CN106594955A - Prefabricated steel structure house central ventilation system and construction method thereof - Google Patents

Prefabricated steel structure house central ventilation system and construction method thereof Download PDF

Info

Publication number
CN106594955A
CN106594955A CN201611145476.XA CN201611145476A CN106594955A CN 106594955 A CN106594955 A CN 106594955A CN 201611145476 A CN201611145476 A CN 201611145476A CN 106594955 A CN106594955 A CN 106594955A
Authority
CN
China
Prior art keywords
fresh air
vertical
prefabrication
control system
mechanical control
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201611145476.XA
Other languages
Chinese (zh)
Inventor
张栋鹏
郎卫国
王红兵
陈晓明
贾宝荣
龚明
马良
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Construction Group Design Institute Co Ltd
Shanghai Mechanized Construction Group Co Ltd
Original Assignee
Shanghai Construction Group Design Institute Co Ltd
Shanghai Mechanized Construction Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Construction Group Design Institute Co Ltd, Shanghai Mechanized Construction Group Co Ltd filed Critical Shanghai Construction Group Design Institute Co Ltd
Priority to CN201611145476.XA priority Critical patent/CN106594955A/en
Publication of CN106594955A publication Critical patent/CN106594955A/en
Pending legal-status Critical Current

Links

Classifications

    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F24HEATING; RANGES; VENTILATING
    • F24FAIR-CONDITIONING; AIR-HUMIDIFICATION; VENTILATION; USE OF AIR CURRENTS FOR SCREENING
    • F24F7/00Ventilation
    • F24F7/04Ventilation with ducting systems, e.g. by double walls; with natural circulation
    • F24F7/06Ventilation with ducting systems, e.g. by double walls; with natural circulation with forced air circulation, e.g. by fan positioning of a ventilator in or against a conduit
    • F24F7/08Ventilation with ducting systems, e.g. by double walls; with natural circulation with forced air circulation, e.g. by fan positioning of a ventilator in or against a conduit with separate ducts for supplied and exhausted air with provisions for reversal of the input and output systems
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04CSTRUCTURAL ELEMENTS; BUILDING MATERIALS
    • E04C2/00Building elements of relatively thin form for the construction of parts of buildings, e.g. sheet materials, slabs, or panels
    • E04C2/44Building elements of relatively thin form for the construction of parts of buildings, e.g. sheet materials, slabs, or panels characterised by the purpose
    • E04C2/52Building elements of relatively thin form for the construction of parts of buildings, e.g. sheet materials, slabs, or panels characterised by the purpose with special adaptations for auxiliary purposes, e.g. serving for locating conduits
    • E04C2/521Building elements of relatively thin form for the construction of parts of buildings, e.g. sheet materials, slabs, or panels characterised by the purpose with special adaptations for auxiliary purposes, e.g. serving for locating conduits serving for locating conduits; for ventilating, heating or cooling
    • E04C2/523Building elements of relatively thin form for the construction of parts of buildings, e.g. sheet materials, slabs, or panels characterised by the purpose with special adaptations for auxiliary purposes, e.g. serving for locating conduits serving for locating conduits; for ventilating, heating or cooling for ventilating
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F24HEATING; RANGES; VENTILATING
    • F24FAIR-CONDITIONING; AIR-HUMIDIFICATION; VENTILATION; USE OF AIR CURRENTS FOR SCREENING
    • F24F13/00Details common to, or for air-conditioning, air-humidification, ventilation or use of air currents for screening
    • F24F13/02Ducting arrangements
    • F24F13/0227Ducting arrangements using parts of the building, e.g. air ducts inside the floor, walls or ceiling of a building
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F24HEATING; RANGES; VENTILATING
    • F24FAIR-CONDITIONING; AIR-HUMIDIFICATION; VENTILATION; USE OF AIR CURRENTS FOR SCREENING
    • F24F13/00Details common to, or for air-conditioning, air-humidification, ventilation or use of air currents for screening
    • F24F13/02Ducting arrangements
    • F24F13/0254Ducting arrangements characterised by their mounting means, e.g. supports
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F24HEATING; RANGES; VENTILATING
    • F24FAIR-CONDITIONING; AIR-HUMIDIFICATION; VENTILATION; USE OF AIR CURRENTS FOR SCREENING
    • F24F13/00Details common to, or for air-conditioning, air-humidification, ventilation or use of air currents for screening
    • F24F13/02Ducting arrangements
    • F24F13/06Outlets for directing or distributing air into rooms or spaces, e.g. ceiling air diffuser

Landscapes

  • Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • Chemical & Material Sciences (AREA)
  • Combustion & Propulsion (AREA)
  • General Engineering & Computer Science (AREA)
  • Civil Engineering (AREA)
  • Architecture (AREA)
  • Structural Engineering (AREA)
  • Ventilation (AREA)

Abstract

The invention provides a prefabricated steel structure house central ventilation system and a construction method thereof. The system comprises a fresh air machine, a fresh air opening and a fresh air vertical pipe; and the fresh air vertical pipe is prefabricated into a vertical prefabricated groove of a prefabricate wallboard of a room needing fresh air, the fresh air opening is formed in the side face of the lower portion of the fresh air vertical pipe, and the fresh air machine is connected with the fresh air vertical pipe through a fresh air pipe. The fresh air vertical pipe is prefabricated into the vertical prefabricated groove of the prefabricate wallboard of the room needing fresh air, the fresh air opening is formed in the side face of the lower portion of the fresh air vertical pipe, and therefore the prefabricating rate and the construction efficiency of a fabricated house can be improved. The fresh air machine supplies fresh air to the room needing fresh air through the fresh air pipe, the fresh air vertical pipe and the fresh air opening, and therefore various unhealthy or noxious gas such as lampblack peculiar smells, CO2, cigarette smell, formaldehyde and benzene and germs, viruses, dust and scurf in the house can be removed, fresh air is provided for the house, and the sick building syndrome is avoided.

Description

Prefabrication and assembly construction steel house VMC (Ventilation Mechanical Control System) and its construction method
Technical field
The present invention relates to house VMC (Ventilation Mechanical Control System), more particularly to a kind of prefabrication and assembly construction steel house VMC (Ventilation Mechanical Control System) and its construction Method.
Background technology
With the continuous development and the support energetically of country policy of society, in recent years, steel house is sent out rapidly at home Exhibition.Steel house has construction speed fast, and climate condition affects less, saves labour force, reduces environmental pollution etc. many Advantage.
In order to meet the multi-faceted application demand of resident family, improve prefabrication and assembly construction steel house using taste, it is various with The related applied research of prefabrication and assembly construction steel house extensively launches.
How using the mounting condition for coordinating the prefabricated wind pipeline of house assembling construction and equipment, assembled-type house is improved prefabricated Rate and efficiency of construction, for house fresh air is provided, and drives away fumes peculiar smell, the CO of premises2, medicated cigarette taste, formaldehyde, benzene etc. it is various Unhealthy or harmful gass and antibacterial, virus, dust, scurf, it has also become construction circle needs technical problem urgently to be resolved hurrily.
The content of the invention
It is an object of the invention to provide a kind of prefabrication and assembly construction steel house VMC (Ventilation Mechanical Control System) and its construction method, by inciting somebody to action Vertical fresh air pipe is formed in advance in the vertical pre-groove of prefabricated panel, improves the prefabricated rate of assembled-type house and efficiency of construction;Fresh air system System can provide fresh air for house, drive away fumes peculiar smell, the CO of premises2, medicated cigarette taste, formaldehyde, benzene etc. it is various unhealthy Or harmful gass and antibacterial, virus, dust, scurf.
To solve above-mentioned technical problem, the present invention provides following technical scheme:
A kind of prefabrication and assembly construction steel house VMC (Ventilation Mechanical Control System), including new blower fan, fresh wind port and vertical fresh air pipe are described new Wind standpipe is formed in advance in the vertical pre-groove of the prefabricated panel in the room for needing fresh air, and the fresh wind port is arranged at the fresh air The lower side of standpipe, the new blower fan is connected with the vertical fresh air pipe by fresh air pipeline.
Preferably, in above-mentioned prefabrication and assembly construction steel house VMC (Ventilation Mechanical Control System), the vertical prefabricated ditch of the prefabricated panel Cover on groove and be provided with dismountable cover plate, one is opened up on the dismountable cover plate corresponding with the size shape of the fresh wind port Through hole.
Preferably, in above-mentioned prefabrication and assembly construction steel house VMC (Ventilation Mechanical Control System), the quantity of the vertical fresh air pipe is at least Two, respectively in the vertical pre-groove of the prefabricated panel in the room for needing fresh air, the VMC (Ventilation Mechanical Control System) also includes a point wind Case, the draught distributing box is connected with the new blower fan, and the draught distributing box is upper with corresponding vertical fresh air pipe respectively by each fresh air pipeline Port connects.
Preferably, in above-mentioned prefabrication and assembly construction steel house VMC (Ventilation Mechanical Control System), also including exhaust blower, exhaust duct and Integrated air exhaust mouth, the exhaust blower is connected by exhaust duct with the integrated air exhaust mouth.
Preferably, in above-mentioned prefabrication and assembly construction steel house VMC (Ventilation Mechanical Control System), the integrated air exhaust mouth is arranged at kitchen Or on the furred ceiling in dining room or living room, the exhaust blower is respectively arranged on balcony with the new blower fan.
Preferably, in above-mentioned prefabrication and assembly construction steel house VMC (Ventilation Mechanical Control System), the new blower fan is adopted with the exhaust blower Powered self by the clean energy resource that solar energy is produced with house.
Preferably, in above-mentioned prefabrication and assembly construction steel house VMC (Ventilation Mechanical Control System), also including some return air inlets, the return air Mouth is arranged in each room for needing fresh air near the door pocket top in kitchen or dining room or living room.
Preferably, in above-mentioned prefabrication and assembly construction steel house VMC (Ventilation Mechanical Control System), the fresh air pipeline is walked in furred ceiling When the girder steel that passes adopt Honeycomb Beam, airduct sleeve pipe is provided with the hole passed through for fresh air pipeline in the Honeycomb Beam.
Preferably, in above-mentioned prefabrication and assembly construction steel house VMC (Ventilation Mechanical Control System), the new blower fan is provided with PM2.5 hazes Defecator.
The invention also discloses a kind of construction method of prefabrication and assembly construction steel house VMC (Ventilation Mechanical Control System) as above, including Following steps:
The first step, prefabrication steel house assembled component:Arrange perpendicular on required prefabricated panel according to design requirement To pre-groove, and the prefabricated vertical fresh air pipe in vertical pre-groove, the lower side of the vertical fresh air pipe is opened up for arranging The through hole of fresh wind port, according to design requirement the through hole for arranging return air inlet is opened up above the door pocket of required prefabricated panel;
Second step, assembled in situ constructs to form steel house, and new blower fan and exhaust blower are installed on balcony;
3rd step, installs draught distributing box, fresh air pipeline, exhaust duct, integrated air exhaust mouth, fresh wind port and return air inlet, by institute State draught distributing box to be connected with the new blower fan, and the draught distributing box is connected by each fresh air pipeline with the upper port of each vertical fresh air pipe Connect, fresh wind port be arranged in the through hole of the lower side of the vertical fresh air pipe, by the integrated air exhaust mouth be arranged at kitchen or On the furred ceiling in person dining room or living room, exhaust blower is connected with integrated air exhaust mouth by exhaust duct, the return air inlet is arranged Near the door pocket top in kitchen or dining room or living room in each room for needing fresh air.
From techniques disclosed above scheme, compared with prior art, beneficial effects of the present invention are as follows:
(1) present invention is provided prefabrication and assembly construction steel house VMC (Ventilation Mechanical Control System) and its construction method, the system includes fresh air Machine, fresh wind port and vertical fresh air pipe, the vertical fresh air pipe is formed in advance the vertical prefabricated ditch of the prefabricated panel in the room for needing fresh air In groove, the fresh wind port is arranged at the lower side of the vertical fresh air pipe, and the new blower fan passes through fresh air with the vertical fresh air pipe Pipeline connects.By the way that the vertical fresh air pipe is formed in advance in the vertical pre-groove of the prefabricated panel in the room for needing fresh air, institute State the lower side that fresh wind port is arranged at the vertical fresh air pipe, it is possible to increase the prefabricated rate and efficiency of construction of assembled-type house. Fresh air is conveyed to the room for needing fresh air by new blower fan Jing fresh air pipelines, vertical fresh air pipe and fresh wind port, house can be driven away Interior fumes peculiar smell, CO2, medicated cigarette taste, formaldehyde, various unhealthy or harmful gass and antibacterial, virus, dust, the scurf such as benzene, Fresh air is provided for house, is solved " Cure of Sick Building Syndrome ".
(2) present invention is provided prefabrication and assembly construction steel house VMC (Ventilation Mechanical Control System) and its construction method, the system also includes row Blower fan, exhaust duct, integrated air exhaust mouth and some return air inlets, the exhaust blower is by exhaust duct and the integrated air exhaust mouth Connection, the return air inlet is arranged in each room for needing fresh air near the door pocket top in kitchen or dining room or living room.Such as This is applied in combination, new blower fan, fresh wind port, exhaust blower, integrated air exhaust mouth and return air inlet, blows by the fresh air positioned at bottom metope Mouth is completed, and return air inlet is arranged at door pocket top, therefore, it can to form the bidirectional flow room ventilation air-flow group of lower air-supply top row wind Knit, air current flow efficiency can be significantly improved.
Description of the drawings
Fig. 1 is the prefabrication and assembly construction steel house VMC (Ventilation Mechanical Control System) schematic diagram of the present invention;
Fig. 2 is the sectional schematic diagram that fresh air pipeline lays along pre-groove.
Fig. 3 is fresh air, air draft airduct plane graph.
Fig. 4 is the prefabricated panel containing fresh air pipeline pre-groove.
In figure:1. new blower fan, 2. prefabricated panel, 3. analog quantity electric control valve, 4. airduct sleeve pipe, 5. vertical fresh air pipe, 6. Fresh wind port, 7. return air inlet, 8. integrated air exhaust mouth, 9. exhaust blower, 10. Honeycomb Beam, 11. fresh air pipelines, 12. exhaust ducts, 13. are erected To pre-groove, 14. furred ceilings, 15. balconies, 16. dining rooms, 17. bedrooms, 18. living rooms, 19. kitchens, 20. draught distributing boxs.
Specific embodiment
The present invention is described in further detail below in conjunction with the drawings and specific embodiments.According to description below and right Claim, advantages and features of the invention will become apparent from.Hereinafter accompanying drawing will be combined by cited embodiment, describe this in detail Bright technology contents and feature.Need to illustrate in addition, accompanying drawing is compared in the form of simplifying very much and accurately using non- Example, only to purpose that is convenient, lucidly aiding in illustrating the embodiment of the present invention.For sake of convenience, described below " on ", The upper and lower direction of D score and accompanying drawing is consistent, but this can not become the restriction of technical solution of the present invention.
Fig. 1 to Fig. 4 is referred to, present embodiment discloses a kind of prefabrication and assembly construction steel house VMC (Ventilation Mechanical Control System), including fresh air Machine 1, fresh wind port 6 and vertical fresh air pipe 5, the vertical fresh air pipe 5 is formed in advance the vertical of the prefabricated panel 2 in the room for needing fresh air In pre-groove 13, described to need the room of fresh air to include bedroom 17, living room 18, dining room 16 etc., the fresh wind port 6 is arranged In the lower side of the vertical fresh air pipe 5, the new blower fan 1 is connected with the vertical fresh air pipe 5 by fresh air pipeline 11.By inciting somebody to action The vertical fresh air pipe 5 is formed in advance in the vertical pre-groove 13 of the prefabricated panel 2 in the room for needing fresh air, and the fresh wind port 6 sets It is placed in the lower side of the vertical fresh air pipe 5, it is possible to increase the prefabricated rate and efficiency of construction of assembled-type house.By new blower fan 1 Jing fresh air pipelines 11, vertical fresh air pipe 5 and fresh wind port 6 to the room for needing fresh air conveys fresh air, can drive away the oil of premises Cigarette abnormal flavour, CO2, medicated cigarette taste, formaldehyde, various unhealthy or harmful gass and antibacterial, virus, dust, the scurf such as benzene, be house Fresh air is provided, is solved " Cure of Sick Building Syndrome ".
Preferably, in the prefabrication and assembly construction steel house VMC (Ventilation Mechanical Control System) of the present embodiment, the prefabricated panel 2 it is vertical pre- Cover on groove processed 13 and be provided with dismountable cover plate (not shown), one is opened up on the dismountable cover plate with the fresh wind port 6 The corresponding through hole of size shape.The dismountable cover plate can be arranged in vertical pre-groove 13 in factory, to protect Internal vertical fresh air pipe 5.
In order to adjust the resh air requirement in each room, the fresh air pipeline 11 of the fresh wind port 6 per root towards each room is provided with mould Analog quantity electric control valve 3.
Preferably, in the prefabrication and assembly construction steel house VMC (Ventilation Mechanical Control System) of the present embodiment, the quantity of the vertical fresh air pipe 5 is extremely Rare two, respectively in the vertical pre-groove 13 of the prefabricated panel 2 of the not chummery for needing fresh air, the VMC (Ventilation Mechanical Control System) Also include draught distributing box 20, the draught distributing box 20 is connected with the new blower fan 1, and the draught distributing box 20 is distinguished by each fresh air pipeline 11 Connect with the upper port of corresponding vertical fresh air pipe 5.
Preferably, in the prefabrication and assembly construction steel house VMC (Ventilation Mechanical Control System) of the present embodiment, also including exhaust blower 9, exhaust duct Road 12 and integrated air exhaust mouth 8, the exhaust blower 9 is connected by exhaust duct 12 with the integrated air exhaust mouth 8.Using exhaust blower 9, can quickly discharge indoor fumes peculiar smell, CO2, medicated cigarette taste, formaldehyde, the various unhealthy or harmful gass such as benzene and antibacterial, Virus, dust, scurf, it is ensured that living environment is comfortable.
Preferably, in the prefabrication and assembly construction steel house VMC (Ventilation Mechanical Control System) of the present embodiment, the integrated air exhaust mouth 8 is arranged at On the furred ceiling 14 in kitchen 19 or dining room 16 or living room 18.
Preferably, in the prefabrication and assembly construction steel house VMC (Ventilation Mechanical Control System) of the present embodiment, the exhaust blower 9 and the fresh air Machine 1 is respectively arranged on balcony 15, and the exhaust blower 9 selects mute type with the new blower fan 1, such that it is able to reduce exhaust blower 9 impacts with the noise of new blower fan 1 to resident family.The new blower fan 1 is produced using house with the exhaust blower 9 self by solar energy Raw clean energy resource is powered, not increase the operation energy consumption of new blower fan 1 and exhaust blower 9.
Preferably, in the prefabrication and assembly construction steel house VMC (Ventilation Mechanical Control System) of the present embodiment, also including some return air inlets 7, institute State return air inlet 7 be arranged in each room (i.e. with the room of fresh wind port 6) for needing fresh air near kitchen 19 or dining room 16 or The door pocket top in living room 18.So it is applied in combination, new blower fan 1, fresh wind port 6, exhaust blower 9, integrated air exhaust mouth 8 and return air inlet 7, to blow and completed by the fresh wind port 6 positioned at bottom metope, return air inlet 7 is arranged at door pocket top, therefore, it can to form lower air-supply top The bidirectional flow room ventilation air current composition of air draft, it is possible to increase air current flow efficiency.
Preferably, in the prefabrication and assembly construction steel house VMC (Ventilation Mechanical Control System) of the present embodiment, the fresh air pipeline 11 passes through can Mode is fixed suspension and support (not shown) and is installed in furred ceiling 14.That is, the walking in furred ceiling 14 of fresh air pipeline 11.
Preferably, in the prefabrication and assembly construction steel house VMC (Ventilation Mechanical Control System) of the present embodiment, the fresh air pipeline 11 is in furred ceiling The girder steel passed during walking in 14 is provided with wind using Honeycomb Beam 10 in the hole passed through for fresh air pipeline 11 in the Honeycomb Beam 10 Pipe-in-pipe 4.Using Honeycomb Beam 10 scene can be avoided from punching, and be easy to fresh air pipeline 11 to select path.By arranging airduct Sleeve pipe 4 can play a part of buffer protection to fresh air pipeline 11.
Preferably, in the prefabrication and assembly construction steel house VMC (Ventilation Mechanical Control System) of the present embodiment, the surrounding of the prefabricated panel 2 sets Have with adjacent structure house assembled component (can be adjacent prefabricated panel 2, or adjacent precast floor slab, it is also possible to Adjacent precast beam such as Honeycomb Beam) connection interface.The upper end of such as described prefabricated panel 2 is provided with inserts for Honeycomb Beam 10 The through hole of connection.
Preferably, in the prefabrication and assembly construction steel house VMC (Ventilation Mechanical Control System) of the present embodiment, the new blower fan 1 is provided with PM2.5 haze defecators (not shown).By arranging PM2.5 haze defecators, it can be ensured that to the fresh air of indoor offer Air quality, improve indoor comfort degree.
Please continue to refer to Fig. 1 to Fig. 4, the construction method of the prefabrication and assembly construction steel house VMC (Ventilation Mechanical Control System) of the present invention, including Following steps:
The first step, prefabrication steel house assembled component, prefabrication steel house assembled component includes prefabricated Wallboard, precast floor slab, precast beam etc., according to design requirement vertical pre-groove 13 is arranged on required prefabricated panel 2, and perpendicular The prefabricated vertical fresh air pipe 5 into pre-groove 13, the lower side of the vertical fresh air pipe 5 opens up the through hole for arranging fresh wind port 6; Through hole for arranging return air inlet 7 is opened up above the door pocket of required prefabricated panel 2 according to design requirement, it is pre- according to design requirement The Honeycomb Beam 10 of requirement processed is honeycomb fashion girder steel;
Second step, assembled in situ constructs to form steel house, and new blower fan 1 and exhaust blower 9 are installed on balcony 15;
3rd step, installs draught distributing box 20, fresh air pipeline 11, exhaust duct 12, integrated air exhaust mouth 8, fresh wind port 6 and return air Mouth 7, the draught distributing box 20 is connected with the new blower fan 1, and causes the draught distributing box 20 new with each by each fresh air pipeline 11 The upper port connection of wind standpipe 5, fresh wind port 6 is arranged in the through hole of the lower side of the vertical fresh air pipe 5, by the concentration Exhaust outlet 8 is arranged on the furred ceiling 14 in kitchen 19 or dining room 16 or living room 18, and exhaust blower 9 is passed through with integrated air exhaust mouth 8 Exhaust duct 12 connects, and the return air inlet 7 is arranged in each room for needing fresh air near kitchen 19 or dining room 16 or is risen The door pocket top in room 18.
In sum, the present invention has the beneficial effect that:
(1) present invention provide prefabrication and assembly construction steel house VMC (Ventilation Mechanical Control System) and its construction method method, using new blower fan 1, Fresh wind port 6 and vertical fresh air pipe 5, the vertical fresh air pipe 5 is formed in advance the vertical prefabricated of the prefabricated panel 2 in the room for needing fresh air In groove 13, the fresh wind port 6 is arranged at the lower side of the vertical fresh air pipe 5, the new blower fan 1 and the vertical fresh air pipe 5 Connected by fresh air pipeline 11.By the vertical fresh air pipe 5 is formed in advance the room for needing fresh air prefabricated panel 2 it is vertical pre- In groove processed 13, the fresh wind port 6 is arranged at the lower side of the vertical fresh air pipe 5, it is possible to increase assembled-type house it is pre- Rate processed and efficiency of construction.It is defeated to the room for needing fresh air by the Jing fresh air pipelines 11 of new blower fan 1, vertical fresh air pipe 5 and fresh wind port 6 Fresh air is sent, fumes peculiar smell, the CO of premises can be driven away2, medicated cigarette taste, formaldehyde, the various unhealthy or harmful gass such as benzene and Antibacterial, virus, dust, scurf, for house fresh air is provided, and is solved " Cure of Sick Building Syndrome ".
(2) present invention is provided prefabrication and assembly construction steel house VMC (Ventilation Mechanical Control System) and its construction method, using exhaust blower 9, row Wind pipeline 12, integrated air exhaust mouth 8 and some return air inlets 7, the exhaust blower 9 is by exhaust duct 12 and the integrated air exhaust mouth 8 connections, the return air inlet 7 is arranged in each room for needing fresh air near kitchen 19 or the door pocket in dining room 16 or living room 18 Top.So it is applied in combination, new blower fan 1, fresh wind port 6, exhaust blower 9, integrated air exhaust mouth 8 and return air inlet 7, blows by the bottom of positioned at The fresh wind port 6 of end wall surface is completed, and return air inlet 7 is arranged at door pocket top, therefore, it can to form the two-way flow chamber of lower air-supply top row wind Interior draft tissue, can significantly improve air current flow efficiency.
Foregoing description is only the description to present pre-ferred embodiments, not to any restriction of the scope of the invention, this Any change, modification that the those of ordinary skill in bright field does according to the disclosure above content, belong to the protection of claims Scope.

Claims (10)

1. a kind of prefabrication and assembly construction steel house VMC (Ventilation Mechanical Control System), it is characterised in that vertical including new blower fan, fresh wind port and fresh air Pipe, the vertical fresh air pipe is formed in advance in the vertical pre-groove of the prefabricated panel in the room for needing fresh air, and the fresh wind port is arranged In the lower side of the vertical fresh air pipe, the new blower fan is connected with the vertical fresh air pipe by fresh air pipeline.
2. prefabrication and assembly construction steel house VMC (Ventilation Mechanical Control System) as claimed in claim 1, it is characterised in that the prefabricated panel it is perpendicular Cover in pre-groove and be provided with dismountable cover plate, the size shape of one and the fresh wind port is opened up on the dismountable cover plate The corresponding through hole of shape.
3. prefabrication and assembly construction steel house VMC (Ventilation Mechanical Control System) as claimed in claim 1, it is characterised in that the number of the vertical fresh air pipe Amount at least two, respectively in the vertical pre-groove of the prefabricated panel in the room for needing fresh air, the VMC (Ventilation Mechanical Control System) is also Including draught distributing box, the draught distributing box is connected with the new blower fan, the draught distributing box by each fresh air pipeline respectively with corresponding fresh air The upper port connection of standpipe.
4. prefabrication and assembly construction steel house VMC (Ventilation Mechanical Control System) as claimed in claim 1, it is characterised in that also including exhaust blower, row Wind pipeline and integrated air exhaust mouth, the exhaust blower is connected by exhaust duct with the integrated air exhaust mouth.
5. prefabrication and assembly construction steel house VMC (Ventilation Mechanical Control System) as claimed in claim 4, it is characterised in that the integrated air exhaust mouth sets It is placed on the furred ceiling in kitchen or dining room or living room, the exhaust blower is respectively arranged on balcony with the new blower fan.
6. prefabrication and assembly construction steel house VMC (Ventilation Mechanical Control System) as claimed in claim 4, it is characterised in that the new blower fan with it is described Exhaust blower is powered using house self by the clean energy resource that solar energy is produced.
7. prefabrication and assembly construction steel house VMC (Ventilation Mechanical Control System) as claimed in claim 4, it is characterised in that also including some return air Mouthful, the return air inlet is arranged in each room for needing fresh air near the door pocket top in kitchen or dining room or living room.
8. prefabrication and assembly construction steel house VMC (Ventilation Mechanical Control System) as claimed in claim 1, it is characterised in that the fresh air pipeline is hanging The girder steel passed during walking in top adopts Honeycomb Beam, and in the hole passed through for fresh air pipeline in the Honeycomb Beam duct sleeve is provided with Pipe.
9. prefabrication and assembly construction steel house VMC (Ventilation Mechanical Control System) as claimed in claim 1, it is characterised in that the new blower fan is provided with PM2.5 haze defecators.
10. a kind of construction method of the prefabrication and assembly construction steel house VMC (Ventilation Mechanical Control System) as described in any one in claim 1-9, Comprise the steps:
The first step, prefabrication steel house assembled component:Arrange vertical pre- on required prefabricated panel according to design requirement Groove processed, and the prefabricated vertical fresh air pipe in vertical pre-groove, the lower side of the vertical fresh air pipe is opened up for arranging fresh air The through hole of mouth, according to design requirement the through hole for arranging return air inlet is opened up above the door pocket of required prefabricated panel;
Second step, assembled in situ constructs to form steel house, and new blower fan and exhaust blower are installed on balcony;
3rd step, installs draught distributing box, fresh air pipeline, exhaust duct, integrated air exhaust mouth, fresh wind port and return air inlet, by described point Bellows are connected with the new blower fan, and the draught distributing box is connected by each fresh air pipeline with the upper port of each vertical fresh air pipe, Fresh wind port is arranged in the through hole of the lower side of the vertical fresh air pipe, the integrated air exhaust mouth is arranged at into kitchen or meal On the furred ceiling in the Room or living room, exhaust blower is connected with integrated air exhaust mouth by exhaust duct, the return air inlet is arranged at respectively Need in the room of fresh air near the door pocket top in kitchen or dining room or living room.
CN201611145476.XA 2016-12-13 2016-12-13 Prefabricated steel structure house central ventilation system and construction method thereof Pending CN106594955A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201611145476.XA CN106594955A (en) 2016-12-13 2016-12-13 Prefabricated steel structure house central ventilation system and construction method thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201611145476.XA CN106594955A (en) 2016-12-13 2016-12-13 Prefabricated steel structure house central ventilation system and construction method thereof

Publications (1)

Publication Number Publication Date
CN106594955A true CN106594955A (en) 2017-04-26

Family

ID=58802047

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201611145476.XA Pending CN106594955A (en) 2016-12-13 2016-12-13 Prefabricated steel structure house central ventilation system and construction method thereof

Country Status (1)

Country Link
CN (1) CN106594955A (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109737546A (en) * 2019-03-07 2019-05-10 重庆海润节能技术股份有限公司 A kind of vertical transmission & distribution ventilating system of modular assembly formula
CN111520862A (en) * 2020-04-14 2020-08-11 王庆虎 Construction method of fresh air system built in range hood and door pocket
CN111623501A (en) * 2020-03-10 2020-09-04 朗诗集团股份有限公司 Hidden fresh air pipeline system
CN111980368A (en) * 2020-08-28 2020-11-24 中国建筑标准设计研究院有限公司 Assembled steel structure combined air duct system and construction method thereof
CN112119194A (en) * 2018-05-16 2020-12-22 增城市碧桂园物业发展有限公司 Construction method of wallboard system
CN113622510A (en) * 2020-05-07 2021-11-09 万平华 Installation method of aerated concrete wallboard

Citations (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP0990859A2 (en) * 1998-09-29 2000-04-05 Roland Baumann Air exhausting and ventilating device
JP2008008501A (en) * 2006-06-27 2008-01-17 Matsushita Electric Ind Co Ltd Ventilation device
CN101457966A (en) * 2009-01-08 2009-06-17 金陵科技学院 Household fresh air scavenger system with multiple duct supercharging device and the supercharging device
CN201351326Y (en) * 2009-01-13 2009-11-25 张晨 Prefabricated sandwich type wall panel
CN202658772U (en) * 2012-05-11 2013-01-09 象山宝盛建设有限公司 Light-core reinforced concrete wall
CN203186036U (en) * 2013-04-18 2013-09-11 中联重科股份有限公司渭南分公司 Air conditioner ventilation unit and have its engineering machine tool
CN103669905A (en) * 2013-12-31 2014-03-26 吕燕 Lightweight composite prefabricated panel combined type house and building method thereof
CN104748284A (en) * 2013-12-30 2015-07-01 北京东方智明科技有限公司 Stand column type central fresh air ventilating system
CN105257021A (en) * 2015-09-16 2016-01-20 住房和城乡***科技发展促进中心 Building structure and equipment integrated passive house and building method thereof
CN105698331A (en) * 2016-03-23 2016-06-22 吉林建筑大学 Fresh air device for house and production method of fresh air device
CN206338911U (en) * 2016-12-13 2017-07-18 上海市建工设计研究总院有限公司 Prefabrication and assembly construction steel house VMC

Patent Citations (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP0990859A2 (en) * 1998-09-29 2000-04-05 Roland Baumann Air exhausting and ventilating device
JP2008008501A (en) * 2006-06-27 2008-01-17 Matsushita Electric Ind Co Ltd Ventilation device
CN101457966A (en) * 2009-01-08 2009-06-17 金陵科技学院 Household fresh air scavenger system with multiple duct supercharging device and the supercharging device
CN201351326Y (en) * 2009-01-13 2009-11-25 张晨 Prefabricated sandwich type wall panel
CN202658772U (en) * 2012-05-11 2013-01-09 象山宝盛建设有限公司 Light-core reinforced concrete wall
CN203186036U (en) * 2013-04-18 2013-09-11 中联重科股份有限公司渭南分公司 Air conditioner ventilation unit and have its engineering machine tool
CN104748284A (en) * 2013-12-30 2015-07-01 北京东方智明科技有限公司 Stand column type central fresh air ventilating system
CN103669905A (en) * 2013-12-31 2014-03-26 吕燕 Lightweight composite prefabricated panel combined type house and building method thereof
CN105257021A (en) * 2015-09-16 2016-01-20 住房和城乡***科技发展促进中心 Building structure and equipment integrated passive house and building method thereof
CN105698331A (en) * 2016-03-23 2016-06-22 吉林建筑大学 Fresh air device for house and production method of fresh air device
CN206338911U (en) * 2016-12-13 2017-07-18 上海市建工设计研究总院有限公司 Prefabrication and assembly construction steel house VMC

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
关文吉: "《供暖通风空调设计手册》", 31 January 2016, 中国建材工业出版社 *

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112119194A (en) * 2018-05-16 2020-12-22 增城市碧桂园物业发展有限公司 Construction method of wallboard system
CN109737546A (en) * 2019-03-07 2019-05-10 重庆海润节能技术股份有限公司 A kind of vertical transmission & distribution ventilating system of modular assembly formula
CN109737546B (en) * 2019-03-07 2023-09-08 重庆海润节能技术股份有限公司 Modularized assembly type vertical transmission and distribution ventilation system
CN111623501A (en) * 2020-03-10 2020-09-04 朗诗集团股份有限公司 Hidden fresh air pipeline system
CN111520862A (en) * 2020-04-14 2020-08-11 王庆虎 Construction method of fresh air system built in range hood and door pocket
CN111520862B (en) * 2020-04-14 2021-08-20 王庆虎 Construction method of fresh air system built in range hood and door pocket
CN113622510A (en) * 2020-05-07 2021-11-09 万平华 Installation method of aerated concrete wallboard
CN111980368A (en) * 2020-08-28 2020-11-24 中国建筑标准设计研究院有限公司 Assembled steel structure combined air duct system and construction method thereof
CN111980368B (en) * 2020-08-28 2021-12-28 中国建筑标准设计研究院有限公司 Assembled steel structure combined air duct system and construction method thereof

Similar Documents

Publication Publication Date Title
CN106594955A (en) Prefabricated steel structure house central ventilation system and construction method thereof
CN206191842U (en) Air supply arrangement of application skirting line air supply and new trend conveying system thereof
JP4294784B2 (en) Air conditioning equipment and air conditioning method
CN101187488A (en) Double layer glass curtain aeration technology and method and structure
CN203654539U (en) Double-layer ventilating curtain wall
CN103174242A (en) Novel ventilating curtain wall structure
CN2921676Y (en) Ventilating system for toilt and bathing room space
CN2923957Y (en) Strong-convection silencing dust-proof window
JPH0894138A (en) Overall house ventilating structure for detached
CN206338911U (en) Prefabrication and assembly construction steel house VMC
KR20050111144A (en) Regulated by pressure for ventilation system
CN201964571U (en) Indoor intake and exhaust device
CN205717723U (en) A kind of placement ventilation device
CN205481540U (en) Ventilation system
JP2009281116A (en) Ventilation structure for building
CN207797316U (en) Intelligent gas stream guidance system
CN207604894U (en) A kind of mute tide gate in bathroom
CN208293721U (en) A kind of noise reduction multi-functional sewer pipe
JP2001289476A (en) System and method for ventilation
JP2011064018A (en) Ventilation structure of building
KR200415389Y1 (en) Natural ventilating system for building using gravity and wind pressure
JP2000081237A (en) Structure of natural ventilation building for low airtightness dwelling and natural ventilation system
Gaczoł Living quarters. A natural balanced ventilation system. Simulations part 1
KR200419410Y1 (en) Ventilation system using replacement of duct by ceiling space
JP5805810B2 (en) Building ventilation structure

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
CB02 Change of applicant information

Address after: 200050 Changning District, Wuyi Road, No. 150,

Applicant after: Shanghai General Construction Engineering Research Institute Co.,Ltd.

Applicant after: SHANGHAI MECHANIZED CONSTRUCTION GROUP Co.,Ltd.

Address before: 200050 Changning District, Wuyi Road, No. 150,

Applicant before: SHANGHAI CONSTRUCTION DESIGN & RESEARCH INSTITUTE CO.,LTD.

Applicant before: SHANGHAI MECHANIZED CONSTRUCTION GROUP Co.,Ltd.

CB02 Change of applicant information
RJ01 Rejection of invention patent application after publication

Application publication date: 20170426

RJ01 Rejection of invention patent application after publication