CN106703070A - Construction method of roof photovoltaic strip foundation - Google Patents
Construction method of roof photovoltaic strip foundation Download PDFInfo
- Publication number
- CN106703070A CN106703070A CN201611020380.0A CN201611020380A CN106703070A CN 106703070 A CN106703070 A CN 106703070A CN 201611020380 A CN201611020380 A CN 201611020380A CN 106703070 A CN106703070 A CN 106703070A
- Authority
- CN
- China
- Prior art keywords
- template
- concrete
- construction
- reinforcing bar
- colligation
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 238000010276 construction Methods 0.000 title claims abstract description 81
- 229910000831 Steel Inorganic materials 0.000 claims abstract description 25
- 239000010959 steel Substances 0.000 claims abstract description 25
- 238000012545 processing Methods 0.000 claims abstract description 12
- 230000003014 reinforcing effect Effects 0.000 claims description 61
- 230000033228 biological regulation Effects 0.000 claims description 20
- 238000000034 method Methods 0.000 claims description 17
- 238000003780 insertion Methods 0.000 claims description 15
- 230000037431 insertion Effects 0.000 claims description 15
- 238000009434 installation Methods 0.000 claims description 15
- 230000002787 reinforcement Effects 0.000 claims description 14
- 238000013461 design Methods 0.000 claims description 11
- XEEYBQQBJWHFJM-UHFFFAOYSA-N Iron Chemical compound [Fe] XEEYBQQBJWHFJM-UHFFFAOYSA-N 0.000 claims description 10
- 238000005259 measurement Methods 0.000 claims description 10
- 238000005086 pumping Methods 0.000 claims description 10
- 238000003466 welding Methods 0.000 claims description 9
- 238000005516 engineering process Methods 0.000 claims description 7
- 239000000463 material Substances 0.000 claims description 7
- 229910001294 Reinforcing steel Inorganic materials 0.000 claims description 5
- 238000005452 bending Methods 0.000 claims description 5
- 238000005422 blasting Methods 0.000 claims description 5
- 230000001680 brushing effect Effects 0.000 claims description 5
- 239000003795 chemical substances by application Substances 0.000 claims description 5
- 238000001816 cooling Methods 0.000 claims description 5
- 239000003344 environmental pollutant Substances 0.000 claims description 5
- 239000004744 fabric Substances 0.000 claims description 5
- 230000004886 head movement Effects 0.000 claims description 5
- 229910052742 iron Inorganic materials 0.000 claims description 5
- JEIPFZHSYJVQDO-UHFFFAOYSA-N iron(III) oxide Inorganic materials O=[Fe]O[Fe]=O JEIPFZHSYJVQDO-UHFFFAOYSA-N 0.000 claims description 5
- 238000011418 maintenance treatment Methods 0.000 claims description 5
- 230000000116 mitigating effect Effects 0.000 claims description 5
- 239000003973 paint Substances 0.000 claims description 5
- 239000012188 paraffin wax Substances 0.000 claims description 5
- 231100000719 pollutant Toxicity 0.000 claims description 5
- 238000002360 preparation method Methods 0.000 claims description 5
- 230000008569 process Effects 0.000 claims description 5
- 239000011241 protective layer Substances 0.000 claims description 5
- 239000002994 raw material Substances 0.000 claims description 5
- 238000005070 sampling Methods 0.000 claims description 5
- 239000002002 slurry Substances 0.000 claims description 5
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 claims description 5
- 210000003205 muscle Anatomy 0.000 claims 1
- 238000009435 building construction Methods 0.000 abstract description 2
- 238000004140 cleaning Methods 0.000 abstract 1
- 239000012535 impurity Substances 0.000 abstract 1
- 239000000047 product Substances 0.000 description 4
- 239000010410 layer Substances 0.000 description 2
- 230000009286 beneficial effect Effects 0.000 description 1
- 239000006227 byproduct Substances 0.000 description 1
- 230000008859 change Effects 0.000 description 1
- 230000006835 compression Effects 0.000 description 1
- 238000007906 compression Methods 0.000 description 1
- 238000012407 engineering method Methods 0.000 description 1
- 230000006872 improvement Effects 0.000 description 1
- 230000035800 maturation Effects 0.000 description 1
- 230000009467 reduction Effects 0.000 description 1
- 239000002689 soil Substances 0.000 description 1
- 230000006641 stabilisation Effects 0.000 description 1
- 238000011105 stabilization Methods 0.000 description 1
- 239000000758 substrate Substances 0.000 description 1
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D27/00—Foundations as substructures
- E02D27/32—Foundations for special purposes
- E02D27/44—Foundations for machines, engines or ordnance
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04D—ROOF COVERINGS; SKY-LIGHTS; GUTTERS; ROOF-WORKING TOOLS
- E04D13/00—Special arrangements or devices in connection with roof coverings; Protection against birds; Roof drainage ; Sky-lights
Landscapes
- Engineering & Computer Science (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Architecture (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Mining & Mineral Resources (AREA)
- Paleontology (AREA)
- General Engineering & Computer Science (AREA)
- On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)
Abstract
The invention belongs to the field of building construction and particularly relates to a construction method of a roof photovoltaic strip foundation. The construction method of the roof photovoltaic strip foundation comprises the following steps: (1) preparing construction; (2) cleaning impurities on the roof; (3) surveying and setting out; (4) processing steel bars; (5) processing and mounting templates; (6) binding and checking the steel bars; (7) pouring concrete; and (8) curing the concrete and removing the templates.
Description
Technical field
The invention belongs to the realm of building construction, and in particular to roofing photovoltaic strip footing construction.
Background technology
Photovoltaic foundation typically uses isolated footing and strip footing.It has been a maturation that strip footing is constructed on the ground
Construction technology, but strip footing roofing construction appoint can so have the following disadvantages:1st, difficulty of construction is bigger, easily to room
Face waterproof and structure sheaf are damaged, destroy it is serious even to lay waterproof layer again, this obviously to construction bring it is many not
Just, it is also never to allow;2nd, construction procedure is cumbersome, and construction progress is slow;3rd, construction interference is more.
The content of the invention
Goal of the invention:The present invention makes improvement for the problem that above-mentioned prior art is present, i.e., the invention discloses roofing
Photovoltaic strip footing construction.
Technical scheme:Roofing photovoltaic strip footing construction, comprises the following steps:
(1), preparation of construction
(11), it is familiar with construction drawing, confirms concrete foundation elevation, center line, length, each built-in fitting and rebar sizes spacing
Meet design requirement;
(12) arrangement and method for construction, is worked out, construction technology design is carried out;
(13), according to construction drawing and field condition, computation and measurement goes out the consumption of reinforcing bar, concrete, template;
(2), the debris to roofing are cleared up
(3), surveying setting-out
Before construction, setting-out is measured using total powerstation according to construction drawing, and relevant axis are indicated with red paint
Position, and repetition measurement is carried out according to drawing axis and construction requirement,
(4), steel bar meter
(41), raw material of reinforcement rebar
(411), the kind of reinforcing bar, rank, specification, quantity have to comply with the regulation of drawing;
(412), every batch of reinforcing bar detected using preceding to its mechanical performance, is detected qualified and is reported rear to a higher authorities for approval and can be used;
(413), after the entering of reinforcing steel bar, nameplate is checked and accepted, stacks and set up respectively by grade, specification, and be sampled censorship;
(414), sampling censorship substandard product removes appearance immediately;
(42) steel bar meter
(421), colligation and welding, the bending of reinforcing bar, the termination of reinforcing bar and joint should all meet and set steel bar meter at the scene
The requirement of meter;
(422), treat after the completion of steel bar meter, the pollutant of rebar surface and iron rust are removed clean;
(5), template processing and installation
(51), template processing
Strict to make template by construction drawing size, requirement, template construct answers physical dimension accurate, and surfacing is bright and clean, and
In the inner side brushing paraffin release agent of template;
(52), template transport and installation
(521), template must assure that template is without damage, pollution-free in transport to roofing procedures;
(522), template is covered when stacking with cloth, and template is protected;
(523), notice that split joint is closely knit during model sheetinstallat, it is ensured that do not reveal slurry;
(6), reinforcing bar colligation and examination
(61), using manually carrying out reinforcing bar carrying;
(62), the colligation of reinforcing bar is performed in strict accordance with regulation, and colligation is firm, smooth vertical and horizontal;
(63), the size of the position of reinforcement installation, spacing, protective layer thickness and reinforcing bar, size are both needed to meet construction drawing
Regulation;
(64), the overlap joint or weld length of reinforcing bar, then position should meet drawing regulation;
(65) after the completion of reinforcing bar colligation, press《Concrete structure engineering job specfication》GB50666-2011 standards, construction drawing
And《Reinforcement welding and control of acceptance》JGJ18-2012 code requirements are inspected for acceptance, and are made a record;
(7), concreting
(71), concreting is used based on truck mounted pumping, and pump rate is 50~60m3/ h, part basis use people
Work is poured, and is being poured simultaneously, and vibrating head movement should be moved immediately following concrete duct;
(72) speed of vibrating head insertion, is noted during concreting, the depth in vibrating head insertion concrete is aggregate depth
The 2/3~3/4 of degree, speed is maintained at 12 beats/min, and when keeping vibrating for 4~5 seconds in concrete after insertion, vibrator must not be touched
Template is hit, the fast theory inserted and pull out slowly should be observed, when pouring near marking line, pumping line is tried one's best away from pump rate is changed to
50m3/h;
(73), concrete before pouring in horizontal wall inscription and longitudinal slope bottom reserving hole, it is ensured that roof drainage is not influenceed by basis;
(8), concrete curing, form removal
(81), the surface to strip footing concrete is processed by shot blasting, maintenance treatment is carried out after determining pore-free;
(82), after concreting, in mould outer wrapping puggaree or cooling of watering, and oversite concrete surface immediately, enter
Row heat and moisture preserving is conserved;
(83), during conserving, when temperature is higher than 10 DEG C, to retaining material timing water filling ensureing constant moisture shape
State;
(84), during conserving, people is forbidden to be walked on concrete;
(85), non-bearing template must after concrete strength reaches 75% form removal, bearing form reaches in intensity
Form removal after 90%;In demolishing process, it is impossible to which cruelty is removed, form removable should take impact mitigation measure;Form removable is just abided by
Follow and first tear open non-bearing template, after tear the theory of bearing form open.
Further, the middle setting foundation elevation of step (3) is within 5mm.
Further, the reinforcing bar without the quality certification and report of dispatching from the factory in step (413) forbids admission.
Beneficial effect:Roofing photovoltaic strip footing construction disclosed by the invention has the advantages that:
By changing roofing photovoltaic base form, traditional independent shape basis is substituted with small-sized strip footing, solve biography
System photovoltaic roof basis is uneven using the roofing load that isolated footing is brought, structure, waterproof layer destructible, and structure is not
The shortcoming of stabilization, is not only improved in quality and roof structure stability, also reduces construction cost.
Carrying out photovoltaic roof construction using this engineering method makes the engineering time shorten 6 days;Skilled worker's saving of time 6X32=192
Man-hour, 192X180 units/man-hour=34560 yuan, general 6X8=48 man-hour of work saving of time, 48X150 units/man-hour=7200 yuan;
Only labour cost just saves 41760 yuan of fund;Use strip footing instead also makes material used in construction (mixed instead of detached pier basis
Solidifying soil, reinforcing bar, template) amount to 15000 yuan of reduction;Total makes cost reduce 55760 yuan.
Brief description of the drawings
Fig. 1 is the flow chart of roofing photovoltaic strip footing construction disclosed by the invention.
Specific embodiment:
Specific embodiment of the invention is described in detail below.
As shown in figure 1, roofing photovoltaic strip footing construction, comprises the following steps:
(1), preparation of construction
(11), it is familiar with construction drawing, confirms concrete foundation elevation, center line, length, each built-in fitting and rebar sizes spacing
Meet design requirement;
(12) arrangement and method for construction, is worked out, construction technology design is carried out;
(13), according to construction drawing and field condition, computation and measurement goes out the consumption of reinforcing bar, concrete, template;
(2), the debris to roofing are cleared up
(3), surveying setting-out
Before construction, setting-out is measured using total powerstation according to construction drawing, and relevant axis are indicated with red paint
Position, and repetition measurement is carried out according to drawing axis and construction requirement,
(4), steel bar meter
(41), raw material of reinforcement rebar
(411), the kind of reinforcing bar, rank, specification, quantity have to comply with the regulation of drawing;
(412), every batch of reinforcing bar detected using preceding to its mechanical performance, is detected qualified and is reported rear to a higher authorities for approval and can be used;
(413), after the entering of reinforcing steel bar, nameplate is checked and accepted, stacks and set up respectively by grade, specification, and be sampled censorship;
(414), sampling censorship substandard product removes appearance immediately;
(42) steel bar meter
(421), colligation and welding, the bending of reinforcing bar, the termination of reinforcing bar and joint should all meet and set steel bar meter at the scene
The requirement of meter;
(422), treat after the completion of steel bar meter, the pollutant of rebar surface and iron rust are removed clean;
(5), template processing and installation
(51), template processing
Strict to make template by construction drawing size, requirement, template construct answers physical dimension accurate, and surfacing is bright and clean, and
In the inner side brushing paraffin release agent of template;
(52), template transport and installation
(521), template must assure that template is without damage, pollution-free in transport to roofing procedures;
(522), template is covered when stacking with cloth, and template is protected;
(523), notice that split joint is closely knit during model sheetinstallat, it is ensured that do not reveal slurry;
(6), reinforcing bar colligation and examination
(61), using manually carrying out reinforcing bar carrying;
(62), the colligation of reinforcing bar is performed in strict accordance with regulation, and colligation is firm, smooth vertical and horizontal;
(63), the size of the position of reinforcement installation, spacing, protective layer thickness and reinforcing bar, size are both needed to meet construction drawing
Regulation;
(64), the overlap joint or weld length of reinforcing bar, then position should meet drawing regulation;
(65) after the completion of reinforcing bar colligation, press《Concrete structure engineering job specfication》GB50666-2011 standards, construction drawing
And《Reinforcement welding and control of acceptance》JGJ18-2012 code requirements are inspected for acceptance, and are made a record;
(7), concreting
(71), concreting is used based on truck mounted pumping, and pump rate is 50m3/ h, part basis are used and manually poured
Build, pouring simultaneously, vibrating head movement should be moved immediately following concrete duct;
(72) speed of vibrating head insertion, is noted during concreting, the depth in vibrating head insertion concrete is aggregate depth
The 2/3 of degree, speed is maintained at 12 beats/min, is kept when vibrating within 4 seconds in concrete after insertion, vibrator must not collision slab, should
The slow theory pulled out is inserted in accordance with fast, when pouring near marking line, pumping line is tried one's best away from pump rate is changed to 50m3/h;
(73), concrete before pouring in horizontal wall inscription and longitudinal slope bottom reserving hole, it is ensured that roof drainage is not influenceed by basis;
(8), concrete curing, form removal
(81), the surface to strip footing concrete is processed by shot blasting, maintenance treatment is carried out after determining pore-free;
(82), after concreting, in mould outer wrapping puggaree or cooling of watering, and oversite concrete surface immediately, enter
Row heat and moisture preserving is conserved;
(83), during conserving, when temperature is higher than 10 DEG C, to retaining material timing water filling ensureing constant moisture shape
State;
(84), during conserving, people is forbidden to be walked on concrete;
(85), non-bearing template must after concrete strength reaches 75% form removal, bearing form reaches in intensity
Form removal after 90%;In demolishing process, it is impossible to which cruelty is removed, form removable should take impact mitigation measure;Form removable is just abided by
Follow and first tear open non-bearing template, after tear the theory of bearing form open.
Further, the middle setting foundation elevation of step (3) is within 5mm.
Further, the reinforcing bar without the quality certification and report of dispatching from the factory in step (413) forbids admission.
The load that roofing can be transmitted superstructure using strip footing concrete, certain bottom surface is extended to by side
Product, makes the compression for acting on substrate be equal to or less than the permitted bearing capacity of roofing, and the stress of basic internal should meet simultaneously
Material intensity requirement in itself.
Roofing photovoltaic uses strip footing concrete, the pre-embedded steel slab in photovoltaic strip footing to increase supporting leg to solve
The roof drainage gradient, it is ensured that photovoltaic panel is in same level.Roofing strip footing solves the buttress that traditional roof photovoltaic is used
The discontinuity that isolated footing is brought, the shortcomings of local pressure is larger;Pre-embedded steel slab facilitates photovoltaic bracket to install on the basis of
Shi Jinhang is welded.Thus unwrapping wire positioning in work progress to basis seems increasingly important.Additionally, the pendulum of strip footing concrete
Put position and spacing also contributes to roofing stress.
Specific embodiment 2
Roofing photovoltaic strip footing construction, comprises the following steps:
(1), preparation of construction
(11), it is familiar with construction drawing, confirms concrete foundation elevation, center line, length, each built-in fitting and rebar sizes spacing
Meet design requirement;
(12) arrangement and method for construction, is worked out, construction technology design is carried out;
(13), according to construction drawing and field condition, computation and measurement goes out the consumption of reinforcing bar, concrete, template;
(2), the debris to roofing are cleared up
(3), surveying setting-out
Before construction, setting-out is measured using total powerstation according to construction drawing, and relevant axis are indicated with red paint
Position, and repetition measurement is carried out according to drawing axis and construction requirement,
(4), steel bar meter
(41), raw material of reinforcement rebar
(411), the kind of reinforcing bar, rank, specification, quantity have to comply with the regulation of drawing;
(412), every batch of reinforcing bar detected using preceding to its mechanical performance, is detected qualified and is reported rear to a higher authorities for approval and can be used;
(413), after the entering of reinforcing steel bar, nameplate is checked and accepted, stacks and set up respectively by grade, specification, and be sampled censorship;
(414), sampling censorship substandard product removes appearance immediately;
(42) steel bar meter
(421), colligation and welding, the bending of reinforcing bar, the termination of reinforcing bar and joint should all meet and set steel bar meter at the scene
The requirement of meter;
(422), treat after the completion of steel bar meter, the pollutant of rebar surface and iron rust are removed clean;
(5), template processing and installation
(51), template processing
Strict to make template by construction drawing size, requirement, template construct answers physical dimension accurate, and surfacing is bright and clean, and
In the inner side brushing paraffin release agent of template;
(52), template transport and installation
(521), template must assure that template is without damage, pollution-free in transport to roofing procedures;
(522), template is covered when stacking with cloth, and template is protected;
(523), notice that split joint is closely knit during model sheetinstallat, it is ensured that do not reveal slurry;
(6), reinforcing bar colligation and examination
(61), using manually carrying out reinforcing bar carrying;
(62), the colligation of reinforcing bar is performed in strict accordance with regulation, and colligation is firm, smooth vertical and horizontal;
(63), the size of the position of reinforcement installation, spacing, protective layer thickness and reinforcing bar, size are both needed to meet construction drawing
Regulation;
(64), the overlap joint or weld length of reinforcing bar, then position should meet drawing regulation;
(65) after the completion of reinforcing bar colligation, press《Concrete structure engineering job specfication》GB50666-2011 standards, construction drawing
And《Reinforcement welding and control of acceptance》JGJ18-2012 code requirements are inspected for acceptance, and are made a record;
(7), concreting
(71), concreting is used based on truck mounted pumping, and pump rate is 60m3/ h, part basis are used and manually poured
Build, pouring simultaneously, vibrating head movement should be moved immediately following concrete duct;
(72) speed of vibrating head insertion, is noted during concreting, the depth in vibrating head insertion concrete is aggregate depth
The 3/4 of degree, speed is maintained at 12 beats/min, is kept when vibrating within 5 seconds in concrete after insertion, vibrator must not collision slab, should
The slow theory pulled out is inserted in accordance with fast, when pouring near marking line, pumping line is tried one's best away from pump rate is changed to 50m3/h;
(73), concrete before pouring in horizontal wall inscription and longitudinal slope bottom reserving hole, it is ensured that roof drainage is not influenceed by basis;
(8), concrete curing, form removal
(81), the surface to strip footing concrete is processed by shot blasting, maintenance treatment is carried out after determining pore-free;
(82), after concreting, in mould outer wrapping puggaree or cooling of watering, and oversite concrete surface immediately, enter
Row heat and moisture preserving is conserved;
(83), during conserving, when temperature is higher than 10 DEG C, to retaining material timing water filling ensureing constant moisture shape
State;
(84), during conserving, people is forbidden to be walked on concrete;
(85), non-bearing template must after concrete strength reaches 75% form removal, bearing form reaches in intensity
Form removal after 90%;In demolishing process, it is impossible to which cruelty is removed, form removable should take impact mitigation measure;Form removable is just abided by
Follow and first tear open non-bearing template, after tear the theory of bearing form open.
Further, the middle setting foundation elevation of step (3) is within 5mm.
Further, the reinforcing bar without the quality certification and report of dispatching from the factory in step (413) forbids admission.
Specific embodiment 3
Roofing photovoltaic strip footing construction, comprises the following steps:
(1), preparation of construction
(11), it is familiar with construction drawing, confirms concrete foundation elevation, center line, length, each built-in fitting and rebar sizes spacing
Meet design requirement;
(12) arrangement and method for construction, is worked out, construction technology design is carried out;
(13), according to construction drawing and field condition, computation and measurement goes out the consumption of reinforcing bar, concrete, template;
(2), the debris to roofing are cleared up
(3), surveying setting-out
Before construction, setting-out is measured using total powerstation according to construction drawing, and relevant axis are indicated with red paint
Position, and repetition measurement is carried out according to drawing axis and construction requirement,
(4), steel bar meter
(41), raw material of reinforcement rebar
(411), the kind of reinforcing bar, rank, specification, quantity have to comply with the regulation of drawing;
(412), every batch of reinforcing bar detected using preceding to its mechanical performance, is detected qualified and is reported rear to a higher authorities for approval and can be used;
(413), after the entering of reinforcing steel bar, nameplate is checked and accepted, stacks and set up respectively by grade, specification, and be sampled censorship;
(414), sampling censorship substandard product removes appearance immediately;
(42) steel bar meter
(421), colligation and welding, the bending of reinforcing bar, the termination of reinforcing bar and joint should all meet and set steel bar meter at the scene
The requirement of meter;
(422), treat after the completion of steel bar meter, the pollutant of rebar surface and iron rust are removed clean;
(5), template processing and installation
(51), template processing
Strict to make template by construction drawing size, requirement, template construct answers physical dimension accurate, and surfacing is bright and clean, and
In the inner side brushing paraffin release agent of template;
(52), template transport and installation
(521), template must assure that template is without damage, pollution-free in transport to roofing procedures;
(522), template is covered when stacking with cloth, and template is protected;
(523), notice that split joint is closely knit during model sheetinstallat, it is ensured that do not reveal slurry;
(6), reinforcing bar colligation and examination
(61), using manually carrying out reinforcing bar carrying;
(62), the colligation of reinforcing bar is performed in strict accordance with regulation, and colligation is firm, smooth vertical and horizontal;
(63), the size of the position of reinforcement installation, spacing, protective layer thickness and reinforcing bar, size are both needed to meet construction drawing
Regulation;
(64), the overlap joint or weld length of reinforcing bar, then position should meet drawing regulation;
(65) after the completion of reinforcing bar colligation, press《Concrete structure engineering job specfication》GB50666-2011 standards, construction drawing
And《Reinforcement welding and control of acceptance》JGJ18-2012 code requirements are inspected for acceptance, and are made a record;
(7), concreting
(71), concreting is used based on truck mounted pumping, and pump rate is 55m3/ h, part basis are used and manually poured
Build, pouring simultaneously, vibrating head movement should be moved immediately following concrete duct;
(72) speed of vibrating head insertion, is noted during concreting, the depth in vibrating head insertion concrete is aggregate depth
The 7/10 of degree, speed is maintained at 12 beats/min, and when keeping vibrating for 4.5 seconds in concrete after insertion, vibrator must not collide mould
Plate, should observe the fast theory inserted and pull out slowly, and when pouring near marking line, pumping line is tried one's best away from pump rate is changed to 50m3/
h;
(73), concrete before pouring in horizontal wall inscription and longitudinal slope bottom reserving hole, it is ensured that roof drainage is not influenceed by basis;
(8), concrete curing, form removal
(81), the surface to strip footing concrete is processed by shot blasting, maintenance treatment is carried out after determining pore-free;
(82), after concreting, in mould outer wrapping puggaree or cooling of watering, and oversite concrete surface immediately, enter
Row heat and moisture preserving is conserved;
(83), during conserving, when temperature is higher than 10 DEG C, to retaining material timing water filling ensureing constant moisture shape
State;
(84), during conserving, people is forbidden to be walked on concrete;
(85), non-bearing template must after concrete strength reaches 75% form removal, bearing form reaches in intensity
Form removal after 90%;In demolishing process, it is impossible to which cruelty is removed, form removable should take impact mitigation measure;Form removable is just abided by
Follow and first tear open non-bearing template, after tear the theory of bearing form open.
Further, the middle setting foundation elevation of step (3) is within 5mm.
Further, the reinforcing bar without the quality certification and report of dispatching from the factory in step (413) forbids admission.
Embodiments of the present invention are elaborated above.But the present invention is not limited to above-mentioned implementation method,
In the ken that art those of ordinary skill possesses, can also be done on the premise of present inventive concept is not departed from
Go out various change.
Claims (3)
1. roofing photovoltaic strip footing construction, it is characterised in that comprise the following steps:
(1), preparation of construction
(11), it is familiar with construction drawing, confirms that concrete foundation elevation, center line, length, each built-in fitting and rebar sizes spacing meet
Design requirement;
(12) arrangement and method for construction, is worked out, construction technology design is carried out;
(13), according to construction drawing and field condition, computation and measurement goes out the consumption of reinforcing bar, concrete, template;
(2), the debris to roofing are cleared up
(3), surveying setting-out
Before construction, setting-out is measured using total powerstation according to construction drawing, and relevant axis position is indicated with red paint,
And repetition measurement is carried out according to drawing axis and construction requirement,
(4), steel bar meter
(41), raw material of reinforcement rebar
(411), the kind of reinforcing bar, rank, specification, quantity have to comply with the regulation of drawing;
(412), every batch of reinforcing bar detected using preceding to its mechanical performance, is detected qualified and is reported rear to a higher authorities for approval and can be used;
(413), after the entering of reinforcing steel bar, nameplate is checked and accepted, stacks and set up respectively by grade, specification, and be sampled censorship;
(414), sampling censorship substandard product removes appearance immediately;
(42) steel bar meter
(421), colligation and welding, the bending of reinforcing bar, the termination of reinforcing bar and joint should all meet design to steel bar meter at the scene
It is required that;
(422), treat after the completion of steel bar meter, the pollutant of rebar surface and iron rust are removed clean;
(5), template processing and installation
(51), template processing
Strict to make template by construction drawing size, requirement, template construct answers physical dimension accurate, and surfacing is bright and clean, and in mould
The inner side brushing paraffin release agent of plate;
(52), template transport and installation
(521), template must assure that template is without damage, pollution-free in transport to roofing procedures;
(522), template is covered when stacking with cloth, and template is protected;
(523), notice that split joint is closely knit during model sheetinstallat, it is ensured that do not reveal slurry;
(6), reinforcing bar colligation and examination
(61), using manually carrying out reinforcing bar carrying;
(62), the colligation of reinforcing bar is performed in strict accordance with regulation, and colligation is firm, smooth vertical and horizontal;
(63), the size of the position of reinforcement installation, spacing, protective layer thickness and reinforcing bar, size are both needed to meet construction drawing regulation;
(64), the overlap joint or weld length of reinforcing bar, then position should meet drawing regulation;
(65) after the completion of reinforcing bar colligation, press《Concrete structure engineering job specfication》GB50666-2011 standards, construction drawing and《Steel
Muscle is welded and control of acceptance》JGJ18-2012 code requirements are inspected for acceptance, and are made a record;
(7), concreting
(71), concreting is used based on truck mounted pumping, and pump rate is 50~60m3/ h, part basis are used and manually poured
Build, pouring simultaneously, vibrating head movement should be moved immediately following concrete duct;
(72) speed of vibrating head insertion, is noted during concreting, the depth in vibrating head insertion concrete is total depth
2/3~3/4, speed is maintained at 12 beats/min, and when keeping vibrating for 4~5 seconds in concrete after insertion, vibrator must not collide mould
Plate, should observe the fast theory inserted and pull out slowly, and when pouring near marking line, pumping line is tried one's best away from pump rate is changed to 50m3/
h;
(73), concrete before pouring in horizontal wall inscription and longitudinal slope bottom reserving hole, it is ensured that roof drainage is not influenceed by basis;
(8), concrete curing, form removal
(81), the surface to strip footing concrete is processed by shot blasting, maintenance treatment is carried out after determining pore-free;
(82), after concreting, in mould outer wrapping puggaree or cooling of watering, and oversite concrete surface immediately, protected
Warm moisture-keeping maintaining;
(83), during conserving, when temperature is higher than 10 DEG C, to retaining material timing water filling ensureing constant moisture state;
(84), during conserving, people is forbidden to be walked on concrete;
(85), non-bearing template must after concrete strength reaches 75% form removal, bearing form is after intensity reaches 90%
Form removal;In demolishing process, it is impossible to which cruelty is removed, form removable should take impact mitigation measure;Form removable is just followed and first torn open
Non-bearing template, after tear the theory of bearing form open.
2. roofing photovoltaic strip footing construction according to claim 1, it is characterised in that setting base in step (3)
Plinth absolute altitude is within 5mm.
