CN106677213A - Positioning and layout method of urban comprehensive pipe gallery - Google Patents
Positioning and layout method of urban comprehensive pipe gallery Download PDFInfo
- Publication number
- CN106677213A CN106677213A CN201710085133.7A CN201710085133A CN106677213A CN 106677213 A CN106677213 A CN 106677213A CN 201710085133 A CN201710085133 A CN 201710085133A CN 106677213 A CN106677213 A CN 106677213A
- Authority
- CN
- China
- Prior art keywords
- piping lane
- pipe gallery
- absolute altitude
- positioning
- centrage
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D29/00—Independent underground or underwater structures; Retaining walls
- E02D29/045—Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them
-
- G—PHYSICS
- G01—MEASURING; TESTING
- G01C—MEASURING DISTANCES, LEVELS OR BEARINGS; SURVEYING; NAVIGATION; GYROSCOPIC INSTRUMENTS; PHOTOGRAMMETRY OR VIDEOGRAMMETRY
- G01C15/00—Surveying instruments or accessories not provided for in groups G01C1/00 - G01C13/00
Landscapes
- Engineering & Computer Science (AREA)
- Environmental & Geological Engineering (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Mining & Mineral Resources (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- Physics & Mathematics (AREA)
- General Physics & Mathematics (AREA)
- Radar, Positioning & Navigation (AREA)
- Remote Sensing (AREA)
- Position Fixing By Use Of Radio Waves (AREA)
- Underground Structures, Protecting, Testing And Restoring Foundations (AREA)
Abstract
The invention discloses a positioning and layout method of an urban comprehensive pipe gallery. The positioning and layout method of the urban comprehensive pipe gallery comprises the steps that a pipe gallery planar graph coordinate system control network is built; the earth excavation central line is positioned; level control points are laid out; the deepening and widening positions of a pipe gallery foundation ditch are positioned; the pipe gallery foundation ditch is excavated; elevation is laid out to the side slope of the foundation ditch for the first time; elevation layout is carried out when the foundation ditch is excavated to the depth of -30 cm, and layout of the pipe gallery underlayer central line and positioning of the pipe gallery structure central line are carried out. The positioning and layout method of the urban comprehensive pipe gallery is characterized by being conducted according to the following steps that (1) the pipe gallery planar graph coordinate system control network is built through a GPS position indicator; (2) the earth excavation central line is positioned; (3) the level control points are laid out; (4) the deepening and widening positions of the pipe gallery foundation ditch are positioned; (5) the pipe gallery foundation ditch is excavated; (6) elevation is laid out to the side slope of the foundation ditch for the first time; (7) elevation layout is carried out when the foundation ditch is excavated to the depth of -30 cm; (8) layout of the pipe gallery underlayer central line is conducted; and (9) positioning of the pipe gallery structure central line is carried out. The positioning and layout method of the urban comprehensive pipe gallery has the advantages of improving positioning accuracy, completing the positioning work efficiently and rapidly, and guaranteeing the time limit and quality of a project.
Description
Technical field
The present invention relates to underground city pipe gallery technical field of construction, more particularly to a kind of positioning of city integrated piping lane
Line-putting method, it is adaptable to the line setting work of all kinds of piping lanes such as cast-type, precast splice type.
Background technology
It is also a most important step that the line setting work of pipe gallery is the first step of piping lane construction, positions the standard of work
The integral construction quality of true relation piping lane.In existing piping lane engineering construction, the line setting work before piping lane is excavated generally makes
Completed with GPS location instrument or total powerstation.During using GPS location instrument, by piping lane plane graph, the coordinate of skiagraph and elevation pair
Should be input in GPS Base Station, excavate prelocalization excavation line, all-the-way tracking digging process, at any time using GPS location cutting depth and
Position is excavated, instructs digging machine to construct, excavation completes to make piping lane main center line using GPS, into normal construction;Using whole station
When instrument is positioned, first by datum mark total powerstation pilot measurement to piping lane construction area, then orient every 50m along piping lane trend and face
When datum mark, piping lane excavation line is made using temporary fiducial point, in digging process using total powerstation positioning benchmark point height
Control cutting depth, foundation ditch is introduced after the completion of excavation by datum mark, orients piping lane main center line, completes to position work.
There is certain enforcement difficulty in both the above method.First, excavated using GPS location instrument and total powerstation,
The workload of positioning is larger, and in terms of kilometer, when multiple spot is excavated, GPS cannot take into account city integrated piping lane length with total powerstation, and GPS
It is higher with the price of total powerstation, it is impossible to a large amount of buyings;Second, GPS are higher using threshold with total powerstation, and those skilled in the art cannot
Its using method is grasped, needs to be equipped with the professional survey crew being consistent with project progress so that project management cost increases;The
Three, typically in -7m to -10m, this depth causes total powerstation to need multiple pilot measurement, cumulative errors in use to piping lane depth
Can accumulate because pilot measurement number of times is excessive, and cannot accurate repetition measurement.Therefore, it is badly in need of proposing that one kind is applied suitable for city integrated piping lane
The localization method of work, to improve the precision of measurement work, reduces technical staff's amount of labour, reduces cost, carries high-quality
Purpose.
The content of the invention
The purpose of the present invention is aiming at the problem of prior art presence, there is provided a kind of line setting of city integrated piping lane
Method, by with reference to GPS location instrument, level gauge measuring instrument, solving the difficulty of the line setting in piping lane construction, reduces construction
In demand to survey crew quantity, reduce survey crew workload, improve positioning precision, efficiently, quickly finish piping lane and apply
The positioning work of work, it is ensured that the requirement of duration and quality.
The object of the present invention is achieved like this:A kind of line setting method of city integrated piping lane, including GPS location instrument
Piping lane plane graph coordinate system control net is set up, earth excavation centrage is oriented, level control point is laid, positioning piping lane foundation trench adds
Deeply, change location is widened, piping lane foundation trench is excavated, level gauge elevation control depth, and first time absolute altitude is surveyed and set to foundation trench side during -5m
Slope, absolute altitude is surveyed and set when being excavated to foundation trench bottom -30cm, and piping lane bed course centrage is surveyed and set and Pipe rack centrage positioning, its feature
It is to carry out according to the following steps:
1), according to the benchmark control point of two and more than two for paying, GPS location instrument sets up piping lane plane graph coordinate system
Control net
Firstly the need of the engineering construction control point of two and more than two provided according to Construction Party or relevant departments, set up
The control net of GPS location instrument, as the benchmark of GPS location;
2), a cubic metre of earth central excavation line is gone out according to piping lane plane graph coordinate setting
According to the coordinate of piping lane site plan, piping lane foundation trench figure side central excavation line is oriented, by position of center line,
Excavating sideline is spread out using ribbon instrument;
3), move towards to lay level control point along piping lane
Because underground pipe gallery absolute altitude is risen and fallen with the fluctuating of top road, thus must according to piping lane skiagraph,
Along piping lane trend, high control point is marked with excavation line exterior measuring, absolute altitude control dot spacing arranges one less than 30m, at control point
While elevation is indicated, as the foundation of absolute altitude control when excavating;As piping lane by-pass road yet to be built builds, also can be by pavement of road absolute altitude
Foundation is controlled as absolute altitude;
4), position piping lane foundation trench to deepen, widen change location
According to each air outlet, line outlet, crossing coordinate in piping lane site plan, clearly survey and set out piping lane foundation trench node
Plus width position, white line is spread out, as excavation foundation;
5), piping lane foundation trench is excavated, level gauge elevation control depth
After preparation is finished, start foundation trench excavation work, foundation trench deep exploitation level gauge coordinates Sopwith staff, lining rope to be controlled
System, the foundation ditch gradient should be calculated substantially when excavating, it is to avoid be backbreak;
6), the survey of first time absolute altitude is set to foundation trench side slope during -5m
Because level gauge Sopwith staff length is usually no more than 7m, therefore level gauge is applied when 5m or so is excavated to by absolute altitude control
Point is projected on excavation slope, used as the absolute altitude control point for continuing to excavate downwards;
7) absolute altitude is surveyed and set when, being excavated to foundation trench bottom -30cm
Mechanical equivalent of light excavation should can pass through ribbon, Sopwith staff to substrate by the reserved 30cm surface dust labor cleanings of specification, absolute altitude
Determine;
8), artificial clear groove, basement process, piping lane bed course centrage is surveyed and set
Surface dust in labor cleaning's substrate above 30cm, basement process is carried out after check of foundation subsoil by design requirement, and GPS is used after examination
Positioning piping lane bed course centrage and node add width position;
9), cushion construction, levelling, waterproof construction, Pipe rack centrage positioning
Bed course template is installed according to bed course centrage, blinding concrete construction is carried out;Waterproof layer is carried out according to drawing requirement to apply
Work, using GPS location Pipe rack centrage after having constructed, hands over main structure construction.
