CN106597943A CN201611180950.2A CN201611180950A CN106597943A CN 106597943 A CN106597943 A CN 106597943A CN 201611180950 A CN201611180950 A CN 201611180950A CN 106597943 A CN106597943 A CN 106597943A
Authority
CN
China
Prior art keywords
oil
mft
fast valve
valve
fuel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201611180950.2A
Other languages
Chinese (zh)
Inventor
邱树良
王学同
王真
宋瑞福
陶蕊
张岩
祝宝营
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Huadian Electric Power Research Institute Co Ltd
Original Assignee
Huadian Electric Power Research Institute Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Huadian Electric Power Research Institute Co Ltd filed Critical Huadian Electric Power Research Institute Co Ltd
Priority to CN201611180950.2A priority Critical patent/CN106597943A/en
Publication of CN106597943A publication Critical patent/CN106597943A/en
Pending legal-status Critical Current

Links

Classifications

    • GPHYSICS
    • G05CONTROLLING; REGULATING
    • G05BCONTROL OR REGULATING SYSTEMS IN GENERAL; FUNCTIONAL ELEMENTS OF SUCH SYSTEMS; MONITORING OR TESTING ARRANGEMENTS FOR SUCH SYSTEMS OR ELEMENTS
    • G05B19/00Programme-control systems
    • G05B19/02Programme-control systems electric
    • G05B19/04Programme control other than numerical control, i.e. in sequence controllers or logic controllers
    • G05B19/042Programme control other than numerical control, i.e. in sequence controllers or logic controllers using digital processors
    • G05B19/0426Programming the control sequence
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F23COMBUSTION APPARATUS; COMBUSTION PROCESSES
    • F23KFEEDING FUEL TO COMBUSTION APPARATUS
    • F23K5/00Feeding or distributing other fuel to combustion apparatus
    • F23K5/02Liquid fuel
    • F23K5/14Details thereof
    • F23K5/16Safety devices
    • GPHYSICS
    • G05CONTROLLING; REGULATING
    • G05BCONTROL OR REGULATING SYSTEMS IN GENERAL; FUNCTIONAL ELEMENTS OF SUCH SYSTEMS; MONITORING OR TESTING ARRANGEMENTS FOR SUCH SYSTEMS OR ELEMENTS
    • G05B2219/00Program-control systems
    • G05B2219/20Pc systems
    • G05B2219/23Pc programming
    • G05B2219/23076Pushbuttons to manually up or down control of motor also for entry of program
    • GPHYSICS
    • G05CONTROLLING; REGULATING
    • G05BCONTROL OR REGULATING SYSTEMS IN GENERAL; FUNCTIONAL ELEMENTS OF SUCH SYSTEMS; MONITORING OR TESTING ARRANGEMENTS FOR SUCH SYSTEMS OR ELEMENTS
    • G05B2219/00Program-control systems
    • G05B2219/20Pc systems
    • G05B2219/23Pc programming
    • G05B2219/23199Reference value, setpoint for regulator
    • GPHYSICS
    • G05CONTROLLING; REGULATING
    • G05BCONTROL OR REGULATING SYSTEMS IN GENERAL; FUNCTIONAL ELEMENTS OF SUCH SYSTEMS; MONITORING OR TESTING ARRANGEMENTS FOR SUCH SYSTEMS OR ELEMENTS
    • G05B2219/00Program-control systems
    • G05B2219/20Pc systems
    • G05B2219/23Pc programming
    • G05B2219/23289State logic control, finite state, tasks, machine, fsm
    • GPHYSICS
    • G05CONTROLLING; REGULATING
    • G05BCONTROL OR REGULATING SYSTEMS IN GENERAL; FUNCTIONAL ELEMENTS OF SUCH SYSTEMS; MONITORING OR TESTING ARRANGEMENTS FOR SUCH SYSTEMS OR ELEMENTS
    • G05B2219/00Program-control systems
    • G05B2219/20Pc systems
    • G05B2219/23Pc programming
    • G05B2219/23375Function switch, knob with piezo, strain gauge