3. roofing photovoltaic strip footing construction according to claim 1, it is characterised in that without conjunction in step (413)
Lattice are demonstrate,proved and the reinforcing bar of report of dispatching from the factory forbids admission.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201611020380.0A CN106703070A (en) | 2016-11-17 | 2016-11-17 | Construction method of roof photovoltaic strip foundation |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201611020380.0A CN106703070A (en) | 2016-11-17 | 2016-11-17 | Construction method of roof photovoltaic strip foundation |
Publications (1)
Publication Number | Publication Date |
---|---|
CN106703070A true CN106703070A (en) | 2017-05-24 |
Family
ID=58940582
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201611020380.0A Pending CN106703070A (en) | 2016-11-17 | 2016-11-17 | Construction method of roof photovoltaic strip foundation |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN106703070A (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109333799A (en) * | 2018-11-09 | 2019-02-15 | 如皋汉府建筑科技有限公司 | A kind of production technology of nonmetallic ore Tetramune |
CN110687560A (en) * | 2019-10-12 | 2020-01-14 | 中国电建集团贵州工程有限公司 | Impeller combination rapid positioning method |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2006104770A (en) * | 2004-10-05 | 2006-04-20 | Hiroshi Ueno | Installation implement for solar cell panel |
CN202108169U (en) * | 2011-05-26 | 2012-01-11 | 泰通(泰州)工业有限公司 | Embedded roof structure with photovoltaic subassemblies |
CN104264543A (en) * | 2014-09-11 | 2015-01-07 | 北京铁五院工程机械有限公司 | Method for constructing small-radius curve ballastless track |
CN104372890A (en) * | 2014-11-07 | 2015-02-25 | 成龙建设集团有限公司 | Construction method of bare concrete prefabricated box beam with complicated structure |
CN104420478A (en) * | 2013-08-22 | 2015-03-18 | 中国电力工程顾问集团华北电力设计院工程有限公司 | Photovoltaic module support simple strip foundation structure in photovoltaic power station |
-
2016
- 2016-11-17 CN CN201611020380.0A patent/CN106703070A/en active Pending
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2006104770A (en) * | 2004-10-05 | 2006-04-20 | Hiroshi Ueno | Installation implement for solar cell panel |
CN202108169U (en) * | 2011-05-26 | 2012-01-11 | 泰通(泰州)工业有限公司 | Embedded roof structure with photovoltaic subassemblies |
CN104420478A (en) * | 2013-08-22 | 2015-03-18 | 中国电力工程顾问集团华北电力设计院工程有限公司 | Photovoltaic module support simple strip foundation structure in photovoltaic power station |
CN104264543A (en) * | 2014-09-11 | 2015-01-07 | 北京铁五院工程机械有限公司 | Method for constructing small-radius curve ballastless track |
CN104372890A (en) * | 2014-11-07 | 2015-02-25 | 成龙建设集团有限公司 | Construction method of bare concrete prefabricated box beam with complicated structure |
Non-Patent Citations (2)
Title |
---|
张原: "《土木工程施工(下册)》", 31 December 2008 * |
杜日武: "《建筑施工技术》", 30 September 2014 * |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109333799A (en) * | 2018-11-09 | 2019-02-15 | 如皋汉府建筑科技有限公司 | A kind of production technology of nonmetallic ore Tetramune |
CN110687560A (en) * | 2019-10-12 | 2020-01-14 | 中国电建集团贵州工程有限公司 | Impeller combination rapid positioning method |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN107989401B (en) | Existing building outer wall reconstruction structure and construction method | |
CN101713237B (en) | Construction method of large-volume original decorative large pier stud fair-faced concrete | |
CN103266767A (en) | Construction method for preventing and treating cracks between concrete structure and filler wall | |
CN102392549B (en) | Construction working method for seamless prestressed-concrete self-waterproof clean water reservoir | |
CN105484391A (en) | Construction method for manufacturing heat-preservation waterproof wall through light heat-preservation GRC disassembling-free formworks | |
CN104846744A (en) | Construction method for pouring and forming urban viaduct curve type pier stud in one-off mode | |
CN109706846B (en) | High and narrow bridge capping beam through steel bar construction method for slope foundation | |
CN101476382A (en) | Construction method of angle steel angle bead dividing joint of large-area concrete floor | |
CN104372890A (en) | Construction method of bare concrete prefabricated box beam with complicated structure | |
CN103821253A (en) | Constructing technique for aerated concrete block filler wall | |
CN105666687A (en) | Construction process for pre-stress reactive powder concrete box girder | |
CN107882321A (en) | Diameter Silo slding form operation engineering method | |
CN106368183B (en) | Under horizontal steel-slag sand side sealing embedded part pour construction method for forming | |
CN110396937A (en) | The asynchronous construction of hollow thin-walled high pier binder pier beam | |
CN103603236A (en) | Method for controlling cracks of double-block ballastless track bed slab | |
CN108532466A (en) | A kind of bridge pier over-form construction technique | |
CN105442629B (en) | A kind of large scale equipment T stage vibration isolation mounts construction | |
CN105839985A (en) | Hydropower station rectangular high tower hydraulic climb slip form system and construction method | |
CN110093852A (en) | Shaped form bridge pier Construction technology of fair-faced concrete | |
CN104894954A (en) | Overall mounting and constructing method of pier stud reinforcing steel bars of urban bridge | |
CN103161176A (en) | Tower crane foundation construction method in main building connected garage | |
CN106703070A (en) | Construction method of roof photovoltaic strip foundation | |
CN110468638A (en) | A kind of road bed board concreting and plastering technique | |
CN207829511U (en) | A kind of existing building external wall reconstruction structure | |
CN105822068B (en) | Ultralong thin walled concrete walls under hot environment pour and maintenance process |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20170524 |