Compared with prior art, it is an advantage of the invention that:Positioning precision is improved, efficiently, piping lane construction is quickly finished
Positioning work, it is ensured that duration and quality.
Description of the drawings
Fig. 1:Plane positioning point arranges schematic diagram.
In figure:1st, the absolute altitude control point 3, node that earth excavation center 2, piping lane is arranged along the line adds width position 4, piping lane
Bed course and Pipe rack centrage
Specific embodiment
To further describe the present invention, with reference to embodiment and accompanying drawing, the invention will be further described.
As illustrated, a kind of line setting method of city integrated piping lane, including GPS location instrument sets up piping lane plane graph seat
Mark system control net, orients earth excavation centrage, lays level control point, and positioning piping lane foundation trench is deepened, widens change location,
Piping lane foundation trench excavate, level gauge elevation control depth, during -5m first time absolute altitude survey set to foundation trench side slope, be excavated to foundation trench bottom -
Absolute altitude is surveyed and set during 30cm, and piping lane bed course centrage is surveyed and set and Pipe rack centrage positioning, it is characterised in that entered according to the following steps
OK:
1), according to the benchmark control point of two and more than two for paying, GPS location instrument sets up piping lane plane graph coordinate system
Control net
Firstly the need of the engineering construction control point of two and more than two provided according to Construction Party or relevant departments, set up
The control net of GPS location instrument, as the benchmark of GPS location;
2), a cubic metre of earth central excavation line is gone out according to piping lane plane graph coordinate setting
According to the coordinate of piping lane site plan, piping lane foundation trench earth excavation centrage 1 is oriented, by centrage position
Put, using ribbon instrument excavating sideline is spread out;
3), move towards to lay level control point along piping lane
Because underground pipe gallery absolute altitude is risen and fallen with the fluctuating of top road, thus must according to piping lane skiagraph,
Along piping lane trend, high control point 2 is marked with excavation line exterior measuring, absolute altitude control dot spacing arranges one less than 30m, at control point
While elevation is indicated, as the foundation of absolute altitude control when excavating;As piping lane by-pass road yet to be built builds, also can be by pavement of road absolute altitude
Foundation is controlled as absolute altitude;
4), position piping lane foundation trench to deepen, widen change location
According to each air outlet, line outlet, crossing coordinate in piping lane site plan, clearly survey and set out piping lane foundation trench node
Plus width position 3, white line spreads out, used as excavation foundation;
5), piping lane foundation trench is excavated, level gauge elevation control depth
After preparation is finished, start foundation trench excavation work, foundation trench deep exploitation level gauge coordinates Sopwith staff, lining rope to be controlled
System, the foundation ditch gradient should be calculated substantially when excavating, it is to avoid be backbreak;
6), the survey of first time absolute altitude is set to foundation trench side slope during -5m
Because level gauge Sopwith staff length is usually no more than 7m, therefore level gauge is applied when 5m or so is excavated to by absolute altitude control
Point is projected on excavation slope, used as the absolute altitude control point for continuing to excavate downwards;
7) absolute altitude is surveyed and set when, being excavated to foundation trench bottom -30cm
Mechanical equivalent of light excavation should can pass through ribbon, Sopwith staff to substrate by the reserved 30cm surface dust labor cleanings of specification, absolute altitude
Determine;
8), artificial clear groove, basement process, piping lane bed course centrage is surveyed and set
Surface dust in labor cleaning's substrate above 30cm, basement process is carried out after check of foundation subsoil by design requirement, and GPS is used after examination
Positioning piping lane bed course centrage 4 and node add width position 3;
9), cushion construction, levelling, waterproof construction, Pipe rack centrage positioning
Bed course template is installed according to bed course centrage, blinding concrete construction is carried out;Waterproof layer is carried out according to drawing requirement to apply
Work, using GPS location Pipe rack centrage 4 after having constructed, hands over main structure construction.