Landscapes

  • Engineering & Computer Science (AREA)
  • Physics & Mathematics (AREA)
  • General Physics & Mathematics (AREA)
  • Automation & Control Theory (AREA)
  • Chemical & Material Sciences (AREA)
  • Combustion & Propulsion (AREA)
  • Mechanical Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Feeding And Controlling Fuel (AREA)

Abstract

The invention relates to a system and method capable of carrying out a fuel oil leakage test after the MFT of a boiler, and the system consists of a fuel oil leakage test performing button, a software channel module, a DO clamping piece, a hardware channel terminal, a control cable, an MFT tripping oil incoming fast valve loop, an oil incoming fast valve bypass loop, an MFT tripping oil returning fast valve loop, an oil returning fast valve bypass loop. The MFT tripping oil incoming fast valve loop consists of a power supply module, an oil incoming fast valve, an oil incoming fast valve DCS control instruction relay, and an MFT tripping oil incoming fast valve relay. The MFT tripping oil returning fast valve loop consists of a power supply module, an oil returning fast valve, an oil returning fast valve DCS control instruction relay, and an MFT tripping oil returning fast valve relay. After the above technical scheme is employed, the system can achieve the cut off the locking, caused by tripping MFT of a main material of the boiler, of oil incoming fast valve and the oil returning fast valve, and successfully carries out the fuel oil leakage test during the MFT.

Description

The system and method for fuel leakage test can be carried out after boiler occurs MFT
Technical field
The present invention relates to a kind of power plant boiler occurs after MFT, the control of fuel leakage test can be carried out before furnace purge System processed.
Background technology
Boiler occurs after MFT, to carry out furnace purge before ignition of the boiler, and establishing criteria DL/T1091-2008《Firepower Power plant boiler Furnace Safeguard Supervisory System technical regulation》5.1.4.2 in, fuel leakage test is distinctly claimed, oil leakage Success of the test is one of furnace purge condition, in the condition that should be met during same 5.2.4 furnace purges, it is desirable to oily leak test into Work(, it is therefore an objective to which the fuel oil that will likely can be leaked in burner hearth in furnace purge blows away, it is ensured that detonation does not occur during igniting.
The valve that action is needed in fuel leakage process of the test is oil-feed fast valve and oil return fast valve, the soft logic of DCS Loop and the hard trip(ping) circuits of MFT are controlled to the normally closed node control loop of unicoil to the two valves, in existing system, After boiler occurs MFT, oil-feed fast valve and oil return fast valve are limited in closing shape by MFT by the out code of rest-set flip-flop State, in this case, oil-feed fast valve and oil return fast valve loop are uncharged, even if DCS sends OPEN, not In the case of carrying out furnace purge i.e. MFT signals not occurring involution, oil-feed fast valve and oil return fast valve can not be operated, so The starting time of boiler will significantly be postponed, the quick startup of Generator Set is affected.
The content of the invention
The present invention is directed to the deficiencies in the prior art, it is proposed that a kind of after boiler occurs MFT, furnace purge advance The system of row oil leak test, the system carries out button, software channel module, DO fasteners, hardware corridor by fuel leakage test Terminal, control cable, MFT tripping operations oil-feed fast valve loop, oil-feed fast valve bypass loop, MFT tripping operation oil return fast valves loop, Oil return fast valve bypass loop is constituted, and described fuel leakage test carries out button, and in parallel mode is connected with two softwares and leads to Road module, described two software channels are connected with DO fasteners, and two hardware corridor terminals are provided with described DO fasteners, described Two hardware corridor terminals on DO fasteners are bypassed respectively by control cable with oil-feed fast valve bypass loop, oil return fast valve Loop is attached.Described MFT tripping operation oil-feed fast valve loops are by supply module, oil-feed fast valve, oil-feed fast valve DCS controls Commands relays processed, MFT trip oil-feed fast valve relay group into the oil-feed fast valve bypass loop trips with the MFT Oil-feed quick closing valve valve relay is in parallel;Described MFT tripping operations oil return fast valve loop is fast by supply module, oil return fast valve, oil return Close valve DCS control instructions relay and MFT and trip oil return fast valve relay group into, the oil return fast valve bypass loop and institute State MFT tripping operation oil return quick closing valve valve relays in parallel;Hard channel terminals are located in DO fasteners, oil-feed fast valve bypass loop, oil return Fast valve bypass loop is connected respectively by cable with the hard channel terminals on DO fasteners.After using the program, can realize cutting Except the oil-feed fast valve and oil return quick closing valve valve blocking that cause due to boiler main fuel trip MFT, smoothly realize being fired in MFT Oily leak test.
Further, logic during fuel leakage test is carried out is preset in described oil-feed fast valve.
Further, logic during fuel leakage test is carried out is preset in described oil return fast valve.
Preferably:Oil-feed fast valve DCS control instruction relays, oil return fast valve DCS control instruction relays are big Capacity DC 220V relays.
Further, oil-feed fast valve DCS control instruction relays, the board of oil return fast valve DCS control instruction relays It is arranged apart, be so conducive to the safe and stable operation of system.
Increase logic during fuel leakage test is carried out in oil-feed fast valve control logic, it is other when logical signal is " 1 " Road MFT action signals, make the valve after MFT generations, force OFF signal to be cancelled, it is allowed to which ON signal is enabled, valve energy automatic switch;
Increase logic during fuel leakage test is carried out in oil return fast valve control logic, it is other when logical signal is " 1 " Road MFT action signals, make the valve after MFT generations, force OFF signal to be cancelled, it is allowed to which ON signal is enabled, valve energy automatic switch;
Two DO passages defined in DCS logics, and be sent to respectively by DO fasteners and control cable 1 and control cable 2 In the hard control loop of oil-feed fast valve and oil return fast valve;
Increase in oil-feed fast valve control loop, oil return fast valve control loop and MFT relay cabinet relay module MFT tripping operation oil-feed fast valve bypass loops and MFT tripping operation oil return fast valve bypass loops;
On the basis of using the program, present invention also offers one kind is carried out before boiler occurs MFT rear hearths purging The method of fuel leakage test, comprises the following steps:
S1:After boiler occurs MFT, before furnace purge, fuel leakage test is carried out, fuel leakage test is mainly to pot The effusion meter used on oil-piping, valve, pipeline and the pressure test of some subsidiary pressure-containing members of stove, its main purpose is inspection Test the load performance and tightness of boiler oil system, it is ensured that the reliably working of oil circuit.
S2:After fuel leakage test starts, oil return fast valve is first shut off, fuel oil is female to fuel oil under the suppressing of oil feed pump Pipe carry out it is oil-filled, Oil feeding process be 60 seconds, if after 60s fuel oil main pipe " pressure satisfaction " is (i.e.:Pressure fires higher than unit design Oily leak test definite value) signal presence, then the oil-filled success of fuel oil main pipe;If within 60 second time, fuel oil main pipe cannot be by pressure The claimed range in " pressure satisfaction " is controlled, then illustrates that a certain link in fuel oil main pipe, oily angle valve or oil return fast valve is present Significant leakage, the interface of leak test then shows " oil-filled failure ";
S3:If the oil-filled success of fuel oil main pipe, is automatically switched off fuel oil fast valve;When the oil-filled success of fuel oil main pipe, fuel oil quick closing valve After valve is closed, now oil-feed fast valve and oil return fast valve Close All, fuel oil before is in air-tight state, if at 180 seconds It is interior, if " pressure satisfaction " signal in fuel oil main pipe is present always, illustrate that oily angle valve is not leaked, the leakage examination of oily angle valve Test successfully;If " pressure satisfaction " signal disappeared in 180 seconds in fuel oil main pipe, illustrate that oily angle valve has leakage, then fuel leakage Test failure;
S4:Fuel leakage test carries out middle signal and sends to MFT tripping operation bypass loops, normal opened contact closure, at this moment passes through Fuel leakage tests program control Automatic Program and sends DCS control instructions 1 and instruction 2, and fuel leakage test can be before furnace purge Carry out.
The present invention for realize before furnace purge is completed, carry out fuel leakage test when, can with dexterous actions the two Valve, after fuel leakage off-test, this two valves of block action before MFT involutions, realizing can be with before furnace purge Carry out fuel leakage test.
Beneficial effects of the present invention are:1st, solve before boiler occurs MFT rear hearths purging, do not remove MFT tripping operations hard Wiring cannot carry out a difficult problem for fuel leakage test, realize fuel leakage success of the test as the condition of furnace purge.2、 Investment cost is low, easily operation, one of ordinary skill in the art, original system can be carried out by the reading present invention excellent Change transformation.
Description of the drawings
In order to be illustrated more clearly that the present invention, embodiment will be described below needed for the accompanying drawing to be used simply be situated between Continue.It should be evident that drawings in the following description are only the description to embodiments of the invention, for ordinary skill For personnel, without having to pay creative labor, can be carrying out simple deformation or title according to technical scheme Change, or take customary means, it is also possible to realize goal of the invention.
Fig. 1 fuel leakages test bypass MFT circuit diagrams.
Fig. 2 oil-feed fast valve DCS logic control charts;
Fig. 3 oil return fast valve DCS logic control charts;
" MFT " being related in application documents refers to main fuel trip for Main Fuel Trip, and " DO " is Digital Output refers to digital output, and " DCS " refers to scattered control system for Distributed Control System.
Label declaration:The test of 1- fuel leakages carries out button, 2- software channel modules, 3-DO fasteners, 4- hardware corridors end Son, 5- control cables, 6- oil-feed fast valves, 7- oil-feed fast valve bypass loops, 8- oil-feed fast valve DCS control instruction relays Device, 9-MFT tripping operation oil-feed fast valves loop, 10- oil return fast valves, 11- oil return fast valve DCS control instruction relays, 12- is returned Oily fast valve bypass loop, 13-MFT tripping operation oil return fast valves loop, 14-MFT tripping operation oil-feed quick closing valve valve relays, 15-MFT is jumped Lock oil return quick closing valve valve relay, 16- oil-feed fast valve supply modules, 17- oil return fast valve supply modules
Specific embodiment
Embodiments of the invention are elaborated below, the present embodiment carries out reality under premised on the technical program Apply, give detailed embodiment and specific operating process, but protection scope of the present invention is not limited to following embodiments.
Embodiment 1
As shown in figure 1, a kind of carry out the system of fuel leakage test after boiler occurs MFT, by fuel leakage test into Row button 1, software channel module 2, DO fasteners 3, hardware corridor terminal 4, control cable 5, MFT tripping operation oil-feed fast valve loop 9, Oil-feed fast valve bypass loop 7, MFT tripping operation oil return fast valve loop 13, oil return fast valve bypass loop 12 constitutes, described combustion Oily leak test carries out button 1, and in parallel mode is connected with two software channel modules 2, described two software channels 2 and DO Fastener 3 is connected, and two hardware corridor terminals 4 is provided with described DO fasteners 3, two hardware corridors on the DO fasteners 3 Terminal 4 is attached respectively by control cable 5 with oil-feed fast valve bypass loop 7, oil return fast valve bypass loop 12.It is described MFT tripping operations oil-feed fast valve loop 9 controlled by oil-feed fast valve supply module 16, oil-feed fast valve 6, oil-feed fast valve DCS Commands relays 8, MFT tripping operation oil-feed quick closing valve valve relay 14 is constituted, and the oil-feed fast valve bypass loop 7 is jumped with the MFT Lock oil-feed quick closing valve valve relay 14 is in parallel;Described MFT tripping operation oil return fast valves loop 13 by oil return fast valve supply module 17, Oil return fast valve 10, oil return fast valve DCS control instructions relay 11 and MFT tripping operation oil return quick closing valve valve relay 15 is constituted, institute State oil return fast valve bypass loop in parallel with MFT tripping operation oil return quick closing valve valve relays 15;Hard channel terminals are located at DO fasteners Interior, oil-feed fast valve bypass loop, oil return fast valve bypass loop are connected respectively by the hard channel terminals on cable and DO fasteners Connect.Within the system, oil-feed fast valve DCS control instruction relays, oil return fast valve DCS control instructions relay are Large Copacity Direct current 220V relays, and board is arranged apart.
Removing locked signal carries out button 1 by the fuel leakage test in DCS logics, is sent to DCS software channel moulds In block 2, then software instruction is entered in DO fasteners 3, respectively by hardware corridor terminal 4, is jumped into MFT along control cable 5 In lock oil-feed fast valve bypass loop 7 and MFT tripping operation oil return fast valves bypass loop 12, when boiler occurs MFT main fuel trips When, the locking that MFT signals pass through MFT tripping operation oil-feed fast valves loop 9 and MFT tripping operation oil return fast valves loop 13, oil-feed quick closing valve Valve 6 and oil return fast valve 10 are akinesias.
After boiler occurs MFT, before furnace purge, fuel leakage test is carried out, fuel leakage test is mainly to boiler The effusion meter used on oil-piping, valve, pipeline and some subsidiary pressure-containing members pressure test, its main purpose be inspection The load performance and tightness of boiler oil system, it is ensured that the reliably working of oil circuit.When boiler occurs MFT, now to carry out Fuel leakage is tested, and DCS is sent after the instruction for starting fuel leakage test, logical by above-mentioned software and hardware with regard to removing locked signal Road, control cable are sent in MFT tripping operation oil-feed fast valves bypass loop 7 and MFT tripping operation oil return fast valves bypass loop 12, so The program that just can be tested according to set fuel leakage, by oil-feed fast valve DCS control instructions relay 8 and oil return fast valve DCS control instructions relay 11 opening and closing oil-feed fast valve 6 and oil return fast valve 10, so as to smoothly without the carrying out of locking Fuel leakage is tested.As shown in Fig. 2 increase logic during fuel leakage test is carried out in oil-feed fast valve control logic, when When logical signal is " 1 ", MFT action signals are bypassed, make the valve after MFT generations, force OFF signal to be cancelled, it is allowed to which ON signal makes Can, valve energy automatic switch;As shown in figure 3, increase logic during fuel leakage test is carried out in oil return fast valve control logic, When logical signal is " 1 ", MFT action signals are bypassed, make the valve after MFT generations, force OFF signal to be cancelled, it is allowed to ON signal Enable, valve energy automatic switch;Two DO passages defined in DCS logics, and by DO fasteners and control cable 1 and control electricity Cable 2 is sent to respectively in the hard control loop of oil-feed fast valve and oil return fast valve;In oil-feed fast valve control loop, oil return quick closing valve Increase MFT tripping operation oil-feed fast valve bypass loops and MFT tripping operation oil returns in valve control loop and MFT relay cabinet relay module Fast valve bypass loop;
The concrete grammar step for carrying out fuel leakage test using the system is as follows:After fuel leakage test starts, first Close oil return fast valve, fuel oil fuel oil main pipe is carried out under the suppressing of oil feed pump it is oil-filled, Oil feeding process be 60 seconds, if at 60 seconds Afterwards fuel oil main pipe " pressure satisfaction " signal is present, then the oil-filled success of fuel oil main pipe;If within 60 second time, fuel oil main pipe cannot be by Stress control then illustrates a certain link in fuel oil main pipe, oily angle valve or oil return fast valve in the claimed range of " pressure satisfaction " There is significant leakage, the interface of leak test then shows " oil-filled failure ";If the oil-filled success of fuel oil main pipe, is automatically switched off fuel oil fast Close valve;When the oil-filled success of fuel oil main pipe, after fuel oil fast valve is closed, now oil-feed fast valve and oil return fast valve Close All, Fuel oil before is in air-tight state, if in 180 seconds, if " pressure satisfaction " signal in fuel oil main pipe is present always, Illustrate that oily angle valve is not leaked, the leak test success of oily angle valve;If " pressure satisfaction " signal was in 180 seconds internal diabetes in fuel oil main pipe Lose, illustrate that oily angle valve has leakage, then fuel leakage test failure;Fuel leakage test carries out middle signal and sends to MFT tripping operations At this moment bypass loop, normal opened contact closure tests program control Automatic Program and sends DCS control instructions 1 and instruction by fuel leakage 2, fuel leakage test can be carried out before furnace purge.
The above is only the preferred embodiment of the present invention, it is noted that for the ordinary skill people of the art Member, without departing from the inventive concept of the premise, can also make some improvements and modifications, and these improvements and modifications also should be regarded as In protection scope of the present invention.Although the present invention is disclosed as above with embodiment, it is not limited to the protection of the present invention Scope, any technical staff for being familiar with the technology, in the variation made without departing from the spirit and scope of the invention and retouching, Protection scope of the present invention all should be belonged to.

Claims (7)

1. it is a kind of to carry out the system of fuel leakage test after boiler occurs MFT, it is characterised in that described system is let out by fuel oil Leakage test carries out button, software channel module, DO fasteners, hardware corridor terminal, control cable, MFT tripping operation oil-feed fast valves and returns Road, oil-feed fast valve bypass loop, MFT tripping operation oil return fast valves loop, oil return fast valve bypass loop composition, described MFT Tripping operation oil-feed fast valve loop by supply module, oil-feed fast valve, oil-feed fast valve DCS control instruction relays, MFT trip into Oily fast valve relay group is into the oil-feed fast valve bypass loop is in parallel with MFT tripping operation oil-feed quick closing valve valve relays;Institute State MFT tripping operation oil return fast valve loop by supply module, oil return fast valve, oil return fast valve DCS control instructions relay and MFT trips oil return fast valve relay group into, the oil return fast valve bypass loop and MFT tripping operation oil return fast valve relays Device is in parallel;Hardware corridor terminal is located in DO fasteners, and oil-feed fast valve bypass loop, oil return fast valve bypass loop pass through respectively Cable is connected with the hard channel terminals on DO fasteners.
2. a kind of system that fuel leakage test is carried out after boiler occurs MFT as claimed in claim 1, it is characterised in that Described fuel leakage test carries out button, and in parallel mode is connected with two software channel modules, described two software channels It is connected with DO fasteners, two hardware corridor terminals is provided with described DO fasteners, two hardware corridors on the DO fasteners Terminal is attached respectively by controlling cable with oil-feed fast valve bypass loop, oil return fast valve bypass loop.
3. a kind of system that fuel leakage test is carried out after boiler occurs MFT as claimed in claim 1 or 2, its feature exists In, preset in described oil-feed fast valve fuel leakage test carry out in logic.
4. a kind of system that fuel leakage test is carried out after boiler occurs MFT as claimed in claim 1 or 2, its feature exists In, preset in described oil return fast valve fuel leakage test carry out in logic.
5. a kind of system that fuel leakage test is carried out after boiler occurs MFT as claimed in claim 1 or 2, its feature exists In the oil-feed fast valve bypass loop control instruction relay, oil return fast valve bypass loop control instruction relay are big Capacity DC 220V relays.
6. a kind of system that fuel leakage test is carried out after boiler occurs MFT as claimed in claim 1 or 2, its feature exists In the oil-feed fast valve bypass loop control instruction relay, the DO of oil return fast valve bypass loop control instruction relay Fastener is arranged apart.
7. a kind of method that fuel leakage test is carried out before boiler occurs MFT rear hearths purging, it is characterised in that using as weighed Profit requires a kind of system that fuel leakage test is carried out after boiler occurs MFT described in 1 or 4, patrols in the control of oil-feed fast valve Increasing fuel leakage test in volume carries out middle logic, when logical signal is " 1 ", bypasses MFT action signals, makes the valve in MFT After generation, OFF signal is forced to be cancelled, it is allowed to which ON signal is enabled, valve energy automatic switch;
Increase logic during fuel leakage test is carried out, when logical signal is " 1 ", bypass in oil return fast valve control logic MFT action signals, make the valve after MFT generations, force OFF signal to be cancelled, it is allowed to which ON signal is enabled, valve energy automatic switch;
Two DO passages defined in DCS logics, and oil-feed is sent to respectively by DO fasteners and control cable 1 and control cable 2 In the hard control loop of fast valve and oil return fast valve;
Increase MFT in oil-feed fast valve control loop, oil return fast valve control loop and MFT relay cabinet relay module to jump Lock oil-feed fast valve bypass loop and MFT tripping operation oil return fast valve bypass loops;
Comprise the following steps:
S1:After boiler occurs MFT, before furnace purge, fuel leakage test is carried out;
S2:After fuel leakage test starts, oil return fast valve is first shut off, fuel oil enters under the suppressing of oil feed pump to fuel oil main pipe Row it is oil-filled, Oil feeding process be 60 seconds, if after 60s fuel oil main pipe " pressure satisfactions " signal presence, fuel oil main pipe it is oil-filled into Work(;If within 60 second time, fuel oil main pipe cannot then illustrate that fuel oil is female by Stress control in the claimed range of " pressure satisfaction " There is significant leakage in a certain link in pipe, oily angle valve or oil return fast valve, the interface of leak test then shows " oil-filled failure ";
S3:If the oil-filled success of fuel oil main pipe, is automatically switched off fuel oil fast valve;When the oil-filled success of fuel oil main pipe, fuel oil fast valve is closed After closing, now oil-feed fast valve and oil return fast valve Close All, fuel oil before is in air-tight state, if in 180 seconds, such as " pressure satisfaction " signal in fruit fuel oil main pipe is present always, then illustrate that oily angle valve is not leaked, the leak test of oily angle valve into Work(;If " pressure satisfaction " signal disappeared in 180 seconds in fuel oil main pipe, illustrate that oily angle valve has leakage, then fuel leakage test Failure;
S4:Fuel leakage test carries out middle signal and sends to MFT tripping operation bypass loops, normal opened contact closure, at this moment by fuel oil The program control Automatic Program of leak test sends DCS control instructions 1 and instruction 2, and fuel leakage test can be carried out before furnace purge.
CN201611180950.2A 2016-12-20 2016-12-20 System and method capable of carrying out fuel oil leakage test after MFT of boiler Pending CN106597943A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201611180950.2A CN106597943A (en) 2016-12-20 2016-12-20 System and method capable of carrying out fuel oil leakage test after MFT of boiler

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201611180950.2A CN106597943A (en) 2016-12-20 2016-12-20 System and method capable of carrying out fuel oil leakage test after MFT of boiler

Publications (1)

Publication Number Publication Date
CN106597943A true CN106597943A (en) 2017-04-26

Family

ID=58600103

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201611180950.2A Pending CN106597943A (en) 2016-12-20 2016-12-20 System and method capable of carrying out fuel oil leakage test after MFT of boiler

Country Status (1)

Country Link
CN (1) CN106597943A (en)

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2008151486A1 (en) * 2007-06-11 2008-12-18 Shanghai Waigaoqiao No. 3 Power Generation Co. Ltd Intelligent protection system for dynamo group thermal control
JP2011127877A (en) * 2009-12-21 2011-06-30 Mitsubishi Heavy Ind Ltd Method for monitoring fuel leakage in fuel burner, and monitoring device
CN105157047A (en) * 2015-09-07 2015-12-16 广东电网有限责任公司电力科学研究院 Method and system for debugging boiler of 1045MW ultra-supercritical coal-fired unit through pipe purging
CN205079254U (en) * 2015-07-08 2016-03-09 大唐阳城发电有限责任公司 Boiler fuel oil system leaks safety monitoring device
CN205102159U (en) * 2015-10-21 2016-03-23 中国大唐集团科学技术研究院有限公司华中分公司 Boiler fuel leak test shunting device
CN206741244U (en) * 2016-12-20 2017-12-12 华电电力科学研究院 A kind of system in boiler occurring that fuel leakage experiment can be carried out after MFT

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2008151486A1 (en) * 2007-06-11 2008-12-18 Shanghai Waigaoqiao No. 3 Power Generation Co. Ltd Intelligent protection system for dynamo group thermal control
JP2011127877A (en) * 2009-12-21 2011-06-30 Mitsubishi Heavy Ind Ltd Method for monitoring fuel leakage in fuel burner, and monitoring device
CN205079254U (en) * 2015-07-08 2016-03-09 大唐阳城发电有限责任公司 Boiler fuel oil system leaks safety monitoring device
CN105157047A (en) * 2015-09-07 2015-12-16 广东电网有限责任公司电力科学研究院 Method and system for debugging boiler of 1045MW ultra-supercritical coal-fired unit through pipe purging
CN205102159U (en) * 2015-10-21 2016-03-23 中国大唐集团科学技术研究院有限公司华中分公司 Boiler fuel leak test shunting device
CN206741244U (en) * 2016-12-20 2017-12-12 华电电力科学研究院 A kind of system in boiler occurring that fuel leakage experiment can be carried out after MFT

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
孙漾: "超超临界二次再热机组炉膛安全监控***设计方案" *
郭子鹏: "火电厂锅炉燃油泄漏试验控制的改进" *

Similar Documents

Publication Publication Date Title
CN101333945B (en) System and methods for heat recovery steam generators hot purging
CN103971764B (en) Multisection type Safety Injection device and the passive safety injection system with the multisection type Safety Injection device
US9410486B2 (en) System and method for washing and purging the liquid fuel system of a turbine with water
CN112460635B (en) Air-entraining purging method for dual-fuel gas turbine
CN107165686A (en) A kind of double reheat fired power generating unit bypass control method and system
CN206741244U (en) A kind of system in boiler occurring that fuel leakage experiment can be carried out after MFT
CN103982249A (en) Emergency trip device capable of isolating testing signal
CN103528772B (en) A kind of micro-device for detecting leakage, the system with this device and detection method thereof
CN107269326B (en) Back pressure type steam turbine generator unit system and operation method thereof
CN206830241U (en) The steam distribution system of steam turbine
CN106597943A (en) System and method capable of carrying out fuel oil leakage test after MFT of boiler
CN108317500A (en) Shut down the system and method for not blowing out in low-heat value gas power plant
JP6495137B2 (en) Combined cycle power plant and control method thereof
CN107084011A (en) A kind of nuclear steam turbine method for rapid cooling
CN201141615Y (en) Blast furnace gas supplying structure for high-proportion mixed burning blast furnace gas coal-fired boiler
CN112780417B (en) Gas turbine starting optimization control system and method applying nitrogen isolation
JPH04148035A (en) Vapor cooled gas turbine system
CN113339252A (en) Water supply characteristic test method for high-capacity electric pump with 100% steam pump unit
CN103267425B (en) Method and device for solving condenser low vacuum in combined cycle unit starting process
US4151712A (en) Protective shutdown system for combined cycle plant having a dual liquid fuel system
CN109340575A (en) A kind of online regulator and its online pressure regulation method of gas pipeline
CN108729961A (en) Control method, device, storage medium and the processor of steam turbine
CN220581425U (en) Hydraulic turbine hydraulic system oil pump loading fault system
CN113777976B (en) Nuclear power plant isolation valve control circuit
CN213574264U (en) Steam turbine power generation system

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20170426

WD01 Invention patent application deemed withdrawn after publication