CN106624292A - Welding process for joint cover plates of blocks and modular plants - Google Patents

Welding process for joint cover plates of blocks and modular plants Download PDF

Info

Publication number
CN106624292A
CN106624292A CN201611049115.5A CN201611049115A CN106624292A CN 106624292 A CN106624292 A CN 106624292A CN 201611049115 A CN201611049115 A CN 201611049115A CN 106624292 A CN106624292 A CN 106624292A
Authority
CN
China
Prior art keywords
welding
cover plates
node
joint
lower cover
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201611049115.5A
Other languages
Chinese (zh)
Other versions
CN106624292B (en
Inventor
李林
张耀
李志强
苏子峰
李明
于浩
李金来
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China National Offshore Oil Corp CNOOC
Offshore Oil Engineering Co Ltd
Offshore Oil Engineering Qingdao Co Ltd
Original Assignee
China National Offshore Oil Corp CNOOC
Offshore Oil Engineering Co Ltd
Offshore Oil Engineering Qingdao Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China National Offshore Oil Corp CNOOC, Offshore Oil Engineering Co Ltd, Offshore Oil Engineering Qingdao Co Ltd filed Critical China National Offshore Oil Corp CNOOC
Priority to CN201611049115.5A priority Critical patent/CN106624292B/en
Publication of CN106624292A publication Critical patent/CN106624292A/en
Application granted granted Critical
Publication of CN106624292B publication Critical patent/CN106624292B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B23MACHINE TOOLS; METAL-WORKING NOT OTHERWISE PROVIDED FOR
    • B23KSOLDERING OR UNSOLDERING; WELDING; CLADDING OR PLATING BY SOLDERING OR WELDING; CUTTING BY APPLYING HEAT LOCALLY, e.g. FLAME CUTTING; WORKING BY LASER BEAM
    • B23K9/00Arc welding or cutting
    • B23K9/18Submerged-arc welding
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B23MACHINE TOOLS; METAL-WORKING NOT OTHERWISE PROVIDED FOR
    • B23KSOLDERING OR UNSOLDERING; WELDING; CLADDING OR PLATING BY SOLDERING OR WELDING; CUTTING BY APPLYING HEAT LOCALLY, e.g. FLAME CUTTING; WORKING BY LASER BEAM
    • B23K9/00Arc welding or cutting
    • B23K9/235Preliminary treatment

Landscapes

  • Engineering & Computer Science (AREA)
  • Physics & Mathematics (AREA)
  • Plasma & Fusion (AREA)
  • Mechanical Engineering (AREA)
  • Arc Welding In General (AREA)

Abstract

A welding process for joint cover plates of blocks and modular plants comprises the following steps: I, rolling single-joint pipes in joints, and performing double-side welding on longitudinal seam X grooves; II, pairing upper joint cover plates and lower joint cover plates at the two ends of the single-joint pipes; III, centering and aligning the head ends and the tail ends of the upper joint cover plates and the lower joint cover plates of the single-joint pipes, and fixing; IV, welding the upper cover plate and the lower cover plate, which are paired in the middle, with supporting pipe sections, and hoisting and placing the upper cover plate and the lower cover plate at the upper edge of a tire, then starting up the tire, and welding the upper cover plate and the lower cover plate with single V grooves of the single-joint pipes; V, repeating the step IV, adjusting the stretching and contracting length of a cross arm of a welder, and welding the rest upper cover plates and lower cover plates with the single V grooves of the single-joint pipes; and VI, cutting off and polishing the supporting pipe sections and temporary fixing rib plates, performing joint separation on the single-joint pipes, and conducting processing inspection submission. According to the welding process, automatic rotation is realized, the joints are butted end to end, and mechanical welding is achieved; and besides, the welding quality, the welding speed and the welding security are greatly improved.

Description

The welding procedure of chunk and module chemical plant node cover plate
Technical field
It is the present invention relates to welding procedure more particularly to a kind of for chunk and the Welder of module chemical plant node cover plate Skill.Belong to Offshore Engineering field.
Background technology
The prefabricated order in the maximization and diversity with ocean engineering steel construction project, deep water chunk and module chemical plant With require also more and more higher.Exist when being welded in welding node cover plate due to existing arc welding and carbon dioxide medicine core gas shield Problems with:
1) because welding bead shaping is bad, qualification rate is relatively low;
2) because unit interval deposition rate is little, welding efficiency is relatively low;
3) larger due to welding loading, cover plate post welding distortion is larger, and the hot straightening workload of postwelding is than larger.
4) due to, workman long-time hand-held electrode holder very high to craftsmanship's level requirement, the sternnesses such as flue dust, high temperature are faced with Test, construction environment is more severe, and security is not high.
The content of the invention
Present invention is primarily targeted at overcoming the disadvantages mentioned above that prior art is present, and provide a kind of chunk and modularization The welding procedure of factory's node cover plate, it can not only be rotated automatically, and node head and the tail docking is got up, and be solved by manually Qualification rate is relatively low caused by welding institute, the hot straightening workload of postwelding than it is larger the problems such as, realize automatic weld;And, greatly The security of welding quality, speed of welding and welding is improve greatly, operating environment is improved, and improves security.
The purpose of the present invention is realized by technical scheme below:
A kind of welding procedure of chunk and module chemical plant node cover plate, it is characterised in that:Using following steps:
The first step:Single-unit pipe in node is rolled, and two-sided welding is carried out to longitudinal joint X-type groove;
Second step:Node upper and lower cover plates is grouping at single-unit pipe two ends, then, to node upper and lower cover plates and single-unit pipe Single double V-groove carries out interruption positioning;
3rd step:The node upper and lower cover plates head and the tail of single-unit pipe are carried out into centering, and it is fixed;
4th step:The upper and lower cover plates center welding at node head and the tail two ends is supported into pipeline section, and upper and lower cover plates is lifted Positioner top is placed on, then, starts positioner, welding upper and lower cover plates and single-unit pipe list double V-groove;
5th step:Repeat the 4th step, adjust the flexible length of the transverse arm of welding machine, weld remaining upper and lower cover plates and single-unit pipe Single double V-groove;
6th step:Pipeline section, interim fixed gusset excision, polishing will be supported, single-unit pipe node is separated, and carries out process inspection declaration Operation.
In the first step, single-unit pipe upper and lower ends hold in advance V45 ° of groove of one side successfully.
The welding is carried out using submerged arc welding machine.
Beneficial effects of the present invention:Due to adopting above-mentioned technical proposal, it can not only be rotated the present invention automatically, by node Head and the tail docking is got up, and realizes automatic weld;And, the security of welding quality, speed of welding and welding is substantially increased, Speed of welding is faster than prior art 2-3 times, improves operating environment, improves security.
Description of the drawings
Fig. 1 is the schematic front view of two classes node of the invention.
Fig. 2 is the upper and lower ring groove type schematic diagram of single-unit pipe of the present invention.
Fig. 3 is of the present invention group to, fixation welding cap plate schematic side view.
Fig. 4 is that single-unit pipe node head and the tail cover plate of the present invention fixes concatenation schematic front view.
Fig. 5 is that cover plate two sections of temporary support pipeline sections of center welding at single-unit pipe head and the tail two ends of the present invention install signal Figure.
Fig. 6 is the present invention using positioner and direct current submerged arc welding machine welding schematic diagram.
Fig. 7 is that postwelding node of the present invention is separated, complete schematic diagram.
Major Symbol explanation in figure:
1. single-unit pipe, 2. node upper and lower cover plates, 3. interim fixed gusset, 4. temporary support pipeline section, 5. adjustment height turn Tire, 6. direct current submerged arc welding machine.
Specific embodiment
The present invention adopts following steps:
The first step:Such as Fig. 1, shown in Fig. 2, the single-unit pipe 1 in node is rolled, and using submerged arc welding machine to longitudinal joint X Type groove carries out two-sided welding;
Above-mentioned single-unit pipe upper and lower ends hold in advance V45 ° of groove of one side successfully.
Second step:As shown in figure 3, be grouping to node upper and lower cover plates 2 at single-unit pipe two ends, then, using handling weldering Rifle, to node upper and lower cover plates 2 and single-unit pipe list double V-groove interruption positioning welding is carried out;
3rd step:As shown in figure 4, the head and the tail of node upper and lower cover plates 2 of single-unit pipe 1 are carried out into centering, and using interim Gusset is welded and fixed;
4th step:As shown in Figure 5, Figure 6, the upper and lower cover plates 2 at node head and the tail two ends is hit exactly into two sections of support tubes of welding Section, and cover plate lifting is placed on into positioner top, then, start positioner, using direct current submerged arc welding machine welded cover plate and single-unit pipe Single double V-groove, then carry out processing the operations such as inspection declaration;
5th step:Repeat the 4th step, adjust the flexible length of the transverse arm of direct current submerged arc welding machine, weld remaining upper and lower cover plates 2 with single-unit pipe list double V-groove;If necessary, can 2 submerged arc welding machine balanced weldings;
6th step:As shown in fig. 7, pipeline section, interim fixed gusset excision, polishing, single-unit pipe node will be supported to separate, carry out Process the operations such as inspection declaration.
Above-mentioned positioner is existing mature technology equipment, and the technology of not specified (NS) is prior art, therefore is repeated no more.
The above, is only presently preferred embodiments of the present invention, and any pro forma restriction is not made to the present invention, all It is above example is made any simple modification, equivalent variations and modification according to the technical spirit of the present invention, still falls within In the range of technical solution of the present invention.

Claims (3)

1. the welding procedure of a kind of chunk and module chemical plant node cover plate, it is characterised in that:Using following steps:
The first step:Single-unit pipe in node is rolled, and two-sided welding is carried out to longitudinal joint X-type groove;
Second step:Node upper and lower cover plates is grouping at single-unit pipe two ends, then, to node upper and lower cover plates and single-unit pipe list V Type groove carries out interruption positioning;
3rd step:The node upper and lower cover plates head and the tail of single-unit pipe are carried out into centering, and it is fixed;
4th step:The upper and lower cover plates center welding at node head and the tail two ends is supported into pipeline section, and upper and lower cover plates lifting is placed In positioner top, then, start positioner, welding upper and lower cover plates and single-unit pipe list double V-groove;
5th step:Repeat the 4th step, adjust the flexible length of the transverse arm of welding machine, weld remaining upper and lower cover plates and single-unit pipe list V Type groove;
6th step:Pipeline section, interim fixed gusset excision, polishing will be supported, single-unit pipe node is separated, and carries out processing inspection declaration work Sequence.
2. the welding procedure of chunk according to claim 1 and module chemical plant node cover plate, it is characterised in that:Described In one step, single-unit pipe upper and lower ends hold in advance V45 ° of groove of one side successfully.
3. the welding procedure of chunk according to claim 1 and module chemical plant node cover plate, it is characterised in that:The weldering Connect is carried out using submerged arc welding machine.
CN201611049115.5A 2016-11-25 2016-11-25 The welding procedure of chunking and module chemical plant node cover board Active CN106624292B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201611049115.5A CN106624292B (en) 2016-11-25 2016-11-25 The welding procedure of chunking and module chemical plant node cover board

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201611049115.5A CN106624292B (en) 2016-11-25 2016-11-25 The welding procedure of chunking and module chemical plant node cover board

Publications (2)

Publication Number Publication Date
CN106624292A true CN106624292A (en) 2017-05-10
CN106624292B CN106624292B (en) 2018-11-27

Family

ID=58811847

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201611049115.5A Active CN106624292B (en) 2016-11-25 2016-11-25 The welding procedure of chunking and module chemical plant node cover board

Country Status (1)

Country Link
CN (1) CN106624292B (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110814490A (en) * 2019-10-19 2020-02-21 秦河新材股份有限公司 Butt welding device for cold-rolled steel bar

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH08243754A (en) * 1995-03-08 1996-09-24 Nippon Steel Corp Inner face welding method of clad steel tube
JP2003136130A (en) * 2001-11-01 2003-05-14 Nippon Steel Corp Method for manufacturing inner and outer surface submerged arc welded steel pipe excellent in toughness characteristics of seam welded portion
US20040234715A1 (en) * 2003-05-20 2004-11-25 John Gandy Method of manufacturing stainless steel pipe for use in piping systems
CN101837387A (en) * 2009-03-16 2010-09-22 王澄 Automated manufacturing method and production line design of large-scale steel tube
CN102489947A (en) * 2011-11-30 2012-06-13 攀钢集团工程技术有限公司 Bottom chord tube manufacturing process of girder of steel tube concrete truss beam bridge
CN104625648A (en) * 2015-01-19 2015-05-20 太原重工股份有限公司 Technological method for machining square and rectangular pipes
CN105643048A (en) * 2016-03-31 2016-06-08 合肥紫金钢管有限公司 Manufacturing technology for long large-diameter LSAW (longitudinal submerged arc welding) pile pipe for ocean platform
CN205465036U (en) * 2016-01-08 2016-08-17 宝钢集团新疆八一钢铁有限公司 Welded structure that submerged arc welding steel pipe sealed

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH08243754A (en) * 1995-03-08 1996-09-24 Nippon Steel Corp Inner face welding method of clad steel tube
JP2003136130A (en) * 2001-11-01 2003-05-14 Nippon Steel Corp Method for manufacturing inner and outer surface submerged arc welded steel pipe excellent in toughness characteristics of seam welded portion
US20040234715A1 (en) * 2003-05-20 2004-11-25 John Gandy Method of manufacturing stainless steel pipe for use in piping systems
CN101837387A (en) * 2009-03-16 2010-09-22 王澄 Automated manufacturing method and production line design of large-scale steel tube
CN102489947A (en) * 2011-11-30 2012-06-13 攀钢集团工程技术有限公司 Bottom chord tube manufacturing process of girder of steel tube concrete truss beam bridge
CN104625648A (en) * 2015-01-19 2015-05-20 太原重工股份有限公司 Technological method for machining square and rectangular pipes
CN205465036U (en) * 2016-01-08 2016-08-17 宝钢集团新疆八一钢铁有限公司 Welded structure that submerged arc welding steel pipe sealed
CN105643048A (en) * 2016-03-31 2016-06-08 合肥紫金钢管有限公司 Manufacturing technology for long large-diameter LSAW (longitudinal submerged arc welding) pile pipe for ocean platform

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110814490A (en) * 2019-10-19 2020-02-21 秦河新材股份有限公司 Butt welding device for cold-rolled steel bar

Also Published As

Publication number Publication date
CN106624292B (en) 2018-11-27

Similar Documents

Publication Publication Date Title
CN204997233U (en) Assembly welding equipment is restrainted to steel pipe
CN217316736U (en) Gas pipeline welding interfacing apparatus
CN104785909A (en) Separator head girth welding work station
CN110576939A (en) Construction method for large conical cylinder segments
CN106624292A (en) Welding process for joint cover plates of blocks and modular plants
CN107350712B (en) The assembly method and double-joint pipe of Two bors d's oeuveres submerged-arc welded (SAW) pipe
CN103317237B (en) Laser welding method of nuclear fuel storage framework bush square tube and small base plate
CN104785890A (en) Steam-injection boiler unit convection section box body welding work station and machining technology thereof
CN202861634U (en) Liner welding production line for water heater
CN105945507A (en) Pipeline fixing welding method in building construction
CN202639739U (en) Hydraulic rounding assembling machine for shell rings
CN110328437A (en) A kind of processing unit (plant) and its processing method of combined pipe
CN103481008A (en) Deep-hole repair welding technology
CN110340555B (en) Welding construction method for linear multi-cavity steel plate and steel bar angle steel truss combined component
CN103157917B (en) Water wall base cone assembly welding and heat treatment device and method
CN204818385U (en) A frock that is used for shield to construct downhand welding of casing body
CN103143873B (en) Full-symmetrical cylindrical membrane wall assembly tooling and assembly method
CN103071886B (en) Method for welding tank shell rings
CN211564986U (en) Pipe welding radial positioning frock
CN109202224B (en) K-TIG-based double-sided double-arc welding system and method for wide-caliber pipeline
KR102038805B1 (en) Tube pannel welding apparatus for manufacturing of water-tube boiler
CN211465328U (en) Water wall pipe simulation welding frame
CN211757887U (en) Intelligent control automatic feeding circular tube arc punching machine
CN104772551B (en) Rubber film sealing coal gas cabinet bottom plate or top plate welding method
CN114609360A (en) Nondestructive testing equipment and method for metal weld defects

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
CP01 Change in the name or title of a patent holder

Address after: 100010 Chaoyangmen North Street, Dongcheng District, Dongcheng District, Beijing

Co-patentee after: Offshore Oil Engineering (Qingdao) Co., Ltd.

Patentee after: China Offshore Oil Group Co., Ltd.

Co-patentee after: Offshore Oil Engineering Co., Ltd.

Address before: 100010 Chaoyangmen North Street, Dongcheng District, Dongcheng District, Beijing

Co-patentee before: Offshore Oil Engineering (Qingdao) Co., Ltd.

Patentee before: China National Offshore Oil Corporation

Co-patentee before: Offshore Oil Engineering Co., Ltd.

CP01 Change in the name or title of a patent holder