Lanzhou new district underground pipe gallery project, using line setting method proposed by the present invention, realizes piping lane positioning
Unwrapping wire is once completed, during cloth of surveyor survey, excavating tracking can be completed by builder with level gauge, be advantageously reduced
Management cost, and positioning progress is improve, the technique preparation time is reduced, with good economic benefit and social benefit.
Claims (1)
1. a kind of line setting method of city integrated piping lane, including GPS location instrument sets up piping lane plane graph coordinate system control net,
Earth excavation centrage is oriented, level control point is laid, positioning piping lane foundation trench is deepened, widens change location, and piping lane foundation trench is opened
Digging, level gauge elevation control depth, first time absolute altitude is surveyed and set to foundation trench side slope during -5m, and absolute altitude is surveyed when being excavated to foundation trench bottom -30cm
If piping lane bed course centrage is surveyed and set and Pipe rack centrage positioning, it is characterised in that carried out according to the following steps:
1), according to the benchmark control point of two and more than two for paying, GPS location instrument sets up the control of piping lane plane graph coordinate system
Net
Firstly the need of the engineering construction control point of two and more than two provided according to Construction Party or relevant departments, GPS is set up
The control net of position finder, as the benchmark of GPS location;
2), a cubic metre of earth central excavation line is gone out according to piping lane plane graph coordinate setting
According to the coordinate of piping lane site plan, piping lane foundation trench earth excavation centrage (1) is oriented, by position of center line,
Excavating sideline is spread out using ribbon instrument;
3), move towards to lay level control point along piping lane
Because underground pipe gallery absolute altitude is risen and fallen with the fluctuating of top road, therefore must be according to piping lane skiagraph, along pipe
Corridor is moved towards, and in excavation line exterior measuring high control point (2) is marked with, and absolute altitude control dot spacing arranges one less than 30m, on control point side
Elevation is indicated, as the foundation of absolute altitude control when excavating;As piping lane by-pass road yet to be built builds, also pavement of road absolute altitude can be made
Foundation is controlled for absolute altitude;
4), position piping lane foundation trench to deepen, widen change location
According to each air outlet, line outlet, crossing coordinate in piping lane site plan, clearly survey sets out piping lane foundation trench node and widens
Position (3), spreads out white line, used as excavation foundation;
5), piping lane foundation trench is excavated, level gauge elevation control depth
After preparation is finished, start foundation trench excavation work, foundation trench deep exploitation level gauge coordinates Sopwith staff, lining rope to be controlled,
The foundation ditch gradient should be calculated substantially when excavating, it is to avoid be backbreak;
6), the survey of first time absolute altitude is set to foundation trench side slope during -5m
Because level gauge Sopwith staff length is usually no more than 7m, therefore when 5m or so is excavated to absolute altitude control point is thrown using level gauge
It is incident upon on excavation slope, as the absolute altitude control point for continuing to excavate downwards;
7) absolute altitude is surveyed and set when, being excavated to foundation trench bottom -30cm
Mechanical equivalent of light excavation can should be determined by the reserved 30cm surface dust labor cleanings of specification, absolute altitude to substrate by ribbon, Sopwith staff;
8), artificial clear groove, basement process, piping lane bed course centrage is surveyed and set
Surface dust in labor cleaning's substrate above 30cm, basement process is carried out after check of foundation subsoil by design requirement, and GPS location is used after examination
Piping lane bed course centrage (4) and node add width position (3);
9), cushion construction, levelling, waterproof construction, Pipe rack centrage positioning
Bed course template is installed according to bed course centrage, blinding concrete construction is carried out;Construction of waterproof layer is carried out according to drawing requirement, is applied
GPS location Pipe rack centrage (4) is utilized after work is complete, main structure construction is handed over.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710085133.7A CN106677213B (en) | 2017-02-17 | 2017-02-17 | A kind of line setting method of city integrated piping lane |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710085133.7A CN106677213B (en) | 2017-02-17 | 2017-02-17 | A kind of line setting method of city integrated piping lane |
Publications (2)
Publication Number | Publication Date |
---|---|
CN106677213A true CN106677213A (en) | 2017-05-17 |
CN106677213B CN106677213B (en) | 2018-08-14 |
Family
ID=58862287
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201710085133.7A Active CN106677213B (en) | 2017-02-17 | 2017-02-17 | A kind of line setting method of city integrated piping lane |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN106677213B (en) |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102877486A (en) * | 2012-10-22 | 2013-01-16 | 济南城建集团有限公司 | Integral cast-in-situ construction method for cable ducts |
CN103076009A (en) * | 2013-01-06 | 2013-05-01 | 长安大学 | Fast lofting method for connecting points of overhead line system of railway tunnel and automatic measuring system |
KR20130121281A (en) * | 2012-04-27 | 2013-11-06 | 장영미 | Apparatus for a in-line mold of precast concrete culverts and method for producing precast concrete culverts |
US20160116112A1 (en) * | 2014-10-23 | 2016-04-28 | Anchor Concrete Products Ltd. | Modular Assembly For Fabricating A Hollow Structure |
CN106382121A (en) * | 2016-12-05 | 2017-02-08 | 中交第三航务工程局有限公司 | Measuring method for subway tunnel shield excavation |
-
2017
- 2017-02-17 CN CN201710085133.7A patent/CN106677213B/en active Active
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR20130121281A (en) * | 2012-04-27 | 2013-11-06 | 장영미 | Apparatus for a in-line mold of precast concrete culverts and method for producing precast concrete culverts |
CN102877486A (en) * | 2012-10-22 | 2013-01-16 | 济南城建集团有限公司 | Integral cast-in-situ construction method for cable ducts |
CN103076009A (en) * | 2013-01-06 | 2013-05-01 | 长安大学 | Fast lofting method for connecting points of overhead line system of railway tunnel and automatic measuring system |
US20160116112A1 (en) * | 2014-10-23 | 2016-04-28 | Anchor Concrete Products Ltd. | Modular Assembly For Fabricating A Hollow Structure |
CN106382121A (en) * | 2016-12-05 | 2017-02-08 | 中交第三航务工程局有限公司 | Measuring method for subway tunnel shield excavation |
Non-Patent Citations (1)
Title |
---|
杨永强: "地下综合管廊的技术施工方法探讨", 《建筑知识》 * |
Also Published As
Publication number | Publication date |
---|---|
CN106677213B (en) | 2018-08-14 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN106641440B (en) | A kind of transverse crossing railway line underground piping jacking construction method | |
CN102996143B (en) | Construction method of fully pouring tunnel inverted arch | |
CN205172598U (en) | Pipe curtain spouts a supporting construction soon | |
CN103883328B (en) | The dark construction method of half lid half of high steep V-type coombe biased segment is worn under separate tunnel | |
CN106761776B (en) | Construction method for ultra-shallow tunnel shield to penetrate existing pipeline downwards | |
CN106503381A (en) | A kind of Underground Subway Station Virtual Construction construction on site method based on BIM GIS technologies | |
CN107130592A (en) | A kind of long screw auger and impact drill two-shipper is combined pore-creating filling pile construction | |
CN104674860B (en) | Wire holing through survey method in seabed tunnel | |
Jones | Low-volume-loss tunnelling for London ring main extension | |
CN106988305A (en) | A kind of pile-column pier construction method of underground integrated molding | |
CN110145309B (en) | Shallow coal seam grouting filling green coal mining method and settlement observation device thereof | |
CN108316283A (en) | The devices and methods therefor of influence of foundation excavation is controlled using hole rising pouring slurry ground-connecting-wall | |
CN103344214B (en) | 1.6-degree parabolic extralarge pier measuring and pier body linear control method | |
CN114018225B (en) | Ultra-large square construction measurement control method | |
CN106677213B (en) | A kind of line setting method of city integrated piping lane | |
CN208235578U (en) | A kind of reserved bridge zone assembled barricade for reinforcing hole slot | |
CN207878451U (en) | A kind of device using hole rising pouring slurry ground-connecting-wall control influence of foundation excavation | |
CN109630194A (en) | Karst region fault fracture zone tunnel water burst treatment structure and construction method thereof | |
CN115012957A (en) | Safe and efficient tunneling construction process for large-section extra-long tunnel under complex condition | |
CN104631257B (en) | Method for constructing Belgian road in testing track | |
CN106764055B (en) | Push pipe sight alignment construction | |
Keppie et al. | Some excavations on the line of the Antonine Wall, 1957-80 | |
CN208996016U (en) | A kind of runoff plots Bian Geng preventing leakage | |
CN208252027U (en) | Packaged type shield section surface subsidence monitoring point drilling equipment | |
Matas et al. | Geodetic works on the construction of the hydropower plant in Kjensvatn, Norway |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |