CN106638954B - Bolt of long stem widens the bean column node connection method in area through beam side - Google Patents

Bolt of long stem widens the bean column node connection method in area through beam side Download PDF

Info

Publication number
CN106638954B
CN106638954B CN201610895523.6A CN201610895523A CN106638954B CN 106638954 B CN106638954 B CN 106638954B CN 201610895523 A CN201610895523 A CN 201610895523A CN 106638954 B CN106638954 B CN 106638954B
Authority
CN
China
Prior art keywords
area
prefabricated post
precast beam
bolt
precast
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201610895523.6A
Other languages
Chinese (zh)
Other versions
CN106638954A (en
Inventor
郑文忠
侯晓萌
周威
王英
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Harbin Institute of Technology
Original Assignee
Harbin Institute of Technology
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Harbin Institute of Technology filed Critical Harbin Institute of Technology
Priority to CN201610895523.6A priority Critical patent/CN106638954B/en
Publication of CN106638954A publication Critical patent/CN106638954A/en
Application granted granted Critical
Publication of CN106638954B publication Critical patent/CN106638954B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/18Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons
    • E04B1/20Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons the supporting parts consisting of concrete, e.g. reinforced concrete, or other stonelike material
    • E04B1/21Connections specially adapted therefor

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Physics & Mathematics (AREA)
  • Electromagnetism (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Joining Of Building Structures In Genera (AREA)
  • Rod-Shaped Construction Members (AREA)

Abstract

Bolt of long stem widens the bean column node and joint connecting method in area through beam side, to solve the connection of existing prefabricated beam and prefabricated Column border node using in the form of cast-in-place, situ wet operation is more, and the duration is longer, difficulty of construction and labor intensity are larger, the problem of increasing the construction cost of precast construction.Node:Side setting beam widens area before and after precast beam and prefabricated post connecting pin, and multiple prestressing force bolt of long stem widen area and prefabricated post through beam, and each prestressing force bolt of long stem both ends are fastened with high-strength nut.Joint connecting method:One, bolt hole is beaten on precast beam and prefabricated post;Two, precast beam and prefabricated post, and the reserved last-cost joint between precast beam and prefabricated post are connected;Three, silicone weather resistant glue will be smeared along edge circumferential direction at the last-cost joint between precast beam and prefabricated post;Four, mortar is poured into a mould;Five, high-strength nut is installed;Six, multiple stirrups are installed, so far, the node for completing precast beam and prefabricated post connects.The present invention is connect for precast beam with prefabricated post.

Description

Bolt of long stem widens the bean column node connection method in area through beam side
Technical field
The present invention relates to a kind of bean column node and joint connecting methods, and in particular to a kind of bolt of long stem is widened through beam side The bean column node and joint connecting method in area.
Background technology
Precast beam, prefabricated post needed for fabricated construction need to carry out live splicing, the connecting node of precast beam and prefabricated post It, i.e., need to be to beam column node area formwork, laying framework of steel reinforcement, casting concrete, when node concrete reaches frequently with cast-in-place form After desired strength, then remove node area correlate template and support etc..This traditional prefabricated beam column connection operation method, essence On be still the thinking for continuing to use cast-in-place concrete, situ wet operation is more, and the duration is longer, and difficulty of construction and labor intensity are larger, The construction cost for increasing precast construction is unfavorable for promoting the efficiency of construction of precast construction.
Invention content
The present invention is to solve the connection of existing prefabricated beam and prefabricated Column border node using cast-in-place form, situ wet operation More, the duration is longer, and difficulty of construction and labor intensity are larger, increases the construction cost of precast construction, is unfavorable for being promoted pre- The problem of efficiency of construction of structure processed, it is proposed that a kind of bolt of long stem widens bean column node and the node connection side in area through beam side Method.
The bolt of long stem of the present invention widens the bean column node in area through beam side, composition include prefabricated post, precast beam, two Anchor slab, multiple prestressing force bolt of long stem, multiple high-strength nuts and multiple stirrups, the side before and after precast beam and prefabricated post connecting pin Setting beam widens area, precast beam connect with prefabricated post the back rest widen area end face outside be arranged there are one anchor slab, multiple prestressing force Bolt of long stem widens area and prefabricated post through beam, and each prestressing force bolt of long stem both ends are fastened with high-strength nut, and multiple stirrups are equal Cloth is arranged on the upper surface in precast beam local widening area.
The bolt of long stem of the present invention widens the bean column node connection method in area through beam side, and the method is by following step Suddenly it realizes:
Step 1: beating bolt hole on precast beam and prefabricated post:The beam of precast beam is widened into area and beats multiple beam spiral shells along longitudinal direction Keyhole beats multiple stud bolt holes in the region that prefabricated post is connect with precast beam, and multiple stud bolt holes and multiple beam bolt holes are one by one It is corresponding;
Step 2: connection precast beam and prefabricated post:Precast beam is lifted into the join domain of prefabricated post, and is made on precast beam Multiple beam bolt holes be aligned one by one with multiple stud bolt holes in prefabricated post, prestressing force bolt of long stem pass through beam bolt hole and column Bolt hole, and the reserved last-cost joint between precast beam and prefabricated post;
Step 3: smearing silicone weather resistant glue:At last-cost joint between precast beam and prefabricated post silicon will be smeared along edge circumferential direction Ketone weather-resistant glue, there are openings at the silicone weather resistant glue that top edge is smeared;
Step 4: cast mortar:Hollow light wall pipe is inserted between prestressing force bolt of long stem and beam bolt hole and stud bolt hole, Mortar is continuously noted into last-cost joint from opening, and is filled;
Step 5: installation high-strength nut:After body condensation, high-strength spiral shell is installed at prestressing force bolt of long stem both ends Mother, and tighten;
Step 6: installing multiple stirrups:Multiple stirrups are uniformly arranged on the upper surface in precast beam local widening area, and Stirrup is fixed on precast beam by casting concrete, and so far, the node for completing precast beam and prefabricated post connects.
The present invention has the advantages that compared with prior art:
One, node of the invention is to be additionally arranged beam in precast beam and prefabricated post join domain to widen area, passes through bolt of long stem Beam through beam side widens the beam-column connection in area, reduces existing difficulty of construction and working strength, it is easier to structural elements Installation positioning, and then reduce project cost, accelerate speed of application.
Two, method of the invention is to devise last-cost joint in precast beam and prefabricated post junction, by noting sand to last-cost joint Slurry comes reinforced cementitious so that the connection of precast beam and prefabricated post is more solid and reliable, strengthens the globality of beam-to-column joint.
Three, method construction technology of the invention is simple, does not need complicated construction machinery.
Description of the drawings
When Fig. 1 is that prefabricated post A is prefabricated side column in specific implementation mode one, prefabricated post A is surveyed with precast beam B node connecting shaft Figure;
When Fig. 2 is that prefabricated post A is prefabricated center pillar in specific implementation mode two, prefabricated post A is surveyed with precast beam B node connecting shaft Figure;
When Fig. 3 is that prefabricated post A is prefabricated side column in specific implementation mode three, prefabricated post A is surveyed with precast beam B node connecting shaft Figure;
When Fig. 4 is that prefabricated post A is prefabricated center pillar in specific implementation mode three, prefabricated post A is surveyed with precast beam B node connecting shaft Figure;
Fig. 5 is the connection relation stereogram of anchor slab 5, prestressing force bolt of long stem 3 and high-strength nut 4;
Fig. 6 is the vertical view of Fig. 1;
In the step of Fig. 7 is specific implementation mode six one on precast beam B multiple beam bolt hole B-1 position view;
In the step of Fig. 8 is specific implementation mode six three after silicone weather resistant glue 8 has been smeared at 7 edge of last-cost joint, silicone is resistance to Wait the cross sectional shape schematic diagram of glue 8;
Fig. 9 is the left view of Fig. 8.
Specific implementation mode
Specific implementation mode one:Illustrate present embodiment in conjunction with Fig. 1 and Fig. 5, present embodiment includes prefabricated post A, prefabricated Beam B, two anchor slabs 5, multiple prestressing force bolt of long stem 3, multiple high-strength nuts 4 and multiple stirrups 6, in precast beam B and prefabricated post A The front and back side setting beam of connecting pin widens area 2, and precast beam B, which connect the back rest with prefabricated post A and widens the end face outside in area 2, is provided with one A anchor slab 5, multiple prestressing force bolt of long stem 3 widen area 2 and prefabricated post A through beam, and each 3 both ends of prestressing force bolt of long stem are high Strong nut 4 fastens, and multiple stirrups 6 are uniformly arranged on the upper surface in precast beam local widening area 1.Stirrup 6 is answered for resisting to cut The effect of power.Prefabricated post A in present embodiment is prefabricated side column.What the beam of the both sides the precast beam B widened area 2 widens width For S.Beam widen area 2 to widen area height W2 equal with the depth of beam W3 of precast beam B.Beam widen area 2 widen sector width S2 and The requirement of bearing capacity due to local compression of concrete should be met by widening section length L2.It is that nut is directly made in order to prevent that anchor slab 5, which is arranged, The office of causing crushes bad on concrete.3 one end of prestressing force bolt of long stem in present embodiment is fixed with precast beam B, another End is fixed with prefabricated post A.
Specific implementation mode two:Embodiment is described with reference to Fig. 2, and the quantity of the precast beam B of present embodiment is two, Two precast beam B are symmetricly set on the left and right sides of prefabricated post A.Prefabricated post A in present embodiment is prefabricated center pillar, this embodiment party The both ends of prestressing force bolt of long stem 3 in formula are fixed on unidirectional two precast beam B.Anchor slab 5 in present embodiment Quantity be four.Other compositions and connection relation are same as the specific embodiment one.
Specific implementation mode three:Illustrate present embodiment in conjunction with Fig. 3 and Fig. 4, present embodiment prefabricated post A with it is prefabricated The region surrounding setting column thickened area 1 of beam B connections, beam widen the thickened area thickness for widening sector width S2 less than column thickened area 1 in area 2 Spend S1.When a precast beam B is connect with a prefabricated post A, prefabricated post A is prefabricated side column;When two precast beam B are symmetrically connected At the prefabricated post both sides A, prefabricated post A is prefabricated center pillar.In order to enable prefabricated post A is good to bear to come from precast beam B The thickened area thickness S1 of column should be arranged in the load at end according to mechanical characteristic.If prefabricated post A and precast beam B linkage interfaces can expire The requirement of the compression bearing of sufficient concrete can be not provided with column thickened area 1;If not satisfied, column thickening need to be arranged around column Area 1, thickened area thickness S1 should be required to be calculated according to the compression bearing of concrete.Prestressing force stock in present embodiment Bolt 3 widens area 2 and column thickened area 1 through beam.Other compositions and connection relation are the same as one or two specific embodiments.
Specific implementation mode four:Embodiment is described with reference to Fig. 3, and the thickened area of the column thickened area 1 of present embodiment is high Degree W1 and beam widen area 2 to widen area height W2 equal.Other compositions and connection relation are the same as the specific implementation mode 3.
Specific implementation mode five:Embodiment is described with reference to Fig. 3, and what the beam of present embodiment widened area 2 widens the head of district Spend the thickening section length L1 that L2 is less than column thickened area 1.Other compositions and connection relation are identical as specific implementation mode four.
Specific implementation mode six:Illustrate present embodiment in conjunction with Fig. 1~Fig. 9, present embodiment is through the following steps that reality Existing:
Step 1: beating bolt hole on precast beam B and prefabricated post A:By the beam of precast beam B widen area 2 beat along longitudinal direction it is multiple Beam bolt hole B-1 beats multiple stud bolt holes, multiple stud bolt holes and multiple beam spiral shells in prefabricated post A with the regions connecting precast beam B Keyhole B-1 is corresponded;
Step 2: connection precast beam B and prefabricated post A:Precast beam B is lifted into the join domain of prefabricated post A, and is made prefabricated Multiple beam bolt hole B-1 on beam B are aligned one by one with multiple stud bolt holes on prefabricated post A, and prestressing force bolt of long stem 3 passes through beam Bolt hole B-1 and stud bolt hole, and the reserved last-cost joint 7 between precast beam B and prefabricated post A;
Step 3: smearing silicone weather resistant glue 8:It will be applied along edge circumferential direction at last-cost joint 7 between precast beam B and prefabricated post A Silicone weather resistant glue 8 is smeared, there are opening 8-1 at the silicone weather resistant glue 8 that top edge is smeared;Silicone weather resistant glue 8 is commercial product;
Step 4: cast mortar:Hollow light wall pipe is inserted into prestressing force bolt of long stem 3 and beam bolt hole B-1 and stud bolt hole Between, mortar is continuously noted into last-cost joint 7 from opening 8-1, and fill;Hollow light wall pipe prevent slurry flow into beam bolt hole B-1 and In stud bolt hole;
Step 5: installation high-strength nut 4:After body condensation, high-strength spiral shell is installed at 3 both ends of prestressing force bolt of long stem Mother 4, and it is screwed to regulation torque;
Step 6: installing multiple stirrups 6:Multiple stirrups 6 are uniformly arranged in the upper surface in precast beam local widening area 1 On, and stirrup 6 is fixed on precast beam B by casting concrete, so far, is completed precast beam B and is connect with the node of prefabricated post A.
Specific implementation mode seven:Illustrate present embodiment in conjunction with Fig. 6, Fig. 8 and Fig. 9, present embodiment be in step 2 after The width T for pouring seam 7 is 20mm~30mm.Other steps are identical as specific implementation mode six.
Specific implementation mode eight:Illustrate present embodiment in conjunction with Fig. 6, Fig. 8 and Fig. 9, present embodiment be in step 2 after The width T for pouring seam 7 is 25mm.Other steps are identical as specific implementation mode six or seven.

Claims (3)

1. a kind of bolt of long stem widens the bean column node connection method in area through beam side, bean column node includes prefabricated post (A), prefabricated Beam (B), two anchor slabs (5), multiple prestressing force bolt of long stem (3), multiple high-strength nuts (4) and multiple stirrups (6), in precast beam (B) widen area (2) with the front and back side of the connecting pin prefabricated post (A) setting beam, precast beam (B) connect the back rest with prefabricated post (A) and widens There are one anchor slab (5), multiple prestressing force bolt of long stem (3) widen area (2) and prefabricated post through beam for the end face outside setting in area (2) (A), each prestressing force bolt of long stem (3) both ends are fastened with high-strength nut (4), and multiple stirrups (6) are uniformly arranged in precast beam office Portion is widened on the upper surface of area (1);The quantity of the precast beam (B) is two, and two precast beams (B) are symmetricly set on prefabricated post (A) column thickened area (1) is arranged in the region surrounding that prefabricated post (A) is connect with precast beam (B) in left and right sides, and beam widens area (2) Widen the thickened area thickness (S1) that sector width (S2) is less than column thickened area (1);The thickened area height (W1) and beam of column thickened area (1) Widen area (2) to widen area's height (W2) equal;The section length (L2) of widening that beam widens area (2) is less than adding for column thickened area (1) Thick section length (L1), it is characterised in that:The method through the following steps that realize:
Step 1: beating bolt hole on precast beam (B) and prefabricated post (A):The beam of precast beam (B) is widened area (2) to beat along longitudinal direction Multiple beam bolt holes (B-1) beat multiple stud bolt holes, multiple stud bolt holes in the region that prefabricated post (A) is connect with precast beam (B) It is corresponded with multiple beam bolt holes (B-1);
Step 2: connection precast beam (B) and prefabricated post (A):Precast beam (B) is lifted into the join domain of prefabricated post (A), and is made Multiple beam bolt holes (B-1) on precast beam (B) are aligned one by one with multiple stud bolt holes in prefabricated post (A), prestressing force stock Bolt (3) passes through beam bolt hole (B-1) and stud bolt hole, and the reserved last-cost joint between precast beam (B) and prefabricated post (A) (7);
Step 3: smearing silicone weather resistant glue (8):By at the last-cost joint (7) between precast beam (B) and prefabricated post (A) along edge ring To silicone weather resistant glue (8) is smeared, there are opening (8-1) at the silicone weather resistant glue (8) that top edge is smeared;
Step 4: cast mortar:Hollow light wall pipe is inserted into prestressing force bolt of long stem (3) and beam bolt hole (B-1) and stud bolt hole Between, mortar is continuously noted into last-cost joint (7) from opening (8-1), and fill;
Step 5: installation high-strength nut (4):After body condensation, high-strength spiral shell is installed at prestressing force bolt of long stem (3) both ends Female (4), and tighten;
Step 6: installing multiple stirrups (6):Multiple stirrups (6) are uniformly arranged in the upper surface in precast beam local widening area (1) On, and stirrup (6) is fixed on precast beam (B) by casting concrete, so far, completes the node of precast beam (B) and prefabricated post (A) Connection.
2. bolt of long stem according to claim 1 widens the bean column node connection method in area through beam side, it is characterised in that: The width (T) of last-cost joint (7) is 20mm~30mm in the step 2.
3. bolt of long stem according to claim 2 widens the bean column node connection method in area through beam side, it is characterised in that: The width (T) of last-cost joint (7) is 25mm in the step 2.
CN201610895523.6A 2016-10-13 2016-10-13 Bolt of long stem widens the bean column node connection method in area through beam side Active CN106638954B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610895523.6A CN106638954B (en) 2016-10-13 2016-10-13 Bolt of long stem widens the bean column node connection method in area through beam side

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610895523.6A CN106638954B (en) 2016-10-13 2016-10-13 Bolt of long stem widens the bean column node connection method in area through beam side

Publications (2)

Publication Number Publication Date
CN106638954A CN106638954A (en) 2017-05-10
CN106638954B true CN106638954B (en) 2018-10-02

Family

ID=58855979

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610895523.6A Active CN106638954B (en) 2016-10-13 2016-10-13 Bolt of long stem widens the bean column node connection method in area through beam side

Country Status (1)

Country Link
CN (1) CN106638954B (en)

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108867861B (en) * 2017-05-12 2021-05-07 吴方华 Bolt reinforcing bar bolt prefabricated assembly concrete beam column side node
CN109098277B (en) * 2017-06-20 2021-05-11 吴方华 Bolt reinforcing bar bolt assembled concrete frame beam column node
CN109183986A (en) * 2018-11-08 2019-01-11 安徽建筑大学 A kind of assembling frame Structure Beam-column connecting node and construction method

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101024975A (en) * 2007-03-16 2007-08-29 北京城建设计研究总院有限责任公司 Shaped-steel concrete frame-steel supporting structure section-changeable conversion node
CN103422576A (en) * 2013-09-10 2013-12-04 南京工业大学 Reinforcement and energy dissipation damping device for wood structure mortise and tenon joint

Family Cites Families (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0715181B2 (en) * 1989-09-01 1995-02-22 鹿島建設株式会社 Method of joining closed-section steel columns to steel beams
JPH0830360B2 (en) * 1990-03-27 1996-03-27 三菱建設株式会社 Connection method for columns and beams
KR101132213B1 (en) * 2005-03-25 2012-03-30 동국대학교 산학협력단 Improved Rigid Joint Structure of CFT Precast Concrete Column Unit and Steel Beam

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101024975A (en) * 2007-03-16 2007-08-29 北京城建设计研究总院有限责任公司 Shaped-steel concrete frame-steel supporting structure section-changeable conversion node
CN103422576A (en) * 2013-09-10 2013-12-04 南京工业大学 Reinforcement and energy dissipation damping device for wood structure mortise and tenon joint

Also Published As

Publication number Publication date
CN106638954A (en) 2017-05-10

Similar Documents

Publication Publication Date Title
EP3670778B1 (en) Prefabricated frame
CN105735112B (en) Bolt connection-based rapid assembling precast rectangular concrete filled steel tube bridge pier
KR101204763B1 (en) Structure of sandwich pannel with precast concrete and cast in place concrete for pipe utility conduit
CN106284655B (en) Precast concrete beam stud connects connecting node and connection method
CN109183986A (en) A kind of assembling frame Structure Beam-column connecting node and construction method
KR101225661B1 (en) Concrete shear key strengthened with steel cover plate and tension member and the construction method therewith
CN205894313U (en) Prefabricated assembled steel pipe retrains frame node entirely
CN107152104B (en) Assembled cavity shear wall horizontal joint tooth socket rotating vane type connection structure
CN106638954B (en) Bolt of long stem widens the bean column node connection method in area through beam side
CN208363404U (en) A kind of prefabricated panel and its connection structure
CN203452228U (en) Frame-shear wall architectural structure
CN108775084B (en) Steel-concrete combined precast beam and precast column connecting structure and construction method
JP2004108034A (en) Foundation structure, construction method and steel-pipe-mounted precast concrete pile for steel-framed building
CN108505647A (en) A kind of prefabricated assembled profiled sheet concrete shear force wall and its construction method
CN108589915A (en) A kind of external steel plate of assembly concrete column is to drawing connecting node and its construction method
CN106869008A (en) The composite bridge prefabricated bridge of dry type connection and its dry type connection method
CN209066596U (en) A kind of assembling frame Structure Beam-column connecting node
CN110107019A (en) A kind of combined type precast floor slab for assembled architecture
CN109113171A (en) A kind of Novel bolt connection Precast Concrete Frame
CN210597875U (en) Cross beam
CN210562663U (en) Connecting structure of prefabricated plate and prefabricated column
CN107201782A (en) A kind of wall of assembled architecture, floor connecting node and method
CN209854778U (en) Post-cast strip support-free structure
CN208884728U (en) Steel-concrete combines precast beam and prefabricated post connection structure
CN109881777B (en) Assembled high-toughness cement-based composite material beam column joint

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant