scheduling of measure and control device The proofing rules of the anti-module of main website five of main website are generated by the anti-module configuration of substation five of supervisory control of substation main frame, safeguarded and school Test.Supervisory control of substation main frame possesses the unique power of management, and scheduling station and supervisory control of substation main frame carry out five to primary equipment respectively Anti- rule verification, operation of the mutual locking other side to certain primary equipment, in synchronization, only allows an operation source to one by one Secondary device is remotely controlled operation.Scheduling station realizes the main website (main website) of dispatching of power netwoks monitoring as power-management centre, bears Blaming carries out main website level proofing rules verification to the primary equipment of the transformer station of compass of competency;Supervisory control of substation main frame is used as transformer station Monitoring control sub-station (substation), be responsible for station level proofing rules verification is carried out to transforming plant primary equipment;Measure and control device conduct Bay device, is responsible for carrying out transforming plant primary equipment wall proofing rules verification.When scheduling station is initiated to certain once When equipment is remotely controlled operation, main website level, control of standing are carried out by scheduling station, supervisory control of substation main frame and measure and control device simultaneously respectively Layer, the verification of wall proofing rules, while operation of the locking supervisory control of substation main frame to the primary equipment.As supervisory control of substation master When machine initiates to be remotely controlled operation to certain primary equipment, station level is carried out by supervisory control of substation main frame and measure and control device simultaneously respectively With the verification of wall proofing rules, and operation of the locking scheduling station to the primary equipment.
In the present embodiment, measure and control device uses the PRS7741 type measure and control devices of CYG Sunrui Co., Ltd., Communication network shutdown is shut down using the PRS7910 types communication network of CYG Sunrui Co., Ltd., supervisory control of substation main frame Using tide NF8420M3 type servers, using the PRS7000 systems of CYG Sunrui Co., Ltd., scheduling station Using the PRS-7000J systems of CYG Sunrui Co., Ltd..Described being partially completed works in detail below:
1. configuration configuration, the configuration that the operational factor of transformer station's whole station is completed by supervisory control of substation main frame is configured, including distant Survey, remote signalling and remote control are configured, the proofing rules configuration of transformer station's station level and wall is generated, safeguards and verified, scheduling station (main website) and the anti-equipment table of comparisons of supervisory control of substation main frame (substation) five, substation monitored picture.
2. substation operation data acquisition, transformer station's remote measurement, remote signals that measure and control device is collected, above delivers to transformer station Monitoring host computer, via communication network shutdown on deliver to scheduling station;Measure and control device carries out five to each remote-control channel of wall in real time to be prevented Rule verification, and supervisory control of substation main frame will be sent in wall proofing rules check results, through being sent to tune in communication network shutdown Degree main website.
3. scheduling station, supervisory control of substation main frame and the main and sub multistage anti-misoperation locking in station of measure and control device cooperative achievement:
(1) main website, substation are consistent to the proofing rules information of transforming plant primary equipment.
Supervisory control of substation main frame is responsible for generating the anti-rule of the primary equipment table of comparisons and substation five between scheduling station and transformer station Then (five anti-mapped file based on two short titles, between substation), by being sent to scheduling station in IEC104 stipulations.Scheduling station is parsed After this document, the mapping one by one of primary equipment and proofing rules between main and sub station.
Supervisory control of substation main frame in the change actively of five anti-mapped files between main and sub station sending scheduling station, response scheduling Main website is called.Scheduling station is received between main and sub station after five anti-mapped files, parses its information and once setting scheduling station Standby information, proofing rules information carry out contrast verification, if inconsistent, notify that supervisory control of substation main frame is reminded and update, with ensure it is main, Primary equipment control information, proofing rules are completely the same between substation.It is main and sub station primary equipment compare sheet format as shown in annex 1, The form of proofing rules file (five anti-mapped files) is as shown in annex 2.
(2) anti-error flow during scheduling station initiation straighforward operation:
As shown in figure 3, scheduling station receives transformer station's remote measurement, the remote signalling information sent in communication network shutdown, adjusted in real time The proofing rules verification of degree main website level, is scheduling station level anti-misoperation locking verification.If being unsatisfactory for the proofing rules of scheduling station Verification, then straighforward operation flow terminates at once in scheduling station.
After the verification of scheduling station proofing rules passes through, it is unique that scheduled data network sends application operation using IEC104 stipulations The order of power is to supervisory control of substation main frame;After supervisory control of substation main frame receives the order of the unique power of scheduling station application operation, Carry out following operation:
Step one:Batch operation is uniquely weighed.Judge that whether the operation of the primary equipment for being operated is unique by transformer station Monitoring host computer or other scheduling stations take, such as now the primary equipment by supervisory control of substation main frame or other scheduling stations In operation, then directly reply the scheduling station " the unique power of operation obtains failure ", failure cause for " supervisory control of substation main frame or its During his scheduling station is operated to the primary equipment ", end operation flow.
Step 2:If the primary equipment is not operated by supervisory control of substation main frame or other scheduling stations, by this once Uniquely power distributes to the scheduling station for the operation of equipment.Then supervisory control of substation main frame verification station level proofing rules, are station control Layer anti mis-closedown function verification.If verification does not pass through, scheduling station " being unsatisfactory for substation five prevention logic " is replied, terminate remote control behaviour Make flow.
Step 3:If supervisory control of substation main frame judges station level proofing rules, verification passes through, and checks in measure and control device The real-time check results of wall proofing rules.If being unsatisfactory for the real-time check results of proofing rules, scheduling station is replied " discontented Sufficient wall five prevention logic ", terminates straighforward operation flow;If the verification of wall proofing rules passes through, by supervisory control of substation Host response scheduling station " the unique power of operation is obtained successfully ".
Step 4:After scheduling station receives supervisory control of substation main frame " the unique power of operation is obtained successfully " commands in return, pass through Dispatch data net, sends primary equipment straighforward operation order to communication network and shuts down using IEC104 stipulations, is forwarded by communication gate The order is realized to primary equipment straighforward operation to measure and control device.Wherein measure and control device can also be carried out before guidance command is performed Proofing rules verification after execution, verification could be outputed into the control loop of primary equipment guidance command after passing through.
Step 5:Treat that straighforward operation order is issued successfully, and scheduling station receives the position of controlled primary equipment and correctly becomes After change, scheduling station sends " the unique power of release operation " order and, to supervisory control of substation main frame, is reclaimed by supervisory control of substation main frame and grasped Make unique power;If supervisory control of substation main frame time-out (default setting is 120 seconds) does not receive the release behaviour that scheduling station actively sends Make unique power order, supervisory control of substation main frame carries out retrieval management, waits next time to the unique power of primary equipment operation automatically Operation.
(3) supervisory control of substation main frame initiates straighforward operation, as shown in figure 4, comprising the following steps:
Step one:Supervisory control of substation main frame checks the behaviour of the primary equipment before operation is remotely controlled to certain primary equipment Make unique power.If during the primary equipment is operated by certain scheduling station, terminating flow.
Step 2:If the primary equipment is not operated by any scheduling station, by the operation of the primary equipment only One power distributes to supervisory control of substation main frame, and supervisory control of substation main frame carries out station level proofing rules verification.If not passing through station level Proofing rules are verified, then terminate flow, while the operation for discharging primary equipment is uniquely weighed.
Step 3:The anti-verification of station level five of supervisory control of substation main frame passes through, then inspection intervals layer proofing rules verification knot Really.If do not verified by wall proofing rules, straighforward operation flow is terminated by supervisory control of substation main frame, while release one The operation of secondary device is uniquely weighed.
Step 4:Supervisory control of substation Host Detection is verified to by wall proofing rules, then by station level network, hair Guidance command to measure and control device is sent, operation is remotely controlled to primary equipment.Wherein measure and control device can also before guidance command is performed Proofing rules verification after being performed, verification could be outputed into the control loop of primary equipment guidance command after passing through. Treat that straighforward operation success, i.e. measure and control device guidance command are correctly returned and primary equipment state position correctly changes, transformer station's prison Actively release operates unique power to control main frame.
The main website of annex 1 -- substation device compares sheet format
Main website-substation device the table of comparisons, file content has four row, and form is as follows:
Equipment name English, equipment name Chinese, sequence number, five anti-substation device numberings
Wherein, " equipment name English ", " equipment name Chinese " are arranged by entering row format between main and sub station;" sequence number " is by becoming Monitoring power station main frame is responsible for creating sequencing generation by equipment;" five anti-substation device numberings " is distributed unitedly by scheduling station, Each Column Cata Format uses half-angle comma.
The proofing rules file format of annex 2
110H:1101=0,1102=0!
110L:1101=1,1102=1!
Wherein, H represents remote control point action type, and L represents remote control closing operation type;The 1101 five anti-sons for representing 1101 equipment Station equipment is numbered;1101=0 represents that 1101 equipment are in point position;“!" represent description end mark.
Above-mentioned proofing rules are expressed as:When 110 equipment is closed in remote control, 1101 equipment and 1102 equipment necessarily be in a point position Put;When 110 equipment of remote control point, 1101 equipment and 1102 equipment necessarily be in conjunction position.

Claims (10)

1. the multistage anti-error locking system in intelligent substation boss station, is provided with measure and control device, supervisory control of substation main frame and scheduling station, It is characterized in that:The measure and control device shuts down and supervisory control of substation main frame connection communication with communication network respectively, scheduling station difference With communication gate and supervisory control of substation main frame connection communication;
The supervisory control of substation main frame carries out configuration generation, maintenance to the proofing rules of measure and control device and scheduling station and verifies, The operation of management supervisory control of substation main frame and scheduling station to primary equipment is uniquely weighed, to the remote-control channel corresponding to straighforward operation Proofing rules verified, operation is remotely controlled to primary equipment;
The remote signalling information and telemetry intelligence (TELINT) of the measure and control device Real-time Collection primary equipment, through delivering to scheduling master in communication network shutdown Stand and on deliver to supervisory control of substation main frame, real-time judge currently gathers the state of information, calculate each remote-control channel five prevent Regular check results, by proofing rules check results through delivering to scheduling station in communication network shutdown and above delivering to supervisory control of substation master Machine, receives the straighforward operation order that supervisory control of substation main frame or scheduling station are sent through communication network shutdown, to the distant of straighforward operation Control passage is carried out after proofing rules verification passes through, and straighforward operation order is just issued to the operation circuit of primary equipment, and realization is to one The straighforward operation control of secondary device;
Before the scheduling station is remotely controlled operation to primary equipment, five anti-rule are carried out to the remote-control channel corresponding to the operation Then verify, by verification, the order of the unique power of operation of the transmission request to the primary equipment dispatches master to supervisory control of substation main frame Stand after obtaining the unique power of operation from supervisory control of substation main frame, send to the straighforward operation order of primary equipment through communication network shut down to Measure and control device, scheduling station receives remote measurement, the remote signalling information that communication network shutdown is sent, and refreshes the instantaneous value of scheduling station real-time database State, produces the alarm record of correspondence transformer station.
2. the multistage anti-error locking system in intelligent substation boss according to claim 1 station, it is characterised in that:The observing and controlling Device respectively with communication network shutdown and supervisory control of substation main frame communicated using station level network connection, scheduling station respectively with communication Gateway and supervisory control of substation main frame use dispatch data net connection communication.
3. the multistage anti-error locking system in intelligent substation boss according to claim 1 station, it is characterised in that:The management The operation of supervisory control of substation main frame and scheduling station to primary equipment is uniquely weighed, and scheduling station or supervisory control of substation main frame will be obtained Unique power is operated, it is necessary to be verified to the proofing rules of corresponding remote-control channel after operation to certain primary equipment, it is then right Supervisory control of substation main frame is filed an application, and supervisory control of substation main frame carries out proofing rules verification, after verification passes through, checks measure and control device The five anti-check results sent in real time, then batch operation is responsible for by supervisory control of substation main frame uniquely weighs, supervisory control of substation main frame or After the operation for obtaining certain primary equipment is uniquely weighed, supervisory control of substation main frame locking miscellaneous equipment is to the primary equipment for scheduling station Operation.
4. the multistage anti-error locking system in intelligent substation boss according to claim 3 station, it is characterised in that:The power transformation Stand monitoring host computer and scheduling station obtains the operation of transforming plant primary equipment is uniquely weighed, and using whose first to file, who first obtains Principle.
5. the multistage anti-error locking system in intelligent substation boss according to claim 4 station, it is characterised in that:The power transformation Stand monitoring host computer or scheduling station obtains the operation of certain primary equipment uniquely after power, complete once to set this within the time of regulation Standby straighforward operation, after operation execution terminates, actively discharges this operation to the primary equipment and uniquely weighs.
6. the multistage anti-error locking system in intelligent substation boss according to claim 5 station, it is characterised in that:The power transformation After the operation of monitoring host computer or scheduling station enforcement to primary equipment of standing uniquely is weighed, actively release operates unique power, by power transformation Monitoring host computer of standing is reclaimed or the unique power of release operation.
7. the multistage anti-error locking system in intelligent substation boss according to claim 1 station, it is characterised in that:The observing and controlling Device receives the straighforward operation order that supervisory control of substation main frame or scheduling station are sent through communication network shutdown, to the distant of straighforward operation Control passage carries out corresponding proofing rules verification and does not pass through, the measure and control device locking straighforward operation order, replys remote control and unsuccessfully reports Text arrives supervisory control of substation main frame or scheduling station.
8. the multistage anti-error locking system in intelligent substation boss according to claim 1 station, it is characterised in that:The scheduling Before main website is remotely controlled operation to primary equipment, proofing rules verification is carried out to the remote-control channel corresponding to the operation, do not led to Verification is crossed to stop operation.
9. the multistage anti-error locking system in intelligent substation boss according to claim 2 station, it is characterised in that:The observing and controlling Device is carried out with communication network shutdown and supervisory control of substation main-machine communication by the agreements of IEC 61850 respectively, communication network shutdown and Scheduling station communication is carried out by by the stipulations of IEC 104, described to be carried out by by the stipulations of IEC 104 with supervisory control of substation main-machine communication.
10. the multistage anti-error locking system in intelligent substation boss according to claim 1 station, it is characterised in that:The pipe The operation of reason supervisory control of substation main frame and scheduling station to primary equipment is uniquely weighed, and scheduling station or supervisory control of substation main frame will be obtained Take and, it is necessary to be verified to the proofing rules of corresponding remote-control channel after operation, then unique power is operated to certain primary equipment Supervisory control of substation main frame is filed an application, batch operation is responsible for by supervisory control of substation main frame and is uniquely weighed, supervisory control of substation main frame enters Row proofing rules are verified, after verification passes through, check measure and control device it is real-time on the five anti-check results sent, supervisory control of substation main frame or After the operation for obtaining certain primary equipment is uniquely weighed, supervisory control of substation main frame locking miscellaneous equipment is to the primary equipment for scheduling station Operation.
CN201710068771.8A 2017-02-08 2017-02-08 The multistage anti-error locking system in intelligent substation boss station Active CN106712300B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710068771.8A CN106712300B (en) 2017-02-08 2017-02-08 The multistage anti-error locking system in intelligent substation boss station

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710068771.8A CN106712300B (en) 2017-02-08 2017-02-08 The multistage anti-error locking system in intelligent substation boss station

Publications (2)

Publication Number Publication Date
CN106712300A true CN106712300A (en) 2017-05-24
CN106712300B CN106712300B (en) 2019-06-25

Family

ID=58909975

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710068771.8A Active CN106712300B (en) 2017-02-08 2017-02-08 The multistage anti-error locking system in intelligent substation boss station

Country Status (1)

Country Link
CN (1) CN106712300B (en)

Cited By (14)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109768619A (en) * 2018-11-20 2019-05-17 重庆甘润科技有限公司 Monitoring information automatic debugging system and adjustment method
CN109787356A (en) * 2018-12-11 2019-05-21 许昌许继软件技术有限公司 A kind of transformer substation remote-control method for preventing misoperation and system based on IEC61850 specification
CN109818420A (en) * 2019-03-26 2019-05-28 国网北京市电力公司 Measuring and controlling equipment and TT&C system
CN110414906A (en) * 2018-04-26 2019-11-05 广东电网有限责任公司 A kind of online checking method of transformer substation remote-control information and system
CN110620429A (en) * 2018-06-20 2019-12-27 北京金风慧能技术有限公司 Batch control method and centralized control system for new energy station and communication gateway machine
CN110752667A (en) * 2019-09-17 2020-02-04 国网山东省电力公司青州市供电公司 Five-prevention integrated misoperation-preventing locking operation and monitoring system for transformer substation
CN110995794A (en) * 2019-11-19 2020-04-10 许继集团有限公司 Debugging workstation, network shutdown machine and remote power data acquisition method
CN111740491A (en) * 2020-05-14 2020-10-02 许继集团有限公司 Substation data communication gateway machine and control method and control device thereof
CN111917179A (en) * 2020-07-02 2020-11-10 江苏胜太电力***有限公司 Real-time online anti-misoperation system of transformer substation based on multimode internet of things
CN111934429A (en) * 2020-08-04 2020-11-13 国网河北省电力有限公司邯郸供电分公司 Method for controlling sequence of calling station end of regulation and control main station
CN112017336A (en) * 2020-09-03 2020-12-01 云南电网有限责任公司信息中心 Method and device for automatic authorization and safe anti-misoperation locking of intelligent lock
CN113612629A (en) * 2021-07-12 2021-11-05 许继电气股份有限公司 Anti-error method and system for overhauling master station, internet access machine and configuration modification of internet access machine
CN114069862A (en) * 2021-11-17 2022-02-18 许继集团有限公司 Transformer substation on-site monitoring and master station information double-checking method and device
CN114648869A (en) * 2022-03-10 2022-06-21 东方电子股份有限公司 Remote control instruction operation method for electric power protection measurement and control device

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104600849A (en) * 2015-02-25 2015-05-06 国电南瑞科技股份有限公司 Smart power grid master station and substation depth anti-misoperation system implementation method
CN105958650A (en) * 2016-06-17 2016-09-21 国网浙江省电力公司绍兴供电公司 Electric power communication protocol extension-based master substation remote programmed control method

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104600849A (en) * 2015-02-25 2015-05-06 国电南瑞科技股份有限公司 Smart power grid master station and substation depth anti-misoperation system implementation method
CN105958650A (en) * 2016-06-17 2016-09-21 国网浙江省电力公司绍兴供电公司 Electric power communication protocol extension-based master substation remote programmed control method

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
林静怀等: ""智能电网调度控制***的远方操作安全防误技术"", 《电力***自动化》 *

Cited By (20)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110414906A (en) * 2018-04-26 2019-11-05 广东电网有限责任公司 A kind of online checking method of transformer substation remote-control information and system
CN110620429A (en) * 2018-06-20 2019-12-27 北京金风慧能技术有限公司 Batch control method and centralized control system for new energy station and communication gateway machine
CN110620429B (en) * 2018-06-20 2021-06-08 北京金风慧能技术有限公司 Batch control method and centralized control system for new energy station and communication gateway machine
CN109768619A (en) * 2018-11-20 2019-05-17 重庆甘润科技有限公司 Monitoring information automatic debugging system and adjustment method
CN109787356A (en) * 2018-12-11 2019-05-21 许昌许继软件技术有限公司 A kind of transformer substation remote-control method for preventing misoperation and system based on IEC61850 specification
CN109787356B (en) * 2018-12-11 2021-06-04 许昌许继软件技术有限公司 Transformer substation remote control anti-misoperation method and system based on IEC61850 protocol
CN109818420A (en) * 2019-03-26 2019-05-28 国网北京市电力公司 Measuring and controlling equipment and TT&C system
CN110752667A (en) * 2019-09-17 2020-02-04 国网山东省电力公司青州市供电公司 Five-prevention integrated misoperation-preventing locking operation and monitoring system for transformer substation
CN110995794A (en) * 2019-11-19 2020-04-10 许继集团有限公司 Debugging workstation, network shutdown machine and remote power data acquisition method
CN110995794B (en) * 2019-11-19 2022-07-15 许继集团有限公司 Remote acquisition method of electric power data
CN111740491A (en) * 2020-05-14 2020-10-02 许继集团有限公司 Substation data communication gateway machine and control method and control device thereof
CN111917179A (en) * 2020-07-02 2020-11-10 江苏胜太电力***有限公司 Real-time online anti-misoperation system of transformer substation based on multimode internet of things
CN111917179B (en) * 2020-07-02 2024-04-30 江苏胜太电力***有限公司 Real-time online misoperation prevention system of transformer substation based on multimode internet of things
CN111934429A (en) * 2020-08-04 2020-11-13 国网河北省电力有限公司邯郸供电分公司 Method for controlling sequence of calling station end of regulation and control main station
CN112017336A (en) * 2020-09-03 2020-12-01 云南电网有限责任公司信息中心 Method and device for automatic authorization and safe anti-misoperation locking of intelligent lock
CN113612629B (en) * 2021-07-12 2024-01-16 许继电气股份有限公司 Anti-misoperation method and system for overhauling master station, gateway machine and configuration modification of gateway machine
CN113612629A (en) * 2021-07-12 2021-11-05 许继电气股份有限公司 Anti-error method and system for overhauling master station, internet access machine and configuration modification of internet access machine
CN114069862A (en) * 2021-11-17 2022-02-18 许继集团有限公司 Transformer substation on-site monitoring and master station information double-checking method and device
CN114648869A (en) * 2022-03-10 2022-06-21 东方电子股份有限公司 Remote control instruction operation method for electric power protection measurement and control device
CN114648869B (en) * 2022-03-10 2023-03-14 东方电子股份有限公司 Remote control instruction operation method for power protection measurement and control device

Also Published As

Publication number Publication date
CN106712300B (en) 2019-06-25

Similar Documents

Publication Publication Date Title
CN106712300A (en) Intelligent master station and sub-station multi-level anti-misoperation locking system
CN105914881B (en) A kind of intelligent substation advanced application system
CN103441570A (en) One-button type sequential control operation control method based on integrated information platform
CN105388370B (en) A kind of substation's wall connection latching logic automated closed-loop test method
CN105406603B (en) A kind of power grid regulation end anti-incorrect manipulation deadlock method
CN105262220B (en) Substation's intelligence shutdown telecontrol information check method and system
CN104467183A (en) Dispatch anti-misoperation system for regional power grid in adjustment and control integrated mode
CN106532660B (en) A kind of main station system, remote system and the control method of relay fixed value modification
CN104463696A (en) Power grid operating risk recognition and prevention method and system
CN107834699A (en) Dispatching of power netwoks based on the regulation and control integration of ground county integrates anti-error system
CN106532955A (en) Implementation method for remote measurement identification function of centralized monitoring transformer station
CN104750095B (en) Regulation and control center inspection pilot system and method
CN109473945A (en) A kind of verification of relay protection model data and method of automatic configuration
CN115313662A (en) Distribution automation intelligence auxiliary tool that patrols and examines
CN107359702A (en) Intelligent linkage Interlocking Methods based on IES700 systems
CN105978146A (en) Way of communication between D5000 scheduling automation master station system and substation five-prevention system
CN107181321A (en) It is a kind of that the quick method for drawing lotus is realized based on topological structure of electric
CN104682566B (en) A kind of new energy power station Fault Identification and condition monitoring system
CN109587161A (en) The monitoring method of smart grid remote control command transmission overall process information
CN106570613A (en) Secondary equipment maintenance strategy generation method based on state monitoring
CN115800519A (en) Control method for ice melting switching one-key sequential control
CN109768619A (en) Monitoring information automatic debugging system and adjustment method
CN106953840B (en) A kind of water power far controls platform method for preventing misoperation
CN105337257A (en) Adaptive method for realizing substation area protection fixed value based on center server
CN109713791A (en) The diagnostic method of smart grid remote control command exception

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant