CN106638295A - Pavement method of steel bridge deck made from epoxy asphalt - Google Patents

Pavement method of steel bridge deck made from epoxy asphalt Download PDF

Info

Publication number
CN106638295A
CN106638295A CN201611251017.XA CN201611251017A CN106638295A CN 106638295 A CN106638295 A CN 106638295A CN 201611251017 A CN201611251017 A CN 201611251017A CN 106638295 A CN106638295 A CN 106638295A
Authority
CN
China
Prior art keywords
temperature
steel
paving
bridge deck
epoxy
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201611251017.XA
Other languages
Chinese (zh)
Inventor
彭申凯
任杰
沈维成
刘晓晗
熊祖发
王帅
段传印
王进
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Anhui Road and Bridge Engineering Co Ltd
Original Assignee
Anhui Road and Bridge Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Anhui Road and Bridge Engineering Co Ltd filed Critical Anhui Road and Bridge Engineering Co Ltd
Priority to CN201611251017.XA priority Critical patent/CN106638295A/en
Publication of CN106638295A publication Critical patent/CN106638295A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D19/00Structural or constructional details of bridges
    • E01D19/08Damp-proof or other insulating layers; Drainage arrangements or devices ; Bridge deck surfacings
    • E01D19/083Waterproofing of bridge decks; Other insulations for bridges, e.g. thermal ; Bridge deck surfacings
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Road Paving Structures (AREA)

Abstract

The invention provides a pavement method of a steel bridge deck made from epoxy asphalt, comprising the following steps: (1) applying abrasive blasting for rust removal and anti-corrosion treatment to the steel bridge deck, and measuring an atmospheric temperature, an atmospheric humidity and a temperature of a steel plate in the process of the rust removal and coating operations; (2) carrying out a construction of a waterproof layer, wherein the spraying quantity on the steel bridge deck interface is 0.66 +/- 0.03 kg/m2====m<2> and the same on the asphalt mixture interface is 0.45 +/- 0.03 kg/m2====m<2> under the construction condition with a temperature ranging from 15 to 30 DEG C; (3) carrying out a construction of a bridge deck pavement layer, wherein the proportion of aggregates of a cold aggregate bin is determined based on the radio of the aggregates determined by the target mix proportion; the heating temperature of aggregates is controlled to be in a range from 130 to 140 DEG C; a sieving test is carried out by sampling from a hot aggregate bin; a mineral aggregate consists of 24% of coarse aggregates with diameter being 5-10mm, 69% of fine aggregates with diameter being 0-5mm and 7% of mineral powder; and the asphalt-aggregate mass ratio is 6.8%. The steel bridge deck made from the epoxy asphalt by using the pavement method has the advantages of being high in bonding strength, not liable to delaminate or slip, good in waterproof performance, not liable to be permeated by water to corrode the steel plate, high in corrosion resistance and capable of extending the service life of the bridge. Therefore, the epoxy asphalt is an excellent binding agent, and is especially applicable for an orthotropic steel bridge deck system.

Description

A kind of method for paving of bituminous epoxy Steel Bridge Deck
Technical field
The present invention relates to technical field of bridge deck pavement is planted, specially a kind of method for paving of bituminous epoxy Steel Bridge Deck.
Background technology
Steel bridge deck stress and deformation ratio highway pavement are much more complex, because it can occur a certain degree of deformation, to bonding Layer and the intensity of pave-load layer, deformability, temperature characterisitic and fatigue durability etc. have higher requirement, paving steel bridge deck technology It is the worldwide technological puzzle for affecting steel bridge durability.In prior art, paving steel bridge deck substantially adopts bituminous concrete System, from the material and construction method angle selected, basically forms the conceptual design of " three kinds of materials, four kinds of structures ":(1) Germany, cast asphalt concrete (Gussasphalt) scheme that Japan is representative;Cast asphalt concrete pave-load layer and drip The major advantage of blue or green matizhi concrete pavement layer is:Voidage close zero, with good waterproof, ageing resistace, cracking resistance Performance is strong, and to the adhesive property between the following and steel plate of steel plate general bituminous concrete is better than.Its major defect is:High temperature Stability is poor, easily forms rut.(2) bitumastic concrete (Mastic asphalt) scheme with Britain as representative is (real It is also that cast asphalt concrete, simply pavement thickness and technique are different with Japan etc. on border);(3) Germany and Japan etc. The modified asphalt SMA scheme (Stone Mastic Asphalt) that state adopts in the recent period;The master of modified asphalt SMA concrete pavement layer The advantage is wanted to be:Pliability, anti-loose, anti-crack ability are strong, with good durability and water resistance;Anti- creeping and anti-permanent change The ability of shape is strong, is not likely to produce rut, and with coarse surface structure, non-skid property is good, and difficulty of construction is relatively small, the construction time Short, expense is relatively low, but needs further to solve the bonding and waterproof problem of pave-load layer and steel plate.(4) with the U.S. as representative Epoxy resin asphalt (Epoxy asphalt) concrete scheme.
The content of the invention
Technical problem solved by the invention is to provide a kind of method for paving of bituminous epoxy Steel Bridge Deck, above-mentioned to solve Problem in background technology.
Technical problem solved by the invention employs the following technical solutions to realize:A kind of bituminous epoxy Steel Bridge Deck is mated formation Method, comprises the following steps:
(1) bridge floor derusting by sandblasting, preservative treatment;In rust cleaning and painting operation, measurement atmospheric temperature, humidity and steel plate temperature Degree, relative humidity of atomsphere 40-85%, steel billet temperature should be higher than that dew-point temperature 3-10 DEG C;
1.1st, bridge floor derusting by sandblasting:Operation is carried out using Full-automatic dustless abrasive blast equipment, bridge floor corner part is using artificial Technique for grinding is eliminated rust;Full-automatic dustless abrasive blast equipment rust cleaning bridge floor cleannes reach the requirement of Sa2.5 levels;Manual polishing work Skill rust cleaning bridge floor cleannes reach the requirement of Sa3.0 levels;The requirement of roughness reaches 50~100 μm;
1.2nd, bridge floor anti-corrosion is disposed:The spray of ground floor epoxy zinc-rich paint on steel plate is completed after Steel Bridge Deck derusting by sandblasting within 4h Apply anti-corrosion to dispose, its performance is detected before spraying epoxy zinc-rich paint, the spraying of ground floor epoxy zinc-rich paint is completed, and is dried 4- Second layer epoxy zinc-rich paint is sprayed after 12h;Continue afterwards to be dried after 4-12h the construction operation for carrying out bituminous epoxy water-proof tack coat, In the spraying process of epoxy zinc-rich paint, Steel Bridge Deck surface is complete, uniform, without holiday phenomenon, after the completion of spraying, coating should it is continuous, Uniformly, it is smooth, without particle, no sag or other defect, color answers uniformity, 50~100 μm of thickness, if enamelled coating have it is show-through or Breakage, should be carried out sectional repair or is all reprocessed according to defect size and the order of severity by above-mentioned technique;Epoxy zinc-rich paint is 25 Surface drying time is 5-15min, is fully cured time 3-7d and steel plate adhesion strength 5-15Mpa at DEG C;
(2) bond capacity construction;Under the conditions of 15-30 DEG C of temperature of construction, bituminous epoxy binding material going out in sprinkling Material temperature degree is 120 DEG C, and the time of staying in pipeline cannot be greater than 10min, and Steel Bridge Deck interface spread quantity is 0.66 ± 0.03kg/ m2;Asphalt interface is 0.45 ± 0.03kg/m2
2.1st, bridge floor cleaning:Tack coat dispenses front soft broom and clears away bridge floor dust, debris;If any greasy dirt, nonionic is used Type soap powder aqueous cleaning is finally clean with water cleaning down and be completely dried;Works surface to protruding bridge floor is also clear Wash clean;Spraying range of each cleaning scope more than subsequent bituminous epoxy binding material;Meanwhile, to avoid being contacted with pave-load layer Position in addition is polluted, and these positions all cover in advance;
2.2nd, tack coat spread:Spread fabric width and boundary line are divided, to ensure that distribution vehicle carries out spread by prescribed limit, bonding Spreading tube highly should ensure that no less than dual repeatedly spread quantity during material spread, enter pedestrian to the grey face of appearance during spread afterwards Work is mended and spilt, and mending the amount of spilling should control in prescribed limit, after the completion of bituminous epoxy water-proof tack coat spread, job site should be kept clear It is clean;
(3) bridge deck pavement construction;Gathered materials ratio according to the proportioning setting cold burden storehouse that gathers materials that Target Mixture Ratio determines, control Aggregate heating temperature is 130-140 DEG C, and from hot aggregate bin sampling sieve test, mineral aggregate composition are carried out:5-10mm coarse aggregates 24%, 0- 5mm fine aggregates 69%, breeze 7%, oilstone mass ratio:6.8%;
3.1st, compound is mixed and stirred:The temperature of bituminous epoxy mix should be maintained at set point of temperature between 105-110 DEG C, mix and stir The operating personnel that stand should keep a close eye on temperature variations, forbid significantly adjusting air door and throttle, it is to avoid temperature fluctuation is too big;
3.2nd, dry mixing:The each cold burden storehouse feeding speed determined during according to trial mix heats mineral aggregate temperature to dryer feeding To 105-110 DEG C, it is heated after enter hot aggregate bin, in strict accordance with refinery operation scheduling determine each hot aggregate bin aggregate quality and The quality of breeze, input is mixed cylinder and carries out dry mixing, and the dry mixing time is the 5-20 seconds, then measures hot material temperature;This operation repeats 3-5 Time, until drop temperature is stable to mix and stir temperature 105-110 DEG C;
3.3rd, wet-mixing:Gathering materials of working good is heated into 105-110 DEG C, while bituminous epoxy is passed through into special adding set It is added to and mixes in cylinder, carries out wet-mixing, 30-90 seconds wet-mixing time;Epoxy asphalt mixture is discharged into interim hot material after the completion of mixing and stirring In bucket, thermometric immediately, the drop temperature of compound should be controlled at 105-110 DEG C;Compound is mixed and stirred after temperature stabilization, you can formal Discharging, per car compound loading time is less than 10 minutes;
3.4th, compound transport:To prevent compound from adhering with material mover carriage, the portion contacted with compound in all compartments Position, used as interleaving agent, haulage vehicle adds a cover canvas or cotton-wadded quilt to brushing vegetable oil in transportation, to slow down mixture temperature Reduce, haulage time is less than 50 minutes;
3.5th, mixture laying:Epoxy asphalt mixture is paved using the bituminous pavement paving machine of regulation, in paving process The workability and surface uniformity of compound is should ensure that, so that compacted depth meets requiring, it is to avoid gather materials isolation, and paves Mix surface afterwards should be without coarse aggregate or fine aggregate hole, the surface that paves must not manually rake;
If special messenger calculates and control spreading speed, discharge time model " is allowed according to feed capacity and each truck feeding list Enclose " adjusted in time, to control not shut down, not overtime, make every effort at the uniform velocity to pave for principle, spreading speed general control 2~ 4m/min;
Paving for compound is carried out according to the coefficient of loose laying that test section is obtained;Once pine is surveyed in paving process per 10m spread thick Degree, and note road camber, adjusted if necessary, must smooth out, in the hope of not affecting the material position in flatness, and spiral distributor It is advisable with being slightly above spiral distributor 2/3, it is to avoid isolation occurs in paved mixture;
3.6th, pave-load layer is rolled:Using two kinds of " rubber tire-steel wheel-rubber tire-steel wheel " and " steel wheel-rubber tire-rubber tire-steel wheel " Compaction assembly mode, compound elapses flatness situation after the completion of situation and final pressure, wheel pelmatogram situation in observation construction, and record grinds Pressure pass and mixture temperature, determine the rational compaction assembly form in different layers position and respectively roll the number of rolling in stage, are guarantor Card consolidation effect, cutting optimal is rolled using the order of " glue-steel-glue-steel ", and upper layer is suitable using " steel-glue-glue-steel " Sequence is rolled, if producing bubble in roller compaction process, is poked with sharp thing at once and is compacted again, for road roller pressing It is real less than local pave-load layer, cutting optimal uses pressure road using hand compaction or hand-held vibration rammer vibration compacting, upper layer Machine is compacted.
Further, it is described to carry out first pressing after mixture laying at once in step (3), temperature drop is just pressed in 75- 80 DEG C complete before, and first pressing should closely follow paver, and number of machine passes is 4-8 time, and multiple pressure 4 times should be at once carried out after the completion of first pressing, multiple After the completion of pressure should final pressure 4 times at once, final pressure should complete before mixture temperature drops to 50 DEG C.
Further, first pressing and the final pressure in step (3) are all after having pressed 3 times, to be measured with infrared thermometry and remembered Surface temperature, when surface temperature is unsatisfactory for requiring, then surveys internal temperature with plug-in type thermometer, when internal temperature is unsatisfactory for wanting When asking, in addition to twice of multiple pressure, to ascertain the reason, adopt an effective measure, and prevent to occur again.
Further, road roller driving wheel when rolling in step (3) from low to high, connects successively towards paver Continue and uniformly roll, the adjacent band that rolls overlaps 1/3 wheel width, does not allow road roller to turn in the scope of operation, reverse end for end, road roller starting, Stop the jogging that must slow down, forbidden emergency brake braking.
Further, it is described distinguishing mark to be arranged to first pressing, multiple pressure, final pressure paragraph in step (3), it is easy to driver to distinguish Recognize, to rolling order, road roller combination, number of rolling, rolling speed and rolling temperature special hilllock management and inspection, record should be set, Firmly prevent surface layer leakage pressure.After mixture laying, road roller is immediately rolled, to shorten rolling operation segment length, but not produce Passage, shattered crack are principle.
Further, it is described in Mechanical Spreading, manually to repair repeatedly in step 3.5, but ought there is section Undesirable, local lack material, local mixing material substantially isolate, the obvious out-of-flatness in surface, dead material problem when, in construction technology people Conscientiously adjustment, partial refuelling, carefully repairing, with compound drop-over is spread, does not stay trace and difference under member's specific guidance.
Further, it is described in step 3.5 in paving process by special messenger to spiral distributor and hopper in " dead material " Cleared up, the waste material of generation, " dead material " should be concentrated and be placed in small handcart in paving process, then clean out job site, If meeting rain suddenly in paving, construction, and the compound of the non-compaction moulding of removing are stopped immediately, non-paved mixture must be whole It is discarded.
It is further, described that when paving with first pressing, the workability of observation and record compound, surface are equal in step (3) Even property, whether there is wheel pelmatogram situation, and temperature when recording construction after first pressing.
Compared with disclosed technology, there is advantages below in the present invention:The present invention has high bond strength, is not likely to produce de- The diseases such as layer, sliding;Water resistance is good, is difficult permeable erosion steel plate;Anti-corrosive properties are strong, extend bridge and benefit from the life-span.Therefore epoxy Pitch is a kind of excellent binding agent, is particularly suited for Orthotropic Steel Bridge Deck system.
Specific embodiment
In order that the technological means of the present invention, creation characteristic, workflow, using method reached purpose and effect are easy to bright It is white to understand, below in conjunction with the embodiment of the present invention, the technical scheme in the embodiment of the present invention is clearly and completely described, Obviously, described embodiment is only a part of embodiment of the invention, rather than the embodiment of whole.Based in the present invention Embodiment, the every other embodiment that those of ordinary skill in the art are obtained under the premise of creative work is not made, all Belong to the scope of protection of the invention.
Embodiment 1
A kind of method for paving of bituminous epoxy Steel Bridge Deck, comprises the following steps:
(1) bridge floor derusting by sandblasting, preservative treatment;In rust cleaning and painting operation, measurement atmospheric temperature, humidity and steel plate temperature Degree, relative humidity of atomsphere 40-85%, steel billet temperature should be higher than that dew-point temperature 3-10 DEG C;
1.1st, bridge floor derusting by sandblasting:Operation is carried out using Full-automatic dustless abrasive blast equipment, bridge floor corner part is using artificial Technique for grinding is eliminated rust;Full-automatic dustless abrasive blast equipment rust cleaning bridge floor cleannes reach the requirement of Sa2.5 levels;Manual polishing work Skill rust cleaning bridge floor cleannes reach the requirement of Sa3.0 levels;The requirement of roughness reaches 50~100 μm;
1.2nd, bridge floor anti-corrosion is disposed:The spray of ground floor epoxy zinc-rich paint on steel plate is completed after Steel Bridge Deck derusting by sandblasting within 4h Apply anti-corrosion to dispose, its performance is detected before spraying epoxy zinc-rich paint, the spraying of ground floor epoxy zinc-rich paint is completed, and is dried 4- Second layer epoxy zinc-rich paint is sprayed after 12h;Continue afterwards to be dried after 4-12h the construction operation for carrying out bituminous epoxy water-proof tack coat, In the spraying process of epoxy zinc-rich paint, Steel Bridge Deck surface is complete, uniform, without holiday phenomenon, after the completion of spraying, coating should it is continuous, Uniformly, it is smooth, without particle, no sag or other defect, color answers uniformity, 50~100 μm of thickness, if enamelled coating have it is show-through or Breakage, should be carried out sectional repair or is all reprocessed according to defect size and the order of severity by above-mentioned technique;Epoxy zinc-rich paint is 25 Surface drying time is 5-15min, is fully cured time 3-7d and steel plate adhesion strength 5-15Mpa at DEG C;
(2) bond capacity construction;Under the conditions of 15-30 DEG C of temperature of construction, bituminous epoxy binding material going out in sprinkling Material temperature degree is 120 DEG C, and the time of staying in pipeline cannot be greater than 10min, and Steel Bridge Deck interface spread quantity is 0.66 ± 0.03kg/ m2;Asphalt interface is 0.45 ± 0.03kg/m2
2.1st, bridge floor cleaning:Tack coat dispenses front soft broom and clears away bridge floor dust, debris;If any greasy dirt, nonionic is used Type soap powder aqueous cleaning is finally clean with water cleaning down and be completely dried;Works surface to protruding bridge floor is also clear Wash clean;Spraying range of each cleaning scope more than subsequent bituminous epoxy binding material;Meanwhile, to avoid being contacted with pave-load layer Position in addition is polluted, and these positions all cover in advance;
2.2nd, tack coat spread:Spread fabric width and boundary line are divided, to ensure that distribution vehicle carries out spread by prescribed limit, bonding Spreading tube highly should ensure that no less than dual repeatedly spread quantity during material spread, enter pedestrian to the grey face of appearance during spread afterwards Work is mended and spilt, and mending the amount of spilling should control in prescribed limit, after the completion of bituminous epoxy water-proof tack coat spread, job site should be kept clear It is clean;
(3) bridge deck pavement construction;Gathered materials ratio according to the proportioning setting cold burden storehouse that gathers materials that Target Mixture Ratio determines, control Aggregate heating temperature is 130-140 DEG C, and from hot aggregate bin sampling sieve test, mineral aggregate composition are carried out:5-10mm coarse aggregates 24%, 0- 5mm fine aggregates 69%, breeze 7%, oilstone mass ratio:6.8%;
3.1st, compound is mixed and stirred:The temperature of bituminous epoxy mix should be maintained at set point of temperature between 105-110 DEG C, mix and stir The operating personnel that stand should keep a close eye on temperature variations, forbid significantly adjusting air door and throttle, it is to avoid temperature fluctuation is too big;
3.2nd, dry mixing:The each cold burden storehouse feeding speed determined during according to trial mix heats mineral aggregate temperature to dryer feeding To 105-110 DEG C, it is heated after enter hot aggregate bin, in strict accordance with refinery operation scheduling determine each hot aggregate bin aggregate quality and The quality of breeze, input is mixed cylinder and carries out dry mixing, and the dry mixing time is the 5-20 seconds, then measures hot material temperature;This operation repeats 3-5 Time, until drop temperature is stable to mix and stir temperature 105-110 DEG C;
3.3rd, wet-mixing:Gathering materials of working good is heated into 105-110 DEG C, while bituminous epoxy is passed through into special adding set It is added to and mixes in cylinder, carries out wet-mixing, 30-90 seconds wet-mixing time;Epoxy asphalt mixture is discharged into interim hot material after the completion of mixing and stirring In bucket, thermometric immediately, the drop temperature of compound should be controlled at 105-110 DEG C;Compound is mixed and stirred after temperature stabilization, you can formal Discharging, per car compound loading time is less than 10 minutes;
3.4th, compound transport:To prevent compound from adhering with material mover carriage, the portion contacted with compound in all compartments Position, used as interleaving agent, haulage vehicle adds a cover canvas or cotton-wadded quilt to brushing vegetable oil in transportation, to slow down mixture temperature Reduce, haulage time is less than 50 minutes;
3.5th, mixture laying:Epoxy asphalt mixture is paved using the bituminous pavement paving machine of regulation, in paving process The workability and surface uniformity of compound is should ensure that, so that compacted depth meets requiring, it is to avoid gather materials isolation, and paves Mix surface afterwards should be without coarse aggregate or fine aggregate hole, the surface that paves must not manually rake;
If special messenger calculates and control spreading speed, discharge time model " is allowed according to feed capacity and each truck feeding list Enclose " adjusted in time, to control not shut down, not overtime, make every effort at the uniform velocity to pave for principle, spreading speed general control 2~ 4m/min;
Paving for compound is carried out according to the coefficient of loose laying that test section is obtained;Once pine is surveyed in paving process per 10m spread thick Degree, and note road camber, adjusted if necessary, must smooth out, in the hope of not affecting the material position in flatness, and spiral distributor It is advisable with being slightly above spiral distributor 2/3, it is to avoid isolation occurs in paved mixture;
In Mechanical Spreading, manually must not repair repeatedly, but when occurring, section is undesirable, locally lack material, local Compound is substantially isolated, the obvious out-of-flatness in surface, dead material problem when, conscientiously adjustment, office under construction technical staff specific guidance Portion reloads, and carefully repairs, and with compound drop-over is spread, does not stay trace and difference.
In paving process by special messenger to spiral distributor and hopper in " dead material " clear up, produce in paving process Waste material, " dead material " should concentrate and be placed in small handcart, then clean out job site, if meeting rain suddenly in paving, stop immediately Only construct, and remove the compound of non-compaction moulding, non-paved mixture must be discarded all;
3.6th, pave-load layer is rolled:Using two kinds of " rubber tire-steel wheel-rubber tire-steel wheel " and " steel wheel-rubber tire-rubber tire-steel wheel " Compaction assembly mode, compound elapses flatness situation after the completion of situation and final pressure, wheel pelmatogram situation in observation construction, and record grinds Pressure pass and mixture temperature, determine the rational compaction assembly form in different layers position and respectively roll the number of rolling in stage, are guarantor Card consolidation effect, cutting optimal is rolled using the order of " glue-steel-glue-steel ", and upper layer is suitable using " steel-glue-glue-steel " Sequence is rolled, if producing bubble in roller compaction process, is poked with sharp thing at once and is compacted again, for road roller pressing It is real less than local pave-load layer, cutting optimal uses pressure road using hand compaction or hand-held vibration rammer vibration compacting, upper layer Machine is compacted.
During construction, first pressing is carried out after mixture laying at once, be just pressed in temperature drop and complete before to 75-80 DEG C, first pressing Paver should be closelyed follow, number of machine passes is 4-8 time, multiple pressure 4 times should be at once carried out after the completion of first pressing, should final pressure at once after the completion of multiple pressure 4 times, final pressure should be completed before mixture temperature drops to 50 DEG C.
During construction, first pressing and final pressure are all after having pressed 3 times, note surface temperature to be measured with infrared thermometry, when surface temperature Degree surveys internal temperature when being unsatisfactory for requiring, then with plug-in type thermometer, when internal temperature is unsatisfactory for requiring, except twice of multiple pressure Outward, to ascertain the reason, adopt an effective measure, and prevent to occur again.
During construction, towards paver, from low to high, successively continuous uniform is rolled road roller driving wheel when rolling, adjacent stone roller Pressure zone overlaps 1/3 wheel width, does not allow road roller to turn in the scope of operation, reverse end for end, and road roller is started, stops the jogging that must slow down, Inaccurate emergency brake braking.
During construction, distinguishing mark is arranged to first pressing, multiple pressure, final pressure paragraph, be easy to driver to recognize, to rolling order, pressure Road machine combination, number of rolling, rolling speed and roll temperature should set the management of special hilllock and check, record, firmly prevent surface layer leakage pressure. After mixture laying, road roller is immediately rolled, to shorten rolling operation segment length, but not produce passage, shattered crack as principle.
During construction, workability, the surface uniformity of compound is observed and recorded when paving with first pressing, wheel is whether there is after first pressing Pelmatogram situation, and temperature when recording construction.
(1) asphalt binder used by epoxy asphalt concrete is a kind of thermosets, fundamentally changes pitch Thermoplasticity, imparts the excellent physical and chemical performance of compound.Bituminous epoxy is to form irreversible, insoluble by chemical reaction Tridimensional network, with good high-temperature stability, Rut resistance, antifatigue, cohesive force, waterproof etc., its mechanical strength is general 3~5 times of logical bituminous concrete.This adapts to completely China's national situation (Heavy Traffic is big, hot weather is more), big with the southeast in recent years Learn the epoxy asphalt mixture based on research and development to be widely used in the deck paving of Large Span Bridges, obtain good effect.It is beautiful State is in 1967 first by pave-load layer of the bituminous epoxy as San Mateo-Hayward bridge orthotropic plate bridge floors, effect Fruit is good, and then epoxy asphalt mixture is used as steel deck paving package material by Japan, Canada, Holland and Australia in succession. The country, Zhoushan peach Tianmen bridge, Qingpu Shanghai bridge, Tianjin Gu Kou bridges, Jiangsu Run-yang bridge, the bridge of yangtze river in nanjing two, Jiangyin Yangtze Bridge etc. adopts epoxy asphalt pavement, runs well, and heavy damage does not occur.
(2) water-proof tack coat adopts epoxy zinc-rich paint+bituminous epoxy binding agent, a large number of experiments show that, epoxy zinc-rich paint tool There is preferable antiseptic effect, this is one of material more than the comparison of early stage domestic steel bridge deck anti-corrosion.Bituminous epoxy binding agent Belong to reactive explosive, with high bond strength, be not likely to produce the diseases such as delamination, sliding;Water resistance is good, is difficult permeable erosion Steel plate;Anti-corrosive properties are strong, extend bridge and benefit from the life-span.Therefore bituminous epoxy is a kind of excellent binding agent, is particularly suited for orthogonal Different in nature steel bridge deck system.
(3) paving hazard is widely applied at home, yangtze river in nanjing two with its excellent high temperature anti-rut behavior There is not the disease such as high temperature rut and passage already close to 10 years in bridge service life.Moisten positive bridge, the main bridge steel of Su-Tong Brideg afterwards Bridge floor all employs epoxy asphalt concrete paving hazard.Deck paving is due to being located on hanging bridge structure, in summer Hot weather, can reach 70 DEG C, higher than road surface 10 DEG C, it is therefore desirable to paving material has good high-temperature stability.Exist successively Respectively rut is carried out to epoxy asphalt concrete, AC modified asphalt concretes and SMA mixture under under the conditions of 60 DEG C and 70 DEG C Test, as a result finds the dynamic stability (secondary mm-1) of AC modified asphalt concretes and SMA at 60 DEG C about more than 2000, And epoxy asphalt concrete does not almost deform.
(4) bituminous epoxy is due to having higher intensity and larger stiffness modulus, so making in equal fatigue stress With under, compared with common pitch, with very excellent fatigue performance, its fatigue life be usually plain asphalt 10~ 30 times or so.According to fatigue behaviour comparative test result of the Australian Xi Men great Qiao management boards to various bituminous concretes, can The fatigue life for drawing epoxy asphalt concrete is 5 × 106It is secondary, and the fatigue life of bituminous concrete is only under equal experiment condition 0.29 × 10 can be reached6Secondary, both have differed as many as 13 times.For Large Span Bridges, when load action thereon when, its change Shape is big compared with road surface, along with wind load, and the use environment of harshness, it is very high to fatigue durability requirement, and epoxy asphalt mixture This excellent fatigue performance the performance of paving bridge floor will be had greatly improved.
(5) the brittle point temperature of epoxy asphalt concrete can not embody the superiority of itself, but this can not illustrate ring The crack resistance at low-temperature of oxygen asphalt is bad.Experiment show -15 DEG C at epoxy asphalt mixture compared with casting mixture, Bending strain result explanation epoxy asphalt mixture comparatively speaking still has certain low temperature advantage.
(6) mixer of epoxy asphalt concrete plain asphalt is mixed and stirred, it paves, compacting machinary is with plain asphalt coagulation Soil does not have any difference, and the only requirement to compound to temperature and time is more harsh.Need to be completed within " presetting period " All of work, then quality can not reach most preferably, or become waste material.At present, epoxy asphalt mixture deck paving technology has been Jing relative maturities, define the system of complete set.
General principle, principal character and the advantages of the present invention of the present invention has been shown and described above.The technology of the industry Personnel it should be appreciated that the present invention is not restricted to the described embodiments, the simply explanation described in above-described embodiment and specification this The principle of invention, without departing from the spirit and scope of the present invention, the present invention also has various changes and modifications, these changes Change and improvement is both fallen within scope of the claimed invention.The claimed scope of the present invention by appending claims and Its equivalent thereof.

Claims (8)

1. a kind of method for paving of bituminous epoxy Steel Bridge Deck, it is characterised in that:Comprise the following steps:
(1) bridge floor derusting by sandblasting, preservative treatment;In rust cleaning and painting operation, measurement atmospheric temperature, humidity and steel billet temperature, Relative humidity of atomsphere 40-85%, steel billet temperature should be higher than that dew-point temperature 3-10 DEG C;
1.1st, bridge floor derusting by sandblasting:Operation is carried out using Full-automatic dustless abrasive blast equipment, bridge floor corner part adopts manual polishing Technique is eliminated rust;Full-automatic dustless abrasive blast equipment rust cleaning bridge floor cleannes reach the requirement of Sa2.5 levels;Manual polishing technique is removed Rust bridge floor cleannes reach the requirement of Sa3.0 levels;The requirement of roughness reaches 50~100 μm;
1.2nd, bridge floor anti-corrosion is disposed:The spraying for completing ground floor epoxy zinc-rich paint on steel plate after Steel Bridge Deck derusting by sandblasting within 4h is prevented Corruption is disposed, and its performance is detected before spraying epoxy zinc-rich paint, and the spraying of ground floor epoxy zinc-rich paint is completed, and is dried 4-12h Second layer epoxy zinc-rich paint is sprayed afterwards;Continue afterwards to be dried after 4-12h the construction operation for carrying out bituminous epoxy water-proof tack coat, epoxy In the spraying process of zinc rich paint, Steel Bridge Deck surface is complete, uniform, without holiday phenomenon, after the completion of spraying, coating should it is continuous, uniform, It is smooth, without particle, no sag or other defect, color answers uniformity, 50~100 μm of thickness, if enamelled coating has show-through or breakage, Should carry out sectional repair by above-mentioned technique or all reprocess according to defect size and the order of severity;Epoxy zinc-rich paint is at 25 DEG C Surface drying time is 5-15min, is fully cured time 3-7d and steel plate adhesion strength 5-15Mpa;
(2) bond capacity construction;Under the conditions of 15-30 DEG C of temperature of construction, bituminous epoxy binding material goes out material temperature in sprinkling Spend for 120 DEG C, the time of staying in pipeline cannot be greater than 10min, Steel Bridge Deck interface spread quantity is 0.66 ± 0.03kg/m2; Asphalt interface is 0.45 ± 0.03kg/m2
2.1st, bridge floor cleaning:Tack coat dispenses front soft broom and clears away bridge floor dust, debris;If any greasy dirt, with nonionic fertilizer Soap powder aqueous cleaning is finally clean with water cleaning down and be completely dried;Works surface to protruding bridge floor also cleans dry Only;Spraying range of each cleaning scope more than subsequent bituminous epoxy binding material;Meanwhile, beyond avoiding being contacted with pave-load layer Position polluted, these positions all cover in advance;
2.2nd, tack coat spread:Spread fabric width and boundary line are divided, to ensure that distribution vehicle carries out spread by prescribed limit, binding material spills Spreading tube highly should ensure that no less than dual repeatedly spread quantity during cloth, and the grey face of appearance during spread is manually mended afterwards Spill, mending the amount of spilling should control in prescribed limit, after the completion of bituminous epoxy water-proof tack coat spread, job site should be kept to clean;
(3) bridge deck pavement construction;Gathered materials ratio according to the proportioning setting cold burden storehouse that gathers materials that Target Mixture Ratio determines, control is gathered materials Heating-up temperature is 130-140 DEG C, and from hot aggregate bin sampling sieve test, mineral aggregate composition are carried out:5-10mm coarse aggregates 24%, 0-5mm Fine aggregate 69%, breeze 7%, oilstone mass ratio:6.8%;
3.1st, compound is mixed and stirred:The temperature of bituminous epoxy mix should be maintained at set point of temperature between 105-110 DEG C, blending station behaviour Making personnel should keep a close eye on temperature variations, forbid significantly adjusting air door and throttle, it is to avoid temperature fluctuation is too big;
3.2nd, dry mixing:The each cold burden storehouse feeding speed determined during according to trial mix is heated to mineral aggregate temperature to dryer feeding 105-110 DEG C, it is heated after enter hot aggregate bin, in strict accordance with refinery operation scheduling determine each hot aggregate bin aggregate quality and ore deposit The quality of powder, input is mixed cylinder and carries out dry mixing, and the dry mixing time is the 5-20 seconds, then measures hot material temperature;This operation repeats 3-5 Time, until drop temperature is stable to mix and stir temperature 105-110 DEG C;
3.3rd, wet-mixing:Gathering materials of working good is heated into 105-110 DEG C, while bituminous epoxy is added by special adding set To mixing in cylinder, wet-mixing, 30-90 seconds wet-mixing time are carried out;Epoxy asphalt mixture is discharged into interim hot material bucket after the completion of mixing and stirring, Thermometric immediately, the drop temperature of compound should be controlled at 105-110 DEG C;Compound is mixed and stirred after temperature stabilization, you can formal discharging, Per car compound loading time is less than 10 minutes;
3.4th, compound transport:To prevent compound from adhering with material mover carriage, the position contacted with compound in all compartments applies Used as interleaving agent, haulage vehicle adds a cover canvas or cotton-wadded quilt to brush vegetable oil in transportation, to slow down the reduction of mixture temperature, Haulage time is less than 50 minutes;
3.5th, mixture laying:Epoxy asphalt mixture is paved using the bituminous pavement paving machine of regulation, should be protected in paving process The workability and surface uniformity of card compound, so that compacted depth meets requiring, it is to avoid gather materials isolation, and after paving Mix surface should be without coarse aggregate or fine aggregate hole, the surface that paves must not manually rake;
If special messenger calculates and control spreading speed, entered according to " the allowing discharge time scope " of feed capacity and each truck feeding list Row in time adjustment, to control not shut down, not overtime, makes every effort at the uniform velocity to pave for principle, and spreading speed general control is in 2~4m/ min;
Paving for compound is carried out according to the coefficient of loose laying that test section is obtained;A loose laying depth is surveyed per 10m in paving process, and Note road camber, adjusted if necessary, must smooth out, in the hope of not affecting the material position in flatness, and spiral distributor with slightly It is advisable higher than spiral distributor 2/3, it is to avoid isolation occurs in paved mixture;
3.6th, pave-load layer is rolled:Rolled using two kinds of " rubber tire-steel wheel-rubber tire-steel wheel " and " steel wheel-rubber tire-rubber tire-steel wheel " Combination, flatness situation, wheel pelmatogram situation after the completion of compound passage situation and final pressure in observation construction, record is rolled time Number and mixture temperature, determine the rational compaction assembly form in different layers position and respectively roll the number of rolling in stage, are to ensure pressure Actual effect fruit, cutting optimal is rolled using the order of " glue-steel-glue-steel ", and upper layer is entered using the order of " steel-glue-glue-steel " Row is rolled, if producing bubble in roller compaction process, is poked with sharp thing at once and is compacted again, for road roller is compacted not The local pave-load layer for arriving, cutting optimal uses road roller pressing using hand compaction or hand-held vibration rammer vibration compacting, upper layer It is real.
2. the method for paving of a kind of bituminous epoxy Steel Bridge Deck according to claim 1, it is characterised in that:It is described in step (3) carry out first pressing in after mixture laying at once, be just pressed in temperature drop and complete before to 75-80 DEG C, first pressing should be closelyed follow and paved Machine, number of machine passes is 4-8 time, and multiple pressure 4 times should be at once carried out after the completion of first pressing, after the completion of multiple pressure should final pressure 4 times at once, final pressure should Completed before mixture temperature drops to 50 DEG C.
3. the method for paving of a kind of bituminous epoxy Steel Bridge Deck according to claim 2, it is characterised in that:It is described in step (3) first pressing and final pressure are all after having pressed 3 times, with infrared thermometry note surface temperature to be measured in, when surface temperature is unsatisfactory for wanting When asking, then internal temperature is surveyed with plug-in type thermometer, when internal temperature is unsatisfactory for requiring, in addition to twice of multiple pressure, to find out original Cause, adopts an effective measure, and prevents to occur again.
4. the method for paving of a kind of bituminous epoxy Steel Bridge Deck according to claim 2, it is characterised in that:It is described in step (3) towards paver, from low to high, successively continuous uniform is rolled road roller driving wheel when rolling in, and the adjacent band that rolls overlaps 1/3 Wheel is wide, does not allow road roller to turn in the scope of operation, reverse end for end, and road roller is started, stops the jogging that must slow down, and is forbidden emergency brake Braking.
5. the method for paving of a kind of bituminous epoxy Steel Bridge Deck according to claim 2, it is characterised in that:It is described in step (3) distinguishing mark is arranged to first pressing, multiple pressure, final pressure paragraph in, is easy to driver to recognize, to rolling order, road roller combination, grinding Pressing pass, rolling speed and roll temperature should set special hilllock management and check, record, and firmly prevent surface layer leakage and press, mixture laying Afterwards, road roller is immediately rolled, to shorten rolling operation segment length, but not produce passage, shattered crack as principle.
6. the method for paving of a kind of bituminous epoxy Steel Bridge Deck according to claim 1, it is characterised in that:It is described in step In 3.5 in Mechanical Spreading, manually must not repair repeatedly, but when occurring, section is undesirable, locally lack material, local mixing When the obvious isolation of material, the obvious out-of-flatness in surface, dead material problem, conscientiously adjust under construction technical staff specific guidance, locally change Material, carefully repairs, and with compound drop-over is spread, does not stay trace and difference.
7. the method for paving of a kind of bituminous epoxy Steel Bridge Deck according to claim 1, it is characterised in that:It is described in step In 3.5 in paving process by special messenger to spiral distributor and hopper in " dead material " clear up, produce in paving process Waste material, " dead material " should be concentrated and be placed in small handcart, then clean out job site, if meeting rain suddenly in paving, be stopped immediately Construction, and the compound of non-compaction moulding is removed, non-paved mixture must be discarded all.
8. the method for paving of a kind of bituminous epoxy Steel Bridge Deck according to claim 1, it is characterised in that:It is described in step (3) in when paving with first pressing observe and record compound workability, surface uniformity, whether there is after first pressing wheel pelmatogram situation, And temperature when recording construction.
CN201611251017.XA 2016-12-29 2016-12-29 Pavement method of steel bridge deck made from epoxy asphalt Pending CN106638295A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201611251017.XA CN106638295A (en) 2016-12-29 2016-12-29 Pavement method of steel bridge deck made from epoxy asphalt

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201611251017.XA CN106638295A (en) 2016-12-29 2016-12-29 Pavement method of steel bridge deck made from epoxy asphalt

Publications (1)

Publication Number Publication Date
CN106638295A true CN106638295A (en) 2017-05-10

Family

ID=58836725

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201611251017.XA Pending CN106638295A (en) 2016-12-29 2016-12-29 Pavement method of steel bridge deck made from epoxy asphalt

Country Status (1)

Country Link
CN (1) CN106638295A (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107815965A (en) * 2017-10-25 2018-03-20 南京林业大学 A kind of bridge deck pavement structure with reinforced structure
CN108151898A (en) * 2018-01-05 2018-06-12 重庆大学 A kind of steel box girder bridge simulation temperature measurement device
CN112482250A (en) * 2020-11-24 2021-03-12 江苏致信桥梁检测与维修加固有限公司 Bridge crack repairing method
CN114016430A (en) * 2021-12-21 2022-02-08 中建六局水利水电建设集团有限公司 Asphalt concrete bridge deck pavement method
CN117569141A (en) * 2023-10-27 2024-02-20 保利长大工程有限公司 Construction process for paving FAC-13 on epoxy asphalt wearing layer

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20090125873A (en) * 2008-06-03 2009-12-08 주식회사 유진플러스건설 Bottom of bridged rainge spatial-temporal methods of bridge
CN103669207A (en) * 2013-11-26 2014-03-26 交通运输部公路科学研究所 Prefabricated asphalt concrete steel bridge deck pavement structure and method
CN104652215A (en) * 2015-01-25 2015-05-27 上海市政工程设计研究总院(集团)有限公司 Pavement method for steel bridge deck pavement structure EES in cold high-latitude areas
CN105113420A (en) * 2015-09-16 2015-12-02 宁波路宝科技实业集团有限公司 Prefabricated reinforced concrete simply-supported girder bridge deck pavement and maintenance structure and construction method
CN205557322U (en) * 2016-04-07 2016-09-07 中铁城建集团南昌建设有限公司 Contains steel bridge face complex of putting steel sheet to one side structure of mating formation

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20090125873A (en) * 2008-06-03 2009-12-08 주식회사 유진플러스건설 Bottom of bridged rainge spatial-temporal methods of bridge
CN103669207A (en) * 2013-11-26 2014-03-26 交通运输部公路科学研究所 Prefabricated asphalt concrete steel bridge deck pavement structure and method
CN104652215A (en) * 2015-01-25 2015-05-27 上海市政工程设计研究总院(集团)有限公司 Pavement method for steel bridge deck pavement structure EES in cold high-latitude areas
CN105113420A (en) * 2015-09-16 2015-12-02 宁波路宝科技实业集团有限公司 Prefabricated reinforced concrete simply-supported girder bridge deck pavement and maintenance structure and construction method
CN205557322U (en) * 2016-04-07 2016-09-07 中铁城建集团南昌建设有限公司 Contains steel bridge face complex of putting steel sheet to one side structure of mating formation

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
SEX81072: "《百度文库》", 14 November 2016 *

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107815965A (en) * 2017-10-25 2018-03-20 南京林业大学 A kind of bridge deck pavement structure with reinforced structure
CN108151898A (en) * 2018-01-05 2018-06-12 重庆大学 A kind of steel box girder bridge simulation temperature measurement device
CN112482250A (en) * 2020-11-24 2021-03-12 江苏致信桥梁检测与维修加固有限公司 Bridge crack repairing method
CN114016430A (en) * 2021-12-21 2022-02-08 中建六局水利水电建设集团有限公司 Asphalt concrete bridge deck pavement method
CN114016430B (en) * 2021-12-21 2023-08-08 中建六局水利水电建设集团有限公司 Asphalt concrete bridge deck pavement method
CN117569141A (en) * 2023-10-27 2024-02-20 保利长大工程有限公司 Construction process for paving FAC-13 on epoxy asphalt wearing layer

Similar Documents

Publication Publication Date Title
CN106638295A (en) Pavement method of steel bridge deck made from epoxy asphalt
CN105350421B (en) A kind of thin overlay construction method suitable for road surface medium-capital overhauling and preventive maintenance
CN104762862B (en) SMA asphaltic road-mix surface course construction methods
CN102071613B (en) Asphalt-treated permeable-base (ATB) construction process
CN102154967B (en) Construction technology of asphalt concrete pavements of long and large longitudinal slopes in mountainous areas, ultra-high road sections and bridge floors
CN105970761B (en) Primary mat formation formula heavy traffic asphalt pavement structure and construction method
CN108221560A (en) The construction technology on rubber powder modified asphalt road surface
CN110258236A (en) A kind of high-performance steel slag road surface and its construction method
CN103953181B (en) Cement flooring breakage method for repairing and constructing
CN101270567A (en) Construction method for high-dosage vinyl benzene-butadiene-vinyl benzene modified asphalt bridge deck water-proof tack coat
CN110409251A (en) A kind of dewatering and noise reduction pavement construction method
CN105176116A (en) Cold mixing self-emulsifying retinasphal material, preparation method and purpose of cold mixing self-emulsifying retinasphal material
CN103924495A (en) Small and medium-sized steel bridge deck pavement system and implementation method
CN215593676U (en) Large-span steel bridge deck pavement structure
CN101481901A (en) Pouring type asphalt concrete construction method for central strip
CN107386111B (en) Composite high-modulus asphalt concrete bridge deck structure and setting method
CN103233405B (en) Old-new bituminous pavement binder course and application thereof
CN108729321A (en) A kind of prefabricated Orthotropic steel plate paving structure and its method for paving
CN102635047B (en) Large-span bridge deck composite structure layer construction technology
CN104652215B (en) A kind of method for paving of high and cold high latitude area bridge deck pavement structure EES
CN102154968B (en) PR-PLASTS blended concrete construction technology
CN105803937B (en) A kind of AC and epoxy construction layer clad steel bridge floor pavement construction method
CN110453570A (en) A kind of urban road water conservation temperature reduction construction of compound road surface method
CN207314073U (en) A kind of fiber asphalt concrete road surface
CN114016430A (en) Asphalt concrete bridge deck pavement method

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20170510