CN106702073A - Hot replacement method for converter bottom blowing element - Google Patents

Hot replacement method for converter bottom blowing element Download PDF

Info

Publication number
CN106702073A
CN106702073A CN201510789669.8A CN201510789669A CN106702073A CN 106702073 A CN106702073 A CN 106702073A CN 201510789669 A CN201510789669 A CN 201510789669A CN 106702073 A CN106702073 A CN 106702073A
Authority
CN
China
Prior art keywords
bottom blowing
blowing element
sealing material
joint sealing
drilling
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201510789669.8A
Other languages
Chinese (zh)
Inventor
王富亮
徐国义
赵雷
尹宏军
牛兴明
陈传忠
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Angang Steel Co Ltd
Original Assignee
Angang Steel Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Angang Steel Co Ltd filed Critical Angang Steel Co Ltd
Priority to CN201510789669.8A priority Critical patent/CN106702073A/en
Publication of CN106702073A publication Critical patent/CN106702073A/en
Pending legal-status Critical Current

Links

Landscapes

  • Carbon Steel Or Casting Steel Manufacturing (AREA)

Abstract

The invention provides a hot replacement method for a converter bottom blowing element. The hot replacement method comprises: keeping the diameter deviation of a new bottom blowing element and an original bottom blowing element not exceed 0.5-1.0mm and the diameter deviation of a drill bit and the bottom blowing element not exceed 1.0mm; after drilling, blowing a refractory in a drill hole to be clean by virtue of compressed air; uniformly smearing a joint sealing material containing the components in percentage by weight: 85-90% of Al2O3 and 10-15% of Cr2O3 at the periphery of the bottom blowing element by using a brush, wherein the smearing thickness is 4-6mm, and the smearing time is 1-2min; then, rapidly inserting the bottom blowing element to the drill hole, tamping the bottom blowing element and a combined part of the tail part of the drill hole by using a magnesium refractory, mounting a seating brick and a flange plate, sintering for 45-55min by virtue of waste heat in a converter, and combining the bottom blowing element with the bottom blowing seating brick after curing the joint sealing material. By using the hot replacement method, the corrosion of high-temperature oxidized molten steel to a bottom tuyere protecting brick and the bottom blowing element can be effectively reduced, the phenomena of steel seepage and leakage caused in a blowing process can be avoided, and accident loss can be avoided.

Description

A kind of bottom-blowing of converter element hot swap method
Technical field
The invention belongs to steelmaking equipment maintenance technique field, more particularly to a kind of hot swap of top and bottom combined blown converter bottom blowing ventilated element Method.
Background technology
At present, the main method that domestic steelwork converter blows long-lived use again is the online hot swap of bottom blowing element, and bottom blowing element is online The know-why of hot swap is that more exchange device is closely affixed into furnace bottom ventilated element position by ring flange, is led to in drilling Enter cooling water, open controlled motor, motor drives drilling pipe rotatably to push ahead, the resistance to material that bottom rifle position puts place is drilled through by drill bit. Drilling pipe length is more than furnace bottom thickness, after drill bit drills through the resistance to material at furnace bottom position, exits drilling pipe, and new bottom blowing element is loaded In drilling, Renewal process is completed.Due to drill bit and bottom blowing element dimensional discrepancy reason, brick and bottom blowing can be protected in converter bottom bottom rifle The gap of 2~4mm is formed between element.During converter melting molten steel, because liquid steel temperature is high, oxidisability is strong, the steel of high-temperature oxydation Water can aggravate to protect bottom rifle the erosion of brick and bottom blowing element, once molten steel forms passage, the hidden danger of bleed-out can be brought, to steel mill Cause great loss.
The content of the invention
The present invention provides a kind of bottom-blowing of converter element hot swap method, and its purpose is intended to prevent between bottom rifle shield brick and bottom blowing element Occurs bleed-out accident in converting process, it is to avoid causality loss.
Therefore, the solution that the present invention is taken is:
A kind of bottom-blowing of converter element hot swap method, its specific method and step are:
(1) new bottom blowing element is no more than -0.5mm~1.0mm with the diameter deviation of former bottom blowing element, and the smooth nothing in surface is split Line;
(2) before drilling, with miking bit diameter and bottom blowing element diameter, it is ensured that bit diameter is inclined with bottom blowing element diameter Difference is no more than 1.0mm;
(3) after drill bit drills through the resistance to material of furnace bottom position, drilling pipe is exited, is purged the resistance to material in drilling with compressed air clean;
(4) by joint sealing material with brush uniform application in bottom blowing element surrounding, smearing thickness control smears time control in 4~6mm System is in 1~2min;It is clay shape under joint sealing material normal temperature, is into wt% is grouped into:Al2O385~90%, Cr2O310~15%;
(5) after joint sealing material is smeared and terminated, quickly bottom blowing element is inserted and is drilled, by joint sealing material by between bottom blowing element and drilling Gap tamp;
(6) after bottom blowing element is installed, bottom blowing element is tamped with the binding site of drilling afterbody with magnesia refractories, then First-class brick cup and ring flange, then sinter 45~55min, by bottom blowing element and bottom blowing after joint sealing material solidification using waste heat in converter Brick cup is combined together.
Beneficial effects of the present invention are:
Due to reducing the dimensional discrepancy between drill bit and bottom blowing element, the gap between drilling and bottom blowing element is relatively reduced; Joint sealing material is filled with gap simultaneously, the joint sealing material after solidification can by bottom blowing element and bottom blowing brick cup combine closely securely for Integrally, so as to be effectively reduced the erosion that high-temperature oxydation molten steel protects bottom rifle brick and bottom blowing element, prevent from occurring oozing in converting process Steel and bleed-out phenomenon, it is to avoid causality loss.
Specific embodiment
The specific method and step of bottom-blowing of converter element hot swap of the present invention be:
1st, new bottom blowing element is no more than -0.5mm~0.5mm, and the smooth flawless in surface with the diameter deviation of former bottom blowing element.
2nd, before drilling, with miking bit diameter and bottom blowing element diameter, it is ensured that bit diameter is inclined with bottom blowing element diameter Difference is no more than 0.8mm.
3rd, after drill bit drills through the resistance to material of furnace bottom position, drilling pipe is exited, is purged the resistance to material in drilling with compressed air clean.
4th, by joint sealing material with brush uniform application in bottom blowing element surrounding, smearing thickness control is smeared time control and is existed in 5mm 1.5min.It is clay shape under joint sealing material normal temperature, is into wt% is grouped into:Al2O388%, Cr2O312%.
5th, after joint sealing material is smeared and terminated, quickly bottom blowing element is inserted and is drilled, by joint sealing material by between bottom blowing element and drilling Gap tamp.
6th, after bottom blowing element is installed, bottom blowing element is tamped with the binding site of drilling afterbody with magnesia refractories, then First-class brick cup and ring flange, then using waste heat sintering 50min in converter, by bottom blowing element and bottom blowing brick cup after joint sealing material solidification Strong bonded is integrated.

Claims (1)

1. a kind of bottom-blowing of converter element hot swap method, it is characterised in that:
(1) new bottom blowing element is no more than -0.5mm~1.0mm, and surface with the diameter deviation of former bottom blowing element Smooth flawless;
(2) before drilling, with miking bit diameter and bottom blowing element diameter, it is ensured that bit diameter and bottom Element diameter deviation is blown no more than 1.0mm;
(3) after drill bit drills through the resistance to material of furnace bottom position, drilling pipe is exited, will be resistance in drilling with compressed air Material purging is clean;
(4) by joint sealing material with brush uniform application in bottom blowing element surrounding, smearing thickness is controlled in 4~6mm, Time control is smeared in 1~2min;It is clay shape under joint sealing material normal temperature, is into wt% is grouped into:Al2O385~ 90%, Cr2O310~15%;
(5) after joint sealing material is smeared and terminated, quickly bottom blowing element is inserted and is drilled, it is by joint sealing material that bottom blowing is first Tamp in gap between part and drilling;
(6) after bottom blowing element is installed, with magnesia refractories by bottom blowing element and drilling afterbody combination Position is tamped, then first-class brick cup and ring flange, then sinters 45~55min, joint sealing material using waste heat in converter Bottom blowing element is combined together with bottom blowing brick cup after solidification.
CN201510789669.8A 2015-11-17 2015-11-17 Hot replacement method for converter bottom blowing element Pending CN106702073A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510789669.8A CN106702073A (en) 2015-11-17 2015-11-17 Hot replacement method for converter bottom blowing element

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510789669.8A CN106702073A (en) 2015-11-17 2015-11-17 Hot replacement method for converter bottom blowing element

Publications (1)

Publication Number Publication Date
CN106702073A true CN106702073A (en) 2017-05-24

Family

ID=58933323

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510789669.8A Pending CN106702073A (en) 2015-11-17 2015-11-17 Hot replacement method for converter bottom blowing element

Country Status (1)

Country Link
CN (1) CN106702073A (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109371195A (en) * 2018-10-29 2019-02-22 甘肃酒钢集团宏兴钢铁股份有限公司 It is a kind of with the production assembly method of furnace labour synchronous converter bottom podwer gun
CN109735679A (en) * 2018-12-29 2019-05-10 甘肃酒钢集团宏兴钢铁股份有限公司 A kind of devices and methods therefor of the replacement of bottom-blowing of converter brick and gap reparation
CN110578033A (en) * 2019-09-24 2019-12-17 张家港宏昌钢板有限公司 Converter bottom blowing replacement method
US20220235427A1 (en) * 2021-01-26 2022-07-28 University Of Science And Technology Beijing Long-life service method for powder-bottom-injecting converter based on collaborative hot replacement of furnace bottom and bottom purging brick

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102399931A (en) * 2010-09-16 2012-04-04 鞍钢股份有限公司 Hot replacement method of bottom blowing element of top-bottom combined blown converter
CN102676730A (en) * 2012-05-25 2012-09-19 宣化钢铁集团有限责任公司 Converter bottom blowing air brick, special drilling machine and quick thermal replacement method of air brick

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102399931A (en) * 2010-09-16 2012-04-04 鞍钢股份有限公司 Hot replacement method of bottom blowing element of top-bottom combined blown converter
CN102676730A (en) * 2012-05-25 2012-09-19 宣化钢铁集团有限责任公司 Converter bottom blowing air brick, special drilling machine and quick thermal replacement method of air brick

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
牛兴明 等: ""底吹透气元件在线热更换技术在260t转炉的应用"", 《鞍钢技术》 *

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109371195A (en) * 2018-10-29 2019-02-22 甘肃酒钢集团宏兴钢铁股份有限公司 It is a kind of with the production assembly method of furnace labour synchronous converter bottom podwer gun
CN109735679A (en) * 2018-12-29 2019-05-10 甘肃酒钢集团宏兴钢铁股份有限公司 A kind of devices and methods therefor of the replacement of bottom-blowing of converter brick and gap reparation
CN110578033A (en) * 2019-09-24 2019-12-17 张家港宏昌钢板有限公司 Converter bottom blowing replacement method
CN110578033B (en) * 2019-09-24 2021-11-23 张家港宏昌钢板有限公司 Converter bottom blowing replacement method
US20220235427A1 (en) * 2021-01-26 2022-07-28 University Of Science And Technology Beijing Long-life service method for powder-bottom-injecting converter based on collaborative hot replacement of furnace bottom and bottom purging brick
US11667982B2 (en) * 2021-01-26 2023-06-06 University Of Science And Technology Beijing Long-life service method for powder-bottom-injecting converter based on collaborative hot replacement of furnace bottom and bottom purging brick

Similar Documents

Publication Publication Date Title
Liu et al. Recent progress on long service life design of Chinese blast furnace hearth
CN102912051B (en) Method for exchanging cooling wall of blast furnace taphole online
CN106702073A (en) Hot replacement method for converter bottom blowing element
CN106435073A (en) Blast furnace liner overall pouring construction method for replacing spraying materials and refractory bricks
CN108033795B (en) High-aluminum castable for permanent layer of torpedo ladle
CN112430699B (en) Long-service-life service method for synergistic hot replacement of bottom powder spraying converter bottom and bottom blowing brick
CN110643768B (en) Method for controlling depth of newly-thrown taphole of blast furnace
CN100595284C (en) Maintaining method for blast furnace
WO2012005119A1 (en) Gas blowing nozzle
CN101319257B (en) Bottom blowing ventilating structure of combined-blowing revolving furnace
JP2009062601A (en) Molten pig iron tapping hole structure in melting furnace, and repairing method therefor
CN204939506U (en) A kind of device stoping blast furnace hearth bottom temp to raise
CN107130080B (en) A kind of method for repairing and mending of external orifice of steel-tapping hole of converter brick breakage
CN110331252B (en) Method for repairing partially damaged brick cup of tap hole of converter on line
CN110184412B (en) Method for replacing bottom blowing brick cup of converter
CN111893231A (en) Blast furnace hearth and casting long-life lifting method thereof
CN109439825B (en) Method for prolonging service life of blast furnace main channel
Geyer et al. Blast furnace tapping practice at arcelor mittal South Africa, vanderbijlpark works
CN102534092B (en) Method for protecting top-bottom combined blown converter
CN210796513U (en) Blast furnace foundation gas leakage plugging structure
CN107779556A (en) A kind of RH refining furnace vacuum chambers base channel restorative procedure
CN206308387U (en) A kind of RH vacuum chambers bottom masonry construction
CN206919675U (en) Special-shaped brick for building gap bridge of cupola and gap bridge structure
CN210886086U (en) Structure for rapidly treating iron notch splashing of blast furnace on line
CN103045807B (en) Vacuum circulation degassing insert tube

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20170524

WD01 Invention patent application deemed withdrawn after publication